Professional Documents
Culture Documents
Andhra Pradesh Cement Works, Ultratech Cement LTD, 515415
Andhra Pradesh Cement Works, Ultratech Cement LTD, 515415
Andhra Pradesh Cement Works, Ultratech Cement LTD, 515415
i
S. NO. CONTENTS PAGE NO.
6.0 Proposed Infrastructure 20
(i) Industrial Area (Processing Area) 20
(ii) Residential Area (Non Processing Area) 20
(iii) Green Belt 20
(iv) Social Infrastructure 20
(v) Connectivity 20
(vi) Drinking Water 20
(vii) Sewerage System 21
(viii) Industrial Waste Management 21
(ix) Solid Waste Management 21
(x) Power Requirement & Source 21
7. Rehabilitation and Resettlement (R & R) Plan 21
Policy to be adopted (Central/ State) in respect of the Project affected persons including Home 21
(i)
Oustees, Land Oustees and Landless Laborers (Brief Outline to be given)
8. Project Schedule & Cost Estimates 21
Likely Date of Start of Construction and Likely Date of Completion (Time Schedule for the Project 21
(i)
to be given)
(ii) Estimated Project Cost 22
9. Analysis of Proposal 22
Financial and Social Benefits with special emphasis on the benefit to the local people including
(i) 22
tribal, population, if any in the area
ii
ABBREVIATIONS
1
R&R Rehabilitation and Resettlement
SE South East
SW South West
SSW South of South West
STP Sewage Treatment Plant
SH State Highway
TPD Tonnes Per Day
TPA Tonnes Per Annum
UTCL UltraTech Cement Ltd.
VRM Vertical Roller Mill
WHRS West Heat Recovery System
WNW West of north West
2
Expansion of Integrated Cement Plant - Clinker (6.5 to 10.0 MTPA), Cement (9.0 to 14.0 MTPA) and WHRS (20 to 36 MW)
At Village: Bhogasamundram, Mandal: Tadipatri, District: Anantapur and Village: Tummalapenta, Mandal: Kolimigundla, District: Kurnool (Andhra Pradesh)
Pre-Feasibility Report
Environmental Clearance for the existing plant has been obtained from MoEFCC, New Delhi and
SEIAA, Andhra Pradesh. Details of the existing clearance is given below -
o Clinker (6.5 MTPA) and Cement (9.0 MTPA) vide MoEFCC letter no. J-11011/303/2008-IA-II (I)
dated 8th Oct., 2008.
o CPP (100 MW) - vide SEIAA letter no. SEIAA/AP/ANT-26/2010-1113 dated 16th July, 2011.
o WHRS (4.0 MW) - vide MoEFCC letter no. J-11011/324/2006-IA II (I) dated 05th March, 2007 &
WHRS (16.0 MW) - vide CFE letter No: Order No. 184 /APPCB/CFE/RO-KNL/HO/2011
on dated 18th May, 2018.
Copy of the EC letters are enclosed as Annexure - 1 and copy of Consent for Establish (CFE) for
installation of additional 16 MW WHRS is enclosed as Annexure - 2.
