Professional Documents
Culture Documents
Tigist Ketsela GC-2022 Hwy Project
Tigist Ketsela GC-2022 Hwy Project
Tigist Ketsela GC-2022 Hwy Project
ACKNOWLEDGEMENT
First and foremost, greatest thanks from the depth of our heart is to the almighty GOD,
for endowing us with the courage, strength as well as health throughout our school time
and the full help provided by him for the successful accomplishment of this final project
We would also like to express our gratitude to Rift Valley University, Labu-Lafto
Next, it is our deepest gratitude and respect to our project advisor Ebisa Adamu, (BSc in
civil engineering) for his valuable advice, sincerity, and very humble way of approach
throughout the working time for the successful completion of this project.
Finally, would like to express our sincere appreciation and heartfelt gratitude to our
families who are always keeping aside of us in contributing financial support and all the
way.
ABSTRACT
Transportation deals with the movement of humans and materials from Place to place. In
the world, there are various types of transportations like Road, railway, air, water, etc.
For rapid economic, social and industrial growth of our country, Ethiopia, a good
system of transportation is very necessary. This road design project connects two
Woredas in Oromia region, namely Dandi to Jaldu town. The topography of this project
route corridor is flat and rolling. The climatic condition of the project area combines
semi – cold and partly warm climatic features.
The reason why the project designer chosen this project was to contribute to the
development of the country at large, as it is straightforward that the development of a
certain nation in various perspectives is dependent on the level of the network of roads.
The other stand point was that, the project designer was highly eager to be part of those
scholars who are highway road designers and believed that, through doing this project,
his knowledge and skills towards designing highway roads will be improved profoundly.
The general objective of this project was to design a rural Link road highway from
Dandi to Jaldu. Whereas, the specific objectives were designing:-the horizontal and
vertical alignment of link road, flexible pavement of Link road and surface and
subsurface drainage of Link road. Estimating the cost of the project and recommending
possible remedial measures for design defects and shortcomings were also the specific
objectives of this project.
While performing this project, in addition to manual computations, the project designer
used software’s like MXROAD for design and analysis of horizontal and vertical
alignments, pavement design and earth work calculations. AUTOCAD for displaying
different cross sections of the roadway and hence obtain the values required. EXCEL for
calculating earth work quantities, calculating both horizontal and vertical curve
elements and thereby offsets, drawing mass haul diagram and the like.
The results of this project were geometric design, pavement and drainage design. The
project designer, designed the tangent sections, both vertical and horizontal curve
alignments, transition curves, super elevations, sight distances both passing and
stopping, cross sectional elements, gradients, calculation of earth work quantities and
hence, mass haul diagram, pavement and drainage designs.
Key words: - Transportation, link road, geometric design, pavement design, drainage
design, earth work, MXROAD, AUTOCAD, EXCEL.
TABLE OF CONTENTS
ACKNOWLEDGEMENT....................................................................................................i
ABSTRACT........................................................................................................................ii
ACRONYMS....................................................................................................................xiv
CHAPTER ONE..................................................................................................................1
INTRODUCTION...............................................................................................................1
CHAPTER TWO.................................................................................................................6
LITERATURE REVIEW....................................................................................................6
2.2.1 Tangents............................................................................................................12
2.3.4 Widening...........................................................................................................25
2.4.1 Profile................................................................................................................30
2.4.2 Gradients...........................................................................................................30
2.6.1 Right-Of-Way....................................................................................................52
2.9.4 Culvert...............................................................................................................80
2.10.1 Introduction.....................................................................................................84
CHAPTER THREE...........................................................................................................93
PROJECT METHODOLOGY...........................................................................................93
3.3 Methodology............................................................................................................94
CHAPTER FOUR..............................................................................................................95
4.4.1 Tangent..............................................................................................................96
CHAPTER FIVE.............................................................................................................142
5.1 Conclusion.........…………………………………………………………………142
5.2 Recommendation...................................................................................................143
References........................................................................................................................144
APPENDIX......................................................................................................................145
LIST OF TABLES
Table 2.1: Standards versus road classification...................................................................7
Table 2.12: Guide Values for the Minimum Provision of Passing Sight Distance...........48
LIST OF FIGURES
ACRONYMS
AADT Average Annual Daily Traffic
DS Design standard
DV Design vehicle
FH Free Haul
PC Point of Curvature
PI Point of Intersection
PT Point of Tangency
RF Rational Formula
ROW Right-of-way
WD Wheel Drive
CHAPTER ONE
INTRODUCTION
1.1 Back Ground
This two-lane highway project is located in west shawa part of Ethiopia in the region of
Oromia, connecting two woredas namely from Dandi to Jaldu towns. The project was
intended for the provision of well-designed and facilitated road for smooth and safe flow
This project, namely Dandi to Jaldu road design, the part that the project designer was
provided with, to design is about 2.980 Km which starts at about 0+000 chainage from
It links two towns, Dandi and Jaldu, which are at high economic growth, where these
towns are the capital city of Ginch and Gojjo towns respectively.
Topography
Topography of the area is also an influence in the different aspects of designing and
construction process of the road, beginning from the report on the corridor selection to
the geometric alignment. The topography data associating with hydrology for instance,
can provide a detail of relief and general stream direction and drainage patterns of the
region.
Low lands (mainly in the eastern regions, from below sea level to 500 meters
Plateau
Mountainous
Climatic condition of the zone has a strong influence on the designing of the road, soil
characteristics of the site, subgrade strength of the road and in general its construction
This is particularly true for our country where a wide range of climatic zones are
encountered, From desert in the north – east triangle to temperate and mountainous
(subalpine) over a significant part of the country with annual rainfall up to 1600 mm.
The climate for instance, influences the subgrade moisture content and strength and
required precautions to ensure adequate drainage. A rainfall also influences the selection
and is a potential incentive to use stabilized materials or borrowed fill materials as well as
Climatic condition also affects the nature of the soil and rocks encountered at subgrade
level. Soil forming processes are very active and the surface rocks are often deeply
weathered. The soils themselves occasionally display unusual properties which can pose
Climatic condition, especially preparation, has of great influential role in drainage facility
of the road. The design of drainage which includes the designing of culverts, bridges, side
ditches is based on the rainfall data of the catchment area. This data enables to design
hydrological data of the site which is the run off discharge. Associating with the
characteristics of the site soil, there will be high drainage cross-section with high
intensity of rainfall.
This project consists part of Dandi to Jaldu road which lies in B2 or the rainfall regions.
The climatic condition of the project area combines semi – cold and partly warm climatic
features. The mean temperature varies between 7.5oc to 27.5° c . The mean annual rainfall
The design of horizontal and vertical alignment of a given road is influenced by the
following factors: the functional classification of the road; the nature of the terrain; the
design vehicle; the traffic volumes expected on the road; the design speed; the density
and character of the adjoining land use; and economic and environmental considerations.
So, for the proper design of both horizontal and vertical alignment, the aforementioned
2. How to design the hot mix asphalt pavement of the link rural road?
In the design of hot mix asphalt pavement, the two governing criteria are the traffic class
and the sub grade strength. After assessing both of them strictly, the economical section
was selected from the possible charts for pavement design that are available on the ERA
3. How to design the surface & sub surface Drainage of the rural road?
The drainage system is designed after a proper hydrologic analysis. Factors like: drainage
meteorological characteristics could be evaluated with due care. After all, design
discharge was computed and a sufficient channel was designed as a means of surface and
Estimating the overall cost of the project is not easy. But after computing both the costs
of earth work and the pavement either manually or by the help of software’s, the total
cost was obtained and estimated thereafter. In this project, designer computed only the
5. What are the remedial measures to improve the design defect rural road?
The project designer prioritized repairs and maintenance to ensure safe travel and steady
Jaldu
2. Specific Objectives
or her practical knowledge and skill on road design and provide a clear and simplified
insight for the fellow students that means; they may use it as a sample while doing their
project. Hence, they will get a grasp of designing the geometric alignments, the pavement
The route of highway should be selected that it can handle the traffic sufficiently.
The route should involve the least impacts on the environment, etc.
In this project, the route was already selected and the project designer was provided with
parameters were: the horizontal and vertical alignments, cross- section, pavement and
This project was undertaken by the help of MX road, AutoCAD and Excel software’s.
CHAPTER TWO
LITERATURE REVIEW
2.1 Design Controls and Criteria
Choice of design controls and criteria’s is influenced by the following factors.
Due to the above factors, the design does not have to be constant for the whole length,
because those factors vary along the route of the road [3].
whole. The functional classification in Ethiopia includes five functional classes. The
following are the functional classes with their description according to ERA GDM.
Trunk Roads (Class I): Centers of international importance and roads terminating at
international boundaries are linked with Addis Ababa by trunk roads. It have a
present AADT≥1000, although they can have volumes as low as 100 AADT.
principal towns and urban centers must be linked between each other by link roads. A
typical link road has over 400 - 1000 first year AADT, although values can range
Main Access Roads (Class III): Centers of provincial importance must be linked
between each other by main access roads. First year AADTs are between “30-1000”.
Collector Roads (Class IV): A collector road must link roads linking locally important
centers to each other, to a more important center, or to higher-class roads. First year
Feeder Roads (Class V): Any road link to a minor center such as market and local
locations is served by a feeder road. First year AADTs are between 0-100.
Road Functional Design Design Traffic Surface Width (m) Design Speed (km/hr.)
Classification Standard Flow (AADT)* Type
Carriageway Flat Rolling Mountaino
us
In this project based on AADT1 and design period the functional classification of the
The geometric design elements of a road depend on the transverse terrain through
which the road passes. Transverse terrain properties are categorized into four classes
as follows:
Flat: Flat or gently rolling country, which offers few obstacles to the construction of a
Rolling: Rolling, hilly or foothill country, where the slopes generally rise and fall
Mountainous: Rugged, hilly and mountainous country and river gorges. This class of
Terrain imposes definite restrictions on the standard of alignment obtainable and often
involves long steep grades and limited sight distance (transverse terrain slope from 25
percent to 50 percent).
