Professional Documents
Culture Documents
Chhattisgarh State Power Generation Comp
Chhattisgarh State Power Generation Comp
PROJECT HIGHLIGHTS
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 2
13. Cooling System : Closed cycle cooling system with Natural Draft
Cooling Towers
14. Primary Fuel & Source : SECL coal fields.
15. Support Fuel & Source : HFO/LDO from nearest refinery/oil depots
17. Transportation
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 3
1.1 The State of Chhattisgarh is endowed with abundant mineral wealth and
is in the threshold of developing industrial infrastructure to cater to the
enhanced need of the region. With industrial development receiving
highest priority, this nascent state has taken up several infrastructural
developments. With the urbanization and increased use of power for
irrigation, has created a level of demand, which has outstripped the
growth of power generation in the state. Several projects have been
identified from time to time meeting the growing demand of power. This
is one of identified projects.
1.2 Installed capacity of Chhattisgarh system at the end of 10th plan was
6839.7 MW including own generation, share from various central sector
projects. As per the 17th EPS, peak load of Chhattisgarh system peak
load at the end of 12th plan will be 5375 MW and 7279 MW by end of
year 2016-17. Considering the utilization factors of 70% Chhattisgarh
system requires about 7628 MW & 10398 MW by the year 2021-22 by
the year 2016-17. In order to bridge the gap between power demand
and supply generating projects will have to be planned & executed.
Keeping in view the growth rate of power demand in the State of
Chhattisgarh. Justification of the project is discussed in Chapter - 2.
1.3 As per the Electricity Act 2003, any generating company may establish,
operate & maintain power generating station.
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 4
1.6 The proposed 2x250 MW power project site at Bundali village, block-
Manendragarh Korea District, Chhattisgarh. Nearest railway station is
Paradol at a distance of about 11 km.
1.7 The power plant will require about 1855 cu.m/hr. of raw water and 2.68
million tonnes of coal per annum at plant load factor of 85%.
1.8 Selection of unit rating & type of boiler unit has been discussed in
Chapter-4.0 and it is proposed to have two units each unit of 250 MW
capacity with conventional pulverized coal fired boiler.
1.9 Technical features outlining the salient parameters of the main plant and
equipment are discussed in the Chapter-5.0. The state-of-the-art
technology will be deployed for auxiliaries and sub-systems to ensure
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 5
1.10 Coal receipt will be through Indian Railway System. Unloading will be
through track hoppers of coal handling plant of the power station. Coal
handling system has the capacity of 1000 tph for two-shift operation.
Two stage crushing; stacking, reclaiming & feeding system have been
envisaged with provision of inter-connection with existing coal handling
system.
1.11 Fly ash generated is proposed to be handled in dry form. Bottom ash
will be extracted and disposed off by slurry disposal system. Ash
utilization will be as per MOEF guidelines. It is proposed to use ash for
the manufacture of cement, bricks & building material etc. Excess fly
ash will be disposed off in high concentration slurry form to ash dyke
1.12 Water will be drawn from Hasdeo River. The clarification and
demineralisation of plant water has been envisaged. Circulating water
system will be closed circuit cooling system using cooling towers. Make
up of water will be drawn from Hasdeo River. Clarified water will be
used for cooling tower makeup. Natural draft cooling towers are
proposed in view of low O&M Cost.
1.13 The electrical system proposed will be equipped with adequately sized
equipments and with generous redundancy to ensure uninterrupted
operation. Electrical equipment and systems are discussed in Chapter
6.2 of the report. Power will be evacuated through 220 KV transmission
lines.
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 6
1.16 Civil engineering aspects envisaged are given in the Chapter – 6.4
would be necessary to provide the staff colony for accommodating the
staff required for the O&M activities of the power plant.
1.18 Adequate facilities will be developed for execution of the project based
on EPC package for BTG alongwith C&I and Civil works implementation
through the supplier selected for the purpose on Turnkey basis. All
remaining balance of plant equipment will be implemented through
agencies deployed in the field through open tender/limited enquiry. In
Chapter–9.0 of the report, O&M staff requirement for operation and
maintenance has been detailed out. This may under go revision as per
CSPGCL own norms of manpower requirement. The training
requirement of O&M persons is also discussed in this Chapter.
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 7
1.20 It is proposed to finance the project such that Capital structure is built up
of Equity Capital 20% & Loan Capital 80%. The equity capital will be
built up by CSPGCL. Project cost with interest during construction is
estimated as ` 2934.76 Crores i.e. ` 5.87 Crores/MW. Levelised tariff at
85% PLF is estimated as ` 3.16/kwh.