Now, M/s. UltraTech Cement Limited is proposing an Expansion of Integrated Cement Plant -
Clinker (6.5 to 10.0 MTPA), Cement (9.0 to 14.0 MTPA) & WHRS (20 to 36 MW) at Village:
Bhogasamundram, Mandal: Tadipatri, District: Anantapur and Village: Tummalapenta, Mandal:
Kolimigundla, District: Kurnool (Andhra Pradesh) as the proposal given below -
Additional Total capacity
Unit Existing Capacity
Capacity after expansion
Clinker (MTPA) 6.5 (Line I: 2.7 & Line II: 3.8) New Line III: 3.5 10.0*
Cement (MTPA) 9.0 (Line I: 3.2 & Line II: 5.8) New Line III: 5.0 14.0
CPP (MW) 100 Nil 100
WHRS (MW) 20 16 36
*Part of Clinker will be dispatched to split Grinding Units
Table - 1
Salient Features of the Project
S. NO. PARTICULARS DETAILS
1. Nature of the Project Expansion Project
Clinker - 6.5 to 10.0 MTPA
2. Size of the Project Cement - 9.0 to 14.0 MTPA
WHRS - 20 to 36 MW
As per EIA Notification dated 14th Sept., 2006 & as amended from
3. Category of the Project time to time; this project falls under S. No. 3 (Material Production),
Category - ‘A’, Project Activity ‘3 (b)’ Cement Plants
M/s. UltraTech Cement Limited 1
(Unit : Andhra Pradesh Cement Works)
Expansion of Integrated Cement Plant - Clinker (6.5 to 10.0 MTPA), Cement (9.0 to 14.0 MTPA) and WHRS (20 to 36 MW)
At Village: Bhogasamundram, Mandal: Tadipatri, District: Anantapur and Village: Tummalapenta, Mandal: Kolimigundla, District: Kurnool (Andhra Pradesh)
Pre-Feasibility Report
Environmental Clearance for the existing plant has been obtained from MoEFCC, New Delhi and
SEIAA, Andhra Pradesh. Details of the existing clearance is given below -
o Clinker (6.5 MTPA) and Cement (9.0 MTPA) vide MoEFCC letter no. J-11011/303/2008-IA-II (I)
dated 8th Oct., 2008.
o CPP (100 MW) - vide SEIAA letter no. SEIAA/AP/ANT-26/2010-1113 dated 16th July, 2011.
o WHRS (4.0 MW) - vide MoEFCC letter no. J-11011/324/2006-IA II (I) dated 5th March, 2007 & WHRS
(16.0 MW) - vide CFE letter No: Order No. 184 /APPCB/CFE/RO-KNL/HO/2011
on dated 18th May, 2018.
Now, M/s. UltraTech Cement Limited is proposing an Expansion of Integrated Cement Plant -
Clinker (6.5 to 10.0 MTPA), Cement (9.0 to 14.0 MTPA) & WHRS (20 to 36 MW) at Village:
Bhogasamundram, Mandal: Tadipatri, District: Anantapur and Village: Tummalapenta, Mandal:
Kolimigundla, District: Kurnool (Andhra Pradesh) as the proposal given below -
M/s. UltraTech Cement Limited 3
(Unit : Andhra Pradesh Cement Works)
Expansion of Integrated Cement Plant - Clinker (6.5 to 10.0 MTPA), Cement (9.0 to 14.0 MTPA) and WHRS (20 to 36 MW)
At Village: Bhogasamundram, Mandal: Tadipatri, District: Anantapur and Village: Tummalapenta, Mandal: Kolimigundla, District: Kurnool (Andhra Pradesh)
Pre-Feasibility Report
As per EIA Notification dated 14thSeptember, 2006, as amended from time to time; the project falls
under Category “A”, Project or Activity ‘3(b)’.
(iii) Need for the project and its importance to the country and or region
With nearly 420 Million Tonnes (MT) of cement production capacity, India is the second largest
cement producer in the world and accounts for 6.9 per cent of World’s cement output.
No wonder, India's cement industry is a vital part of its economy, providing employment to more
than a million people, directly or indirectly. Ever since it was deregulated in 1982, the Indian cement
industry has attracted huge investments, both from Indian as well as foreign investors.
India has a lot of potential for development in the infrastructure and construction sector and the
cement sector is expected to largely benefit from it. Some of the recent major government
initiatives such as development of 98 smart cities are expected to provide a major boost to the
sector.
Also, a significant factor which aids the growth of this sector is the ready availability of the raw
materials for making cement, such as limestone and coal.
The housing sector is the biggest demand driver of cement, accounting for about 67% of the total
consumption in India. The other major consumers of cement include infrastructure at 13%,
commercial construction at 11% and industrial construction at 9%.
There is a capacity addition of 109 MTPA between 2013-16. Cement Industry is expected to grow at
5-6 percent CAGR between FY17 - FY20. The industry is currently producing 280 MT for meetings its
domestic demand and 5 MT for exports requirement. The country's per capita consumption stands
at around 225 kg.
