Gasco Engineering (Pvt) Limited

Water System Construction Work-Vajihr Pipeline Project


Level-I Summary of Daily Progress Report
Report No. 96 Date: 9-Aug-21
Today's
POB 267 Cloudy Rainy Windy Hot Cold Normal
WATER SYSTEM CONSTRUCTION WORK-VAJIHR Weather:
PIPELINE Planned Actual
43.78% 42.34% Variance -1.43%
Progress Progress
Today's Progress Highlights
Hubco Pipeline Works

Civil Works at TEL HUBCO Pumping Station

1 Formwork and Concrete Pouring of Generator Pad are 100% completed.

2 Formwork for Column above Plinth Beam of Accommodation Building are in progress and 38% completed so far.

3 Concrete Pouring for Column above Plinth Beam of Accommodation Building are in progress and 25% completed so far.

4 Lean Concrete of Guard Room is in progress and 38% completed so far.

5 Layout of Underground Diesel Tank is 100% completed.

6 Excavation of Underground Diesel Tank is in progress and 25% completed so far.

7 Leveling and Compaction of Boundary Wall is in progress and 20 Meters are completed so far.

8 Steel Cutting & Bending, Steel Fixing and Formwork of Cable Trench 20 Meters are completed.

Mechanical Works at TEL HUBCO Pipeline

1 Today Dune Cutting 100 Meters and Dune Filling 100 Meters are completed from Chainage 12+800 for ROW Preparation.

TEL Hubco Pipeline ROW Preparation Works is in progress and 300 Meters are completed today. (Total 28600 Meters Hubco Pipeline ROW Preparation
2
works are done out of 35.5 KM).
TEL Hubco Pipeline Production Welding Works is in progress and 18 Joints are completed today. (Total 2064 Joints Hubco Pipeline Production Welding
3
works are done out of 3000 Joints).

GEL-PPM-F-02_DPR Page No. 1 of 26


Gasco Engineering (Pvt) Limited
Water System Construction Work-Vajihr Pipeline Project
Level-I Summary of Daily Progress Report
Report No. 96 Date: 9-Aug-21
Today's
POB 267 Cloudy Rainy Windy Hot Cold Normal
WATER SYSTEM CONSTRUCTION WORK-VAJIHR Weather:
PIPELINE Planned Actual
43.78% 42.34% Variance -1.43%
Progress Progress

TEL Hubco Pipeline Radiography Works is in progress and 02 Joints are completed today. (Total 243 Joints Hubco Pipeline Radiography works are done out
4
of 300 Joints).
TEL Hubco Pipeline HSS Application Works is in progress and 20 Joints are completed today. (Total 1721 Joints Hubco Pipeline HSS Application works are
5
done out of 3000 Joints).
Mechanical Pipeline Works at Inside Vajihar Dam

TEL Hubco Pipeline Inside Vajihar Dam Production Welding Works is in progress and 03 Joints are completed today. (Total 52 Joints Hubco Pipeline
1
Production Welding are done out of 65 Joints)

GEL-PPM-F-02_DPR Page No. 2 of 26


Progress %age

0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%

GEL-PPM-F-02_DPR
20-Apr
0.00%
0.00% 1.77%
1.97%
22-Apr
0.00% 2.13%

Report No. 96
0.00%
24-Apr
0.00% 2.24%
2.43%
0.00%
26-Apr
0.00% 2.56%
2.78%
0.00% 2.86%

April-21
28-Apr
0.00%
0.04% 2.98%
3.05%
30-Apr
0.09%
0.18% 3.23%
3.36%
2-May
0.27%
0.36% 3.42%
3.46%
4-May
0.46%
0.57% 3.50%
3.53%
6-May
0.70%
0.82% 3.54%
3.54%
8-May
0.96%
1.11% 3.54%
3.54%
10-May
1.11%
1.11% 3.54%
3.54%
12-May
1.11%
1.11% 3.54%
3.54%
14-May
1.11%
1.11% 3.54%
3.54%
PIPELINE
16-May
1.11%
1.28% 3.54%
3.54%
18-May
1.47% 3.55%

May-21
1.66%
20-May
1.86% 3.59%
3.61%
2.09%
22-May
2.32% 3.65%
3.68%
2.56%
24-May
2.80% 3.71%
3.91%
3.03%
26-May
3.28% 3.94%
4.05%
3.53%
28-May
3.77% 4.17%
4.38%
4.02%
30-May
4.23% 4.55%
4.80%
4.54%
1-Jun
4.84% 5.38%
6.77%
5.36%
3-Jun
5.85% 7.86%
8.80%
6.36%
5-Jun
6.73% 9.71%
10.33%
7.10%
7-Jun
7.43% 11.43%
12.16%
7.78%
9-Jun8.14% 12.95%
13.33%
8.66% 13.71%
WATER SYSTEM CONSTRUCTION WORK-VAJIHR

11-Jun9.17%
9.54% 14.13%
14.57%
9.93%
13-Jun10.32% 14.99%
15.36%
15-Jun10.84%
11.35% 15.79%
16.11%
17-Jun 11.86% 16.44%

June-21
12.36%
19-Jun 12.87% 16.69%
16.99%
13.46%
21-Jun 13.98% 17.24%
17.68%
14.51%
23-Jun 15.04% 18.02%
18.52%
POB

25-Jun 15.68%
16.33% 19.05%
19.64%
16.87% 20.25%
Planned
Progress

27-Jun 17.44%
17.97% 20.82%
21.52%
29-Jun 18.50%
19.05% 22.33%
23.09%
1-Jul 19.60%
20.21% 23.71%
24.35%
3-Jul 20.88%
21.57% 25.17%
25.97%
5-Jul 22.18%
22.81% 26.24%
27.01%
7-Jul 23.45%
24.05% 27.66%
28.25%
9-Jul 24.68%
25.27% 28.90%
29.60%
11-Jul 25.95%
26.66% 30.13%
30.64%
267

13-Jul 27.27%
27.90% 31.21%
31.99%
15-Jul 32.58%
43.78%

28.55%
29.25% 33.18%
17-Jul 29.94% 33.77%

July-21
30.65% 33.85%
Planned Prog. %age (Accumulative)

19-Jul 30.65%
30.65% 33.85%
33.85%
21-Jul 30.65%
30.65% 33.85%
33.85%
23-Jul 30.65%
30.65% 33.85%
33.88%
25-Jul 30.65%
31.35% 34.22%
34.84%
27-Jul 32.01%
32.86% 35.45%
35.99%
29-Jul 33.72%
34.59% 36.11%
36.68%
31-Jul 35.49%
36.39% 37.26%
37.79%

Page No. 3 of 26
2-Aug 37.34% 38.21%
Actual
Today's

38.25% 38.69%
Progress
Weather:

4-Aug 39.17%
40.08% 40.14%
40.53%
6-Aug 40.99%
41.90% 40.86%
41.47%
8-Aug 42.84%
43.78% 41.89%
42.34%
10-Aug 44.72%
45.66%
12-Aug 46.64%
47.68%
14-Aug 48.72%
49.76%
16-Aug 50.85%
51.94%
18-Aug 53.08%
Gasco Engineering (Pvt) Limited

54.25%
Cloudy

August-21
20-Aug
42.34%

55.40%
56.55%
22-Aug 57.68%
Level-I Summary of Daily Progress Report

24-Aug 58.73%
59.73%
26-Aug 60.71%
61.69%
28-Aug 62.66%
63.63%
30-Aug 64.60%
65.58%
1-Sep 66.58%
67.57%
68.48%
Rainy

3-Sep 69.40%
70.31%
Variance

5-Sep 71.23%
71.97%
7-Sep 72.67%
73.37%
Water System Construction Work-Vajihr Pipeline Project

9-Sep 74.08%
74.79%
11-Sep 75.48%
Earned Prog. %age (Accumulative)

13-Sep 76.20%
76.91%
15-Sep 77.63%
78.41%
17-Sep 79.18%
79.76%
Windy

80.32%
-1.43%

19-Sep 80.88%
81.43%
21-Sep
September-21

81.99%
Water System Construction Work-Vajihr Pipeline Project Progress S- Curve

23-Sep 82.56%
83.15%
25-Sep 83.79%
84.40%
27-Sep 85.02%
85.63%
29-Sep 86.35%
87.06%
1-Oct 87.75%
88.44%
Hot

3-Oct 89.11%
89.68%
5-Oct 90.26%
90.83%
7-Oct 91.42%
91.99%
9-Oct 92.56%
93.12%
11-Oct 93.70%
94.28%
13-Oct 94.79%
95.30%
15-Oct 95.79%
96.28%
96.74%
Cold

17-Oct 97.17%
97.54%
19-Oct 97.91%
October-21

21-Oct 98.31%
98.67%
23-Oct 98.94%
99.13%
25-Oct 99.30%
99.40%
27-Oct 99.54%
99.68%
29-Oct 99.82%
99.95%
100.00%
Date: 9-Aug-21

Normal

0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Gasco Engineering (Pvt) Limited
Water System Construction Work-Vajihr Pipeline Project
Daily Progress Report (Detailed)
Report No. 96 Mech.
Rev-01 Mech. #REF! Date: 9-Aug-2021

Today's Todate Todate Today's Today's


Budgeted Activity Planned Todate Planned Todate Earned Today's Earned
Activity ID Activity Description Unit Earned Earned Progress % Planned Progress %
Qty Weightages Quantity Progress % Progress % Progress %
Quantity Quantity Variance Progress % Variance

Water System Construction Work-Vajihr Pipeline 100.0% 43.78% 42.34% -1.43% 0.94% 0.45% -0.49%