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 8
TABLE – 2.1
(Figures in MW)
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 9
TABLE – 2.2
LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE: - CHATTISGARH
Status
Type
(MW) During XIth of state 2007-2012 Date/ (Likely Date
Plan (MW) (MW) of
(MW) Commissioning)
CENTRAL-SECTOR
SIPAT STPS II U-4,5 T C 1000.00 1000.00 158 COMM 1000.00 27.05.2008
1.08.2008
BHILAI JV U-1,2 T C 500.00 500.00 50 COMM 500.00 20.04.2008
12.07.2009
*KORBA ST.-III U-7 T C 500.00 500.00 81 COMM 500.00 26.12.2010
KAHALGAON 6,7 T C 1000.00 1000.00 20 COMM 1000.00 16.03.2008
31.07.2009
CENTRAL – SECTOR TOTAL 309.00
STATE-SECTOR
KORBA EAST EXTN. U-2 T C 250.00 250.00 250.00 COMM 250.00 11.12.2007
STATE - SECTOR TOTAL 250.00
PRIVATE SECTOR
LANCO (AMARKANTAK) T U 600.00 600.00 600 COMM 600.00 04.06.2009,
25.03.2010
U-1,2
RAIGARH TPP-(JINDAL) T C 1000.00 1000.00 1000 COMM 1000.00 2.09.2007
PH I & II U-1,2,3,4 10.02.2008
6.03.2008
17.06.2008
PRIVATE-SECTOR TOTAL:- 1600
WITH BEST EFFORTS
VINDHYACHAL IV U-2 T U 1000.00 500.00 31.27 (2011-2012)
SIPATI T U 1980.00 1980.00 313 (2010-2011)
MAUDA TPP U - 1 T U 1000.00 500.00 31.27 (2011-2012)
PRIVATE-SECTOR TOTAL:- 375.54
GRAND-TOTAL 2534.54
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 10
From the Table 2.1 it will be seen that Chhattisgarh State has
installed capacity of 4882.47 MW including Central Sector Share.
With likely capacity addition (as per Table 2.2) the capacity
availability will be about 5258.01 MW (i.e. 4882.47+375.54) by the
year 2011-12 i.e. by end of 11th plan period.
TABLE 2.3
From the above table, it may be also seen the State of Chhattisgarh
suffered peaking power deficit of 8.8% and energy deficit of (-) 1.7%
during year 2010-11.
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 11
Considering the above scenario, the need for installing 2x250 MW TPP
is fully justified.
2.2.1 In the State of Chhattisgarh the Electricity Act 2003 has come in force.
As per Electricity Act 2003, clause 7 “Any Generating Company may
establish, operate and maintain a generating station without obtaining
licence under this act if it complies with technical standards relating to
connectivity with the grid.
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 12
2.2.2.1 Electricity Act 2003 do not indicate special requirement like clearances
from the concerned statutory or non-statutory authorities for setting up
thermal power plant. However clause 10 (3) stipulates that generating
company will:-
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 13
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 14
a) Availability of land
b) Rail/road accessibility
c) Availability of fuel and proximity to source
d) Availability of water and proximity to source
e) Load demand/ Power absorption plan
f) Environmental consideration
The most important criteria for selection of site for TPS is availability of
land with least R&R issues, fuel availability and its transportation, water
availability and acceptability from environmental considerations.
The basic requirement for establishing the project was studied in the
backdrop of available infrastructure facilities and requirement of
developing facilities to ensure compatibility and adequacy of system.
Various sites in Korea District were explored and three (3) potential
sites for the project were identified.
Site – 1 Bundali
Site – 2 Banji
Site – 3 SajaPahar
The site – 1, i.e. Bundali has been selected in view of adequate land
availability, proximity to water source, least R&R issue etc.
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 15
a) Land
Land Requirement
b) Rail/Road Accessibility
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 16
transportation of coal and fuel oil for the power plant. The rail
system will be developed as per recommendation of the study
conducted for the purpose. No problem is envisaged in
accessibility and transportation of heavy equipment to site by
road or rail.
. Coal
Fuel oil
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 17
d) Availability of Water
e) Power evacuation
f) Environmental Aspects
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 18
twin flue stack of 220 meters height will be provided for the
generating units as per the guidelines.
M/s CSPGCL will obtain TOR for conducting the EIA studies and
the recommendations and environmental stipulation will be
followed during the implementation phase of the project.
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 19
i. 2 units of 250 MW
ii. 1 unit of 500 MW
ii) Better efficiency of large sized boiler and steam turbine and lower
overall heat rate.
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 20
units also gives flexibility in operation by adjusting load as per supply &
load demand.
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 21
The basic plant designs consider the proven concept as far as possible.
Judicious provision to be considered for reasonable spare capacities in
various system and system components and interchangeability of
equipment/ system. State of art technology has been considered for
design of the proposed system.