Due to the increasing demand in various sectors such as housing, commercial construction and
industrial construction, cement industry is expected to reach 550-600 Million Tonnes Per Annum
(MTPA) by the year 2025.
During Construction Phase: Approx. 1000 persons will be employed from nearby area during
construction phase.
(ii) Location (map showing general location, specific location, and project boundary & project site
layout) with coordinates
(iii) Details of alternative sites consideration and basis of selecting the proposed site, particularly the
environmental considerations gone into should be highlighted.
Since, proposed expansion and installation will be done within the existing project area, which is in
possession of the company; therefore, no alternative site has been considered.
As per EIA Notification dated 14th Sept., 2006 & as amended from time to time; this project falls
under S. No. 3 (Material Production), Category - ‘A’, Project Activity ‘3 (b)’ Cement Plants.
v) Project description with process details (a schematic diagram/ flow chart showing the project
layout, components of the project etc. should be given)
Project Description
M/s. UltraTech Cement Limited is proposing an Expansion of Integrated Cement Plant - Clinker (6.5
to 10.0 MTPA), Cement (9.0 to 14.0 MTPA) & WHRS (20 to 36 MW) at Village: Bhogasamundram,
Mandal: Tadipatri, District: Anantapur and Village: Tummalapenta, Mandal: Kolimigundla, District:
Kurnool (Andhra Pradesh).
Process Details
Cement Plant
The process involves in cement production largely comprises of the following steps:
o Transport of excavated limestone from Captive mines via covered conveyor belt
o Raw Mix Preparation & Homogenization
o Preheating, Calcination &Clinkerization
o Clinker Cooling
M/s. UltraTech Cement Limited 10
(Unit : Andhra Pradesh Cement Works)
Expansion of Integrated Cement Plant - Clinker (6.5 to 10.0 MTPA), Cement (9.0 to 14.0 MTPA) and WHRS (20 to 36 MW)
At Village: Bhogasamundram, Mandal: Tadipatri, District: Anantapur and Village: Tummalapenta, Mandal: Kolimigundla, District: Kurnool (Andhra Pradesh)
Pre-Feasibility Report
Process Description:
The Cement Plant is based on Dry Process Technology for Cement manufacturing with Pre-Heating
and Pre-Calciner Technology. Dry process of cement manufacturing offers more advantages,
particularly in fuel consumption and is the most rational and logical choice. The proposed expansion
plant will adopt dry process to manufacture Portland Pozzolana Cement (PPC), Ordinary Portland
Cement (OPC) and Portland Slag Cement, Composite Cement, SRPC & GGBS using rotary kiln,
preheater and precalciner.
Pre-blending of crushed limestone: Two nos. Chevron type, longitudinal stockpiles have been
proposed for storage and homogenization of limestone. The storage capacity has been considered
as 5 active days for a Clinkerization plant catering to the requirement of the plant. The limestone
received from the crusher shall be stacked with the help of a stacker. The reclaiming is envisaged
through a bridge reclaimer. The quality of the stockpile shall be controlled by the PGNAA based
cross belt analyser installed on the belt conveying material from crusher to stacker.
While stacking of limestone will be done in one pile, its reclaiming will be done from the other.
Reclaimed limestone shall be transported to the raw material hoppers in the raw material
department through a series of belt conveyors.
Drying – cum – Grinding of raw materials. Hot gases from the Preheater are used for drying raw
materials. A suitably designed hot air generator has been provided for start up when kiln does not
run. An independent raw grinding system is envisaged and based on the merits of vertical roller mill
(VRM) has been selected for the expansion project. The mill shall be equipped with a new
generation, high efficiency dynamic separator. A suitably designed static cyclone separator shall
also be installed for separation of raw meal from the system gases.
Gas from the VRM system fan along with the gases from the PH fan exit are dedusted in bag house
separating the fine product from gases and the dust free gases are then vented out through the
bag house fan.
