Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Project Title: Wagud-Buaya Bridge (Sub-structure) Phase I

Location: Tanudan, Kalinga

QUANTITY COMPUTATIONS (Accomplishment)

TOTAL AREA OF CORRECTED DEFECTS

Length (m) Width (m) Average Width (m) PCCP Area (sq.m)

2.45 2.50 2.50 6.13


3.00 2.50 2.50 7.50
4.53 2.50 2.50 11.33
4.48 2.50 2.50 11.20
4.49 2.50 2.50 11.23
0.80 2.50 2.50 2.00
4.60 2.50 2.50 11.50
4.45 2.50 2.50 11.13
4.52 2.50 2.50 11.30
4.41 2.50 2.50 11.03
Total Corrected Area 94.35

TOTAL AREA INCURRED DEFECTS AS PER PREVIOUS FINDINGS OF TAS

Total Area of Defects in previous findings = 146.25

Unit Cost of Item 311 as per contract = 1,441.39 Php/sq.m

Item Decription Unit Quantity Unit Cost Total Cost

PCC Pavement
A. 311(1)a sq.m 146.25 1,441.39 Php210,803.29
(Plain), 200mm THK
PCC Pavement
B. 311(1)a sq.m 94.35 1,441.39 Php135,995.15
(Plain), 200mm THK
Total Area of uncorrected defects/deficiency = 51.90
Total Amont of uncorrected defects/deficiency = Php74,808.14

Prepared by:

Engr. JUN JUN P. ANCHETA


Technical Audit Specialist - I

You might also like