Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S.
Item Details
No.

Details of Project:
Proposed project for expansion in existing products with deletion of some of the existing
(a)Name of the project(s) products & addition of new products for manufacturing of synthetic organic chemicals at
Plot No.: A-21, Mahad
1.
(b)Name of the Company / Organisation PIDILITE INDUSTRIES LIMITED
Ramkrishna Mandir Road, Near Off. Sir Mathuradas Vasanji Road, Kondivita, Andheri
(c)Registered Address
(E),Mumbai,400059,Raigad,Maharashtra-400059
(d)Legal Status of the Company Others

Address for the correspondence:


(a)Name of the Applicant Sagar Jadhav
(b)Designation (Owner/ Partner/ CEO) CMO
Plot no. A-21, MIDC Mahad, Dist- Raigad, Maharashtra-
(c)Address
402309,,Mahad,Raigad,Maharashtra-400059
(d)Pin code 400059
2.
(e)E-mail sagar.jadhav@pidilite.com
(f)Telephone No. 234188
(g)Fax No. 28364565
(h)Copy of documents in support of the competence/authority
of the person making this application to make application on Annexure-Uploaded Copy of documents in support of the competence/authority
behalf of the User Agency .

Category of the Project/Activity as per Schedule of EIA Notification,2006:


(a)Major Project/Activity 5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
(b)Minor Project/Activity NIL
(c)Category B1
3.
(d)Proposal Number SIA/MH/IND2/31682/2018
(e)Master Proposal Number(Single Window) SW/96713/2019
(f)EAC concerned (for category A Projects only) Industrial Projects - 2
(g)Project Type Fresh EC

Location of the Project:


(a)Plot/Survey/Khasra No. A-21
(b)Pincode 402309
(c)Bounded Latitudes (North) FROM 18.113397 To 18.113583
(d)Bounded Longitudes (East) FROM 73.472779 To 73.474433
(e)Survey of India Topo Sheet No. 47
4.
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 24.84
(h)Uploaded (kml) File Copy of Kml File
(i)Distance of Nearest HFL from the project boundary within the
2.2
study area
(j)Seismic Zone 3

(a)Number of States in which Project will be Executed 1


5.
(b)Main State of the project Maharashtra

Details of State of the project

S.
State Name District Name Tehsil Name Village Name
No.

NIL

Details of Terms of Reference (ToR):


(a)MoEF&CC / SEIAA File Number SEIAASTATEMENT - 0000001563
6.
(b)Date of Issue of TOR / Standard ToR 04 Oct 2018
(c)Previous TOR Letter Copy of Previous TOR letter

Details of Public Consultation:


(a)Whether the Project Exempted from Public Hearing? Yes
7.
(b)Reason factory is located in approved MIDC area, Mahad
(c)Supporting Document Copy of Supporting Document

8. Details of Project Configuration/Product:

8.1. Project Configuration

S.
Plant/Equipment/Facility Configuration Remarks
No.

1 of 9 8/10/2020, 6:54 PM
Report Part 1 http://environmentclearance.nic.in/state/FB_ECGeneral_Report.aspx?pi...

Plant : Isopropanol by 60 M3 Reactor,2 to 85m3/hr


(1.)
hydration route Distillation columns

Cooling towers, Boilers (Coal &


(2.) Utilities
Oil fired)

Plant: Isopropanol by
(3.) 50 M3 & 16 m3 Reactor
hydrolysis route.

Plant : Propylene Trimer /


(4.) 1.5 T / hr Reactor
Tetramer

(5.) Plant : Nonyl Phenols 2.5 T/hr Reactor

8.2. Product

Other Mode of
S. Product/Activity Mode of Transport / Transport /
Quantity Unit Other Unit
No. (Capacity/Area) Transmission of Product Transmission of
Product

By Product - Nonene
(1.) 110 Tons per Annum Road
(Propylene trimer)

By Product -
(2.) Hydrocarbon mix - 140 Tons per Annum Road
light

By Product -
(3.) Hydrocarbon mix - 55 Tons per Annum Road
Medium

1 c4) Isopropyl alcohol


(4.) 100000 Tons per Annum Road
(IPA)

(5.) By product - Propane 15840 Tons per Annum Road

1 c1) Isopropyl
(6.) 10800 Tons per Annum Road
acetate (IPAc)

1 a) Vinyl acetate
(7.) 0 Tons per Annum Others --
monomer

1 c3) Di-isopropyl
(8.) 5400 Tons per Annum Road
ether(DIPE)