Escarpment: In addition to the terrain classes given above, a fourth class is added to
cater to those situations whereby the standards associated with each of the above
roadway sections, or side hill transverse sections where earthwork quantities are
slope (%)
controls in geometric design of highway. The road elements affected by design vehicle
include:
According to ERA geometric manual there are four general designs vehicle include:-
Designation Turning
Radius (m)
4x4 Utility DV1 1.3 2.1 5.8 0.9 1.5 3.4 7.3
Vehicle
Single Unit Truck DV2 4.1 2.6 11.0 1.5 3.0 6.5 12.8
Single Unit Bus DV3 4.1 2.6 12.1 2.1 2.4 7.6 12.8
A highway necessary has wide ranging effects in addition to providing traffic service to
uses it is essential that the highway considered as an elements of the total environment
that includes the human and plant communities. The highway can & should be located &
designed to complement its environment. Highway location and decision have an affect
The Design Speed is used as an index which links road function, traffic flow and
terrain to the design parameters of sight distance and curvature to ensure that a driver is
presented with a reasonably consistent speed environment. In practice, most roads will
geometric elements. Design elements such as lane and shoulder widths, horizontal
radius, super elevation, sight distance and gradient are directly related to, and vary,
with design speed. Thus all of the geometric design parameters of a road are directly
related to the selected design speed. It is important to note that the design of a road in
accordance with a chosen design speed should ensure a safe design. The various design
minimum values for one or a few of the elements at a particular location when
the other elements are considerably above the minimum requirements. For this
horizontal curves, which have normally circular curves with or without transition (spiral)
curves. The basic feature of horizontal alignment includes minimum radius, transition
curves, super elevation and sight distance [3]. Changes in direction are necessary in high
In this sub topic tangents, minimum radius, design speed, horizontal curves and super
elevation which are considered while designing the horizontal alignment will be
presented.
2.2.1 Tangents
According to its geometric definition a tangent (straight) section is the shortest distance
between two points. Straight section is advantageous because it has no centrifugal force
aesthetic point of view, tangent sections may often be beneficial in flat country but are
Even though straight sections have the above mentioned advantages, long tangent
sections increases the danger from head height glare and usually land to excessive
speeding. The length of a tangent section should not exceed 4.0 Kilometers. But due to
the land features of the project road, tangent with length greater than 4 Kilometers is not
encountered [3].
design speed and curvature and on their joint relationships with super elevation and side
friction. Curves are provided along the routes of highway where the change in direction is
tangent distance, external distance, middle ordinate, cord length depends on the design
Reverse curve
Compound curve
Spiral curve
horizontal alignment the use of compound curve, reverse, broken back and switch back
should be avoided except where very unusual topographic or right-way condition dictates
the use of these curves. When a vehicle moves in a circular path, it is forced radially
of the roadway land or the side friction developed between the tires and the road surface.
For calculation of the minimum horizontal radius, R min, for a particular design speed,
R min=VD2/127(e + f)
Side friction factor (f) 0.18 0.17 0.17 0.16 0.15 0.14 0.14 0.12 0.10
standards are:-
Deflation angle
Curve length
Radius of curve
Design speed
methods of setting a curve on the field depend on the type of the curve. For this particular
project, since all the circular curves are provided with transition, there are two options to
1. Offset Method
In this project all the parameters required to set the horizontal curves are prepared using
the method of deflection angles. This method is used because while designing the
horizontal curves Euler spiral formula was used and the offset method is not applicable
is provided to avoid immediate transition from straight line to simple curve. In other
words, it avoids the discontinuity in the curvature value, which is unsatisfactory for the
demand of a constant route development. Here curvature value linearly increases from
zero at the beginning of spiral curve to the constant value at the end of the spiral (i.e. at
Spiral curves are also advantageous because they fit the transition length needed to
develop the full design super elevation without the need to develop any transition on
A more practical control for the length of spiral is that it should equal the length needed
length that allows for a comfortable increase in lateral acceleration as a vehicle enters a
curve [2].
Ls,min= √(24R*Pmin)
Where: Pmin= minimum lateral offset between the tangent and circular curve (0.20m)
2. Criteria based on lateral shift are intended to ensure that a spiral curve is sufficiently
long to provide a shift in a vehicles lateral position within its lane that is consistent with
The use of lower values of ‘C’ will yield longer, more comfortable spiral curve lengths.
However, such lengths would not represent the minimum length consistent with driver
comfort.
the circular curve. Such problems occur when the spiral is so long as to mislead the driver
about the sharpness of the approaching curve. A conservative maximum length of spiral
that should minimize the likelihood of such problems can be computed as [1]:-
L s, max=√ (24*P max *R, Where: - maximum lateral offset between the tangent and
P
Δ
T L S
P
P
l
φs R R
φs
Δ-
2. Shift: - circular curve shifted inward towards the center to make space for additional
spirals.
S=Ls2/24R
S= shift, m
R= Radius, m
The central angel subtended by the circular portion of the curve is:
∆C = ∆-2θS
LC=R* ∆C =R [∆-2θS]
The length X being offset from tangent to curve can be used to locate points on the
elevation runoff and super elevation run out without in cooperating the transition curves
in the horizontal alignment. In other words it considers only transition the roadway
tangent directly adjoins the main circular curves. Super elevation runoff and run out
section first the super elevation and normal crown slope should be determined [3].
at the horizontal curve. Its main purpose is to counterbalance the centrifugal force and it
contributes safety and comfort feeling to the passenger while passing along changed
There are two forces acting on the vehicle that passes through the horizontal curve [1].
1. Centrifugal forces: Force acting outward in radial direction. It depends on the moving
Mathematically F=mv2/r
v= speed
r= radius of curve
2. Weight of the vehicle: The weight of the vehicle act downward on moving vehicle it
related to the road way super elevation and side friction developed between the tires and
Mathematically
e + f = v2/127R
f= side friction
v= velocity (km/hr.)
The maximum super elevation rate applied on highways controlled by climate condition,
terrain condition, type of area and frequency of very slow moving vehicles.
To decide the amount of super elevation we use ERA geometric design manual and
AASHTO jointly. ERA provides Super elevation with maximum Super elevation of 8%.
In design of curves without spirals the super elevation runoff is considered to be that
length beyond the tangent run out. Empirical methods are employed to locate the super
elevation runoff length with respect to the point of curvature (PC). Current design
practice is to place approximately two-thirds of the runoff on the tangent approach and
In providing of run out length, at the same time there is a calculated designed speed value
When a fast moving vehicle enters a horizontal curve, it will experience out ward force
(centrifugal). If the value of this force exceeds the lateral resistance like friction between
Therefore, drivers are advised to reduce their speed before entering the curve. Designers
give transversal slope tilt the road on horizontal curves to reduce vehicle skidding. This
Design speed
The centerline
The inside
The outside
It consists of the length of the road way needed to accomplish a change in outside-lane
cross slope from zero (flat) to full super elevation length or vice versa.
The length of tangent run out is determined by the amount of adverse cross slope to be
removed and the rate at which it is removed. To effect smooth edge of pavement profile,
the rate of removal should equal the relative gradient used to define the super elevation
Super elevation drawing should be done after determining the super elevation rate, super
elevation run out. This drawing is used during phasing of horizontal and vertical
alignment.
To draw super elevation and normal crown the following procedure was followed:
Select an appropriate scale for drawing which make super elevation visible.
Mark the point PC and PT of horizontal curve along the station under profile.
Write the necessary parameter: Super elevation rate and angel of deflection, Δ.
If ∆ is to the right, curve is to the right and the outer side has positive super elevation and
this minimize the peak lateral acceleration and the resulting side friction demand and a
spiral path results from a driver’s natural steering behavior during curve entry or exit.
This natural spiral usually begins on the tangent and ends beyond the beginning of the
circular curve. One third portion length of the runoff length is placed on the tangent and
In the alignment design with spirals, the super elevation runoff is affected over the whole
the transition curve. The length of the super elevation runoff is almost equal to the spiral
length for the tangent to spiral (TS) transition at the beginning and the spiral to curve
(SC) transition at the end of circular curve. The change in the cross slope began with
removing the adverse cross slope from the lane or lane on the outside of the curve on the
Between TS and SC, spiral curve and the super elevation run out are coincide and
travelled way is rotated to reach the full super elevation at SC. This arrangement reversed
on leveling the curve. In the alignment transition, the whole of the circular curve portion
2.3.4 Widening
The traveled way on horizontal curve is widened to make operating conditions on curves
comparable to those on tangents. The amount of widening needed increases with the size
of the design vehicle and decreases with increasing radius of curvature. For some
conditions of speed, curvature, and width it remains appropriate to widen traveled ways.
1. The design vehicle occupies a greater width because the rear wheels generally
2. Drivers experience difficulty in steering their vehicles in the center of the lane.
The effect of variation in lateral placement of the rear wheels with respect to the front
curves but the appropriate amount of widening cannot be determined since it depends on
The width elements of the design vehicle used in determining the appropriate roadway
widening on curves include the track width of the design vehicles that may meet or pass
vehicle. The design vehicle should usually be a truck because off tracking is much greater
for trucks than for passenger cars. Widening is costly and it is not appropriate to provide
for all curves. The amount of widening to be provided for curves is specified only by
reasonably smooth alignment of the edge of the traveled way and to fit the paths of
On simple (not spiraled) curves, widening should be applied on the inside edge of
On curves designed with spirals, widening may be applied on the inside edge or
divided equally on either side of the centerline. In the latter method, extension of
the outer edge tangent avoids a slight reverse curve on the outer edge.
Preferably, widening should transition over the super elevation runoff length, but
From the stand point of usefulness and appearance, the widening should be
smooth.
DS5 at high fill. Since, the project road is DS3, widening for fill should be provided. The
height of fill in the table below is measured from the edge of the shoulder to the toe of the
slope. [3].
