MALAYSIAN CIVIL

ENGINEERING STANDARD
METHOD OF MEASUREMENT
SECOND EDITION

MyCESMM2
© Copyright 2018

CONSTRUCTION INDUSTRY DEVELOPMENT BOARD (MALAYSIA)


CONTENTS

PAGE

Committee representation ii

Foreword iii

Introduction iv

SECTION 1: SCOPE AND GENERAL 1

SECTION 2: APPLICATION OF WORK CLASSIFICATION 1

SECTION 3: CODING AND NUMBERING OF ITEMS 1

SECTION 4: PREPARATION OF THE BILL OF QUANTITIES 1

SECTION 5: COMPLETION, PRICING AND USE OF THE BILL OF QUANTITIES 1

SECTION 6: METHOD-RELATED CHARGES 1

SECTION 7: WORK CLASSIFICATION 2

Class A: General items 3


Class B: Environmental protection and enhancement 11
Class C: Traffic management and control 21
Class D: Site investigation work 25
Class E: Demolition and site clearance 33
Class F: Earthworks 37
Class G: Geotechnical work 47
Class H: Piling work 55
Class I: Concrete work 63
Class J: Brickwork, blockwork and masonry 73
Class K: Timber work 77
Class L: Metalwork 79
Class M: Building work 85
Class N: Painting work 91
Class O: Pipework 95
Class P: Pipe rehabilitation work 105
Class Q: Drainage work 111
Class R: Roads and pavings 117
Class S: Tunnel work 125
Class T: Rail track 133
Class U: Mechanical and electrical work 141
Class V: Miscellaneous work 155
Class W: Provisional and prime cost sum 159

Bibliography 161

Acknowledgements 163
Malaysian Civil Engineering
Standard Method of Measurement ̵ Second Edition
(MyCESMM2) COMMITTEE REPRESENTATION

COMMITTEE
REPRESENTATION
The Working Group on Malaysian Civil Engineering Standard Method
of Measurement Second Edition also known as MyCESMM2 which
developed this document was managed by the Construction Industry
Development Board Malaysia (CIDB) and consists of representatives
from the following organisations:

Association of Consulting Engineers Malaysia


Board of Engineers Malaysia
Board of Quantity Surveyors Malaysia
Construction Industry Development Board Malaysia
Construction Industry Development Board Malaysia (Secretariat)
Department of Irrigation and Drainage Malaysia
Gamuda Berhad
Indah Water Konsortium Sdn Bhd
Jabatan Kerja Raya Malaysia
Jabatan Perkhidmatan Pembetungan
JUB Central Sdn Bhd
Lembaga Lebuhraya Malaysia
Mass Rapid Transit Corporation Sdn Bhd
Pengurusan Aset Air Berhad
Prasarana Malaysia Berhad
Projek Lebuhraya Usahasama Berhad
Royal Institution of Surveyors Malaysia
Suruhanjaya Perkhidmatan Air Negara
Tenaga Nasional Berhad
The Institution of Engineers, Malaysia
Universiti Teknologi Malaysia

ii | MyCESMM2
FOREWORD

FOREWORD

This Malaysian Civil Engineering Standard Method of Measurement Second Edition (MyCESMM2) was
developed by the Working Group under the authority of the Industry Standards Committee on Building,
Construction and Civil Engineering. Development of this standard was carried out by the Construction
Industry Development Board Malaysia which is the Standards-Writing Organisation (SWO) appointed by
SIRIM Berhad to develop standards for construction practices.

In developing this MyCESMM2, reference was made to the Malaysian Standard Civil Engineering Standard
Method of Measurement (MSCESMM) (JSM, 2018) and Malaysian Civil Engineering Standard Method of
Measurement (MyCESMM) (CIDB (M) 2011).

Compliance with a Malaysian Standard does not in itself confer immunity from legal obligations.

MyCESMM2 | iii
Malaysian Civil Engineering
Standard Method of Measurement ̵ Second Edition
(MyCESMM2) INTRODUCTION

INTRODUCTION

MyCESMM2 has been designed to cater for various aspects of local construction practices and is
published to accommodate a comprehensive coverage of civil engineering work in Malaysia.

There are 3 other publications which have been published to complement this MyCESMM2 in order to
provide detail clarification of the work items and to assist measurers in simplifying their tasks when
describing the work items.

a) The Malaysian Standard Method of Measurement in Civil Engineering Works (MSCESMM) (JSM, 2018).

b) ‘Guide to MyCESMM2’ which offers detail technical clarifications on work items found in MSCESMM and
MyCESMM2.

c) ‘Library of Standard BQ Descriptions for MyCESMM2’ which contains a comprehensive option of list of
descriptions of work items from which measurers can extract to facilitate efficiency in the preparation
of the bill of quantities.

iv | MyCESMM2
SECTION 1 - SECTION 6

Brief on contents in MSCESMM – There are 6 sections in MSCESMM (JSM, 2018) and they are briefly described below:

SECTION 1: SCOPE AND GENERAL

This section defines the scope, normative references, terms and definations, abbreviations and units as described
in MSCESMM (JSM, 2018).

SECTION 2: APPLICATION OF WORK CLASSIFICATION

This section explain about item description, modes of description, separate items, units of measurement,
measurement rule, definition rules, coverage rules, additional description rules and application of rules as described
in MSCESMM (JSM, 2018).

SECTION 3: CODING AND NUMBERING OF ITEMS

This section explain about coding, item numbers, coding of unclassified items and numbering of items with additional
description as described in MSCESMM (JSM, 2018).

SECTION 4: PREPARATION OF THE BILL OF QUANTITIES

This section explain purpose of the bill of quantities, measurement of completed work, sections of the bill of quantities,
preamble, work items, division of the bill of quantities into parts, daywork schedule, heading, sub-headings, extent
of itemisation, descriptions, ranges of dimensions, prime cost items, provisional sums, quantities, work affected by
water, form, setting and grand summary as described in MSCESMM (JSM, 2018).

SECTION 5: COMPLETION, PRICING, AND USE OF THE BILL OF QUANTITIES

This section explains insertation of rates, prices and parts to be totalled as described in MSCESMM (JSM, 2018).

SECTION 6: METHOD-RELATED CHARGES

This section described method-related charges, insertation by a tenderer, intemisation, description, contractor shall
not be bound to adopt method, charges shall not be measured and payment as described in MSCESMM (JSM, 2018).

MyCESMM2 | 1
Malaysian Civil Engineering
Standard Method of Measurement ̵ Second Edition
(MyCESMM2) SECTION 7

SECTION 7: WORK CLASSIFICATION

Work classification is in MyCESMM2 and consisted of 23 classes of work classification commonly encountered in a
civil engineering contract are as follows:

Class A : General items

Class B : Environmental protection and enhancement

Class C : Traffic management and control

Class D : Site investigation work

Class E : Demolition and site clearance

Class F : Earthworks

Class G : Geotechnical work

Class H : Piling work

Class I : Concrete work

Class J : Brickwork, block work and masonry

Class K : Timber work

Class L : Metalwork

Class M : Building work

Class N : Painting work

Class O : Pipework

Class P : Pipe rehabilitation work

Class Q : Drainage work

Class R : Roads and pavings

Class S : Tunnel work

Class T : Rail track

Class U : Mechanical and electrical work

Class V : Miscellaneous work

Class W : Provisional and prime cost sum

2 | MyCESMM2
CLASS A
GENERAL ITEMS

MyCESMM2 | 3
4
ADDITIONAL
CLASS A: GENERAL ITEMS MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES

Measurement covered under other classes: M1 A1


The unit of measurement Item description for
Method-related charges (refer Section 6). for general items shall Engineer/SO/PD/ER
be the sum, unless requirements shall
Plant and equipment (included in Class D: Site investigation work, Class G: otherwise stated. A state the provision

| MyCESMM2
(MyCESMM2)

Geotechnical work, and Class H: Piling work). quantity shall be given for establishment,
Temporary road diversion (included in Class C: Traffic management and control against all items for maintenance and
Malaysian Civil Engineering

and Class R: Roads and pavings). Engineer/SO/PD/ER removal where


requirements of which applicable.
Temporary staging for piling (included in Class H: Piling work).
the value is to be
ascertained and
determined by
remeasurement. The
unit of measurement
shall be stated for each
such item.
Standard Method of Measurement ̵ Second Edition

FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT

1 Contractual 1 Bond 1 Performance bond sum M2 A2


requirements 2 Design guarantee sum Design guarantee bond Item description for
bond shall cover sections of design guarantee bond
work that are designed shall state the section
by the contractor. of work to be designed
2 Insurances 1 Insurance of the sum by the contractor.
works M3
2 Public liability sum An item may be given
insurance for a parent company
3 SOCSO/Workmen sum guarantee where it is
compensation envisaged a tenderer
insurance may be a subsidiary of
a larger company or
3 Parent company sum group.
guarantee

4 Statutory obligation sum M4


Statutory obligation
fee shall be determined
5 Stamp duty sum as required by the local
by-law.

2 Engineer/SO/ 1 Facilities 1 Office sum M5 C1 A3


PD/ER 2 Maintenance of mth Measurement of office Engineer/SO/PD/ ER Item description for
requirements office equipment can be requirements shall be office and laboratories
3 Laboratories sum measured in number deemed to include shall specify type and
4 Maintenance of mth where applicable. employer requirements. area required.
laboratories
CLASS A: GENERAL ITEMS
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
2 Engineer/SO/ 2 Equipment 1 Office equipment sum M6 D1 C2 A4
PD/ER 2 Maintenance of mth A quantity shall be All works other than Items for Engineer/SO/ Item description for
requirements office equipment given against all items the permanent works PD/ER requirements office equipment shall
3 Laboratory sum for Engineer/SO/ which is expressly shall be deemed to state the type and
equipment PD/ER requirements stated in the contract include the provisions quantity.
4 Maintenance of mth of which the value such as facilities, of water supply,
laboratory is to be ascertained equipment, services, electricity, sanitary, A5
equipment and determined by attendance and work and communication Item description for
5 Surveying sum measurement. A unit to enable the Engineer/ facilities. office, laboratory, and
equipment of measurement shall SO/PD/ER to carry out surveying equipment
6 Maintenance of mth be stated for each such the supervision of the C3 shall specify the type
survey equipment item. work shall be classed Items for Engineer/ and quantity required.
as Engineer/SO/PD/ER SO/PD/ER
requirements. requirements shall be A6
3 Services 1 Provision of transport sum deemed to include Item description
vehicle the maintenance of for equipment and
2 Maintenance of mth camera. transport vehicle shall
vehicle state when items are
3 Provision of mobile sum to be reverted to the
phones employer or contractor
4 Maintenance of mth after completion of the
mobile phones works.
5 Provision of camera sum
A7
Item description
4 Attendance 1 Drivers man-mth for attendance for
2 Survey assistants man-mth Engineer/SO/PD/ER
3 Laboratory assistants man-mth shall state the number
4 General labours man-mth of staff required.
5 Security guards man-mth
A8
Item description for
works programme
shall state the type and
5 Submission of 1 Project execution sum format required.
documents plan
2 Drawings sum
3 Method statement sum
4 Works programme sum

6 Miscellaneous 1 Progress report mth D2 C4 A9


2 Project signboard nr As-built drawings Progress report shall Item description for
3 As-built drawings sum shall be defined in the be deemed to include progress report shall
4 Video recording sum standard specifications the provision of dated specify the date
5 Temporary fencing sum or the Engineer/SO/ progress photographs. and number of sets
and hoarding PD/ ER requirements required.

MyCESMM2 |
in the contract.

5
CLASS A: GENERAL ITEMS
6
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
3 Project 1 Survey and setting sum A10
requirements out Item description for
survey and setting
out shall state type of
surveys and when

| MyCESMM2
(MyCESMM2)

licensed surveyor is
required to carry out
Malaysian Civil Engineering

the work.
2 Quality assurance/ 1 QA/QC plan sum M7 D3 C5 A11
Quality control 2 Testing of materials sum Items shall be given in Testing and Testing and Item description for
3 Testing of works sum this class for all testing commissioning shall commissioning shall factory acceptance
4 Factory acceptance sum for which items are be performed and be deemed to comply test shall state the
test separately as set out in fulfilled in accordance with the requirements material to be tested,
5 Testing and sum other classes. with relevant as expressly stated. type of test, and the
commissioning authorities/ employer number of person to
requirements/ witness the test.
Standard Method of Measurement ̵ Second Edition

specification.
A12
D4 Item description
Testing and for testing and
commissioning commissioning of plant
shall include man shall state the duration
hours, mobilisation, in months
demobilisation,
competent personnel, A13
specific tools and all Item description for
other required items to testing of the works
operate fully functional. shall state particulars
of samples and of the
methods of testing.

A14
Item description
for testing and
commissioning shall
state the material to be
tested and type of test.
3 Operation and 1 Operation and sum D5 A15
maintenance of maintenance The operation and Item description
plant manual maintenance of plant for operation and
2 Training of operating sum only applies to work maintenance of
personnel where the process plant shall state the
3 Provision of sum plant is required to be sequence/interval,
manpower tested. type, requirement and
4 Provision of chemicals sum duration in month.
and consumables
5 Utility cost sum
CLASS A: GENERAL ITEMS
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
3 Project D6 A16
requirements Training shall include Item description for
all training materials, training of operating
manhours, mobilisation, personnel shall state
demobilisation, the duration of training.
competent personnel,
specific tools,
accommodation and all
other required items to
complete the training.

D7
Operation and
maintenance manual
shall include all
operational manual
material,
man hours, competent
personnel, and all
other required items to
complete the operation
and maintenance
manual for the training.

4 Maintenance 1 Scheduled sum D8 C6


maintenance Care of works Items for scheduled
2 Care of works sum shall start after the maintenance shall be
certificate of practical deemed to include
completion until labours, mobilisation
the end of defect and demobilisation
liability period or line of plant, specialist
completion whichever personnel, specific
applicable. tools and all other
required items to
operate fully functional.

C7
Items for care of works
shall be deemed to
include providing
security services,
payment of all the
utilities charges and
maintain existing
facilities.

MyCESMM2 |
7
CLASS A: GENERAL ITEMS
8
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
3 Project 5 Maintenance of 1 Routine sum D9 C8 A17
requirements road maintenance – Maintenance of road Routine and periodic Item description for
existing road shall be as defined maintenance shall be maintenance of road
2 Periodic sum in the standard deemed to comply shall state the type of
maintenance – specification for road with the requirements maintenance required.

| MyCESMM2
(MyCESMM2)

existing road works as specified. as expressly stated.


3 Routine sum
Malaysian Civil Engineering

maintenance – D10
temporary Routine maintenance is
road diversion the road maintenance
4 Periodic sum works which include
maintenance – pothole patching, drain
temporary cleaning, grass cutting,
road diversion road sweeping, and
other ancillary work.

D11
Standard Method of Measurement ̵ Second Edition

Periodic maintenance
refers to the
resurfacing work
required to be done
for the duration or
period as stated in the
contract.

6 Clearance of sum C9
site upon Clearance of site upon
completion completion shall be
deemed to include
making good all
affected works.
7 Temporary vworks 1 Traffic diversion sum D12 C10 A18
2 Traffic regulation sum Item traffic diversion is Traffic diversion shall Item description for
3 Access roads sum diversion of traffic on be deemed to include de-watering shall state
4 Bridges sum existing road. temporary road controlled de-watering
5 Cofferdams sum diversion. when required.
6 Pumping sum
7 De-watering sum
8 Compressed air sum
for tunnelling

8 Access to site 1 Restrictions on sum M8


working hours Items access to site
2 Restrictions on sum shall be provided
working methods where there are
restrictions on working
hours.
CLASS A: GENERAL ITEMS
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
4 Authorities 1 Occupational safety 1 Occupational health sum D13 C11 A19
requirements and health and safety plan HAZOP is a study on The appointment of Item description for
requirements 2 Occupational safety man-mth structured hazard and the occupational safety health and safety
and health officer operational to identify and health officer shall report shall state
3 Personal protective sum and evaluate problems be deemed to include the number of sets
equipment which may represent site safety supervisors required.
4 Health and safety mth risks to personnel or for the duration of the
report equipment. construction period.
5 Training on health sum
and safety D14 C12
6 Safety signages sum HAZREV is the review Items for health and
7 Safety tools, sum of the HAZOP after safety report shall be
apparatus and completion. deemed to include tool
equipment box meeting.
8 HAZOP & HAZREV sum
2 Permits and fees sum D15 A20
3 Deposit sum License shall be Item description for
4 License to sum classed as permit and permits and fees shall
contravene fees. state the name of the
authorities and identify
the requirement under
the respective contract.
5 Contractor 1 Facilities 1 Office sum M9 C13 A21
requirements 2 Office equipment sum Items for method- Items for contractor Item description for
3 Laboratories sum related charges, if any, requirements shall be laboratories equipment
4 Laboratories sum shall be inserted by the deemed to include the shall specify type and
equipment tenderer in accordance provision of facilities quantity of equipment
5 Stores sum with Section 6. and their continuing required.
6 Workshops sum operation and
7 Workmen sum maintenance.
accommodations
8 Transport sum
2 Temporary work 1 Access roads sum
2 Bridges sum
3 Cofferdams sum
4 Pumping and sum
dewatering
5 River diversion sum
6 Jetty sum
7 Staging sum
8 Compressed air sum
3 Temporary work 1 Access scaffolding sum
2 Support scaffolding sum
and propping
3 Piling sum
4 Formwork sum
5 Shafts and pits sum

MyCESMM2 |
6 Hardstanding sum

9
CLASS A: GENERAL ITEMS
10
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
5 Contractor 4 Services 1 Electricity sum
requirements 2 Water sum
3 Sanitary facilities sum
4 Hoardings sum
5 Site transport sum

| MyCESMM2
(MyCESMM2)

6 Security sum
7 Other services sum
Malaysian Civil Engineering

5 Site management 1 Supervision sum D16


2 Administration sum Supervision shall
3 Labour teams sum include site agents and
QA/QC officer.
Standard Method of Measurement ̵ Second Edition

6 Mobilisation and sum C14 A22


demobilisation Mobilisation and Item description for
demobilisation shall mobilisation and
be deemed to include demobilisation state
remobilisation, if the conditions on
expressly required. how remobilisation is
required.

6 Design and build 1 Preliminary sum D17 C15


element engineering studies Design and build Design fees shall be
2 Engineering survey sum element applies to deemed to include
3 Utilities survey sum the design and build reimbursable but
4 Site investigation sum contract. exclude professional
indemnity insurance,
unless expressly
required.
5 Consultant fees 1 Design sum
2 Supervision sum

6 Independent 1 Structural sum


checkers fees 2 Geotechnical sum
3 Road safety sum
CLASS A: GENERAL ITEMS
CLASS B
ENVIRONMENTAL
PROTECTION AND
ENHANCEMENT

MyCESMM2 | 11
12
ADDITIONAL
CLASS B: ENVIRONMENTAL PROTECTION AND ENHANCEMENT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES

Measurement covered under other classes: M1 C1


Temporary works and Preparation of EMP,
Traffic management and control (included in Class C: Traffic management and permanent works shall flora survey report,
control). be clearly stated and fauna survey report,
identified in the item environmental

| MyCESMM2
(MyCESMM2)

Geotextile and geogrid items (included in Class G: Geotechnical work). description. monitoring report and
Bio-degradable erosion control blanket (included in Class F: Earthworks). environmental audit
Malaysian Civil Engineering

report shall be deemed


to include the cost of
any survey required,
literature, references,
consultation and the
production of the
documents. It shall
also include the cost
for the engagement
of the environmental
Standard Method of Measurement ̵ Second Edition

specialists registered
with DOE required
for carrying out the
respective survey and
the preparation of the
said survey report.

C2
Item for appointment
of environmental
officer shall be deemed
to include appointment
of qualified and
experienced officer.

FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT

1 Environmental 1 Preparation of sum D1 A1


management plan environmental EMP is a document Item description on the
management plan describing the preparation of the EMP
2 Appointment of man-mth contractor’s proposal shall state additional
environmental on the contractor’s requirements.
officer organisation
structure, work
programme related
to environmental
abatement and
mitigating measures,
environmental
monitoring
programmes, and
environmental auditing
and reporting.
CLASS B: ENVIRONMENTAL PROTECTION AND ENHANCEMENT
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
1 Environmental D2
management plan EMP shall be prepared
in accordance with
the general guidelines
for the preparation
of the EMP published
by the DOE and JKR
ArahanTeknik (Jalan).
2 Erosion and 1 Silt fence m D3 C3 A2
sediment control 2 Silt curtain m2 Requirements of silt Items for silt fence, Item description for silt
plan 3 Sand bag nr fence, silt curtain, sand silt curtain, sand bag, fence shall state the
4 Gabion wall m3 bag, gabion wall and gabion wall and rock height of the fence.
5 Rock check dam m3 rock check dam shall check dam shall be
be in accordance with deemed to include A3
JKR Arahan Teknik provisions as expressly Item description for
(Jalan) and MSMA. required and removal gabion wall shall state
of the items upon type and size of
completion, unless material and wire
otherwise stated. gauge.

C4 A4
Items for gabion wall Item description for
and rock check dam sand bag shall state
shall be deemed to type and size.
include excavation and
other requirements as
expressly stated.

6 Sediment basin 1 Excavation m3 D4 C5 A5
7 Silt trap 2 Granular filling m3 Requirements of Items for granular Items description for
3 Concrete m3 sediment basin and filling shall be deemed concrete shall state the
4 Reinforced m silt trap shall be in to include imported fill grade and type.
concrete pipe accordance with MSMA as expressly required.
5 Rock-filled gabion m3 and as specified. A6
6 Rock-filled gabion m3 C6 Items description for
mattress D5 Items for concrete reinforced concrete
7 Riprap m2 Gabions filled with shall be deemed to pipe shall state the
rocks exceeding 300 include formwork and diameter and class.
mm high shall be reinforcement.
classed as rock-filled A7
gabion and those not Item description for
exceeding 300 mm rock-filled gabion and
high as rock-filled rock-filled gabion
gabion mattress. Filling mattress shall state
shall be deemed to material type and wire
be imported, unless gauge size.
otherwise stated.
A8

MyCESMM2 |
Item description for
rock-filled gabion

13
CLASS B: ENVIRONMENTAL PROTECTION AND ENHANCEMENT

mattress and riprap


shall state the thickness.
14
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
2 Erosion and 8 Maintenance 1 Silt fence sum C7
sediment control 2 Silt curtain sum Items for maintenance
plan 3 Sand bag sum of silt fence, silt curtain,
4 Gabion wall sum sand bag, gabion wall,
5 Rock check dam sum rock check dam,

| MyCESMM2
(MyCESMM2)

6 Sediment basin sum sediment basin, and


7 Silt trap sum silt trap shall be
Malaysian Civil Engineering

deemed to include
disposal of accumulated
debris, sediment and
silt to approved site,
and all associated
works as expressly
required.
3 Water quality 1 Skid tank bund sum M2 D6 C8 A9
control and 2 Water treatment sum Water treatment and Water treatment Items for skid tank Item description for
Standard Method of Measurement ̵ Second Edition

monitoring facilities sewage treatment facilities are used bund shall be deemed skid tank bund shall
3 Sewage treatment sum facilities shall only be to treat effluent to include traps, oil state the intended
facilities measured where it is produced by the work and grease separators, location, material and
expressly required. processes in the work and its maintenance principal dimensions.
that are required to and removal upon
be discharged off the completion.
site to comply with the
Environmental Quality
Act.

D7
Waste water treatment
facilities is used to
treat sewage from the
contractor’s workmen
accommodation.

4 Water quality 1 pH nr M3 D8 C9 A10


sampling and in situ 2 Total suspended nr Sewage and effluent Sewage and effluent Items for water Item description for
testing solid testing shall be testing are tests and quality testing shall water quality testing
5 Water quality 3 Biochemical nr measured for project analysis carried out be deemed to include shall state interval and
sampling and oxygen demand involving sewage on raw samples to testing by approved type of testing, testing
laboratory testing 4 Chemical oxygen nr treatment. determine content of accredited laboratory location, duration of
6 Sewage and demand effluent or wastewater for analysis, compile report and analysis
effluent testing 5 Dissolved oxygen nr within parameters and submit the analysis on monthly basis for
6 Escherichia coli nr stated. report to the engineer the duration of the
7 Ammoniacal nr on a monthly basis contract.
nitrogen for the duration of the
8 Oil and grease nr contract.
CLASS B: ENVIRONMENTAL PROTECTION AND ENHANCEMENT
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
3 Water quality C10 A11
control and Items for sewage and Item description for
monitoring effluent testing shall water quality sampling
be deemed to include shall state the water
testing and analysis by parameters required
accredited laboratory. by DOE, the interval
and type of testing
including the sampling
location.

A12
Item description for
sewage and effluent
testing shall state
the parameters
and as required
by the regulatory
requirements.
4 Air quality control 1 Tyre washing set C11 A13
and monitoring facilities Items for tyre washing Item description for
2 Wash trough nr facilities shall be tyre washing facilities
3 Water bowser truck nr deemed to include shall state type and
4 Water sprinkler sum construction of tyre equipment required.
washing concrete
platform and provision A14
and maintenance of Item description for
water supply system wash trough shall
and portable water jets. state the material and
principal dimensions.
C12
Items for water bowser A15
truck shall be deemed Item description
to include the provision for water bowser
and maintenance of truck shall state the
the vehicle, water minimum number of
supply, and driver. water spraying per day.

C13 A16
Items for water sprinkler Item description for
shall be deemed to water sprinkler shall
include provision and state the type, location
maintenance of water and equipment
supply. required.
5 Air quality sampling 1 Total suspended nr C14 A17
particulates Air quality sampling Item description
2 Wind velocity and nr shall be deemed to for air quality
direction include testing by sampling shall state
3 Particulate matter nr

MyCESMM2 |
accredited laboratory. the air parameters,
interval and type
testing including the

15
CLASS B: ENVIRONMENTAL PROTECTION AND ENHANCEMENT

sampling location.
16
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
5 Noise and vibration 1 Noise barrier m M4 C15 A18
control and 2 Vibration control sum Measurement for Items for noise Item description for
monitoring item of noise barrier barrier shall be noise barrier shall
shall be the exposed deemed to include state the height,

| MyCESMM2
plain surface area on supply, fabrication, type, material and
(MyCESMM2)

the traffic side of the installation, bolts, enclosure.


3 Noise level 1 Ambient noise nr barrier. nuts, posts and other
Malaysian Civil Engineering

measurement level measurement ancillary work. A19


2 Spot noise level nr Item description
measurement C16 for noise level
Noise level and vibration
and vibration measurements
4 Vibration 1 Ground vibration sum measurements shall state the
measurement 2 Structural vibration sum shall be deemed to type, duration
include services by and frequency
accredited laboratory. of measurement
Standard Method of Measurement ̵ Second Edition

required and the


location.
6 Waste management 1 Scheduled wastes sum M5 D9 C17 A20
2 Household solid sum Household and Scheduled wastes Items for scheduled Item description for
waste construction solid shall be those wastes wastes and recycle bio-solid waste shall
3 Construction solid sum waste shall be deemed as prescribed in the waste shall include state conformance
waste to be included in Environmental Quality separation and with local authority
4 Biomass disposal sum Class A and shall be Act. recycling storage, regulations, treatment
5 Bio-solid waste sum measured only where it labelling, and required and
6 Temporary sum is expressly required. D10 transportation from parameters.
treatment facilities Household solid site by a licensed
M6 waste means any solid contractor for disposal
Biomass disposal is waste generated by a as per the DOE
deemed to be included household and of the regulation and Solid
in Class E and shall be kind that is ordinarily Waste and Public
measured only where it generated or produced Cleansing Management
is expressly required. by any premises Act respectively.
when occupied as a
M7 dwelling house, and C18
Bio-solid waste shall includes garden waste Items for household
be measured in sum. as prescribed in the and construction solid
Solid Waste and Public waste shall be deemed
Cleansing Management to include provision
Act. of collection bins,
temporary storage
D11 area, and disposal to
Temporary treatment approved site as per
facility is required DOE regulations.
whenever any existing
treatment process
to be shut down
during upgrading,
refurbishment or
maintenance.
CLASS B: ENVIRONMENTAL PROTECTION AND ENHANCEMENT
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
6 Waste management D12 C19
The temporary Items for biomass
treatment facilities disposal shall be
shall be designed deemed to include
to comply with preparation and
related parameters as construction of
expressly stated. temporary area and the
disposal to approved
D13 site.
Construction solid
waste means any solid C20
waste generated from Items for temporary
any construction or treatment facilities
demolition activity, shall be deemed to
including improvement, include design and
preparatory and repair construct prior to
or alteration work divert existing flow into
as prescribed in the temporary treatment
Solid Waste and Public facility and able to
Cleansing Management maintain existing
Act. performance.

D14 C21
Organic matter Items for bio-solid
including forest and waste shall be deemed
agricultural waste to include collection,
generated from site composting temporary
clearing activities shall storage area,
be classed as biomass. transportation and
haulage to designated
D15 locations.
Bio-solid waste
is treated sewage
sludge converted to
soil conditioner for
agricultural purposes.

