TAKE OF SHEET QUANTITY SUM

(TIPE 135/204)

A. PERHITUNGAN VOLUME PONDASI

A1. Keliling pondasi lanjur


P = 1700 + 1200 + 1260 + 120 + 820 + 460 + 730 + 150 +
420 + 620 + 651 + 451 + 870 + 400 + 250
P = 10102 cm' = 101 m'

Tipe 1 = 8402 cm' = 84 m'


Tipe 2 = 1700 cm' = 17 m'

A2. Pekerjaan tanah


A2.1 Detail E (dalam ruangan)
a. galian tanah untuk pondasi
P = 630 + 120 + 700 + 243 +
580 + 200 + 250 + 290
P = 3013 cm = 30.13 m'

L = 115 x 50 = 5750 cm2 = 0.575 m2


V = 30.13 x 0.575 = 17.32 m3

b. mengurug kembali bekas galian


Luas pondasi lajur = ( 35 + 20 ) x 0.5 x
50 = 1375 cm2 = 0.14 m2
Luas telapak = ( 50 x 15 ) +
( 50 x 20 )
= 1750 cm2 = 0.18 m2
Luas galian = 0.575 m2
Luas urugan = 0.575 - 0.14 - 0.18
= 0.26 m2
Volume urugan = 0.26 x 30.1
= 7.9091 m3

c. urugan pasir di bawah pondasi


Luas urugan pasir = 50 x 5 = 250 cm2
= 0.025 m2
Volume urugan = 30.13 x 0.03 = 0.753 m3

AMURANG BAY RESIDANCE


(PT. CAHAYA INTI ENERGY)
TAKE OF SHEET QUANTITY SUM
(TIPE 135/204)

A2.2 Detail F (teras)


a. galian tanah untuk pondasi
P = 365 cm = 3.65 m'
L = 115 x 50 = 5750 cm2 = 0.575 m2
V = 3.65 x 0.575 = 2.099 m3

b. mengurug kembali bekas galian


Luas pondasi lajur = ( 35 + 20 ) x 0.5 x
50 = 1375 cm2 = 0.14 m2
Luas telapak = ( 50 x 15 ) +
( 50 x 20 )
= 1750 cm2 = 0.18 m2
Luas galian = 0.575 m2
Luas urugan = 0.575 - 0.14 - 0.18
= 0.26 m2
Volume urugan = 0.26 x 3.65
= 0.9581 m3

c. urugan pasir di bawah pondasi


Luas urugan pasir = 50 x 5 = 250 cm2
= 0.025 m2
Volume urugan = 3.65 x 0.03 = 0.091 m3

A2.3 Detail G (luar ruangan)


a. galian tanah untuk pondasi
P = 300 + 250 + 420 + 150 + 651
290 + 240 + 460 + 150 + 315
P = 3226 cm = 32.26 m'

L = 115 x 50 = 5750 cm2 = 0.575 m2


V = 32.26 x 0.575 = 18.55 m3

b. mengurug kembali bekas galian


Luas pondasi lajur = ( 35 + 20 ) x 0.5 x
50 = 1375 cm2 = 0.14 m2
Luas telapak = ( 50 x 15 ) +
( 50 x 20 )
= 1750 cm2 = 0.18 m2
Luas galian = 0.575 m2
Luas urugan = 0.575 - 0.14 - 0.18
= 0.26 m2
Volume urugan = 0.26 x 32.3
= 8.4683 m3

c. urugan pasir di bawah pondasi


Luas urugan pasir = 50 x 5 = 250 cm2
= 0.025 m2
Volume urugan = 32.26 x 0.03 = 0.807 m3

AMURANG BAY RESIDANCE


(PT. CAHAYA INTI ENERGY)
TAKE OF SHEET QUANTITY SUM
(TIPE 135/204)

A2.4 Detail H (batas bangunan)


a. galian tanah untuk pondasi
P = 300 + 250 + 400
P = 950 cm = 9.5 m'

L = 115 x 50 = 5750 cm2 = 0.575 m2


V = 9.5 x 0.575 = 5.463 m3

b. mengurug kembali bekas galian


Luas pondasi lajur = ( 27.5 + 20 ) x 0.5 x
50 = 1188 cm2 = 0.12 m2
Luas telapak = ( 35 x 15 ) +
( 50 x 20 )
= 1525 cm2 = 0.15 m2
Luas galian = 0.575 m2
Luas urugan = 0.575 - 0.12 - 0.15
= 0.30 m2
Volume urugan = 0.30 x 9.5
= 2.8856 m3

c. urugan pasir di bawah pondasi


Luas urugan pasir = 35 x 5 = 175 cm2
= 0.0175 m2
Volume urugan = 9.5 x 0.02 = 0.166 m3