Curve (m) Single Lane (m) Two Lanes (m) Height of fill (m) Amount (m)
<20 Switchbacks
Note; in this project we have not designed curve widening because all of our radiuses are
following the design speed will find it difficult to remain in the traffic lane. Curve
widening reduces such problems. Curve widening shall generally be applied to both sides
of the roadway. It should start at the beginning of the transition curve and be fully
by vertical curves. The basic design features of vertical alignment include vertical
profiles, grades, critical length of grades, climbing lane, and vertical curve length. Since
the vertical alignments are the most critical elements in the determination of the project
The characteristics of vertical alignments are greatly influenced by basic controls related
to design speed, traffic volumes and composition, road classification, sight distance,
natural and cultural resources, and terrain. Due to these basic controls, vertical alignment
In this road project, we have considered the following criteria’s in the selection of
vertical alignments.
Gradient of the route are between the allowable maximum and minimum.
Avoiding of combination of two vertical curves in the same direction, i.e. they
2.4.1 Profile
It is the vertical aspect of the road, including crest and sag and the straight grades
connecting them.
Profile is a drawing showing the original ground level as it is plotted using the elevation
data calculated from the contour data. Profile is drawn longitudinally along the centerline
of the road using the centerline elevation obtained from the contour at each interval
(station). Once the natural ground level is plotted, vertical alignment parameters are
addition of climbing lane, addition of emergency escape ramps and provide sufficient
sight distance.
2.4.2 Gradients
One of the important considerations in designing a high way is the gradient. The cost of
operation vehicles, the speed of vehicles, and the capacity of high way are largely
operation as far as possible for the given terrain and vertical profile should be as smooth
as economical. Due to the above controls desirable gradient are appropriate for design
purpose. But, the limiting gradient may be used where the topography of the area
complies this or where the adoption of gentler gradient enormously adds with the cost.
Sometimes exceptional gradient can be used in very exceptional situations and for short
lengths the selection of ruling (desirable) gradient and limiting gradient are based on
DS8
D A D A D A D A D A
Flat 3 5 4 6 6 8 6 8 6 8
Rolling 4 6 5 7 7 9 7 9 7 9
Mountainous 6 8 7 9 10 12 13 15 14 16
Escarpment 6 8 7 9 10 12 13 15 14 16
Urban 6 8 7 9 7 9 7 9 7 9
Based on the above values grade can be determined from the plotted vertical profile by
1
considering the natural ground or profile. This profile drawing is used as guide to decide
a grade or longitudinal slope from which amount of the earth work is computed. In
determining grade from the plotted profile the straight line is drawn which best fits the
natural ground and the slope the line between two points is calculated by:-
levation 2−Elevation 1
Slope=
Station 2−station 1
The value obtained is compared with the value on the ERA manual and it should conform
to the desirable gradient as much as possible, we have to consider the following when we
I. Maximum gradient
Vehicle operation on gradients depends on number of factors, severity and length of the
gradient, level and composition of the traffic and number of overtaking opportunities on
the gradients and its vicinity. Therefore, due to the above factors, the maximum gradient
should not exceed in design of the high way because the traffic is unable to ascend the
grade above the maximum limited grade. Although it adds cost to develop the road
infrastructure, ERA finds it in the position where it has no choice than the limiting
Standards for desirable maximum gradient were set to assure user comfort and to avoid
severe reduction in the design speed but if occasional terrain is encountered that requires
excessive earth work to reduce the vertical alignment to desirable standard on absolute
maximum gradient can be used. See table 2.8 above the desirable and maximum gradient
cut section or hill roads, or along curbed edge of pavement, a certain minimum
longitudinal gradient is necessary for efficient drainage however, flat grades can be
typically used without the problem on uncurbed high way where the cross slope is
adequate to drain the pavement surface laterally. But, with the curbed high way or street
longitudinal grades should be provided to facilitate surface drainage. For this purpose the
appropriate minimum grade is typically 0.5%, but grade of 0.3% may be used where
there is light type pavement accurately sloped and supported on firm sub grade [3].
point at which it has lost a certain amount of speed. Critical length of gradient is
considered to be the maximum length of a designated upgrade upon which a loaded truck
Critical length of gradient is, to some extent, dependent on the gradient of the approach; a
downhill approach will allow vehicles to gain momentum and increase the critical length.
In general, the critical length of gradient decreases as gradient increases. This is shown in
climbing lane is an auxiliary lane added outside the continuous lanes and has the effect
of reducing congestion in the through lanes by removing slower moving vehicles from
the traffic stream. It also enhances road safety by reducing the speed differential in the
through lane. The requirements for climbing lanes are therefore based on road standard,
speed and traffic volume. Benefits from the provision of a climbing lane accrue because
faster vehicles are able to overtake more easily, resulting in shorter average journey
times, reduced vehicle-operating costs, and increased safety. Benefits will increase with
increases in gradient, length of gradient, traffic flow, the proportion of trucks, and
queues of vehicles held up by a slow moving truck will continue for some distance along
the road [3]. On this project the length of the gradient and the maximum gradient is not
greater than the critical length of the gradient and the maximum gradient given on ERA
grades .It is normally provided at points of change in grades. Vertical curve provision is
vertical curve can be either crest vertical curve or sag vertical curve depending on
position of points of vertical intersection ,in either case vertical curve should be simple in
application and result in design that is safe and comfort in operation, pleasing in
appearance and adequate for drainage the major control for safe operation on crest
vertical curve is the provision of adequate sight distance once for design speed because
vertical curve with limited sight distance recommended that all vertical curve should be
There are two types of curves. Summit (crest) and sag (valley) curves, which are
gradient occurs. The minimum length of vertical curves can be calculated using a formula
based on comfort and stopping sight distance requirement and the governing one can be
used. In determining the length of the curve the following points are taken in to account
Curvature
general appurtenance
gradient. The minimum values for sag vertical curves are determined by the required
head light sight distances, drainage requirements and the level of driver’s comfort
expected. Short sag vertical curves and short grades between two vertical curves have to
be avoided.
The length of the curve is determined by taking the following criteria’s in to account:-
passengers comfort
drainage control
general appearance
In the design of the vertical curves we have tried to avoid short sag vertical curves and
of which both crest vertical curves and sag vertical curves are incorporated. The type of
curve and the grade in which those curve are incorporated are listed as below:
As ERA design manual specification the minimum length requirement for vertical and
sag curves have been designed to provide sufficient stopping sight distance. The design is
based on allowable K-value for different design speed and algebraic difference in grades
they provide.
L=KA
The minimum value for crest vertical curves and sag vertical are provided by [3].
20 2 10
30 3 50
40 5 90
50 10 130
60 18 180
70 31 250
85 60 350
20 2 10
30 4 50
40 8 90
50 12 130
60 18 180
70 25 250
85 36 350
100 51 480
120 74 680
Using the above K-value from the table, the minimum length of vertical curve is
calculated.
the line of the road appears to a driver to flow smoothly, avoiding the creation of hazards
and visual defects. It is particularly important in the design of high-speed roads on which
a driver must be able to anticipate changes in both horizontal and vertical alignment well
within the safe stopping distance. It becomes more important with small radius curves
defects occur, phasing may be achieved either by separating the curves or by adjusting
their lengths such that vertical and horizontal curves begin at a common station and end
one end of each of the curves is at a common station. Cases of mis-phasing fall into
several types.
If a vertical curve overlaps either the beginning or the end of a horizontal curve, a
driver’s perception of the change of direction at the start of the horizontal curve may be
the curves. If this is uneconomic, the curves must be adjusted so that they are coincident
at both ends, if the horizontal curve is of short radius, or they need be coincident at only
one end, if the horizontal curve is of longer radius.in our project vertical and horizontal
If there is insufficient separation between the ends of the horizontal and vertical curves, a
false reverse curve may appear on the outside edge-line at the beginning of the horizontal
Corrective action -Can be corrected by increasing the separation between the curves; or
Mis-phasing 3-both ends of the vertical curve lie on the horizontal curve
If both ends of a crest curve lie on a sharp horizontal curve, the radius of the horizontal
curve may appear to the driver to decrease abruptly over the length of the crest curve. If
the vertical curve is a sag curve, the radius of the horizontal curve may appear to
increase.
Corrective action -make both ends of the curves coincident, or to separate them.
-If a vertical crest curve overlaps both ends of a sharp horizontal curve, a hazard may be
created because a vehicle has to undergo a sudden change of direction during the passage
If the horizontal curve is less sharp, a hazard may still be created if the crest occurs off
the horizontal curve. This is because the change of direction at the beginning of the
horizontal curve will then occur on a downgrade (for traffic in one direction) where
Corrective action-make the curves coincident at one end so as to bring the crest on to the
horizontal curve.
If the vertical curve is a sag curve, an illusory crest or dip, depending on the “hand” of
Other mis-phasing
A sag curve occurs between two horizontal curves in the same direction.
ability to see ahead is of the utmost importance in the safe and efficient operation of a
vehicle on a highway. For safety on highways, sight distance of sufficient length that
drivers can control the operation of their vehicles to avoid striking an unexpected object
in the traveled way should be provided. Two lanes high way should also have sufficient
sight distance to enable drivers to occupy the opposing traffic lane for passing other
vehicles without risk of a crash. In general two-lane rural highways should provide such
passing sight distance at frequent intervals and for substantial portions of their length.
1. The sight distances needed for stopping, which are applicable on all highways;
2. The sight distances needed for the passing of overtaken vehicles, applicable on all
highways;
4. The criteria for measuring these sight distances for use in design.
vehicle, traveling at a given speed, to bring his vehicle to a stop after an object on the
road becomes visible. In other words, the available sight distance on roadway should be
sufficiently long to enable a vehicle traveling at or near the design speed to stop before
reaching a stationary object on its path. Although greater length of visible roadway are
desirable, the sight distance at every point along a roadway should be at least that needed
for below-average driver or vehicle to stop. Stopping sight distance is the sum of brake
recognizes the existence of an obstacle on the roadway a head that necessitates braking to
the instant that the driver actually applies the brakes. Such determination take time and
the amount of time needed varies considerably with the distance to the object, the visual
acuity of the driver, the natural rapidity with which the driver reacts, the atmospheric
visibility, the type and the condition of the roadway, and nature of the obstacle [1].