MyCESMM2 |
17
CLASS B: ENVIRONMENTAL PROTECTION AND ENHANCEMENT
18
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
7 Conservation/ 1 Preservation of 1 Flora survey report sum D16 C22 A21
Preservation flora 2 Relocation of flora nr Flora survey report is a Items for the relocation Item description for
to approved sites document identifying of flora shall be the flora survey report
3 Relocation of flora nr the flora species and deemed to include shall state the number
to arboreta their distribution, in the cost of relocation or sets of documents

| MyCESMM2
(MyCESMM2)

particular those of to the temporary to be produced.


rare, endangered, and the final sites
Malaysian Civil Engineering

and endemic flora specified. It shall also


species that require include excavation,
preservation and transportation,
conservation, which protection, watering,
may include possible fertilising and nurturing
relocation to other until the flora are
designated sites. established at the
temporary and the final
sites of relocation.
Standard Method of Measurement ̵ Second Edition

2 Preservation of 1 Fauna survey report sum D17 C23 A22


fauna 2 Relocation of fauna nr Fauna survey is to Items for the relocation Item description for the
identify the fauna of fauna shall be relocation of flora shall
species and their deemed to include state the flora species
distribution, in the cost of temporary and the temporary and
particular those of relocation to the final sites of relocation.
rare, endangered, and rehabilitation centres
endemic fauna species and final relocation to A23
that require protection sites specified. It shall Item description for
and rehabilitation, also include trapping, the fauna survey report
which may include transportation and shall state the number
possible relocation to protection, and or sets of documents
other designated sites. treatment required to be produced.
for the well being
3 Preservation of 1 Report sum of the fauna at the A24
archaeological/ 2 Protection sum rehabilitation centres Item description for
heritage sites and before their the relocation of
release at the final fauna shall state the
place of relocation/ fauna species and
rehabilitation. sites of temporary
and final relocation/
rehabilitation.
CLASS B: ENVIRONMENTAL PROTECTION AND ENHANCEMENT
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
8 Environmental 1 Environmental sum D18 A25
report monitoring report Environmental Item description
2 Environmental sum monitoring report for environmental
audit report is the report on the monitoring report shall
3 Environmental sum assessment of the state the parameter
closure audit report effectiveness of compliance with
the environmental current regulations,
protection measures indicating the interval
and the identifying of report submission,
of threshold value as number or sets of
a trigger mechanism documents to be
for corrective and produced.
preventive actions
in cases where A26
the environmental Item description for
standards are environmental audit
breached. report shall state
the interval between
D19 report submissions,
Environmental audit and the number or sets
report is the report of documents to be
on the evaluation produced.
of the adequacy
and compliance of A27
the environmental Item description for
management environmental closure
programme. audit report shall state
the number or sets
D20 of documents to be
Environmental produced.
closure audit report
is the report on
the evaluation of
the adequacy and
compliance of the
environmental
management
programme prior to
the issuance of the
certificate of practical
completion.

MyCESMM2 |
19
CLASS B: ENVIRONMENTAL PROTECTION AND ENHANCEMENT
Malaysian Civil Engineering
Standard Method of Measurement ̵ Second Edition
(MyCESMM2)

20 | MyCESMM2
CLASS C
TRAFFIC
MANAGEMENT
AND CONTROL

MyCESMM2 | 21
22
ADDITIONAL
CLASS C: TRAFFIC MANAGEMENT AND CONTROL MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES

Measurement covered under other classes: M1 D1 C1 A1


Temporary road The traffic The preparation of Item description for
Earthworks (included in Class F: Earthworks). diversion involving management plan is a traffic management traffic management
earthwork, roads, document describing plan shall be deemed plan shall state the
Roadwork (included in Class R: Roads and pavings). and pavings shall be the contractor’s to include the cost of number of copies and

| MyCESMM2
(MyCESMM2)

measured separately proposed strategy any survey required, format of the report.
under their respective and procedure to literature, references,
Malaysian Civil Engineering

classes. mitigate and minimise consultations, and


the impacts of the the production of the
construction of the document. It shall
work on the capacity, also include the cost
performance and for the engagement
safety of the local road of qualified traffic
network and traffic engineers required
system to authorities for carrying out the
approval. respective study and
preparation of the plan.
Standard Method of Measurement ̵ Second Edition

FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT

1 Traffic management 1 Traffic impact study sum M2 D2 C2


plan 2 Preparation of sum Traffic impact study to Traffic impact study Traffic management
traffic management be measured only as is an assessment plan shall be deemed
plan expressly required. of the impact of a to include emergency
construction proposal response plan, parking
on the existing traffic. space for machinery
and the associated
work.

3 Traffic management 1 Traffic manager man-mth


team 2 Traffic management man-mth
officer
3 Supervisor man-mth
4 Traffic controller man-mth
CLASS C: TRAFFIC MANAGEMENT AND CONTROL
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
2 Temporary road 1 Temporary traffic 1 Non-illuminated nr M3 D3 C3 A2
furniture signs retro-reflective Lengths measured Barriers and barricades Items for traffic signals Item description for
sheeting for linear temporary are impenetrable shall be deemed to temporary traffic signs
2 Portable changeable nr road markings shall devices meant to guide include signal posts shall state the type,
message signs not include gaps in and channel traffic or signal mast arms, size, substrate, the
(PCMS) intermittent line. away from hazardous signal lanterns, traffic reflective sheeting,
3 Traffic signals set work zone area. controllers, cabling material, grade and
and removal upon whether they are fixed
D4 completion. or portable.
Delineators are devices
to guide and channel
traffic through a work
zone area.

2 Barriers and 1 Heavy duty water/ nr D5 C4 A3
barricades sand-filled PVC The colour of the Items for temporary Item description
barrier temporary road road furniture shall for traffic signals
2 Concrete barrier nr markings, unless be deemed to include shall state the
3 Wooden barricade nr otherwise stated shall the supply, installation, number of optical
4 Sand bags m3 be deemed to be maintenance and systems for each set
5 Temporary guardrail m yellow. removal upon and the mounting
completion. requirements.

C5 A4
The supply of Item description heavy
temporary road duty PVC barrier shall
furniture shall be state to be filled with
deemed to include water or sand.
base preparation, cost
of material, fabrication,
and fixing including
posts, struts, bolts and
nuts, base, storage and
transportation.
3 Delineators 1 Cones nr M4 D6 C6 A5
2 String delineators m Area measurement Heavy duty water/ Installation of Item description
3 Flashing arrows nr for chevron markings sand filled PVC temporary road for barriers and
4 Beacon lights nr shall be the gross barrier shall include furniture shall be barricades shall state
5 Blinkers nr area. plastic hoarding deemed to include the type, material,
6 Delineator strip nr where expressly cost for multiple dimensions and
required. shifting within whether fixed or
the contractual portable.
D7 boundaries and
Super cones shall its vicinities that is A6
be classed as cones affected by the traffic Item description for
where expressly management plan. super cones shall
required. state the materials,
size and shape

MyCESMM2 |
including fixed or
portable.

23
CLASS C: TRAFFIC MANAGEMENT AND CONTROL
24
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
2 Temporary road 4 Temporary road 1 Letters and shapes nr C7 A7
furniture markings 2 Continuous line m Temporary road Item description for
3 Intermittent line m furniture shall be delineators shall state
4 Chevron marking m2 deemed to include the type, material and
5 Transverse bars m2 cost for the inspection, dimensions.

| MyCESMM2
(MyCESMM2)

immediate repair
and replacement
Malaysian Civil Engineering

of any damaged,
missing or stolen
items throughout
the duration of
the construction,
and removal upon
completion.

5 Mechanical robot nr C8 A8
Standard Method of Measurement ̵ Second Edition

flagman Mechanical robot Item description for


6 Temporary street nr flagman shall be mechanical robot
lightings deemed to include flagman shall state
7 Vehicle-mounted nr cost of power whether half-man or
impact attenuator pack, installation, full-man.
maintenance and
removal upon A9
completions. Item description for
vehicle-mounted
impact attenuator shall
state the type.

3 Traffic management 1 Traffic management sum D8 C9 A10


report safety report Traffic management The preparation of Item description for
2 Road safety audit sum safety report is road safety audit traffic management
report the report on the report shall be deemed safety report shall
assessment of the to include the cost of state the interval of
effectiveness of the any survey required, the report submission
traffic management literature, references, and the number of
plan and to identify consultations and documents or sets to
any unsafe conditions the production of the be produced.
and to collect any road document. It shall also
accident data for the include the cost to A11
purpose of corrective engage the road safety Item description for
and preventive action. auditor to carry out the road safety audit
audit and prepare the report shall state the
D9 audit report. interval of the report
The road safety submission and the
audit report shall be number of documents
prepared in accordance or sets to be produced.
with the Guidelines for
The Safety Audit of
Roads in Malaysia by
the relevant authority.
CLASS C: TRAFFIC MANAGEMENT AND CONTROL
CLASS D
SITE INVESTIGATION
WORK

MyCESMM2 | 25
26
ADDITIONAL
CLASS D: SITE INVESTIGATION WORK MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES

Measurement covered under other classes: M1 D1 C1 A1


The depth of boring, Plant movement is the Items for plant Item description for
Excavation not carried out for the purpose of soil investigation work (included in drilling, sampling. shifting of plant and movement shall be water sample shall
Class F: Earthworks). and testing shall be ancillaries/ equipment deemed to include state the volume.
measured from the from one borehole/test dismantling and

| MyCESMM2
(MyCESMM2)

Mobilisation and boring for piling (included in Class H: Piling work). commencing surface as position to the next erecting from one A2
Survey and setting out (included in Class A: General items). follows: position. position to another. Item description for
Malaysian Civil Engineering

disturbed sample shall


Instrumentation (included in Class G : Geotechnical work).
a) Not exceeding 10 m. D2 C2 state the weight of
b) 10 m - 20 m. Hillslopes is an access Sampling shall be samples.
c) 20 m - 30 m. with gradient greater deemed to include
d) 30 m - 40 m. than 15 degrees. transportation and A3
e) 40 m - 50 m. preservation. Item description for
f) Exceeding 50 m. D3 block sample shall
Small disturbed C3 state the size of
samples is less than All field explorations sample.
5 kg. and tests shall be
Standard Method of Measurement ̵ Second Edition

deemed to include A4
daily field records Item description for
and sample logging site investigation work
in accordance with shall state the category
relevant codes of of land.
practice.

FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT

1 Mobilisation and 1 Deep boring sum C4


demobilisation 2 Cone penetration sum Items for mobilisation
tests and demobilisation
3 Miscellaneous tests sum shall be deemed to
include provision of
all plant, equipment
and ancillaries,
transportation to
the site and removal
off the site upon the
completion of the
operation.
2 Deep boring 1 Plant movement 1 Land nr C5 A5
2 Miscellaneous plant 2 Hillslopes nr Deep boring shall Item description for
3 Over water nr be deemed to deep boring and
4 Swampy ground nr include ground water drilling in rock shall
3 Boring in soil 1 Water m observation. state type and make
2 Water with additives m of boring plant,
3 Air/foam m C6 ancillaries, inclination
Plant movement on angle, diameter of
4 Drilling in rock 1 Water m land, over water and boring and depth as
2 Water with additives m swamp area shall be per measurement rule
3 Air/foam m deemed to include M1.
4 Reaming casing m stable platform.
5 Grouting m3
CLASS D: SITE INVESTIGATION WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
2 Deep boring 5 Test 1 Standard penetration nr C7 A6
2 Vane shear nr Boring in soil shall be Item description for
3 Pressure meter nr deemed to include testing shall state the
4 Field permeability nr provision of casing type of test, cycles
5 Dynamic cone nr where necessary. where applicable,
6 Sampling 1 Disturbed sample nr nominal diameter
2 Undisturbed sample nr C8 and the depth, as per
using thin wall tube Drilling in rock shall measurement rule M1.
sampler be deemed to include
3 Undisturbed sample nr core boxes and A7
using Mazier sampler become the property Item description for
4 Undisturbed sample nr of the employer, unless sampling shall state the
using piston sampler otherwise stated. size, type, and depth,
5 Undisturbed sample nr as per measurement
using Denison rule M1.
sampler
6 Water sample nr
7 Miscellaneous 1 Borehole marker nr

3 Cone penetration 1 Plant movement 1 Land nr A8


tests 2 Hillslopes nr Item description for
cone penetration test
shall state the type,
capacity of cone,
machine capacity,
and depth, as per
measurement rule M1.

2 Test 1 Mechanical cone m A9


2 Piezocone m Item description for
3 Dissipation test nr dissipation test shall
state the maximum
hours of test required.

3 Miscellaneous 1 Test location nr


marker

MyCESMM2 |
27
CLASS D: SITE INVESTIGATION WORK


28
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
4 Miscellaneous test 1 Hand auger 1 Augering in soil m C9 A10
2 Disturbed sample nr Miscellaneous tests Item description for
3 Undisturbed nr shall be deemed miscellaneous test
samples using thin to include plant shall state special
wall tube sampler movements on the site. preparation for

| MyCESMM2
(MyCESMM2)

4 Water sample nr equipment when


C10 expressly stated to be
Malaysian Civil Engineering

Hand auger shall be provided separately.


deemed to include
ground water A11
2 Trial pit 1 Excavation nr observation. Item description for
2 Small disturbed nr trial pit shall state the
sample C11 dimensions.
3 Bulk sample nr Trial pit shall be
4 Block sample nr deemed to include A12
5 Water sample nr lateral support, ground Item description
water observation, for miscellaneous
Standard Method of Measurement ̵ Second Edition

logging and mapping tests shall state the


of site wall, and equipment used,
backfilling, unless setting up where
3 Mackintosh probe nr otherwise stated. applicable, method and
4 Vane shear nr depth.
5 Plate bearing nr
6 In situ CBR nr A13
7 Pocket nr Item description for
penetrometer plate bearing test
8 Field density nr shall state the required
plate size, test load, or
pressure and number
of cycles.
5 Miscellaneous test 1 Sampling 1 Small disturbed nr D4 A14
sample Samples taken from Item description for
2 Bulk sample nr location other than sampling shall state
3 Undisturbed nr borehole, hand auger the location (which is
samples using thin or trial pit shall be other than borehole,
wall tube sampler classed as sampling. hand auger and trial
4 Block sample nr pit).
5 Water sample nr
6 Bulk density nr
CLASS D: SITE INVESTIGATION WORK


ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
6 Laboratory tests 1 Classification 1 Moisture content nr D5 C12 A15
2 Atterberg’s limits. set A set, for soil strength Laboratory tests Item description for
3 Specific gravity nr tests, shall be defined shall be deemed to laboratory tests shall
4 Particle size nr as of three specimens; include preparation of state the method
distribution for fine except for unconfined specimens. of testing and the
grained soils compresssive test shall standard requirements.
5 Particle size nr be defined as of two C13
distribution for specimens. Special preparation A16
coarse grained soils for equipment shall be Item description for
2 Soil strength 1 Unconfined set deemed to be provided soil strength tests
compressive strength separately when shall state the size of
2 Unconsolidated set expressly stated. testing specimen and
undrained triaxial type of soil sample,
compression i.e. undisturbed or
3 Consolidated set remoulded.
undrained triaxial
compression test A17
with pore water Item description for
pressure direct shear box and
measurement multi reversal shear
4 Consolidated set box tests shall state
drained triaxial the size of the shear
compression test box.
with pore water
pressure
measurement
5 Direct shear box set
6 Multi reversal shear set
box
3 Soil compaction 1 Standard compaction set D6 C14 A18
related (2.5 kg hammer) A set, for soil CBR test shall be Item description for
2 Heavy compaction set compaction related deemed to be carried contaminants shall
(4.5 kg hammer) test, shall be defined as out on both ends of state the standard
3 Vibrating hammer set of five specimen tests each specimen, unless requirements and the
4 Unsoaked CBR nr from the same bulk otherwise stated. contaminants to be
5 Soaked CBR nr sample. analysed.
4 Chemical and 1 Organic matter nr
electro-chemical content
2 Loss on ignition nr
3 Total sulphate nr
content
4 Sulphate content nr
5 Chloride content nr
6 pH value nr
7 Resistivity test nr
8 Contaminants nr

MyCESMM2 |
29
CLASS D: SITE INVESTIGATION WORK
30
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
6 Laboratory tests 5 Rock strength 1 Unconfined nr
compressive
strength
2 Unconfined nr
compressive

| MyCESMM2
(MyCESMM2)

strength with
Young’s Modulus
Malaysian Civil Engineering

and Poisson’s ratio


measurement
3 Point load nr
4 Petrographic nr
examination
6 Compressibility and 1 One dimension nr
permeability consolidation
2 Variable head nr
permeability
Standard Method of Measurement ̵ Second Edition

3 Fixed head nr
permeability
7 Geophysical survey 1 Seismic refraction 1 Setting out sum M2 D7 C15 A19
and mapping survey 2 Installation and spread Intervals of geophones A spread of installation Setting out for seismic tem description
2 Multi-channel readings for seismic refraction and readings shall refraction survey, for installation and
analysis 3 Preparation of sum survey and multi- include a 24-channel multi-channel analysis readings for seismic
of surface wave bedrock and soil channel analysis of seismograph with of surface wave and refraction survey and
(MASW) contour maps surface wave shall be geophones at not more resistivity profiling multi-channel analysis
measured along the than 5-metre intervals shall be deemed of surface wave shall
3 Parallel seismic 1 Setting out sum
slope. for seismic refraction to include survey state the interval of
logging 2 Installation and point
survey and not more coordinates, reduced geophones, number of
readings
than 3-metre intervals levels and topographic shots per set and the
3 Preparation of sum
for multi-channel profile for each set type of shots required.
subsurface
analysis of surface of installation and
profiles
wave survey. readings. A20
Item description
for installation and
readings for resistivity
profiling shall state the
type of configuration,
number, and interval of
electrodes required.

4 Resistivity profiling 1 Setting out sum M3 D8 A21


2 Installation and spread Intervals of electrodes Resistivity profiling Item description for
readings for resistivity profiling shall be two- installation and reading
3 Preparation of sum shall be measured dimensional with for gravity imaging
resistivity profiles along the slope. electrodes at not more and profiling shall state
5 Gravity imaging 1 Setting out sum than 5-metre intervals. the interval distance
2 Installation and point M4 of every gravitymeter
readings A spread shall be 115 point reading.
3 Preparation of sum m line.
gravity imaging
and profiles
CLASS D: SITE INVESTIGATION WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
7 Geophysical survey 6 Geological terrain 1 Preparation of m2 M5 D9 C16 A22
and mapping mapping thematic maps Area measured for Geological terrain Items for verification Item description for
geological terrain mapping and with utilities provider seismic refraction
mapping and engineering geological shall be deemed to survey and geological
engineering geological mapping shall include purchasing of terrain mapping and
mapping shall be the be in accordance necessary documents engineering geological
plan area. with guidelines and verification on mapping shall state
by the Minerals the utilities detected, the location and
and Geoscience as compared with the area of the site to be
7 Engineering 1 Preparation of m2
Department Malaysia. records of the utilities investigated.
geological mapping engineering
provider.
geological map
A23
Item description for
geological terrain
mapping and
engineering geological
mapping shall state
8 Utilities detection 1 Locate, detect, and sum the requirement
and mapping map all utilities and in the Minerals
services and Geoscience
2 Verification with sum Department guidelines.
utilities provider
3 Conduct site sum
verification

8 Report 1 Preliminary report 1 Soil investigation sum D10 C17 A24


2 Final report 2 Geophysical survey sum A report shall include Items for soil Item description for
and mapping instrumentation investigation report report shall state
reading and data shall be deemed to the type, number of
interpretation by include laboratory test sets and the format
professional engineers. results. required.

C18
Items for geophysical
survey and mapping
report shall be
deemed to include
geological sections and
interpretations of data
by specialists.

MyCESMM2 |
31
CLASS D: SITE INVESTIGATION WORK
Malaysian Civil Engineering
Standard Method of Measurement ̵ Second Edition
(MyCESMM2)

32 | MyCESMM2
CLASS E
DEMOLITION AND
SITE CLEARANCE

MyCESMM2 | 33
34
ADDITIONAL
CLASS E: DEMOLITION AND SITE CLEARANCE MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES

Measurement covered under other classes: D1 C1 A1


Site clearance shall Items for demolition Item description for
Stripping of top soil (included in Class F: Earthworks). include general and site clearance work from which
clearance, the shall be deemed to the materials arising
Scarifying of road surfaces (included in Class R: Roads and pavings). demolition and removal include disposal of the remain the property

| MyCESMM2
(MyCESMM2)

Dismantling of rail track (included in Class T: Rail track). of all articles, objects, materials arising and of the employer shall
and obstructions stating disposal area be stated as well as
Removal of existing pipeline below ground level not exceeding 300 mm
Malaysian Civil Engineering

which are expressly on or off site. the handing over and


(included in Class F: Earthworks).
required to be cleared, location of storage.
except those for Where the so stated
which separate items materials are to be
are given as set out salvaged by the
in this class. Clearing contractor, a separate
shall also include the bill of credit shall be
levelling of obsolete prepared.
dikes, terraces, ditches,
etc.
Standard Method of Measurement ̵ Second Edition

FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT

1 General clearance 1 Above ground ha M1 D2 C2 A2


2 Water bodies ha Area measured for General clearance Items for general Item description for
general clearance shall above ground shall clearance above general clearance
be the plan area. consist of the cutting ground shall be above ground shall
and/or taking down, deemed to include state the type of
M2 removal, and disposal the removal of trees vegetation such as
Where measurement of everything above and stumps (unless primary forest, bushes,
for trees are expressly ground level, including otherwise stated in oil palm estate, etc.
required, it shall be objects overhanging the item description),
measured as trees the areas to be cleared. undergrowth, shrubs, A3
under Class E2*0. roots, and the like. Item description for
D3 general clearance at
Water bodies shall C3 water bodies shall
consist of, but not General clearance at state the type of items
limited to, rivers, water bodies shall be and whether the object
lakes, and sea, unless deemed to include the is floating, submerged
expressly required. removal and disposal or at the bed of the
of items in or at the water bodies.
D4 water bodies, including
Site clearance using objects either floating,
plant and equipment submerged, or at
with the aid of floating the bed of the water
mechanism shall be bodies.
classed as general
clearance at water
bodies.
CLASS E: DEMOLITION AND SITE CLEARANCE
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
1 General clearance C4
Items for general
clearance which
include the removal
of hedges shall be
deemed to include
the removal of
hedges stumps of any
diameter where these
are also required to be
removed.
2 Trees 1 Trees of girth: nr M3 C5 A4
0.5 m - 1.0 m Girth of trees shall be Items for clearance Item description for
2 Trees of girth: nr measured 1 m above of trees shall be general clearance
1.0 m 2.0 m ground level. deemed to include the and trees shall state
3 Trees of girth: nr uprooting and removal the nature of the
2.0 m - 5.0 m of stumps. backfilling material
4 Trees of girth: nr where holes left
exceeding 5.0 m by stump removal
are required to be
backfilled.
3 Buildings 1 Concrete 1 Individual buildings sum D5 A5
2 Brickwork and 2 Group of buildings sum Methods of demolition Item description for
masonry of buildings shall be building and structures
3 Timber in accordance with MS shall state the number
4 Metal 2318: Code of practice of storeys and principal
for demolition of dimensions.
building.
A6
D6 Item description for
The material used building and structures
in the classification shall state special
of buildings and method of demolition
structures shall be the where required.
predominant material.
A7
4 Structures 1 Above ground sum Item description for
5 Scrap materials 2 Below ground sum scrap materials shall
state the principal
dimensions and state
special method of
demolition where
required.

MyCESMM2 |
35
CLASS E: DEMOLITION AND SITE CLEARANCE
36
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
6 Equipment and 1 Disposed off sum A8
accessories 2 Dismantle and sum Item description
refurbishment for equipment and
3 Dismantle and sum accessories shall
reinstall state the principal

| MyCESMM2
(MyCESMM2)

dimensions.
Malaysian Civil Engineering
Standard Method of Measurement ̵ Second Edition

7 Pipelines 1 Nominal bore: m M4 D7 C6


Exceeding 300 mm Pipelines within Water mains, sewers, Items for demolition
buildings and other ducts, and other of pipelines shall be
structures shall be utility services shall be deemed to include
measured separately classed as pipelines. demolition and removal
only where their of supports.
nominal bore exceeds D8
300 mm. Pipelines shall include
pipes laid below and
above ground.

8 Relocation of 1 Water sum M5


existing utilities 2 Sewerage sum Relocation of
3 Gas sum existing utilities and
4 Electrical sum materials reused shall
5 Telecommunication sum be measured and
described as A1.
CLASS E: DEMOLITION AND SITE CLEARANCE
CLASS F
EARTHWORKS

MyCESMM2 | 37
38
ADDITIONAL
CLASS F: EARTHWORKS MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES

Measurement covered under other classes: M1 D1 C1 A1


The quantities of Earth shall be deemed Items for excavation The commencing
Geotextile and geogrid (included in Class G: Geotechnical work). earthwork shall be to be materials other shall be deemed to surface shall be
computed nett using than topsoil, natural include disposal of identified in the
Site clearance (included in Class E: Demolition and site clearance). dimension from the hard material, rock, excavated material, description of each

| MyCESMM2
(MyCESMM2)

Excavation and backfill for drain and pipe in trenches (included in drawings with no artificial hard material unless otherwise item of work involving
Class O: Pipework and Class Q: Drainage work). allowance for bulking, or unsuitable material, stated. excavation for which
Malaysian Civil Engineering

shrinkage, or wastage. unless otherwise stated the commencing


Excavation for piles included (included in Class H: Piling work).
Where boundaries in item description. C2 surface is not the
Excavation for tunnels, shafts, heading and other sub-terranian cavities (included between different Items for excavation original surface. The
in Class S: Tunnel work). materials are not D2 shall be deemed to excavated surface shall
Excavation for foundation for fences and gates (included in Class V: shown on the drawings, Natural hard material include upholding be identified in the
Miscellaneous work). measurement shall be shall be material sides of excavation, description of each
made on the site. other than rock and additional excavation item of work involving
artificial hard material to provide working excavation for which
M2 that requires ripping space and removal of the excavated surface
The commencing and other specialised dead services. is not the original
Standard Method of Measurement ̵ Second Edition

surface adopted in equipment. surface.


the preparation of C3
the bill of quantities D3 Items description for A2
shall be used for the Rock and artificial excavation shall be Item description for
measurement of the hard material shall deemed to include artificial hard material
completed work. be material that removal of existing shall state the material,
requires the use of pipes not exceeding and depth to which
M3 hydraulic rock breaker, 300 mm of any extent it shall be
An item shall be given pneumatic tools or material or diameter. excavated.
for each separate stage explosives.
of excavation where A3
separate stages in the D4 Item description for
conduct of the work Disposal of excavated excavation in rock shall
are expressly required. material shall be state the method of
deemed to be disposal blasting, and whether
M4 off the site, unless for reuse or disposal.
Detached pieces of otherwise stated in
boulders shall only be item description. A4
regarded as natural Item description for
hard material, rock, or D5 excavation in natural
artificial hard material Sub-ballast shall be hard material and rock
if each individually ballast placed before shall state the method
exceeds 0.5 m³ in the bottom ballast is of excavation, where
volume and shall be laid. appropriate.
measured separately.
CLASS F: EARTHWORKS
ADDITIONAL
CLASS F: EARTHWORKS MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
M5 D6
An isolated volume of The commencing
artificial hard material surface shall be
or rock occuring within identified in the
other material to be description of each
excavated shall not be item for work involving
measured separately excavation, boring, or
unless its volume driving for which the
exceeds 1 m³ except commencing surface is
that the minimum not the original surface.
volume shall be 0.25
m³ where the net width D7
of excavation is less The depths of
than 2 m. excavation stated in
accordance with the
work classification shall
be measured from the
commencing surface to
the excavated surface.
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT

1 Excavation 1 Stripping 1 Topsoil m2 M6 A5


Area measured for Item description for
topsoil shall be the stripping of topsoil
plan area. shall state whether for
reuse or disposal.

A6
Item description for
stripping shall state
the thickness of
excavation.
2 Cut to fill 1 Earth m3 M7 D8 C4 A7
3 Cut and dispose 2 Natural hard m3 Item classed as Excavation to form Items classified as Item description for
material excavation to remove a profile expressly excavation in cut shall excavation in cut
3 Rock m3 unsuitable material required shall be be deemed to include shall state, where
4 Artificial hard m3 shall be measured, classed as cut. transportation from expressly required,
material irrespective of the source to place of fill or the excavation to be
5 Unsuitable material m3 method of excavation D9 disposal. carried out manually.
6 Hazardous materials m3 adopted by the Excavation in or under
contractor. an embankment, C5 A8
executed prior to Items classified as Item description for
placing of the fill, excavation in cut excavation in cut
shall be classed as shall be deemed to for rock shall state
excavation in cut. include the trimming any requirement for
and preparation of controlled blasting and
excavated surface. pre-splitting.

MyCESMM2 |
39
CLASS F: EARTHWORKS
40
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
1 Excavation M8 D10 A9
The volume of disposal Hazardous material Item description for
of excavated material shall include any hazardous material
measured shall be the material whose shall state the nature of
difference between excavation and the material.

| MyCESMM2
(MyCESMM2)

the total net volume of disposal is governed


excavation and the net by legislation including A10
Malaysian Civil Engineering

volume of excavated invasive plant species. Item description for cut


material used for filling. and dispose shall state
D11 backfilling in layers and
Material, either artificial compaction, where
or natural, that are required.
not to be used for the
works are classed as
unsuitable material.

D12
Standard Method of Measurement ̵ Second Edition

Disposal of excavated
material shall be
deemed to be disposal
off the site unless
otherwise stated in
item descriptions.

