PRECOMMISSIONING & COMMISSIONING METHOD STATEMENT
PROCEDURE FOR CCTV SYSTEM
Join for Latest Articles
Enter your email address & Click Join: PURPOSE :

The purpose of this procedure is to define the step by step method to implement the correct  practices for the pre-
commissioning & commissioning of “CCTV System”through the guidelines contained herein so as to ensure that the job
execution complies with the project requirements and serves the intended function to satisfactory level.
JOIN
TOOLS / EQUIPMENTS
Portable Hand tools
Step Ladder
Recent Publications Multimeter
Block Wall Construction Control Procedure for
Blockwork Pre-commissioning Procedure for CCTV System
Slab Concrete Procedure for Ground Floor Slab 1. Ensure that the CCTV System Field devices & panels installation is complete
and mechanical completion is approved.
Construction Vehicle and Plant Servicing Procedure 2. Ensure that no damage has occurred between mechanical completion
Drainage Piping Above Ground Installation Plumbing & pre-commissioning.
Work Method of Statement 3. Repair / replace damaged components, if any.
4. Ensure the complete link products are in-place such as cable
Touchup Paint Method for Protective Painting and connectors, end line resistors, etc.
Coating of Piping and Supports 5. Ensure the number of different type of cameras, DVRs & monitors are as per
approved drawings.
6. Ensure the cameras are fitted with appropriate size of lens to
offer appropriate coverage & are tagged and identified properly.
7. Ensure the availability configuration & software settings of the cameras.
8. Ensure that the cable installation & termination is complete in field devices & panels.
9. Ensure the cables are secured well on to the connections to avoid data loss or system misbehavior due to any loose
connection.
10. Ensure that each camera is tested for proper image using appropriate instrument.
11. Ensure that the number of digital video recorders are in tune with the number of cameras.
12. Ensure the digital recorder is provided with enough hard disk capacity and speed as specified.
13. Ensure the key board is provided with pan, tilt, zoom controls.
14. Ensure all proper hard switch settings are done for proper function as stated in the installation manual.
15. Ensure that proper components are used for the interface with BMS, Fire alarm & security system.
16. Ensure the software available is of the latest version.

Popular Categories
 Civil Method Statements (72)
 Electrical Method Statements (43)

 Fire Fighting Systems (14)


 HVAC Method Statements (39)

 Occupational Health and Safety (20)

 Oil & Gas Systems (9)


 Plumbing Method Statements (32)

 Technical Guides (31)

 Testing & Commissioning (59)

Popular Tags
AV System block work method statement block work Commissioning Procedure for CCTV System
procedure CCTV ceramic floor tiles Clean Agent System
Commissioning COMMISSIONING PROCEDURE Drainage 1. Ensure that all the pre-commissioning checks are carried out successfully & are approved.
piping drainage piping method statement Electric Water 2. The digital recorder shall be properly designated in the software  with each DVR having a dedicated address on the
Heaters excavation safe work Fire Fighting System Fire system.
Suppression System hse management procedure 3. Each camera shall also be designated in the software with a dedicated address on the system.
Installation Installation Method Statement installation 4. The motion detection for cameras shall be set wherever required.
Procedure job safety analysis jsa safety Lightning 5. The I/O configuration for door monitoring (if any) shall be carried out as per end user requirement to trigger cameras.
Protection System Method Of Statement method 6. The video signal received in the monitors shall be checked & set for fine quality without any distortion.
statement Method Statement For Testing &
Commissioning pipe coating Precommissioning
Precommissioning & Commissioning Safe Method of
Statement Safe Method Statement safe work for
excavation safe work method of statement Safe Work
Method Statement Sanitary Wares Specifications
swimming pool civil works SWMS Testing &
Commissioning Testing & Commissioning Method
Statement Testing and Commissioning Tile Installation
Method Tower Crane Foundation Upper Floor Wall Frames
UPS Testing Procedure working at height Work Safe

Meta
Log in

Previous Next
 Entries feed

 Comments feed
 WordPress.org

Visitor Stats
664,255 Visitors

All Rights Reserved. Safework Method Of Statement. Serving Construction Industry Since 10 years.

You might also like