1. The steam generating unit is sized for 810 tphr. steam flow
(minimum) at 155 kg/cm2 (g) minimum super heater outlet steam
pressure and 540(5)C steam temperature re-heated steam
flow at RH out let 37.31 kg/cm2(g) pressure 540+50C
temperature at MCR with specified coal. This will ensure
adequate margin over the requirement of Turbine at 100% MCR
to cater for:
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 22
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 23
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 24
a) Air Heaters
The boiler furnace and flue gas passages will be designed for
low gas velocity of 10 m/s to minimize erosion and slagging
effect.
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 25
b) Draft System
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 26
d) Soot Blowers
Each boiler will be provided with a set of soot blowers, which will
be automatic, sequential, electrically operated type, arranged for
on-line cleaning of the furnace, super heaters, reheaters, air
heaters economiser. Steam for the soot blowing system will be
from PRDS system. The soot blowing system will comprises of
long retractable soot blower wall blower (for furnace) a rotary
swivel arm type for air pre-heater. The system will be complete
with piping, valves and fittings etc.
e) Structural Works
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 27
The unit will comprise of 3x50% electric motor driven boiler feed pumps
per unit with the booster pumps mounted on the common shaft. Each
pump will be designed to give parameters to suit the steam generator
requirements. The feed pump will be able to handle feed water of pH.
8.5 to 9.5 and of temperature upto 185 deg. C (tentative).
The boiler feed pump will be of horizontal, centrifugal type. The boiler
feed pump outer casing will be of barrel type with end removal. The
inner pump assembly comprising of shaft, impellers, stage casings will
be capable of being removed and replaced as a unit without disturbing
the feed piping. Each feed pump will be equipped with mechanical seal
at drive end and non-drive of the shaft. The pump will be of robust
construction and does not require warm-up. The shaft of booster pump
and the electric drive motor, drive motor and gear box, gear box and
boiler feed pump will be connected by diaphragm type dry coupling.
The boiler feed water system will be designed to operate primarily in an
automatic mode over the range of system design loads. The
arrangement will provide automatic start-up one of the standby feed
pump under conditions like tripping of the running BFP’s and/or
discharge header pressure low etc.
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 28
* Clean environment
due to no Mill
rejects -(No reject
handling system
required due to the
inherent design)
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 29
Each steam generator will be provided with “n” number operating + one
(1) as standby mills, while generating at BMCR with worst coal. Coal fed
size to mills will be (-) 25 mm.
The pulverizer and its motor will be capable of being started after having
tripped without removing the coal contained in the pulverizer. The
equipment will be designed to operate over a wide range of capacity to
minimize start-stop during load changes. All wearing parts will be
arranged such that they are replaced easily, without total dismantling of
the pulverizer. Design will be such that heavy parts can be handled easily
for maintenance purpose.
Coal chutes of approved type and size will be provided between raw
coal bunker shut off gate and inlet to the coal feeder and from feeder to
the pulverizers. Height of coal chute between bunker outlet and feeder
inlet will be adequately maintained to prevent hot air to come out.
Material of chute will be stainless steel. Coal chutes will be provided
with poke holes. An emptying chute, suitable for loading trucks at
ground floor, will also be provided.
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 30
Apart from the pulverizers, boiler unit will be equipped with gravimetric
raw coal feeders. Mill reject handling system of adequate capacity will
be provided.
Primary Air Fans and seal air fans of adequate capacity will be complete
with necessary ducting, local instruments, valves, suitable for remote
operation from the control room, etc will be included with the sealing
system designed so as to prevent any leakage of coal dust into the
bearing and atmosphere.
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 31
Boiler
1 2 3
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 32
1 2 3
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 33
The each steam turbine 250 MW MCR will be three cylinders, (one HP,
one IP and one LP cylinders), high pressure 3000 RPM, multistage,
tandem compound, single reheat, condensing reaction turbine unit with
six (6) uncontrolled extractions for regenerative feed water heating &
steam sealings. The HP and IP cylinder will be single flow type and LP
cylinder will be double flow type.
5.2.1.1 HP Turbine
The HP turbine will be designed with single flow. This will have a
double - shell casing consisting of axially split inner shell enclosing the
rotor and barrel-type outer shell. Main steam to the HP turbine will be
supplied through two combined stop and control valves. The exhaust
branch will be located below the turbine.
5.2.1.2 IP Turbine
The IP-turbine will be designed with single flow. This will have a double
- shelled casing with horizontally split inner casing, and outer casing.
Reheat steam will be admitted through two combined stop and control
valves of the IP turbine. The valves will be arranged on either side of IP
casing. The exhaust branches will be on the top of the casing.
