Professional Documents
Culture Documents
DT 321 Pre Lim Module
DT 321 Pre Lim Module
DT 321 Pre Lim Module
COURSE CONTENT
REQUIREMENTS IN ESTIMATING BILL MATERIALS
Course Description:
This course deals with the preparation bill of materials of a residential house. It
includes estimates of concrete, masonry, metal reinforcement, wood and lumber,
roofing materials, tile works, painting hardware, staircase and auxiliaries, scaled model
is given emphasis on the course.
The course aims task of calculating the various materials required for a
construction project involves considerable mathematical computation works. As such, it
needs concentration on the part of the estimator and the least amount of outside
distraction.
It is envisioned as a transfer course, applying calculations in pure science and
mathematics to the realm of building technology. The project drawing plan and
specification should be carefully studied and the computation works should be done
orderly and systematic manner and recorded computation sheets.
OBJECTIVES
At the end of the module, you should be able to:
Pre- Test
Direction:
A. Write TRUE if the statement is correct and FALSE if it is not.
_______1. There are three main types of bills of materials, manufacturing, engineering
and architecture BOM
________2. Pencils, eraser, papers, ballpen, etc. are required in estimating BOM.
________3. Electronic calculator or adding machine doesn’t needed in estimating BOM.
_______4. Estimating implies a judgment, considered or casual, that precedes or takes
the place of actual measuring or projecting the future.
________5. This includes the number of labourers, skilled and unskilled, and their
respective wages multiplied by the hours required to complete per unit called cost of
equipment.
2|Page
FACTS
There are different types of bills of materials specific to engineering used in the design
process; they're also specific to the manufacturing used in the assembly process.
KEY NOTES
What Is Estimating?
Estimating is simply the process used to determine the amount of effort and cost
required to implement a project, in part or in full. It is important to acknowledge that
estimating is fundamentally an effort at projecting the future. An estimate improves in
accuracy in direct relation to the level of detail considered. A methodology defines the
sequence of events by which parts are assembled. For example, a construction
methodology identifies all of the resources of a product, such as lumber, steel, glass,
etc. and how they are assembled.
1. Clear the table or working area of things not needed in connection with the work
at hand.
2. Have on hand all the things required:
3. Study carefully all the plans and specifications to get a clear understanding of the
various elements of the project and to know the materials required;
4. The plans and the specification are meant to complement each other, but should
there be discrepancies between the two, these would be referred to the designing
architect or engineer for clarification;
3|Page
5. If, in the building plans, there are discrepancies between the scaled distance and
the requirements indicated, it is usually the latter to prevail;
6. Where the measurements or positions of dimension lines indicate on small scale
drawings are not the same as their full size or large-scale drawing; those shown
full size or large-scale detail drawings should be followed.
Abstract of cost
The estimated cost of each and every individual item of work is calculated by
multiplying the quantity by the specified rate in tabular form known as "Abstract form' as
shown below, then adding all together to get the actual estimated cost of work. A
percentage (1.5 to 2.5 percent) of the above estimate is usually added for a work charge
along with an amount (usually 0.5 percent) for tools and plant, to calculate the grand
total of the estimated cost.
In order to ensure that the detailed estimates can be easily surveyed, sub-
headings are usually required. In this case, each sub-heading of the estimate is grouped
for similar items of work. For example an aquaculture project, the sub-headings should
be as follows:
Analysis of rates
In order to provide a correct and reasonable rate per unit for a particular item, a
detailed surveyed called an "Analysis of rate" should be conducted on costs of
materials, labour and equipment as required for the unit following its specification. The
rate per unit of an item consists of the following:
• Labour cost
This includes the number of labourers, skilled and unskilled, and their respective wages
multiplied by the hours required to complete per unit.
4|Page
• Cost of equipment, tools or plant
Wherever possible, the cost of equipment should be allocated to a specific item of rate,
i.e. the cost of operating a concrete mixer should be spread over those items for which it
is used. For certain tools and plant it is difficult to allocate their use to an individual item
of rate, and it is therefore suggested that this expenditure be included in overheads, i.e.
establishment charges.