Vehicle speed and roadway environment probably also influence reaction time and a
2.5sec brake reaction time for stopping sight situations encompasses the capabilities of
most drivers.
d1=0.278Vt
d=d1+d2
2
v
d=0.728Vt +
254 f
20 .42 20 160 50
30 .40 30 217 75
When a highway is on a grade, the equation of braking distance is modified to take the
Where; G – is the percentage of grade divided by 100. And the other terms are as
previously stated.
The stopping sight distances needed on upgrades are shorter than on level roadways and
The positive sign is used inside the brackets, if the gradient is upgrade and negative is
used when it is down grade. In this case the stopping sight distance is given by:
with sight distance for the design speed as a control the actual conditions on each curve
sight distance.
widen cuts on the insides of curves to obtain the required sight distance [3].
Using radius of curvature and sight distance for the design speed, gives the middle
ordinate (M) which is the clear distance from centerline of inside lane to the obstruction.
Comfort: L = 0.038(GV3)1/2
that must be available to enable the driver of one vehicle to pass another vehicle safely
without interfering with the speed of an oncoming vehicle traveling at the design speed.
Within the sight area the terrain should be the same level or a level lower than the
roadway. If passing is to be accomplished safely, the passing driver should be able to see
a sufficient distance ahead, clear of traffic, to complete the passing maneuver without
cutting off the passed vehicle that appears during the maneuver. When appropriate, the
driver can return to the right lane without completing the pass if the driver sees opposing
Sight distance should be determined for a single vehicle passing a single vehicle. Longer
sight distances occur in design and such locations can accommodate an occasional
multiple passing. Sight distance records also are useful on two-lane highways for
less than the minimum needed for passing. This is important in evaluating capacity and it
is a simple process to determine the percentage of length of highway with a given sight
Table 2.12: Guide Values for the Minimum Provision of Passing Sight Distance
standard
The passing sight distance is determined by a formula with four components, as follows:
PSD = d1 + d2 +d3 + d4
d1_ initial maneuver distance, including a time for perception and reaction
ERA geometric design manual provides the PSD for different speed. For our project we
vehicle traveling downgrade because the overtaking vehicle can accelerate more rapidly
than on the level and thus can reduce the time of passing. However, the over taken
vehicle can also accelerate easily so that a situation akin to a racing contest may result.
The sight distance needed to permit vehicles traveling upgrade to pass safely are greater
than those needed on level roads because of reduced acceleration of the passing vehicle
which increases the time of passing and the likelihood that opposing traffic may speed up
which increases the distance traveled by an opposing vehicle during the passing
maneuver [1].
In this project while vertical alignment is done all the above consideration was taken in to
account on choosing the grade and the vertical length of the grade in order to make
calculated by the formula described in stopping sight distance with value of h 1=1.07 and
h2=1.30m [3].
The passing sight distance is generally determined by a formula with four components, as
follows:
d1=0.278tı (v-m+atı/2)
v = average speed of passing vehicle, is taken to be 85Km/hr. for safety out of the
d3 = safe clearance distance between vehicles at the end of the maneuver, is dependent on
d3(m) 30 50 80 100
Less the portion of d2 whereby the passing vehicle is entering the left lane.
Estimated at:
d4 = 2d2/3
PSD = d1+ d2 + d3 + d4
less the portion of d2 whereby the passing vehicle is entering the left lane.
Estimated at:
d4 = 2d2/3
It is calculated with the same formula for stopping sight distance. But h 1=1.07m &
h2=1.30m [3]
and traffic requirements. Even though the cross section may vary over a particular
route because of varying controlling factors, the section should be designed in such a
way that it can fulfill the basic requirements. The basic requirements include:-
the route.
Any changes of a cross section shall be affected gradually & logically over
because it will not be feasible to replace it. Here traffic sings & road markings are
Road cross section normally consists right of way, lane width, carriage way, shoulder
width, normal cross fall, side slope and back slope, and road side ditch will be discussed
[3].
2.6.1 Right-Of-Way
Right of way provided in order to accommodate road width and to enhance the safety,
operation and appearance of the roads. The width of right-of-way depends on the
cross section elements of the highway, topography, and other physical controls
right-of-way to accommodate all elements of the cross section and appropriate border
areas, right-of-way widths should be limited to a practical minimum in both rural and
developed areas affecting the economy of the inhabitants. Right of ways will be
equidistant from the centerline of the road to the left and to the right of the carriageway.
% Passing Opportunity % 50 33 25 0
Right of Way m 50 50 50 50
exclusive of shoulders. For link roads of design standard, DS3 7m wide paved travel way
is provided. The traveled way width at a horizontal curve section is larger due to the
widening applied for the curve. The travelled way width is varied from the beginning of
the start of transition runoff to the point of full super elevation is attained. Travelled way
For this project the lane width considered based on the design standard adopted which is
DS3 Link road is 7.0 m since no widening for curve is not provided [3].
normal cross fall should be 2.5 percent on paved roads and 4 percent on unpaved roads
as shown on table above. Shoulders having the same surface as the roadway should
have the same normal cross fall. Cross fall of the roadway. Normal cross-fall of 2.5%
and shoulder cross-fall Normal cross fall (or camber, crown) should be sufficient to
provide adequate surface drainage whilst not being so great as to make steering
difficult. The ability of a surface to shed water varies with its smoothness and
integrity [3].
way. In contiguous with the travelled way, it is used for accommodation of stopped
vehicles for emergency use, for lateral support of the base and surface courses. For DS3
ERA recommends shoulder width of 1.50m-3.00m for both flat and rolling terrain. Since
project road is rural road way and there will not be large number of non-motorized traffic,
as a result we adopted 1.50m shoulder width of the entire road for economical reason [3].
Embankment or fill slopes parallel to the flow of the traffic may be defined as
Recoverable slopes: 1:4 or flatter slopes are categorized under this category. A driver
who encroaches on this kind of slope can easily stop or return to the roadway easily.
Non-recoverable slopes: slopes between 1:3 to1:4 generally fall into this category. A
driver will be unable to stop and return the vehicle easily to the roadway.
Critical slopes: slopes on which a vehicle is likely to overturn, Slopes steeper than
1:3 generally falls in to this category. The selection of aside slope & aback slope
dependent on four factors: safety consideration, height of cut or fills, Type of material
and economic consideration. Side slopes should be designed to insure the stability
Cut Fill
Earth or Soil 0.0 - 1.0m 1:4 1:4 1:3 Recoverable
1.0 - 2.0m 1:3 1:3 1:2 Non-recoverable
Over 2.0m 1:2 1:2 1:1.5 Critical
Rock Any height See Standard Details Critical
Black Cotton Soil* 0.0 - 2.0m - 1:6 - Recoverable
Over 2.0m 1:4
mountainous and escarpment terrain, and 1.0m elsewhere. Side drains should be
avoided in areas with expansive clay soils such as black cotton soils. Where this is not
possible, they shall be kept at a minimum distance of 4-6m from the toe of the
Figure 2.17. The ditch in this instance should have a trapezoidal, flat-bottom
configuration [3].
haul diagram are essential elements in providing the best-combined horizontal, vertical,
and cross-sectional design. This is especially true when the design includes
consideration of the least cost in relation to earthworks. Key terms associated with this
Borrow- material not obtained from roadway excavation but secured by widening
cuts, flattening back slopes, excavating from sources adjacent to the road within the
Waste- material excavated from roadway cuts but not required for making the
embankment.
Free Haul (FH) - the maximum distance through which excavated material may
be transported without the added cost above the unit bid price.
Overhaul- excavated material transported to a distance beyond the free haul distance.
The steps involved in the computation of earthwork quantities and the development of
Earthwork calculations
These steps are presented in the following text. Of note is the fact that most current
highway design computer programs, including MX (MOSS), will produce the mass
haul diagram as part of the output when typical sections and horizontal and vertical
alignments are inputs. A final stage of geometric design is then usually to make
quantities [3].
1. Planimeter Method - The original ground line and template section (cross
section) must be plotted on grid paper. Centerline profile grade must first be
calculated for each cross section station to determine the centerline reference of each
template plot. Areas of cut and fill quantities are calculated using a planimeter,
2. Electronic Computer Method - This method is widely used due to its versatility
and speed of calculations. The end area calculation on modern computer programs is
an integral part of the alignment design program and shown on output listings
end area" method. This method consists of averaging the cut and fill quantities of
cubic meters of excavation and embankment between the two stations. This
procedure is followed when manual methods are used. Projects designed by computer
will be tabulated on the mass plot listing and these calculations are integral parts of the
compaction factor to the excavation so that a compaction factor of –25 percent would
meters. Likewise, a 10 percent swell factor would result in 100 cubic meters of rock
should be determined or estimated for each project taking into consideration the
various types of soils and depth of proposed cuts and fills. Accumulation totals of cut and
Total accumulated fill is the sum of the embankments from station to station
( no adjustment)
The mass ordinate can now be calculated by taking the algebraic sum of adjusted
excavation and unadjusted embankment from station to station, using "+" for
survey and the ordinates represent the algebraic sum of excavation and embankment
quantities from some point of beginning on the profile. The plot can be to any scale,
depending on the quantities involved. Project designed by computer will list, tabulate,
and plot all of the data shown above including a mass haul diagram and balance points.
