Status of Work to be completed from January to March 2020 as per approved construction schedule

Work Completed up-to Work to be completed up Work completed up to 31st


Total Remarks / Reasons
S.N. Particulars Unit Dec-19 to 31st March 2020 March 2020
Work

Qty % Qty % Qty %


Dam & Spillways works left bank and
1
spillway (Stage - 1)

Work withheld initially by AIL despite availbility of


Soil Excavation Work approved drawings. AIL started left bank excavation
- Cum 26,240 24,000 91.46% 26,240 100.00% 24,930 95.01%
(Left Bank) works in stilling basin area on .....with the already
approved drawings. Dam Flooding had no impact on
left bank excavation which was to be carried out on
Rock Excavation Work
- Cum 21,102 18,854 89.35% 21,102 100.00% 18,914 89.63% higher elevations.
(Left Bank)

Foundation treatment & Consolidation


- Cum 2,000 100.00% 843.60 42.18%
Grouting

There was a Flashflood in the River on 24th Feb 2020.


Concreting in NOF sections The water flowed over the Coffer dam and the complete
- cum 2,400.00 -- -- 240.00 10.00% 0.00 0.00%
(Block B2) dam area was flooded with water and silt. As on date,
the dewatering is completed and the de-silting works is
Concreting in central spillway block B3 going on. The work of balance excavation and
- cum 12,234.00 -- -- 1,223.40 10.00% 0.00 0.00%
and B4 including Pier / Breast Wall etc concreting would resume only after removal of
complete silt in the dam area.
- Training Wall (Left side - Main spillway) cum 553.00 55.30 10.00% 0.00 0.00%

- Instrumentation (Blocks B2, B3 and B4) 20.00% 0.00 0.00%

Desilting Chambers & Associated


2
Underground Works
Feeder Tunnels
- Development of portal 100.00% 100.00% Completed
- Excavation m 98.25 -- -- 65 66.16% 98.25 100.00% Completed
- Desilting Chamber
Rock class – V encountered in complete length.
Excavation is being done together with RIB erection
Excavation in Desilting Chamber - DC1
- RM 119 20.60 17.31% 98.40 82.69% 29.00 24.37% which is time consuming(No work from 11.03.2020 due
(Header)
to insufficient manpower and machinery. Details given
in WAPCOS email dated 23.02.2020.)
Loose rock encountered in Nov 2019 at RD 88 m. No
Excavation in Desilting Chamber - DC2
- RM 119 95.50 80.25% 23.50 19.75% 0.00 0.00% work due to insufficient manpower and machinery.
(Header)
Details given in WAPCOS email dated 23.02.2020.
Excavation in Desilting Chamber - DC2 Shall be taken up after finishing excavation in header
- RM 119 -- -- 119.00 100.00% -- 0.00%
(Hopper) portion.
Excavation in Desilting Chamber - DC1 Shall be taken up after finishing excavation in header
RM 119 -- -- 70.00 58.82% -- 0.00%
(Hopper) portion.
- Silt Flushing Tunnel (SFT)
Page 1 of 5
Status of Work to be completed from January to March 2020 as per approved construction schedule

Work Completed up-to Work to be completed up Work completed up to 31st


Total Remarks / Reasons
S.N. Particulars Unit Dec-19 to 31st March 2020 March 2020
Work

Qty % Qty % Qty %


- Development of SFT portal 100.00% 100.00% Completed.
Rock class – V encountered in complete length.
- Excavation RM 202 -- -- 35.00 17.30% 31.00 15.32% Excavation is being done together with RIB erection
which is time consuming.
- Adits to Gate Chamber

AIL initiated the excavation for Portal however it was


observed that there was no good rock for construction
of Portal. Therefore, the location was chosen again and
- Development of Portal -- -- -- 100.00% -- 0.00% during the last visit of WAPCOS Official to site, the
same was informed and new location was finalied.
Thereafter, the drawings were prepared and got
approved on 16th March 2020.

Excavation and rock support- Open


- -- -- -- 100.00% -- 0.00% Shall be taken up after completion of portal works
excavation
Underground Works HRT with support
3
system
Due to extremely poor rock strata, work has been
Face -1 (from Outlet towards Adit-2) RM 397.85 185.36 46.59% 103.00 25.89% 70.65 17.76% delayed. For 82% of excavated length on particular
face, we encounted IV & V rock class.
Rock class – V encountered. Excavation is being done
Face -2 ( From Adit 2 towards Adit 1) RM 701 652.50 93.08% 48.50 6.92% 46.50 6.63%
together with RIB erection .
We temporarily stopped this face to attack on other
Face -3 ( Adit 2 towards Outlet) RM 806.91 582.30 72.16% 100.00 12.39% 74.50 9.23%
faces.
Face -5 ( from Adit-1 towards adit- 2) RM 439 313.65 71.45% 125.35 28.55% 125.35 28.55% Completed

4 Surge Shaft
Surface excavation and slope supports Cum 21,168 2021.9 9.55% 19,146 90.45% 21,168 100.00% Completed

Couldn't be started due to delay in completion of


surface excavation.
Underground excavation & supports m 79 -- -- 30 37.97% 0 0.00% The surface excavation is completed and the
underground excavation works will be started by 15th
April 2020.

