SCOPE OF WORK FOR HIGH PRESSURE ROTOMOL CLEANING OF

UNDERGROUND COOLING WATER PIPELINES


Introduction :
BPCL Kochi Refinery is implementing a Propylene derivative Petrochemical Project (PDPP)
for the production of Niche petrochemicals such as Acrylic Acid, Acrylates and Oxo
Alcohols.
PDPP project consist of Cooling Tower package ,which consist of 6 cells (6 X 4000 M3/Hr,
including one spare cell) having a total design capacity of 20000 m3/hr. The cooling water
system envisaged to meet the cooling water requirement of PDPP complex which includes
Acrylic Acid, Oxo Alcohol & Acrylates process units and offsites & utilities system. The
cooling water major piping network consists of supply line of 72” (WCS), return line of 50”
(WCR), bearing cooling water return line of 14” (BCR) and chilled cooling water return line
of 50” (WCHR) with multiple tap-off locations at units and offsites & utilities system. In
cooling tower pipeline network, underground pipelines of WCS, WCR & WCHR are having
total length of around 1186.7 meters

OBJECTIVE

This procedure for high pressure Rotomol Cleaning of piping essentially is carried for the
removal of loose rust, welding burs, mill scale and welding slag, construction materials such
as Helmets, ropes, Safety Harnesses Hammers that commonly are present in internal pipes.

The Cleaning is achieved by use of a Rotating Hose Device/RHD System which is fed water
at high pressure of about 15,000psi /1035bar.At such high pressures almost all debris can
be eliminated from the pipes.

PRE-QUALIFICATION CRITERIA (PQC)


Technical Criteria

Bidder as the Principal Contractor should have successfully executed minimum one job
during the last seven years from the bid due date towards flushing & cleaning with the help
of Rotary Hose Device (RHD) / Rotocar / Rotomole device of underground/submerged
pipeline having minimum diameter of 42” and minimum length of 175 Mtrs & above in any
Petrochemical Complex/ Petroleum Refinery / Power plant / Hydrocarbon pipeline
installation / Steel Plant/Fertilizer plant located in India.
The Bidder shall provide necessary documents as a proof for meeting the above condition.
The documents shall have details like work order/purchase order details with brief scope
of work, job completion certificates etc.
Explanatory Note: To assess the technical capability of contractor for carrying out job on
highest diameter 72” cooling water supply underground pipeline, minimum 60% of pipe
diameter and 60% of cooling water supply underground pipelines above 60” ( 292.3 Mtrs)
are considered to ensure healthy competition from technically competent contractors to
carry out the job based on the market study.

Financial Criteria:

1. The average annual turnover of the bidder during the immediate preceding 03 (Three)
financial years shall not be less than Rs. 13.19 Lakhs as per the audited annual financial
results as on final due date of submission of bid.
1
2. Bidder’s Net Worth as per latest audited financial statement shall be positive.

The above confirmation should be supported by copy/copies of documents such as Audited


Profit & Loss Account, Audited Balance sheet etc.

Scope of work:

The scope of work consists, Carrying out cleaning / removal of deposited silt, sludge, muck,
etc. deposited in the underground cooling water pipe line including stacking at site,
ensuring without mixing up with other materials, depositing the same in the specified
location, anywhere inside the refinery including necessary transportation, flushing the
whole line with water and draining/ pumping out the water, to nearby drains, etc. All jobs
have to be done as per direction from engineer in charge

Contractors scope of supply:


Contractor's scope of supply: All arrangements required for successful completion of job is
in contractors scope.

Some of the items like mentioned below:


a) Provide the high pressure hydro jetting pump.
b) Provide one standby pump for the high pressure hydro jetting pump.
c) Provide the high pressure rotating hose device system with power pack, with
rotating nozzles, high pressure hoses, high pressure lances, foot operated valve, high
pressure gun, and required tools and tackles for the execution of this job.
d) Provide Electrical mud pumps.
e) Provide minimum 14 technical crews for the job.
f) Required PPE’s for the crews.
g) Scaffolding if required for executing the job.
h) Provide facility of remote inspection of underground line using camera and
monitor. Person entering the underground line must wear necessary SCBA.
Recorded inspection has to be given to BPCL. The cleaning will be certified based on
camera inspection by BPCL Engineer in-charge.