Project Initiation Phase 0.0% 100.0% 100.0% 0.0% 0.0% 0.1% 0.1%
Award of Contract & Mobilization 0.0% 100.0% 100.0% 0.0% 0.0% 0.1% 0.1%

NTP 0.0% 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%


HUBCO1000 Notice To Proceed 1.00 Job 0.0% 1.0 1.0 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

Kick Off Meeting 0.0% 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%
HUBCO1020 Kick off Meeting 1.00 Job 0.0% 1.0 1.0 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

HUBCO1040 Local Engagement Meeting 1.00 Job 0.0% 1.0 1.0 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

Mobilization 0.0% 100.0% 100.0% 0.0% 0.0% 5.0% 5.0%


HUBCO1010 Site Setup 1.00 Job 0.0% 1.0 1.00 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

HUBCO1030 Resource & Manpower 1.00 Job 0.0% 1.0 1.00 100.0% 100.0% 0.0% 0.0% 10.0% 10.0%

Preparations 0.0% 100.0% 95.5% -4.5% 0.0% 0.0% 0.0%

Documentation Review & Approval 0.0% 100.0% 95.5% -4.5% 0.0% 0.0% 0.0%

HUBCO1050 WQT 1.00 Job 0.0% 1.0 1.00 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

HUBCO1060 Issuance & Review of IFC Drawings 1.00 Job 0.0% 1.0 0.95 100.0% 95.0% -5.0% 0.0% 0.0% 0.0%

Project Procurement Phase 9.7% 16.8% 0.0% -16.8% 0.0% 0.0% 0.0%
Material Issuance by HUBCO 0.0% 6.0% 4.8% -1.1% 0.0% 0.9% 0.9%
Flow line Material 0.0% 100.0% 63.6% -36.4% 0.0% 0.0% 0.0%
HUBCP1000 Flow Line Pipe 1.00 Job 0.0% 1.0 1.00 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

HUBCP1010 Flow Line Sleeving /Epoxy Material 1.00 Job 0.0% 1.0 0.60 100.0% 60.0% -40.0% 0.0% 0.0% 0.0%

Electrical Material 0.0% 20.0% 0.0% -20.0% 0.0% 0.0% 0.0%


HUBCP1020 Diesel Generators 1.00 Job 0.0% 1.0 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBCP1050 LV Switchgear / MCC (SWG-001) 1.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBCP1060 Cable Tray 1.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBCP1070 Synchronizing Panel 1.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBCP1180 Deep Well Turbine Pumps 1.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Field Instrumentation & Control Material 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
HUBCP1140 Automatic Circulating Valve & PSV's 1.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBCP1080 Instruments (PI, FI, LI, ANLY & MI) 1.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBCP1090 Instrument junction boxes 1.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBCP1100 Installation of plc 1.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBCP1110 Conductivity Meter 1.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBCP1120 Instrument cable 1.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

GEL-PPM-F-02_DPR Page No. 4 of 26


Gasco Engineering (Pvt) Limited
Water System Construction Work-Vajihr Pipeline Project
Daily Progress Report (Detailed)
Report No. 96 Mech.
Rev-01 Mech. #REF! Date: 9-Aug-2021

Today's Todate Todate Today's Today's


Budgeted Activity Planned Todate Planned Todate Earned Today's Earned
Activity ID Activity Description Unit Earned Earned Progress % Planned Progress %
Qty Weightages Quantity Progress % Progress % Progress %
Quantity Quantity Variance Progress % Variance

HUBCP1130 Tubing / fittings 1.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBCP1150 Instrument cable glands 1.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBCP1160 G.I. Conduit 1.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBCP1170 Automation & Control 1.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Piping Material 0.0% 0.0% 50.0% 50.0% 0.0% 15.0% 15.0%


HUBCP1030 Piping (Pipe, Fittings) 1.00 Job 0.0% 1.0 0.0% 100.0% 100.0% 0.0% 30.0% 30.0%

HUBCP1040 Valves (Ball, Check, Gate & Globe) & Strainers 1.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Material Supplied by GASCO 9.7% 16.8% 0.0% -16.8% 0.0% 0.0% 0.0%
Flow Line 0.0% 47.0% 0.0% -47.0% 0.0% 0.0% 0.0%
HUBGP1050 Cathodic Protection System For Flow Line 1.00 Job 0.0% 0.47 47.0% 0.0% -47.0% 0.0% 0.0% 0.0%

Building Electrification 1.7% 4.0% 0.0% -4.0% 0.0% 0.0% 0.0%


HUBGP1160 PVC Conduiting 1.00 Job 0.2% 0.07 7.0% 0.0% -7.0% 0.0% 0.0% 0.0%

HUBGP1170 Wiring/ wiring accessories 1.00 Job 0.2% 0.09 9.0% 0.0% -9.0% 0.0% 0.0% 0.0%

HUBGP1180 Sockets 1.00 Job 0.2% 0.10 10.0% 0.0% -10.0% 0.0% 0.0% 0.0%

HUBGP1190 Cable raceways / containment 1.00 Job 0.2% 0.06 6.0% 0.0% -6.0% 0.0% 0.0% 0.0%

HUBGP1220 Light controlled Switches 1.00 Job 0.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBGP1230 Lighting fixtures 1.00 Job 0.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBGP1240 Air conditioner units 1.00 Job 0.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBGP1250 Fans 1.00 Job 0.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

External Lighting & Power Distribution 8.0% 19.5% 0.0% -19.5% 0.0% 0.0% 0.0%
HUBGP1000 Power & control cable 1.00 Job 0.4% 0.44 44.0% 0.0% -44.0% 0.0% 0.0% 0.0%

HUBGP1010 Cable glands (for hazardous area) 1.00 Job 0.4% 0.41 41.0% 0.0% -41.0% 0.0% 0.0% 0.0%

HUBGP1020 Weather proof cable glands 1.00 Job 0.4% 0.40 40.0% 0.0% -40.0% 0.0% 0.0% 0.0%

HUBGP1030 Weatherproof local control stations 1.00 Job 0.4% 0.36 36.0% 0.0% -36.0% 0.0% 0.0% 0.0%

HUBGP1040 Conduits 1.00 Job 0.4% 0.20 20.0% 0.0% -20.0% 0.0% 0.0% 0.0%

HUBGP1060 L.V Distribution Panels / Switchboards 1.00 Job 0.4% 0.20 20.0% 0.0% -20.0% 0.0% 0.0% 0.0%

HUBGP1070 Receptacles 1.00 Job 0.4% 0.20 20.0% 0.0% -20.0% 0.0% 0.0% 0.0%

HUBGP1080 Junction Box for Lighting 1.00 Job 0.4% 0.20 20.0% 0.0% -20.0% 0.0% 0.0% 0.0%

HUBGP1090 Switch 1.00 Job 0.4% 0.20 20.0% 0.0% -20.0% 0.0% 0.0% 0.0%

HUBGP1100 Trench & Road Crossing UPVC Pipe 1.00 Job 0.4% 0.16 16.0% 0.0% -16.0% 0.0% 0.0% 0.0%

HUBGP1110 Earthing & Lighting System 1.00 Job 0.4% 0.15 15.0% 0.0% -15.0% 0.0% 0.0% 0.0%

HUBGP1120 Local control stations (for hazardous area) 1.00 Job 0.4% 0.14 14.0% 0.0% -14.0% 0.0% 0.0% 0.0%

HUBGP1130 AC UPS Along with UPS DB 1.00 Job 0.4% 0.13 13.0% 0.0% -13.0% 0.0% 0.0% 0.0%

HUBGP1140 Flood Lights 1.00 Job 0.4% 0.20 20.0% 0.0% -20.0% 0.0% 0.0% 0.0%

HUBGP1150 M.S. Channels 1.00 Job 0.4% 0.09 9.0% 0.0% -9.0% 0.0% 0.0% 0.0%

GEL-PPM-F-02_DPR Page No. 5 of 26


Gasco Engineering (Pvt) Limited
Water System Construction Work-Vajihr Pipeline Project
Daily Progress Report (Detailed)
Report No. 96 Mech.
Rev-01 Mech. #REF! Date: 9-Aug-2021

Today's Todate Todate Today's Today's


Budgeted Activity Planned Todate Planned Todate Earned Today's Earned
Activity ID Activity Description Unit Earned Earned Progress % Planned Progress %
Qty Weightages Quantity Progress % Progress % Progress %
Quantity Quantity Variance Progress % Variance

HUBGP1200 Generator shed lights 1.00 Job 0.4% 0.11 11.0% 0.0% -11.0% 0.0% 0.0% 0.0%

HUBGP1210 Maintenance Shed Lights 1.00 Job 0.4% 0.10 10.0% 0.0% -10.0% 0.0% 0.0% 0.0%

HUBGP1260 Lighting Poles 1.00 Job 0.4% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBGP1270 Emergency Lights 1.00 Job 0.4% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Project Construction Phase 90.3% 46.7% 46.9% 0.2% 1.0% 0.5% -0.5%
Pipe line 35.5 KM Dia 24" Water Supply Works 63.2% 53.1% 59.2% 6.1% 0.9% 0.4% -0.6%
Survey Works 4.0% 100.0% 83.0% -17.0% 0.0% 0.7% 0.7%
Survey and ROW Preparation 4.0% 100.0% 83.0% -17.0% 0.0% 0.7% 0.7%
HUBFLW1000 Survey 35,500.00 RM 0.5% 35,500.0 35,500.00 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

HUBFLW1010 ROW Preparation 35,500.00 RM 3.5% 35,500.0 300.00 28,600.00 100.0% 80.6% -19.4% 0.0% 0.8% 0.8%

