BUSINESS DEVELOPMENT PLAN

Waste Waste Waste


Transportation Collection Utilization

Liquid Waste Solid Waste Eco


Treatment Treatment Landfill
PT JIA LIN ENVIRONMENTAL
Jakarta

Consulting
MAP OF THE DISTRIBUTION OF FACILITIES NHL AND JLE
WILL BUILD

Captive market Integrated facility Potential transfer station locations/


operating office

Target market: Papua


Target market: Integrated Integrated
management facilities (landfill) management landfill
Duri, Sumatera facilities
⮚ Oil & gas waste
⮚ Oil & gas waste
⮚ Waste of crude palm oil
⮚ Medical waste ⮚ Mining Waste

Target market: South Sumatra


Target market: South Sulawesi
transfer station Target market : Integrated transfer station
⮚ Oil & gas waste Target market : Central Java & East management facilities ⮚ Mining waste
⮚ Mining waste Java Transfer Station (landfill) East Kalimantan ⮚ Manufacture Waste
⮚ Medical Waste ⮚ Oil & gas waste ⮚ Oil & gas waste ⮚ Medical Waste
⮚ Manufacture Waste ⮚ Manufacture Waste ⮚ Mining Waste
⮚ Medical Waste ⮚ Medical Waste
SWOT
STRENGTHS
- Initiation of formation by 3 (three) Ministries.
- Shareholders of 4 largest mining BUMNs.
- There is a representative from the Ministry of BUMN.

WEAKNESSES
- Organizational structure has not been going well.
- The duties and work procedures have not been
established.
- Do not have processing facilities.
- Does not have a comprehensive RENSTRA / BUSINESS
PLAN.

OPPORTUNITIES
- The large volume of potential waste that can be
managed.
- The first BUMN subsidiary assigned to carry out waste
management.
THREATS
- An old company that has been engaged in B3 waste
management.
- Officials and law enforcers.
- BUMN / Affiliate engaged in hazardous waste management.
LANDFILL – DURI - RIAU
ORGANIZATION STRUCTURE - KSO
Board Of Director
Board Of Director
PT JIA LIN
NHL
ENVIROMENTAL