The mass haul diagram shows excavation (adjusted) and embankment quantities from
some point of beginning on the profile, considering cut volumes positive and fill
volumes negative. At the beginning of the curve the ordinate is zero, and ordinates
are calculated continuously from the initial station to the end of the project. The mass
Direction of haul.
downward slope indicates embankment. The steeper the slope of the mass curve, the
b) The maximum ordinate of the mass curve occurs at the point where excavation ends
and embankment starts. Similarly, the minimum ordinate occurs at the point where
c) Cut and fill quantities between the points at which any horizontal line cuts off a loop
of the mass curve will exactly balance. Such horizontal lines are called balance lines
and the points at which these lines intersect the mass curve are called balance points.
d) Areas below the balance line indicate that hauling of excavation to embankment is
from right to left, whereas areas above the balance line indicate that the haul is from
left to right.
e) The area between a balance line and its corresponding loop of the mass curve is a
f) The ordinate at any station represents the accumulated amount of surplus or deficit of
material at the station. It does not indicate the amount of cut or fill volume at that
According to ERA 2002 there is a recommended shrinkage and swelling factor therefore
the following tables show the recommended values of Shrinkage factors [3].
surfaces for safe and speedy movement of people and goods with an acceptable level of
comfort to users. The basic idea in building a pavement for all-weather use by vehicles
that will:-
Have sufficient total thickness and internal strength to carry expected traffic.
Have a surface that is reasonably smooth and skid resistant at the same time, as
The two major considerations in structural design of high way pavements are:-
Thickness design
pavement surface, and transfer and spread that load to the sub grade without
exceeding either the strength of the subgrade or the internal strength of the pavement
itself [3].
1. Flexible pavement.
Flexible pavement provides sufficient thickness for the load distribution through a
multilayer structure so that the stresses and strains in the subgrade soil layers are within
the required limit. It is expected that the strength of subgrade soil would have a direct
bearing on the total thickness of the flexible pavement. The layered structure is designed
to take the advantage of the decreasing magnitude of stresses with depth [3].
2. Rigid pavements
Rigid pavements (also called concrete pavements), as the name implies, are rigid and
concrete slab, unlike flexible pavements where successive layers of the pavement
A relatively thin pavement slab distributes the load over a wide area due to its
high rigidity. Localized low strength subgrade materials can be overcome due to
last longer.
concrete does not suffer deterioration from weathering. Neither its strength nor
Concrete Slab
Rigid
Sub base
Capping Layer
(If required)
Subgrade
Natural ground or
Embankment
3. Composite pavements
A composite pavement is composed of both HMA and PCC. The use of PCC as a bottom
layer and HMA as top layer results in an ideal pavement with the most desirable
characteristics. The PCC provides a strong base and the HMA provides smooth and non-
reflective surface. However, this type of pavement is very expensive and is rarely used as
for the purpose of decreasing the load distribution to the sub grade and to limit the
Base Course: - Base and sub base layers of the flexible pavement make up
larger proportion of the total pavement thickness needed to distribute the stresses
imposed by traffic loading. Crushed stone is commonly used for this purpose.
Sub-base Course: - is lower quality than the base material in strength, plasticity
and gradation but superior to sub grade material. It can be compacted granular
Subgrade: - it is a natural soil forming the road bed for pavement construction. Depth of
compaction and compacted density requirement depends on the type of soil, and
total traffic loading during service that determines the actual design life of the pavement.
It is thus more appropriate to associate the design traffic loading is for pavement design.
The ultimate aim of traffic analysis for pavement design is to determine the magnitude of
wheel loads and the number of times each of these loads will be applied on the pavement
during its design life. For highway pavement the computation of design traffic loading
multiple unit trucks expected to use the high way must be estimated.
In this project, the traffic load computation factor is taken from ERA design manual,
since there is no available data for axle load survey. Using this factor and data from
traffic counts, the equivalent standard axle load (ESA) is computed to classify the road
in both directions. To determine the design traffic loading on the design lane, one must
split the traffic by direction and distribute the directional traffic by lanes. An even split
assigning 50% of the traffic to each direction appears to be the norm. If an even split
occurs, pavements are designed based on the heavier directional traffic loading. The
directional split for this purpose is 50%. The design lane for pavement structural design is
usually the slow lane (lane next to the shoulder in most cases) in which a large proportion
of directional heavy vehicle traffic is expected to travel. This principle is used to design a
highway which has more than two travel lanes. But since the highway which has more
than two lane, the design lane is the one with large number of traffic composition or the
design lane is the one with large number of traffic composition or. If the directional split
Many factors may influence this decision, including budget constraints. However, the
taking into account the conditions governing the project. Some of the points to be
considered include:
Traffic volume
Financial constraints
It generally appears economical to construct roads with longer design periods, especially
for important roads and for roads with high traffic volume. Where rehabilitation would
cause major inconvenience to road users, a longer period may be recommended. For
roads in difficult locations and terrain where regular maintenance proves to be costly and
Trunk Road 20
Link Road 20
Other Roads 10
equivalent axle loads. The types of vehicles are defined according to the breakdown
adopted by ERA for traffic counts: cars; pick-ups and 4-wheel drive vehicles such as
Land Rovers and Land Cruisers; small buses; medium and large size buses; small trucks;
medium trucks; heavy trucks; and trucks and trailers. This breakdown is further
simplified, for reporting purposes, and expressed in the five classes of vehicles (with
Code
tons load
Truck
categories [3].
Normal Traffic: - traffic which would pass along the existing road or track even if new
Diverted Traffic: - traffic that changes from another route or made of transport to the
project road because of the improved pavement, but still travels between the same origin
and destination.
1. Determine the initial traffic volume (AADT0) using the results of the traffic survey
and any other recent traffic count information that is available. For paved roads, detail the
2. Estimate the annual growth rate “i” expressed as a decimal fraction, and the anticipated
number of years “x” between the traffic survey and the opening of the road.
3. Determine AADT1 the traffic volume in both directions on the year of the road
For paved roads, also determine the corresponding daily one-directional traffic volume
4. Determine the average daily one directional traffic flow on the year of opening for
5. Make forecast of cumulative one directional traffic flow for each class of vehicle to
determine the total traffic in each class that will travel over the design lane using the lane
6. Determine the EALF for each class of vehicle and for each direction from the results of
7. The product of the cumulative one directional traffic flow and the mean EALF is the
The base year is 2015 when the collected data is for analysis.
In paved roads, determine the corresponding one-directional traffic volume for each type
of vehicle. Then the cumulative number of vehicles, T over the chosen design period N
(in years) is
Ti = cumulative volume of traffic for the ith commercial vehicle class in the design
lane over the design period (adjusted for lane distribution and direction).
the axle loads of the vehicles. For pavement design purposes the damaging power of
axles is related to a “standard” axle of 8.16 metric tons using empirical equivalency
factors. In order to determine the cumulative axle load damage that a pavement will
sustain during its design life, it is necessary to express the total number of heavy vehicles
that will use the road over this period in terms of the cumulative number of equivalent
standard axles (ESAs). Axle loads can be converted and compared using standard factors
to determine the damaging power of different vehicle types. A vehicle’s damaging power,
or Equivalency Factor (EF), can be expressed as the number of equivalent standard axles
(ESAs), in units of 80kN. The design lives of pavements are expressed in terms of the
The following table shows traffic classes with their range of ESAs [3].
Based on the computation performed in the above table total ESAs equals to
base, base course and pavement. Sub grades are commonly compacted before the
sub base is laid. The types and strength of sub grades are largely determined by the
location of the road. The soil within the corridor of the road usually varies significantly
in strength from place to place thus, strength of road sub grade should be determined
&the determination of sub grade strength is assessed in terms of CBR which depends
S1 2
S2 3-4
S3 5-7
S4 8-14
S5 15-29
S6 30+
to a safe level at which sub grade deformation is insignificant whilst at the same time
ensuring that the road pavement layers themselves do not deteriorate to any serious
The thickness of the pavement is selected from the structural catalogue chart. The
selection of chart depends on variety of factors but should minimize total cost. Given
highway. For a highway to serve its function properly, it should be provided with
drainage facility. It is aimed at the protection of the road through the prevention of
damage due to water to achieve a chosen level of service without major rehabilitation at
the end of the selected design period, as economically as possible. The design procedures
take in to account factors such as rainfall intensity, catchment areas, ground cover and
run-out.
The water flows considered in this project was the flows generated by the run off of the
in thickness as it flows to the edge of the pavement. Factors which influence the depth of
water on the pavement are the length of flow path, surface texture, surface slope, and
rainfall intensity. As the depth of water on the pavement increases, the potential for
hydroplaning is presented and design guidance for the following drainage elements is
presented:-
Bridge decks.
include:
Location of outlets and cleanout points to allow for ultimate shape; and
Paved and unpaved roads are subjected to problems associated with excess water within
the foundation structure of the roadway. This excess water originates from water
infiltrating along the roadway surface, groundwater seeping in from upslope areas, high
The excessive wetness of the road foundation leads to a weakening of the road foundation
and, eventually, failure of the surface, whether it is paved or unpaved. The national
economic cost of pavement damage as a result of excess water can be estimated in tens of
millions of Birr annually. While surface drainage practices do help to alleviate some of
the problems associated with excess water conditions, the principal way of handling the
groundwater, and drain the road foundation. Subsurface drainage is normally necessary in
order to remove any water which may permeate through the pavement layers of roads in
Sub-surface drainage in cuttings must provide not only for the necessary drainage of
pavement layers, but also for the removal, to an adequate depth, of any groundwater,
which may be present in the cutting. Changes to the water table and groundwater flows
[3].
Ground cover
Type of soil
unavailable. In this case, it is an accepted practice to estimate peak runoff rates using
empirical methods.
There are two methods available for calculating the discharge that best reflects local
I. Ration al method: - Provides peak runoff rates for small urban and rural catchment
areas, less than 50 hectares, but is best suited to urban storm drain systems and rural
II. SCS method: - SCS method is based on an analysis of a large number of natural unit
hydrographs from a broad cross section of geographic locations and hydrologic regions.