Dia 24" x 35.5 KM Pipeline Construction 59.3% 49.9% 57.6% 7.7% 1.0% 0.4% -0.6%
Water Line Construction Works 56.1% 51.9% 60.8% 8.9% 1.1% 0.4% -0.7%
HUBFLW1020 Hauling & Stacking of pipe 35,500.00 RM 3.0% 31,699.0 35,500.00 89.3% 100.0% 10.7% 7.3% 0.0% -7.3%

HUBFLW1040 Stringing of pipe 35,500.00 RM 4.0% 24,929.0 25,584.00 70.2% 72.1% 1.8% 1.1% 0.0% -1.1%

HUBFLW1060 Fit-up 3,000.00 Joints 8.1% 1,825 18.00 2,064.00 60.8% 68.8% 8.0% 0.8% 0.6% -0.2%

HUBFLW1080 Production Welding 3,000.00 Joints 24% 1,825 18.00 2,064.00 60.8% 68.8% 8.0% 0.8% 0.6% -0.2%

HUBFLW1100 Trench Excavation for Pipe Laying 35,500.00 RM 4.5% 11,510 17,088.00 32.4% 48.1% 15.7% 0.6% 0.0% -0.6%

HUBFLW1110 Radiography 300.00 Joints 1.0% 174 2.00 243.00 58.0% 81.0% 23.0% 1.0% 0.7% -0.3%

HUBFLW1130 Pipe Bending 1.00 Job 0.5% 0.57 57.0% 0.0% -57.0% 1.0% 0.0% -1.0%

HUBFLW1190 Heat Shrink Sleeving HSS for Pipe 3,000.00 Joints 2.0% 1,515 20.00 1,721.00 50.5% 57.4% 6.9% 0.9% 0.7% -0.2%

HUBFLW1260 Holiday Testing 35,500.00 RM 0.5% 8,380.0 16,364.00 23.6% 46.1% 22.5% 0.6% 0.0% -0.6%

HUBFLW1290 Installation of Weights 1.00 Job 0.4% 0.18 18.0% 0.0% -18.0% 1.0% 0.0% -1.0%

HUBFLW1300 Lower-in of Pipeline 35,500.00 RM 3.0% 5,950.0 16,364.00 16.8% 46.1% 29.3% 0.6% 0.0% -0.6%

HUBFLW1370 Partial Backfilling of Pipeline 35,500.00 RM 0.5% 13,933.00 0.0% 39.2% 39.2% 0.0% 0.0% 0.0%

HUBFLW1430 Hydro Testing of Pipeline 1.00 Job 2.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBFLW1440 Air Pigging of Pipeline 1.00 Job 0.9% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBFLW1450 Final Backfilling & Crowning 35,500.00 RM 1.0% 4,300.00 0.0% 12.1% 12.1% 0.0% 0.0% 0.0%

HUBFLW1460 Cathodic Post Installation 7.00 Nos 0.4% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBFLW1470 Pipeline Marker Installation 55.00 Nos 0.1% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Tie Ins 2% 3.4% 2.8% -0.7% 0.0% 0.0% 0.0%


HUBFLW1380 Fab & Welding of Pipeline Tie-Ins points 218.00 Joints 0.5% 12.0 8.00 5.5% 3.7% -1.8% 0.0% 0.0% 0.0%

HUBFLW1390 Radiography of Pipeline Tie-Ins points 218.00 Joints 0.5% 12.0 8.00 5.5% 3.7% -1.8% 0.0% 0.0% 0.0%

HUBFLW1400 Heat Shrink Sleeving HSS of Pipeline Tie-Ins points 218.00 Joints 0.5% 6.0 8.00 2.8% 3.7% 0.9% 0.0% 0.0% 0.0%

HUBFLW1420 Riser Installation 2.00 Nos 0.5% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

GEL-PPM-F-02_DPR Page No. 6 of 26


Gasco Engineering (Pvt) Limited
Water System Construction Work-Vajihr Pipeline Project
Daily Progress Report (Detailed)
Report No. 96 Mech.
Rev-01 Mech. #REF! Date: 9-Aug-2021

Today's Todate Todate Today's Today's


Budgeted Activity Planned Todate Planned Todate Earned Today's Earned
Activity ID Activity Description Unit Earned Earned Progress % Planned Progress %
Qty Weightages Quantity Progress % Progress % Progress %
Quantity Quantity Variance Progress % Variance

Crossings 0.5% 7.3% 0.0% -7.3% 0.0% 0.0% 0.0%


HUBFLW1350 Crossings 3.00 Nos 0.5% 0.22 7.3% 0.0% -7.3% 0.0% 0.0% 0.0%

Pre Casting of Pipeline Marker 0.50% 73.8% 0.0% -73.8% 0.0% 0.0% 0.0%
HUBFLW1140 Reinforcement 55.00 Nos 0.10% 55.0 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBFLW1150 Formwork 55.00 Nos 0.10% 55.0 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBFLW1160 Pouring of Concrete 55.00 Nos 0.10% 55.0 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBFLW1170 Curing 55.00 Nos 0.10% 20.0 36.4% 0.0% -36.4% 0.0% 0.0% 0.0%

HUBFLW1180 Coating (Bitumen Coating) 55.00 Nos 0.10% 18.0 32.7% 0.0% -32.7% 0.0% 0.0% 0.0%

Pre Casting of Cathodic Post 0.25% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
HUBFLW1240 Reinforcement 7.00 Nos 0.05% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBFLW1280 Formwork 7.00 Nos 0.05% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBFLW1320 Pouring of Concrete 7.00 Nos 0.05% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBFLW1330 Curing 7.00 Nos 0.05% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBFLW1340 Coating (Bitumen Coating) 7.00 Nos 0.05% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Construction Work Location-1 27.1% 31.7% 18.1% -13.6% 1.3% 0.8% -0.5%
Infrastructure Work 8.8% 23.9% 5.9% -18.0% 2.4% 1.7% -0.7%
Grading Work 1.1% 100.0% 38.3% -61.7% 0.0% 9.7% 9.7%
HUBL1ISW1000 Cutting 8,670.00 Cum 0.3% 8,670.0 8,435.00 100.0% 97.3% -2.7% 0.0% 0.0% 0.0%

HUBL1ISW1010 Filling 1.4 (i) 1,000.00 Cum 0.2% 1,000.0 973.00 100.0% 97.3% -2.7% 0.0% 0.0% 0.0%

HUBL1ISW1015 Filling 1.4 (ii) 1,000.00 Cum 0.7% 1,000.0 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

Boundary Wall 2.2% 42.3% 4.1% -38.2% 2.5% 0.0% -2.5%

HUBL1ISW1020 Survey & Marking 1.00 Job 0.04% 1.0 1.0 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

HUBL1ISW1030 Leveling & Dressing 1.00 Job 0.04% 1.0 1.0 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

HUBL1ISW1040 Excavation & Lean 314.00 Cum 0.04% 314.0 80.0 100.0% 25.5% -74.5% 0.0% 0.0% 0.0%

HUBL1ISW1050 Reinforcement & formwork 3.00 Ton 0.15% 3.0 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBL1ISW1060 Concrete Pouring of Fence Post 26.00 Cum 0.12% 26.0 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBL1ISW1070 Block Masonry 154.00 Cum 0.78% 100.0 64.9% 0.0% -64.9% 6.5% 0.0% -6.5%

HUBL1ISW1080 Plaster Works 407.00 SQM 0.07% 260.0 63.9% 0.0% -63.9% 7.4% 0.0% -7.4%

HUBL1ISW1090 Chain link Fence 350.00 RM 0.84% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1ISW1100 Barbed Wire Fencing 1,100.00 RM 0.16% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Storm Water Drain System 2.1% 2.0% 0.0% -2.0% 0.1% 0.0% -0.1%

HUBL1ISW1110 Layout & Marking 1.00 Job 0.02% 0.50 50.0% 0.0% -50.0% 0.0% 0.0% 0.0%

HUBL1ISW1120 Excavation 272.00 cum 0.04% 70.0 25.7% 0.0% -25.7% 0.0% 0.0% 0.0%

HUBL1ISW1130 CS&RCC Pipe Installation 25.00 RM 0.03% 6.0 24.0% 0.0% -24.0% 0.0% 0.0% 0.0%

GEL-PPM-F-02_DPR Page No. 7 of 26


Gasco Engineering (Pvt) Limited
Water System Construction Work-Vajihr Pipeline Project
Daily Progress Report (Detailed)
Report No. 96 Mech.
Rev-01 Mech. #REF! Date: 9-Aug-2021

Today's Todate Todate Today's Today's


Budgeted Activity Planned Todate Planned Todate Earned Today's Earned
Activity ID Activity Description Unit Earned Earned Progress % Planned Progress %
Qty Weightages Quantity Progress % Progress % Progress %
Quantity Quantity Variance Progress % Variance