Project Management
Officer
Agus Fitriadi Bayu Firdaus Charles

Finance Legal
JLE JLE - NHL

Project Control
JLE - NHL

Project
Contractor Management
Consultant
PROGRESS FACILITIES

No Activities Status

1 Topography Done

2 Site Review Done (the result is the best Landfill Land from LAPI ITB Study)

3 Pre Feasibility Study Done (LAPI ITB)

4 Review BPKP Done

5 Economic Preview Done (BPKP & NHL)

6 Site of Investigation Done (LAPI ITB)

7 Detailed Engineering Design + FS Done (LAPI ITB)

8 AMDAL (Environmental Protection Permit) Done (Status AMDAL Masih Atas nama CPI)

9 Collective Land Use Agreement (PPLB) Done


NHL has paid the rent to the State (PNBP) for 47 Hectars land in Duri

10 Spatial planning and territory (RTRW) On Progress (Pemda Bengkalis)

11 Change of Name of Environmental Permit On Progress (CPI)


Certificate (SKIL)
ANALYSIS RESULTS
The conclusion from the results of the site investigation analysis at Based on the analysis results, in general the location of
the Landfill Location was:
the Duri landfill plan meets the requirements of the
• In regional geology, the landfill location is covered by the Farmer
Formation. Minister of Forestry and Environment Regulation
• The lithology on the surface of the landfill location is dominated
by clay with localized sand, while at the subsurface up to a depth LHK No. P.63/menlhk/Setjen/ KUM.1/7/2016.
of 25 m, the lithology is dominated by clay with sandy clay lenses.
• Free aquifers are found locally, while confined aquifers are not
found to a depth of 25 meters.
• The layers that act as aquifers are sand, loamy sand and peat.
• The layers that act as aquifers are clay, silt, and sandy clay. No Requirements Complied (yes / no)
• Landfill location is not a recharge area. (not a water catchment 1 Free from flood 100 years Yes
area)
2 The greatest soil permeability value 10 -7 Yes
• The distance from the landfill site to the nearest permanent river
is more than 8.2 km. cm/sec
• Jarak dari lokasi landfill ke garis pantai adalah lebih dari 46,6 km. 3 There is no potential for natural disasters Yes
• Landfill locations are not in protected areas. 4 Outside protected areas/forestry. Yes
• Ground movement disaster risk: low.
5 Not a water catchment area Yes
• Volcanic disaster risk: low.
• Earthquake disaster risk: moderate. 6 The base of the final stockpile is 4 m from Yes
• There are no faults and the closest fault distance to the landfill the top of the aquifer layer
location is 7 km. 7 Not a body of water Yes
• Tsunami disaster risk: low.
8 The closest distance to a permanent river or Yes
• There is no sinkhole hazard.
• There is no danger of land subsidence. lake is 500 m
9 The distance to the nearest coastline is Yes
2,500 m
PROJECT OVERVIEW
Integrated Waste Facility Development Plan in Duri, Bengkalis District.

NB : The red point is the location of the distribution of petroleum


PROJECT OVERVIEW

• The landfill location plan with a total area based on technical drawings is
469,900 m2 or 46.99 ha.
LAYOUT FACILITIES
BUSINESS MODEL FOR LANDFILL – DURI - RIAU
START
START

FINISHED
FINISHED
BUSINESS MODEL
PERMIT AND LEGAL : PT. JIA LIN ENVIRONMENTAL :
• Environmental impact analysis permit • Memorandum of Understanding
from the Ministry of Forestry and the Exclusive agreed on working together
environment. (PMO) for 5 Projects including Landfill
• Assignment as an Executing Company Duri Site.
for managing Oil and Gas Business • Next will be soon Detail Agreement.
activity waste (Assignment Letter) from
Ministry of State Owned Enterprises. PROJECT MANAGEMENT OFFICE :
• Memorandum of understanding • Between NHL and JLE. (PMO)
between SKK Petroleum and Gas
(Ministry of Energy and Mineral Mining,
Oil and Gas) and the Ministry of State- VENDOR OR CONSTRUCTOR :
Owned Enterprises regarding Waste • Bid or Direct Assignment
Management in the upstream Oil and
Gas mining.
• Assignment to Develop Landfill facility BUILD AND OPERATE
to manage oil and gas waste

PAYMENT
management from Chevron / Every 30 days the results of the hoarding of
confirmation letter from SKK Oil and Gas. the weighing results will be made an Official
• Capable to handle 150 types of Report and must be signed by SKK Oil and
hazardous waste code permit. Gas. And after that get a payment to
• ISO Certificates. Chevron or Pertamina Hulu Rokan (PHR).
• Memorandum of Understanding with
PT.Pertamina Hulu Rokan (PHR) about
cooperation waste management for soil
contaminated oil. Chevron or Pertamina Hulu Rokan as the Oil
and Gas contractor from SKK Oil and Gas will
pay with a term of payment of 45 days. Pay
or Transfer to PMO A/C Bank.
BUSINESS MODEL

SKK OIL AND GAS :


Report and InvoiceLandfill Report & investigation

• After the Facility is finished, SKK will


provide a trial landfill with a quantity of
100,000 at a price of USD 60 / Ton.
• After the trial period is over, the
quantity to be given is 6,780,000 at a
price of USD 150 / Ton.
• Payment Order to Chevron / PHR.

CHEVRON / PHR.
report

PAY
PAY
PROJECT MANAGEMENT OFFICE :
• Between NHL and JLE. (PMO)
CONSULTANTS AND SUPERVISORS
PAY Plans/Analysis/Report

VENDOR OR CONSTRUCTOR :
• Build Operate Transfer ADVISE AND SUPERVISION
THANK YOU