(9.) 1 b) Allyl alcohol 0 Tons per Annum Others --

1 c2) n-propyl acetate


(10.) 0 Tons per Annum Others --
(nPAc)

(11.) 3 Nitrogen 0 Tons per Annum Others --

(12.) 4 Soft PVC film 8640 Tons per Annum Others --

5 Oligomers
(13.) (Propylene trimer, 11000 Tons per Annum Road
Tetramer, Pentamer)

6 Alkyl phenols (
(14.) Nonyl , Dodecyl, 20000 Tons per Annum Road
Dinonyl )

(15.) 2 Oxygen 0 Tons per Annum Others --

In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) /
Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
9.
Details Not Applicable

Details of Consent to Operate


(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
9.1.
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA

Project Cost:
(a)Total Cost of the Project at current price level (in crores) 485.12
(b) Funds Allocated for Environment Management (Capital) (in
15.40
crores)
10. (c) Funds Allocated Towards ESC (Entrepreneur Social
2.75
Responsibility) (in crores)
(d) Funds Allocated for Environment Management Plan (EMP)
10.975
(Recurring per Annum) (in crores)
(e) Funds Allocated for Environment Management Capital(%) 3.09

2 of 9 8/10/2020, 6:54 PM
Report Part 1 http://environmentclearance.nic.in/state/FB_ECGeneral_Report.aspx?pi...

Whether project attracts the General Condition specified


11. No
in the Schedule of EIA Notification ?

Whether project attract the Specific Condition specified


12. No
in the Schedule of EIA Notification ?

Raw Material / Fuel Requirement:


(a)Proposed quantity of raw material/fuel 147000
13.
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 147000

13.1. Raw Material / Fuel Profile

Distance of
Source Source
(incase of from
Import. Project Site
please (in
specify Kilometres)
country (In case of
Raw Other Mode Uploaded
S. Other and Name Mode of import, Type of Other Type
Material / Quantity Unit of Copy of
No. Unit of the Transport distance Linkage of Linkage
Fuel Transport Linkage
port from from the
which port from
Raw which the
Material / raw
Fuel is material /
received ) fuel is
received)

Tons per Copy of


(1.) Acetic Acid 6900 Local Road 180 Open Market
Annum Linkage

Tons per Copy of


(2.) Phenol 9000 Local Road 180 Open Market
Annum Linkage

Propylene Tons per Copy of


(3.) 3540 Local Road 180 Open Market
Tetramer Annum Linkage

Tons per Copy of


(4.) Furnace Oil 3650 Local Road 200 Open Market
Annum Linkage

Copy of
(5.) LPG 12 Others Cylinder/A Local Road 100 Open Market
Linkage

Tons per Copy of


(6.) Propane 32330.97 In House Others -- 00 Others In House
Annum Linkage

Copy of
(7.) HSD 365 Others KL/A Local Road 100 Open Market
Linkage

Tons per Copy of


(8.) Propylene 118020 Local Road 180 Open Market
Annum Linkage

Tons per Copy of


(9.) Coal 108770 Local Road 200 Open Market
Annum Linkage

Propylene Tons per Copy of


(10.) 9540 Local Road 180 Open Market
Trimer Annum Linkage

Baseline Data :
14. (a)Period of Base Line Data Collection FROM 01 Nov 2017 To 31 Jan 2018
(b)Season Post-Monsoon

14.1. No. of ambient Air Quality (AAQ) Monitoring Locations : 8

S. Maximum Minimum 98 Percentile Prescribed


Criteria Pollutants Other Criteria Pollutants Unit
No. Value Value Value Standard

Micro Gram per


(1.) PM10 84.6 49 83.8 100
Meter Cube

Micro Gram per


(2.) PM2.5 56.3 20.6 55.58 60
Meter Cube

Micro Gram per


(3.) Others Co 2.1 0.2 2.06 4
Meter Cube

Micro Gram per


(4.) NOx 55.3 10.2 54.39 80
Meter Cube

Micro Gram per


(5.) SO2 39.2 10.2 38.62 80
Meter Cube

14.2. No. of Ground Water Monitoring Locations : 6

Other Maximum
S. Criteria Maximum Minimum Desirable
Criteria Heavy Metal Unit Other Unit Permissible
No. Pollutants Value Value Limit
Pollutants Limit

(1.) TDS mg/l 300 109 500 2000

(2.) Total Hardness mg/l 204 76 200 600

3 of 9 8/10/2020, 6:54 PM
Report Part 1 http://environmentclearance.nic.in/state/FB_ECGeneral_Report.aspx?pi...