HUBL1ISW1140 Lean Concrete 31.00 Cum 0.12% 4.0 12.9% 0.0% -12.9% 0.0% 0.0% 0.0%

HUBL1ISW1150 Steel Reinforcement 8.00 Ton 0.39% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1ISW1160 Concrete Pouring 114.00 Cum 0.46% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1ISW1165 Plaster Works 617.00 SQM 0.16% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1ISW1180 Grating 10.00 Ton 0.72% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1ISW1190 Structural Works 1.00 Ton 0.08% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1ISW1210 Manhole Covers 7.00 Nos 0.08% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Paving Work 1.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1ISW1170 Layout & Marking 1.00 Job 0.28% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1ISW1200 Excavation 56.00 Cum 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1ISW1220 Subgrade Preparation 695.00 Cum 0.09% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1ISW1230 Base course 99.00 Cum 0.10% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1ISW1240 Sand Bedding 37.50 Cum 0.04% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1ISW1250 Installation of Pavers 660.00 SQM 0.47% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Road Works 2.4% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1ISW1260 Layout & Marking 1.00 Job 0.21% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1ISW1265 Excavation 244.00 Cum 0.04% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1ISW1270 Leveling & Grading 244.00 Cum 0.04% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1ISW1280 Crush Aggregate Sub Base Course 152.00 Cum 0.14% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1ISW1290 Compaction 1.00 Job 0.21% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1ISW1300 Crush Aggregate Base Course 152.00 Cum 0.14% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1ISW1310 Asphalt Binder Course 759.00 SQM 0.51% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1ISW1320 Asphalt Wearing Course 759.00 SQM 0.60% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1ISW1330 Final Compaction 1.00 Job 0.21% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1ISW1340 Kerb Stone Placement 550.00 RM 0.28% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Building & Shade Works 10.4% 40.2% 27.6% -12.6% 1.0% 0.3% -0.6%
Gen Set Building 5.4% 68.4% 31.8% -36.6% 1.1% 0.2% -0.9%

Sub Structure 0.7% 100.0% 76.5% -23.5% 0.0% 0.0% 0.0%

HUBL1BSW1000 Layout 1.00 Job 0.02% 1.0 1.0 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1010 Excavation & Lean 283.00 Cum 0.02% 283.0 283 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1020 Reinforcement & formwork for Base & Column 3.00 Ton 0.11% 3.0 3.0 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1030 Stone Soiling 63.00 Cum 0.10% 63.0 25.2 100.0% 40.0% -60.0% 0.0% 0.0% 0.0%

HUBL1BSW1040 Earth Filling 74.00 Cum 0.10% 74.0 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBL1BSW1050 Pouring of Concrete for Base & Column 100.00 Cum 0.13% 100.0 100.0 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

GEL-PPM-F-02_DPR Page No. 8 of 26


Gasco Engineering (Pvt) Limited
Water System Construction Work-Vajihr Pipeline Project
Daily Progress Report (Detailed)
Report No. 96 Mech.
Rev-01 Mech. #REF! Date: 9-Aug-2021

Today's Todate Todate Today's Today's


Budgeted Activity Planned Todate Planned Todate Earned Today's Earned
Activity ID Activity Description Unit Earned Earned Progress % Planned Progress %
Qty Weightages Quantity Progress % Progress % Progress %
Quantity Quantity Variance Progress % Variance

HUBL1BSW1060 Reinforcement & formwork for Plinth beam 2.00 Ton 0.11% 2.0 2.00 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1070 Pouring of Concrete for Plinth Beam 35.00 Cum 0.12% 35.0 35.0 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

Super Structure for GF 1.6% 100.0% 73.3% -26.7% 0.0% 0.0% 0.0%

HUBL1BSW1080 Reinforcement & formwork for Column above plinth beam 2.00 Ton 0.13% 2.0 2.00 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1090 Pouring of Concrete for Column above plinth beam 8.00 Cum 0.31% 8.0 8.00 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1100 Reinforcement & formwork for lintel beam 2.00 Ton 0.11% 2.00 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBL1BSW1110 Pouring of Concrete for lintel beam 8.00 Cum 0.32% 8.00 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBL1BSW1120 Scaffolding for Mid Slab 1.00 Job 0.11% 1.00 1.0 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1140 Reinforcement & formwork for Mid Slab 3.00 Ton 0.11% 3.0 3.0 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1160 Pouring of Concrete for Mid Slab 12.00 Cum 0.51% 12.0 12.0 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

Super Structure for FF 0.8% 100.0% 2.8% -97.2% 7.6% 1.4% -6.2%

HUBL1BSW1190 Reinforcement & formwork for Column 2.00 Ton 0.11% 2.00 0.4 100.0% 20.0% -80.0% 0.0% 10.0% 10.0%

HUBL1BSW1250 Pouring of Concrete for Column 8.00 Cum 0.12% 8.0 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBL1BSW1270 Reinforcement & formwork for lintel beam 1.00 Ton 0.11% 1.0 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBL1BSW1320 Pouring of Concrete for lintel beam 8.00 Cum 0.12% 8.0 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBL1BSW1340 Scaffolding for Roof 1.00 Job 0.10% 1.0 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBL1BSW1370 Reinforcement & formwork for Roof 3.00 Ton 0.11% 3.0 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBL1BSW1410 Pouring of Concrete for Roof 13.00 Cum 0.11% 13.0 100.0% 0.0% -100.0% 53.8% 0.0% -53.8%

Block Masonary & Plaster Works 0.5% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1430 Block Masonry Work 10.00 Cum 0.12% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1480 Block Masonry above lintel 16.00 Cum 0.11% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1560 Plaster works 669.00 SQM 0.11% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1650 Painting works 670.00 SQM 0.11% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Misc Works 0.6% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1620 Installation of Doors 6.00 Nos 0.10% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1640 Tiles Works 79.00 SQM 0.12% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1700 Installation Windows 12.00 Nos 0.11% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1740 Installation of Ventilators 6.00 Nos 0.10% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1760 Roof Screeding 121.00 SQM 0.10% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1800 House keeping 1.00 Job 0.10% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Shade Erection Work 1.3% 51.4% 0.0% -51.4% 0.0% 0.0% 0.0%

Pre Fabrication 0.5% 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBL1BSW1130 Fabrication 1.00 Job 0.14% 1.00 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBL1BSW1150 Welding 1.00 Job 0.14% 1.00 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

GEL-PPM-F-02_DPR Page No. 9 of 26


Gasco Engineering (Pvt) Limited
Water System Construction Work-Vajihr Pipeline Project
Daily Progress Report (Detailed)
Report No. 96 Mech.
Rev-01 Mech. #REF! Date: 9-Aug-2021

Today's Todate Todate Today's Today's


Budgeted Activity Planned Todate Planned Todate Earned Today's Earned
Activity ID Activity Description Unit Earned Earned Progress % Planned Progress %
Qty Weightages Quantity Progress % Progress % Progress %
Quantity Quantity Variance Progress % Variance

HUBL1BSW1170 Sandblasting & Initial Painting 1.00 Job 0.14% 1.00 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBL1BSW1200 Final Painting 1.00 Job 0.14% 1.00 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

Erection 0.7% 14.3% 0.0% -14.3% 0.0% 0.0% 0.0%

HUBL1BSW1280 Installation of Column 6.00 Nos 0.10% 6.0 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBL1BSW1300 Installation of Rafter 7.00 Nos 0.10% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1330 Installation of Trusses 62.00 Nos 0.10% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1360 Purlin & Girds 24.00 Nos 0.10% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1390 Installation of Roof Sheets 75.00 SQM 0.10% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1420 Installation of Wall Sheets 181.00 SQM 0.10% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1550 Grouting 6.00 Nos 0.10% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Control Room 0.8% 49.4% 15.5% -34.0% 3.8% 0.0% -3.8%

Sub Structure 0.2% 100.0% 50.7% -49.3% 0.0% 0.0% 0.0%

HUBL1BSW1180 Layout 1.00 Job 0.03% 1.0 1.0 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1210 Excavation & Lean 37.00 Cum 0.03% 37.0 37.0 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1220 Reinforcement & formwork for Base & Column 0.60 Ton 0.03% 0.60 0.60 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1230 Stone Soiling 6.00 Cum 0.03% 6.00 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBL1BSW1240 Earth Filling 12.00 Cum 0.03% 12.00 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBL1BSW1260 Pouring of Concrete for Base & Column 8.00 Cum 0.03% 8.0 8.0 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1290 Reinforcement & formwork for Plinth beam 0.60 Ton 0.03% 0.6 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBL1BSW1310 Pouring of Concrete for Plinth Beam 5.00 Cum 0.03% 5.0 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

Super Structure 0.2% 71.4% 0.0% -71.4% 14.2% 0.0% -14.2%

HUBL1BSW1350 Reinforcement & formwork for Column above plinth beam 0.60 Ton 0.03% 0.6 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBL1BSW1380 Pouring of Concrete for Column above plinth beam 6.00 Cum 0.03% 6.0 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBL1BSW1400 Reinforcement & formwork for lintel beam 0.60 Ton 0.03% 0.6 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBL1BSW1460 Pouring of Concrete for lintel beam 4.00 Cum 0.03% 4.0 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBL1BSW1510 Scaffolding for Roof 1.00 Job 0.03% 1.0 100.0% 0.0% -100.0% 100.0% 0.0% -100.0%

HUBL1BSW1530 Reinforcement & formwork for Roof 0.60 Ton 0.03% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1580 Pouring of Concrete for Roof 4.00 Cum 0.03% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Block Masonary & Plaster Works 0.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1600 Block Masonary Work 5.00 Cum 0.03% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1660 Block Masonary above lintel 4.00 Cum 0.03% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1690 Plaster works 272.00 SQM 0.05% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1730 Painting works 273.00 SQM 0.05% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

GEL-PPM-F-02_DPR Page No. 10 of 26


Gasco Engineering (Pvt) Limited
Water System Construction Work-Vajihr Pipeline Project
Daily Progress Report (Detailed)
Report No. 96 Mech.
Rev-01 Mech. #REF! Date: 9-Aug-2021

Today's Todate Todate Today's Today's


Budgeted Activity Planned Todate Planned Todate Earned Today's Earned
Activity ID Activity Description Unit Earned Earned Progress % Planned Progress %
Qty Weightages Quantity Progress % Progress % Progress %
Quantity Quantity Variance Progress % Variance