For this project, rational method was used because our catchment is less than 50 hectares
Which is 32.45hectares.
to 50 hectares (0.5km2). Some precautions shall be considered when applying the rational
method:
The first step in applying the rational method is to obtain a good topographic map
In determining the runoff coefficient C value for the catchment area, thought shall
The rate of runoff resulting from any rainfall intensity is a maximum when the rainfall
intensity lasts as long as or longer than the time of concentration. That is the entire
catchment area does not contribute to the peak discharge until the time of concentration
has elapsed. Frequencies antecedent moisture conditions in the catchment area and the
The rational method formula estimates the peak rate of runoff at any location in
catchment area as a function of the catchment area, runoff coefficient, and means rainfall
intensity for duration equal to the time of concentration (the time required for water to
flow from the most remote point of the basin to the location being analyzed) [3].
Parameter Values
Intensity 45mm/hr.
Area 32.45hectares
Q=0.00278CIA
remote point of the catchment area to the point under investigation. Use of the rational
method requires the time of concentration (tc) for each design point within the catchment
L – Length of steam
H – Level difference in meters between the origin of the stream and the crossing site.
time of concentration for a selected return period. Once a particular return period has
been selected for design and a time of concentration calculated for the catchment area,
The project area from Dandi to Jaldu rainfall intensity is given 45mm/hr.
represents the integrated effects of many drainage basin parameters. To determine the
runoff coefficient, first the type of surface, hydrologic soil group and slope of the project
area should be determined. Once this parameters are determined the composite runoff
differing rates of infiltration. Permeability and infiltration are the principal data required
to classify soils in to hydrologic soil groups. Based on infiltration rates, the soil
Among those groups the soil type of our project area falls under soil group B. Group B
soil is soils having a moderately low runoff potential due to moderate infiltration rates.
These soils primarily consist of moderately deep to deep, moderately well to well drained
Soil Type
Terrain Type A B C D
2.9.4 Culvert
Culvert is a structure that is designed hydraulically to take advantage of submergence to
increase hydraulic capacity. It is also a structure used to convey surface runoff through
based on economic considerations. Culverts are used where bridges are not hydraulically
required, where debris is tolerable, and where they are more economical than abridge.
Culverts can be concrete box culverts, reinforced concrete pipe culverts, or corrugated
metal culverts. For highway in this project concrete pipe culvert was chosen based on the
site condition, amount of discharge, availability, durability, from economic point of view,
the degree practicable. The culvert invert was aligned with the channel bottom and the
skew angle of the stream. Also the culvert entrance shall match the geometry of the
roadway. The culvert size and shape selected was to be based on engineering and
The slope for the culvert alignment was chosen depending on the terrain condition at the
location of the culvert. The culvert should be aligned with skew of not exceeding 45
and protection from buoyancy. They shorten the required structure length, and
Aprons: - They are used to reduce scour from high head water depths or from
approach velocity in the channel. They should extend at least 1.5m pipe diameters
upstream, and should not protrude above the normal stream bed elevation. An
For the culvert designed here end treatments were selected from standard details provided
by [3]. As such Inlet, Outlet and end wall of type A were provided.
Annual rainfall
Mean temperature
But, in our project we have not designed culvert because the elevation decrease smoothly
all over sag curve. So, the water can easily flow without providing cross drainage.
within the limits of the highway right-of-way. Its primary function is to collect runoff
from the highway and areas adjacent to the right-of-way and to transport this
is to drain the base of the roadway to prevent saturation and loss of support for the
The three main types of x- sections for roadside ditches are trapezoidal, triangular and
parabolic. Of the three shapes, the parabolic section is hydraulically the best and most
resistant to erosion, even though not as easy in construction as the trapezoidal and
triangular shapes.
The triangular section although easy to construct is very much susceptible to erosion and
The most commonly used cross section is the trapezoidal section as it is accepted from
For this project, trapezoidal side ditch has been chosen because it is more economical and
Discharge calculation.
1
Q = A R2/3 S ½
n
eroded soil type manning coefficient ranges from 0.02 to 0.05 in our case we take
operations are called Road furniture. The general requirement of these are attention,
meaning, time of response and respect of the road user. Traffic signs provide essential
information to drivers for their safe and efficient maneuvering on the road. Marker posts
assist in a timely perception of the alignment ahead and, when equipped with reflectors,
For the safe traffic operation on highways adequate regulation and controls have to be
Traffic signs
Road marking
Traffic signals
Give timely warning of hazardous situations when they are not self-evident.
Types of Traffic Sign:-According to the U.N. protocol (United Nations publication) the
Regulatory sign
Information signs
A) Warning sign
These sign convey to the drivers, the conditions ahead that some caution is required.
Zig zag
Right turn
Left turn
Dead end
Cross-road
Steep slopes
Cross-road T-intersection
Y-intersection
b) Regulatory Sign
Regulatory signs are also called Mandatory signs. They indicate to the traffic an
considered an offence. These signs also convey to the driver not to exceed specific speed
limit or not to park his vehicle. No parking, speed limit, dead slow, weight limit
In this case we have recommended the use of speed limit and overtaking prohibited on
the approach of both side of the reverse curves and along the road. It will be better if a
c) Information Sign
It provides information and guidance to drivers. End of speed limit sign, parking sign,
parking limits, road junction approach etc. are examples of informatory sign.
For imparting and sense of respect towards signs, proper enforcement should be
taken.
some rural junctions. Traffic signals are not used in this project because the road is found
markings through the length of modern highways. Traffic marking may be in the form of
line, words, symbols or reflectors on the pavement. Traffic marking may be considered as
2. Object marking
Carriage way markings are markings which are applied on the roadway and object
markings are such as abutment, piers, kerbs, etc. categories of Carriages way are :-
Pedestrian crossings
2. Transverse markings – stop line, give way line and pedestrian crossings
Longitudinal markings
Urban areas: 3 m mark with 6 m gap. Rural areas: 4 m mark with 8 m gap
Warning line
Urban areas: 4 m mark with 2 m gap. Rural areas: 6 m mark with 3 m gap
Lane lines
Urban areas: 3 m mark with 6 m gap. Rural areas: 4 m mark with 8 m gap
Edge lines
Standard edge line
Continuity line
No parking line
Transverse markings
crossing
Hump
Solid lines are restrictive in nature and it is an offence to cross such line
In our project, we recommend longitudinal marking for the whole length of the road.
This includes:
Dividing line
Edge lines.
CHAPTER THREE
PROJECT METHODOLOGY
3.1 .Study Area
The Dandi to Jaldu road is found in west shawa part of Ethiopia in the region of Oromia.
It links two towns, Ginchi to Gojjo, which are at high economic growth. This project lies
in B2 or the rainfall regions. The climatic condition of the project area combines semi –
cold and partly warm climatic features. The mean temperature varies between 7.5 0c to
27.50c. The mean annual rainfall of the project area is between 200 – 2400 mm.
Project area
Pavement design
Drainage design
Cost estimation
3.3 Methodology
While performing this project, in addition to manual computations, the project designer
used software’s like MXROAD for design and analysis of horizontal and vertical
alignments, pavement and earth work design. AUTOCAD for displaying different cross
sections of the roadway and as a result, read necessary values. EXCEL for calculating
earth work quantities, calculating both horizontal and vertical curve elements and thereby
population including :- five horizontal curves, six transition curves, five super elevations,
five vertical curves of which one is crest curve and the remaining four are sag curves,
CHAPTER FOUR
RESULT AND DISCUSSION
4.1 Route Selection
Basically, we used the selected route for designing of the road that means a surveying
data has been given for us. Depending on this survey data we have tried to set our
horizontal alignment along the center line of the given data as possible as we can.
for 2022E.C. To make more accurate we use 2015 traffic data as seven days count and we
estimate AADT0 for the counting time. The projected AADTs 2022 for both directions
AADT 1= AADT o ¿
x=the anticipated number of years between traffic survey & the opening of the road
AADT 1= AADT o ¿
Σ AADT1=27+134+107+94+137+279+174+161
Σ AADT1 =1112
favorable condition for providing sufficient tangent section its length is to such extents
that doesn’t causes danger from head light and excessive speeding
All tangent length provided is much less than 4km which is the maximum limit provided.
In our case the radius of all the curves are already specified in alignment.
