Status of Work To Be Completed From January To March 2020 As Per Approved Construction Schedule
Status of Work To Be Completed From January To March 2020 As Per Approved Construction Schedule
4 Surge Shaft
Surface excavation and slope supports Cum 21,168 2021.9 9.55% 19,146 90.45% 21,168 100.00% Completed
Page 2 of 5
Status of Work to be completed from January to March 2020 as per approved construction schedule
Laying of Earthmat (for Machine Hall, Service Work delayed as AIL did not take up earthing works
sqm. 2,193.75 225 10.26% 1,969 89.74% 325 14.81%
Bay, Control Room and TRC) during service bay and control room backfilling
Machine Hall
PCC in machine hall area 95.70 -- -- 96 100.00% 33.00 34.48% Under progress
- Finishing LS - 70.00% 30.00% 65.00% Furniture rates obtained and under finalisation with
WAPCOS / Client for procurement.
Page 4 of 5
Status of Work to be completed from January to March 2020 as per approved construction schedule
Page 5 of 5