Material collected at the bottom of the cyclones and bag house shall be elevators and air slides. Bag
house is designed to meet the requirements of prevalent environmental norms.
Clinkerisation of the raw meal in a rotary kiln with preheater and precalciner: A dry process kiln
installation has been envisaged. The Preheater has six stage cyclones lowering PH exit gas
temperature thereby reducing the specific heat consumption. A suitably designed double string 6-
stage PH system having new generation, high efficiency cyclones with low pressure drop has been
planned with a set of preheater fans having low specific power consumption for proposed line III.
The overall separation efficiency of the Preheater will be minimum 94%. In-line calciners (ILC) are
proposed to be installed. About 40% fuel shall be fired in the kiln and the balance 60% fuel shall be
fired in the pre calciner.
The kiln feed material from storage silo shall be introduced into the preheater by means of an
energy efficient mechanical transport system having bucket elevator and air slides. The material will
be preheated in the preheater before entering the precalciner. Fuel firing in the PC shall be
controlled to achieve about 90-95% calcination of the material at its discharge. Separate tertiary air
ducts will be installed to transport the preheated air from the clinker cooler to precalciner for each
preheater string.
For the preheater strings, high efficiency, suitably designed variable speed drive fans will be
installed for handling the gases.
The technical concept considers a rotary kiln with a capacity of 10000 tpd. The kiln shall be three
roller stations and shall be driven by suitably sized frequency controlled variable speed drive. A
modern multi-channel, multi fuel type burner with low primary air consumption shall be installed
for fuel firing in the kiln. Kiln burner will be suitable for using multiple fuels.
A new generation, high heat recuperation efficiency (75% Min.), modular type, pit-less clinker cooler
shall be provided. The cooler shall be capable to cope with fluctuations and disturbances in the kiln,
which may occur during kiln operation. The cooler discharge has been considered above the ground
level to avoid any pit or tunnel and considering the environmental hazards. Clinker transport from
cooler to clinker has been considered to be with the help of pan conveyor.
Clinker Grinding, storage and packing: The clinker and gypsum are transported to the grinding mill
from storage through a set of belt conveyors which feeds the raw material to the mill inlet. Based
upon the evaluation of parameters like power consumption, investment cost, proven performance
and customer preference, a vertical roller mill (VRM) has been selected.
The cement is transported to existing cement silos by air slide and bucket elevator. Final product is
transported to multiple spout roto-packers for packing of cement in bags. A separate arrangement
has been provided for bulk loading of cement into bulkers for sale of loose cement to bulk markets.
The Waste Heat coming out of Pre-heater and cooler from kiln will be used in Waste Heat Recovery
Boiler to produce low pressure steam which is fed to turbine to produce power. WHR boiler will be
based on steam rankine cycle and envisaging recovery of heat from exhaust gases at two points viz.
pre-heater and clinker cooler (tapping at exhaust or mid-cooler). Steam generated in the boiler will
be used in the turbine to generate electricity in the generator.
Table - 6
Air Pollution Control Equipment
Proposed Air
Existing Air Pollution
Locations Pollution Control
S. No. Control Equipment
Equipment
Existing Line 1 Existing Line 2 Proposed Line 3 Line 1 Line 2 Proposed Line 3
Limestone Limestone Limestone
1. Bag Filter Bag Filter Bag Filter
Crusher Crusher Crusher
2. KILN/ Raw Mill KILN/ Raw Mill KILN/ Raw Mill RABH RABH RABH
3. Coal Mill Coal Mill Coal Mill Bag House Bag House Bag House
4. Cooler Cooler Cooler ESP ESP ESP
Cement Mill 3, 4
Cement Mill 1 & Cement Mill 6 &
5. (Common stack) Bag House Bag House Bag House
2 7
&5
6. Boiler CPP Boiler CPP - ESP ESP -
(vi) Raw material required along with estimated quantity, likely source, marketing area of final
products, mode of transport of raw material and finished product.
a) Raw Material Requirement
Table - 7
Raw Material Requirement
Table - 8
Fuel Requirement
Quantity (TPD) Distance & Mode Calorific
S. No. Name Source of Value % Ash % Sulphur
Existing Proposed Total
Transportation (Kcal/Kg)
2157
Indian Coal
1. 4000 6157 SCCL Rail/Road 3500 35 1.5
(100%)
(vii) Resources optimization/ recycling and reuse envisaged in the project, if any, should be briefly
outlined.
