Installation of Transformer

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 24

Republic of the Philippines

CITY OF SAN FERNANDO

OFFICE OF THE CITY ENGINEER

INDIVIDUAL PROGRAM OF WORK


( For all types of Projects )
Date: September 7, 2021
LOCATION OF PROJECT: Appropriation: P 4,192,503.99
Barangay One Source of Fund: For Funding
Issued Obligated
PROJECT CATEGORY: Authority : City of San Fernando
Electrical
Calendar Days : 35 days
PROJECT DESCRIPTION:

Upgrading of Six (6) Units 100kva Distribution Transformer and Accessories


City Hall & Marcos Building, Barangay I, City of San Fernando, La Union
MINIMUM EQUIPMENT REQUIREMENTS TECHNICAL PERSONNEL REQUIREMENTS
DESCRIPTION NO. DESCRIPTION NO. DESCRIPTION NO. DESCRIPTION NO.
Boom truck 1 Foreman 1
Chain block 1 Electrician 6
Helper 5

ESTIMATED COST OF PROPOSED WORK ITEMS


ITEM
DESCRIPTION % of UNIT QUANTITY DIRECT COST UNIT
NO.
01 General Requirements 0.88 lot 1 P 35,896.88 35,896.88
02 Upgrading of Transformer 99.12 units 6 P 4,062,919.88 677,153.31

TOTAL- - - - - - 100.00 P 4,098,816.75


BREAKDOWN OF ESTIMATED EXPENDITURES % of Total Amount

I. ESTIMATED COST:

A. DIRECT COST:
1. Mobilization / Demobilization 0.48 P 20,000.00

2. Materials:
2.1 Supply Delivery 70.37 2,950,058.00

3. Labor 3.65 152,850.00


4. Equipment Expenses - -

B. INDIRECT COST:
1. Overhead Contingencies &
Miscellaneous ( 7% to 15% A1to A4) 11.17 468,436.20
3. Profit ( 5% to 12% of A1 to A4 ) 7.45 312,290.80
4. V.A.T. 4.66 195,181.75

(SUB-TOTAL) CONTRACT COST 97.77 P 4,098,816.75

II. ESTIMATED GOVERNMENT EXPENDITURES:


1. Engineering & Administrative
Overhead ( 3% of A1 to A4 ) 2.23 93,687.24
2. Quality Control
3. Materials to be Furnished by the
Government
4. R.O.W./ Site Acquisition

SUB-TOTAL 2.23 P 93,687.24

III. CONTENGENCIES/RESERVES:
1. Physical ( up to 1% of the Estimated
Cost )
2. Price Escalation
( up to 12% of the estimated Cost )
SUB- TOTAL
TOTAL ESTIMATED PROJECT COST 100.00 P 4,192,503.99

Prepared by: Recommending for Approval :

JAY-AR CHRIS T. CARIAGA MADELINE R. TADIFA


Engineer II City Engineer

Checked by: Approved by:

ARNOLD D. ADUCA HON. HERMENEGILDO A. GUALBERTO


Architect III City Mayor
ITEM NO.: 01
General Requirements
QUANTITY : 1 lot

I. General
1 lot Mobilization/Temporary Structures,Utilities and P 10,000.00
Services/Demobilization
1 lot Safety(PPE) and Health 7,000.00
1 lot Standard Billboard 3,000.00
sub-total- - - - - - - - P 20,000.00

II. Labor
1 Foreman 450.00 for 5 days 2,250.00
3 Helpers 340.00 for 5 days 5,100.00
sub-total- - - - - - - - P 7,350.00

TOTAL DIRECT COST - - - - - - - - - - - - P 27,350.00

III. OVERHEAD CONT. & MANAGEMENT - - - - - - - - - - - - - - - - - - - - P 4,102.50


IV. CONTRACTORS PROFIT - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 2,735.00
V. Value Added Tax - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1,709.38
TOTAL INDIRECT COST - - - - - - - - - - - - P 8,546.88

TOTAL COST FOR ITEM 01 - - - - -P- - 35,896.88


UNIT COST FOR ITEM 01 - - - - - - P- - - 35,896.88 /lot
WORKING DAYS - - - - - - - - - - - - - - - 5 days
ITEM NO. 02
Upgrading of Transformer
Quantity: 6 units

I. Materials

2 pc Bolt, Machine 1/2 X 14” 54.00 108.00

Bolt, Machine 3/16” x


6 pcs 8.00 48.00
1/2”
Bolt, Machine 3/16” x 1-
8 pcs 14.00 112.00
1/2” stainless
Bolt, Machine 3/8” x 1-
48 pcs 8.50 408.00
1/2” stainless