• Profit
In general, a profit of 10 percent is calculated for ordinary contracts after allocating
all charges for equipment, establishment, etc. For small jobs 15 percent profit and for
large jobs 8 percent profit should be considered as common figures.
Quantity estimates
Quantity estimates of items of various works should be prepared to provide an
accurate cost estimate for the implementation of a project. Quantity estimates should be
prepared separately for both the structures and the earthworks.
(i) Quantity estimates for structures and buildings
Measurement of all structures and buildings should be taken as per the standard
specification, or as per the schedule of rate, or as per current practice.
(ii) Quantity estimates of earthworks
The quantity estimates of earthworks, using the plans of cross and longitudinal sections,
as well as contour plans if needed, should be prepared. Measurements for earthwork
shall be calculated from the relevant drawings.
SELF CHECK
A. IDENTIFICATION
Direction: Define the following building components and types of doors below
and write your answer in the provided space.
_______1. Material that is used for building or repairing a roof.
_______2. A decorative texture or appearance of a surface (or the substance that
gives it that appearance) synonyms: coating, finish.
_______3. Construction; an establishment where steel is made.
_______4. Skill of making items from wood, and includes cabinet making (cabinetry and
furniture), wood carving, joinery, carpentry, and woodturning.
_______5. Specialized ruler designed to facilitate the drafting and measuring
of architectural drawings, such as floor plans and Multi-view orthographic projections.
5|Page
_______6. Used to refer to a single view, sheet, or drawing in a set of plans
_______7. It is allocated to a specific item of rate, i.e. the cost of operating a concrete
mixer should be spread over those items for which it is used.
_______8. This includes plain and reinforced concrete works, prefabricated concrete
works, formwork for concrete structures, etc.
_______9. This includes stone work for bed or wave protection and in structures, etc.
_______10. This includes excavation, filling, dressing, dewatering, etc.
B. ENUMERATION:
ASSESSMENT
Task A: Multiple Choice: Write the letter of the correct answer.
A roof with the ends inclined, as well as the sides.
1. This includes excavation, filling, dressing, dewatering, etc.
a. filling c. earth work
b. concrete work d. stonework
2. It is allocated to a specific item of rate, i.e. the cost of operating a concrete mixer
should be spread over those items for which it is used.
a. profit c. cost of equipment
b. labor cost d. quantity of material
3. This includes stone work for bed or wave protection and in structures, etc.
a. brickwork c. concrete work
b. stonework d. earth work
4. Simply the process used to determine the amount of effort and cost required to
implement a project, in part or in full.
a. calculate c. computation
b. estimating d. costing
5. BOM stands for?
a. Basic of materials c. bill of materials
b. Bill on materials d. building materials
6. Items of various works should be prepared to provide an accurate cost estimate
for the implementation of a project.
a. quantity estimates c. bill estimates
b. quantity cost d. building cost
7. This includes plain and reinforced concrete works, prefabricated concrete
works, formwork for concrete structures, etc.
c. earth work c. stone work
d. brickwork d. concrete work
6|Page
8. Using the plans of cross and longitudinal sections, as well as contour plans if
needed, should be prepared.
a. Quantity estimates for structures and buildings c. quantity estimates
b. quantity estimates of earthworks d. building estimtes
9. Lists the finished product at the top, down to individual components and
materials.
Glossary
• Architect scale - Specialized ruler designed to facilitate the drafting and
measuring of architectural drawings
• BOM – bills of materials
• Cost - estimate the price of
• Estimating - determine the amount of effort and cost required
References
Estimate Bill of Materials
By. Vicenti A. Tagayun
https://www.modernanalyst.com/Resources/Articles/tabid/115/ID/3235/BOM-
Project-Estimating.aspx
https://www.investopedia.com/terms/b/bill-of-materials.asp
http://sketchup3dconstruction.com/const/estimation-of-any-projected-residential-
building.html
http://www.fao.org/3/x5744e/x5744e08.htm
Prepared by:
7|Page