Misc Works 0.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1610 Tiles Works 37.00 SQM 0.03% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1710 Roof Screeding 59.00 SQM 0.03% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1720 Installation of Doors 3.00 Nos 0.03% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1770 Installation Windows 13.00 Nos 0.03% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1790 Installation of Ventilators 4.00 Nos 0.03% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1830 House keeping 1.00 Job 0.03% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Accommodation Building 2.3% 2.4% 25.2% 22.8% 0.6% 1.0% 0.4%

Sub Structure 0.7% 8.2% 75.2% 67.1% 2.1% 0.0% -2.1%

HUBL1BSW1440 Layout 1.00 Job 0.08% 0.5 1.0 50.0% 100.0% 50.0% 10.0% 0.0% -10.0%

HUBL1BSW1450 Excavation & Lean 79.00 Cum 0.09% 12.0 79.0 15.2% 100.0% 84.8% 6.8% 0.0% -6.8%

HUBL1BSW1470 Reinforcement & formwork for Base & Column 2.00 Ton 0.08% 2.00 0.0% 100.0% 100.0% 0.0% 0.0% 0.0%

HUBL1BSW1490 Stone Soiling 18.00 Cum 0.08% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1500 Earth Filling 36.00 Cum 0.08% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1590 Pouring of Concrete for Base & Column 16.00 Cum 0.09% 16.0 0.0% 100.0% 100.0% 0.0% 0.0% 0.0%

HUBL1BSW1670 Reinforcement & formwork for Plinth beam 2.00 Ton 0.08% 2.0 0.0% 100.0% 100.0% 0.0% 0.0% 0.0%

HUBL1BSW1780 Pouring of Concrete for Plinth Beam 10.00 Cum 0.09% 10.0 0.0% 100.0% 100.0% 0.0% 0.0% 0.0%

Super Structure 0.6% 0.0% 11.9% 11.9% 0.0% 4.1% 4.1%

HUBL1BSW1820 Reinforcement & formwork for Column above plinth beam 1.00 Ton 0.08% 0.03 0.58 0.0% 58.0% 58.0% 0.0% 3.0% 3.0%

HUBL1BSW1850 Pouring of Concrete for Column above plinth beam 9.00 Cum 0.09% 2.3 2.3 0.0% 25.6% 25.6% 0.0% 25.6% 25.6%

HUBL1BSW1870 Reinforcement & formwork for lintel beam 1.00 Ton 0.08% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1890 Pouring of Concrete for lintel beam 10.00 Cum 0.08% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1920 Scaffolding for Roof 1.00 Job 0.08% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1950 Reinforcement & formwork for Roof 2.00 Ton 0.08% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2080 Pouring of Concrete for Roof 20.00 Cum 0.09% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Block Masonary & Plaster Works 0.4% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2110 Block Masonry Work 12.00 Cum 0.09% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2170 Block Masonry above lintel 19.00 Cum 0.09% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2210 Plaster works 786.00 SQM 0.13% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2290 Painting works 783.00 SQM 0.12% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Misc Works 0.6% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2120 Plumbing Works 1.00 Job 0.08% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2190 Tiles & sanitary fittings Works 249.00 SQM 0.10% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2200 Installation of Doors 21.00 Nos 0.09% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

GEL-PPM-F-02_DPR Page No. 11 of 26


Gasco Engineering (Pvt) Limited
Water System Construction Work-Vajihr Pipeline Project
Daily Progress Report (Detailed)
Report No. 96 Mech.
Rev-01 Mech. #REF! Date: 9-Aug-2021

Today's Todate Todate Today's Today's


Budgeted Activity Planned Todate Planned Todate Earned Today's Earned
Activity ID Activity Description Unit Earned Earned Progress % Planned Progress %
Qty Weightages Quantity Progress % Progress % Progress %
Quantity Quantity Variance Progress % Variance

HUBL1BSW2250 Roof Screeding 150.00 SQM 0.09% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2260 Installation Windows 15.00 Nos 0.09% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2320 Installation of Ventilators 4.00 Nos 0.08% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2350 House keeping 1.00 Job 0.08% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Guard Room 0.6% 7.5% 7.3% -0.2% 0.0% 0.1% 0.1%

Sub Structure 0.1% 34.0% 33.1% -0.9% 0.0% 0.5% 0.5%

HUBL1BSW1520 Layout 1.00 Job 0.02% 1.0 1.0 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1540 Excavation & Lean 25.00 Cum 0.02% 25.0 0.75 23.8 100.0% 95.0% -5.0% 0.0% 3.0% 3.0%

HUBL1BSW1570 Reinforcement & formwork for Column 0.50 Ton 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1630 Pouring of Concrete for Column 3.00 Cum 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1680 Reinforcement & formwork for Plinth beam 1.00 Ton 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1750 Pouring of Concrete for Plinth Beam 5.00 Cum 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Super Structure 0.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1810 Reinforcement & formwork for Column above plinth beam 0.50 Ton 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1840 Pouring of Concrete for Column above plinth beam 2.00 Cum 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1860 Reinforcement & formwork for lintel beam 0.50 Ton 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1880 Pouring of Concrete for lintel beam 3.00 Cum 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1900 Scaffolding for Roof 1.00 Job 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1910 Reinforcement & formwork for Roof 1.00 Ton 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1940 Pouring of Concrete for Roof 6.00 Cum 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Block Masonary & Plaster Works 0.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1970 Block Masonry Work 3.00 Cum 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW1990 Block Masonry above lintel 6.00 Cum 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2010 Stone Soiling 5.00 Cum 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2020 Earth Filling 9.00 Cum 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2030 Plaster works 247.00 SQM 0.04% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2040 Painting works 248.00 SQM 0.04% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Misc Works 0.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2000 Plumbing Works 1.00 Job 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2050 Installation of Doors 3.00 Nos 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2060 Tiles & Sanitary Fittings Works 46.00 SQM 0.03% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2070 Roof Screeding 45.00 SQM 0.03% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2100 Installation Windows 6.00 Nos 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2140 Installation of Ventilators 4.00 Nos 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

GEL-PPM-F-02_DPR Page No. 12 of 26


Gasco Engineering (Pvt) Limited
Water System Construction Work-Vajihr Pipeline Project
Daily Progress Report (Detailed)
Report No. 96 Mech.
Rev-01 Mech. #REF! Date: 9-Aug-2021

Today's Todate Todate Today's Today's


Budgeted Activity Planned Todate Planned Todate Earned Today's Earned
Activity ID Activity Description Unit Earned Earned Progress % Planned Progress %
Qty Weightages Quantity Progress % Progress % Progress %
Quantity Quantity Variance Progress % Variance

HUBL1BSW2160 House keeping 1.00 Job 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Maintenance Shade 1.3% 0.0% 31.8% 31.8% 0.0% 0.0% 0.0%

Sub Structure 0.4% 0.0% 100.0% 100.0% 0.0% 0.0% 0.0%

HUBL1BSW1930 Layout 1.00 Job 0.06% 1.0 0.0% 100.0% 100.0% 0.0% 0.0% 0.0%

HUBL1BSW1960 Excavation & Lean 53.00 Cum 0.06% 53.0 0.0% 100.0% 100.0% 0.0% 0.0% 0.0%

HUBL1BSW1980 Reinforcement & formwork for Base & Column 1.50 Ton 0.06% 1.5 0.0% 100.0% 100.0% 0.0% 0.0% 0.0%

HUBL1BSW2090 Pouring of Concrete for Base & Column 5.00 Cum 0.06% 5.0 0.0% 100.0% 100.0% 0.0% 0.0% 0.0%

HUBL1BSW2130 Reinforcement & formwork for Plinth beam 2.50 Ton 0.06% 2.5 0.0% 100.0% 100.0% 0.0% 0.0% 0.0%

HUBL1BSW2150 Pouring of Concrete for Plinth Beam 9.50 Cum 0.06% 9.5 0.0% 100.0% 100.0% 0.0% 0.0% 0.0%

HUBL1BSW2240 Flooring Works 4.50 SQM 0.06% 4.5 0.0% 100.0% 100.0% 0.0% 0.0% 0.0%

Block Masonary & Plaster Works 0.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2270 Block Masonary Work 8.00 Cum 0.06% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2300 Installation of Corrugated Sheets 140.00 Cum 0.07% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2390 Plaster works 24.00 SQM 0.06% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2410 Painting works 24.00 SQM 0.06% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Shade Erection Work 0.6% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Pre Fabrication 0.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2280 Fabrication 1.00 Job 0.06% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2310 Welding 1.00 Job 0.06% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2330 Sandblasting & Initial Painting 1.00 Job 0.06% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2370 Final Painting 1.00 Job 0.06% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Erection 0.4% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2340 Installation of Column 6.00 Nos 0.06% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2360 Installation of Rafter 7.00 Nos 0.06% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2380 Installation of Trusses 62.00 Nos 0.06% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2400 Perlin & Girds 24.00 Nos 0.06% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2420 Installation of Roof Sheets 75.00 SQM 0.06% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2430 Installation of Wall Sheets 181.00 SQM 0.06% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1BSW2440 Grouting 6.00 Nos 0.06% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Civil Structure Work 5.2% 41.6% 28.9% -12.8% 0.6% 0.4% -0.2%
Intake Structure Pit 2.6% 71.6% 48.9% -22.7% 1.1% 0.0% -1.1%

HUBL1CSW1000 Layout 1.00 Job 0.1% 1.0 1.0 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1010 Excavation & Lean 370.00 Cum 0.1% 370.0 370.0 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1020 Installation of PVC Water Stopper 122.00 RM 0.1% 122.0 82.0 100.0% 67.2% -32.8% 0.0% 0.0% 0.0%