The company is proposing expansion in WHRS (from 20 MW to 36 MW) for re-utilization of the
exhaust gases from the Pre-heater/ Cooler to generate electric power and consequently reduce
consumption of grid power through fossil fuel.
Dust from various air pollution control equipment is being / will be recycled back to process.
Sludge from STP is being / will be used as manure in greenbelt development / plantation.
Domestic wastewater is being / will be treated in STP and treated water is being / will be re-
used for greenbelt development/ plantation and dust suppression.
The company utilizes minimal ground water, most of the water requirement is met by existing
rainwater harvesting pits/ mine sumps. Water conservation measures implemented are like
Permanent water sprinklers, use of air cooling in place of water cooling in process fans,
Installation of screw compressors in place of conventional compressors.
Rooftop rainwater harvesting in colony, drain water harvesting, implementation of rain water
harvesting in mines pit and development of recharging pits.
(viii) Availability of water it’s source, energy /power requirement and source should be given.
a) Water Requirement and Source
The existing water requirement is 3645 KLD; which is being sourced from Existing Rainwater water
sump at Mine site, Ground water and treated water from STP. Company has obtained permission
from CGWA for withdrawal of 4000 KLD of Ground Water vide order number CORD-11028/6/2018-
SNLA-GIS-CORD on 18th Dec., 2018.
Additional water requirement for proposed expansion project will be 1300 KLD; which will be
sourced from existing rainwater sump at mine site, ground water and treated water from STP. No
additional permission for drawl of Ground Water will be required for the proposed expansion
project.
(ix) Quantity of waste to be generated (liquid and solid) and scheme for their management/disposal
o Domestic waste water from colony & plant is being / will be treated in the existing STP of 600
m3/day capacity & treated waste water is being / will be utilized for green belt development.
o No effluent is being/will be discharged outside the project premises.
o Boiler blow down water is being / will be collected in neutralization pit. After neutralization, the
same is being / will be used for dust suppression and ash quenching.
o No solid waste is being/will be generated from the plant. However, dust collected from the air
pollution control equipment (Bag house & Bag filters) is totally recycled back to the process.
o STP Sludge utilized as manure for greenbelt development / plantation.
with communication facilities like telephone, fax, wireless and telex and as such, no constraints are
envisaged in this aspect as the Tehsil and District headquarters are near to the site.
(iii) Topography
The topography of the region is almost flat with gentle undulations.
(iv) Existing land use pattern (agriculture, non-agriculture, forest, water bodies (including area under
CRZ)), shortest distances from the periphery of the project to periphery of the forests, national
park, wild life sanctuary, eco sensitive areas, water bodies (distance from the HFL of the river),
CRZ. In case of notified industrial area, a copy of the Gazette notification should be given
Table -9
Environmental Settings of the Area
Details
S. No. Particulars (with approximate aerial distance and direction from the nearest boundary of
plant site)
Bhogasamundram (0.5 km in SW direction) and
1. Nearest Village
Tummalapenta (0.5 km in NE direction)
2. Nearest Town Tadipatri (11.0 km in SSW direction)
3. Nearest City Anantapur (58 km in SW direction)
Inter District Boundary (Kurnool & Anantapur) passing through the
4. Inter District Boundary
plant site
Nearest National Highway / State o SH - 30 (Adjacent in South direction)
5.