A2.5 Detail I (non bangunan)


a. galian tanah untuk pondasi
P = 615 + 300 + 365 + 535 +
1700 + 1200 + 265
P = 4980 cm = 49.8 m'

L = 50 x 35 = 1750 cm2 = 0.175 m2


V = 49.8 x 0.175 = 8.715 m3

b. mengurug kembali bekas galian


Luas pondasi lajur = ( 35 + 20 ) x 0.5 x
50 = 1375 cm2 = 0.14 m2
Luas galian = 0.175 m2
Luas urugan = 0.175 - 0.14
= 0.04 m2
Volume urugan = 0.04 x 49.8
= 1.8675 m3

c. urugan pasir di bawah pondasi


Luas urugan pasir = 35 x 5 = 175 cm2
= 0.0175 m2
Volume urugan = 49.8 x 0.02 = 0.872 m3

A3. Timbunan tanah & pasir di bawah lantai dipadatkan


No. Ruang Luas (m2) T.Tanah (m) Vol. (m3) T.Pasir (m) Vol. (m3)
1 R. Tamu 32 0.210 6.67 0.050 1.59
2 R. Mkn/Dpr 15 0.210 3.19 0.050 0.76
3 Toilet lt.1 6 0.165 0.93 0.050 0.28

AMURANG BAY RESIDANCE


(PT. CAHAYA INTI ENERGY)
TAKE OF SHEET QUANTITY SUM
(TIPE 135/204)

4 R.Tidur 24 0.210 5.13 0.050 1.22


5 Teras 5.6 0.185 1.03 0.050 0.28
Total 16.95 4.13

A3. Galian tanah untuk septictank

V = 100 x 100 x 200


= 2E+06 cm2 = 2.00 m2
100

100

Rekapitulasi volume pekerjaan tanah

No. Pekerjaan Satuan Volume Catatan.


1 Galian tanah untuk pondasi m3 65.86 Total galian = 67.9
2 Mengurug kembali bekas galian m3 22.09 Total timbunan = 39.0
3 Urugan pasir di bawah pondasi m3 2.69 Selisih = 28.8
4 Timbunan tanah padat di bawah lantai m3 16.95 *Tanah untuk timbunan cukup
5 Urugan pasir di bawah lantai m3 4.13
6 Galian tanah septic tank m3 2

B. PEKERJAAN PASANGAN/BETON

B1. Pas. Pondasi Batu Belah


Pondasi tipe 1
20
Luas = ( 20 + 35 ) x 0.5 x 50
= 1375 cm2 = 0.1375 m2
50 Volum = 0.1375 x 84 = 11.6 m3

35

20
Luas = ( 20 + 27.5 ) x 0.5 x 50
= 1187.5 cm2 = 0.1188 m2
50 Volum = 0.1188 x 17 = 2.0 m3

27.5

Volumr Pas. Pondasi Batu Belah = 11.6 + 2.0


= 13.6 m3

AMURANG BAY RESIDANCE


(PT. CAHAYA INTI ENERGY)
TAKE OF SHEET QUANTITY SUM
(TIPE 135/204)

B2. Pasangan dinding Bata


B2.1 Dinding lantai 1

Dinding luar
P = 820 + 665 + 120 + 270 + 420 + 160 + 651
290 + 250 + 460 + 120 + 315
P = 4541 cm' = 45.41 m'

Dinding dalam
P = 180 + 300 + 100 + 300 + 400 + 300 +
275 + 275
P = 2130 cm' = 21.3 m'

Keliling total dinding lantai 1


P = 45.41 + 21.3
= 66.71 m
Luas bruto dinding lantai 1 (tinggi bangunan) = 3.5 m
L = 66.71 x 3.5
= 233.5 m2

B2.2 Dinding lantai 2

AMURANG BAY RESIDANCE


(PT. CAHAYA INTI ENERGY)
TAKE OF SHEET QUANTITY SUM
(TIPE 135/204)

Dinding luar
P = 723 + 300 + 261 + 365 + 250 + 815 +
130 + 355 + 435
P = 3634 cm' = 36.34 m'

Dinding dalam
P = 180 + 195 + 312
P = 687 cm' = 7 m'