4 Foundation 1 Earth m3 M9 C6 A11


2 Natural hard m3 The volume measured Items for excavation Excavation for
material for the excavation for for foundation shall foundation around
3 Rock m3 foundation shall be the include upholding pile shafts, and for
4 Artificial hard m3 volume which is to be sides of excavation, underpinning, shall
material either occupied by or preparation of each be so described.
5 Unsuitable material m3 vertically above any excavated surface,
part of the structure or additional excavation A12
building. to provide working Item description
space and removal of for excavation for
dead services. foundation to be
carried out under
water shall be so
described.

A13
Maximum depth
of excavation for
foundation shall be so
described in the item
description.
CLASS F: EARTHWORKS
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
1 Excavation 5 Under water m3 M10 C7 A14
Measurement of Items for excavation Item description for
excavation under under water shall be excavation under water
water shall be made deemed to include all shall identify the water
from soundings, unless necessary temporary body and the limit of
otherwise stated. work. excavation.

M11
The volume measured
for excavation below
a body of open water
shall be the nett
volume of excavation
commencing from
firm ground level such
as river or sea bed as
shown on the drawing
to which reference is
given in the preamble
in accordance with
4.14.

M12
Item classed as
excavation under water
shall be measured,
irrespective of the
method of excavation
adopted by the
contractor.

6 Dredging 1 Provision of plant sum M13 C8 A15


and equipment Item classed as Provision of plant Item description for
2 Dredging work m3 dredging shall be and equipment for dredging shall state
measured, irrespective dredging shall be the location and limits
of the method of deemed to include of dredging.
excavation by the mobilisation and
contractor. demobilisation.

M14 C9
Measurement of Items classified as
dredging shall be made excavation by dredging
from sounding, unless shall be deemed to
otherwise stated. include transportation
from source to disposal
site.

MyCESMM2 |
41
CLASS F: EARTHWORKS
42
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
1 Excavation M15 C10 A15
The volume measured Items coverage for Item description for
for dredging below a dredging shall be dredging shall state
body of open water deemed to include the location and limits
shall be the net any mopping up of silt of dredging.

| MyCESMM2
(MyCESMM2)

volume of excavation which accumulates


commencing from after the final surface
Malaysian Civil Engineering

firm ground level such has been reached.


as river or sea bed as
shown on the drawing
to which reference is
given in the MSCESMM
in accordance with 4.14.

M16
Dredging to remove
silt shall be measured
Standard Method of Measurement ̵ Second Edition

only to the extent that


is expressly required.
2 Excavation 1 Double handling of 1 Earth m3 M17 A16
ancillaries excavated material 2 Natural hard m3 Double handling of Item description for
material excavated material excavation ancillaries
3 Rock m3 shall be measured, only in connection with
4 Artificial hard m3 to the extent that it is excavation by dredging
material expressly required. shall be so described.

M18
The volume measured
for double handling
of excavated material
shall be that of the
void formed in the
temporary stockpile
from which the
materials are removed.

2 Timber support m2 M19


left-in The volume measured
3 Metal support m2 for excavation within
left-in borrow pits shall be the
net volume measured
for filling.

M20
The area measured
for timber or metal
supports left-in shall be
the area of supported
surface for which the
supports are expressly
CLASS F: EARTHWORKS

required to be left-in.
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
3 Filling 1 General 1 Excavated material m3 M21 D13 C11 A17
2 Embankments 2 Imported material m3 All filling shall be Excavated material Items for filling shall Item description for
3 Replacement 3 Mass concrete m3 measured nett. shall be deemed to be deemed to include filling using imported
4 To structure 4 Other stated m3 Excavation after be from cut, or from filling in layers and material and excavated
5 To stated depth or material “filling” shall only be borrow pit on the site. compaction. material shall state
thickness measured where it is the type, gradation
expressly required. D14 C12 limit and size where
Imported material Items for filling applicable.
M22 shall be deemed to be shall be deemed to
Excavation from material from off site. include additional A18
borrow pit on the Site filling necessitated Item description for
for filling, shall not be D15 by settlement or filling using mass
measured separately, Filling shall be classed penetration into concrete shall state
unless expressly as to stated depth underlying material. the specification of
required. or thickness where concrete.
material is provided C13
M23 of uniform total Items for filling to
The volume of compacted depth or embankments or on
imported material thickness such as in sloping ground shall
measured shall be the drainage blankets, be deemed to include
difference between the topsoiling, pitching benches.
nett volume of filling and beaching. Bulk
and the nett volume filling shall not be
of excavated material classed as to stated
derived from work depth or thickness
within Classes F and S not withstanding that
used for filling. it may be compacted
in separate layers of
M24 material of stated
The volume of thickness.
imported fill shall be
measured nett at the
place of fill.

M25
Backfill material for
excavation to remove
unsuitable material
shall be measured as
filling under item for
filling for replacement.

6 Below water m3 M26


When rock is
deposited into soft
areas, the volume shall
be measured as in the
transport vehicle at the

MyCESMM2 |
place of deposition.

43
CLASS F: EARTHWORKS
44
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
3 Filling M27
Filling of excavation
around completed
structures shall
be measured nett

| MyCESMM2
(MyCESMM2)

between the volume of


excavation under rule
Malaysian Civil Engineering

M9 and the completed


structure measured
from the commencing
surface.

M28
Where filling is to be
deposited below water,
and the quantity
cannot be measured
Standard Method of Measurement ̵ Second Edition

satisfactorily by
any other means,
the volume shall be
measured as in the
transport vehicle at the
place of deposition.
Where filling is by
pumping, the volume
shall be measured by
settlement plates.
7 High energy impact 1 Selected excavated m3 M29
compaction general material other than High energy impact
filling topsoil or rock compaction general
2 Imported natural m3 fill existing ground
material other than shall be measured to
topsoil or rock the surface area to be
3 Existing ground m2 treated.
CLASS F: EARTHWORKS
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
4 Landscaping 1 Turfing m2 M30 D16 C14 A19
2 Hydroseeding m2 Measurement for spot The girth of trees Items for landscaping Item description for
3 Bio-degradable m2 turfing shall include the shall be measured shall be deemed landscaping shall state
erosion control areas of unturfed space from ground level to to include digging, the species of the
blanket between the sods. one-third height of planting media, turfing, hydroseeding,
4 Hedges m the trees or 1m from bedding, stalking, hedges and trees
5 Trees nr M31 ground level, whichever protection, watering, required.
The area of turfing and is lower. weeding, required
hydroseeding shall be fertilising, and A20
the area to the slope, if D17 replacement of Item description for
applicable. The height of trees dead items until turfing shall state the
shall be measured the vegetation is type of turfing (close
M32 from ground level to established. or spot).
Ungrown areas the lowest branch or
of turfing and crown, whichever is C15 A21
hydroseeding lower. Items for turfing on Item description for
exceeding 1 m² shall slopes steeper than hydroseeding shall
not be measured. 1 (vertical) and 3 state the technical
(horizontal) shall be specification.
M33 deemed to include
The lengths of hedges pegging down with A22
measured shall be their stakes. Item description for
developed lengths bio-degradable erosion
along the centre line. C16 control blanket shall
Items for bio- state the location and
M34 degradable erosion the spacing of the
The area of bio- control blanket shall fastening hook.
degradable erosion be deemed to include
control blanket shall fastening hooks and A23
be measured nett and netting required. Item description for
no allowance shall be trees shall state the
made for laps. minimum girth and
height.

A24
Item description for
landscaping and
hydroseeding shall
identify work upon
surface which is
inclined at an angle
exceeding 10° to the
horizontal.

MyCESMM2 |
45
CLASS F: EARTHWORKS
Malaysian Civil Engineering
Standard Method of Measurement ̵ Second Edition
(MyCESMM2)

46 | MyCESMM2
CLASS G
GEOTECHNICAL
WORK

MyCESMM2 | 47
48
ADDITIONAL
CLASS G: GEOTECHNICAL WORK MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES

Measurement covered under other classes: D1 C1 A1


Earth shall be deemed Items for pull out test Item description shall
Excavation, filling, and turfing for retaining structures (included in to be materials other shall be deemed to state the location of
Class F: Earthworks). than topsoil, natural include all necessary the item if the work is
hard material, rock, equipment, and more than 6 m above

| MyCESMM2
(MyCESMM2)

Reinforced concrete foundation for retaining structures (included in artificial hard material submission of test or below the road level.
Class I: Concrete work). or unsuitable material, procedure, records and
Malaysian Civil Engineering

Sand replacement for ground treatment (included in Class F: Earthworks). unless otherwise stated reports.
in the item description.
Sub-soil drainage (included in Class Q: Drainage work).
Pile embankment measured under respective classes (included in D2
Class F: Earthworks, Class I: Concrete work, Class H: Piling work). Natural hard material
shall be materials
other than rock and
artificial hard material,
and requires other
specialised equipment.
Standard Method of Measurement ̵ Second Edition

D3
Rock and artificial
hard material shall be
materials that require
the use of either
hydraulic rock breaker
or pneumatic tools or
explosives.

FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT

1 Plant and 1 Provision sum C2


equipment 2 Moving and sum Items for provision shall
handling be deemed to include
3 Temporary staging sum provision of all necessary
plant and equipment,
transportation to the site,
handling, assembling,
and removal off the
site after completion of
operation.

C3
Items for moving
and handling shall be
deemed to include the
moving and handling of
all necessary plant and
equipment within the
site and from location
to location as often as it
is, whenever necessary
for the execution of the
CLASS G: GEOTECHNICAL WORK

whole operation.
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
2 Retaining structures 1 Gabion 1 Rock-filled gabion m3 D4 A2
2 Rock-filled gabion m2 Gabions filled with Item description for
mattress rocks exceeding 300 gabion shall state the
3 Filter layer m2 mm high shall be type and size of filling,
separator classed as rock-filled and the type, gauge, and
gabion, and those not protective coatings of
exceeding 300 mm the wire mesh. If laying
high as rock-filled underwater is required, it
gabion mattress. Filling shall be so stated.
shall be deemed to
be imported, unless A3
otherwise stated. Item description for rock-
filled gabion mattress
shall state the thickness.
2 Cribwall 1 Single cell m2 M1 C4 A4
2 Double cell m2 The area of single cell Items for cribwall shall Item description for
3 Triple cell m2 cribwall shall be the be deemed to include cribwall shall state the
4 Quadruple cell m2 sloping area from the precast reinforced concrete grade, length
5 Filter layer/ m2 commencing surface. concrete components of precast concrete
separator and granular infill header, combination
M2 materials. and type of granular
The area of multiple infill.
cells cribwall shall be
the sloping area of the
highest cells from the
commencing surface.
3 Reinforced soil 1 Reinforced earth m3 M3 D5 A5
slope filling Reinforced earth filling Reinforced earth Item description for
2 Reinforced granular m3 and reinforced granular filling and reinforced reinforced soil slope
filling filling shall be measured granular filling is shall state the location,
3 Erosion protection m2 nett volume within defined as filling within type and strength of
mats the reinforced zone. the reinforced zone. material used.

M4 D6
The area of erosion Reinforced earth A6
protection mat shall be filling and reinforced Item description for
the nett area to the granular filling shall be erosion protection mats
slope with no allowance in accordance with BS shall state the type of
for laps and anchorage. 8006-1:2010+ A1:2016. material and strength,
where applicable.
M5 D7 C5 A7
4 Reinforced soil wall 1 Wall facing m2
The area of reinforced Precast concrete panel Items for wall facing shall Item description for
2 Reinforced earth m3
soil wall is measured shall be classed as be deemed to include wall facing shall state
filling
from the commencing wall facing in retaining soil reinforcement and the type,
3 Reinforced granular m3
surface. stucture. galvanising where size, and shape, where
filling
4 Pull out test nr applicable, connections applicable; and the
M6 and/or jointing, geotextile concrete grade, type of

MyCESMM2 |
Sub-soil drainage shall be and accessories for wall soil reinforcement and
measured under Class Q. joints. wall height.

49
CLASS G: GEOTECHNICAL WORK
50
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
3 Slope stabilisation 1 Soil nailing 1 Stated length nr C6 A8
2 Pull out test nr Items for soil nailing Item description
shall be deemed to for soil nailing shall
include drilling of state the diameter
borehole, corrugated of the borehole and

| MyCESMM2
(MyCESMM2)

HDPE pipe if reinforcement bar,


applicable, sleeve concrete grade and the
Malaysian Civil Engineering

grouting, sealant size of concrete pad.


compound, galvanised
steel bearing plate and
all associated works.

2 Rock bolt 1 Stated length nr C7 A9


2 Pull out test nr Items for rock bolt shall Item description
be deemed to include for rock bolt shall
drilling of borehole, state the diameter
Standard Method of Measurement ̵ Second Edition

reinforcement bar, of the borehole and


reinforced concrete reinforcement bar,
pad, sleeve grouting, concrete grade and the
sealant compound and size of concrete pad.
all associated works.

3 Ground anchor 1 Earth m C8 A10


2 Natural hard m Items for ground Item description for
material anchor shall be ground anchor shall
3 Rock m deemed to include state the size and type
4 Pull out test nr prestressed tendons, of anchor tendons and
drilling, and grouting, grouting.
concreting and all
associated works.

4 Concrete buttress m2 C9 A11


Items for concrete Item description for
buttress shall be concrete buttress shall
deemed to include state the grade and
steel wire mesh, PVC average thickness of
drain pipe, dowel bars, the concrete.
filter materials and all
associated works.

5 Horizontal drain 1 Earth m M7 C10 A12


2 Natural hard m Concrete channel for Items for horizontal Item description for
material horizontal drain shall drain shall be deemed horizontal drain shall
3 Rock m be measured under to include drilling, state the type and
4 Artificial hard m Class R740. perforated pipe and all diameter.
material associated works.
5 Unsuitable materials m
CLASS G: GEOTECHNICAL WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
4 Surface protection 1 Guniting m2 M8 C11 A13
2 Articulating slab m2 The area of guniting Items for guniting shall Item description for
3 Rock netting m2 and articulating slab be deemed to include guniting shall state the
4 Stone pitching m2 shall be their nett area steel wire mesh, PVC average thickness of
5 Stone revetment m2 to the slope. drain pipe, dowel bar, the concrete and the
filter materials, and all concrete grade.
M9 necessary formwork.
The area of rock A14
netting shall be C12 Item description for
measured nett with no Items for articulating articulating slab shall
allowance made for slab shall be deemed state the thickness,
laps. to include preparation type and jointing of the
of surface, blinding, slab.
aggregate, geotextile
and all necessary A15
concrete and Item description for
formwork. rock netting shall state
the type and gauge
C13 of chain mesh and
Items for rock netting anchoring system.
shall be deemed to
include all necessary A16
accessories. Item description for
stone pitching and
stone revetment shall
state the stone size
and thickness.
5 Ground treatment 1 Prefabricated m M10 A17
vertical drains Any filling required Item description for
2 Dynamic nr under this class to prefabricated vertical
compaction be used as a working drains
3 Vibro compaction nr platform shall be shall state type
4 Sand column m measured under Class and cross-sectional
5 Stone/Aggregate m F3**. dimensions of drainage
column tube, wrapping
6 Soil-cement column m M11 material and vacuum
Surcharge material consolidation wherere
(for pre-loading) used quired.
with prefabricated Type of soil shall be
vertical drains shall be stated.
measured under Class
F3**. A18
Item description for
dynamic compaction
shall state the weight
of the drop hammer,
number of drops and
height of drop.

MyCESMM2 |
51
CLASS G: GEOTECHNICAL WORK
52
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
5 Ground treatment A19
Item description for
vibro compaction shall
state the depth of
treatment required.

| MyCESMM2
(MyCESMM2)

A20
Malaysian Civil Engineering

Item description for


sand column, stone/
aggregate column and
soil-cement column
shall state the diameter
of the columns and
the size of aggregate,
where applicable.

A21
Standard Method of Measurement ̵ Second Edition

Item description for


soil-cement column
shall state the grout mix
design.
7 Geotextile m2 M12 A22
8 Geogrid m2 The area of geogrid Item description for
and geotextile shall be geotextile and geogrid
measured nett with no shall state the type,
allowance for laps. grade and the technical
specification of the
materials or reference
number of the product.
6 Grouting work 1 Drilling for grout 1 Earth m M13 C14 A23
holes 2 Natural hard m Drilling through Items for sleeve pipe Item description for
material previously grouted shall be deemed to drilling for grout holes
3 Rock m holes in the course of include grouting of shall state the method,
4 Artificial hard m stage grouting shall annulus space between diameter and maximum
material not be measured. the sleeve pipe and the depth.
5 Unsuitable material m Where grout holes are drilled holes
expressly required to
2 Sleeve pipes m be extended, drilling A24
through previously Item description for
grouted holes shall be sleeve pipe shall state
measured as drilling the diameter and type
through rock. of material.
3 Injection 1 Cement t M14
2 Sand t The mass of grout
3 Bentonite t injection measured
4 Aluminium powder kg shall not include the
5 Chemical t mass of mixing water.
6 Pulverised fuel ash t
7 Pea gravel t
CLASS G: GEOTECHNICAL WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
6 Grouting work 4 Connection for nr C15 A25
grouting Connection for Item description
5 Water pressure test nr grouting shall be for connection for
deemed to include grouting shall identify
provision of packer as those which are in
expressly required. stages, distinguishing
between those which
are in ascending and
descending stages.
7 Diaphragm walls 1 Excavation 1 Earth m3 M15 D8 C16 A26
2 Natural hard m3 The depths of concrete Diaphragm walls are Items for excavation Item description for
material in diaphragm walls walls constructed with for diaphragm walls excavation shall state
3 Rock m3 shall be measured from the use of bentonite shall be deemed to the maximum depth
4 Artificial hard m3 the cut-off level to the slurry or other include preparation and thickness of wall.
material toe level. temporary support and upholding sides of
5 Unsuitable m3 fluids. excavation.
materials M16
The mass of steel C17
2 Concrete m3 reinforcement shall D9 Items for A27
be taken as 0.785 The nominal diameter reinforcement shall The mix specification
kg/m per 100 mm² of stated in the item be deemed to include or strengths shall
cross-section (7.85 t/ description for bar labour for cutting, be stated in item
3 Reinforcement 1 Mild steel bar t m³). The mass of other reinforcement shall bending and placing. description for concrete
2 High tensile steel t reinforcing materials be the cross-sectional in diaphragm walls.
bar shall be taken as stated diameter defined in MS
3 High tensile steel m2 in the contract. 146. A28
fabric Item description for
4 Fabric of other m2 steel bars shall state the
stated material size of the bars.
4 Waterproofed joints sum M17
5 Guide walls m The mass measured
6 Preparing top of m for reinforcement
walls to receive shall include the mass
cappings of reinforcement
7 Preparing cast in m expressly required in
pockets or chases laps and special chairs.

M18
The mass measured
for reinforcement, in
tonne, shall be up to
two decimal place.

M19
Guide walls shall be
measured on both
sides of the diaphragm
walls.

MyCESMM2 |
53
CLASS G: GEOTECHNICAL WORK
54
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
8 Instrumentation 1 Piezometer nr C18 A29
2 Inclinometer nr Items for piezometer Item description
3 Surface marker nr and inclinometer for piezometer and
4 Settlement plate nr shall be deemed to inclinometer shall state
5 Displacement nr include pre-boring and the type, depth and

| MyCESMM2
(MyCESMM2)

marker installation. material used.


6 Magnetic nr
Malaysian Civil Engineering

extensometer A30
7 Deep levelling nr Item description for
datum settlement plate shall
state the dimensions
of plate, depth and
material used.
Standard Method of Measurement ̵ Second Edition

8 Monitoring nr M20 C19 A31


Measurement of Items for monitoring Item description
monitoring in number shall be deemed to for monitoring shall
shall be based on the include preparation of state the personnel
trips to the location of monitoring report. and number of trips
the instrumentation. required.
CLASS G: GEOTECHNICAL WORK
CLASS H
PILING WORK

MyCESMM2 | 55
56
ADDITIONAL
CLASS H: PILING WORK MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
M1 C1 A1
Measurement covered under other classes:
Bored and driven depths Items for piling work shall Item description for piles
shall be measured along be deemed to include shall identify preliminary
Boring for site investigation work (included in Class D: Site investigation work). the axes of piles from the disposal of excavated and piles. Item description
commencing surface: surplus materials. shall identify raked piles
Setting out of piles and as-built drawings (included in Class A: General items). and their inclination

| MyCESMM2
(MyCESMM2)

a) to the toe levels of C2 stated.


Ground anchor and stone column (included in Class G: Geotechnical work).
bored piles; and Items for piling work shall
be deemed to include A2
Malaysian Civil Engineering

Walling and tie rod (included in Class L: Metalwork).


b) to the bottom of piling records and number Item description for piles
Diaphragm wall (included in Class G : Geotechnical work). casing of driven cast stated. shall state the materials
in situ piles composition.
C3
M2 Items for pre-boring shall A3
The commencing be deemed to include Items description for piles
surface is the surface at backfilling between the shall state the structure to
which boring or driving pile and the bore. be supported and identify
is expected to begin, the commencing surface.
and shall be for the C4
Standard Method of Measurement ̵ Second Edition

measurement of the Items for pre-boring shall A4


completed work. be deemed to include Item description for
grouting void with stated piles shall identify initial
M3 materials between the piles and extension piles.
Each group item for piles piles and the bores. Details of driving head and
to be driven shall comprise shoes shall be so stated in
C5 item description.
a) an item for the total Items for depth driven
supply number of pile shall be deemed to A5
points of state length include handling, hoisting, Item description for depth
and pitching, and driving of driven shall state jack-in
piles. method when required.
b) an item for the total
depth driven C6 A6
Items for preparing head Item description for
M4 shall be deemed to include reinforcement shall state
Depth driven shall be pile plug, starter bar, steel details of couplers when
measured from the cut-off plates and welding works. expressly required.
levels to the toe levels.
A7
M5 Item description
The concreted lengths reinforcement shall state
of cast in place concrete materials and grade
piles shall be measured including identifying
from the cut-off level to straight or helical and
the toe levels expressly nominal diameter to be
required. stated as not exceeding
20 mm and exceeding
20 mm.
CLASS H: PILING WORK
ADDITIONAL
CLASS H: PILING WORK MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
A8
Item description
for supply of pile
shall state the cross-
sectional type and
cross-sectional
dimensions or
diameter, lengths,
concrete grade, class
of piles, detail of
treatment and coatings
required and working
load, where jack-in
method expressly
required.

A9
Item description for
jointings shall state
type, method and
detail of jointing
required.
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT

1 Plant and 1 Provision sum C7


equipment 2 Moving and sum Items for provision
handling shall be deemed to
3 Temporary staging sum include provision of
all necessary piling
plant and equipment,
transportation to
the site, handling,
assembling and
removal off the site
after completion of
operation.

C8
Items for moving
and handling shall be
deemed to include
moving and handling
all piling plant and
equipment within the
site, and from location
to location as often
as is, and whenever
necessary for the

MyCESMM2 |
execution of the whole
piling operation.

57
CLASS H: PILING WORK
58
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
2 Piles 1 Bored piles 1 Depth bored or m M6 D1 C9 A10
2 Driven cast in situ driven Each group of items for Piles consisting of Items for bored piles Item description for
concrete piles 2 Boring through rock m bored piles, barrette driven permanent steel and barrette piles shall bored, cast in place,
3 Barrette piles 3 Permanent casings m pile, driven cast in casing, which is filled be deemed to include barrette piles and
4 Reinforcement t situ concrete piles, with concrete, shall be temporary casings, caisson piles shall state

| MyCESMM2
(MyCESMM2)

straight bars and caisson piles shall classified as driven cast stabilising agent, and the diameter.
5 Reinforcement t comprise: in situ piles where the enlarged bases.
Malaysian Civil Engineering

helical bars piles are designed for A11


6 Concreted length m a) An item for the total the load to be carried C10 Item description for
7 Cut-off piles nr depth bored or total on the concrete. Items for boring and bored piles shall state
8 Preparing head nr depth driven or total excavation through contiguous bored piles
depth excavated, D2 rock shall be deemed where applicable.
stating total number The nominal diameter to include natural and
of pile points, and used for classification artificial hard materials A12
of bar reinforcement including backfilling Item description for
b) An item for the total shall be the cross- bore with stated permanent casings
concreted length of sectional diameter materials. shall state materials,
Standard Method of Measurement ̵ Second Edition

piles defined in BS 4449 or thickness, and details


MS 146. C11 of treatments and
M7 Items for permanent coating.
The lengths of casing shall be
permanent casings for deemed to include the A13
bored piles shall be supply and jointing of Item description for
measured from the cut- casings, driving heads, concreted length shall
off level to the bottom and shoes, where state when required
of the casings. The applicable. particular method of
length of permanent concrete placement,
casing for driven cast C12 concrete grade,
in situ concrete piles Items for poured at a stated
shall be measured from reinforcement speed, temperature,
the cut-off levels to the shall be deemed to compacted or cured in
toe levels. include supporting a particular method.
reinforcement.

C13
Items for driven cast in
situ concrete piles shall
be deemed to include
pre-boring, where
applicable.
CLASS H: PILING WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
2 Piles 4 Caisson piles 1 Depth excavated m M8 D3
2 Excavation through m The length of permanent Piles comprising
rock casings for caisson piles placement of
3 Permanent casings m shall be measured from permanent concrete
4 Reinforcement bars t the top of casing to the or steel casing, where
5 Concreted length m bottom of the casings. the material within the
casing is excavated and
M9 filled with concrete,
The mass of steel shall be classified as
reinforcement shall be caisson piles when the
taken as 0.785 kg/m piles are designed for
per 100 mm² of cross- the load to be carried
section (7.85 t/m³). on the concrete.
The mass of other
reinforcing materials
shall be taken as stated
in the contract.

5 Micropiles 1 Depth bored m M10 C14 A14


2 Boring through rock m The mass measured Items for boring Item description for
3 Steel pipe as m for reinforcement shall through rock shall be micropiles shall state
reinforcement include the mass of deemed to include the diameter.
4 Reinforcement bars t reinforcement expressly artificial hard materials.
5 Grouting m3 required in laps. A15
6 Cut-off piles nr C15 Item description for
7 Preparing head nr M11 Items for steel pipe grouting shall state the
8 Permanent casing m The length of steel pipe as reinforcement shall grout design mix and/
casing shall be measured be deemed to include or strength.
from top of pipe to toe. jointing/welding.
6 Precast reinforced 1 Supply of piles nr M12 D4 C16 A16
concrete piles 2 Depth driven m Each group of items for The supply lengths of Items for filling hollow Item description for
7 Precast prestressed 3 Pre-boring m precast reinforced and precast reinforced piles with concrete filling hollow piles
concrete piles 4 Jointing m precast prestressed concrete piles and shall be deemed to with concrete shall
5 Filling hollow piles m concrete piles shall precast prestressed include removal of state the specification
with concrete comprise: concrete piles shall be materials from within of the concrete and
6 Cut-off piles nr the total number of the piles before reinforcement.
7 Preparing head nr a) one or more items piles of stated lengths concreting.
for the number of expressly required to
piles of stated be supplied.
length; and
8 Steel H-piles 1 Supply nr D5 A17
2 Depth driven m b) an item for the total The supply lengths Item description for
3 Pre-boring m depth driven. of steel H-piles and supply of steel H-piles
4 Filling hollow piles m steel pipe piles shall and steel pipe piles
with concrete be the total number of shall state the mass per
5 Cut-off piles nr piles of stated lengths meter, cross-sectional
6 Jointing nr expressly required to dimensions and grade
7 Preparing head nr be supplied. of steel, length and

MyCESMM2 |
3 Piles 1 Steel pipe piles concrete infill, where
applicable.

59
CLASS H: PILING WORK
60
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
3 Piles A18
Item description for
steel H-piles and steel
pipe piles shall state
details of treatments,

| MyCESMM2
(MyCESMM2)

coatings and cathodic


protection where
Malaysian Civil Engineering

required.

A19
Item description for
steel H-piles and steel
pipe piles shall state
type of jointing.
2 Timber piles 1 Supply nr M13 D6 C17 A20
3 Precast concrete 2 Depth driven m The areas of driven The lengths of timber Items for jetting Item description for
Standard Method of Measurement ̵ Second Edition

sheet piles 3 Pre-boring m precast prestressed piles and precast deemed to include jet supply of timber piles
4 Precast prestressed 4 Jointing nr concrete sheet piles concrete sheet piles pipes, hoses and jet shall state the grade of
concrete sheet piles 5 Cut-off piles nr shall be calculated shall be the total pump. timber, cross-sectional
6 Preparing head nr by multiplying the number of piles, dimensions, length and
7 Jetting m horizontal lengths of of stated lengths, any pressure treatment
the pile walls formed expressly required to required.
by the average depths be supplied.
measured from the A21
cut-off levels. Item description for
supply of precast and
prestressed concrete
sheet piles shall state
thickness, length and
width.

5 Interlocking steel 1 Supply m M14 D7 A22


sheet piles 2 Depth driven m2 The areas of driven Interlocking steel Item description for
3 Pre-boring m interlocking steel piles corner, junction, interlocking steel
4 Jetting m shall be calculated by closure, and taper piles sheet pile shall state
5 Special piles m multiplying the mean shall be classified as the section reference
6 Cut-off piles m undeveloped horizontal special piles. or mass per metre and
7 Ground anchorages nr lengths of the pile walls section modulus.
8 Preparing head m formed (including lengths D8
occupied by special The supply lengths of A23
piles) by the depths interlocking steel piles Item description for
measured from cut-off shall be the total length supply area of piles
levels to the toe-levels. expressly required to shall state details of
be supplied. treatment and coatings
M15 required.
Closure and taper piles
classed as special piles A24
shall be measured Item description for
only where they are special piles shall state
expressly required. the type and length.
CLASS H: PILING WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
3 Piles M16 A25
The lengths measured Item description for
for cutting of surplus ground anchorages
lengths of interlocking shall state the
steel sheet piles composition and
shall be the mean working load.
undeveloped horizontal
lengths to be cut
(including lengths
occupied by special
piles).

