Suroj Buildcon Pvt. LTD.: Job Safety Analysis
Suroj Buildcon Pvt. LTD.: Job Safety Analysis
12.Ensure supervision.
13.Ensure housekeeping.
1. Slippery surface,Slip Trip and Fall 1. Dedicated route demarcation for pedestrian and vehicle movement.
2. Uneven ground condition
3. Open pit or trench on access way 2. Restrict Speed limit 15KM/H for vehicles at site.
4. Adjacent structure/Obstruction 3. Ensure barrication for demarcation and signages in pedestrian and vehicles movement area.
6. Sharp object on access way 4. Entry of pedestrian in vehicle access is strictly prohibited.
7. Over head power lines 5. Ensure there is no overhead powerlines or dangling powerlines on ground which could
8. Lack of illumination hindrance for pedestrian and vehicle movement.
9. Lack of signages(speed limit) 6. Ensure sufficient illumination in pedestrian and vehicle movement access way and welfare
areas.
7. Ensure there is no sharp objects and slippery condition on pedestrian and vehicle access way.
8. Ensure there is no open pit and trench on vehicle and pedestrian access way.
10. Ensure the access way shouldn't block without making alternate way.
14.Ensure signal batton lights are made availabe to signal man for night works.
15.Ensure all crew involved in night shift must use hi-Viz jackets with reflective tapes.
16.Ensure supervision.
1.) Fall of concrete pipe, 2.) 1.Ensure adeqaute access/egress to work location.
Fall of person Injury to
Person, Property damage 2.Ensure sufficient illumination is maintained at work location and
3) Improper usage of access egress area. 3. Only trained
hand tools 4.) slip /trip & persons allow for erection of pipeline work. 4. Provide close
fall 5.) Concrete supervision during the work.
may come in contact with Skin & eye 5. Provide & ensure use of PPE’s like safety helmet, safety shoes, safety belt,jacket,face
sheild,goggles,ear plugs.
6. Area should barricade.
7. Provide & ensure use of rope for lifting & lowering pipe.
8. Provide proper working platform.
9. Pipe line should be inspected for proper fixing before taking in to use.
13.Ensure all people involved in pipe line work are aware of the risks
involved in the activity.
14.Ensure TBT is conducted prior to start of
activity.
15.provide sufficient manpower as per safe lifting
limits.
16.Avoid saging & provide proper manpower to give support.
17.Provide close supervision.
18.In case of spillage of concrete ensure the it is removed at the same time.
19. Ensure the concrete pumps complies
with HSE Prerequestie checklist.
18.Ensure flagmans are deployed at various locations to control vehicle and pedestrain
movements along the designated vehile movement area.
19.Ensure vigilient supervision.
.1. Slippery surface,Slip Trip and 1. Provide & ensure use of hand gloves(Cut resistant), shoulder pad,Safety Shoes,Safety
Fall Helmets,Hi Viz Jacket.
2. TBT should be conducted before start the work. 3.Sharp
2. Uneven ground condition edges must be protected.
3. Open pit or trench on access 4. Ensure materials are stacked properely.
way 5.Ensure housekeeping.
4. Adjacent structure/Obstruction
6. Sharp object on access way 6. Provide close supervision during Night work.
7. Lack of illumination 7. Provide proper access during the work.
8. Lack of signages(speed limit) 8. Access should be from obstacles.
9. Provide proper illumination at work location.
5 Ensure materails are stacked properley and secured.
7.Ensure House keeping is maintained at work location during and after the work activity.
8 Shuttering work at night shift Site PM/Engineer
8.Ensure the walkway to rest area and drinking water facility is illluminated.
10.Dedicated Banks man to be deployed when vehicle movement is in or near to work area.
11.Ensure the temporary lighting arrangement is made on the opposite side of the access
egress to work location.
1. Hit by vehicles 1. Ensure Job specific PPE(safety helmet, safety vest, hand gloves, safety shoe etc.)
2.Improper access at work area – 2. Ensure trained flagman deployed to escort vehicle at site
3. Follow 15KMPH speed limit at site(strictly)
3. Slip, trip & fall of person 4. 4. Don't horseplay(no over speed, no over turn) during driving vehicles at site
Unauthorized entry at work area - 5. Ensure flagman to escort transit mixers/trucks to prevent unauthorised entry on vehicle
5 movement way.
5.Vehicles - hit by vehicle, Toppling 6. Ensure vehicles are parked in designated place. No blocking access way.
of vehicle 7. Use wheel stopper after parking vehicle in designated area.
8. Ensure hand brake pulled while parking.
9. Ensure driver don't leave key on vehicle while leave driving seat.
10. Ensure vehicle lights are switched on during work in night.
11. Ensure sufficient illumination in workplace in case of night work.
12. Ensure good supervision. Site Engineer/Superviosr/
9 Vehicle Movement in Night Shift
13.Ensure adequate warning signages are displayed. Banksman
14.Ensure blinkers are placed for excavtion near the access area.
15.Ensure the drivers are aware of the site routes and emergency procedures.
7.Ensure housekeeping.
1. Improper Access. 1. Ensure all are follow site layout plan for safe access 8.Ensure supervision.
2.Slip, trip & fall of person 2.for workers and staff seprate Dinning hall availble with drinking water facility,
illumanation.
3. all food waste kept in dust bin.
4. Toilet availble with illumanation
5. Area illumanation availble and ensure the walk way is adequately illuminated.
11 Welfare Facility HR
6.Ensure all workers take rest in designated location only.