(3.) Chlorides mg/l 44 7 250 1000

(4.) Fluoride mg/l 1.8 0.2 1.0 1.5

(5.) pH NA 8.27 6.5 6.5....8.5 6.5....8.5

(6.) TSS mg/l .. .. .. ..

(7.) Others Sulphates mg/l 48.81 10 200 400

(8.) Heavy Metals Zinc mg/l 0.09 0.01 5 15

14.3. No. of Surface Water Monitoring Locations : 6

Classification
S. Maximum Minimum
Criteria Pollutants Other Criteria Pollutants Unit Other Unit of inland
No. Value Value
water body

(1.) DO NA 5.77 5.07 A

(2.) COD mg/l .. .. E

(3.) pH NA 7.4 6.7 A

(4.) BOD mg/l 8 7 D

(5.) Others Sodium Absorption Ratio (SAR) mg/l 1.4 0.02 D

14.4. No. of Ambient Noise Monitoring Locations : 8

S.
Parameter Unit Maximum Value Minimum Value Prescribed Standard
No.

(1.) Leq(Night) A-weighted decibels(dB(A)) 64.0 54.6 70

(2.) Leq(Day) A-weighted decibels(dB(A)) 68.9 63.5 75

14.5. No. of Soil Sample Monitored Locations : 8

S.
Parameter Unit Other Unit Maximum Value Minimum Value
No.

(1.) pH 6.6 5.8

(2.) Electric Conductivity Millisiemens per Centimetre 0.08 0.025

(3.) K(Potassium) Milligram per Kilogram 214 35

(4.) N(Nitrogen) Milligram per Kilogram 1471 376

(5.) P(Phosphorus) Milligram per Kilogram 27 4

Details of Ground Water Table:


(a)Range of Water Table Pre-Monsoon Season (Meters Below
From 18 To 38
Ground Level (m bgl))
14.6.
(b)Range of Water Table Post-Monsoon Season (Meters Below
From 15 To 38
Ground Level (m bgl))
(c)Whether Ground Water Intersection will be there ? No

15. Details of Water Requirement (During Operation)

Copy of
Other
Distance Permission Other Method of
S. Source Required Mode of Method of Date of Permitted
Source from from Mode of Water Letter No.
No. Other Quantity Transport Water Issue Quantity
Source Competent Transport Withdrawal
Withdrawal
Authority

Copy of IFMS No.


14 Dec
(1.) Others MIDC 2267 2.2 Permission Pipeline Others MIDC EE/TB/E19091/ 1151
2018
Letter of 18

15.1. (a)Whether Desalination is proposed No

16. Waste Water Management(During Operation)

Quantity of
Treatment Quantity of Treated Quantity of
Waste Water
S. Capacity Treatment Mode of Other Mode of Water Used in Discharged
Type/Source Generated
No. (Kilolitre per Method Disposal Disposal Recycling/Reuse Water (Kilolitre
(Kilolitre per
Day) (Kilolitre per Day) per Day)
Day)

Industrial Zero Liquid Reuse within the


(1.) 569.2 650 569.2
Projects - 2 Discharge Plant & Recycling

(a)Total Waste Water Generation 569.2


16.1. (b)Total Discharged Water 0
(c)Total Reused Water 569.2

17. Solid Waste Generation/Management

Quantity Distance
S. Other Mode of Other Mode Mode of Other Mode of
Name of Waste Item per Unit from
No. Item Transport of Transport Disposal Disposal
Annum Site(KM)

4 of 9 8/10/2020, 6:54 PM
Report Part 1 http://environmentclearance.nic.in/state/FB_ECGeneral_Report.aspx?pi...

Hazardous
Waste (as
per Treatment,
Distillation Hazardous Storage and
(1.) 275 Tons 180 Road
Residue and Other Disposal
Waste Facility(TSDF)
Management
rules 2016)

Hazardous
Waste (as
per
Hazardous Authorized
(2.) Used/Spent oil 3.201 Kilolitre 100 Road
and Other Recyclers
Waste
Management
rules 2016)

Hazardous
Waste (as
per
Thermic Fluid Hazardous Authorized
(3.) 10 Kilolitre 100 Road
spent oil and Other Recyclers
Waste
Management
rules 2016)

Hazardous
Waste (as
per
Discarded
Hazardous Authorized
(4.) containers/Barrels 1000 Tons 100 Road
and Other Recyclers
in Number
Waste
Management
rules 2016)