4 Miscellaneous work 1 Obstructions 1 Excavation through m M17 A26


obstructions Excavation through Item description for
obstructions shall excavation through
be measured only obstruction shall state
for breaking out the cross-sectional
obstructions or dimension or diameters
artificial hard materials of the excavation.
encountered above the
founding stratum.

5 Pile tests 1 Static load/ nr C18 A27


maintained load Items for pile test Item description for
2 Pile dynamic nr deemed to include static load test shall
analyser necessary equipments, state the test loads.
3 Pile integrity nr inserts and accessories. Where the load is
4 Sonic logging nr applied to raked piles,
5 Lateral nr it shall be so stated.
6 Statnamic nr
7 Bi-directional nr A28
static load Item description for
8 Global strain nr pile test shall identify
extensometers those which are for
static load preliminary piles.

6 Pile tests 1 Plate loading nr A29


2 Shaft friction nr Item description for
plate loading test
and shaft test shall
state type of pile and
identify location of pile
test.

MyCESMM2 |
61
CLASS H: PILING WORK
Malaysian Civil Engineering
Standard Method of Measurement ̵ Second Edition
(MyCESMM2)

62 | MyCESMM2
CLASS I
CONCRETE WORK

MyCESMM2 | 63
64
ADDITIONAL
CLASS 1: CONCRETE WORK MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES

Measurement covered under other classes: M1 C1 A1


The volume of Items for in situ Item description for
In situ concrete for: concrete measured concrete shall concrete shall state
shall include that be deemed to mass, reinforced
Concrete diaphragm walls (included in Class G: Geotechnical work). occupied by: include placing prestressed concrete

| MyCESMM2
(MyCESMM2)

Piling work (included in Class H: Piling work). and compaction of and maximum size of
a) reinforcement and concrete. aggregate.
Manholes for sewerage pipework (included in Class O: Pipework).
Malaysian Civil Engineering

other metal sections;


Roads, pavings, and kerbs (included in Class R: Roads and pavings). A2
Concrete sleeper (include in Class T: Rail track). b) prestressing Item description for
components; components classed
Foundations for fences and gates (included in Class V: Miscellaneous work). as other concrete
Concrete fencing (included in Class V: Miscellaneous work). c) cast-in components forms shall state the
each not exceeding components and
Formwork and reinforcement for sleeper (included in Class T: Rail track). 0.1 m³ in volume; include one of the
Formwork and reinforcement for fences and gates foundation (included in following:
Class V: Miscellaneous work). d) rebates, grooves,
Standard Method of Measurement ̵ Second Edition

throats, fillets, a) the principal


Formwork and reinforcement in manholes for sewerage pipework (included in
chamfers or internal dimensions of the
Class O: Pipework).
splays each not concrete component;
Precast concrete piling work (included in Class H: Piling work). exceeding 0.01 m²
Precast concrete manholes for sewerage pipework (included in cross-sectional area b) a type or mark
Class O: Pipework). number of a concrete
e) voids not exceeding component for which
Precast concrete pipeworks (included in Class O: Pipework). 0.05 m³; principal dimensions
Precast concrete paving, kerbs, and traffic sign supports (included in are given on the
Class R: Roads and pavings). f) joints or joint drawings; or
components
Precast concrete fencing (included in Class V: Miscellaneous work).
between adjacent c) a statement locating a
Concrete drain and sumps (included in Class Q: Drainage work). volume of in situ concrete component
Precast concrete panel for reinforced soil wall (included in Class G: concrete, and nibs for which principal
Geotechnical work). or external splays dimensions are given
on the drawings.
g) not exceeding
0.01 m2 cross- A3
sectional area. Item description for
cement component
other than ordinary
portland cement shall
be so described.

A4
Item description for
concrete required
to be placed by a
particular method,
poured at a stated
speed, temperature,
and compacted or
cured in a particular
CLASS I: CONCRETE WORK

way shall be described.


ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
1 In situ concrete 1 Grade: C15 1 Blinding m2 M2 D1 C2 A5
designed mix 2 Grade: C20 2 Bases, footings, pile m3 Columns and piers A concrete mix shall be Items for sprayed Item description for
3 Grade: C25 caps, and ground more than 1 m wide classified as a designed concrete shall be In situ concrete shall
4 Grade: C30 slabs or long and integral mix where the deemed to include state the concrete
5 Grade: C35 3 Suspended slabs m3 with a wall shall be performance is stated reinforcing materials admixtures when
6 Grade: C35A 4 Columns and piers m3 measured as part of in the contract and the added to the mix. required.
7 Grade: C40 5 Beams and walls m3 the wall except where mix proportions are
8 Grade: C50 6 Sprayed concrete m2 expressly required to to be proposed by the A6
7 Encasing to metal m3 be cast separately. contractor, subject to Item description for
sections conditions imposed blinding shall state the
8 Other concrete m3 M3 by specifications such thickness.
forms Beams more than 1 as minimum cement
m wide or long and content, water cement A7
integral with a slab ratio, etc. Item description for
shall be measured concrete which is
as part of the slab D2 expressly required
except where expressly A concrete mix shall be to be placed against
required to be cast classified as prescribed an excavated surface
separately. mix where the exact (other than building)
mix proportions of shall be stated.
cement, sand, and
aggregates are stated A8
in the contract. Item description for
sprayed concrete
D3 support shall state the
2 Proprietary
Concrete in suspended specification of the
concrete
slabs and walls less concrete and whether
than 1 m wide or long it is reinforced and the
shall be classed as minimum thickness.
concrete in beams and
columns, respectively.

3 In situ concrete 1 1:3:6 D4


prescribed mix 2 1:2:4 Concrete shall be
3 1:1½:3 classed as proprietary
4 1:1:2 concrete where the
application is to
achieve a particular
performance outside
normal performance
criteria.

MyCESMM2 |
65
CLASS I: CONCRETE WORK
66
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
4 Precast concrete 1 Columns nr M4 D5 C3 A9
2 Beams nr Parapet shall be Concrete components Items for precast Item description for
3 Prestressed beams nr measured as wall. which are cast other concrete shall be each type of precast
4 Walls nr than in their final deemed to include concrete unit shall state
5 Slabs nr M5 position shall generally reinforcement, the position of the work

| MyCESMM2
(MyCESMM2)

6 Segmental units nr Plank shall be be classed as precast formwork, joint and and specification of the
7 Units for subways, nr measured as slab. concrete units. finishes. concrete to be used.
Malaysian Civil Engineering

vehicular or
pedestrian culverts D6 C4 A10
and viaducts Where site precasting Items for prestressed Item description for
8 Other concrete nr of units is adopted precast units shall be each precast concrete
forms (excluding those deemed to include unit shall state the
with multiple use of prestressing. concrete mix type or
formwork), and the mark number. Units with
nature of the work is different dimensions shall
the characteristic of be given defferent types
in situ concrete but or mark numbers.
Standard Method of Measurement ̵ Second Edition

involves the movement


of the cast units into A11
their final positions, the Item description for
unit shall be classed as prestressed beams shall
in situ concrete. identify pre-tensioned
or post –tensioned
beam including stating
particulars of tendon
used.

A12
Item description for
columns, beams,
segmental units, units for
subways, and vehicular
or pedestrian culverts
and ducts, copings,
viaducts and other
concrete forms, shall
state the cross-section,
type and total length.

A13
Item description for walls
and slabs shall state the
type, area and average
thickness.

A14
Item description for units
for subways, vehicular or
pedestrian culverts and
viaducts shall state the
CLASS I: CONCRETE WORK

mass per metre.


ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
5 Formwork 1 Sides 1 Bases, footings, m2 M6 D7 C5 A15
2 Soffit pile caps, and Formwork shall be Formwork shall be Items for formwork Item description for
3 Sides and soffit ground slabs measured for surfaces classified according to shall be deemed to formwork shall state
4 Sloping 2 Columns and piers m2 of in situ concrete which its angle of inclination include any temporary when formwork left-in
5 Curved to one 3 Beams m2 require temporary as follows: staging required. is required.
radius in one plane 4 Walls m2 support during casting,
6 Other curve 5 Suspended slabs m2 except where otherwise Class Angle of C6 A16
7 For concrete 6 Other members m2 stated. inclination Items for formwork Item description for
components of from the shall be deemed to formwork adopting the
constant cross- M7 horizontal include the projections use of table form system,
sections Formwork shall not and intrusions. slipform system and
be measured for the Soffit 0° - 15° the like shall be stated.
following: Sloping 15° - 80°
Sides 80° - 90° A17
a) edges of blinding Item description for
concrete not D8 formwork shall state
exceeding 0.2 m Formwork for type F1, the required concrete
wide or deep; F2, and F3 finish shall finish as follows:
be as defined in the a) F1: rough finish;
b) joints, associated standard specification b) F2: fair finish;
rebates, and grooves; for road works as c) F3: smooth finish;
specified. d) other stated finish;
c) temporary surfaces e) other surface features.
formed at the
discretion of the A18
contractor; and Item description for
formwork to upper
d) surfaces of concrete surfaces shall be so
which are expressly stated, except where the
required to be cast surfaces are inclined at
against an excavated an angle not exceeding
surface. 15° from the horizontal.

M8 A19
Formwork to upper Item description for
surfaces of concrete formwork to curved
shall be measured to concrete components of
surfaces inclined at constant cross-sections
angle exceeding 15° shall state the radii.
from the horizontal,
and to other upper A20
sufaces for which Item description for
formwork is expressly formwork to concrete
required. constant cross
section shall state the
M9 principal cross-section
The area of formwork dimensions of the
measured shall include components, location

MyCESMM2 |
the area of formwork or other unique
obscured by voids and identifying feature.

67
CLASS I: CONCRETE WORK

inserts.
68
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
5 Formwork 8 For voids 1 Depth not nr M10 D9 A21
exceeding 1 m Formwork for the The size of voids for Item description
2 Depth exceeding m2 surfaces of voids larger I58* shall be as follows: for voids shall state
1m than the upper bound the cross-section or
values as defined Class Cross diameter and the

| MyCESMM2
(MyCESMM2)

in rule D9 shall be section depth of voids.


measured as set out in Circular 0.35 m -
Malaysian Civil Engineering

this class. (diameter) 0.7 m

M11
No deduction shall be Other voids 0.1 m² -
made for formwork to (area) 0.5 m²
voids smaller than the
lower bound values as D10
defined in rule D9. The depth of voids
shall be measured
perpendicularly to the
Standard Method of Measurement ̵ Second Edition

adjacent surface of
concrete.

D11
The maximum
diameter or cross-
section shall be taken
when the voids have
two unequal diameters
or cross-sections.
6 Reinforcement 1 Mild steel bars 1 Nominal diameter: t M12 D12 C7 A22
2 High tensile bars 6 mm The mass of steel The nominal diameter Items for Item description for
3 Reinforcing bars of 2 Nominal diameter: t reinforcement shall stated in item reinforcement shall special joint shall state
other stated 8 mm be taken as 0.785 description for bar be deemed to include the type of joint and
materials 3 Nominal diameter: t kg/m per 100 mm² of reinforcement shall labour for cutting, size of reinforcing bars.
4 Stainless steel bars 10 mm cross-section (7.85 t/ be the cross-sectional bending, and placing.
of stated quality 4 Nominal diameter: t m³). The mass of other diameter defined in MS A23
12 mm reinforcing materials 146. C8 Item description
5 Nominal diameter: t shall be taken as stated Items for for steel fabric
16 mm in the contract. D13 reinforcement reinforcement to MS
6 Nominal diameter: t Sleeve joints, steel shall be deemed to 145 shall state the type,
20 mm M13 welded, swaged or include supporting fabric ref number or
7 Nominal diameter: t The area of additional screwed and the like in reinforcement other letter in accordance
25 mm fabric in laps shall not reinforcing bars shall than steel supports to with MS 145.
8 Nominal diameter: t be measured. be classed as special top reinforcement.
stated exceeding joints.
32 mm
CLASS I: CONCRETE WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
6 Reinforcement 5 Special joints nr M14 A24
The mass measured Item description
6 Steel fabric 1 Nominal mass: m2 for steel support to for other fabric
7 Fabric of other not exceeding top reinforcement reinforcement shall
stated material 2 kg/m2 shall include the mass state the materials,
2 Nominal mass: m2 of reinforcement fabric reference sizes
2 - 3 kg/m2 expressly required in and nominal mass per
3 Nominal mass: m2 laps and special chairs. square meter.
3 - 4 kg/m2
4 Nominal mass: m2 M15
4 - 5 kg/m2 The mass measured
5 Nominal mass: m2 for reinforcement is in
5 - 6 kg/m2 tonne and shall be up
6 Nominal mass: m2 to two decimal places.
6 - 7 kg/m2
7 Nominal mass: m2
7 - 8 kg/m2
8 Nominal mass: m2
stated exceeding
8 kg/m2
7 Concrete ancillaries 1 Joints 1 Construction joints m M16 C9 A25
2 Contraction joints m Joints shall be Items for joints shall Item description
3 Expansion joints m measured at locations be deemed to include for joints shall state
4 Waterstops m where they are formwork. the dimensions,
5 Sealed rebates m expressly required. materials and nature of
or grooves C10 components.
6 Dowels - plain or nr M17 Items for waterstops
greased The length of shall be deemed to A26
7 Dowels - sleeved nr waterstops shall be include cutting and Item description for
or capped measured along their jointing of waterstops waterstops shall state
centre lines. and provision of special the material and the
fittings at angles and actual width.
junctions.

2 Post-tensioned 1 Horizontal internal nr M18 D14 C11 A27


prestressing tendons in in situ Prestressing shall Profiled tendons in Items for prestressing Item description for
concrete be measured by the horizontal components shall be deemed to prestressing shall
2 Inclined or vertical nr number of tendons shall be classed as include ducts, jacking, identify the concrete
internal tendons in where tendons are horizontal tendons. grouting and other components to be
in situ concrete used and by the components, and stressed, and stating
3 Horizontal internal nr number of external D15 tasks ancillary to the composition,
tendons in precast jacking operations The length of tendons prestressing. strength and length
concrete where stress is induced used shall be their of the tendon and
4 Inclined or vertical nr by jacking them. developed length particulars of the
internal tendons in between the outer anchorage.
precast concrete faces of anchorage.

MyCESMM2 |
69
CLASS I: CONCRETE WORK
70
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
7 Concrete ancillaries 3 Finishing of 1 Class U1 finish m2 M19 D16 C12 A28
top surfaces 2 Class U2 finish m2 The areas of tops Class U1, U2, U3 and Items for other stated Item description for
3 Class U3 finish m2 of walls and other U4 finishes shall be as surface treatment shall concrete ancillaries
4 Class U4 finish m2 surfaces which are not defined in the standard be deemed to include shall state the
given separate finishing specification for road materials, surface materials, thickness

| MyCESMM2
(MyCESMM2)

treatment shall not be works as expressly treatment, joints and and surface treatment,
measured as finishings stated. formwork. and other stated
Malaysian Civil Engineering

of top surfaces. applied finish.


4 Finishing of formed 1 Aggregate exposure m2 M20 C13
surfaces using retarder Finishing of top Items for finishing of
2 Bush hammering m2 surface shall be top surfaces shall be
3 Other stated surface m2 measured for areas deemed to include
treatment carried or surfaces where wood float or steel
out after striking expressly required. trowel.
formwork
M21
Standard Method of Measurement ̵ Second Edition

No deduction from the


areas measured for
finishing shall be made
for holes and openings
in the finished surfaces
each not exceeding
0.5 m².
5 Inserts 1 Linear inserts m M22 D17 A29
2 Other inserts nr Where inserts are Components cast Item description for
expressly required or grouted into in inserts shall identify
to be grouted into situ concrete, except the components to be
preformed openings reinforcement, cast or grouted-in and
the formwork shall be prestressing, and stating their principal
measured separately. jointing materials shall dimensions.
be classed as inserts.
A30
Item description for
inserts shall identify:

a) those which project


from one surface of
the concrete

b) those which project


from two surfaces of
the concrete; and

c) those which are


totally within the
concrete volume.
CLASS I: CONCRETE WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
7 Concrete ancillaries A31
Item description for
inserts which are
expressly required
to be grouted into
preformed openings
in concrete items
descriptions shall
so stated including
materials for grouting
and sizes of openings.

6 Grouting under nr A32


plates Item description for
grouting under plates
shall state materials
and area for grouting.

8 Ancillary work for 1 Water proofing m3 M23 C14 A33


water retaining admixtures Items for water Items for water Item description
structure 2 Water tightness m3 tightness testing and tightness testing of for water proofing
testing of tanks sterilising of tanks shall tanks shall be deemed admixtures shall state
3 Sterilising and m3 be measured up to the to include provision of the type and the mix
flushing of tanks capacity of the tanks water and all testing proportion.
as expressly stated. equipment as expressly
required.

C15
Items for sterilising and
flushing of tanks shall
be deemed to include
provision of potable
water and chemicals as
expressly required.

4 Linings and 1 High alumina m2 M24 C16


coatings cement Area of PVC and Items for linings and
2 PVC m2 HDPE linings shall be coatings shall be
3 HDPE m2 measured nett not deemed to include
4 Sodium silicate m2 inclusive of laps. supply and installation/
5 Epoxy coatings m2 application.

MyCESMM2 |
71
CLASS I: CONCRETE WORK
Malaysian Civil Engineering
Standard Method of Measurement ̵ Second Edition
(MyCESMM2)

72 | MyCESMM2
CLASS J
BRICKWORK,
BLOCKWORK
AND MASONRY

MyCESMM2 | 73
74
ADDITIONAL
CLASS J: BRICKWORK, BLOCKWORK AND MASONRY MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES

Measurement covered under other classes: M1 A1


Each skin of brickwork, Item description for
Prefabricated panels (included in Class M: Building work). blockwork, or masonry, brickwork, blockwork,
either in cavity or and masonry shall state
Sump brickwork (included in Class Q: Drainage work). composite wall the type and thickness

| MyCESMM2
(MyCESMM2)

construction shall be of material used.


measured.
Malaysian Civil Engineering

M2
Volumes and areas
measured for
brickwork, blockwork,
and masonry shall
include the areas of
joint, and exclude
those of copings and
sills. No deduction
Standard Method of Measurement ̵ Second Edition

from, or addition to,


areas measured shall
be made for intruding
or projecting surface
features. No deduction
from the areas
measured shall be made
for holes and openings
in walls where surface of
the hole/opening each
not exceeding 0.25 m²
in cross-sectional area.
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT

1 Brickwork 1 Vertical straight m2 M3 D1 C1 A2


2 Blockwork walls Mean dimensions shall In determining the Items for brickwork Item description
3 Masonry 2 Vertical curved walls m2 be used to calculate thickness of walls, and blockwork walls for walls, facing to
3 Battered straight m2 the areas of wall, facing, and casing, the shall be deemed concrete, casing to
walls facing to concrete, presence of surface to include joint metal sections, and
4 Battered curved m2 and casing to metal features shall be reinforcement, columns and piers
walls sections and the ignored. movement joints, fixing shall either state the
5 Vertical facing to m2 heights of columns and ties, bonds to existing materials, nominal
concrete piers. D2 work, and fixing dimensions and
6 Battered facing to m2 Walls or facing battered clamps. types of brick, block
concrete on one or both sides and stone or give
7 Casing to metal m2 shall be classed as C2 equivalent references
sections battered walls or Items for masonry shall to the applicable MS
8 Column and piers m3 battered facing. be deemed to include or BS.
fair facing finish.
D3
The thickness of
battered walls shall be
their mean thickness.
CLASS J: BRICKWORK, BLOCKWORK AND MASONRY
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
1 Brickwork A3
2 Blockwork Item description for
3 Masonry masonry walls, facing
to concrete, casing to
metal sections, and
columns and piers shall
state the surface finish.

A4
Item description
for walls, facing to
concrete, casing
to metal sections,
columns and piers
shall state the bonding
pattern, type of mortar,
type of jointing and
pointing.

A5
Item description
for walls, facing to
concrete, casing
to metal sections,
and columns and
piers, either in cavity
or composite wall
construction, shall be
so stated.
4 Miscellaneous work 1 Surface features 1 Copings and sills m M4 D5 A6
2 Rebates and chases m The length of surface Columns and piers Item description for
3 Cornices m features measured attached to walls or surface features shall
4 Band courses m shall be the mean facing of the same include sufficient
5 Corbels m lengths. The areas material shall be details to identify
6 Pilasters m measured for fair classed as pilasters. the materials, special
7 Plinths m facing finishes shall masonry, special or cut
8 Fair facing m2 be those expressly bricks and blocks. The
required, and shall be spacing of intermittent
measured at the face. surface features shall
be stated in the item
description.

A7
Item description
for surface features
shall state the cross-
sectional dimensions.

MyCESMM2 |
75
CLASS J: BRICKWORK, BLOCKWORK AND MASONRY
76
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
4 Miscellaneous work 2 Ancillaries 1 Damp proof m M5 C3 A8
courses The length of Items for built-in pipes Item description for
2 Infills of stated m2 additional material in and ducts shall be damp proof courses
thickness laps of damp proof deemed to include and infills shall state
3 Built-in pipes and nr course and joint their supply, unless the materials and

| MyCESMM2
(MyCESMM2)

ducts reinforcement shall not otherwise stated. dimensions.


4 Bonds to existing m2 be measured.
Malaysian Civil Engineering

works C4 A9
5 Movement joints m Items for bonds to Item description for
6 Joint reinforcements m existing works shall built-in pipes and
be deemed to include ducts shall stated the
fixing and ties. length where they
exceed 1.0 m.

A10
Item description for
built-in pipes and
Standard Method of Measurement ̵ Second Edition

ducts shall state the


cross-sectional area
where they exceed
0.05 m2.
CLASS J: BRICKWORK, BLOCKWORK AND MASONRY
CLASS K
TIMBER WORK

MyCESMM2 | 77
78
ADDITIONAL
CLASS K: TIMBER WORK MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES

Measurement covered under other classes: D1 C1 A1


Grades A, B, C, and D Items for timber shall Item description for
Formwork to concrete (included in Class I: Concrete work). shall be in accordance be deemed to include timber shall state the
with the Malaysian fixing components, grade and treatment
Timber piles (included in Class H: Piling work). grading rules by fixing, fastening, requirements or special

| MyCESMM2
(MyCESMM2)

Timber sleepers (included in Class T: Rail track). Malaysian Timber boring, cutting and surface finishes.
Industry Board or jointing.
Timber fencing (included in Class V: Miscellaneous work).
Malaysian Civil Engineering

by other relevant
Timber roof structure, doors, windows and skirting (included in Class M: Building work). governing authorities.
Finishes (included in Class N: Painting work).

FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT

1 Timber components 1 Grade A 1 Length: m M1 D2 A2


2 Grade B not exceeding 6 m The length of timber The size stated shall be Item description for
3 Grade C 2 Length: m components shall be the finished size. timber components
4 Grade D exceeding 6 m their overall lengths shall state the
Standard Method of Measurement ̵ Second Edition

with no allowance for structural use and


scarfed or other joints. sizes.

2 Decking 1 Floors m2 M2 D3 C2 A3
3 Boarding 2 Walls m2 No deduction from the Surfaces of columns Items for walls and Item description for
3 Soffits m2 areas measured for shall be classed as soffits shall include decking and boarding
timber decking shall walls. Surfaces of any temporary staging shall state the use and
be made for openings beams and ceiling shall required. thickness of timber.
and holes each not be classed as soffits.
exceeding 0.50 m². C3 A4
D4 Decking and boarding Item description for
M3 The thickness stated shall be deemed to decking and boarding
Structural load bearing shall be the nominal include framework shall state the size
timber forming part of thickness. where expressly and spacing of the
the framework shall be required. members in framework
measured under timber where expressly
components. required.

4 Miscellaneous work 1 Handrails m A5


2 Cornice m Item description for
3 Dado m handrails, cornice and
dado shall state the
location and size.
CLASS K: TIMBER WORK
CLASS L
METALWORK

MyCESMM2 | 79
80
ADDITIONAL
CLASS L: METALWORK MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES

Measurement covered under other classes: M1 A1


No allowance shall Item description shall
Traffic signs (included in Class C: Traffic management and control and be made in the state the surface
Class R: Roads and pavings). measurement for treatment and painting
rolling margins and carried out prior to

| MyCESMM2
(MyCESMM2)

Metalwork in piling work (included in Class H: Piling work). other permissible delivery of components
Metal formwork in concrete (included in F: Earthworks and deviations. The mass to site where required.
Malaysian Civil Engineering

Class I: Concrete work). of welds, fillets, bolts,


washers, rivets, and
Metalwork in roofing structure (included in Class M: Building work).
protective coatings
Metalwork in pipework (included in Class O: Pipework). shall not be measured.
Gantries (included in Class R: Roads and pavings).
M2
Permanent and temporary rail tracks and accessories (included in No deduction shall be
Class T: Rail track). made for the mass of
Metalwork in fences (included in Class V: Miscellaneous work). metal removed to form
notches and holes each
Standard Method of Measurement ̵ Second Edition

not exceeding 0.10 m²


in area measured on
plan.

M3
The mass of members,
other than plates shall
be calculated from
overall lengths of the
members with no
deductions for splay
cut or mitred ends.

M4
The mass of member
measured shall be that
of rolled or extruded
sections, built up and
fabricated sections,
bracings, external
diaphragms, shear
connectors, stiffeners,
cleats, packs, splice
plates, and other
fittings.
CLASS L: METALWORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
1 Supply and erection 1 Hot rolled section 1 Vertical members t M5 D1 C1 A2
of structural 2 Cold rolled section and columns The mass of steel to Frames shall include Items for supply and Item description for
members 3 Built-up box or 2 Horizontal members t BS 4449 or MS146 plane frames, trusses, erection of structural supply and erection
fabricated sections and beams shall be taken for space frames, lattice members shall be of structural members
4 Extruded sections 3 Portal frames t measurement as 785 frames and tower deemed to include shall state the materials,
4 Frames t kg/m² per 100 mm structures delivery, protective grades, and their use.
5 Decking panel t thickness (7.85 t/m³), and decorative surface
6 Ancillaries t unless otherwise stated D2 treatment, jointing A3
7 Grillages t in the specification Decking shall include type, fabrication, and Item description for
or in the supplier’s plates and deck panels. handling and hoisting. supply and erection
catalogue. The masses of structural members
of other metals shall D3 C2 shall state the alignment
be taken as stated in Ancillaries shall include Items for supply and on plan, and camber
the specification or bracings, purlins, erection of structural requirements.
supplier’s catalogue. cladding rails, and members shall be
struts. deemed to include A4
non-destructive testing Item description for
as expressly required. supply and erection
of structural members
C3 shall state separately
Items for supply and and locate separate
erection of structural structural frames and,
members shall be where appropriate the
deemed to include parts of the frames.
bolted connections
using bolts of nominal A5
diameter less than 16 Item description for
mm, together with supply and erection
gusset and end plates. of structural members
shall state tapered or
castellated members.

8 Overhead crane nr D4 C4 A6
Overhead crane shall Items for supply and Item description for
be permenant structure erection of structural supply and erection
with platform, crane members shall be of structural members
runways, bridge crane, deemed to include other than for portal
hoist, frame, motor, welded connections. frames shall state
track as expressly Welded connections cranked members.
stated. shall be deemed to
include gusset and end A7
plates. Item description
for overhead crane
shall state the crane
capacity tonnage, type,
materials and principal
dimensions.

MyCESMM2 |
81
CLASS L: METALWORK
82
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
1 Supply and erection C5 A8
of structural Items for overhead Item description for
members crane shall be deemed overhead crane shall
to include runways, state where fixing
bridge, motor, track, clips and resilient pads

| MyCESMM2
(MyCESMM2)

fabrication, installation, are used to secure


foundation work, overhead crane rails.
Malaysian Civil Engineering

and protective and


decorative surface
treatment.
5 Black bolts 1 Nominal diameter: nr C6 A9
6 High strength 16 mm – 20 mm Items for black bolts Items description for
friction grip bolts 2 Nominal diameter: nr and high-strength high-strength friction
20 mm – 24 mm friction grip bolts shall grip bolts shall state
3 Nominal diameter: nr be deemed to include the grade and load
24 mm – 30 mm nuts, washers, gusset limits.
Standard Method of Measurement ̵ Second Edition

4 Nominal diameter: nr and end plates, and


30 mm – 36 mm other accessories.
5 Nominal diameter: nr
36 mm – 42 mm
6 Nominal diameter: nr
42 mm – 48 mm
7 Nominal diameter: nr
48 mm – 56 mm
8 Stated nominal nr
diameter exceeding
56 mm
7 Anchorage and nr M6 A10
holding down bolts Anchorages and Item description for
assemblies holding down bolt anchorages shall state
assemblies shall be particulars and the
measured by the type of anchorages.
number of complete
assemblies. A11
Item description for
holding down bolt
assemblies shall state
particulars of the type,
diameter and length of
the bolts.
2 Miscellaneous 1 Stairways and nr M7 C7 A12
metalwork landings Painting carried Items for miscellaneous Item description for
2 Walkways and m2 out on the site metalwork shall be stairways and landings
platforms for miscellaneous deemed to include shall state the size, and
3 Ladders m metalwork shall be fixing to other work, number of risers and
4 Handrails m classed as painting supply of fixing landings.
5 Parapets m (Class N). components, and
drilling or cutting of
other work.
CLASS L: METALWORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
2 Miscellaneous 6 Decking 1 Plate flooring m2 M8 C8 A13
metalwork 2 Open grid flooring m2 No deductions from Items for ladders and Item description
3 Welded mesh m2 the area measured parapets shall be for miscellaneous
paneling for miscellaneous deemed to include the metalwork assemblies
4 Trench covers m2 metalwork shall be full assemblies. Items shall state the
5 Ducts covers m2 made for openings for handrails shall be specification and
and holes each not deemed to include thickness of metal,
exceeding 0.50 m². balustrade. surface treatments and
principal dimensions.
7 Cladding m2 M9 C9
8 Walings m The lengths of ladders Items for decking shall A14
shall be measured be deemed to include Item description for
along the lengths supporting metalwork, ladders shall state
of stringers. The unless otherwise include safety loops,
lengths of handrails expressly stated. rest platforms or
and parapets shall be returned stringers.
measured along their
top members.