HUBL1CSW1030 Reinforcement & formwork 3.00 Ton 0.1% 3.0 3.00 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

GEL-PPM-F-02_DPR Page No. 13 of 26


Gasco Engineering (Pvt) Limited
Water System Construction Work-Vajihr Pipeline Project
Daily Progress Report (Detailed)
Report No. 96 Mech.
Rev-01 Mech. #REF! Date: 9-Aug-2021

Today's Todate Todate Today's Today's


Budgeted Activity Planned Todate Planned Todate Earned Today's Earned
Activity ID Activity Description Unit Earned Earned Progress % Planned Progress %
Qty Weightages Quantity Progress % Progress % Progress %
Quantity Quantity Variance Progress % Variance

HUBL1CSW1040 Pouring of Concrete for Base 23.00 Cum 0.3% 23.0 23.0 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1050 Reinforcement & formwork for Pits Wall Sec.1 2.00 Ton 0.1% 2.0 2.0 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1060 Pouring of Concrete Sec.1 35.00 Cum 0.1% 35.0 35.0 100.0% 100.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1070 Application of Joint Sealent 1.00 Job 0.1% 1.0 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBL1CSW1090 Reinforcement & formwork for Pits Wall Sec.2 3.00 Ton 0.1% 3.0 2.5 100.0% 83.3% -16.7% 0.0% 0.0% 0.0%

HUBL1CSW1110 Pouring of Concrete Sec.2 35.00 Cum 0.2% 35.0 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBL1CSW1130 Reinforcement & formwork for Pits Wall Sec.3 2.00 Ton 0.1% 2.0 0.4 100.0% 20.0% -80.0% 0.0% 0.0% 0.0%

HUBL1CSW1150 Pouring of Concrete Sec.3 35.00 Cum 0.2% 35.0 100.0% 0.0% -100.0% 14.3% 0.0% -14.3%

HUBL1CSW1160 Reinforcement & formwork for Roof 2.00 Ton 0.1% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1180 Pouring of Concrete for Roof 35.00 Cum 0.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1200 Coating & Backfilling 370.00 Cum 0.1% 267 0.0% 72.0% 72.0% 0.0% 0.0% 0.0%

HUBL1CSW1210 Plaster Works 314.00 SQM 0.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1290 Installation of Filter Screen 1.00 Job 0.1% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Intake Structure Works 0.6% 4.0% 0.0% -4.0% 0.0% 0.0% 0.0%

HUBL1PFW1130 Fitup/Fabrication 1.00 Job 0.13% 0.10 10.0% 0.0% -10.0% 0.0% 0.0% 0.0%

HUBL1PFW1160 Welding 1.00 Job 0.13% 0.10 10.0% 0.0% -10.0% 0.0% 0.0% 0.0%

HUBL1PFW1180 Sand Blasting & Initial Paintiing 1.00 Job 0.13% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1PFW1210 Erection 1.00 Job 0.13% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1PFW1240 Final Painting 1.00 Job 0.13% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Under ground diesel storage tank 0.6% 44.8% 3.3% -41.4% 0.0% 3.3% 3.3%

HUBL1CSW1080 Layout 1.00 Job 0.01% 1.0 1 1.0 100.0% 100.0% 0.0% 0.0% 100.0% 100.0%

HUBL1CSW1100 Excavation & Lean 155.00 Cum 0.03% 155.0 37 37.0 100.0% 23.9% -76.1% 0.0% 23.9% 23.9%

HUBL1CSW1120 Reinforcement & formwork 1.00 Ton 0.08% 1.00 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBL1CSW1140 Pouring of Concrete for Base 14.00 Cum 0.10% 14.0 100.0% 0.0% -100.0% 0.0% 0.0% 0.0%

HUBL1CSW1170 Reinforcement & formwork for Tanks Wall 1.00 Ton 0.05% 0.5 50.0% 0.0% -50.0% 0.0% 0.0% 0.0%

HUBL1CSW1190 Pouring of Concrete for Tanks Wall 15.00 Cum 0.11% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1230 Reinforcement & formwork for Roof 1.00 Ton 0.03% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1260 Pouring of Concrete for Roof 15.00 Cum 0.11% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1270 Plaster Works 98.00 SQM 0.03% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1360 Coating & Backfilling 155.00 Cum 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Construction of Valve Pit 1.0% 0.0% 19.2% 19.2% 0.0% 0.0% 0.0%

HUBL1CSW1330 Layout 3.00 Nos 0.10% 1.0 0.0% 33.3% 33.3% 0.0% 0.0% 0.0%

HUBL1CSW1340 Excavation & Lean 223.70 Cum 0.12% 119.0 0.0% 53.2% 53.2% 0.0% 0.0% 0.0%

HUBL1CSW1370 Installation of PVC Water Stopper 44.00 RM 0.10% 14.5 0.0% 33.0% 33.0% 0.0% 0.0% 0.0%

HUBL1CSW1390 Reinforcement & formwork 3.65 Ton 0.10% 1.21 0.0% 33.0% 33.0% 0.0% 0.0% 0.0%

GEL-PPM-F-02_DPR Page No. 14 of 26


Gasco Engineering (Pvt) Limited
Water System Construction Work-Vajihr Pipeline Project
Daily Progress Report (Detailed)
Report No. 96 Mech.
Rev-01 Mech. #REF! Date: 9-Aug-2021

Today's Todate Todate Today's Today's


Budgeted Activity Planned Todate Planned Todate Earned Today's Earned
Activity ID Activity Description Unit Earned Earned Progress % Planned Progress %
Qty Weightages Quantity Progress % Progress % Progress %
Quantity Quantity Variance Progress % Variance

HUBL1CSW1420 Pouring of Concrete for Base 24.57 Cum 0.10% 8.1 0.0% 33.0% 33.0% 0.0% 0.0% 0.0%

HUBL1CSW1430 Reinforcement & formwork for Pits Wall 4.00 Ton 0.10% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1440 Pouring of Concrete 50.00 Cum 0.10% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1450 Installation of Sleeve including Sealant' 8.00 Nos 0.10% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1460 Installation of Chequred Plate 38.18 SQM 0.10% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1480 Coating & Backfilling 223.70 Job 0.10% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Septic Tank 0.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1470 Layout 3.00 Nos 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1490 Excavation & Lean 23.00 Cum 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1530 Reinforcement & formwork 0.50 Ton 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1560 Pouring of Concrete for Base 2.00 Cum 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1580 Reinforcement & formwork for Tanks Wall 0.50 Ton 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1600 Pouring of Concrete for Tanks Wall 2.50 Cum 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1630 Reinforcement & formwork for Roof 0.50 Ton 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1640 Plaster Works 23.00 SQM 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1660 Pouring of Concrete for Roof 2.50 Cum 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1680 Coating & Backfilling 23.00 Cum 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Soak pit 0.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1500 Layout 1.00 Nos 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1510 Excavation & Lean 54.00 Cum 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1520 Placement of Boulders 21.00 Cum 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1540 Reinforcement & formwork 0.50 Ton 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1550 Pouring of Concrete for Base 3.50 Cum 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1570 Reinforcement & formwork for Wall 0.50 Ton 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1590 Pouring of Concrete for Wall 3.50 Cum 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1610 Reinforcement & formwork for Roof 0.50 Ton 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1620 Plaster Works 1.00 Job 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1650 Pouring of Concrete for Roof 3.50 Cum 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1670 Coating & Backfilling 54.00 Cum 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

GEL-PPM-F-02_DPR Page No. 15 of 26


Gasco Engineering (Pvt) Limited
Water System Construction Work-Vajihr Pipeline Project
Daily Progress Report (Detailed)
Report No. 96 Mech.
Rev-01 Mech. #REF! Date: 9-Aug-2021

Today's Todate Todate Today's Today's


Budgeted Activity Planned Todate Planned Todate Earned Today's Earned
Activity ID Activity Description Unit Earned Earned Progress % Planned Progress %
Qty Weightages Quantity Progress % Progress % Progress %
Quantity Quantity Variance Progress % Variance

Pumping Facility 0.9% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%


Sleeper and Supports 0.1% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1PFW1000 Survey & Marking 1.00 Job 0.03% 0.05 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1PFW1010 Leveling & Dressing 1.00 Job 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1PFW1020 Excavation 53.00 Cum 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1PFW1030 Reinforcement & formwork 2.00 Ton 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1PFW1040 Installation of Embedded Plate & Bolts 225.00 Nos 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1PFW1050 Concrete Pouring 19.00 Cum 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1PFW1070 Backfilling 53.00 Cum 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Mechanical Works 0.8% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1PFW1060 Material Inspection & Segregation 1.00 Job 0.07% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1PFW1080 Fit-up /Fabrication 1,071.00 Dia Inches 0.07% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1PFW1090 Production Welding & Tie In Joints 1,071.00 Dia Inches 0.07% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1PFW1100 Radiography 145.00 Joints 0.07% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1PFW1110 Sand Blasting & Initial Paintiing 190.00 SQM 0.07% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1PFW1190 Erection of Spools 1.00 Job 0.07% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1PFW1200 Installation of Valves 1.00 Job 0.07% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1PFW1230 Installation of Deep Well Turbine Pumps 10.00 Ton 0.07% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1PFW1250 Installation of Crane 1.00 Job 0.07% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1PFW1260 Hydro Testing 1.00 Job 0.07% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1PFW1270 Final Painting 190.00 SQM 0.07% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Piping Supports 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1PFW1120 Fabrication 1.00 Ton 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1PFW1140 Welding 1.00 Ton 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1PFW1150 Sand Blasting & Initial Painting 1.00 Ton 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1PFW1170 Installation of Pipe Supports 1.00 Ton 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1PFW1220 Final Painting 1.00 Ton 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Shade Erection Work 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Pre Fabrication 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1220 Fabrication 1.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1240 Welding 1.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1250 Sandblasting & Initial Painting 1.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1280 Final Painting 1.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