Highway o SH - 57 (Adjacent in SE direction)
5. Nearest Railway station Tadipatri Railway station (11.0 km in SSW direction)
6. Nearest Airport Kadapa Airport (97 km in SE direction)
National Parks, Wildlife Sanctuaries,
No National Park, Wildlife Sanctuary, Biosphere Reserve Reserve
Biosphere Reserves, Reserve Forests
7. Forests (RF) / Protected Forest (PF) exist within 10 km radius study
(RF) / Protected Forest (PF) within 10
area.
km radius
o Pedda Vanka (6.0 km in SW direction)
River / Water Body (within 10 km o Pedda Vanka (8.5 km in NNE direction)
8.
radius) o Saddala Venganna Cheruvu (9.0 km in NE Direction)
o Penneru River (9.5 km in SW Direction)
9. Seismic Zone Zone II [as per IS 1893 (Part-I): 2002]
• Workshop
A common mechanical and electrical workshop is located to take care of the regular
maintenance/ repair jobs in the plant.
• Machinery stores
A store building needed for storing tools, spare parts, consumables, etc. Open area for storing
machinery and construction materials for the proposed expansion plant.
• Cranes, Monorails and Pulley blocks
Adequate sized maintenance cranes/ hoists, monorails and pulley blocks at all suitable locations
at the plant for ease of maintenance and operation.
• Time and Security office
At the entrance of the main plant, a time office and a security office has been provided.
• Dispensary
A small dispensary with first aid facilities has been provided in the plant premises.
• Bags godown
Space has been provided in the packing plant area for the storage of bags.
• Parking
Adequate parking space has been/will be provided in the plant premises for the parking of
vehicles.
• Residential Area (Non processing area)
Residential colony for staff has been developed within the plant premises along with all the
required social amenities except for a dormitory to house essential skilled workmen.
• Storage facilities
Covered storage facilities have been / will be provided for the storage of raw materials and
product which are detailed below:
Table - 10
Storage facilities
(iii) Land use planning (breakup along with green belt etc.)
Total plant area is 320.68 ha. Land use of existing land is already industrial; since, the proposed
expansion will be done within the existing plant premises, therefore, there will be no change in land
use, only intensity will increase due to proposed Expansion Project. Out of the total plant area 119.2
ha (~37% of the total plant area) has already been developed under greenbelt/plantation which will
be further enhanced & maintained for proposed expansion.
(v) Amenities/Facilities
The company has constructed township, dispensary, shopping complex, canteen etc. for the
permanent and contract employees.
Company will develop the Amenities/Facilities in nearby area of the plant site as per requirement
of local people of the nearby area under corporate social responsibilities programme.
o Sludge generated from STP is being / will be used as manure in greenbelt development /
plantation.
(ii) Estimated project cost along with analysis in term of economic viability of the project.
o Total cost of the expansion Project is: Rs. 1250 Crores
o Cost for Environment Protection
Capital Cost: Rs. 125 Crores
Recurring Cost/annum: Rs. 6.4 Crores / annum
Sub: APPCB – CFE – M/s. UltraTech Cement Limited, Bhogasamudram (V), Tadipatri
(M), Anantapuram District – Consent for Establishment of the Board for Waste Heat
Recovery Plant (WHRP) of 16 MW under Sec.25 of Water (P&C of P) Act, 1974 and
Under Sec.21 of Air (P&C of P) Act, 1981 – Issued – Reg.
Ref: 1. CFE orders dt. 14.10.2016, 03.06.2017 & Amendment order dt. 16.07.2017.
2. Industry’s CFE application received through A.P. Single Desk Portal on 19.04.2018.
3. R.O’s inspection report dt. 05.05.2018.
4. CFE Committee meeting held on 17.05.2018.
******
1. In the reference 2nd cited, an application was submitted to the Board seeking Consent for
Establishment (CFE) for Waste Heat Recovery Plant (WHRP) with an additional project
cost of Rs. 100 Crores.
2. As per the application, the above activity is to be located within the existing Cement plant
premises at Bhogasamudram (V), Tadipatri (M), Anantapuram District, in the total factory
area of 320.68 Ha.