3 Miscellaneous 1 Miscellaneous 1 Angle section m M10 A15


metalwork framing 2 Channel section m The length of Item description for
3 I-section m miscellaneous framing miscellaneous framing
4 Tubular section m shall be measured shall state the size and
5 Plate m2 along the external section of members.
perimeter of framing.

2 Tie rod nr

3 Uncovered tanks 1 Volume: n.e 1 m³ nr A16


4 Covered tanks 2 Volume: 1 m³ - 3 m³ nr Item description for
3 Volume: 3 m³ - 10 m³ nr tanks shall state the
4 Volume: nr size and capacity of
10 m³ - 30 m³ tanks and specification
5 Volume: nr of material.
30 m³ - 100 m³
6 Volume: nr
100 m³ - 300 m³
7 Volume: nr
300 m³ - 1000 m³
8 Volume: stated nr
exceeding
1000 m³

MyCESMM2 |
83
CLASS L: METALWORK
Malaysian Civil Engineering
Standard Method of Measurement ̵ Second Edition
(MyCESMM2)

84 | MyCESMM2
CLASS M
BUILDING WORK

MyCESMM2 | 85
86
ADDITIONAL
CLASS M: BUILDING WORK MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES

Measurement covered under other classes:

Concrete roof structure (included in Class I: Concrete work).


Pipework and septic tank (included in Class U: Mechanical and electrical work).

| MyCESMM2
(MyCESMM2)

FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT


Malaysian Civil Engineering

1 Roofing work 1 Roof structure 1 Timber of stated m M1 D1 C1 A1


member sizes The area measured Proprietary roofing Timber roof structure Item description for
2 Timber of stated m2 for roofing system system shall be shall be deemed to roof structure shall
roofing system and components to roofing system and include connecting state the member
and components be designed by the components to be plates, bolts and nuts, nominal size, grade
to be designed contractor shall be designed by the and other fastening of materials, and
by the contractor the plan area of roof contractor. system. structural locations
3 Metal of stated kg structures. for roof structures
roof structure C2 not designed by the
Standard Method of Measurement ̵ Second Edition

member sizes Metal roof structure contractor.


4 Metal of stated m2 shall be deemed to
roofing system include connecting
and components plates, bolts and nuts,
to be designed all welding, and other
by the contractor fastening systems.

2 Roof covering 1 Flat sheet m2 M2 D2 C3 A2


2 Profiled sheet m2 Roof covering, Flat sheet shall be Items for roof Item description for
3 Tiles m2 underlay, and classed for a broad, coverings, underlay roof covering shall
insulation for curved flat, and thin piece and insulation shall state the angle of
or domed surface shall of felt or material, be deemed to include inclination to the
not be distinguished by usually in square and preparing surfaces, horizontal.
angle of inclination. rectangular shapes. forming joints,
overlaps, mitres, A3
M3 D3 angles, fillets, built- Item description for
The areas measured Profiled sheet shall be up edges, and laying roof covering for
for roof covering, classed for material to falls or cambers, curved or domed
3 Underlay 1 Wire mesh m2 underlay, and with alternating ridges cutting, notching, surfaces shall be
4 Insulation 2 Sisalation m2 insulation shall be and grooves, usually in bending and bedding. described, and the
3 Rock wool m2 those of the surface square and rectangular radius of the curvature
4 Fibreglass m2 covered. No deduction shapes. of the surface shall be
from the areas so stated.
measured shall be D4
made for holes and Tiles shall be classed A4
openings in the roof for discrete material Item description
covering each not either flat or profiled, for roof covering,
exceeding 0.5 m² in laid in overlapping underlay, and
area. rows, and are usually insulation shall state
square or rectangle. the materials used,
locations, number and
thickness of coatings
or layers.
CLASS M: BUILDING WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
1 Roofing work 5 Roofing ancillaries 1 Eaves and verges m C4 A5
2 Fascia m Items for roofing Item description for
3 Flashing m ancillaries, flat/ roofing ancillaries
4 Kerbs m profiled sheet shall state the work to
5 Hood nr components and tile be covered, the type
6 Roof ventilators nr components shall be of materials, the size
7 Soaker nr deemed to include and the thickness.
6 Flat sheet 1 Crank and upstand m forming holes, cutting
components 2 Ridge, hip, and m and making good for
7 Profiled sheet vertical angle services.
components capping
3 Roof light and nr C5
special sheets Items for roofing
4 Transparent sheet nr ancillaries, flat/
5 Ventilator sheet nr profiled sheet
6 Sheet with soaker nr components and tile
flanges component shall be
7 Ridge ventilator nr deemed to include
preparing surfaces,
8 Tiles components 1 Valley m
forming joints, mitres,
2 Mitred hips m
angles, fillets, built-up
3 Mitred vertical angles m
edges, overlaps and
4 Ridge and hip m
laying to cambers or
capping
falls.
5 Vertical angle m
6 Saddles nr
7 Glass tiles nr
2 Roofing work 1 Gutters and 1 Gutters m M4 D5 C6 A6
downpipes 2 Fittings to gutters nr Lengths of gutters Fittings to gutters shall Items for gutters and Item description for
3 Downpipes m and downpipes shall include bends, angles, downpipes shall be gutters and downpipes
4 Fittings to nr be measured along stop ends, and outlets. deemed to include shall state the type,
downpipes their centre lines and Fittings to downpipes fixing and supply of principal dimensions,
shall include lengths shall include bends, fixing components. and materials of the
occupied by fittings, swan necks, shoes, components.
with no allowance for and roof outlet, fixed
laps. directly to downpipes.
3 Waterproofing 1 Asphalt 1 Sloping m2 M5 D6 C7 A7
2 Bituminous 2 Horizontal m2 The areas measured Sloping: Angle of Items for Item description for
3 Sheet metal 3 Vertical m2 for waterproofing and inclination from the waterproofing and waterproofing and
4 Waterproofing 4 Surfaces of width m sheet lining membrane horizontal is 5° - 80°. sheet lining membrane sheet lining membrane
sheeting not exceeding shall be those of the shall be deemed to shall state the materials
5 Waterproof coating 300mm surfaces covered. No D7 include preparing used, and the number
6 Rendering in 5 Isolated group of nr deduction from the Horizontal: Angle of surfaces, forming and thickness of
ordinary cement surfaces not areas measured shall inclination from the joints, overlaps, mitres, coatings or layers and
mortar exceeding 1 m² be made for holes horizontal is 0° - 5°. angles, fillets, built-up method of application
7 Rendering in 6 Lining to other nr and openings in the edges, and laying to as per manufacturer’s
waterproof cement stated fixtures waterproofed surfaces D8 falls or cambers. instructions.
mortar each not exceeding 0.5 Vertical: Angle of

MyCESMM2 |
8 Sprayed or brushed m² in area. inclination from the
waterproofing horizontal is 80° - 90°.

87
CLASS M: BUILDING WORK
88
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
3 Waterproofing A8
Item description
for isolated groups
of surfaces shall
identify the work to

| MyCESMM2
(MyCESMM2)

be waterproofed and
its location shall be so
Malaysian Civil Engineering

stated.
4 Sheet lining 1 Butyl rubber M6
membrane 2 Ethylene propylene Isolated groups of
monomer rubber surfaces of different
3 PVC shapes or dimensions
4 Polypropylene shall be measured as
5 Polyethylene separate items.
6 Polyurethane
7 Proprietry system
Standard Method of Measurement ̵ Second Edition

5 Windows and 1 Timber 1 Windows sub- nr D9 C8 A9


doors 2 Metal frames All fire-rated doors Items for windows Item description for
3 Plastic 2 Windows nr shall be obtained and doors shall be windows and doors
3 Doors sub-frames nr from approved deemed to include shall identify the shape,
or lining sets manufacturers and fixing, supply of fixing size and type.
4 Door leaf nr in compliance with components, and
5 Ironmongery nr Jabatan Bomba dan drilling or cutting of A10
6 Anti-vermin netting nr Penyelamat Malaysia associated work. Item description for
7 Screens and nr or by other relevant windows and doors
borrowed lights governing authorities. C9 shall state glazing
8 Roof lights nr Items for windows requirements.
D10 and doors shall be
Hinges, door closers, deemed to include A11
locks, and handles all associated glazing Item description for
shall be classed as work as expressly ironmongery shall state
ironmongery. required. the materials, type and
design.
C10
All necessary fixing
with screws to match
the ironmongery
shall be deemed to
be included with the
items.

C11
All locks deemed to be
supplied with master
keys and keys.
CLASS M: BUILDING WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
6 Glazing 1 Glass m2 D11 A12
2 Glass in large panes m2 Panels which exceeded Item description for
3 Special glass nr 4 m² shall be classed glazing shall state the
4 Hermetically sealed nr as glass in large panes. materials, their nominal
units thickness, the method
5 Mirrors nr D12 of glazing and the
6 Patent glazing nr The following materials method of securing the
used in glazing shall glass and incidental
be classed as special metal work supporting
glass: patent glazing.

a) glass whose A13


thickness Item description for
exceeds 10 mm glazing shall state work
which is curved or
b) non-rectangular faceted.
panes of glass.
A14
c) toughened, Item description shall
laminated, state the construction
solar control and of hermetically sealed
other speciality units.
glass.
A15
d) acrylic, polycarbonate Item description
and similar materials. for special glass,
hermetically sealed
units, mirrors and
patent glazing shall
state the shape and
size of panes.
7 Finishes 1 Floor finishes 1 Tiles m2 M7 C12 A16
2 Cement and sand m2 No deduction from Items for floor finishes, Item description for
screed areas of finishes shall wall finishes and finishes shall state the
3 Granolithic m2 be made for holes and skirting to floor shall materials and thickness.
4 Wash aggregates m2 openings each not be deemed to include
5 Carpet m2 exceeding 0.5 m² in fixing, supply of fixing A17
6 Vinyl m2 area. components, and Item description for
7 Floor hardener m2 drilling or cutting of carpet shall state the
8 Timber laminate m2 associated work. knot density.
2 Skirting 1 Tiles m
2 Timber m C13 A18
3 Concrete m Items for floor finishes, Item description for
wall finishes and skirting to floor shall
3 Wall finishes 1 Tiles m2
skirting to floor shall state the height.
2 Cement and sand m2
be deemed to include
plasterings
preparing surfaces, A19
3 Granolithic m2
forming joints, mitres, Item description for
m2

MyCESMM2 |
4 Wash aggregates
angles, fillets, built-up prefabricated panels
5 Spray tiles m2
edge and laying to shall state the size and
6 Prefabricated panel m2

89
CLASS M: BUILDING WORK

cambers or falls. number of panels.


90
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
7 Finishes 4 Ceiling finishes 1 Skim coating m2 C14 A20
2 Rendering m2 Items for floor finishes, Item description for
3 Suspended ceiling m2 wall finishes and suspended ceiling shall
4 Cornices m skirting to floor with state the type and
5 Access panels nr tiles shall be deemed material of support

| MyCESMM2
(MyCESMM2)

to include cement system and material of


mortar screed where ceiling.
Malaysian Civil Engineering

applicable.
A21
C15 Item description for
Items for ceiling finishes access panel in ceiling
shall be deemed to shall state the overall
include any temporary dimensions.
staging required.

C16
Items for suspended
Standard Method of Measurement ̵ Second Edition

ceilings shall be deemed


to include associated
primary support or
hanger systems.

C17
Items for ceiling shall
be deemed to include
sloping ceiling.
8 Floor and wall 1 Wall partitions 1 Solid m2 M8 C18 A22
system 2 Full board m2 The length measured Items for wall partitions Item description for
3 Half board with m2 for wall partitions shall shall be deemed to wall partitions shall
fixed glass exclude the length of include fixing, supply state the materials,
4 Cubicle sets nr voids which extend to of fixing components, finishes and finished
the full height of the and drilling or cutting thickness.
partition. of associated work.
A23
C19 Item description for
Items for wall partitions cubicle sets shall state
shall be deemed to the overall dimensions.
include forming holes,
cutting and making
good for services.
2 Raised access floor m2 D13
Item for raised access
floor refers to a false
floor raised from the
ground to serve as
an accessible floor
system for the laying of
flooring services such
as power lines and
cables.
CLASS M: BUILDING WORK
CLASS N
PAINTING WORK

MyCESMM2 | 91
92
ADDITIONAL
CLASS N: PAINTING WORK MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES

Measurement covered under other classes: M1 D1 C1 A1


No deduction from Metal other than Items for painting shall Item description for
Painting for structural metalwork (included in Class L: Metalwork). the areas measured metal sections and be deemed to include painting shall state the
shall be made for holes pipework shall include preparation of surfaces material used, number
Painting to gantries (included in Class R: Roads and pavings). and openings in the miscellaneous metal before painting, of coats, and whether

| MyCESMM2
(MyCESMM2)

painted surfaces each work. including all necessary it is for internal or


not exceeding 0.5 m² temporary staging. external surfaces.
Malaysian Civil Engineering

in area.
C2 A2
Items for painting shall Item description for
be deemed to include preparation of surfaces
the application of base shall be identified and
primer/sealer required stated where more
before painting the than one type of
subsequent coats. preparation is specified
for the same surface.
Standard Method of Measurement ̵ Second Edition

FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT

1 Oil paint 1 Metal other than 1 Surfaces of m2 M2 D2 C3 A3


2 Alkyd gloss paint metal sections and members: exceeding Isolated groups of Concrete formed using Items for painting of Item description for
3 Emulsion paint pipework 300 mm girth surfaces of different Class F1 formwork shall metal shall be deemed isolated groups of
or acrylic paint 2 Timber 2 Surfaces of m shape or dimensions be classed as rough to include painting the surfaces shall identify
4 Cement paint 3 Smooth surfaces members: not shall be measured as surfaces and concrete surfaces of connecting the work to be painted
5 Epoxy or exceeding separate items. formed using Classes F2 plates, brackets, rivets, and its location.
polyurethane paint 300 mm girth and F3 shall be classed bolts, nuts and similar
6 Bituminous or coal 3 Isolated groups nr as smooth surfaces. projections.
tar paint of surfaces
7 Chlorinated rubber D3 C4
paint Smooth concrete Items for painting
8 Fire resistance paint surfaces and plastered of timber shall be
surfaces shall be classed deemed to include
as smooth surfaces. painting the surfaces of
recesses, projections,
D4 and fittings.
Rough concrete
surfaces and rendered
surfaces shall be classed
as rough surfaces.
CLASS N: PAINTING WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
1 Oil paint 4 Rough surfaces 1 Surfaces of members: m2 M3 C5
2 Alkyd gloss paint 5 Masonry exceeding In calculating the Items for painting
3 Emulsion paint 6 Brickwork and 300 mm girth painted area of of pipework shall be
or acrylic paint blockwork 2 Surfaces of m metal, the presence deemed to include
4 Cement paint members: not of connecting plates, painting the surfaces of
5 Epoxy or exceeding brackets, rivets, bolts, flanges, valves, other
polyurethane paint 300 mm girth nuts and similar projecting fittings and
6 Bituminous or coal 3 Isolated groups nr projections, and inner hangers.
tar paint of surfaces surfaces of openings
7 Chlorinated rubber and outer edges shall
paint be ignored.
8 Fire resistance paint

7 Metal sections m2 M4
8 Pipework m2 The area measured
for painting pipework
shall be the length
multiplied by the girth
of each length of
pipe or lagged pipe
with no deductions or
additions for flanges,
valves, other projecting
fittings and hangers.

MyCESMM2 |
93
CLASS N: PAINTING WORK
Malaysian Civil Engineering
Standard Method of Measurement ̵ Second Edition
(MyCESMM2)

94 | MyCESMM2
CLASS O
PIPEWORK

MyCESMM2 | 95
96
ADDITIONAL
CLASS O: PIPEWORK MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES

Measurement covered under other classes: C1 A1


Items for pipework Item description for
Steel pipe piles (included in Class H: Piling work). and the associated pipework shall identify
work shall be deemed separately work which
Pipes and ducts built into brickwork (included in Class J: Brickwork, blockwork to include supply and is expressly required

| MyCESMM2
(MyCESMM2)

and masonry). laying or installation. to be carried out


Valve chambers and thrust blocks (included in Class I: Concrete work). manually.
Malaysian Civil Engineering

Pipe reinstatements works (included in Class P: Pipe rehabilitation work).

FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT

1 Excavation 1 Trench in earth 1 Depth: Not m M1 D1 C2 A2


exceeding 1.5 m Length of trench The depth used for Items for trench Item description for
2 Depth: 1.5 m - 2.0 m m excavation shall be classification of trench excavation shall be excavation shall identify
3 Depth: 2.0 m - 2.5 m m measured along the excavation shall be deemed to include the commencing
4 Depth: 2.5 m - 3.0 m m centre line of the measured from the preparation of surfaces, surface of each item
Standard Method of Measurement ̵ Second Edition

5 Depth: 3.0 m - 4.0 m m pipeline. commencing surface to multiple handling, for work involving
6 Depth: 4.0 m - 5.0 m m the inverts of the pipes. disposal of surplus excavation which the
7 Depth: 5.0 m - 6.0 m m M2 excavated material commencing surface is
8 Depth: Length of trench D2 (including unsuitable also the original surface.
Exceeding 6.0 m m excavation shall be Unless otherwise material), upholding
measured through expressly required, the sides of excavation, A3
and include any space nominal width of the allowance for working Item description for
occupied by valves trench shall be the space, backfilling, excavation shall state
(except those in nominal diameter of and removal of dead where more than
chambers) and fittings. the pipe or of the larger services. one pipe is expressly
pipe if laid one above required to be laid in
the other, plus 500 mm. one trench and also
Where pipes are laid identify the pipe runs.
side by side, the nominal
trench width shall be the A4
sum of all the internal Item description for
diameters and spacing trench excavation shall
2 Extra over 1 Rock m3 M3 between the pipes, plus C3 state the pipe diameter
2 Natural hard material m3 Excavation in rock, 500 mm. Items for excavation in and location.
3 Artificial hard m3 natural and artificial roads and pavements
material hard material, and shall be deemed to
4 Unsuitable materials m3 unsuitable materials include road cutting and
5 Roads and m2 shall be measured as the reinstatement.
pavements volume of the respective
item removed within
the limits of trench
excavation.
CLASS O: PIPEWORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
1 Excavation 3 Manhole and 1 Earth m3 M4 D3 C4 A5
chamber 2 Rock m3 An isolated volume of Earth shall be deemed Extra over excavation Item description for
3 Natural hard material m3 rock or natural hard to be materials other shall be deemed to roads and pavements
4 Artificial hard m3 material and artificial than topsoil, natural include for breaking up shall state thickness.
material hard material occurring hard material, rock, rock, natural or artificial
5 Unsuitable materials m3 within the trench artificial hard material hard materials when it
6 Roads and m2 excavation shall not be or unsuitable material, occur.
pavements measured separately, unless otherwise stated
unless its volume in the item description.
C5
exceeds 0.25 m³. Items for trench
D4 excavation shall be
M5 Extra over item is deemed to include
Excavation shall be measured as extra reinstatement of original
measured as excavation in and above excavation surface unless covered
earth to stated depth and measured in earlier item. by separate items in this
another item for extra over class.
breaking up rock.
C6
M6 Items for trench
Excavation in roads excavation shall be
and pavements shall deemed to include
be measured vertically excavation for bedding
from the nominal trench if applicable.
width for pipes and up to
the external surfaces for C7
manholes and chambers. Items for trench
excavation shall be
M7 deemed to include
Volume of excavation excavation for trust
for manholes and blocks and anchor
chambers shall be blocks.
measured vertically
between their external
surfaces or extended
base and the limits of
trench excavation.

M8
The volume of extra
over excavation and
backfilling for pipe laying
in headings, in thrust
boring and pipe jacking
shall be measured by
multiplying together the
internal cross-sectional
area of pipe and the
length of the material

MyCESMM2 |
excavated or backfilled.
Packing in headings

97
CLASS O: PIPEWORK

shall not be measured.


98
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
2 Below ground 1 River, stream, culvert nr M9 D5 C8 A6
crossings or canal width: Below ground River, stream, culvert, Items for below ground Item description
1m-3m crossings shall be and canal crossings crossings shall be for below ground
2 River, stream, culvert nr measured as extras shall be classified by deemed to include crossings shall state
or canal width: to items for pipes in their widths measured reinstatement, unless where existing linings to

| MyCESMM2
(MyCESMM2)

3 m - 10 m trenches. along pipe, duct or otherwise stated. rivers, streams, culverts


3 River, stream, culvert nr culvert centre line or canals are to be
Malaysian Civil Engineering

or canal width: M10 when the water surface broken through and
exceeding 10 m Below ground is at the higher level of reinstated and the type
4 Fence nr crossings of streams fluctuation. of lining.
5 Sewer or drain nr shall be measured
6 Wall nr only where their width A7
7 Other stated nr exceeds 1 m. Item description
underground for below ground
services M11 crossings shall state the
River, stream, diameter and method of
culvert, and canal excavation.
Standard Method of Measurement ̵ Second Edition

crossings exceeding
10 m in width shall
be measured where
special pipe laying
methods are not used.
3 Backfilling, bedding, 1 Backfilling 1 Sand m3 M12 C9 A8
support and 2 Selected excavated m3 Backfilling of trenches Items for concrete Item description for
protection suitable materials with excavated material shall be deemed to backfilling, bedding,
3 Imported materials m3 shall not be measured. include formwork support and protection
4 Mass concrete m3 and reinforcement as shall state the type and
5 Reinforced concrete m3 M13 applicable. dimensions.
The volume of
backfilling in pipe
trenches shall
be calculated by
multiplying the average
depth by the length of
backfill placed by the
nominal trench width
less volume occupied by
the pipe.
2 Beds 1 Sand m A9
3 Surround 2 Selected excavated m Item description for
4 Haunches suitable materials bedding shall state the
3 Imported materials m pipe nominal diameter.
4 Mass concrete m
5 Reinforced concrete m A10
Item description for
bed, haunches and
surrounds shall state
the depth and material
used.
CLASS O: PIPEWORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
3 Backfilling, bedding, 5 Wrapping and m A11
support and lagging Item description for
protection 6 Concrete stools and nr bed, haunches and
thrust blocks surrounding to multiple
7 Other isolated pipe nr pipes shall state the
supports number of pipes and
maximum nominal
distance between the
inside faces of the other
pipe walls.
4 Pipes 1 Sewerage 1 Vitrified clay m M14 C10 A12
2 Water supply 2 Reinforced concrete m Lengths of pipes shall Items for pipes shall Item description for
3 Other pipe works 3 Ductile iron m be measured along their be deemed to include pipes shall state the
4 Unplasticised m centre lines between supply, and laying or shape, joint types,
polyvinyl chloride straight specials, fittings installation. nominal pipe diameter,
5 Stainless steel m or fittings connected to internal and external
6 Polyethylene m manholes and chambers C11 lining or protection
7 Mild steel m for pipes of diameter Items for pipes shall be requirements and
8 Galvanised steel m more than 100 mm. deemed to include all reference given to
wrapping, lining, and applicable Malaysian or
M15 lagging as required. other relevant standard.
Length of pipes
entering sewerage C12 A13
5 Pipes 1 Glass reinforced m manholes and other Items for pipes shall Item description for
plastic chambers shall be be deemed to include pipes in steel shall state
2 Concrete/cement m measured to the inside pipe cutting where the type (mild or carbon
lined surface of the chambers, applicable, unless steel) and the grade.
3 HDPE m except that pipes and otherwise stated.
4 Acrylonitrile m fittings comprising
butadiene styrene backdrops shall be C13
5 Oriented m included in the items for Items for pipes of
unplasticised manholes. diameters less than 100
polyvinyl chloride mm shall be deemed to
include fittings, valves
and joints.
6 Fittings, valves and 1 Straight specials 1 Plain ended nr M16 D6 C14 A14
joints 2 Plain and flange nr Fittings, valves and A straight special is a Items for straight Item description for
ended joints of diameter less length of pipe either specials shall be fittings, valves and
3 Flange ended nr than 100 mm shall not cut to length or made deemed to include joints shall state the
4 Plain ended with nr be measured. to order. cutting. material, nominal
puddle flange diameter, joint type
5 Plain and flange nr M17 D7 and pressure rating.
ended with Straight specials Straight specials
puddle flange shall be measured and joints on pipes A15
6 Flange ended with nr only where they are of different nominal Item description for
puddle flange expressly required diameter shall be straight specials shall
classified according to state the length and
the nominal diameter location of flanges

MyCESMM2 |
of the largest pipe. including puddle
flange.

99
CLASS O: PIPEWORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
6 Fittings, valves and 2 Fittings 1 Bends nr M18 A16
joints 3 Fittings special 2 Junction and nr Fittings, valves and Item description for
branches joints comprising fittings and fittings
3 Tapers nr backdrops to manholes special shall state the
4 Bell mouths nr shall be included in the nominal diameter, angle

100 | MyCESMM2
(MyCESMM2)

5 Blank flanges nr items for manhole. and type.


6 Duckfoot bend nr
Malaysian Civil Engineering

7 Hydrants nr A17
8 Tapping saddle Item description for
tapers shall state the
principal dimension and
nominal diameter of
the main pipe and the
reduce pipe.

A18
Item description for
Standard Method of Measurement ̵ Second Edition

junction and branches


shall state tee, wye,
flanges, sockets and
flange branch types.
4 Valve 1 Linear motion valve nr D8 C15 A19
2 Rotary motion valve nr Linear motion valve is Items for valve shall ltem description for
3 Quarter turn valve nr the closure member be deemed to include type of valve, penstock
4 Special valve nr moves in a straight line reduction gears where and actuator shall state
5 Penstock nr throttle the flow such applicable mode of operation,
6 Actuator nr as needle, globe, sluice, location to be installed,
fixed cone valve etc. C16 specification, material,
Items for valve shall size and capacity
D9 be deemed to include designed.
Rotary motion valve all supply, jointing,
is the closure member couplings, flange,
travel along an angular bolting, washers, and
or circular path such as gaskets including make
gate valve. good all joint.

D10 C17
Quarter turn valve is Items for actuator shall
the valve that required be deemed to include
quarter turn motion valve where expressly
such as butterfly, ball required.
valve etc.

D11
Special valve is a valve
that the operation is
assisted by the special
medium such as air
or pressure or valve
operated by itself.
CLASS O: PIPEWORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
6 Fittings, valves 5 Joints 1 Welded collar joints nr M19 D12 C18
and joints 2 Welded slip joints nr Joints shall be Mechanical coupling Items for joints shall
3 Butt welded joints nr measured separately, shall mean normal be deemed to include
4 Mechanical coupling nr unless otherwise mechanical coupling thrust block and supply
joints expressly stated. and stepped mechanical of all jointing materials,
5 Flange adaptor joints nr coupling. bolts, nuts, washers,
6 Expansion joints nr gaskets, making good of
7 Push-on collar joints nr joints both internally and
8 Push-on slip joints nr externally as expressly
required.

C19
Items for welded collar
6 Joints 1 Stepped coupling nr joints and welded slip
2 Universal coupling nr joints shall be deemed
to include welding to
the internal of the pipe
and air testing of joints
as expressly stated.
7 Flow meter/bulk nr A20
meter Item description for
flow meter shall state
the diameter and type.
7 Special pipe laying 1 In heading 1 Jacking pit nr M20 D13 C20 A21
method 2 Thrust boring 2 Receiving pit nr Special pipe laying Pipe made with Items for special Item description for
3 Pipe jacking 3 Pipe sleeve m methods shall be reinforced concrete as pipe laying methods special pipe laying
4 Microtunneling 4 Composite pipe m measured only where the external shell and excluding submarine methods shall identify
5 Utility pipes in pipe m they are expressly pipe from O4** and pipe laying shall be the material and
sleeves required. O5** shall be classed as deemed to include nominal diameter, and
6 Pressure grouting m3 composite pipe. mobilisation and the run of pipes.
5 Controlled 1 Horizontal m demobilisation.
drilling directional drilling A22
2 Impact molling m C21 Item description for
Items for special pipe pipe sleeves and
laying methods shall composite pipe shall
6 Submarine pipe 1 Bathymetric survey m be deemed to include state the type of
laying 2 Sub-sea geophysical m excavation, sheet piles, material, diameter and
survey shoring, and backfilling. the class.
3 Mobilisation and sum
demobilisation C22 A23
4 Provision of winch sum Items for sub-sea Item description for
equipment geophysical survey slip lining shall state
5 Trenching m shall be deemed to diameter, the minimum
6 Concrete cladding m include report by a finished internal size,
to pipes geophysicist. type of lining, its
7 Pipes laid by float m thickness or grade.
and sink
8 Pipes laid by bottom m
pull

MyCESMM2 | 101
CLASS O: PIPEWORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
7 Special pipe laying 7 Submarine pipe 1 Pipes laid by lay m C23 A24
method laying barge Items for pipe sleeves Item description of
2 Tie in to land pipes sum and composite pipe pipe jacking pit shall
3 Swabbing and m shall be deemed to state pit size and depth
gauging include excavation of 2 m stages.