2 pc Bolt, Machine 5/8 x 14” 62.00 124.00

16 pcs Bolt, Machine 5/8 x 6” 36.00 576.00

4 pcs Conduit Coupling 1” 11.00 44.00

Conduit Flexible Metal


14 m 236.00 3,304.00
1”

4 pcs Conduit, IMC 1”, 10’ 891.00 3,564.00

2 pc Conduit, IMC 1”, 5’ 473.00 946.00

90 0 Angle Connector,
4 pcs 189.00 756.00
liquid tight

Connector, Hotline #2/0


6 pcs 1148.00 6,888.00
Cu-al

Connector, straight 1”,


20 pcs 189.00 3,780.00
liquid tight

2 set Connector UD 365.00 730.00

2 pc CTPT Rack 13102.00 26,204.00

12 pcs Dummy Plate (Cluster) 115.00 1,380.00

2 pc LB Condulet 74.00 148.00


Arrester, Lightning 9/10
6 pcs 3780.00 22,680.00
KV
4 pcs Lock Bushing 18.00 72.00
4 pcs Locknut 6.00 24.00
Meter Box, stainless,
2 pc 11610.00 23,220.00
22”x14”x10”
8 pcs Pole strap 297.00 2,376.00

4 pcs Electrical tape 40.00 160.00

4 pcs Rubber tape 115.00 460.00


Terminal lugs, 5.5-5 stud,
52 pcs 11.00 572.00
yellow
Terminal lugs, 5.5-8 stud,
20 pcs 14.00 280.00
yellow
Test Switch, 10 poles,
2 pc 4725.00 9,450.00
30A
Current Transformer
6 pcs 62667.00 376,002.00
15kV, 30/25/15:5

Potential Transformer
6 pcs 58131.00 348,786.00
15kV, 8400:120V

48 pcs Round washer 12.00 576.00

4 pcs Washer, square 5/8” 18.00 72.00

36 m Wire, 14 sq. mm Bare 88.00 3,168.00

Wire, 22 sq. mm TW
36 m 135.00 4,860.00
(4/7 AWG)
Wire, 5.5 sq. mm Black
28 m 42.00 1,176.00
THHN
Wire, 5.5 sq. mm Green
70 m 42.00 2,940.00
THHN
Wire, 5.5 sq. mm Red
70 m 42.00 2,940.00
THHN
Wire, 5.5 sq. mm
70 m 42.00 2,940.00
Yelllow THHN

6 units Arrester, Lightning 10kV 4104.00 24,624.00

Bolt, Double-Arming 5/8


8 pcs 143.00 1,144.00
x 20”
12 pcs Bolt, Eye 5/8” 176.00 2,112.00

4 pcs Bolt, Machine ½ x 12” 49.00 196.00

2 pc Bolt, Machine ½ x 14” 54.00 108.00

4 pcs Bolt, Machine ½ x 6” 27.00 108.00

16 pcs Bolt, Machine 5/8 x 4” 35.00 560.00

40 pcs Bolt, Machine 5/8 x 5” 38.00 1,520.00

4 pcs Bolt, Oval-Eye 5/8 x 16” 136.00 544.00

4 pcs Brace, Alley Arm 7’ 1499.00 5,996.00

6 pcs Bracket, Cut-out/Arrester 1013.00 6,078.00

4 pcs Clamp, Guy 3 bolt 5/8 “ 236.00 944.00

Clamp, pole 9-11” RL-


4 pcs 513.00 2,052.00
type
12 pcs Clamp, Strain 2 Bolt 648.00 7,776.00
12 pcs Clevis, Ball 170.00 2,040.00
6 pcs Clevis, Half Oval 270.00 1,620.00
Connector Hotline 2/0 al-
8 pcs 1148.00 9,184.00
cu
Connector Split bolt
12 pcs 5373.00 64,476.00
1000MCM cu (KS44)

Connector Universal
4 pcs 389.00 1,556.00
Distribution type

Cross Arm steel 6 pin (3


4 pcs 2228.00 8,912.00
x 4 x 8’)