Keliling total dinding lantai 2


P = 36.34 + 7
= 43 m

Luas dinding persegi panjang (tinggi bangunan) = 3.2 m


L = 43 x 3.2
= 138.3
Luas bruto dinding segitiga (tinggi atap) = 1.9 m
L ka = 0.5 x 7.23 x 1.9 = 6.869 m2
L ki = 0.5 x 8.15 x 1.9 = 7.743 m2

Luas bruto dinding lantai 2 (tinggi bangunan) = 3.5 m


L = 138.3 + 7.743
= 146 m2

B2.3 Luasan pintu, jendela, ventilasi dan bukaan lainnya

B C D E
A

F G H

Luasan bukaan depan


LA = 80 x 405 = 32400 cm2 X 1 = 32400 cm2 = 3.24 m2
LB = 140 x 215 = 30100 cm2 X 1 = 30100 cm2 = 3.01 m2
LC = 89 x 200 = 17800 cm2 X 1 = 17800 cm2 = 1.78 m2

AMURANG BAY RESIDANCE


(PT. CAHAYA INTI ENERGY)
TAKE OF SHEET QUANTITY SUM
(TIPE 135/204)

LD = 60 x 139 = 8340 cm2 X 1 = 8340 cm2 = 0.834 m2


LE = 89 x 200 = 17800 cm2 X 1 = 17800 cm2 = 1.78 m2
LF = 235 x 40 = 9400 cm2 X 4 = 37600 cm2 = 0.94 m2
LG = 120 x 248 = 29760 cm2 X 1 = 29760 cm2 = 2.976 m2
LH = 235 x 40 = 9400 cm2 X 3 = 28200 cm2 = 0.94 m2
L Total bukaan depan = 15.5 m2

C
A B

D E

Luasan bukaan belakang


LA = 165 x 40 = 6600 cm2 X 4 = 26400 cm2 = 0.66 m2
LB = 230 x 50 = 11500 cm2 X 1 = 11500 cm2 = 1.15 m2
LC = 50 x 35 = 1750 cm2 X 1 = 1750 cm2 = 0.175 m2
LD = 175 x 215 = 37625 cm2 X 1 = 37625 cm2 = 3.763 m2
LE = 210 x 40 = 8400 cm2 X 5 = 42000 cm2 = 0.84 m2
L Total belakang = 6.588 m2

Luasan bukaan samping kanan


LA = 130 x 95 = 12350 cm2 X 1 = 12350 cm2 = 1.235 m2
LB = 20 x 10 = 200 cm2 X 4 = 800 cm2 = 0.02 m2
L Total samping kanan = 1.255 m2

AMURANG BAY RESIDANCE


(PT. CAHAYA INTI ENERGY)
TAKE OF SHEET QUANTITY SUM
(TIPE 135/204)

C D
E F

Luasan bukaan samping kiri


LA = 20 x 10 = 200 cm2 X 4 = 800 cm2 = 0.02 m2
LB = 235 x 89 = 20915 cm2 X 1 = 20915 cm2 = 2.09 m2
LC = 60 x 30 = 1800 cm2 X 1 = 1800 cm2 = 0.18 m2
LD = 225 x 89 = 20025 cm2 X 1 = 20025 cm2 = 2.00 m2
LE = 110 x 70 = 7700 cm2 X 1 = 7700 cm2 = 0.77 m2
LF = 225 x 89 = 20025 cm2 X 4 = 80100 cm2 = 2.00 m2
L Total samping kiri = 7.067 m2

Total luas bukaan Total luasan dinding bruto


L Total bukaan depan = 15.5 m2 Luas bruto dinding lantai 1 = 233 m2
L Total belakang = 6.588 m2 Luas bruto dinding lantai 2 = 146 m2
L Total samping kanan = 1.255 m2 L Total = 379 m2
L Total samping kiri = 7.067 m2
L Total = 30.41 m2

Luasan dinding Netto = 379 - 30.41 = 349 m2

Jadi,
Vol. Pas. Dinding Bata = 349 m2
Vol. Plesteran = 349 x 2 = 698 m2
Vol. Acian = 349 x 2 = 698 m2

B3. Pekerjaan beton bertulang


B3.1 Sloof
Dimensi beton bertulang
b = 0.15 m
s h = 0.20 m
bk h s = 0.02 m

AMURANG BAY RESIDANCE


(PT. CAHAYA INTI ENERGY)
TAKE OF SHEET QUANTITY SUM
(TIPE 135/204)
bk
bk = 0.02 m
b
Panjang tulangan pokok Panjang tulangan geser
= 12 m = 12 m
Diameter pokok Diameter geser
= 0.01 m = 0.008 m
Jumlah tulangan pokok Jarak tulangan geser
= 4 bh = 0.15 m