PI1=0+392.29
ΔRT = 07046'15.73"
R taken =2000m
1. Tangent distance
2. Length of curve
R∗Π∗Δ
L= =2000∗3.14∗07 °0 46 ' 15.73} over {180 ¿ =271.26m
180
3. Point of curvature
4. Point of tangency
5. External distance
6. Middle ordinate
7. Chord length
Horizontal curve -2
R taken =1300m
1. Tangent distance
2. Length of curve
R∗Π∗Δ
L= =1300∗3.14∗07 ° 0 5 ' 51.41 } over {180 ¿ =161.041m
180
3. Point of curvature
4. Point of tangency
5. External distance
6. Middle ordinate
[
M =R ¿]¿ 1300 1−cos
2 ]
07 ° 05 ΄ 51.41”
= 2.493m
7. Chord length
Horizontal curve – 3
PI3=2+079.059
ΔRT = 10024'49.612"
R taken =900m
1. Tangent distance
2. Length of curve
R∗Π∗Δ
L= =900∗3.14∗10 0 24 ' 49.612 } over {180 ¿ =163.579m
180
3. Point of curvature
4. Point of tangency
5. External distance
6. Middle ordinate
M =R ¿] M =900 ¿ = 3.714m
7. Chord length
No. PC PI PT min
R1=2000,
PC1=0+256.453,
PT1=0+527.713
The next full station on the curve at 20 interval is equal to 0+260; Therefore the length of
C1=0+260-0+256.453=3.547
C2=527.713-520=7.713
1718.873C
δ=
R
1718.873∗20
δ= =17.19΄
2000
1718.873∗3.547
δ1 = =3.04΄
2000
1718.873∗7.713
δ2 = =6.62΄
2000
Checked = Δ/2
Taken
R2=1300,
PC2=1+672.217,
PT2=1+833.257
The next full station on the curve at 20 interval is equal to 1+680; therefore the length of
C1=1+680-1+672.217=7.783
C2=1+833.257-1+820=13.257
1718.873C
δ=
R
1718.873∗20
δ= =26.44΄
1300
1718.873∗7.783
δ1 = =10.29΄
1300
1718.873∗13.257
δ2 = =17.53΄
1300
Taken
R3=900,
PC3=1+997.043,
PT3=2+160.623
The next full station on the curve at 20 interval is equal to 2+000; Therefore the length of
C1=2+000-1+997.043=2.957
C2=2+160.623-2+160=0.623
1718.873C
δ=
R
1718.873∗20
δ= =38.20΄
900
1718.873∗2.957
δ1 = =5.65΄
900
1718.873∗0.623
δ2 = =1.19΄
900
Δ= 07005'51.41"
R taken =1300
V=85Kph
2. Length of spiral
3. Shift
4. Tangent length
=90.74m
Ls, calculated=20.25m
=√ (24*1300*0.2)
=78.993m
Ls = 853/46.66*1.2*1300 = 8.436m
The calculated Ls = 78.993m < Ls max=176.635m so that for driver comfort take Ls =
78.993m
At x=10, Y=0.00162
At x=20, Y=0.0129
At x=30, Y=0.043
At x=39.5, Y=0.099
Spiral Curve -2
Chainage of PI=1+978.384
Δ=10024'49.612"
R taken =900
V=85Kph
2. Length of spiral
3. Shift
4. Tangent of length
= 96.644m
θS =28.65LS/R=28.65*29.25/900=0.931°
∆C = ∆-2θS=10.414°-2*0.931° = 8.551°
Ls, calculated=29.25m
=√ (24*900*0.2)
= 65.726m
Ls=853/46.66*1.2*900 =12.186m
The calculated Ls= 65.726m < Ls max=146.969m so that for driver comfort take Ls =
65.726m
At x=10, Y=0.0028
At x=20, Y=0.0225
At x=30, Y=0.076
At x=32.86, Y=0.0999
Spiral Curve -3
Chainage of PI=4+096.346
Δ= 21037'53.576"
R taken =1200
V=100Kph
2. Length of spiral
3. Shift
4. Tangent lenght
=248.798m
θS =28.65LS/R=28.65*39.068/1200=0.933°
Ls, calculated=39.068m
=√ (24*1200*0.2)
=75.895m
=1003/46.66*1.2*1200 =14.883m
The calculated Ls= 75.895m < Ls max=169.706m so that for driver comfort take
At x=10, Y=0.00173
At x=20, Y=0.0141
At x=30, Y=0.0476
At x= 37.95 Y=0.0961
based on the above formula. The following table summarizes the calculation done and
results obtained. The vertical curve alignment output is shown on appendix C-1.
g1= -0.817
g2= -4.623
A=|g1-g2| = 3.806
Length of curve L = Ak
K= 60 from table
L= 60*3.806=228.36m
L provided= 250m
Chainage of PVI=0+379.385
= 0+256.453
=1429.755+1.021=1430.776m
EVC=PVI+L/2
=0+379.385+125=0+504.385
=1429.755-5.779=1423.977m
g1= - 4.623
g2= - 3.795
A=|g1-g2| = 0.828
Length of curve L = AK
L=36*0.828 = 29.808m
L provided = 300m
PVI=0+940
BVC=PVI-L/2
=0+940-150=0+790
=1403.839+6.935=1410.773m
EVC=PVI+L/2
=0+940+150 =1+090
=1403.839 – 5.693=1398.147m
g1 = - 3.795
g2 = - 2.274
A=|g1-g2| = 1.521
L = 36*1.521= 54.756m
L provided = 250m
PVI=1+460
BVC=PVI-L/2
=1+460-125=1+335m
=1384.105+4.744=1388.849m
EVC=PVI+L/2
=1+460+125 =1+585m
PVI=2+448.78
BVC=PVI-L/2
=2+448.78-150=2+298.78m
= 1361.625+3.411= 1365.035m
EVC=PVI+L/2
= 2+448.78+150 = 2+598.78m
corves in the longitudinal profile and then set vertical curves at the filed [2]. Sample
calculation for vertical alignment of setting is done for curve -1 the others are found on
appendixC-3
1430.7 - BV
1430.7 -
1430.7 -
1430.7 -
1430.7 -
1430.7 -
76 3.806
1430.7 -
vd 2
SSD=0.278vt+
254 f
V=85km/hr.
f=0.30
t=2.5sec
2
85
SSD=0.278*85*2.5+ =153.891m
254∗0.30
V=85km/hr
f=0.30
t=2.5sec
2
85
SSD=0.278*85*2.5+ =153.891m
254∗0.30
vd 2
SSD=0.278vt+
254 f
V=85km/hr.
f=0.30
t=2.5sec
2
85
SSD=0.278*85*2.5+ =153.891m
254∗0.30
vd 2
SSD=0.278vt+
254 f
V=100km/hr.
f=0.29
t=2.5sec
2
100
SSD=0.278*100*2.5+ =205.259m
254∗0.29
V=100km/hr.
f=0.29
t=2.5sec
2
100
SSD=0.278*100*2.5+ =205.259m
254∗0.29
L = AK
g1 = -0.817 %
g2= -4.623%
L=3.806*60=228.36m
S= 155m
H1 = 1.070m
H2 = 0.15m
Assume ssd>L
[ ]
2
100 ( √ h 1+ √h 2 )
L=2 S− =2 S−¿
A
=2*155-(658/3.806) = 137.115m
L=AK
g1= -4.623%
g2= -3.795%
L=36*0.828=29.81m
S= 155m
H1 = 1.070m
H2 = 0.15m
Assume ssd>L
2
AS AS
2
L= 2 =
100 ( √ 2∗h 1+ √ 2∗h 2 ¿ ¿ ) 658
=0.828*1552/658=30.232m
V d 2∗A
L c=
389
Curve length
L=AK
g2=-2.274% K=36
L= 1.521*36=54.756 m
1. Assume ssd>L
A S2 A S2
L= 2 =
100 ( √ 2∗h 1+ √ 2∗h 2 ¿ ¿ ) 658
=1.521*1552/658=55.535m
V d 2∗A
L c=
389
Hence length 54.756 m< 55.535m which is a little bit unsafe for sight distances. So, it
L=AK
g1= -2.274%
g2= -1.218%
L=1.055*=99.10m
S= 205m
H1 = 1.070m
H2 = 0.15m
Assume ssd>L
=1.055*2052/658=67.381m
V d 2∗A
L c=
389
The curve length 99.1m>67.381m which is safe for sight distance and L provided is
300m
It was considered for those grades which have value greater than or equal to 3%.
d = 0.278Vt + V2/254(f±0.01*G)
SSD=0.278*85*2.5 + 852/254(0.30-0.01*4.623)
=171.164m
Here, it can be noted that SSD downgrade is less than that of the level road by comparing
d = 0.278Vt + V2/254(f±0.01*G)
SSD=0.278*85*2.5 + 852/254(0.30-0.01*3.795)
=167.622m
Here, it can be noted that SSD downgrade is greater than that of the level road by
comparing
=83.1776m
d2 = 0.278 vt2
d2=0.278*85*10
=236.3m
d3 = safe clearance distance between vehicles at the end of the maneuver, is dependent on
d3(m) 30 50 80 100
Less the portion of d2 whereby the passing vehicle is entering the left lane.
d4 = 2d2/3
d4=2*236.3/3=157.53m
PSD = d1+ d2 + d3 + d4
=83.18+236.3+80+157.53
=557.01 m
=51.53m
d2 = 0.278 vt2
d2=0.278*100*10
=278m
d4 = 2d2/3
d4=2*278/3=185.333m
PSD = d1+ d2 + d3 + d4
=51.53+278+80+185.333
=594.863m
It is calculated with the same formula for stopping sight distance. But h 1=1.07m &
G S2 G S2
Case1: S < L; L= =
100¿ ¿ 945.76 m
3.806∗155 2
L= =96.683m
945.76
Note; in this project we have not designed curve widening because all of our radiuses
Nc =2.5%; ∆=0.485%, nı =1, bw =1, Length of run off provided, L prov. =47m
Lt = Nc/ed*(Lr) =2.5%/2.5%*47=47m
For curve -2
Nc =2.5%; ∆=0.485%, nı=1, bw=1 Length of run off provided, L prov. =47m
Lt = Nc/ed*(Lr) =2.5%/2.8%*47=41.96m
For curve-3
NC=2.5%; ∆=0.485%, Ni=1, bw =1, Length of run off provided, L prov. =47m
Lt = Nc/ed*(Lr) = 2.5%/4.2%*47=27.98m
(base year 2022) will be forecasted with the growth rate shown below. Traffic and soil
Vehicle Cars 4WD Small Large Large Medium Heavy Truck &
For this project opening of the road is at starting of 2022. So, X= (2022-2015)-1=6
Then the cumulative number of vehicles, T over the chosen design period N (in years) is
For link road, a design period of 20 years, the cumulative number of vehicles in one
expressed as the number of equivalent standard axles (ESAs), in units of 80kN [3].
Axle load n
EF=( ) , n = 4.5
8160
Sample EF for Truck trailer is calculated here, where other are on appendix E-2 and E-3
T/Trailer
1 2 L
EF
Vehicle
One directional Cumulative equivalent
classification
2007(AADT1) traffic volume factor ESLA*10^6
Equivalent standard axles (ESAs) = EF*T, T = 365 AADT1 [(1+i) N –1] / (i)
Based on Sub grade class S4 and Traffic class T6 there are eight alternatives [3]
material is listed and for each alternatives of pavement structure should be economically
evaluated.