GEL-PPM-F-02_DPR Page No. 16 of 26


Gasco Engineering (Pvt) Limited
Water System Construction Work-Vajihr Pipeline Project
Daily Progress Report (Detailed)
Report No. 96 Mech.
Rev-01 Mech. #REF! Date: 9-Aug-2021

Today's Todate Todate Today's Today's


Budgeted Activity Planned Todate Planned Todate Earned Today's Earned
Activity ID Activity Description Unit Earned Earned Progress % Planned Progress %
Qty Weightages Quantity Progress % Progress % Progress %
Quantity Quantity Variance Progress % Variance

Erection 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1300 Installation of Column 6.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1310 Installation of Rafter 7.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1320 Installation of Trusses 62.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1350 Perlin & Girds 24.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1380 Installation of Roof Sheets 75.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1400 Installation of Wall Sheets 181.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1CSW1410 Grouting 6.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Electrical Instrumentation and Control Work 1.8% 8.0% 0.1% -7.9% 0.0% 0.0% 0.0%
Building Electrification 0.2% 0.0% 0.9% 0.9% 0.0% 0.0% 0.0%

Generator Room 0.1% 0.0% 3.2% 3.2% 0.0% 0.0% 0.0%

HUBL1EIC1010 PVC Conduiting 210.00 RM 0.01% 54.0 0.0% 25.7% 25.7% 0.0% 0.0% 0.0%

HUBL1EIC1020 Wiring / wiring accessories 46.00 Nos 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1030 Sockets 11.00 Nos 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1040 Cable raceways / containment 210.00 RM 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1120 Light controlled Switches 6.00 Nos 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1190 Lighting fixtures 24.00 Nos 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1200 Air conditioner units 3.00 Nos 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1220 Fans 1.00 Nos 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Control Room 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1060 PVC Conduiting 250.00 RM 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1070 Wiring / wiring accessories 29.00 Nos 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1090 Sockets 9.00 Nos. 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1100 Cable raceways / containment 250.00 RM 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1230 Light controlled switches 2.00 Nos. 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1240 Lighting fixtures 12.00 Nos. 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1250 Air conditioner units 3.00 Nos. 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1260 Fans 2.00 Nos 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Guard Room 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1270 PVC Conduiting 130.00 RM 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1280 Wiring / wiring accessories 17.00 Nos 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1290 Sockets 7.00 Nos. 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1300 Cable raceways / containment 130.00 RM 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1380 Light controlled switches 2.00 Nos. 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

GEL-PPM-F-02_DPR Page No. 17 of 26


Gasco Engineering (Pvt) Limited
Water System Construction Work-Vajihr Pipeline Project
Daily Progress Report (Detailed)
Report No. 96 Mech.
Rev-01 Mech. #REF! Date: 9-Aug-2021

Today's Todate Todate Today's Today's


Budgeted Activity Planned Todate Planned Todate Earned Today's Earned
Activity ID Activity Description Unit Earned Earned Progress % Planned Progress %
Qty Weightages Quantity Progress % Progress % Progress %
Quantity Quantity Variance Progress % Variance

HUBL1EIC1450 Lighting fixtures 8.00 Nos. 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1460 Air conditioner units 2.00 Nos. 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1490 Fans 2.00 Nos. 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Accomodation Building 0.1% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1410 PVC Conduiting 271.00 RM 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1440 Wiring / wiring accessories 95.00 Nos 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1470 Sockets 24.00 Nos. 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1480 Cable raceways / containment 271.00 RM 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1560 Light controlled switches 11.00 Nos. 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1600 Fans 5.00 Nos. 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1620 Lighting fixtures 35.00 Nos. 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1630 Air conditioner units 4.00 Nos. 0.01% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Electrical Works 1.4% 10.1% 0.0% -10.1% 0.0% 0.0% 0.0%

Installation of Electrical Equipment 0.6% 25.3% 0.0% -25.3% 0.0% 0.0% 0.0%

HUBL1EIC1000 Diesel Generators 1.00 Nos 0.19% 0.8 76.0% 0.0% -76.0% 0.0% 0.0% 0.0%

HUBL1EIC1080 Synchronizing Panel 1.00 Set 0.19% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1150 LV Switchgear / MCC (SWG-001) 1.00 Set 0.19% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

External Lighting & Power Distribution 0.8% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1050 Conduits 900.00 RM 0.05% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1110 Power & control cable 5,933.00 RM 0.05% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1130 Cable glands (for hazardous area) 80.00 Nos. 0.05% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1140 Weather proof cable glands 10.00 Nos. 0.05% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1160 M.S. Channels 150.00 RM 0.04% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1170 Cable tray/ladder, trench & road crossing 3.00 Nos 0.04% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1180 Earthing & lighting system 1.00 Job 0.04% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1210 Weatherproof local control stations 6.00 Nos 0.04% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1340 L.V Distribution Panels / Switchboards 1.00 Set 0.04% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1350 Receptacles 9.00 Nos 0.04% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1360 Junction box for Lighting 4.00 Nos. 0.04% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1370 Switch 27.00 Nos 0.04% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1500 Local control stations (for hazardous area) 2.00 Nos 0.04% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1510 Uninterruptible AC power supply system (UPS) 1.00 Nos 0.04% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1520 Flood lights 27.00 Nos 0.04% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1530 Lighting poles 11.00 Nos 0.04% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1540 Emergency lights 5.00 Nos 0.04% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

GEL-PPM-F-02_DPR Page No. 18 of 26


Gasco Engineering (Pvt) Limited
Water System Construction Work-Vajihr Pipeline Project
Daily Progress Report (Detailed)
Report No. 96 Mech.
Rev-01 Mech. #REF! Date: 9-Aug-2021

Today's Todate Todate Today's Today's


Budgeted Activity Planned Todate Planned Todate Earned Today's Earned
Activity ID Activity Description Unit Earned Earned Progress % Planned Progress %
Qty Weightages Quantity Progress % Progress % Progress %
Quantity Quantity Variance Progress % Variance

HUBL1EIC1580 Generator shed lights 8.00 Nos 0.04% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1590 Maintenance shed lights 8.00 Nos 0.04% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Installation Of Instrumentation and Control System 0.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Installation of field instrumentation and Control 0.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1310 Instruments (PI, FI, LI, ANLY & MI) 48.00 Nos. 0.03% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1320 Instrument junction boxes 2.00 Nos 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1330 Installation of plc 1.00 Job 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1390 Instrument cable 1,000.00 RM 0.07% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1400 Tubing / fittings 40.00 RM 0.03% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1420 Instrument cable glands 45.00 Nos 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1430 G.I. conduit 100.00 RM 0.02% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Instrumenatation and Control System Work 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

System Integration 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1550 Cable Glanding & Termination 1.00 Job 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1570 Panel Installation 1.00 Job 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1610 Cold Loop Tests 1.00 Job 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1640 Cause & Effects 1.00 Job 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBL1EIC1650 Hot Loop Tests 1.00 Job 0.00% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Project Closure Phase 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
Testing & Commissioning 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Testing & Commissioning 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBCO1070 Punch List 1.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBCO1080 Dossier Preparation & Submission 1.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

HUBCO1200 Handover 1.00 Job 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

GEL-PPM-F-02_DPR Page No. 19 of 26


Gasco Engineering (Pvt) Limited
Water System Construction Work-Vajihr Pipeline Project
Daily Manpower Report (Detail)
Report No. 96 Date: 9-Aug-21

S. No. Designation POB Name

Water System Construction Work-Vajihr Pipeline Project


1 Site Manager 1 Nisar Ahmed Lashari

2 Civil I/C 2 Zahoor Ahmed,Muhammad Abbas

3 Planning Engineer 1 Ali Ahmed

4 Administrator 1 Fahd Ali Khan

5 Project Engineer 1 Hammad Afzal

6 QA/QC Team Leader 1 Imran Rafiq

7 QA/QC Mechanical 4 Sartaj Ahmed,Muhammad Asim,Syed Asif Ali,Atif

8 QA/QC Civil 1 Abdul Salam

9 Flow Line Superintendent 1 Shabbir Ahmed

10 Flow Line Supervisor 3 Zahid Ali,Asif,GM Durse

11 HSE Team Leader 1 Nadeem Tehseen

12 HSE Engineer 1 Abdul Basit

13 HSE Supervisor 4 Zahoor,Arsalan,Mehdi Hassan,Arshad

14 Medic 1 Saith Ali

15 Document Controller 1 Amir Shah

16 Surveyor 2 Hamid Javeed,Zahoor

17 Surveyor Helper 1 Dhani Bux

18 Store I/C 1 Abdul Waheed Abbasi

19 Logestic Officer 2 Aziz,Syed Masood

20 Trainee Engineer 3 Ali Hassan,Syed Faisal,Waseem Ahmed

21 Camp Boss 1 Kashif Abdul Salam

22 Diesel Man 1 Zakir Hussain

23 Rigger Supervisor 1 Manawer Ali

Iqbal,Sher Ali,Jaleel Ahmed,Waheed,Zameer,Amir,Hashim,Hasan


24 Rigger/ Scaffolder 15 Ali,Ibrahim,Somar,Ali Gul,Saeed Ahmed,Abdul
Hameed,Mangla,Mukhtiar

25 NDT 5 Riaz,Zubair,Lakmeer,Asif,Irfan

26 Civil Supervisor 3 Muhammad Musadiq,Gul Hassan,Zain Noorani

27 Mason 2 Anayat Ullah, Rehmat Ullah

28 Mixture Machine Operator 1 Shahid Hussain

29 Steel Fixer 4 Sabir,Imran,Ghulam Abbas,Hakim

30 Carpenter 6 Martab,Allah Bux,Muhammad Hussain,Shokat,Irfan,Yousaf

Muhammad Shoaib,Junaid,Riaz,Mula Bux,Aftab,Allah


Wassayo,Ejaz,Manzoor,Sahib,Ghulam
31 Civil Labor 20
Rasool,Mehboob,Abbas,Yousaf,Fayaz,Aslam,Ali Gul,Abdul
Ghani,Saradr,Rasheed,Sikandar