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 34
5.2.1.3 LP Turbine
5.2.1.4 Blading
5.2.1.5 Valves
The HP-Turbine will be fitted with two combined emergency stop valve
and control valves for main steam admission. Two combined stop and
control valves will be installed at the IP-Turbine for hot reheat steam
admission.
Each combined valve consists of a stop valve and a control valve that
will be mounted on a common body. Every stop valve and control
valve will be equipped with separate Electro-Hydraulic-Actuator. The
main steam valves will be directly mounted on the HP-turbine.
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 35
All shaft glands, sealing the steam in the cylinders will be of the axial-
flow labyrinth type.
During start-up and low loads seal steam will be supplied to the turbine
glands from the auxiliary steam header or cold reheat line through a
seal steam regulating valve. During normal operation, the HP and IP
turbines will be of self-sealing type and under that condition the
auxiliary / CRH steam source will be cut off and the leak-off steam from
HP and IP glands will be used for sealing the LP glands. The excess
leak-off steam will be led to the condenser.
The turbine will have an over speed limit of (+) 10%, the critical speeds
being at (-) 15% below and (+) 15% above the normal speed while the
turbine blades are tuned for a frequency variation from (+) 3% to (-)
5%.
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 36
The journal bearings and one combined journal & thrust bearing will be
used for supporting the turbine shafting system. The combined journal
and thrust bearing at the rear of the HP turbine comprises a self-
adjusting journal bearing and a thrust bearing to accept the unbalanced
residual thrust. The other journal bearings will also be of the self-
adjusting type. Bearing temperatures will be acquired by
thermocouples located directly under the white-metal lining of the
bottom shell in the journal bearings and in two diametrically opposed
pads in the thrust bearing.
The oil system will supply oil for lubrication and cooling of turbine and
generator bearings, and to the hydraulic shaft turning gear during start-
up and shutdown. This system will be provided with AC & DC powered
oil pumps. To improve lubrication of the bearings during start-up and
shut down, a jacking oil system will be installed which also supplies
motive oil to turning gear.
(a) The main oil pump will be centrifugal/gear type. The turbine
shaft will directly drive it. It will have sufficient capacity to handle
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 37
(d) One (1x100%) each AC & DC motor jacking oil pumps will be
provided to lift the rotor at the bearing during turning gear
operation.
(e) Seal oil pumps to supply oil for generator seals by separate AC
driven oil pumps.
(f) Oil tank of sufficient capacity for oil changes. 2x100% duty
vapour extraction fans. The 2x100% capacity oil coolers will be
provided for oil cooling.
(g) A lube oil purification unit will be permanently installed for each
unit for the total oil charge on a continuous basis.
The turbine will be equipped with two channel digital turbine controller
ensuring stable operation under all operating condition, including grid
disturbances and level throw off condition. The turbine governing
system will be designed for high accuracy, high operating speed and
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 38
60% H.P. and L.P. Turbine bypass station will be provided to act not
only as a protection to the turbine during pressure rise resulting from
sudden load throw-off but also to enable operation of the unit at loads
lower than the control load. Further HP/LP bypass will permit quick,
repeated hot starts of the unit on its tripping.
The LP bypass station will be connected to the hot reheat line and
discharges the steam into the condenser. The hot reheat steam will be
desuperheated by means of condensate injection. The bypass system
shall be in operation when the steam turbine is not able to receive the
entire steam quantity, e.g. during start-up or in case of a load rejection.
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 39
(a) Quick start up of the steam generator from cold, warms & hot
conditions.
(b) Parallel operation of the bypass with turbine under large load
throw-off.
2. The condenser will be a two pass single shell surface type, box
type construction with divided water box design. The steam
space will be of rectangular cross-section to achieve optimum
utilization of the enclosed volume for the necessary condensing
surface. The condenser will be located below the LP turbine and
form an integral part of it.
3. The steam dome, shell and hot well are steel fabrications, as are
the water boxes. The condenser will be fixed supported on the
foundation beneath.
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 40
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 41
The unit will comprise of (2x100%) vacuum pumps along with all
accessories and instrumentation for condenser air evacuation. The
vacuum pumps and accessories will be used to create vacuum by
removing air and non-condensate gases from steam condenser during
plant operation. Vacuum pumps will be of single / two stage liquid ring
type with rotor eccentric to the casing with both stages (if two stage
pump is selected) mounted on a common shaft. Vacuum pumps will
be sized as per latest HEI requirements.
Each unit will have 3x50% capacity motor driven condensate extraction
pumps (two operating and one standby). The condensate pumps will
be vertical canister type, multistage centrifugal diffuser design with a
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 42
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 43
5.2.3.2 Deaerator
Certificate No.07/170/J
CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED Sheet - 44
5.2.4 The brief typical turbine parameters of 250 MW unit are as under:-
Certificate No.07/170/J