CB2
Based on the above economic comparison, 2.23 (alternative 5) is the list total relative unit
Alternative 5
Bituminous surface
Granular sub-base, GS
L=0+020-0+000=20m
( A 1+ A 2) (6.487+ 1.1)
V 12= ∗L =V 12= ∗20
2 2
V12 =75.86m2(cut)
( A 1+ A 2) (0+ 0.857)
V12=V 12= ∗L = ∗20
2 2
V12=8.57m2
( A 1+ A 2) (1.1+0)
V 23= ∗L= ∗20
2 2
V23 =10.999m2(cut)
( A 1+ A 2) (0.857+ 6.045)
V23=V 12= ∗L = ∗20 =69.019m2
2 2
Discharge calculation.
1
Q = A R2/3 S ½
n
Intensity=45mm/hr
Length=379.385m
Pavement width=7m
Shoulder=1.5*2m
1. Carriageway area
L =379.385m W=3.5m
A1=379.385*3.5=1327.8 m2=0.133ha
C=0.825
Q=0.00278*C*I*A=0.00278*0.825*45*0.133=0.014m3/s
2. Shoulder area
L=379.385m W=1.5m
C=0.8
Q=0.00278*C*I*A=0.00278*0.8*45*0.0569=0.0057m3/s
3. Cultivated land
A=379.385*45= 17072.3m2=1.71ha
C=0.7
Q=0.00278*C*I*A=0.00278*0.7*45*1.71=0.15m3/s
Ditch assumed to be laid in easily eroded soil type manning coefficient ranges from 0.02
to 0.05 in our case we take n=0.022 from [3] maximum velocity in this range will be
2.4m/s.
V= , A=Bd+zd2
R=A/P=4d2/6.472d=0.618d
V=1/0.022*(0.618d) 2/3*(0.00817)0.5
V=2.98d2/3
Q=AV=4d2*2.98d2/3 = 11.92d8/3
0.17=11.92d8/3
d=0.203m, use d=0.25m and B=2d=0.5m. Then take free board of 0.3m.
Area, A=4d2=4*0.252=0.25m2
Perimeter, P=6.472*0.25=1.618m
R=A/P=0.25/1.618=0.155m
Q=1/0.022*0.25* (0.155)2/3*(0.00817)0.5=0.3m3/s
The maximum capacity of the ditch is greater than the maximum discharge in its design
life.
0.5 0.
55
d=0.55 55 1
55
552
55
B=0.5 55
. 55
Figure 4.5: Provided Trapezoidal Cross55
Section
55
From station 0+379.385 to 0+940.00 55
55
Length=560.615m 55
5Y
1. Carriageway area
L =560.615m W=3.5m
A1=560.615*3.5=1962 m2=0.1962ha
C=0.825
Q=0.00278*C*I*A=0.00278*0.825*45*0.1962=0.02m3/s
2. Shoulder area
L=560.615 W=1.5m
A2=560.615*1.5= 796m2=0.0796ha
C=0.8
Q=0.00278*C*I*A=0.00278*0.8*45*0.0796=0.00796m3/s
3. Cultivated land
A=560.615*45= 23880m2=2.388ha
C=0.7
Q=0.00278*C*I*A=0.00278*0.7*45*2.388=0.21m3/s
V=1/0.022*(0.618d) 2/3*(0.04623)0.5
V=7.09d2/3
0.25=28.36d8/3
d=0.17m, use depth of 0.25m. So, d=0.25m and B=2d=0.5m. Then take free board of
0.3m.
For this station it is not necessary to design longitudinal ditch because it is fill section.
Length=988.78m
1. Carriageway area
L =988.78m W=3.5m
A1=988.78*3.5=3460 m2=0.346ha
C=0.825
Q=0.00278*C*I*A=0.00278*0.825*45*0.346=0.0356m3/s
2. Shoulder area
L=988.78m W=1.5m
A2=988.78*1.5= 1483m2=0.148ha
C=0.8
Q=0.00278*C*I*A=0.00278*0.8*45*0.148=0.0148m3/s
3. Cultivated land
A=988.78*45=44495 m2=4.45ha
C=0.7
Q=0.00278*C*I*A=0.00278*0.7*45*4.45=0.389m3/s
Total discharge
V=1/0.022*(0.618d) 2/3*(0.02274)0.5
V=4.97d2/3
Q=AV=4d2*4.97d2/3 = 19.88d8/3
0.194=19.88d8/3
d=0.18m, use depth of 0.25m. So, d=0.25m and B=2d=0.5m. Take free board 0.3m.
Length=331.22m
1. Carriageway area
L =331.22m W=3.5m
A1=331.22*3.5=1159.27m2=0.12ha
C=0.825
Q=0.00278*C*I*A=0.00278*0.825*45*0.12=0.012m3/s
2. Shoulder area
L=331.22m W=1.5m
A2=331.22*1.5=496.8m2=0.05ha
C=0.8
Q=0.00278*C*I*A=0.00278*0.8*45*0.05=0.005m3/s
3. Cultivated land
A=331.22*45= 14904.9m2=1.49ha
C=0.7
Q=0.00278*C*I*A=0.00278*0.7*45*1.49=0.13m3/s
Total discharge
V=1/0.022*(0.618d) 2/3*(0.01218)0.5
V=3.63d2/3
Q=AV=4d2*3.63d2/3 = 14.52d8/3
0.147=14.52d8/3
d=0.18m, use depth of 0.25m. So, d=0.25m and B=2d=0.5m. Then take free board of
0.3m.
For this station it is not necessary to design longitudinal ditch because it is fill section.
Case1
0+970
to 2+980
0+320
1+960
0+020
0+540
85
KPH
0+230
60
KPH
2+275
100
KPH
CHAPTER FIVE
CONCLUSION AND RECOMMENDATION
5.1 Conclusion
The designer provides both horizontal alignment, with tangents, having lengths
R=900m, and vertical alignment with four vertical curves having respective
For this project, depending on the calculated traffic class, T 6 and subgrade
strength S4, the most economical section, which has three layers namely;
cm thickness and Granular sub-base, GS with 25 cm was selected and the flexible
The discharge was computed using rational formula (RF) based on the total
depth d=0.55m, top width T=1.5m and bed width B=0.5m that accommodates this
5.2 Recommendation
The project designer recommends that, this designed project should be
reducing problems between the two localities namely: Dandi and Jaldu.
The contractor should adopt three layers of pavement during the construction of
flexible pavement from Dandi to Jaldu; these are bituminous surface with
thickness of 10cm, Granular road base with thickness of 20cm and Granular sub-
The project designer also recommends that, fellow students should use MXROAD
software instead of using other software’s like EAGLE POINT, INROAD and
others while doing their project. This is owing to MXROAD software will not
allow any mistakes that means one cannot go any further without correcting a
The other recommendation is that, the width of the shoulder should be up graded
The traffic signs should be installed wherever necessarily required with due care
References
[1] American Association of State Highway and Transportation Officials
edition.
APPENDIX
Table of sample survey data, Figure of contour lines and slope band and
Chainage Road Left Side Road Right Side Right Of Way Transverse Terrain
Tangent 135.838
External 4.608
Radius 2000
Tangent 80.623
External 2.498
Radius 1300
Tangent 82.016
External 3.729
Radius 900
IP Chainage 0+379.385
IP Level 1429.755
M Value -1.522
K Value 65.687
IP Chainage 0+940.000
IP Level 1403.839
M Value 0.276
K Value 362.415
IP Chainage 1+460.000
IP Level 1384.105
M Value 0.609
3 K Value 164.312
Elev. Offset
Figure of Carriage way and Shoulder, Earth work cross section, and
(m2) (m2)
0 6.486 0 0 0 0 0 0
Table of Axle load surveys, Equivalent Factor for S/Bus and L/Buss,
Axle Axle Axle Axle Axle Axle Axle Axle Axle Axle Axle Axle
1 2 1 2 1 2 1 2 1 2 3 4
287 546
2178 3038 5184 5634 6829 5612 8963 12036 7323 7623
0 5
287 564
2405 2925 5617 5782 6436 6289 7189 10405 7305 7418
6 5
283 514
2315 2977 5665 4694 7374 5308 9894 10372 6964 8699
2 8
285 563
2251 3099 5376 4351 7075 6531 7615 11955 8206 7550
5 5
309 504
1917 2998 5620 4928 6464 6601 9407 9397 7208 6660
6 6
321 578
2291 2698 5665 4784 7895 5394 8634 8154 8892 9704
2 7
282 566
1950 2844 5267 5249 6350 6917 8954 12279 7889 9138
9 9
318 594
2234 2753 5191 4154 7822 5592 7451 9940 7368 9435
4 1
305 513
2293 3064 5271 4733 7680 5312 9991 12523 6005 9481
6 7
2427 265 3119 5036 4900 6641 5888 7764 583 11497 6385 6718
276 534
2013 3046 5286 4358 6717 6021 9298 8825 8197 7776
6 8
0.01 0.13
2178 0.003 2870 0.009 0.012 3038 5184 0.142
2 0
0.01 0.18
2405 0.004 2876 0.009 0.013 2925 5617 0.196
0 6
0.01 0.19
2315 0.003 2832 0.009 0.012 2977 5665 0.204
1 4
0.01 0.15
2251 0.003 2855 0.009 0.012 3099 5376 0.166
3 3
1917 0.001 3096 0.013 0.014 2998 0.01 5620 0.18 0.198
1 7
0.00 0.19
2291 0.003 3212 0.015 0.018 2698 5665 0.200
7 4
0.00 0.13
1950 0.002 2829 0.009 0.010 2844 5267 0.148
9 9
0.00 0.13
2234 0.003 3184 0.014 0.017 2753 5191 0.138
8 1
0.01 0.14
2293 0.003 3056 0.012 0.015 3064 5271 0.152
2 0
0.01 0.11
2427 0.004 2652 0.006 0.011 3119 5036 0.127
3 4
0.01 0.14
2013 0.002 2766 0.008 0.010 3046 5286 0.154
2 2
L/Truck M/Truck
0.18 1.52
5634 6829 0.449 0.638 5612 0.186 8963 1.711
9 6
4358 0.05 6717 0.417 0.476 6021 0.25 9298 1.79 2.054
9 5 9