32 Sand Blaster/ Sleeve Man Lead Man 1 Yaseen

Muhammad Aslam,Ali Dad,Rizwan,Imran,Rehmat,Ali,Asif


33 Sand Blaster/ Sleeve Man 11
Ali,Humair,Abid Hussain,Ghulam Mustafa,Ayaz Ali

34 Sand Blaster/ Sleeve Man/ Holiday Helper 1 Allah Bux

35 Cook 3 Gul Hassan,Ali Nawaz,Mumtaz

36 Cook Helper 1 Ghulam Hassan

37 Chappati Man/ Helper 4 Roshan,Allah Dino,Riaz,Sikandar

38 Waiter 2 Irshad Ali,Khalid

39 Room Boy 6 Raju,Mohan,Younas,Amit Kumar,Yousaf,Gurmuk

40 Generator Operator 2 Abdul Majeed,Idress

GEL-PPM-F-02_DPR Page No. 20 of 26


Gasco Engineering (Pvt) Limited
Water System Construction Work-Vajihr Pipeline Project
Daily Manpower Report (Detail)
Report No. 96 Date: 9-Aug-21

S. No. Designation POB Name


41 Electrician 0 Liaquat Ali

42 Fire Watch Man 2 Haji Khan,Budhal

43 Mechanic 2 Abid,Akbar

44 Store Helper 1 Sakib Ali

45 Holiday Operator 1 Ali Kausar

46 Loundary Man 2 Fida,Shah Muhammad

47 Welding Team Incharge 1 Sajjad Khan

48 Spacer Man 2 Muhammad Imran,Farooq

49 Bursh Man 4 Asif Ali,Rahib,Nawaz,Sabir,Mazhar

50 Grinder Man 4 Waris,Barkat,Saleem,Shafiq,Shahid

Zulfiqar,Zahid Abbas,Shabbir,Seeraj,Gul
51 Welder 7
Hamid,Hussain,Yaseen,Jabbar

52 Welder Helper 8 Abdul Waheed,Sher Muhammad,Ghulam Qadir,Sher Khan,Taj,Sand

53 Rigger 2 Nabi Bux,Sanjar

54 Cook 1 Ali Jan

Kambo,Esro,Arab,Jhaman,Perano,Krishan,Moha,Photo,Jalal,Mitho,
55 Local Labor 13
Khamiso,Ramesh,Heman,Arab,Abu Bakar,Muqeem,Doongro,Khato

56 Civil Contractor 1 Gul Muhammad

57 Civil Supervisor 1 Abdul Malik

58 Carpenter 1 Dilshad

59 Carpenter Helper 1 Shahzad Ali

60 Scaffolder 2 Gul Sher,Shehraz

61 Steel Fixer 2 Ghulam Qadir,Munawer Ali

62 Steel Fixer Helper 1 Kareem Baksh

63 Mason 1 Bada

64 Mason Helper 1 Peer Jon

65 Vigo Driver 5 Muhammad Imran,Lal Bux,Shahzad,Wazeer,Ali Sher

66 Coaster Driver 7 Bhai Khan,Inayat,Bacho,Ghulam Shabbir,Mukesh,Imdad Ali

67 Coaster Helper 0 Khamiso

68 Single Cabin Driver 2 Muhammad Shoaib,Shabbir

69 Ambulance Driver 1 Saif Ur Rehman

70 Dozer Operator 3 Imtiaz,Hussain,Imam Din

71 Dozer Helper 0 Ghulam Hassan

72 Crane Operator 2 Majid Ali,Muhammad Arsalan

73 Crane Helper 1 Sajid Ali

74 Side Boom Operator 5 Usman,Abdul Latif,Ashraf,Ghulam Sarwer,Iqbal,Muneer

75 Side Boom Helper 1 Muhammad Ramzan

76 Loader Operator 1 Muhammad Akmal

77 Kakra Driver/ Helper 2 Mukesh,Shahzad

78 Excavator Operator 4 Ejaz Ali,Nadeem,Ghulam Haider,Ghulam Rasool

79 Excavator Helper 0 Rustam Ali

80 Compactor Roller Operator 1 Rashid Ali

81 Mazda Driver 0 Maqbool

82 Diesel Bowser Driver 1 Habib Ullah

83 Double Cabin Driver 1 Mehdi Hassan

GEL-PPM-F-02_DPR Page No. 21 of 26


Gasco Engineering (Pvt) Limited
Water System Construction Work-Vajihr Pipeline Project
Daily Manpower Report (Detail)
Report No. 96 Date: 9-Aug-21

S. No. Designation POB Name


84 Fresh Water Bowser Driver 1 Roshan

85 Long Jeep Driver 2 Ghulam Rasool,Manthar

Niaz Hussain,Muhammad Hashum,Allah


86 Local Watch Man 42 Dad,Peerano,Penal,Tamil,Hero,Jeevan,Jeetho,Amulakh,Bhuto,Hanif,
Hassan,Manan,Khalid,Khan Muhammad,Panchraj

87 Visitor 1 Gul Bahar

Total 267

GEL-PPM-F-02_DPR Page No. 22 of 26


Gasco Engineering (Pvt) Limited
Water System Construction Work-Vajihr Pipeline Project
Daily Equipment Status
Report No. 96 Date: 9-Aug-21

S. No. Equipment & Tools Qty. Remarks

Water System Construction Work-Vajihr Pipeline Project


1 Porta Cabin Office (40 ft) 4

2 Porta Cabin (20 ft) 2

3 Genset 100 KVA 1

4 Genset 60 KVA 1

5 Genset 20 KVA 1

6 Vigo 5

7 Ambulance 1

8 Coaster 6

9 Single Cabin 2

10 Dozer 3

11 Crane 35 Ton 1

12 Crane 25 Ton 1

13 Side Boom 8

14 Kakra 6x6 9

15 Double Cabin 1

16 Loader 1

17 Long Jeep 2

18 Trailer Low Bed 0

19 Fresh Water Bowser 1

20 Mixture Machine 3

21 Welding Machine 7

22 Rectifier 6

23 Desiccator 8

24 Oven 2

25 Gas Cutting Torch 1

26 Plate Compactor 3

27 Roller Compactor 1

28 Grinder 9" 15

29 Baby Grinder 4" 8

30 Pencil Grinder 4

31 Mazda 0

32 Chain Excavator 5

33 Sand Blasting Setup (Compressor & Hooper) 1

34 Diesel Bowser 1

35 Water Tank 2

36 Internal Clamp 2

37 External Clamp 1

38 Holiday Detector 1

39 Total Staton 2

40 Level Instrument 2

Total 125

GEL-PPM-F-02_DPR Page No. 23 of 26


Gasco Engineering (Pvt) Limited
Water System Construction Work-Vajihr Pipeline Project
Next Day Plan

Report No. 96 Date: 9-Aug-21

S. No. Next Day Plan Report

1 ROW Preparation Works at Hubco Pipeline.

2 Dune Cuttting & Filling Works at Hubco Pipeline.

3 Pipe Stringing Works at Hubco Pipeline.

4 Production Welding Works at Hubco Pipeline.

5 Radiography Works at Hubco Pipeline.

6 HSS Application Works at Hubco Pipeline.

7 Trench Excavation Works at Hubco Pipeline.

8 Holiday, Pipe Lowering and Partial Backfilling Works at Hubco Pipeline.

9 Final Backfilling Works at Hubco Pipeline.

10 Tie In Welding Works at Hubco Pipeline.

11 Excavation of Underground Diesel Tank at TEL Hubco Pumping Station.

Formwork & Pouring for Column above Plinth Beam of Accommodation Building at TEL Hubco
12
Pumping Station.

13 Formwork of Intake Structure Pit Walls Sec.2 at TEL Hubco Pumping Station.

GEL-PPM-F-02_DPR Page No. 24 of 26


Gasco Engineering (Pvt) Limited
Water System Construction Work-Vajihr Pipeline Project
Permits Requisition
Report No. 96 Date: 9-Aug-21

S. No. Permits/Certificates Requisition

1 Cold Work Permit is required.


2 Hot Work Permit is required.

GEL-PPM-F-02_DPR Page No. 25 of 26


Gasco Engineering (Pvt) Limited
Water System Construction Work-Vajihr Pipeline Project
Bottleneck/Holdup Report

Report No. 96 Date: 9-Aug-21

S. No. Bottleneck/Holdup Report

Today Trench Excavation, Holiday Testing, Pipe Lowering, Partial Backfilling and Final Backfilling works
1
were hold @ Chainage 22+000 due to local community issue of land clearance.
Today Pipe Stringing works was hold @ Chainage 25+800 due to local community issue of land
2
clearance.
Today Production Welding works was hold at 04:30 PM @ Chainage 25+800 due to unavailability of pipe
3
stringing and pipe stringing activity was hold due to local issue.

GEL-PPM-F-02_DPR Page No. 26 of 26