102 | MyCESMM2
(MyCESMM2)

4 Inspection by divers sum within the pipe.


A25
Malaysian Civil Engineering

Item description for


special jacking method
to be stated.

8 Slip lining m A26


Item description for
slip lining shall state
Standard Method of Measurement ̵ Second Edition

the offset where the


lining is curved to an
offset which exceeds
35 mm per metre.

8 Miscellaneous work 1 Sewer manholes 1 Brick nr D14 C24 A27


2 Chamber 2 Brick with backdrop nr The depth of manholes Items for manhole shall Item description for
3 Reinforced in situ nr shall be measured be deemed to include manhole shall state
concrete from the top of covers all items of metalwork type or mark numbers
4 Reinforced in situ nr to channel inverts or and pipework, benching, and depth where
concrete with the top of base slabs, plastering, painting, and details are expressly
backdrops whichever is lower. excavation which occur given. Manholes with
5 Precast concrete nr within or at the surface backdrops shall be so
6 Precast concrete nr of the item. described.
with backdrops
C25 A28
Items for brick Item description for
manholes shall be manholes shall state
deemed to include types and loading
blinding, reinforced duties of manhole
concrete base and top covers.
slabs.

C26
Items for manhole
with backdrops shall
be deemed to include
the pipework and
associated fittings
comprising the
backdrops.
CLASS O: PIPEWORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
8 Miscellaneous work 3 Testing and 1 Testing of gravity m M21 C27 A29
inspection sewer The unit of Items for testing and Item description for
2 Testing of vacuum m measurement for items inspection shall be testing and inspection
sewer O831 to O836 can be deemed to include shall state the material
3 Pressure and m measured in sum where provision and removal and diameter of pipe to
leakage testing applicable. of all equipment and be tested.
4 Flushing and m ancillaries required for
sterilising testing.
5 Close circuit m
television inspection C28
6 Radiographic test nr Items for testing of
7 Holiday detector test sum gravity sewer shall
8 Ultrasonic test sum be deemed to include
provision of all water
required for testing.

C29
Testing of gravity
sewer shall be deemed
to include testing by
infiltration as required.

C30
Items for pressure and
leakage testing shall
be deemed to include
provision of all water
required for testing.

C31
Items for flushing
and sterilising shall
be deemed to include
chemicals and provision
of water.

C32
Items for holiday
detector test and
ultrasonic test
shall be deemed to
include provision of
equipment, testing and
maintenance.

MyCESMM2 | 103
CLASS O: PIPEWORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
8 Miscellaneous work 4 Temporary diversion 1 Temporary diversion sum C33 A30
of existing utilities Items for temporary Item description for
2 Temporary diversion sum diversion shall be temporary pumping
of sewage flows deemed to include over of sewage flows
coordination with shall state the pipe

104 | MyCESMM2
(MyCESMM2)

relevant authorities, and manhole sizes and


provision and removal the distance between
Malaysian Civil Engineering

of all equipment and manholes.


ancillaries required
including pumping over.
5 Connections to 1 Existing manhole nr D15 C34 A31
existing sewer 2 Manhole junction nr Manhole junction Items for connections Item description for
system connection typical detail shall be as to existing sewer connection to existing
3 Sewer saddle nr per MSIG. system shall be sewer system shall
connection deemed to include state existing material,
4 New manhole nr coordination with pipe and manhole sizes.
Standard Method of Measurement ̵ Second Edition

authorities, payment
of fees, isolations for
shutdown of flows and
dewatering.

C35
Items for new manhole
shall be deemed to
include breaking away
of existing sewer pipe
as required, and all
pipework and metalwork
within the manhole.
6 Connection to 1 Hot tapping nr C36 A32
existing water mains connection Items for shut down Item description for
2 Line stopping nr connection shall be connection to existing
3 Shut down nr deemed to include water main shall state
connection coordination with the material and sizes of
authorities, payment the existing pipe to be
of fees, isolations for connected.
shutdown of flows, and
dewatering.
7 Pipework ancillaries 1 Marker posts nr C37 A33
2 Ring girder nr Items for marker post, Item description for ring
3 Pipe strap nr ring girder, pipe straps, girder, pipe strap, and
4 Spike guard nr and spike guards shall spike guard shall state
be deemed to include the type of material and
supply and installation, diameter of pipe.
including painting.
8 Water sampling nr C38
station Water sampling station
shall be deemed to
include connection to
CLASS O: PIPEWORK

the mains.
CLASS P
PIPE
REHABILITATION
WORK

MyCESMM2 | 105
ADDITIONAL
CLASS P: PIPE REHABILITATION WORK MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES

Measurement covered under other classes: M1 C1 A1


The lengths of sewers Items for work which Item description shall
New manhole and pipework (included in Class O: Pipework). shall be measured is expressly required state the location of
along their centre to be carried out by work in each item or
New fittings and valves used in pipe rehabilitation works (included in lines between the excavation shall be group of items. Work

106 | MyCESMM2
(MyCESMM2)

Class O: Pipework). inside surfaces of deemed to include can be identified


Extras to excavation and backfilling for new manhole and other chambers manholes but exclude preparation of by reference to the
Malaysian Civil Engineering

(included in Class O: Pipework). lengths occupied surfaces, disposal of drawing.


by pipes and fitting excavated materials,
comprising backdrops upholding sides of A2
to manholes. excavation, backfilling Item description shall
and removal of dead state the principal
M2 services. dimensions and
Where work is profiles of sewer.
expressly required C2
to be carried out by Items for work which A3
excavation, crossing, is expressly required Item description
Standard Method of Measurement ̵ Second Edition

reinstatement and to be carried out by shall state work


other pipework excavation shall be which is expressly
ancillaries and extras deemed to include required to be carried
to excavation and preparation of out manually or by
backfilling shall be surfaces, disposal of remote controlled.
measured in Class O. excavated material,
upholding sides A4
of excavation, Item description shall
backfilling, and identify work which
removal of dead is expressly required
services. to be carried out
by excavation and
(except for manholes)
shall state the
maximum depth of
excavation in stages
of 1 m measured to
the invert level of
sewer or water mains.

A5
Item description
for preparation,
stabilisation,
renovation and
laterals shall state the
material forming the
existing sewer or water
main.
CLASS P: PIPE REHABILITATION WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
1 Rehabilitation of 1 Cleaning m M3 D1 C3 A6
existing pipework Lengths of pipeworks Items shall be Items for surveys shall Item description for
system shall be measured classed as removal be deemed to include pipework shall state
along their centre of intrusions where report by licensed the location of the
lines between the intrusions into the surveyor. work in each item or
inside surfaces of bores of existing group of items, so that
manholes/ chambers pipework are to be C4 it can be identified
but shall exclude removed prior to Items for cleaning shall by reference to the
lengths occupied by renovation. be deemed to include drawings.
pipes and fittings pre-cleaning.
comprising backdrops D2 A7
2 Removal of 1 Lateral bore n.e nr to manholes. The areas stated in the C5 Item description
intrusions 150 mm item description for Items for local internal for pipework shall
2 Laterals bore nr M4 local internal repairs repairs shall be state the principal
exceeding 150 mm External grouting shall be the finished deemed to include dimensions and pipe
3 Other stated nr shall be measured surface areas. cutting out. profiles.
artificial intrusions only where grouting
is expressly required D3 C6 A8
to be carried out as External grouting shall Items for cleaning shall Item description for
a separate operation be grouting of voids be deemed to include surveys shall state type
from annulus grouting. outside the existing temporary structure and copies required.
pipework from within and removal after
the existing pipework completion
other than voids
grouted in the course
of annulus grouting.
3 Surveys 1 Closed-circuit m M5 D4 C7 A9
television The volume measured Annulus grouting shall Items for removal of Item description for
for annulus grouting be grouting of the intrusions shall be removing intrusions
shall not include the annular voids between deemed to include shall state the materials
volume measured for new lining and existing making good. forming the intrusion.
external grouting. pipework and of other
voids grouted in the C8 A10
course of grouting Items for pipe joint Item description for
4 Pipe joint sealing 1 Materials and m annular voids. sealing shall be pipe bursting shall
diameter stated deemed to include state the pipe diameter.
preparation of joints.
A11
Where external
grouting is
carried out through
5 Local internal m2 pipe joints,
repairs description of items for
the number of holes
shall be so stated.

6 Pipe bursting m

MyCESMM2 | 107
CLASS P: PIPE REHABILITATION WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
1 Rehabilitation of 7 External grouting 1 Number of holes nr A12
existing pipework 2 Injection of grout m3 Item description for
system and materials stated cured in place lining,
in situ jointed pipe
lining, segmental lining

108 | MyCESMM2
(MyCESMM2)

and stated proprietary


lining shall state the
Malaysian Civil Engineering

type of lining material,


its minimum finished
internal size, diameter
and its thickness or
grade.

A13
8 Pipework 1 Cured in place lining m
Item description for
2 In situ jointed pipe m
in situ jointed pipe
lining
lining and segmental
Standard Method of Measurement ̵ Second Edition

3 Segmental lining m
lining shall state the
4 Stated proprietary m
offset where the lining
lining
is curved to an offset
5 Gunite coating m2
which exceeds 35 mm
6 Annulus grouting m3
per metre.

A14
Item description for
gunite coating shall
state thickness.
2 Rehabilitation of 1 Abandonment of nr
existing manholes existing manholes
2 Modification/ 1 Identification of nr C9 A15
Alteration of lost manhole Items for abandonment Item description
manholes 2 Raise-up manhole nr of existing manholes for rehabilitation of
3 Replace of manhole nr shall be deemed to existing manholes shall
cover include sealing off state the details of
4 Reinstatement nr the ends of existing work required.
pipework, breaking
down of top of
manhole to flush with
existing ground and
backfilling.
3 Rehabilitation 1 Marker posts nr C10 A16
ancillaries of work 2 Ring girder nr Items for marker post, Item description for
3 Pipe strap nr ring girder, straps, ring girder, pipe strap,
4 Spike guard nr and spike guards shall and spike guard shall
5 Water sampling nr be deemed to include state the type of
station supply and installation, material and diameter
6 Special treatment of sum including painting. pipe.
sludge
CLASS P: PIPE REHABILITATION WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
3 Rehabilitation C11 A17
ancillaries of work Items for water Item description
sampling station shall for rehabilitation
be deemed to include ancillaries work shall
connections to the state detail of the
mains. works.

A18
Item description
for water sampling
station and special
treatment of sludge
shall state details
and descriptions that
can be identified
by reference to the
drawings.

4 Desilting 1 Desludging, 1 Mechanical system sum D5 C12 A19


dewatering and 2 Non mechanised sum The treatment for wet Items for desludging, Item description shall
disposal works 3 Tanker sum sludge for desilting dewatering and identify where special
works shall be disposal shall be treatment of sludge is
conducted until dry deemed to include expressly required in
sludge has achieved submission of monthly desilting works.
a minimum of 20% effluent
dry solid content to test result and
the existing pond bed laboratory test for
level. moisture content
during the desilting
works.

2 Special treatment of 1 Composting of sum D6 C13 A20


sludge cake sludge cake Only supernatant water Desilting works Item description for
(clear water portion) shall be deemed to desilting works shall
shall be pumped for include desludging state the estimated
discharge. and dewatering of wet sludge volume,
sludge disposal to range of solid content,
D7 contractors’s own desilting method,
Limit of the desilting approved site including identify sludge disposal
works for pond shall be transportation, loading, site.
approximately 100mm unloading, dump site
from the bed level of maintenance, removal A21
pond. or preservation of Item description for
identified under water desilting works for
D8 life and cleaning works mechanical equipment
Desilting works for after completion. ie tanks, chambers and
structure other than pumps shall state the
pond, full desludging method for cleaning
works shall be carried works i.e. water jetting.
out.

MyCESMM2 | 109
CLASS P: PIPE REHABILITATION WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
4 Desilting A22
Item description for
desilting works for
mechanical equipment
ie tanks, chambers and

110 | MyCESMM2
(MyCESMM2)

pumps shall state the


size of the equipment.
Malaysian Civil Engineering

5 Interruptions 1 Preparation of hr M6
existing sewer Interruption shall be
2 Stabilisation of hr measured only where
existing sewers a minimum capacity
is expressly required
and for periods of time
during normal working
hours when the flow
Standard Method of Measurement ̵ Second Edition

in the sewer exceeds


the installed pumping
capacity and work is
interrupted.

3 Renovation of 1 Cured in place lining hr D9 A23


existing sewers 2 In situ jointed pipe hr Annulus grouting shall Item description for
lining be grouting of the in situ jointed pipe
3 Segmental lining hr annular voids between lining and segmental
4 Stated proprietary hr new lining and existing lining shall state the
lining pipework and of other offset where the lining
5 Gunite coating hr voids grouted in the is curved to an offset
6 Annulus grouting hr course of grouting which exceeds 35 mm
annular voids. per metre.

4 Work on lateral to hr
renovated sewers
5 Work on manhole hr

6 Reinstatement 1 Landscaping sum C14 A24


2 Roads m2 Items for reinstatement Item description for
3 Pavements m2 works shall be deemed to landscaping, road and
4 Strip topsoil from m2 include connection and to pavement shall state
easement and match existing work. depth and method.
reinstate
5 Connections to sum
existing manhole
and chambers
6 Connections to sum
existing pipes, ducts
and culverts
7 Other structure sum
CLASS P: PIPE REHABILITATION WORK
CLASS Q
DRAINAGE WORK

MyCESMM2 | 111
ADDITIONAL
CLASS Q: DRAINAGE WORK MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES

Measurement covered under other classes:

Horizontal and vertical drains (included in Class G: Geotechnical work).


In situ culverts, sump and inlet/outlet (included in Class I: Concrete work).

112 | MyCESMM2
(MyCESMM2)

Brick sidewall for surface drain (included in Class J: Brickwork, blockwork


and masonry).
Malaysian Civil Engineering

In situ inlet and outlet structures (included in Class I: Concrete work).


Foundations for structures (included in Class H: Piling work and
Class I: Concrete work).

FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT

1 Excavation 1 Drain trench in earth 1 Depth: Not m M1 D1 C1 A1


exceeding 1.5 m The length of drain The depth used Items for excavation Item description for
2 Depth: 1.5 m - 2.0 m m excavation shall be for classification of shall be deemed to excavation shall identify
Standard Method of Measurement ̵ Second Edition

3 Depth: 2.0 m - 2.5 m m measured along the excavation shall be include preparation the commencing
4 Depth: 2.5 m - 3.0 m m centre line of the drain. measured from the of surfaces, multiple surface of each item
5 Depth: 3.0 m - 4.0 m m commencing surface to handling, disposal for work involving
6 Depth: 4.0 m - 5.0 m m M2 the inverts of the drain. of surplus excavated excavation for which the
7 Depth: 5.0 m - 6.0 m m The length of drain material (including commencing surface is
8 Depth: m excavation shall be D2 unsuitable material), also the original surface.
Exceeding 6.0 m measured up to inlet Earth shall be deemed upholding sides of
and outlet structures, to be materials other excavation, allowance A2
and to the sumps. than topsoil, natural for joints, backfilling, Item description for
hard material, rock, and removal of dead excavation shall identify
artificial hard material, services. separately excavation
or unsuitable material, which is expressly
unless otherwise stated required to be carried
in the item description. out by hand.

2 Extra over 1 Rock m3 M3 C2 A3


2 Natural hard material m3 Excavation in rock, Items for excavation Item description for
3 Artificial hard m3 artificial and natural shall be deemed to excavation shall state
material hard material shall include reinstatement the size and type of
4 Unsuitable materials m3 be measured as the works. drain and culvert.
5 Roads and m2 volume of the respective
pavements item removed within C3
the limits of drain Items for excavation in
excavation. roads and pavements
shall be deemed to
include road cutting and
reinstatement.
CLASS Q: DRAINAGE WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
1 Excavation 3 For inlet and outlet 1 Earth m3 M4 A4
structure 2 Rock m3 An isolated volume of Item description for
4 Sumps 3 Natural hard m3 rock or artificial hard extra over excavation
5 Culvert material material occurring shall state the width of
4 Artificial hard m3 within the excavation trench.
material shall not be measured
5 Unsuitable m3 separately, unless its A5
materials volume exceeds Item description for
6 Roads and m2 0.25 m³. excavation in roads
pavements and pavements shall
M5 state thickness.
Excavation in roads
and pavements
shall be measured
vertically from the
drain excavation width
and up to the external
surfaces, or to the
extended base for
sumps.

M6
Volume of excavation
in sumps shall be
measured between
their external surfaces,
or extended base,
until the limits of drain
excavation.

2 Surface drains 1 Interceptor drain m C4 A6


2 Bench/berm drain m Items for surface Item description for
3 Roadside drain m drains shall be deemed surface drains shall
4 Median drain m to include cement state the material, type,
5 Toe drain m jointing, sand and size, shape and the
6 Cascade drain m concrete beddings, thickness of the linings.
7 Monsoon drain m shuttering, struts and
8 Grass swale m weepholes. A7
Item description for
unlined surface drains
shall be so described.

A8
Item description for
cascade drains shall
state the location.

MyCESMM2 | 113
CLASS Q: DRAINAGE WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
3 Subsurface drains 1 Subsoil drain m C5 A9
2 Outlet drain m Items for subsurface Item description for
3 Drainage blanket m2 drains shall be deemed subsurface drains shall
4 Scupper drain m to include geotextiles state the material, type,
5 Slotted drain m fabric, lining and filter size, shape, spacing,

114 | MyCESMM2
(MyCESMM2)

material. pipe diameter, width


and height.
Malaysian Civil Engineering

C6
Items for outlet drain A10
shall be deemed to Item description for
include bends, filter drainage blankets shall
fabric, and concrete state the material, type
surround. and thickness.

4 Drainage to 1 Downpipes m M7 D3 C7 A11


structures above 2 Fittings to nr The length of Pipework such Items for downpipes Item description for
Standard Method of Measurement ̵ Second Edition

ground downpipes downpipes shall be as downpipes for shall be deemed to downpipes shall state
measured along their drainage of structures include fixing and the type, diameter and
centre lines, and shall to ground level shall be supply of fixing the materials of the
include the lengths classified as drainage components. components.
occupied by fittings, to structures above
with no allowance for ground.
laps.
D4
Fittings to downpipes
shall include bends,
swan necks, shoes, and
outlet fixed directly to
downpipes.

5 Drain covers 1 Precast concrete m C8 A12


2 Metal m Items for drain covers Item description for
3 Fibre reinforced m shall be deemed to drain covers shall
plastic include lifting hook/ state the type, loading
hole and all associated duties, size and
fittings. thickness.

6 Culverts 1 Precast concrete 1 Single m C9 A13


pipe 2 Twin m Items for culverts Item description for
2 Precast box 3 Triple m shall be deemed to culverts shall state the
3 Metal pipe include all joints, water class, type and the size
4 Plastic pipe stop, concrete base or diameter.
or bedding, unless
otherwise stated.
CLASS Q: DRAINAGE WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
7 Sumps 1 Brick nr C10 A14
8 Inlet/Outlet 2 Precast concrete nr Items for sumps shall Item description for
be deemed to include sumps shall state the
sand and concrete type, size, location and
bedding, cement the loading duties of
plastering, sump cover covers where required.
and other metalwork.

C11
Items for inlet/outlet
shall be deemed to
include concrete,
reinforcement, formwork,
rib-rabs, river protection
and all associated works.

MyCESMM2 | 115
CLASS Q: DRAINAGE WORK
Malaysian Civil Engineering
Standard Method of Measurement ̵ Second Edition
(MyCESMM2)

116 | MyCESMM2
CLASS R
ROADS AND
PAVINGS

MyCESMM2 | 117
ADDITIONAL
CLASS R: ROADS AND PAVINGS MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES

Measurement covered under other classes: M1 D1 C1


The width of each Subgrade preparation, Items for the work in
Earthworks (included in Class F: Earthworks). course of materials shall sub-base, road base, this class involving in
be measured at the road shoulder and situ/precast concrete
Maintenance of existing road and temporary road diversion (included in Class C: top of surface of that pavement courses shall be deemed to

118 | MyCESMM2
(MyCESMM2)

Traffic management and control). course. The areas of shall be classified as include concrete,
Temporary traffic signs and barriers, barricades, and delineators (included in manholes covers and reference to to JKR reinforcement, joints,
Malaysian Civil Engineering

Class C: Traffic management and control). other intrusions into ArahanTeknik (Jalan) formwork to form and
a course shall not be or by other relevant shape and finishes to
Fences and gates (included in Class V: Miscellaneous work).
deducted where the authorities. concrete.
Drainage (included in Class Q: Drainage work). area of the intrusion is
Geotextile and geogrid (included in Class G: Geotechnical work). less than 1 m².

FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT

1 Subgrade 1 Earth m2 C2
preparation 2 Hard material m2 The subgrade
Standard Method of Measurement ̵ Second Edition

3 Rock m2 preparation shall be


deemed to include
clearing, grabbing,
stripping top soil, the
scarifying, levelling
and compaction of the
top 300 mm of the
subgrade.

4 Stabilised subgrade 1 Lime m2 C3 A1


2 Cement m2 The subgrade Item description
3 Polymer m2 preparation on rock- for stabilised
filled embankment subgrade shall state
shall be deemed to the proportion of
include the trimming of stabilisation agent,
protruding rock above and the thickness of
final surface, filling of the subgrade to be
all cavities with lean stabilised.
concrete, and filling with
approved crushed rock
or gravel to the final
surface.
CLASS R: ROADS AND PAVINGS
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
2 Sub-base 1 Drainage layer 1 Granular material m2 D2 C4 A2
2 Sub-base course 2 Laterite m2 The granular material Items for sub-base Item description for
3 Lean concrete m2 shall be classified course, road-base sub-base shall stated
according to gradation shall be deemed to the type, thickness
limits for sub-base include chamfer spread and grade where
material in the over the full width of applicable.
standard specification the formation and to
for road works as include attainment of
expressly stated. the surface levels.

D3
Laterite material shall
be according to the
gradation limits for
gravel surfacing in the
standard specification
for road works as
expressly stated.
3 Roadbase 1 Removal of flexible m2 D4 C5 A3
surfaces The crushed Items for removal of Item description for
2 Crushed m2 aggregates shall be flexible surface shall roadbase shall state
aggregates classified according to be deemed to include the type, grade and
3 Bituminous mix m2 the gradation limits for scarifying the existing thickness of the
4 Wet mix m2 crushed aggregates roadbase before material.
roadbase in the receiving the new
standard specification roadbase material. A4
5 Stabilised roadbase 1 Lime m2 for road works as Item description
2 Cement m2 expressly stated. for stabilised
roadbase shall state
the proportion of
stabilisation agent.
4 Road shoulder 1 Earth shoulder m2 M2 C6 A5
2 Gravel shoulder The areas of sub- Earth shoulders shall Item description
3 Paved shoulders m2 base, road base and be deemed to include for road shoulders
bituminous pavement verge. shall state the size,
m2 courses for road thickness, type and
shoulder shall be material used.
measured under Class
R2**, R3**, and R5*0.
5 Bituminous 1 Removal of m2 D5 C7 A6
pavement courses flexible surface Item surface dressing Item removal of Item description for
2 Prime coat m2 material shall be in flexible surface of bituminous pavement
3 Tack coat m2 accordance with the bituminous pavement courses shall state the
gradation limits for courses shall be type and compacted
bituminous surface deemed to include thickness (where
4 Binder course 1 Asphaltic concrete m2 dressing in the scarifying the existing appropriate)
standard specification exposed surface.
for road works as
expressly stated.

MyCESMM2 | 119
CLASS R: ROADS AND PAVINGS
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
5 Bituminous 5 Wearing course 1 Asphaltic concrete m2 D6 C8 A7
pavement courses 2 Porous asphalt m2 Item bituminous Items for bituminous Item description shall
3 Stone mastic asphalt m2 pavement courses to pavement courses shall state where removal of
4 Gap graded asphalt m2 be read in conjunction be deemed to include flexible surface is to be
5 Polymer modified m2 with JKR Specification cutting of pavement done by milling.

120 | MyCESMM2
(MyCESMM2)

asphaltic concrete for Roadwork – Section and attainment of


6 Recycling 1 Hot in-place m2 4: Flexible Pavement surface level. A8
Malaysian Civil Engineering

2 Cold in-place m2 Item description for


tack coat and prime
7 Surface treatment 1 Chip seal m2
coat shall state the
2 Micro surfacing m2
spread rate of applied
3 Crack sealing m2
surface finishes.
4 Coloured m2
surfacing system
8 Regulating course t
of stated materials
6 Concrete pavement 1 Membranes below 1 Plastic sheeting m2 M3 A9
Standard Method of Measurement ̵ Second Edition

concrete 2 Bond breaker m2 The areas of additional Item description for


pavements 3 Bitumen m2 membranes in laps membranes shall state
shall not be measured. the materials and
thickness.
2 Reinforcement 1 Mild steel bar t M4 D7 C9 A10
reinforcement The mass of steel The nominal diameter Items for Item description for
2 High tensile steel t reinforcement shall stated in the item reinforcement shall bar reinforcement shall
bar reinforcement be taken as 0.785 description for bar be deemed to include state the size of the
3 High tensile steel m2 kg/m per 100 mm² of reinforcement shall labour for cutting, bars.
fabric reinforcement cross-section (7.85 t/ be the cross-sectional bending, and placing.
4 Fabric of other m2 m³). The mass of other diameter defined in MS A11
stated material reinforcing materials 146. Item description
shall be taken as stated for steel fabric
in the contract. reinforcement for
MS 145 shall state
M5 the type, number or
The mass measured letter in accordance
for reinforcement with MS 145. Item
shall include the mass description for other
of reinforcement fabric reinforcement
expressly required in shall state the material,
laps and special chairs. sizes, and nominal
mass per square metre.
M6
The mass for
reinforcement, measured
in tonne, shall be up to
two decimal places.

M7
The areas of additional
fabric reinforcement in
laps shall not be
CLASS R: ROADS AND PAVINGS

measured.
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
6 Concrete pavement 3 Carriageway slab m2 C10 A12
4 Other concrete slab m2 Items for carriageway Item description for
slab and other carriageway slab and
concrete slab shall be other concrete slab
deemed to include shall state the grade
trial mix, mixing, and thickness of the
laying, spreading, concrete and type of
formwork, treatment formwork including
at manholes and edge support used.
gullies, compaction,
finishing, curing and
surface texturing. It
also deemed to include
attainment of surface
levels.
5 Joints in concrete 1 Longitudinal joints m M8 D8 C11 A13
pavement 2 Expansion joints m Joints shall be Sleeve joints, Items for joint in Item description for
3 Construction joints m measured at location connectors and the like concrete pavements joints shall state the
4 Warping joints m where they are in bar reinforcement shall be deemed depth of joint.
5 Butt joints m expressly required. shall be classed as to include base
6 Special joints m special joints. preparation, installing A14
7 Transverse joints m dowel bars and tie Item description for
bars, debonding agent, special joints shall
joint sealing material, state the type of joint,
and saw cutting. and type and size of
the reinforcing bar.
6 Pavers 1 Interlocking m2 C12 A15
concrete block Items for pavers shall Item description for
2 Concrete flags m2 be deemed to include pavers shall state type,
3 In situ concrete m2 base preparation, size, thickness and
pavers sand bedding, lay in whether it is precast or
specified interlocking in situ.
pattern, edge segment,
joints and cutting.
7 Kerbs, channels 1 Precast concrete m M9 C13 A16
and edgings kerbs Excavation and filling Items for kerbs, Item description for
2 In situ concrete m for kerbs, channels channels, and edgings kerbs, channels, and
kerbs and edgings shall be shall be deemed to edgings shall state the
3 Concrete edgings m classed as earthworks include beds, backings, type and size.
4 Concrete channels m (Class F). reinforcement, joints
and cutting. A17
Item description for
in situ concrete kerbs,
concrete channels,
and concrete edgings
shall state the use of
slip-form, if expressly
required.

MyCESMM2 | 121
CLASS R: ROADS AND PAVINGS
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
8 Road furniture 1 Signage 1 Non-illuminated nr C14 A18
retro-reflective Post-mounted Item description for
2 Illuminated nr signage shall be signage mounted on
3 Electronic m2 deemed to include gantry shall be so
foundation, support stated.

122 | MyCESMM2
(MyCESMM2)

post, excavation,
preparation of surfaces, A19
Malaysian Civil Engineering

disposal of excavated Item description for


materials, upholding signage shall state the
sides of excavation, material grade, size,
backfilling, concrete, and diagram number
reinforcement and taken from JKR
joints. ArahanTeknik (Jalan)
or by other relevant
authorities.
2 Pavement 1 Letters and shapes nr M10 D9 A20
Standard Method of Measurement ̵ Second Edition

markings 2 Continuous line m Lengths measured The colour of the Item description for
3 Intermittent line m for linear pavement pavement markings, pavement markings
4 Chevron marking m2 markings shall not shall be deemed to be shall state the material
include gaps in white unless otherwise grade, size, and
intermittent line. stated. diagram number taken
from JKR ArahanTeknik
M11 (Jalan) or by other
Area measured for relevant authorities.
chevron marking shall
be the gross area. A21
Item description for
pavement markings
shall state the
shape, type, e.g.
thermosetting plastic,
and colour if required.