Page 2 of 5
Status of Work to be completed from January to March 2020 as per approved construction schedule

Work Completed up-to Work to be completed up Work completed up to 31st


Total Remarks / Reasons
S.N. Particulars Unit Dec-19 to 31st March 2020 March 2020
Work

Qty % Qty % Qty %


5 Power House

Laying of Earthmat (for Machine Hall, Service Work delayed as AIL did not take up earthing works
sqm. 2,193.75 225 10.26% 1,969 89.74% 325 14.81%
Bay, Control Room and TRC) during service bay and control room backfilling

Machine Hall

PCC in machine hall area 95.70 -- -- 96 100.00% 33.00 34.48% Under progress

First stage concreting


Unit-1 - -- -- - 100.00% - 100.00% Drawing not yet approved.
Unit-2 - -- -- - 100.00% - 100.00% Drawing not yet approved.
Service Bay Cum 1,301.42

Backfill concrete below Service Bay from


- Cum 200 -- 0.00% 200 100.00% 200.00 100.00% Completed.
foundation level up to 8.0 m height
Backfill concrete in Service Bay upto
- Cum 1,101.42 25.8 2.34% 1,075.62 97.66% 1,041.40 94.55% As per schedule.
895.5 m (next 7 m)
Control Room
- Backfill concrete Cum 125.76 0 0.00% 125.76 100.00% 154.2 100.00% Completed.
In Contro Room from foundation level up Completed. Due to over-break, extra qty of about 59.67
- Cum 399 22.2 5.56% 412.8 100.00% 412.8 103.46%
to LT room floor cum is required.
Tail Race Channel
- Concreting bottom raft including weir 50.00% - 50.00%
- Concreting left wall 10.00% - 10.00%

6 Penstock & Valve house

Open excavation for valve house, anchor blocks


Cum Drawing not yet finalised.
and saddle supports
- Shall be taken up after completion of laying of pressure
Laying of earthmat in Valve house 100.00% 0.00%
shaft upto Outlet Portal
7 Infrastructure works (Buildings)

a Permanent work (Residential/Non-


Residential)
i Housing for client ( 2Nos) - Dam
- Finishing LS - 35.00% 65.00% 35.00% Furniture rates obtained and under finalisation with
WAPCOS / Client for procurement.
Page 3 of 5
Status of Work to be completed from January to March 2020 as per approved construction schedule

Work Completed up-to Work to be completed up Work completed up to 31st


Total Remarks / Reasons
S.N. Particulars Unit Dec-19 to 31st March 2020 March 2020
Work

Qty % Qty % Qty %

ii Housing for client ( 2Nos)


Powerhouse
- Finishing LS - 60.00% 40.00% 65.00% Furniture rates obtained and under finalisation with
WAPCOS / Client for procurement.

iii Guest House for client ( 2Nos) Surge


shaft
- Earthwork LS 50.00% 50% 100%
- Sub-structure/Foundation works LS 0% 100.00% 100.00%
- Super structure LS 0.00% 100.00% 50.00%
- Finishing LS 0.00% 100.00% 0.00% Furniture rates obtained and under finalisation with
WAPCOS / Client for procurement.

iv Client housing (2 Nos) Surge shaft

- Sub-structure/Foundation works LS 50.00% 100.00% 100.00%


- Super structure LS 15.00% 85.00% 100.00%
- Finishing LS 0.00% 100.00% 0.00% Furniture rates obtained and under finalisation with
WAPCOS / Client for procurement.

v Client Site Office (1 Nos) Dam site


- Finishing LS - 35.00% 65.00% 35.00% Furniture rates obtained and under finalisation with
WAPCOS / Client for procurement.

vi Client Site Office (2 Nos)


Powerhouse site
- 65.00% Furniture rates obtained and under finalisation with
Finishing LS - 65.00% 35.00% WAPCOS / Client for procurement.

vii Executive Guest House (2 Nos)


Powerhouse site

- Finishing LS - 70.00% 30.00% 65.00% Furniture rates obtained and under finalisation with
WAPCOS / Client for procurement.

viii Officers Guest House (2 Nos) Dam site

Page 4 of 5
Status of Work to be completed from January to March 2020 as per approved construction schedule

Work Completed up-to Work to be completed up Work completed up to 31st


Total Remarks / Reasons
S.N. Particulars Unit Dec-19 to 31st March 2020 March 2020
Work

Qty % Qty % Qty %


- Finishing LS - 25.00% 75.00% 55.00% Furniture rates obtained and under finalisation with
WAPCOS / Client for procurement.

ix AIL Site Office (1 Nos) PH site

- Finishing LS - 55.00% Furniture rates obtained and under finalisation with


50.00% 50.00%
WAPCOS / Client for procurement.

Page 5 of 5