Professional Documents
Culture Documents
Exam 1 (2021) : This Is A Preview of The Published Version of The Quiz
Exam 1 (2021) : This Is A Preview of The Published Version of The Quiz
This is a preview of the published version of the quiz
Started:
Jan 22 at 4:58pm
Quiz Instructions
You have 60 minutes or until the end of class (whichever comes first)
ALLOWED:
NOT ALLOWED:
By taking this online exam, you accept the following statement: “I affirm that I will not give or receive
any unauthorized help on this exam, and that all work will be my own.”
Question 1 1 pts
Question 2 1 pts
________ is/are the process(es) that an analyst will follow to help ensure that his
work is complete, well-done, and understood by project team members.
Techniques
Data flow
Methodologies
Tools
Question 3 1 pts
Which of the below is a true statement regarding the systems development life cycle
(SDLC?)
The life cycle can be thought of as a linear process in which the end of the useful life of one
system leads to the beginning of another project to develop a new version of or replace an
existing system.
It is not possible to complete some activities in one phase in parallel with those of another
phase.
The life cycle can be thought of as a circular process in which the end of the useful life of one
system leads to the beginning of another project to develop a new version of or replace an
existing system.
Question 4 1 pts
Which of the following are delivered after the completion of the implementation
phase?
Priorities for systems and projects; an architecture for data, networks, and selection
hardware, and IS management are the result of associated systems
Description of current system and where problems and opportunities are with a general
recommendation on how to fix, enhance, or replace current system
Question 5 1 pts
Which of the following is one of three key principles shared by the Agile
Methodologies?
A focus on roles
Question 6 1 pts
Which of the following is NOT valued according to the Agile Manifesto for software
development?
Question 7 1 pts
________ is/are the property that occurs when entity types or object classes are
arranged in a hierarchy and each entity type or object class assumes the attributes
and methods of its ancestors, that is, those higher up in the hierarchy.
Objects
Participatory design
Inheritance
Question 8 1 pts
Because all companies outsource parts of their organization to focus on the core business.
Question 9 1 pts
Quicken
Cloud Computing
Open Source
Question 10 1 pts
Which of the following is NOT an example of open-source software?
MS Excel
Linux
MySQL
Mozilla Firefox
Question 11 1 pts
If a company has a generic software need, they should consider acquiring its
software from a(n) ________.
In-house development
Cloud sourcing
Question 12 1 pts
All of the following are ways of validating purchased software information except
________.
sending prospective vendors a questionnaire asking specific questions about their packages
using the software yourself and running it through a series of tests based on the criteria for
selecting software
The software reuse approach that allows individuals to find or develop reusable
assets on their own, and has few, if any, organizational rewards for reusing assets
best describes ________.
Flexible reuse
Facilitated reuse
Managed reuse
Ad hoc reuse
Question 14 1 pts
Data flow
Methodology
Feasibility study
Tool
Question 15 1 pts
Project bidding
Project development
Project execution
Question 16 1 pts
Question 17 1 pts
Networking
Network diagramming
Network programming
Network scheduling
Question 18 1 pts
________ refers to the amount of time a task can be delayed without delaying the
completion of the project.
Free slack
Shortest time
Total slack
Response time
Question 19 1 pts
If a project has a small or narrow focus, it most likely was chosen by ________.
A functional area
A steering committee
Top management
The IT leader
Question 20 1 pts
As an analyst, which type of project would you most likely have contact with in the
beginning of your career?
Planning of projects
Top-down projects
Bottom-up projects
Mission statement
Corporate statement
Strategic state
Current plan
Question 22 1 pts
A developmental group
A project team
Top management
A steering committee
Question 23 1 pts
The ________ refers to a broad class of physical objects that feature an Internet
address and connectivity that communicate between these objects and other
Internet-enabled devices and systems.
Internet-of-Things
Local Area Network
Electronic Commerce
Question 24 1 pts
Who is typically responsible for performing the project initiation and planning (PIP)
process?
Managers
Systems analyst
Users
Question 25 1 pts
A great budget
Limited scope
Question 26 1 pts
Customer goodwill
Employee training
Labor costs
Question 27 1 pts
Which part of the Baseline Project Plan contains an outline of the recommended
course of action?
System description
Feasibility assessment
Introduction
Management issues
Question 28 1 pts
Practice.
Keep it simple.
Question 29 1 pts
Shawn is preparing for a(n) ________ to verify all of the information and assumptions
in the baseline plan.
Feasibility assessment
Walk-through
System description
Introduction
Question 30 1 pts
Impertinence
Relax constraints
Impartiality
Attention to details
Question 31 1 pts
If group members work alone in the beginning of the project and then pool the ideas
with guidance, they are participating in ________.
A group interview
A single interview
Question 33 1 pts
Mission statement
Goals document
Work procedure
System document
Question 34 1 pts
Temporary; permanent
Evolutionary; throwaway
Joshua is bringing together the key users, managers, and systems analysts involved
in the analysis of the current system. He believes it should be a great ________.
Department meeting
Walkthrough
JAD meeting
Corporate meeting
Question 36 5 pts
What are the five major phases of the conventional Systems Development Lifecycle
(SDLC?) List and explain.
12pt Paragraph
p 0 words </>
Question 37 5 pts
Define tangible and intangible benefits and costs. Give examples for each. What is
the difference between the two?
12pt Paragraph
p 0 words </>
Question 38 5 pts
12pt Paragraph
p 0 words </>
Not saved
Submit Quiz