A22
Item description
shall sate temporary
pavement markings
and its subsequent
removal.
3 Delineators 1 Chevron nr A23
2 Delineator posts nr Item description for
3 Roadstud nr delineators shall state
the type, size and
colour.
CLASS R: ROADS AND PAVINGS
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
8 Road furniture 4 Traffic barrier 1 New Jersey barrier m M12 C15 A24
2 Wire rope m The length of traffic Items for guardrail Item description for
3 Guardrail m barrier shall be and wire rope shall be traffic barrier shall
4 Guardrail nr measured overall, no deemed to include the state excavation in
end-treatment deduction shall be supply and installation rock, where applicable.
5 Pedestrian barrier m made for the gaps for of corrugated guardrail
6 Concrete barrier nr street lightings poles, beam and wire rope A25
sign and gantries. inclusive of bolts, Item description for
nuts, posts, and other New Jersey barrier
ancillary work. shall state the type and
dimension.
C16
Items for guardrail A26
end-treatment shall be Item description for
deemed to include the New Jersey barrier
supply and installation shall state the use of
inclusive of bolts, slip form, if expressly
nuts, posts and other required.
ancillary work.
A27
Item description of
guardrail shall state the
type and thickness of
beam element, type of
post, and post spacing.

A28
Item description
for guardrail end-
treatment shall state
the type of treatment.

MyCESMM2 | 123
CLASS R: ROADS AND PAVINGS
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
8 Road furniture 5 Miscellaneous 1 Crash cushion nr C17 A29
2 Crash barrier nr Items for crash Item description of
3 Kilometre post nr cushion, crash barrier, crash cushion, crash
4 Hectometre marker nr kilometre post, barrier, kilometre post,
5 Anti-glare screen m hectometre marker, hectometre marker,

124 | MyCESMM2
(MyCESMM2)

6 Noise barrier m anti-glare screen,noise anti-glare screen, noise


7 Right of way nr barrier, and right of barrier, and right of
Malaysian Civil Engineering

marker way marker shall be way marker shall state


deemed to include the the size, type and
supply and installation material.
of the said items
inclusive of bolts, A30
nuts, posts and other Item description of
ancillary work required crash barrier, crash
for the completion of barrier, kilometre post,
the work. anti-glare screen, noise
barrier, and right of
Standard Method of Measurement ̵ Second Edition

way marker shall state


excavation in rock,
where applicable.

6 Gantry nr C18 A31


Items for gantry shall Item description for
be deemed to include gantry shall state the
fabrication, installation, type, materials and
foundation work principal dimensions.
and protective and
decorative surface
treatment.
CLASS R: ROADS AND PAVINGS
CLASS S
TUNNEL WORK

MyCESMM2 | 125
ADDITIONAL
CLASS S: TUNNEL WORK MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES

Measurement covered under other classes: C1


Plant and equipment
shall be deemed to
External stabilisation work (included in Class G: Geotechnical work). include the purchase
Micro tunnelling for pipework (included in Class O: Pipework). cost, factory

126 | MyCESMM2
(MyCESMM2)

acceptance test,
External drainage system (included in Class Q: Drainage work).
assembly and
Malaysian Civil Engineering

Excavation, filling, and turfing for external work (included in Class F: Earthworks). transportation to site
Cut and cover tunnel (included in Class F: Earthwork and Class I: Concrete work). including maintenance
cost.
Temporary wastewater treatment facility (included in Class B: Environmental
protection and enhancement).
Ground investigation (included in Class D: Site investigation work).
Relocation of services (included in Class E: Demolition and site clearance and
Class O: Pipework).
Standard Method of Measurement ̵ Second Edition

FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT

1 Temporary 1 Facilities 1 Power supply sum C2 A1


requirements system Items for temporary Item description for
for Tunnel Boring 2 Water supply and/ sum facilities shall be temporary launch/
Machine or treatment system deemed to include all retrieval shaft shall
3 Ventilation system sum provision as expressly state the number of
4 Lighting system sum required. shaft.
5 Compressed air sum
system C3
6 Telecommunication sum Items for temporary
system foundation for surface
7 Dewatering system sum plant and equipment
shall be deemed to
include all provision
2 Foundation for sum
as expressly required
surface plant and
to complete the work.
equipment
Including excavation,
piling, geotechnical,
concreting, formwork,
reinforcement, removal,
reinstatement and
make good upon
completion.
CLASS S: TUNNEL WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
1 Temporary 3 Launch shaft sum C4 A2
requirements 4 Retrieval shaft sum Items for launching Item description for
for Tunnel Boring 5 Launching facilities sum facilities and retrieval launching facilities
Machine 6 Retrieval facilities set facilities shall be and retrieval facilities
deemed to include shall state the thrust
retaining structure frame, blind steel
for shaft, excavation, ring, pressure ring,
temporary support temporary structure,
for shaft, reinforced temporary support
concrete, backfill and frame, shield cradle,
all other necessary sealing system,
materials required to tunnel break in/break
complete the work out facilities and all
including reinstatement necessary temporary
and make good upon support and structures.
completion.
2 Plant and 1 Mobilisation and sum C5 A3
equipment demobilisation Items for mobilisation Item description for
and demobilisation mobilisation and
shall be deemed to demobilisation state
include provision of the conditions on
all plant, equipment how remobilisation is
and ancillaries, required.
transportation to
the site and removal
off the site upon the
completion of the
operation.

2 Tunnel boring 1 Earth pressure set C6 A4


machine balance Items for tunnel boring Item description for
2 Slurry set machine shall be tunnel boring machine
3 Rock set deemed to include the shall state the back-
4 Variable density set back-up system for up system for tunnel
5 Hybrid set tunnel boring machine. boring machine.

3 Surface plant and 1 Slurry treatment set C7 A5


equipment plant Items for surface plant Item description for
2 Grout batching set and equipment shall tunnel boring machine
plant be deemed include ancillary equipment
3 Water chiller plant set transportation to shall state the type of
4 Medical lock set the site handling, plant and equipment to
5 Silo and storage set assembling which be used.
tank include all necessary
6 Lifting crane set piping and electrical
7 Ancillary equipment set work and removal off
site after completion of
operation as expressly
stated.

MyCESMM2 | 127
CLASS S: TUNNEL WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
2 Plant and 4 Transportation 1 Locomotive and sum C8
equipment system rolling stock Items for locomotive
2 Multi service vehicle set and rolling stock shall
3 Conveyor belt set be deemed to include
system the rail for transport of

128 | MyCESMM2
(MyCESMM2)

locomotive and rolling


stock shall be including
Malaysian Civil Engineering

removal of rail after


completion.
3 Excavation 1 Bored tunnel by 1 Single track m M1 C9 A6
tunnel boring 2 Twin track m The volume measured Items for bored tunnel Item description for
machine for excavation shall shall be deemed to bored tunnel shall state
be the payment lines include all plants and the external diameter.
shown on the drawings equipment during
or, where no payment tunnel construction, A7
lines are shown, to major and minor tunnel Item description of
Standard Method of Measurement ̵ Second Edition

the nett dimensions boring machine, wear disposal of excavated


of the volume to be and tear parts, grease, material shall state
excavated. lubricants, setting the location of the
up and connection approved dumping
for all temporary site.
electrical and
mechanical system,
connection of water
and electical supply,
including treatment,
multiple handling and
disposal of excavated
materials off site or to
designated area.
2 Tunnel 1 Earth m3 C10 A8
3 Shaft 2 Natural hard m3 Items for excavation Item description for
4 Other underground material shall be deemed to excavation in rock shall
space 3 Rock m3 include all alignment state the method of
4 Artificial hard m3 and inclination. blasting and whether for
material reuse or disposal.
5 Unsuitable material m3 C11
Items for excavation A9
shall be deemed to Item description for
include scaling, washing other underground
down, multiple handling, space shall state the
disposal off site or to dimensions of the space.
designated area.

C12
Items for excavation
shall be deemed to
include over break and
backfill with concrete,
CLASS S: TUNNEL WORK

shotcrete, mortar and


grout.
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
3 Excavation 5 Enlarged 1 Assembly and sum C13
tunnel section dismantle yard Items for enlarged
2 Vehicle turning sum tunnel section shall
3 Switching station sum be deemed to include
4 Transformer bay sum all necessary tunnel
5 Pump sump sum support and backfilling
with approved materials
to design profile after
completion of tunnel
work.
6 Drilling 1 Probe ahead hole m C14 A10
2 Drain hole m Items for drilling probe Item description for
3 Grout hole m ahead hole, drain hole drilling shall state the
and grout hole shall length and diameter of
be deemed to include hole.
installation of pipe as
expressly required.
7 Grouting 1 Surface m3 M2 A11
The mass measured for Item description for
injection of grouting grouting shall state
materials shall be the type and mix of
taken from the surface grouting material.
4 In situ lining 1 Shotcrete 1 Mass m2 M3 D1 C15 A12
2 Reinforced m2 The area for shotcrete Shotcrete shall be Items for shotcrete Item description for
shall be measured defined as expressly shall be deemed to shortcrete shall state
at the payment lines required. include smoothing the the nominal thickness
shown on the drawings surface as expressly and class of surface
or, shown to the nett required. finish.
dimension of lining to
be provided. A13
Item description for
reinforced shotcrete
shall state thickness and
the reinforcing material
added to the mix.

A14
Item description for
shotcrete reinforced
with fibres, shall state
the dosages of the
fibres added to the mix.

2 In situ concrete 1 Mass m3 M4 A15


2 Reinforced m3 The volume for cast in Item description for
situ concrete shall be in situ concrete shall
the nett dimension of state admixtures where
the lining volume. required.

MyCESMM2 | 129
CLASS S: TUNNEL WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
4 In situ lining 3 Reinforcement 1 Mild steel bar t M5 D2 C16 A16
2 High tensile steel t The mass of steel The nominal diameter Items for reinforcement Item description for bar
bar reinforcement shall be stated in item shall be deemed to reinforcement shall state
3 High tensile steel m2 taken as 0.785 kg/m per description for bar include labour for the size of the bars.
fabric 100mm² of the cross- reinforcement shall cutting, bending, and

130 | MyCESMM2
(MyCESMM2)

4 Fabric of other m2 section (7.85 t/m³). be the cross-sectional placing. A17


stated material The mass of the other diameter defined in MS Item description
Malaysian Civil Engineering

reinforcing materials 146. for steel fabric


shall be taken as stated reinforcement shall
in the contract. state the material, size
and nominal mass per
M6 square metre.
The mass measured for
reinforcement shall
include the mass of
reinforcement, expressly
required in laps and
Standard Method of Measurement ̵ Second Edition

special chairs.

M7
The areas of additional
fabric reinforcement
in laps shall not be
measured.

4 Formwork m2 M8 C17
Formwork shall be the Items for formwork
nett surface of in situ shall be deemed to
concrete. include travel steel
form for all inclinations,
alignment and end form
to the construction joint
form for all inclinations,
alignment, and end form
to the construction joint.

5 Waterproofing 1 Waterstop m M9 D3 C18 A18


2 Membrane m2 The length of waterstop Membrane shall be a Items for waterstop Item description for
shall be measured along layer of impermeable shall be deemed to waterproofing shall
their centre lines. materials installed in the include cutting, jointing state the type of
tunnel before placing and special fittings at materials and size.
M10 in situ concrete or angles and junctions.
The area for membrane shotcrete, either using
shall be the nett area. sheet C19
Lapping shall not be system, to keep water Items for membrane
measured. from entering. shall be deemed to
include cutting, jointing
and lapping.
CLASS S: TUNNEL WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
4 In situ lining 6 Cross passage nr D4 C20
Cross passage is a Items for cross passage
tunnel connecting shall be deemed to
between tunnels for include excavation,
the purpose of exit/ grouting, lining works
emergency movement. tunnel support, backfill,
instrumentation, finishes
and all necessary
works to complete the
construction.
5 Preformed lining 1 Concrete lining 1 Precast segmental m M11 C21 A19
ring The length of Items for preformed Item description for
preformed lining shall concrete lining shall precast segmental
be measured along the be deemed to include ring shall state the
axis. reinforcement/ steel internal diameter and
fibre/polypropylene thickness.
fibre, formwork,
2 Steel lining m M12 packing, caulking, joint A20
3 Cast iron lining m Volume for annulus seal, finished, bolt and Item description for
4 Ductile iron lining m grouting shall be the nut, waterstop and steel, cast iron and
5 Annulus grouting m3 nett volume of gap preformed threaded ductile iron lining
between the lining and grout holes. shall state the grade,
the excavation profile. thickness and internal
C22 diameter.
Items for steel, cast
iron, ductile iron lining A21
shall be deemed to Item description for
include cutting and annulus grouting shall
jointing internal and state the type of grout
external. material.

C23
Items for annulus
grouting shall be
deemed to include
corrosion protection,
stiffener, fish tails, and
purpose made holes.
6 Tunnel support 1 Steel support 1 Steel rib t M13 C24 A22
The areas of additional Items for the steel Item description for
fabric reinforcement support shall be steel support and
in laps shall not be deemed to include all lagging shall state
measured. necessary accessories the dimensions and
such as tie rod, end nominal mass.
plate, bolts and nuts.
2 Lagging 1 Steel section t A23
2 Steel plate t Item description for
3 High tensile steel m2 permanent tunnel
fabric reinforcement support shall be
measured separately.

MyCESMM2 | 131
CLASS S: TUNNEL WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
6 Tunnel support 3 Bolting 1 Rock dowel nr C25 A24
2 Rock bolt nr Items for bolting shall Item description for
3 Pull out test nr be deemed to include bolting shall state the
all provision as expressly length and diameter.
required.

132 | MyCESMM2
(MyCESMM2)

4 Shotcrete 1 Plain m2 M14 A25


2 Reinforced m2 The areas for shotcrete Item description for pull
Malaysian Civil Engineering

and fibre mortar shall out test shall state the


be the nett area of type of bolt, diameter,
surface to be supported. length and test load.
No allowance shall
be made for uneven A26
5 Fibre mortar m2 surfaces. Item description for
fibre mortar shall state
the nominal thickness.

A27
Standard Method of Measurement ̵ Second Edition

Item description for fore


poling shall state the
6 Fore poling 1 Dowel bar nr length and diameter of
2 Canopy tube nr the dowel bar.

A28
Item description for
canopy tube system shall
state length, diameter
and thickness of tube.
7 Backfill 1 Invert 1 Concrete m3 M15 A29
2 Behind lagging 2 Shotcrete m3 Volume for backfill shall Item description for
3 Other underground 3 Mortar m3 be the nett dimension invert shall state the
space 4 Grout m3 of volume to be filled. principal dimension.
5 Tunnel muck m3 Backfill to over break
shall not be measured.

M16
Item for backfill behind
lagging shall be the
nett volume of gap
between the lagging
and the nett excavation
profile.
8 Tunnel 1 Convergence nr C26 A30
Instrumentation measurement Items for tunnel Item description for tunnel
2 Settlement nr instrumentation shall be instrumentation shall state
deemed to include all the specification detail.
measurement
provision and accessories
3 Stress 1 Strain gauge nr as expressly required.
measurement 2 Pressure cell nr
3 Inclinometer nr
4 Pneumatic nr
piezometer
CLASS S: TUNNEL WORK
CLASS T
RAIL TRACK

MyCESMM2 | 133
ADDITIONAL
CLASS T: RAIL TRACK MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES

Measurement covered under other classes: C1 A1


Items for supplying Item description for
Earthwork, sub-grade preparation and sub-ballast (included in shall be deemed to supplying shall state
Class F: Earthworks). include delivery and all the location of delivery
necessary associated where expressly

134 | MyCESMM2
(MyCESMM2)

Geotextile and geogrid (included in Class G: Geotechnical work). components to site. required.
Concrete track foundations (included in Class I: Concrete work).
Malaysian Civil Engineering

FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT

1 Supplying 1 Track foundation 1 Bottom ballast m3 M1 D1 A2


2 Top ballast m3 The volume of top Ballast below the Item description for
3 Waterproofing m2 ballast measured shall soffit level of sleepers, supplying bottom and
membrane include the volume timbers or bearers of a top ballast shall state
occupied by sleepers. track shall be classed the type of material
as bottom ballast. and grading.
M2
Standard Method of Measurement ̵ Second Edition

Sub ballast shall be D2 A3


measured under Class Ballast above the Item description for
F34*. underside of the waterproof membrane
sleepers, timbers shall state the type,
or bearers shall be grade and technical
classed as top ballast. specification.

2 Rails 1 Flat bottom rails/ t M3 A4


running rails The mass measured Item description for
2 Check and guard t for supplying of rails supplying of rails shall
rails shall exclude the state either the section
3 Twist rail pr mass of twist rails and reference and the mass
4 Combination rails pr combination rails. per metre, or the cross-
sectional dimensions
and the mass per
metre.

3 Sleepers 1 Timber nr A5
2 Concrete nr Item description for
3 Steel nr supplying of sleepers
4 Special type nr shall state the type,
size and identify
the fittings which
are attached by the
supplier.
CLASS T: RAIL TRACK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
1 Supplying 4 Conductor 1 Mass, not exceeding m C2 A6
rails 20 kg/m Items for supplying Item description for
2 Mass, 20 - 30 kg/m m of conductor rails supplying of conductor
3 Mass, 30 - 40 kg/m m shall be deemed to rails shall state the
4 Mass, 40 - 50 kg/m m include guard boards, type.
5 Mass, exceeding m fixings, bolts, nuts,
50 kg/m screws, washers,
insulating bushes,
cable terminals, rail
insulators, rail supports,
rail expansion joints,
ramps (high/low
speed), covers and
packing.
5 Fittings 1 Chairs nr M4 C3 A7
2 Baseplates nr Fishplates and Items for supplying Item description for
3 Rail fastenings nr rail joints shall be of fittings shall be supplying of fittings
4 Plain fishplates nr measured by number deemed to include shall state the type.
5 Insulated fishplates nr of pairs. fixings, keys, clips,
6 Insulated rail joints nr washers, bolts, nuts,
7 Glued insulated rail nr screws, insulating
joints bushes, spikes, ferrules,
track circuit insulator,
shoulders, pads, shims,
baseplates, inserts and
packing.
6 Turnouts set C4 A8
7 Diamond crossing set Items for supplying of Item description for
turnouts and diamond supplying of turnouts
crossing shall be and diamond crossing
deemed to include shall state the type,
timbers, fittings and type of joint and
check rails. length.
2 Supplying 1 Sundries 1 Buffer stops nr A9
2 Wheel stops nr Item description for
3 Lubricators nr supplying of sundries
4 Switch levers nr shall state the type
5 Rail expansion joints pr
6 Jumper cables nr A10
7 Traction rail bonds nr Item description for
8 Signalling rail bonds nr supplying of buffer
2 Sundries 1 Stray current nr stops shall state their
continuity cables approximate weight.
2 Cross track ducts nr
A11
Item description for
supplying of cross track
ducts shall state their
duct size and length.

MyCESMM2 | 135
CLASS T: RAIL TRACK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
2 Supplying 3 Rail furniture 1 Kilometers markers nr A12
2 Change of nr Item description
geometry, for supplying of rail
horizontal and furniture shall state the
vertical markers type.

136 | MyCESMM2
(MyCESMM2)

3 Turnout markers nr
4 Track slab markers nr
Malaysian Civil Engineering

5 Conductor rail nr
support marker
6 Fouling point nr
markers
7 Level crossing nr
4 Cable trough 1 In situ m C5 A13
2 Precast m Items for supplying Item description for
of cable trough shall supplying of cable
be deemed to include trough shall state the
Standard Method of Measurement ̵ Second Edition

the cable trough type and size.


lid, reinforcement,
concrete, formworks,
jointing.

5 Emergency 1 Side walkway m M5 C6 A14


walkway 2 Centre walkway m Emergency walkway Items for supplying of Item description
shall be measured nett emergency walkway for supplying of
across the walkway shall be deemed to emergency walkway
ramps. include all required shall state the type and
fittings, fixings, fixtures details.
and accessories
including walkway slab,
handrails and cable
containment.

3 Laying 1 Track foundation 1 Bottom ballast m3 M6 D3 C7 A15


2 Top ballast m3 The volume of top Ballast below the Items for laying of Item description for
3 Waterproofing m2 ballast measured shall soffit level of sleepers, bottom ballast shall laying bottom and
membrane include the volume timbers or bearers of a be deemed to include top ballast shall state
occupied by sleepers. track shall be classed laying of ballast using the type of material,
as bottom ballast. a ballast box and grading requirements
compaction of ballast. and thickness.
D4
Ballast above the C8
underside of the Items for laying of
sleepers, timbers top ballast shall be
or bearers shall be deemed to include
classed as top ballast. regulating and tamping
of ballast.
CLASS T: RAIL TRACK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
3 Laying 2 Rails 1 Flat bottom rails/ m M7 C9 A16
running rails The length of laying of Item for laying of rails Item description for
2 Check and guard m rails shall be measured shall be deemed to laying of rails shall
rails along the centre line include all necessary state transportation
3 Twist rail pr of the track (two rail) works carried out in and location when rails
4 Combination rails pr including the length accordance with the are not to be supplied
occupied by turnouts specification. by the contractor.
and diamond crossing.
A17
M8 Item description
The length of laying for laying of rails
check and guardrails shall state the pre-
shall be measured fabricated lengths of
along the length of the each member.
rail (one rail).
A18
Item description for
laying of rails shall
state either the section
reference and the mass
per metre, or the cross-
sectional dimensions
and the mass per
metre.

3 Sleepers 1 Timber nr C10 A19


2 Concrete nr Items for laying Item description for
3 Steel nr of sleepers shall laying of sleepers shall
4 Special type stated nr be deemed to state the type, the size,
include, distribution, and identify the fittings
adjustment and laying. which are attached by
the supplier.

4 Conductor rails 1 Mass, not exceeding m M9 C11 A20


20 kg/m The length of laying of Items for laying of Item description for
2 Mass, 20 - 30 kg/m m conductor rails shall conductor rails shall laying of conductor
3 Mass, 30 - 40 kg/m m be measured along the be deemed to include rails shall state the
4 Mass, 40 - 50 kg/m m length of the rail (one fixings, bolts, nuts, type and jointing
5 Mass, exceeding m rail). screws, washers, method.
50 kg/m insulating bushes,
cable terminals, rail
insulators, rail supports,
rail expansion joints,
ramps (high/low
speed), covers and
packing.

MyCESMM2 | 137
CLASS T: RAIL TRACK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
3 Laying 5 Fittings 1 Chairs nr M10 C12 A21
2 Baseplates nr Fishplates and Items for laying Item description for
3 Rail fastenings nr rail joints shall be of fittings shall be laying of fittings shall
4 Plain fishplates nr measured by number deemed to include state the type.
5 Insulated fishplates nr of pairs. fixings, keys, clips,

138 | MyCESMM2
(MyCESMM2)

6 Insulated rail joints nr washers, bolts, nuts,


7 Glued insulated nr screws, insulating
Malaysian Civil Engineering

rail joints bushes, spikes, ferrules,


track circuit insulator,
shoulders, pads,
shims, baseplates,
inserts, packing and all
required fittings, fixing
and accessories.

6 Welded joints 1 Flash butt nr C13 A22


2 Alumino thermic nr Items for laying of Item description for
Standard Method of Measurement ̵ Second Edition

3 Gas pressure nr flash butt welded laying of welded joints


joints, alumino thermic shall state the rail
welded joints and section and the type of
gas pressure shall be weld.
deemed to include
welding kits.

7 Turnouts set C14 A23


8 Diamond crossing set Items for laying of Item description for
turnouts and diamond laying of turnouts and
crossing shall be diamond crossings
deemed to include shall state their type,
timbers, fittings, and type of joint and
check rails. length.

4 Laying 1 Sundries 1 Buffer stops nr C15 A24


2 Wheel stops nr Items for laying of Item description for
3 Lubricators nr sundries shall be laying of sundries shall
4 Switch levers nr deemed to include state the type.
5 Rail expansion pr all required fittings,
joints fixings, fixtures and A25
6 Jumper cables nr accessories. Item description
7 Traction rail bonds nr for laying of buffer
8 Signalling rail nr stops shall state their
bonds approximate weight.

A26
Item description for
laying of cross track
ducts shall state their
duct size and length.
CLASS T: RAIL TRACK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
4 Laying 2 Sundries 1 Stray current nr
continuity cables
2 Cross track ducts nr

3 Rail furniture 1 Kilometers markers nr C16 A27


2 Change of nr Items for laying of Item description for
geometry, rail furniture shall be laying of rail furniture
horizontal and deemed to include shall state the type.
vertical markers all required fittings,
3 Turnout markers nr fixings, fixtures and
4 Track slab markers nr accessories.
5 Conductor rail nr
support marker
6 Fouling point nr
markers
7 Level crossing nr

4 Cable trough 1 In situ m C17 A28


2 Precast m Items for laying of Item description for
cable trough shall be laying of cable trough
deemed to include the shall state the type.
cable trough lid.

5 Emergency 1 Side walkway m M11 C18 A29


walkway 2 Centre walkway m Emergency walkway Items for laying of Item description for
shall be measured nett emergency walkway laying of emergency
across the walkway shall be deemed to walkway shall state the
ramps. include all required type.
fittings, fixings, fixtures
and accessories
including walkway slab
and cable containment.

MyCESMM2 | 139
CLASS T: RAIL TRACK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
5 Dismantling 1 Flat bottom rails 1 Plain track m M12 C19 A30
2 Turnouts nr The length of Items for dismantling Item description
3 Diamond crossings nr dismantling of shall be deemed to for dismantling of
plain track shall be include taking up, work from which
measured along the lifting, packing and the materials arising

140 | MyCESMM2
(MyCESMM2)

centre line of the track slewing. remain the property


(two rail) taken over all of the employer shall
Malaysian Civil Engineering

roads and shall exclude C20 be stated as well as


lengths occupied by Items for dismantling the handing over and
turnouts and diamond of plain track shall be location of storage.
crossings. deemed to include Where the so stated
opening out, packing materials are to be
and boxing in with salvaged by the
ballast and insertion of contractor, a separate
closure rails. bill for the credit of the
employer shall be so
C21 described.
Standard Method of Measurement ̵ Second Edition

Items for dismantling


2 Check and guard m M13 of turnouts and A31
rails The lengths of diamond crossings Item description for
3 Conductor rails m dismantling of shall be deemed to dismantling of plain
checkrail and include checkrail, track shall state the
guardrails and guardrail and approximate weight
conductor rails shall conductor rails. of taking up, details of
be measured along the disposal of the track
lengths of the rail (one and the type of rail,
rail) and shall exclude sleeper and joint.
lengths within turnouts
and diamond crossings

4 Sundries 1 Buffer stops nr M14 A32


2 Wheel stops nr Dismantling of Item description for
3 Lubricators nr switch levers shall be dismantling of buffer
4 Switch levers nr measured from the stops shall state
toes of switches. their approximate
weight and type of
construction.

A33
Where extra ballast
is required, item
description for
dismantling shall be
stated.
CLASS T: RAIL TRACK
CLASS U
MECHANICAL AND
ELECTRICAL WORK

MyCESMM2 | 141
ADDITIONAL
CLASS U: MECHANICAL AND ELECTRICAL WORK MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES

Measurement covered under other classes: D1 C1 A1


Items for mechanical Items for mechanical Item description
Concrete structures (included in Class I: Concrete work). and electrical work and electrical work for mechanical and
supplied and installed shall be deemed to electrical work shall
Valve chambers and thrust blocks (included in Class I: Concrete work). shall comply with the include supply, deliver, state the location,

142 | MyCESMM2
(MyCESMM2)

Valves (included in Class O : Pipework). respective employer’s and install all fittings type of services and
specification. and accessories and reference to the
Malaysian Civil Engineering

any modification works drawings.


D2 to authority’s approval.
Items for electrical A2
supplied and installed C2 Item description
shall be rated for the Items for mechanical for mechanical and
intended voltage and and electrical work electrical work shall
in accordance with the shall be deemed to state the type, material,
relevant and latest IEC include mimic-panel, size, thickness, design
Standards. tagging, labelling, capacity, method of
and painting where fixing and reference
Standard Method of Measurement ̵ Second Edition

D3 necessary. given to applicable


Items for electrical specifications and
systems shall be C3 specified qualities.
fire rated, weather Items for mechanical
proof, waterproof and and electrical work
explosion proof as shall be deemed to
expressly stated. include all ancillary
works as expressly
stated.
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT

1 Ducted services 1 Circular ductwork 1 Straight m M1 A3


2 Rectangular 2 Curved m Lengths of ducted Item description for
ductwork 3 Fittings nr and cabled services circular ductwork and
3 Flexible ducting 4 Insulation m work systems shall be flexible ducting shall
measured along the state the diameter.
centre line including
lengths occupied by
fittings.
2 Cabled services 1 Cables/conductors 1 Laid/drawn into m
conduits, trunking
or duct
2 Laid on trays m
3 Fixed to surfaces m
4 Laid in trenches m
5 Suspended m
6 Busbar trunking/ m
busduct

2 Conduits 1 Plain m
2 Flexible m
3 Box fittings nr
CLASS U: MECHANICAL AND ELECTRICAL WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
2 Cabled services 3 Final circuit 1 Cable only m C4
2 Cable and conduit m Items for lighting/
3 Lighting/power point nr power point deemed
4 Trunking 1 Plain m to include the cable,
2 Fittings m cable containment,
3 Busbar trunking m and other necessary
accessories.
5 Earthing and 1 Tape m
bonding 2 Fittings nr
6 Accessories 1 Trays m
2 Switches nr
3 Lighting outlets nr
4 Sockets nr
3 Air conditioning 1 Direct expansion 1 Window AC unit nr
and mechanical system air 2 Single Split nr
ventilation conditioning Compressor
3 Multi Split nr
Compressor
4 Fan Coil nr
5 Air Handling Unit nr
2 Precision air 1 Direct expansion nr
conditioning 2 Chilled water nr
3 Centralised system 1 Air side handling unit nr
air conditioning 2 Air side fan coil unit nr
3 Chiller nr
4 Cooling tower nr
5 Water treatment nr
system
4 Fan 1 Propeller nr D4 A4
2 Axial nr Items for fan shall be Item description for fan
3 Forward curved nr categorised as radial/ shall state the rating.
impeller propeller, centrifugal
4 Backward curved nr axial, centrifugal
impeller forward, etc.
5 Radial type impeller nr
6 Airfoil type impeller nr
5 Accessories 1 Insulation m2 C5
2 Filter nr Items for grilles shall
3 Diffuser nr be deemed to include
4 Air grille nr termination box, air
5 Acoustic grille nr dampers (where
6 Variable volume box nr relevant) and with
7 Silencers nr or without acoustic
8 Louvers nr insulation.
6 Dampers 1 Fire damper nr D5
2 Volume control nr Items for fire damper
3 Isolation nr shall be categorised as
electric actuator, fusible
link or pneumatic.