Cut-out fuse Assy


6 sets 5670.00 34,020.00
100A/15kV ABChance

10 pcs Dummy Plate (cluster) 115.00 1,150.00

6 pcs Fuse Link, 12Amps 257.00 1,542.00


Grounding Rod 5/8” x
2 pc 776.00 1,552.00
10’
Grounding Clamp
2 pc 38.00 76.00
Aluminum
Insulator, Brown Spool
12 pcs 31.00 372.00
(#53-2)
Insulator, Pin-type 5.5”
8 pcs 149.00 1,192.00
(#55-4)

Insulator, Suspension 10”


24 pcs 783.00 18,792.00
(#52-3 Brown)

Pin Steel 5/8” long shank


8 pcs 513.00 4,104.00
7/8x8-1/4x5.5”x1”

Pole, concrete 40’/5


2 pc 21659.00 43,318.00
(12.0m)

2 pc Rack, Secondary 3 spool 675.00 1,350.00

12 pcs Socket, Eye 5/8” 243.00 2,916.00

12 pcs Transformer Cluster 3p 567.00 6,804.00

Distribution Transformer
6 units 286070.00 1,716,420.00
100kva ST

14 pcs Washer, round ½ 12.00 168.00

26 pcs Washer, square 5/8 18.00 468.00

Wire, #6/7 (14 mm sq.)


70 m 81.00 5,670.00
cu, bare

110 m Wire, ACSR #2/7 bare 28.00 3,080.00

10 m Wire, Guy 3/8 x 7 strand 44.00 440.00

Wire, THW #650 MCM


50 m 2264.00 113,200.00
(325 mm sq.) poly

sub-total- - - - - - - - - - - - - P 2,950,058.00
III. Labor Cost
1 Foreman 450.00 for 30 days 13,500.00
6 Electrician 450.00 for 30 days 81,000.00
5 Helper 340.00 for 30 days 51,000.00
sub-total- - - - - - - - - - - - - P 145,500.00

TOTAL DIRECT COST- - - - - - - - - P 3,095,558.00

IV. Overhead Contingencies- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 464,333.70


V. Contractor's Profit- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 309,555.80
VI. Value Added Tax- - - - - - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - 193,472.38
TOTAL INDIRECT COST- - - - - - - -P 967,361.88

TOTAL COST FOR ITEM 02- - - - - P 4,062,919.88


UNIT COST FOR ITEM 02- - - - - - - 677,153.31 /unit
WORKING DAYS- - - - - - - - - - - - - 30 days
-

496,340.00
4,192,503.99
500,000.00
5,188,843.99
98,171.83 P 4,192,503.99

2,098,171.83 (2,094,332.16)

6,000.00
P 2,950,058.00 P 145,500.00

885,017.40
- v
- c
- s
- g

P 6.00

3.84
12.60 1.40
16.44 B 0.70
-
23.33333333333
- 23
-23
-
day -
Attachment to D.O. No. 22 S.2015
ATTACHMENT "A"
APPROVED BUDGET FOR THE CONTRACT
Upgrading of Six (6) Units 100kva Distribution Transformer and Accessories
City Hall & Marcos Building, Barangay I, City of San Fernando, La Union
Project Name and Location
Contract Duration : 35 days
ESTIMATED MARKS UP IN PERCENT TOTAL MARKUP TRANSHI TOTAL DIRECT
ITEM NO. DESCRIPTION QTY. UNIT DIRECT COST PMENT VAT COST TOTAL COST UNIT COST
OCM PROFIT % VALUE
10 12 13 14 15
1 2 3 4 5 6 8 9 11
5X9 5%(5)+(10) (10)+(12) (5)+(13) (14)/(3)
01 General Requirements 1.00 lot 27,350.00 15% 10% 25% 6,837.50 1,709.38 8,546.88 35,896.88 35,896.88

Upgrading of
104 6.00 units 3,095,558.00 15% 10% 25% 773,889.50 193,472.38 967,361.88 4,062,919.88 677,153.31
Transformer
FOUR MILLION NINETY-EIGHT THOUSAND EIGHT HUNDRED SIXTEEN PESOS AND SEVENTY-FIVE
TOTAL P 4,098,816.75
CENTAVOS ONLY

Prepared by: Recommending for Approval :

JAY-AR CHRIS T. CARIAGA MADELINE R. TADIFA


Engineer II City Engineer

Checked by: Approved by:

