Professional Documents
Culture Documents
MC - MH - Final Boq V2
MC - MH - Final Boq V2
Unit Quantity
ITEM DESCRIPTION
DIVISION 1 : DEMOLISHING
1-1 DEMOLISHING WORK
Demolishing and removing the existing construction according to the demolition drawings and also cleaning the site.
1-1-1 For walls at (First floor, Second floor & entrance porch ). Lump Sum 1
DIVISION 2 : MASONRY
Supply and install clay blocks for non bearing interior walls, with the required strength; rate includes Portland cement
mortar for bedding, cement not less than 250 kg/m3, connection to the structure elements, scaffolding, special
pieces, ties, lintels, utility opening, curing 4 days with potable water and any material or activity required to finish the
work as per drawings and specifications for the following:
2-1 Solid clay blocks for walls 120 mm thick (240*120*60) m2 35
DIVISION 3 : PLUMBING WORKS ( Establishing only )
Establishing plumbing internal sanitary work - Polypropylene pipes for water supply and PVC pipes for drainage for
all sanitary works.
3-1 For all bathrooms ,Kitchen & A/C drainage (price doesn't include supply bath tub ) Lump Sum 1
3-2 Supply and install flush tank grohe only (price doesn't include supply bowl ) no 3
Supply and install frame only for wall hung bowl Ideal Standard for other bathrooms (price
3-3 no 1
doesn't include supply bowl).
Supply and install Ruud residential electric water heater (pacemaker water heaters) 200
3-4 lump 1
liter
3-5 Supply and install standard heating circulation pumps (helm made in Germany) lump 1
Supply and install torch applied bituminous membrane sheets 4 mm thick for water proofing, overlap not less than
100mm, work includes ; prepare surfaces, testing with water for 24 hours, sloped plain concrete , vertical torch
applied bituminous 4 mm thick on wall perimeter not less than 200 mm high, and any material or activity required to
finish the work as per drawings and specifications for the following:
6-4 Per unit supply and apply Aluminum box for electric water heater Lump Sum 1
Dismantling & commission of air-cooled direct expansion mini split units ducted split air-
7-1 Lump Sum 1
conditioners ﺑﺩﻭﻥ ﻓﻙ ﺍﻟﻛﻭﻣﺑﺭﺳﻭﺭ
Supply, install, connect & test lighting outlet fed by cu. wires of cross section 3x3mm2 (EL-Sweedy) run through
PVC conduit with a diameter of 20 mm (engineering home) for the main and sub-circuits.
Data outlets complete including rigid pvc conduits 20mm, conduit fittings ( cat 6, EL-Sweedy cable ) & all necessary
accessories and ancillary work according to specification and design.
10-3-1 Supply, install, connect and test outlets for internet cat 6 for (internet ,tv & tel) no 17
10-4 LIGHTING FIXTURE (Supplied by the owner )
Supply, install, connect and test light fixtures including: all lamps, all mounting devices and brackets according to
specifications and as shown on drawings.
11-1-2 supply & install imported porcelain tiles for ground floor (reception &kitchen ) m2 90
supply & install imported porcelain tiles for first floor ( master+bedroom 01,02,03+
11-1-3 m2 106
terrace 01&02)
11-1-4 supply & install HDF tiles for first floor ( master+bedroom 01,02,03) m2 85
11-1-8 supply & install imported porcelain tiles for mater toilet m2 5
11-1-9 supply & install imported porcelain tiles for nanny's room & laundry room m2 20
11-1-10 supply & install imported porcelain tiles for nanny's bathroom m2 24
11-2-2 supply & install local triesta gray for skirting in entrance ml 20
11-2-3 Supply, install and finishing flower box terista gray in entrance lump sum 1
Supply, install and finishing water feature in entrance ( cast +demolision +marble terista
11-2-4 lump sum 1
gray +plumping +isolation )
Imported Pietra gray marble steps consisting of 2cm thick polished treads and 2cm thick
11-2-5 ml 26
polished risers together 15 cm height
11-2-6 supply &install pietra gray tiles for stairs landing & lobby m2 17
11-2-7 supply &install pietra gray for skirting in landing & lobby ml 22
11-2-8 For walls tiles local hexagon white Turkish tiles for master toilet m2 25
Supply and install local Triesta gray acid marble tiles for built in sofa seat (block, & local
11-2-9 lump sum 1
Triesta gray acid ).in outdoor
DIVISION 12: PAINTING WORKS
ACRYLIC PAINT
Supply and apply acrylic paint (Jotun) , work include cleaning the surface, two final coats with approved materials,
masking and protection and any material or activity required to finish the work as per drawings and specifications for
the following;
12-1 Plastic paint for ceiling & walls m2 580
14-3 QDM 18000 (3 HP) B.T.U/HR for master bedroom & bedroom 1,2,3 no 4
Supply, installation test and commission of air-cooled direct expansion mini split units HI
14-4 no 1
WALL 12000 (1.5 HP-carrier C) for nanny's room
Supply & Install galvanized sheet metal duct network for supply, return, fresh & exhaust
air c/w all hangers, supports and fixing elements as drawings. Supply & erection
fiberglass insulation for supply and return ducts with aluminum vapor barrier, thickness
14-5 1", density 24 kg/m3 c/w all fixations. lump sum 1
Supply & install all outlets (supply, return, grills and diffusers) made from extruded
aluminum coated with electrostatic painting.
Supply & install copper pipes network for mini split units for more than 3 meter (made in
south Africa )
14-6 *NOTE: ACs copper pipes quantities are calculated based on the assumption that the ml 80
compressors will be placed in the upper roof, otherwise the quantities will be calculated
after the installation on site.
Supply and install black -glass cladding 10 mm, work include fixation, all accessories and
15-1 any material or activity required to finish the work as per drawings and specifications for m2 17
the following: for ( master ) *NOTE: Price doesn't include sticker for glass.
Supply and install fixed transparent -glass handrail 15 mm, work include fixation, all
15-2 accessories and any material or activity required to finish the work as per drawings ml 8
height 70 cm
DIVISION 16 : FIXTURES
16-1 Total Electric fixtures (attached) Lumpsum 1
16-2 Total sanitary fixtures (attached) Lumpsum 1
TOTAL
PARADIGM SUPERVISION 10%
GRAND TOTAL
Payment Terms:
1-Downpayment : 60%
The remaining amount are based on invoices, due in one week from receiving it.
REMARKS:
A- After approval of this BOQ, if the client changed any of the materials, specifications or fixtures; there will be a
variation addendum to be presented to the client (either with decrease or increase). The changes request should be
written, signed and presented to Studio Paradigm for approval before implementation on site.
B- During the fit-out phase, the client shouldn’t ask any external suppliers or contractors to work on site unless
agreed before starting with the fit-out.
C-If the client stopped the site for any reason during the fit-out works, the time schedule and prices would be subject
to change
D- All the invoices are due in one week
E- The boq are subject to 10% increase or decrease based on the actual dimensions on site.
F- All coordination & inquiries regarding the site should be with Studio PARADIGM.
G- This BOQ is proposed based on design development