3. The above site was inspected by the Environmental Engineer and Asst. Environmental
Engineer, Regional Office, Kurnool, A.P Pollution Control Board on 30.04.2018 and found
that the site is surrounded by
Page 1 of 7
5. This Consent Order now issued is subject to the conditions mentioned in Annexure.
6. This order is issued from pollution control point of view only. Zoning and other regulations
are not considered.
7. This order is valid for a period of 7 years from the date of issue.
Encl: Annexue
MEMBER SECRETARY
To
Copy to: 1. The JCEE, Z.O., Kurnool for information and necessary action.
2. The E.E., R.O., Kurnool for information and necessary action.
Page 2 of 7
ANNEXURE
1. The proponent shall obtain Consents for Operation (CFO) from APPCB, as required Under
Sec.25/26 of the Water (P&C of P) Act, 1974 and under sec. 21/22 of the Air (P&C of P)
Act, 1981, before commencement of the activity.
Water:
2. The source of water is Bore well, Water collected in Thummalapenta Captive limestone
mines and also from penna river. The maximum permitted water consumption after
installation of WHRP is as following:
Qty. as per
Proposed Total qty. after
Sl. CFE orders
Purpose quantity for installation of
No. dt: 03.06.2017
expansion WHRP
(KLD)
a) Process & washing 1667 KLD --- 1667 KLD
b) Boiler feed & Captive power 1378 KLD 100 KLD 1478 KLD
plant
c) Industrial Cooling (Makeup/ ---
Humidification/Water Spraying
d) Domestic (Plant) 600 KLD --- 600 KLD
Total * (fresh + recycled) 3645 KLD 3745 KLD
3. The maximum waste water generation shall not exceed the following after installation of
WHRP:
Page 3 of 7
4. Under no circumstances the waste water shall be discharged out side the factory premises.
The zero discharge shall be implemented.
5. The sewage shall be treated to the on land for irrigation standards, stipulated under
Environment (Protection) Rules, 1986, notified and published by Ministry of Environment
and Forests, Government of India as specified in Schedule VI vide G.S.R.422 (E),
dt.19.05.1993 and its amendments thereof.
6. Separate flow meters with totalisers to necessary pipe-line shall be provided for assessing
the quantity of water used for each of the purposes mentioned below.
Air:
7. The proponent shall comply with the following to control air pollution:
Existing:
Sl. Details of
Stack 1 Stack 2 Stack 3 Stack 4 Stack 5 Stack 6 Stack 7
No Stack
a) Attached to Kiln / Raw Cooler Coal Cement Cement Attached Attached
mill –I –I Mill Mill- I Mill -2 to to
separator separator
–I –II
b) Capacity 8000 TPD 141.38 70 TPH 161 161
/265 TPH m2 TPH TPH
c) Name of the Coal -- Coal / -- -- -- --
Fuel /Petcoke Petcok
e
d) Stack height 141.5 50 75 60 60 45 45
above ground
(m.)
e) Air Pollution Bag house ESP Bag Bag Bag -- --
Control house house house
Equipment
f) Conc. of < 30 40 <30 < 30 40 <30 <30
particulate
matter
mg/Nm3
Page 4 of 7
Sl. Stack 23
Details of Stack Stack 21 Stack 22 Stack 27 Stack 28
No to 26
a) Attached to: Cement Limestone Packers CFBC CFBC
Mill -V Crusher –I VII, VIII , Boilers Boilers
IX & X ( 1 & 2) ( 2 & 4)
b) Capacity 140 TPH 1200 TPH 120 TPH 2 X 115 2 X 115
TPH TPH
c) Name of the Fuel : -- -- -- Coal / Coal /
Petcoke Petcoke
d) Stack height above 50 60 32 50 50
ground (m.)
e) Air Pollution ESP Bag Bag filters ESP ESP
Control Equipment: house
f) Conc. of particulate 40 < 30 <30 < 50 < 50
matter mg/Nm3
Proposed 16 MW Captive Power Plant: Waste heat gases from pre-heater of Line - II &
Cooler of Line - II shall be used.
8. Industry shall comply with the standards stipulated in the CFO order issued by the Board
for the existing cement plant.