ARNOLD D. ADUCA HON. HERMENEGILDO A. GUALBERTO


Architect III City Mayor
4,098,816.75
-
BILL OF QUANTITIES

Upgrading of Six (6) Units 100kva Distribution Transformer and Accessories


City Hall & Marcos Building, Barangay I, City of San Fernando, La Union

Equipment
Item No.: Description Qty Unit Material Cost Labor Cost OCM CP VAT Total Cost
Rental
01 General Requirements 1 lot 20,000.00 7,350.00 4,102.50 2,735.00 1,709.38 35,896.88
02 Upgrading of Transformer 6 cu.m. 2,950,058.00 145,500.00 464,333.70 309,555.80 193,472.38 4,062,919.88
Grand-Total P 4,098,816.75

Prepared by: Recommending for Approval :

JAY-AR CHRIS T. CARIAGA MADELINE R. TADIFA


Engineer II City Engineer

Checked by: Approved by:

ARNOLD D. ADUCA HON. HERMENEGILDO A. GUALBERTO


Architect III City Mayor
4,098,816.75
-
Section VI. Specifications

Item No. Description


01 General Requirements
Mobilization/Temporary Structures,Utilities and Services/Demobilization
Safety(PPE) and Health
Standard Billboard
2 Upgrading of Transformer
Bolt, Machine 1/2 X 14”
Bolt, Machine 3/16” x 1/2”
Bolt, Machine 3/16” x 1-1/2” stainless
Bolt, Machine 3/8” x 1-1/2” stainless
Bolt, Machine 5/8 x 14”
Bolt, Machine 5/8 x 6”
Conduit Coupling 1”
Conduit Flexible Metal 1”
Conduit, IMC 1”, 10’
Conduit, IMC 1”, 5’
90 0 Angle Connector, liquid tight
Connector, Hotline #2/0 Cu-al
Connector, straight 1”, liquid tight
Connector UD
CTPT Rack
Dummy Plate (Cluster)
LB Condulet
Arrester, Lightning 9/10 KV
Lock Bushing
Locknut
Meter Box, stainless, 22”x14”x10”
Pole strap
Electrical tape
Rubber tape
Terminal lugs, 5.5-5 stud, yellow
Terminal lugs, 5.5-8 stud, yellow
Test Switch, 10 poles, 30A
Current Transformer 15kV, 30/25/15:5
Potential Transformer 15kV, 8400:120V
Round washer
Washer, square 5/8”
Wire, 14 sq. mm Bare
Wire, 22 sq. mm TW (4/7 AWG)
Wire, 5.5 sq. mm Black THHN
Wire, 5.5 sq. mm Green THHN
Wire, 5.5 sq. mm Red THHN
Wire, 5.5 sq. mm Yelllow THHN
Arrester, Lightning 10k
Bolt, Double-Arming 5/8 x 20”
Bolt, Eye 5/8”
Bolt, Machine ½ x 12”
Bolt, Machine ½ x 14”
Bolt, Machine ½ x 6”
Bolt, Machine 5/8 x 4”
Bolt, Machine 5/8 x 5”
Bolt, Oval-Eye 5/8 x 16”
Brace, Alley Arm 7’
Bracket, Cut-out/Arrester
Clamp, Guy 3 bolt 5/8 “
Clamp, pole 9-11” RL-type
Clamp, Strain 2 Bolt
Clevis, Ball
Clevis, Half Oval
Connector Hotline 2/0 al-cu
Connector Split bolt 1000MCM cu (KS44)
Connector Universal Distribution type
Cross Arm steel 6 pin (3 x 4 x 8’)
Cut-out fuse Assy 100A/15kV ABChance
Dummy Plate (cluster)
Fuse Link, 12Amps
Grounding Rod 5/8” x 10’
Grounding Clamp Aluminum
Insulator, Brown Spool (#53-2)
Insulator, Pin-type 5.5” (#55-4)
Insulator, Suspension 10” (#52-3 Brown)
Pin Steel 5/8” long shank 7/8x8-1/4x5.5”x1”
Pole, concrete 40’/5 (12.0m)
Rack, Secondary 3 spool
Socket, Eye 5/8”
Transformer Cluster 3p
Distribution Transformer 100kva ST
Washer, round ½
Washer, square 5/8
Wire, #6/7 (14 mm sq.) cu, bare
Wire, ACSR #2/7 bare
Wire, Guy 3/8 x 7 strand
Wire, THW #650 MCM (325 mm sq.) poly

Prepared by: Recommending for Approval :

JAY-AR CHRIS T. CARIAGA MADELINE R. TADIFA


Engineer II City Engineer

Checked by: Approved by:

ARNOLD D. ADUCA HON. HERMENEGILDO A. GUALBERTO


Architect III City Mayor

You might also like