Panjang lanjur total = 101 m


Panjang lanjur pagar = 615 + 1200 + 1700 + 1200 + 265
= 4980 cm' = 49.8 m'
Panjang sloof = 101 - 49.8 = 51.2 m'
Volume sloof = 0.15 x 0.20 x 51.22 = 1.54 m3
Jumlah tul. pokok = ( 51.22 x 4 ) : 12 = 18.0 uj'

Panjang 1 tul. geser = 0.15 + 0.15 + 0.20 + 0.20 = 0.70 m


= 0.70 - ( 4 x 0.02 ) = 0.62 m
= 0.62 + 0.02 = 0.64 m
Jumlah tul. geser = ( 51.22 : 0.15 ) + 1 = 343 bh
Panjang tul geser = 343 x 0.64 = 536 m
Jumlah tul. geser = 536 : 12 = 45 uj'

B3.2 Kolom
LANTAI 1

TIPE K1

Dimensi beton bertulang


b = 0.20 m
h = 0.20 m
s = 0.02 m
bk = 0.02 m

Tulangan pokok Tulangan geser


Panjang tulangan pokok Panjang tulangan geser
= 12 m = 12 m
Jumlah kolom = 10 bh Diameter pokok Diameter geser
Panjang kolom = 3.5 m' = 0.12 m = 0.08 m

AMURANG BAY RESIDANCE


(PT. CAHAYA INTI ENERGY)
TAKE OF SHEET QUANTITY SUM
(TIPE 135/204)

Luas penampang = 0.04 m2 Jumlah tulangan pokok Jarak tulangan geser


Volume = 1.4 m3 = 8 bh = 0.15 m

Jumlah tul. Pokok = 10 x 3.5 x 8 = 280 m'


= 280 : 12 = 24 Uj'
Panjang 1 tul. Geser = ( 0.20 x 4 ) + 0.04 = 0.8 m'
= 0.8 - ( 0.02 x 4 ) = 0.72 m'
Jumlah tul. Geser = 10 x 3.5 = 35 m'
= ( 35 : 0.15 ) + 1 = 235 Bh
Panjang tul. Geser = 235 x 0.72 = 169 m'
Jumlah tul. Geser = 169.2 : 12 = 15 Uj'

TIPE K2

Dimensi beton bertulang


b = 0.15 m
h = 0.35 m
s = 0.02 m
bk = 0.02 m

Tulangan pokok Tulangan geser


Panjang tulangan pokok Panjang tulangan geser
= 12 m = 12 m
Jumlah kolom = 4 bh Diameter pokok Diameter geser
Panjang kolom = 3.5 m' = 0.12 m = 0.08 m
Luas penampang = 0.053 m2 Jumlah tulangan pokok Jarak tulangan geser
Volume = 0.735 m3 = 6 bh = 0.15 m

Jumlah tul. Pokok = 4 x 3.5 x 6 = 84 m'


= 84 : 12 = 7 Uj'
Panjang 1 tul. Geser = 0.70 + 0.30 + 0.04 = 1.04 m'
= 1.04 - ( 0.02 x 4 ) = 0.96 m'
Jumlah tul. Geser = 4 x 3.5 = 14 m'
= ( 14 : 0.15 ) + 1 = 95 Bh
Panjang tul. Geser = 95 x 0.96 = 91.2 m'
Jumlah tul. Geser = 91.2 : 12 = 8 Uj'

TIPE K3

Dimensi beton bertulang


Penampang A Penampang B
bA = 0.10 m bB = 0.15 m
hA = 0.15 m hB = 0.35 m
A B
LA = 0.015 m2 LB = 0.05 m2
Ltotal = 0.015 + 0.0525 = 0.07 m2
s = 0.02
bk = 0.02

Tulangan pokok Tulangan geser


Panjang tulangan pokok Panjang tulangan geser Jumlah kolom = 2 bh
= 12 m = 12 m Panjang kolom = 3.5 m
Diameter pokok Diameter geser
= 0.12 m = 0.08 m
Jumlah tulangan pokok Jarak tulangan geser
= 10 bh = 0.2 m

AMURANG BAY RESIDANCE


(PT. CAHAYA INTI ENERGY)
TAKE OF SHEET QUANTITY SUM
(TIPE 135/204)

