Installation of Transformer
Installation of Transformer
Installation of Transformer
I. ESTIMATED COST:
A. DIRECT COST:
1. Mobilization / Demobilization 0.48 P 20,000.00
2. Materials:
2.1 Supply Delivery 70.37 2,950,058.00
B. INDIRECT COST:
1. Overhead Contingencies &
Miscellaneous ( 7% to 15% A1to A4) 11.17 468,436.20
3. Profit ( 5% to 12% of A1 to A4 ) 7.45 312,290.80
4. V.A.T. 4.66 195,181.75
III. CONTENGENCIES/RESERVES:
1. Physical ( up to 1% of the Estimated
Cost )
2. Price Escalation
( up to 12% of the estimated Cost )
SUB- TOTAL
TOTAL ESTIMATED PROJECT COST 100.00 P 4,192,503.99
I. General
1 lot Mobilization/Temporary Structures,Utilities and P 10,000.00
Services/Demobilization
1 lot Safety(PPE) and Health 7,000.00
1 lot Standard Billboard 3,000.00
sub-total- - - - - - - - P 20,000.00
II. Labor
1 Foreman 450.00 for 5 days 2,250.00
3 Helpers 340.00 for 5 days 5,100.00
sub-total- - - - - - - - P 7,350.00
I. Materials
90 0 Angle Connector,
4 pcs 189.00 756.00
liquid tight
Potential Transformer
6 pcs 58131.00 348,786.00
15kV, 8400:120V
Wire, 22 sq. mm TW
36 m 135.00 4,860.00
(4/7 AWG)
Wire, 5.5 sq. mm Black
28 m 42.00 1,176.00
THHN
Wire, 5.5 sq. mm Green
70 m 42.00 2,940.00
THHN
Wire, 5.5 sq. mm Red
70 m 42.00 2,940.00
THHN
Wire, 5.5 sq. mm
70 m 42.00 2,940.00
Yelllow THHN
Connector Universal
4 pcs 389.00 1,556.00
Distribution type
Distribution Transformer
6 units 286070.00 1,716,420.00
100kva ST
sub-total- - - - - - - - - - - - - P 2,950,058.00
III. Labor Cost
1 Foreman 450.00 for 30 days 13,500.00
6 Electrician 450.00 for 30 days 81,000.00
5 Helper 340.00 for 30 days 51,000.00
sub-total- - - - - - - - - - - - - P 145,500.00
496,340.00
4,192,503.99
500,000.00
5,188,843.99
98,171.83 P 4,192,503.99
2,098,171.83 (2,094,332.16)
6,000.00
P 2,950,058.00 P 145,500.00
885,017.40
- v
- c
- s
- g
P 6.00
3.84
12.60 1.40
16.44 B 0.70
-
23.33333333333
- 23
-23
-
day -
Attachment to D.O. No. 22 S.2015
ATTACHMENT "A"
APPROVED BUDGET FOR THE CONTRACT
Upgrading of Six (6) Units 100kva Distribution Transformer and Accessories
City Hall & Marcos Building, Barangay I, City of San Fernando, La Union
Project Name and Location
Contract Duration : 35 days
ESTIMATED MARKS UP IN PERCENT TOTAL MARKUP TRANSHI TOTAL DIRECT
ITEM NO. DESCRIPTION QTY. UNIT DIRECT COST PMENT VAT COST TOTAL COST UNIT COST
OCM PROFIT % VALUE
10 12 13 14 15
1 2 3 4 5 6 8 9 11
5X9 5%(5)+(10) (10)+(12) (5)+(13) (14)/(3)
01 General Requirements 1.00 lot 27,350.00 15% 10% 25% 6,837.50 1,709.38 8,546.88 35,896.88 35,896.88
Upgrading of
104 6.00 units 3,095,558.00 15% 10% 25% 773,889.50 193,472.38 967,361.88 4,062,919.88 677,153.31
Transformer
FOUR MILLION NINETY-EIGHT THOUSAND EIGHT HUNDRED SIXTEEN PESOS AND SEVENTY-FIVE
TOTAL P 4,098,816.75
CENTAVOS ONLY
Equipment
Item No.: Description Qty Unit Material Cost Labor Cost OCM CP VAT Total Cost
Rental
01 General Requirements 1 lot 20,000.00 7,350.00 4,102.50 2,735.00 1,709.38 35,896.88
02 Upgrading of Transformer 6 cu.m. 2,950,058.00 145,500.00 464,333.70 309,555.80 193,472.38 4,062,919.88
Grand-Total P 4,098,816.75