Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

APPEXDIX G – Simple Lifting Plan

Number: RJ/LP/SI/
LIFTING PLAN (Simple) Part 1

Date: Work Area: Work Permit No:

Task:

Job Safety Analysis No: Diagram, Drawing or Sketches Attached:

Maximum Weight of Load: Actual / Assumed / Calculated:

Description of Lifting Operation:

Check List: Possible considerations (not exhaustive)


Hazards to personnel in the area Weigh of load verified Trial lift required
No lifting points directly above the load Load on pallets requires securing Risk of overturning
Awkward size / Shape /Sharp edges Transport fastenings removed Working under load
Dedicated lifting points on the load Stability of the load an issue Cross Hauling required
Certified suspension points available High Center of gravity Tandem lifts involved
Restricted headroom or confined area Lifting chemicals Tag lines Required
Correctly installed lifting equipment Conflicting tasks in the area Barriers Required
Correctly installed lifting accessories Dynamic factors involved Certification Checked
Engineering Support required Method of communication agreed Safe Access available
Number of people involved identified Adequate lighting and visibility Lifting over live plant

Route to Be Travelled and Laydown Area Yes No


1 Are the route and laydown area clear of obstructions?
2. Is the laydown / landing area adequate
3. Is the laydown /landing area adequate in term of load bearing
4. Is suitable packing avaialble for protecting the load, lifting equipment, slings etc.
5. Have barriers been positioned to prevent access by unauthorised personnel
6. Have you confirmed that the laydown area is within the operating limits / radius of the equipment.
7. Have environmental conditions been considered with regards to the safety of the lifting operation
8. Will the Lifting Equipment operator be able to see the banksman throughout the operation
9. Are there hazardous process plan or materials in the areas.

Step by Step of the Lifting Operation


Person Responsible
1. Identify the loactions for lifting of Office bunk (5 ton) in two section. Ensure area is clear from any
obstruction.
2. Alert other group about the lifting activity.
3. Position the crane for lifting within in detailed working radius
4. Deploy the competent riggers and identify the signal man.
5. Ensure proper communication established between
6. Ensure certified lifting tools & tackles for lifting operations
7. Secure the load properly, ensure correct angle achieved for the lift
8. Use tag lines to the load to prevent the sudden swing.
9. Lift the load slowly, check the load is secured properly
10.Ensure no movement in loading area, no one working under the load
11.Place the load in designated area. Signalman to guide crane operator
12.unsecure the load from pad eye.
SKETCH DETAILING THE RIGGING UP OF THE LIFTING EQUIPMENT AND LIFTING ACCESSORIES
Name of the Plant:
Weight of Load:
Crane Capacity:
(Crane type:
*Crane SWL: ………..Tons
*Working Radius: ……………Max)
*Boom Length: … Meters
(* Refer From Crane Load Chart)

Tools & tackles:


Web Slings:
No. of Web Sling: ………nos.
Sling Details: Length: …. Mts,
Width: ……. inch,
SWL: …... ton
Wire Rope Slings:
No. of Sling: ……nos.
Sling Details: Length: ….. Mts,
Width: ……. inch,
SWL : ……. ton

D- Shackles: ……… Nos.


D-Shackle SWL……………… tons.

(SWL- Safe working load)

LIFTING EQUIPMENT AND LIFTING ACCESSORIES TO BE USED (SPECIFY TYPE AND SWL)
1
2.
3.
4.
6.
7.
8.
9.
10
AUTHORISATION:
Lifting Authority: I have reviewed the details of the lifting plan and agree the work can proceed

Name: Signature:

DEBRIEF AND LEARNING (Did the lifting opertaion go as planned or are change to plan required)

You might also like