9. The industry shall not stack the raw materials in open place. All the raw materials
shall be stored in the sheds.
10. The industry shall provide concrete roads in the plant and water shall be sprinkled on the
roads periodically to control the fugitive dust emissions. Vacuum / pneumatic dust collection
system shall be used for cleaning the internal roads.
11. The proponent shall ensure compliance of the National Ambient Air quality standards
notified by MOE&F, GOI vide notification No. GSR 826(E), dated. 16.11.2009, during
construction and regular operational phase of the project.
12. A sampling port with removable dummy of not less than 15 cm diameter shall be provided
in the stack at a distance of 8 times the diameter of the stack from the nearest constraint
such as bends etc. A platform with suitable ladder shall be provided below 1 meter of
sampling port to accommodate three persons with instruments. A 15 AMP 250 V plug point
shall be provided on the platform.
13. The generators shall be installed in a closed area with silencers and suitable noise
absorption systems. The ambient noise level shall not exceed 75 dB (A) during day time
and 70 dB (A) during night time.
Page 5 of 7
Solid Waste:
14. The industry shall comply with the following after installation of WHRP:
Source of solid
S. No quantity Method of disposal
waste
a) ETP/STP sludge 10 MTPA Mixed with lime stone and is being
used as manure for Plantation
b) Flyash 540 TPD Is being reused in the process for
manufacturing of PPC
c) Bottom ash 145 TPD Is being reused in the cement process
d) Tank bottom Sludge 78.00 KL/Annum
e) Used grease 24.2 TPA Is being used in the cement kiln for co-
processing within the premises
f) Gears (Grease) 24.5 TPA
g) Waste/Used Oil 70.60 KL/Annum
h) Transformer Oil 5 KL/Annum Is being disposed to the authorized re-
processors/recyclers
i) Hi-Chrome Forge 40 TPA
steel balls
j) Lead acid Batteries 528 Nos /Annum Sent to authorized agencies on buy
back basis
15. All the bag filter dust, raw meal dust, coal dust, clinker dust and cement dust from pollution
control devices shall be 100% recycled and reused in the process and used for cement
manufacturing. Solid waste from sewage treatment plant (STP) shall be used as manure.
No solid waste shall be disposed off from the cement plant. Spent oil, grease and grinding
media shall be disposed to licensed vendors.
16. The following rules and regulations notified by the MoE&F, GoI shall be implemented.
Other Conditions:
17. The existing green belt shall not be disturbed for the proposed activity. The area of the
greenbelt shall not be less than 33% of the total area.
18. The noise levels in and around the plant shall be kept well within the standards by
providing noise control measures including acoustic hoods, silencers, enclosures, etc., on
all sources of noise generation.
19. The proponent shall ensure that there shall not be any change in the process technology
and scope of working without prior approval from the Board.
20. Concealing the factual data or submission of fabricated data and failure to comply with any
of the conditions mentioned in this order attracts action under the provisions of relevant
pollution control Acts.
21. Notwithstanding anything contained in this conditional letter or consent, the Board hereby
reserves its right and power Under Sec.27(2) of Water (Prevention and Control of
Pollution) Act, 1974 and Under Sec.21(4) of Air (Prevention and Control of Pollution) Act,
1981 to revoke the order, to review any or all the conditions imposed herein and to make
such modifications as deemed fit and stipulate any additional conditions by the Board.
Page 6 of 7
22. Any person aggrieved by an order made by the State Board under Section 25, Section 26,
Section 27 of Water Act, 1974 or Section 21 of Air Act, 1981 may within thirty days from the
date on which the order is communicated to him, prefer an appeal as per Andhra Pradesh
Water Rules, 1976 and Air Rules,1982, to such authority (hereinafter referred to as the
Appellate Authority) constituted under Section 28 of Water (Prevention and Control of
Pollution)Act,1974 and Section 31 of the Air (Prevention and Control of Pollution) Act, 1981.
MEMBER SECRETARY
To
Page 7 of 7