Jumlah tul. Pokok = 2 x 3.5 x 10 = 70 m'


= 70 : 12 = 6 Uj'
Panjang 1 tul. Geser = 0.50 + 0.15 + 0.3 + 0.7 + 0.08 = 1.03 m'
= 1.03 - ( 0.02 x 8 ) = 0.87 m'
Jumlah tul. Geser = 2 x 3.5 = 7 m'
= ( 7 : 12 ) + 1 = 2 Bh
Panjang tul. Geser = 2 x 0.87 = 1.7 m'
Jumlah tul. Geser = 1.7 : 12 = 1 Uj'

TIPE K3

Dimensi beton bertulang


Penampang A Penampang B
bA = 0.15 m bB = 0.15 m
hA = 0.30 m hB = 0.15 m
A
LA = 0.045 m2 LB = 0.02 m2
B
Ltotal = 0.045 + 0.0225 = 0.07 m2
s = 0.02
bk = 0.02

Tulangan pokok Tulangan geser


Panjang tulangan pokok Panjang tulangan geser Jumlah kolom = 5 bh
= 12 m = 12 m Panjang kolom = 3.5 m
Diameter pokok Diameter geser
= 0.12 m = 0.08 m
Jumlah tulangan pokok Jarak tulangan geser
= 8 bh = 0.2 m

Jumlah tul. Pokok = 5 x 3.5 x 8 = 140 m'


= 140 : 12 = 12 Uj'
Panjang 1 tul. Geser = 0.60 + 0.15 + 0.6 + 0.15 + 0.08 = 1.43 m'
= 1.43 - ( 0.02 x 6 ) = 1.31 m'
Jumlah tul. Geser = 5 x 3.5 = 17.5 m'
= ( 17.5 : 12 ) + 1 = 3 Bh
Panjang tul. Geser = 3 x 1.31 = 3.9 m'
Jumlah tul. Geser = 3.9 : 12 = 1 Uj'

AMURANG BAY RESIDANCE


(PT. CAHAYA INTI ENERGY)
HARGA SATUAN UPAH, BAHAN, ALAT

Jenis Bahan Satuan Harga (Rp)

Tenaga
Mandor oh 125,000.00
Pekerja oh 105,000.00
Kepala Tukang oh 155,000.00
Tukang oh 130,000.00
Tukang Batu oh 130,000.00
Tukang Kayu oh 130,000.00
Tukang Besi oh 130,000.00
Tukang Cat oh 130,000.00
Tukang Pipa oh 130,000.00
Bahan
Balok Kayu m3 -
Batu Belah m3 260,800.00
Baut GRC bh 250.00
Besi angker dia 8 mm kg
Besi beton kg 6,355.14
Cat Besi kg 65,000.00
Cat Dasar kg 135,000.00
Cat Meni kg 60,000.00
Compoun kg 11,815.00
Bata Merah bh 850.00
Cotton Plaster bh 15,000.00
Dynabolt bh 1,500.00
Engsel Jendela bh 22,000.00
Engsel Pintu bh 45,000.00
Floor Drain bh 25,000.00
genteng onduline m2 157,000.00
GRC 3 mm 65,000.00
hollow 2/4 m 57,175.00
hollow 4/4 m 78,615.38
Kaca Bening 5 mm m2 179,025.00
Kawat beton 24,000.00
Kayu kls 3 m3 4,500,000.00
Keramik artistik 10 x 20 bh 8,270.00
Kerikil 485,145.42
Kloset Duduk bh 1,000,000.00
Kran Air bh 40,000.00
Kunci kualitas Baik 275,000.00
Lem kayu 45,000.00
Paku 24,000.00
Paku screw GRC bh 250.00
Papan Kayu kls II m3 7,000,000.00
Papan Listplank GRC m3 35,416.67
Pasir beton 259,000.00
Pasir Pasang 259,000.00
Pipa PVC 1/2 m 16,575.00
Pipa PVC3" m 41,750.00
Plamir Kg 50,000.00
Nok onduline 95,000.00
Plywood uk. 90 x 220 78,000.00
Profil pc 75 Ujg 15,000.00
Reng GDC 6,666.67
screw 1,000.00
Screw reng 250.00
Screw Truss 300.00
Seal Tape
Semen KG 1,269.00
Semen Portland KG 1,269.00
Semen warna KG 13,860.00
Ubin Keramik 40 x 40 km bh 13,700.00
Talang onduline 95,000.00
ALAT

Con Vibrator -
Conc Mixer -
Water Tanker