MyCESMM2 | 143
CLASS U: MECHANICAL AND ELECTRICAL WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
4 Fire fighting 1 Portable fire 1 Dry powder nr
extinguisher 2 Carbon dioxide nr
3 Others nr
2 Fire detection and 1 Conventional/ sum A5
alarm system addressable Item description for

144 | MyCESMM2
(MyCESMM2)

2 Linear heat sum linear heat detection


detection shall identify and state
Malaysian Civil Engineering

3 Centralised nr the type for linear heat


monitoring system detector cable.

3 Total flooding fire 1 Gas kg C6 A6


extinguishing 2 Gas cylinder nr Items for fire fighting ltem description for
system/wet 3 Cylinder strap nr shall be deemed total flooding fire
chemical system 4 Outlet adapter nr to include groove extinguishing system/
5 Cylinder valve nr coupling, groove wet chemical system
6 Emergency nr end cap, bracket, shall state the type of
Standard Method of Measurement ̵ Second Edition

release handle junction box, flexible gas.


7 Nozzle nr connectors, strainers,
steel section, jointing
and other accessories.

4 Total flooding fire 1 Control panel nr D6 C7


extinguishing 2 Warning light nr ltems for control Items for control panel
system/wet 3 Flashing/ nr panel shall be stated shall be deemed to
chemical system warning sign as temperature include conduit, cable,
4 Alarm bell nr controllers, trunking or trays as
5 Manual release nr thermostate, control required.
switch panels, motor starter
panels.

5 Accessories 1 Breeching inlet nr D7 C8


2 Manual selection nr Items for control panel Items for control panel
switch shall be categorised as shall be deemed to
3 Pressure gauge nr manually or automatic. include built-in battery
4 Pressure switch nr and charger and other
5 Mechanical tee nr accessories and any
6 Interface terminal nr modification works.
box
7 Fire shutter nr
8 Flashing beacon nr
6 Accessories 1 Alarm valve static nr C9
2 Sprinkler nozzle nr Items for hose reel set
3 Hose reel set nr deemed to include
4 Cabinet nr drums, swivel arm,
5 Landing valve nr cradle, hose and nozzle.

C10
Items for landing valve
deemed to include
CLASS U: MECHANICAL AND ELECTRICAL WORK

coupling.
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
5 Piped services 1 Accessories 1 Pressure vessel nr M2 C11 A7
2 Multimedia filter nr Piped services Items for piped Item description for
3 Particle diverter nr measured over all pipe services shall piped services shall
4 First flush device nr fittings, short running be deemed to include state diameter and
5 Basket strainer nr lengths and branches all fittings, jointing, jointing method
6 Oil & grease nr in linear metres. fixing and perforating
Interceptor the pipe or flange. A8
Item description for
2 Pipework 1 Cold water sum M3 C12 purpose made and
plumbing system Item description for Items for storage tank bare piped services
2 Soil and waste sum flexible pipes and shall be deemed to shall be stated.
plumbing system extensible pipes include supporting
3 Sanitary appliances sum (measured as fully frame. A9
and fittings extended) shall be Item description for
4 Recycle water sum stated. pipework in or fixed
plumbing system in ducts, trenches and
5 Rain water sum chases or embedded
harvesting system in in situ concrete or
6 Gas pipe sum screeds shall be stated.
7 Storage tank nr
3 Septic Tank 1 Cast in situ concrete nr C13 A10
2 Pre-fabricated nr Items for septic tanks Item description for
shall be deemed to septic tank shall state
include foundation, the capacity in term of
excavation, upholding population.
sides of excavation,
bedding, installation,
backfilling and all other
related work where
expressly required.
6 Electrical services 1 High voltage (33 kV 1 Cables/ sub-main m M4 D8 C14 A11
and above) 2 Compact nr The acoustic system for The electrical services Items for uninterruptible Item description for
incoming services/ sub-station generator room shall be standby equipment electrical power supply electrical services shall
main installation 3 Metering kiosk nr measured separately supplied and installed supplied and installed state the spacing and
4 Final sub-circuits nr under their respective shall be inclusive shall be deemed to voltage.
5 Ducts and nr classes of work. of diesel generator, include of batteries,
2 Medium voltage
manholes alternator, Automatic UPS module, coupling
(1 kV up to 33 kV)
6 Lightning nr Mains Failure (AMF) panels, isolation
main installation
protection/earthing panels and all other transformer and
required accessories. all other required
accessories.
3 Low voltage
(up to 1 kV) M5 D9 C15
main installation Electronic motor starter The electrical services Items for electrical
shall be measured in voltage categorisation services shall be
number inclusive of shall be in accordance deemed to include
enclosure and all other to IEC classification. supporting brackets,
required accessories covers, tap-off/feeder
where expressly stated. units, fire barriers,
earthing conductors,

MyCESMM2 | 145
CLASS U: MECHANICAL AND ELECTRICAL WORK

cable termination.
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
6 Electrical services 4 Extra low voltage D10 C16
(below 50 V) All incoming electrical Items for incoming
services and main electrical services shall
installation shall be deemed to include
be described in connection cable ends

146 | MyCESMM2
(MyCESMM2)

conjuction with and all cable tails and


manufacturer’s details cable termination
Malaysian Civil Engineering

and specification. glands.

C17
Items for electrical
services shall be
deemed to include
ratings, capacity, type,
configuration (1/2 way
switches, single or
gang switches, switch
Standard Method of Measurement ̵ Second Edition

centres etc), power


socket outlets and
environmental class
shall be included for
fittings.

C18
The lightning
protection/ earthing
installation shall
include all the
necessary excavation,
concrete pit, make
good, copper rod/earth
materials to achieve
the desired ohmic
value.
5 System 1 Multi-media set C19
Visual system Items for system shall
2 Perimeter security set be deemed to include
system supporting brackets,
3 Intelligent tunnel set cable termination,
emergency ancillary works and
evacuation system all other required
4 Audio-visual system set accessories.
6 Accesssories 1 Light fittings nr C20
2 Street Lighting nr Items for accessories
3 Traffic Light nr shall be deemed to
include supporting
brackets, covers, cable
termination, ancillary
works and all other
required accessories.
CLASS U: MECHANICAL AND ELECTRICAL WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
6 Electrical services 7 Equipment 1 Generator set nr M6 C21 A12
2 UPS nr The UPS room for wet Items for UPS supplied Item description for
3 Transformers nr battery cell shall be and installed shall be standby equipment
4 Variable Speed nr measured separately deemed to include shall be stated.
Drive/Variable under respective batteries, UPS module,
Frequency Drive classes of work where coupling panels,
5 Soft starter nr expressly required. isolation transformer
6 Switch gear nr and all other required.
7 Standby nr
8 Low Voltage nr
enclosure
7 Communication 1 Telephone system 1 Private Automatic set C22
Branch Exchange Items for
(digital/analogue) communication shall
2 Local area network set be deemed to include
3 Wireless local set supporting brackets,
area networking cable termination,
ancillary works and
all other required
accessories.
2 Supervisory Control set C23
and Data Items for Supervisory
Acquisition System Control and Data
3 Programme Logic sum Acquisition System
Control (SCADA), Programme
4 Telemetry system sum Logic Control (PLC)
5 Close Circuit sum and Close Circuit
Television Television (CCTV) shall
be deemed to include
all accessories.
8 Mechanical work 1 Equipment and 1 Static screen nr D11 C24
appliances 2 Automatic screen nr Static screen is a Items for static screen,
3 Non-static screen nr screen that is fixed or automatic screen
stationary condition. and non-static screen
shall be deemed to
D12 include all design,
Non-static screen endorsement, capacity,
is a screen which material, system,
is designed to be supply, install and
movable manually. make good.

MyCESMM2 | 147
CLASS U: MECHANICAL AND ELECTRICAL WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
8 Mechanical work 1 Equipment and 4 Aeration nr D13 C25 A13
appliances Aeration shall be Items for equipment Item description for
classified as air diffuser, and appliances shall aeration shall state the
mechanical aerator, be deemed to include function.
gravity fall weir and design, all fittings and

148 | MyCESMM2
(MyCESMM2)

biological process. accessories and any


modification works,
Malaysian Civil Engineering

D14 supplied, delivered and


Aeration is the installed on site.
process by which air
is circulated through,
mixed with or
dissolved in a liquid or
substance which by
designed as gravity
based, air based or
mechanical based.
Standard Method of Measurement ̵ Second Edition

D15
Items for aeration type
shall consist of but not
limited to air blower
aerator, surface aerator,
brush aerator, fixed
type surface aerator,
submersible aerator,
paddle aerator, ejector,
diffuser, membrane
aerator and etc.

5 Mixer nr D16 C26 A14


Mixer is the device for Items for mixer shall be Item description for
mixing the chemicals deemed to include all mixer shall state the
in the pre and post supply, install, jointing, type of mixers.
treatment process. integration with other
structure and make
good.

6 Flocculation nr M7 D17 C27 A15


Other ancillaries work Flocculation refers to The flocculation shall Item description for
related to flocculation the process by which be deemed to include flocculation shall state
and sedimentation fine particulates are all supply, install and the function.
shall be measured caused to clump make good.
using their respective together into a
classes. flocculation.
CLASS U: MECHANICAL AND ELECTRICAL WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
8 Mechanical work 1 Equipment and 7 Sedimentation nr D18 C28 A16
appliances 8 Clarification nr Sedimentation is a Items for Item description for
process built with sedimentation shall be sedimentation and
mechanical means for deemed to include all clarification shall
continous removal of design, endorsement, state the function and
solids being deposited approval drawing, as associated works.
by sedimentation built drawing, fittings
inclusive of clarifier and accessories and A17
and thickener. any modification Item description for
works, supplied, clarification shall state
D19 delivered and installed the type of dissolve
Clarification is the on site. air flotation (DAF),
process that solids or etc, function and
particles rising to the associated works.
surface.
A18
Item description for
sedimentation and
clarification shall state
type i.e clarifier or
thickener and to define
the process i.e lamella,
tube settler, solid
contact, sand ballasted,
etc.
2 Equipment and 1 Filtration nr D20 C29 A19
appliances Filtration is any of Items for filtration shall Item description for
various operations be deemed to include all filtration shall state the
that separate solids fittings and accessories function.
from fluids by adding a and installed on site
medium through which inclusive of filter nozzle
only the fluid can pass. and filter slab.

2 Chemical treatment sum D21 C30 A20


process and system The chemical and Items for chemical Item description for
3 Special treatment sum special treatment and special treatment chemical and special
process and system process and system process and system treatment process
is the common steps shall be deemed to and system shall state
used in treatment include all design, the system type, and
process that comprises drawings, endorsement, function.
of various types and supply, deliver,
duties in order to treat installation, testing,
water for consumption fittings, accessories
or release to the as built drawing and
nature. any modification
works including to
achieve the output
design associated and
integration with other
system.

MyCESMM2 | 149
CLASS U: MECHANICAL AND ELECTRICAL WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
8 Mechanical work 2 Equipment and D22
appliances The chemical and
special treatment
process and system
plant type shall consist

150 | MyCESMM2
(MyCESMM2)

of but not limited to


lime system, potassium
Malaysian Civil Engineering

permanganate system,
aluminium system, Poly
Aluminium Chloride
(PAC) system, Powder
Activated Carbon
(powder AC) system,
main polymer system,
sludge polymer system,
chlorination system,
scrubber system,
Standard Method of Measurement ̵ Second Edition

auto shut off system,


fluoride system etc.
4 Sludge treatment sum D23 C31 A21
facility Item sludge treatment The sludge treatment Item description for
5 Dewatering system sum facility and dewatering facility and dewatering mechanical type sludge
system type shall system shall be deemed treatment facility and
consist of but not to include all design, dewatering system
limited to decanter, drawings, endorsement, shall state all related
belt press, filter press, supply, deliver, components, function,
drum thickener, etc. installation, testing, and associated works
fittings, accessories as components.
built drawing and any
modification works, A22
design output and Item description for non
integrate works with mechanical type sludge
other system. treatment facility and
dewatering system
shall state the function.

A23
Item description for non
mechanical type sludge
treatment facility and
dewatering system
shall state in detail all
related components
type i.e sludge lagoon,
sludge drying bed etc.
inclusive of all necessary
associated works and
integration with other
system.
CLASS U: MECHANICAL AND ELECTRICAL WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
8 Mechanical work 2 Equipment and 6 Lifting equipment nr D24 C32 A24
appliances The lifting equipment The motorised or Item description for
is a specific system non motorised lifting lifting equipment shall
of hoisting apparatus equipment shall be state the type capacity,
travelling overhead deemed to include function, motorised,
for lifting and hoisting all required design, manual, electric current
other equipment and is drawings, endorsement, requirement for the
designed to carry the supply, deliver, motor, power supply,
specific load. installation, testing, motor and switch
fittings, accessories and controller.
D25 any modification works
The lifting equipment including associated
shall be categorised as works with other
motorised or manual. components.

C33
The installation of
lifting equipment shall
be deemed to include
obtaining the PMA
Certificate from DOSH.

7 Pressure tanks nr C34 A25


8 Non-pressure tanks nr Items for pressure and Item description for
non-pressure tanks pressure tanks shall
shall be deemed to state the system plant
include all required type i.e surge vessel,
design, drawings, air receiver tank, etc.
endorsement, supply,
deliver, installation, A26
testing, fittings, Item description for
accessories and any non-pressure tanks
modification works shall state the system
including integration plant type, i.e silo,
with other system. storage tank, process
tank, powder chemical
C35 tank, liquid chemical
The installation of tank, bin activator, silo
pressure and non- dehumidifier etc.
pressure tanks
equipment shall be A27
deemed to include Item description for
obtaining of the PMT non-pressure tanks
Certificate from DOSH. shall state the function.

MyCESMM2 | 151
CLASS U: MECHANICAL AND ELECTRICAL WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
8 Mechanical work 3 Equipment and 1 Other equipment nr D26 A28
appliances and accessories Items for other Item description for
equipment and other equipment and
accessories shall accessories shall state
be categorised but the function.

152 | MyCESMM2
(MyCESMM2)

not limited to odour


control, exhaust fan,
Malaysian Civil Engineering

pump guide rail, guide-


barholder and float
switch .

4 Miscellaneous 1 Rotating nr D27 C36


equipment Item for rotating Item for miscellaneous
2 Non-rotating nr equipment shall shall be deemed to
Standard Method of Measurement ̵ Second Edition

equipment include but not limited include all fixing screw


to air blower, air or belt based.
compressor, conveyor,
scapper, scan skimmer,
fluoride crusher,
dust collector, arch
breaker,transporter etc.

D28
Item for non-
rotating equipment
shall include but
not limited to tube
diffuser, universal/
flexible coupling/
adaptor, analyser rack,
laboratory equipments,
headstocks/ spindlers,
portable actuator,tools
and spare parts etc.

3 Effluent equipment nr D29


Item for effluent
equipment shall
include but not limited
to flowmeter, parshall
flume, thickener, UV
disinfection system,
ozone etc.
CLASS U: MECHANICAL AND ELECTRICAL WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
8 Mechanical work 5 Instrumentation 1 Flow measurement nr M8 D30 C37 A29
2 Level measurement nr The associated works Item for quality Instrumentation Item description
3 Pressure nr to instrumentation measurement shall shall be deemed to for flow measuring
measurement shall be measured consist of but not include all wiring, equipment shall state
4 Quality nr separately under limited to water and air control panel, fittings, the system plant
measurement respective classes of quality in compliance hacking, conduit, type, function and
5 Water content nr work. to authorities related accessories and associated integration
analyser requirements. all associated works with other system.
including making good.
D31 A30
Item for water Item description for
contents analyser level, pressure and
type shall consist of quality measuring
but not limited to pH equipment shall state
analyser, temperature, the system plant
turbidity, conductivity, type i.e ultrasonic,
iron, aluminium, etc., function and
manganese, chlorine, associated integration
colour, fluoride, with other system.
hydrocarbon, oxygen
demand, sludge stray, A31
chlorine, ammonia, Item description
salinity, stream current for water content
monitoring (SCM). analyser shall state
type of analyser and
all associated works as
expressly stated.

MyCESMM2 | 153
CLASS U: MECHANICAL AND ELECTRICAL WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
8 Mechanical work 6 Pumps 1 Positive nr M9 D32 C38 A32
displacement Item for replacement Pumps shall be Items for pumps Item description for
2 Dynamic nr of motor to be stated categorised to type of shall be deemed to motor shall state the
3 Special nr separately when pumps ie dosing pump, include all fittings and type of motors, power
4 Diesel nr expressly required. metering pump, jet accessories and any capacity.

154 | MyCESMM2
(MyCESMM2)

5 Motor nr pump etc. modification works


supplied, delivered and A33
Malaysian Civil Engineering

D33 installed on site and Item description for


Positive displacement make good all joints. motor with pumps
pump is a pump which shall be stated when
is categorised whether C39 expressly required.
as reciprocating or Items for motor with
rotary where the flow pump shall be deemed
volume is driven by to include all supply,
mechanical force. jointing, couplings,
flange, bolting,
D34 washers, and gaskets
Standard Method of Measurement ̵ Second Edition

Dynamic pump is including make good


the pump which is all joint.
designed as centrifugal
which the flow diven
by rotating vane
impeller include radial,
axial and mixed flow
unit.

D35
Special pump is
the pumps that is
determined to be used
for special purpose
other than positive
displacement and
dynamic pump.

D36
A motor is a machine
which converts electric
energy into mechanical
energy which
categorised under
synchronous (plain and
super) and induction
(squirrel cage and slip
ring) motors.
CLASS U: MECHANICAL AND ELECTRICAL WORK
CLASS V
MISCELLANEOUS
WORK

MyCESMM2 | 155
ADDITIONAL
CLASS V: MISCELLANEOUS WORK MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES

Measurement covered under other classes:

Silt fence (included in Class B: Environmental protection and enhancement).


Brickwall (included in Class J : Brickwork, blockwork, and masonry).

156 | MyCESMM2
(MyCESMM2)

FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT


Malaysian Civil Engineering

1 Fences 1 Timber m M1 C1 A1
2 Metal m The length of fences Items for fences and Item description for
3 Chain link m shall exclude lengths gates shall be deemed fences and gates
4 Barb/bladed wire m occupied by gates. to include excavation, shall state the types,
5 Composite material m foundation, preparation dimensions and size of
6 Concrete m of surfaces, type of foundations.
7 Precast concrete m finishing, disposal of
panel excavated material, A2
upholding sides of Item description for
Standard Method of Measurement ̵ Second Edition

excavation, backfilling, fences shall state the


concrete, formwork and sizes, types, material
reinforcement. of post and type of
finishing.

2 Gates nr C2 A3
Items for fences shall Item description for
be deemed to include fences shall state the
all posts and their types of metal and
foundation. grade of timber used.

C3 A4
Items for chain link shall Item description for
be deemed to include chain link shall state
all posts, raked angle, the size, gauge and
straining wires, barb protective coating of
wires, kerbs where wire mesh.
applicable and their
foundation. A5
Item description for
C4 gates shall state number,
Items for gates shall size of leaf and type of
be deemed to include finishing.
posts and foundations,
hinges, bolts, rollers, A6
lockplates and all Item description for
necessary welding. gate shall state the
mode of operation.
C5
If mode of operation of
gate is automatic, the
items shall be deemed
to include the control
system.
CLASS V: MISCELLANEOUS WORK
ADDITIONAL
FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES
3 Signage for 1 Painting of logos nr C6 A7
buildings and tanks 2 External signage nr Items for internal and Item description for
3 Internal signage nr external signage shall painting of logo shall
be deemed to include state the location,
fixing cost. name of logo, and the
type of paint.

A8
Item description for
external and internal
signage shall state the
type of material, size
and location.

4 Bearing pads 1 Bridge bearing 1 Roller nr C7 A9


2 Other bearing 2 Slide nr Items for bearing pads Item description for
3 Rocker nr shall be deemed to bearing shall state the
4 Plain rubber nr include grouting and dimensions.
5 Laminated rubber nr temporary works.
6 Pot bearing nr A10
Item description for
pot bearing shall state
the type of material
used.

MyCESMM2 | 157
CLASS V: MISCELLANEOUS WORK
Malaysian Civil Engineering
Standard Method of Measurement
(MyCESMM)

158 | MyCESMM2
CLASS W
PROVISIONAL AND
PRIME COST SUM

MyCESMM2 | 159
ADDITIONAL
CLASS W: PROVISIONAL AND PRIME COST SUM MEASUREMENT RULES DEFINITION RULES COVERAGE RULES
DESCRIPTION RULES

Measurement covered under other classes:

FIRST DIVISION SECOND DIVISION THIRD DIVISION UNIT

160 | MyCESMM2
(MyCESMM2)

1 Provisional sums 1 Item stated sum M1 D1 C1 A1


Each prime cost The term ‘prime Items for provisional Item description for
Malaysian Civil Engineering

sums item shall be cost sum’ is defined sums shall be deemed provisional sums and
followed by an item as a sum provided to include allowances prime cost sums shall
for attendance and for work or services to programme, plan identify the work
percentage for profit. to be executed and price the works included.
by a nominated within the tenderer’s
M2 sub-contractor, a general items.
Where provisional and government or a
prime cost sum form a statutory authority or
separate bills in the bill for materials or goods
of quantities, this item to be obtained from
Standard Method of Measurement ̵ Second Edition

shall make reference a nominated supplier.


to the relevant bills Such sum shall be
instead. deemed to be exclusive
2 Provisional sums 1 Attendance sum of any profit required
procured by 2 Profit % and/or attendance to
employer/ others be provided by the
main contractor and
provision shall be made
for the addition thereof
where applicable.

D2
The term ‘provisional
sum’ is defined as a
sum provided for work
or for costs which
cannot entirely be
foreseen, defined or
detailed at the time the
3 Prime cost items 1 Item stated sum tender documents are
2 Attendance sum issued.
3 Profit %
D3
Item stated is the
item identified to
be measured as
provisional sum or
prime cost sum.
CLASS W: PROVISIONAL AND PRIME COST SUM
BIBLIOGRAPHY

MyCESMM2 | 161
Malaysian Civil Engineering
Standard Method of Measurement ̵ Second Edition
(MyCESMM2) BIBLIOGRAPHY

BIBLIOGRAPHY

[1] Civil Engineering Standard Method of Measurement, Fourth Edition, CESMM4 (UK),
Institution of Civil Engineers and the Civil Engineering Contractors Association, 2012

[2] JKR 20800-0183-14, Standard Specifications for Building Works 2014

[3] JKR 20403-0003-07, Standard Specifications for Road Works 2014

[4] KTMB Permanent Work Manual 2015

[5] Malaysian Standard Method of Measurement for Civil Engineering Works, CESMM,
Construction Industry Development Board (CIDB), 2003

[6] Malaysian Standard Method of Measurement for Civil Engineering Works, MyCESMM,
Construction Industry Development Board (CIDB), 2011

[7] Malaysian Standard Method of Measurement of Building Works, Second Edition, SMM2,
Instituitionsof Surveyors Malaysia (ISM), 2000

[8] Rail Method of Measurement 2 - Detailed Measurement, July 2014

162 | MyCESMM2
ACKNOWLEDGEMENTS

MyCESMM2 | 163
Malaysian Civil Engineering
Standard Method of Measurement ̵ Second Edition
(MyCESMM2) ACKNOWLEDGEMENTS

ACKNOWLEDGEMENTS
Members of Technical Committee on Construction Practices

Ir. Noraini Bahri (Chairman) Construction Industry Development Board Malaysia

Ms. Nur Mastura Sahran (Secretary) Construction Industry Development Board Malaysia

Mr. Khairunnizam Sulaiman Construction Industry Development Board Malaysia

Ir. Patrick C Augustin Association of Consulting Engineers Malaysia

Ir. Sin Wai Ho Association of Consulting Engineers Malaysia

Ar. Thulasaidas Sivasubramaniam Jabatan Kerja Raya Malaysia

Mr. Muhammad Imraan Mohd Annuar Jabatan Kerja Raya Malaysia

Mr. Ong Ka Thiam Master Builders Association Malaysia

Mr. Fong Fatt Kee Master Builders Association Malaysia

Ir. Tang Lai Peng Master Builders Association Malaysia

Ir. Ahmad Redza Ghulam Rasool Ministry of Urban Wellbeing, Housing and Local Government

Ir. Roslan Mat Sapri Ministry of Urban Wellbeing, Housing and Local Government

Ir. Kamaruddin Mohd Salleh Persatuan Kontraktor Melayu Malaysia

Dato’ Ir. Jamaludin Non Persatuan Kontraktor Melayu Malaysia

Ar. Jasmin Kamarudin Pertubuhan Akitek Malaysia

Ir. Tiah Oon Ling Real Estate and Housing Developers’ Association Malaysia

Mr. Kamal Pasha Mokhtar Real Estate and Housing Developers’ Association Malaysia

Sr Amnah Salleh Royal Institution of Surveyors Malaysia

Ir. Tu Yong Eng The Institution of Engineers, Malaysia

Ir. Gunasagaran Kristnan The Institution of Engineers, Malaysia

Prof. Ir. Dr. Mohd Zamin Jumaat Universiti Malaya

Ir. Dr. Raizal Saifulnaz Muhammad Rashid Universiti Putra Malaysia

Dr. Sumarni Ismail Universiti Putra Malaysia

164 | MyCESMM2
ACKNOWLEDGEMENTS

ACKNOWLEDGEMENTS
Members of Working Group on Malaysian Standard Civil Engineering Standard Method of Measurement

Datuk Ir. Abdul Kadir Mohd Din (Chairman) Ranhill Capital Sdn Bhd

Sr Nazir Muhamad Nor (Secretary) Construction Industry Development Board Malaysia

Ir. K Sundraraj Association of Consulting Engineers Malaysia

Prof. Ir. Dr. Hajjah Siti Hawa Hamzah Board of Engineers Malaysia

Sr Nik Zainal Alam Hasan Board of Quantity Surveyors Malaysia

Sr Sariah Abd Karib Construction Industry Development Board Malaysia

Ms. Zainora Zainal Construction Industry Development Board Malaysia

Sr Mohd Zaid Zakaria Construction Industry Development Board Malaysia

Sr Dr. Mahmudah Yahya Department of Irrigation and Drainage Malaysia

Sr Ruzimah Othman Department of Irrigation and Drainage Malaysia

Sr Alvin Chin Kok Wah Gamuda Berhad

Mr. Abdul Rahim Abdul Salam Indah Water Konsortium Sdn Bhd

Mr. Muhamad Zaidi Basri Indah Water Konsortium Sdn Bhd

Ir. Abd Rahman Salleh Jabatan Kerja Raya Malaysia

Dato’ Sri. Ir. Dr. Zullkefle Nordin Jabatan Perkhidmatan Pembetungan

Sr Azmi Mohamed Lembaga Lebuhraya Malaysia

Sr Chen Seong Wai Mass Rapid Transit Corporation Sdn Bhd

Mr. Azman Mohd Ihsan Pengurusan Aset Air Berhad

Sr Megat Ab Rahman Megat Wah Prasarana Malaysia Berhad

Mr. Rossizaen Ismail Projek Lebuhraya Usahasama Berhad

Sr Lim Kok Sang Royal Institution of Surveyors Malaysia

Mr. Ahmad Hafizullah Amir Ahmad Razali Suruhanjaya Perkhidmatan Air Negara

Sr Aminuddin Saidin Tenaga Nasional Berhad

Ir. Gunasagaran Kristnan The Institution of Engineers, Malaysia

Assoc. Prof. Sr Dr. Zakaria Mohd Yusof Universiti Teknologi Malaysia

The work of analysing the comments, suggestions and drafting of this Malaysian Standard was undertaken by Sr Hajjah Sabaria
Datuk Haji Hassan and Sr Jailani Jasmani from JUB Central Sdn Bhd. The committee is indebted to the above mentioned experts
for their invaluable advice and assistance throughout.

MyCESMM2 | 165
© Copyright 2018
All rights reserved. No part of this publication may be reproduced or utilised in any form
or by any means, electronic or mechanical, including photocopying and microfilm, without
permission in writing from the CIDB Malaysia.