Lower Fars Heavy Oil Field
Lower Fars Heavy Oil Field
Lower Fars Heavy Oil Field
Latest News
Title Description
EXCLUSIVE: Kuwait heavy oil project enters final phase Contract is worth $4.1bn and was awarded to Petrofac and
Consolidated Contractors Company in 2015
Kuwait reveals expected production from the Ratqa Lower Fars Phase one of Kuwait’s Ratqa Lower Fars heavy oil megaproject is
project expected to produce 11,000 barrels of oil a day (b/d) in August,
according to a statement released by state-owned upstream operator
Kuwait Oil Company (KOC).
Kuwait Oil aims to produce 200,000 barrels per day of light crude in KOC's Executive Vice President for Planning and Trade Imad Sultan
October said the company aims to reach 200,000 barrels of light crude per day
in October.
Sultan pointed out that the company has exported 5 million barrels of
excellent light oil since last July, considering that this step constitutes "a
new historic breakthrough for the oil industry in Kuwait.
KOC to start Lower Fars operation in Aug Kuwait Oil Company (KOC) announced on Thursday that the initial
operation of its heavy crude oil development project will commence in
the north of the country next August.
KOC will increase the project's production gradually until reaching its
maximum capacity of 60,000 barrels of oil per pay (bpd) as required,
KOC spokesman and deputy CEO for administrative and financial
affairs Ahmad Al-Hamad said in a press statement, carried by state
news agency Kuna.
Kuwait awards $4.2bn heavy oil contract(Phase I) Kuwait has awarded a $4.2 billion contract to develop heavy oil fields in
the north of the country, the central tenders committee announced
yesterday (January 8).
The project, called Lower Fars Heavy Oil Development Phase 1, was
awarded to UAE-based Petrofac International and the Athens-based
Consolidated Contractors Company, the largest construction firm in the
Middle East, said a report in the Gulf Daily News (GDN), our sister
publication.
Kuwait plans US$7b heavy oil fields The first phase of the Lower Fars heavy oil project will cost US$4.2
billion, with contracts to be awarded by the end of this year, Hashem S.
Hashem, chief executive officer (CEO) of state-owned Kuwait Oil Co
(KOC), said at a conference, here, yesterday.
KOC, which plans to drill 900 wells and pump 60,000 barrels a day by
2018 in the project’s first phase, targets output of 180,000 barrels a day
by 2025 and 270,000 by 2030, Hashem said.
07/Feb/2022 08:50:31
Page 2
KOC - Ratqa Lower Fars Heavy Oil (LFHO) Handling Facilities
Kuwait Oil Company evaluates bids on Lower Fars Phase-1 project The wholly state-owned Kuwait Oil Company (KOC) is planning to drill
more than 900 wells to develop the heavy crude oil lying in the Lower
Fars field in the north of Kuwait.
Discovered in 1978, the Lower Fars formation belongs to the Ratqa
field, a reservoir saturated by crude oil.
British progressing the lowest prices in the development project The British company Petrofac has provided the lowest prices in the
main contract to build the project to develop heavy oil field in the bottom
of Persia, which dates back to the interest of the Kuwait Oil Company.
The magazine added that the price put forward by the British company
in the tender, which will be implemented system engineering,
procurement and construction reached 1.
Kuwait plans to award $4.3bn oil project deal Kuwait plans to award a KD1.2 billion ($4.3 billion) contract later this
year for the first phase of a project to produce heavy oil at its northern
Ratqa field, the head of state-owned Kuwait Oil Company (KOC) said.
This phase-1 is part of the Lower Fars heavy crude oil scheme planned
by KOC to meet its oil production targets for 2018.
03/02/2022 The project was in the On Hold stage as per the last update in August
2021. Since then, neither information has been procured related to its
progress, nor obtainable from contact with key stakeholders. We believe
the project to still be On Hold and have amended the project dates
accordingly. We will continue our efforts to obtain information on this
project.
04/08/2021 The Phase 3 project is still on hold and the time frame of revival is
unknown at this juncture.
06/03/2021 Phase 3 continues to be on hold.
12/02/2020 Worley has been appointed as the FEED consultant for Phase 2 and 3.
FEED works are progressing on phase 2 whereas phase 3 is kept on hold
due to unknown reasons.
09/10/2019 The drilling package has been completed. Phases 2 & 3 are in study
phase.
19/08/2019 The phase-I of the LFHO project is completed.
19/06/2019 Construction works are nearing completion on Phase 1 and Drilling while
study activities are underway on phases 2, 3.
(Source: MEED)
17/04/2019 Construction works are underway on the first phase and Drilling package,
while study activities are underway on phases 2, 3. (Source: MEED)
21/02/2019 Construction works are underway on the first phase and Drilling while
07/Feb/2022 08:50:31
Page 3
KOC - Ratqa Lower Fars Heavy Oil (LFHO) Handling Facilities
10/09/2018 Ratqa Lower Fars Heavy Oil Handling Facilities:Drilling : Drilling has
progressed up to 930 wells and 86 percent construction has been
completed.
22/07/2018 Construction works are underway on the first phase and scheduled to be
completed by August 2018.
18/02/2018 KOC is in the process to issue a tender for selecting a service provider for
enhanced oil recovery technology this year. Glasspoint is expected to bid
when the tender is issued.
25/01/2018 Production Facilities/Support Complex/Tank Farm (Phase I): The project
is expected to be complete by end of 2018. The construction works are
ongoing on the project and is expected to be complete by mid-2019 for
drilling works.
09/10/2017 Phase III is in the early stage.
07/Feb/2022 08:50:31
Page 4
KOC - Ratqa Lower Fars Heavy Oil (LFHO) Handling Facilities
07/Feb/2022 08:50:31
Page 5
KOC - Ratqa Lower Fars Heavy Oil (LFHO) Handling Facilities
12/09/2013 Drilling works are underway. Alghanim International General Trading &
Contracting and HOT E&C are undertaking the civil work for the drilling
package whereas Weatherford International is undertaking the
mechanical part for drilling.
12/09/2013 WorleyParsons has completed FEED on the project and the main
contract tenders are likely to be issued in end Q4 2013.
17/01/2013 KOC will shortlist the consultants to bid for the contract, which includes
detailed engineering, technical support, procurement, construction,
commissioning, startup and turnover of facilities using cyclic steam
stimulation (CSS).
25/11/2012 KOC is planning to invite the international engineering firms to prequalify
for a deal to design new facilities for the development of heavy oil using
cycling steam stimulation (CSS) for which the interested firms have been
asked to submit prequalification documents by January 2, 2013.
09/12/2007 KOC announced plans to undertake the Lower Fars Heavy Oil Field
Development project.
07/Feb/2022 08:50:31
Page 6
KOC - Ratqa Lower Fars Heavy Oil (LFHO) Handling Facilities
Page 7