BPCL Scope of supply:


a) Electrical Power supply.
b) Raw water required for the high pressure jet.
c) Designated place for the disposal of the debris.

Mechanical Details of piping are illustrated as below in the table:

Line Sizes Length


Sl.NO Description of Lines Total IM
(Inch) (M)

1 Cooling Water Supply (WCS) 72 148.4 10683.4


2 Cooling Water Supply (WCS) 64 10.7 682.3
3 Cooling Water Supply (WCS) 60 133.2 7992.0
2
4 Cooling Water Supply (WCS)(Units) 38 40.0 1520.0
5 Cooling Water Supply (WCS)(Units) 40 92.9 3716.9
6 Cooling Water Return (WCR) 40 88.7 3548.6
7 Cooling Water Return (WCR) 40 34.0 1358.3
8 Cooling Water Return (WCR) 50 93.4 4669.6
9 Cooling Water Return (WCR) 28 181.0 5067.7
10 Chilled Cooling Water Header (WCHR) 40 89.8 3590.2
11 Chilled Cooling Water Header (WCHR) 50 274.7 13734.1
1186.7

Terms and conditions:


General conditions of Contract (GCC) shall be applicable except compensation for delay,
security deposit and PBG clauses.
Contract Period: 20 days from the date of issue of contract.

Payment terms: Payment shall be made on the basis of actual work done and on the due
certification by BPCL-KR Engineer in charge and shall be subject to retention money
deduction and as per the clauses in GCC.

GOODS AND SERVICES TAX: - The quoted prices shall be deemed to be inclusive of all
taxes and duties except “Goods and Services Tax” (hereinafter called GST) (i.e. IGST
applicable in case of interstate supply or CGST and SGST/UTGST applicable in case of intra
state supply).

GST shall be paid against receipt of tax invoice. In case of non-receipt of tax invoice, BPCL
shall withhold the payment of GST. Contractor/vendor shall be required to issue tax invoice
in accordance with GST Rules so that input credit can be availed by OWNER/BPCL. In the
event that the Contractor / Vendor fails to provide the invoice in the form and manner
prescribed under the GST Act read with GST Invoicing Rules there under, OWNER/BPCL
shall not be liable to make any payment against such invoice.

GST payable under reverse charge, if any, shall not be paid to the Contractor/Vendor but
will be directly deposited by BPCL to the Government of India.

GST DEDUCTIONS
GST at the prevailing rate is applicable on liquidated damages and shall be recovered extra
on the amount of LD levied.
GST at prevailing rate is applicable on any penal recovery that is levied under the contract
and shall be recovered extra.

VARIATION IN TAXES & DUTIES


No variation on account of taxes and duties, statutory or otherwise, shall be payable by
BPCL to contractor/vendor except for GST. However, any statutory variation for GST shall
be payable up to contractual date of completion/delivery against documentary evidence.
Any reduction in taxes and duties included in the price shall be passed on to BPCL.

3
Any new taxes, duties, cess, levies notified or imposed after the submission of last /final
price bid but before the contractual date of completion/delivery of work/item shall be to
BPCL’s Account.

SAFETY CONSIDERATIONS

1. High Pressure Rotomol Cleaning operator should have 1 assistant standby in case of
emergency.

2. Work Permit will be applied before entry to work place area.

3. During operating in narrow area one operator should closely look after and ensure the
operator work safely.

4. Where the operator working more than 1 persons with HIGH PRESSURE ROTOMOL
Cleaning equipment in the same time. The work order should be clearly prioritized to
prevent hazard from another operators who is working nearby such area.

5. The HIGH PRESSURE ROTOMOL Cleaning operator should working in convenience area
and safe condition.

6. Each pump should have operator in their place and he should be able to communicate
with jetting operator.

7. Pump operator should be able to see jetting operator during working at all time in order
to assist immediately where needed.

8. To remove residual oil from working floor in order to protect slippery hazard.

9. Get permission from BPCL/ client before release waste water to ditch.

10. High pressure hose/ air hose and electric cable to provide cover for footpath to prevent
damage when vehicle driving passes.

11. The contractor shall abide by the company's safety and security regulations. Any work
in the BPCL-Kochi Refinery shall be covered through work / safety permits. All the
workmen shall be provided with safety gadgets specified for the work.