Professional Documents
Culture Documents
Performance Bond
Performance Bond
Performance Bond
& PERFORMANCE
GUARANTEE SUM
Introduction
- The deduction
- Demanding - Suing contractor
from the amount
payment from the in court
retained by the
guarantor
employer
PERFORMANCE BOND
GENERAL
The contractor is essential to submit the performance
bond before he is allowed to start work on the site
The value of the performance bond does not change even though
the contract sum changes
USE OF PERFORMANCE
BOND
The performance bond can be used at any time when ever
there is non-performance of the contract by the contractor
4.1 Generally
‘The Contractor may opt for a Performance Bond in the form of
Performance Guarantee Sum…..’ (Clause 13.2)
To provide collateral
• normally in the form of
To pay premium, cash deposit/assets
normally 2-3% of • equal to value of
amount insured. amount insured by the
bank i.e. 5% of
contract sum.
‘If the Contractor fails to submit the said
Performance Bond as specified in sub-clause (a)
above on the date of possession of site, then the
Contractor shall be deemed to have opted for
Performance Bond in the form of Performance
Guarantee Sum...’(Clause 13.1(b))
The gross value of work done and material delivered as ascertained in the
interim payment certificate is subject to deduction for Performance
guarantee sum.
Percentage of retention is 10% of accumulated value of work done
including materials on site.
The deduction for Performance guarantee sum in the interim certificate
must stop when the accumulated amount so retained reaches 5% of
contract sum.
4.3 Payment of Performance Guarantee Sum
c) Condition Precedent
The contract has 2 methods of safe guarding the
interest of the employer in case non-performance
by the contractor:
Performance
Bond
Retention
Fund
(3months)