Hazardous
Waste (as
per Treatment,
Oil soaked cotton Hazardous Storage and
(5.) 1 Kilolitre 180 Road
waste and Other Disposal
Waste Facility(TSDF)
Management
rules 2016)

Hazardous
Waste (as
per Treatment,
Hazardous Storage and
(6.) Glass wool 20 Tons 180 Road
and Other Disposal
Waste Facility(TSDF)
Management
rules 2016)

Hazardous
Waste (as
per Treatment,
Hazardous Storage and
(7.) Spent resin 5 Kilolitre 180 Road
and Other Disposal
Waste Facility(TSDF)
Management
rules 2016)

Authorized
(8.) Batteries E Waste 30 Tons 100 Road
Recyclers

Authorized
(9.) E waste E Waste 1000 Kilolitre 100 Road
Recyclers

Hazardous
Waste (as
per
Used/Spent Hazardous Authorized
(10.) 200 Kilolitre 100 Road
catalyst and Other Recyclers
Waste
Management
rules 2016)

Hazardous
Waste (as
per Treatment,
Chemical sludge Hazardous Storage and
(11.) 380 Tons 180 Road
from WWt and Other Disposal
Waste Facility(TSDF)
Management
rules 2016)

Hazardous
Waste (as Treatment,
per Storage and
(12.) Spent carbon Hazardous 158 Tons 180 Road
Disposal
and Other Facility(TSDF)
Waste

5 of 9 8/10/2020, 6:54 PM
Report Part 1 http://environmentclearance.nic.in/state/FB_ECGeneral_Report.aspx?pi...

Management
rules 2016)

Hazardous
Waste (as
per
Discared Liners & Hazardous Authorized
(13.) 5 Tons 100 Road
Bags and Other Recyclers
Waste
Management
rules 2016)

Hazardous
Waste (as
per Treatment,
Hazardous Storage and
(14.) MEE salts 209 Tons 180 Road
and Other Disposal
Waste Facility(TSDF)
Management
rules 2016)

Hazardous
Waste (as
per Treatment,
Used oil filter non
Hazardous Storage and
(15.) metallic in 50 Tons 180 Road
and Other Disposal
Number
Waste Facility(TSDF)
Management
rules 2016)

18.

18.1. Air Quality Impact Prediction

Other
S. Criteria Baseline Incremental Prescribed
Criteria Unit Distance GLC Total GLC
No. Pollutants Concentration Concentration Standard
Pollutants

(1.) PM10 Microgram per Meter Cube 78.3 1.6 0.5 78.8 100

(2.) PM2.5 Microgram per Meter Cube .. .. .. .. ..

(3.) NOx Microgram per Meter Cube 53.8 1.6 0.0 53.8 80

(4.) SO2 Microgram per Meter Cube 38.7 1.6 7.0 45.7 80

18.2. Stack Details

S.
Source Fuel Stack Height(m) Stack Diameter(m) Pollutants Other Pollutants Emission (GLS)
No.

(1.) Boiler 10 TPH Coal 34.5 1 PM10,SO2,PM2.5 SPM: 1.33 Gm/S

(2.) Thermopack Coal 34.5 1 PM10,SO2,PM2.5 SPM: 0.046 Gm/S

(3.) Boiler 50 TPH Coal /Propane 52 2 PM10,SO2,PM2.5 SPM:2.22 Gm/S

Thermopack 8
(4.) Coal 52 2 PM10,SO2,PM2.5 SPM:0.046 Gm/S
Lac K/cal

LPG/Propane
(5.) Flare 35 1 Others ..
purge gas

LPG/ Propane
(6.) Flare 35 1 Others ..
purge gas

DG 750 KVA x
(7.) HSD 3.5 0.2 SO2 SO2: 2.27 Gm/S
3 Nos.

Diesel engine
driven fire
(8.) HSD 3.5 0.2 SO2 SO2: 0.28 Gm/S
water pump
(2 no.)

(9.) Boiler 6 TPH FO/Propane 32.5 0.9 SO2 SO2: 4.63 Gm/S

(10.) Boiler 6 TPH FO/Propane 32.5 0.9 SO2 SO2:4.63 Gm/S

(11.) Boiler 50 TPH Coal/Propane 52 2 PM10,SO2,PM2.5 SPM:2.22 Gm/S

Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 16293
(b)Source MSEDCL & Solar panel
19.
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 750 KVA x 3 Nos.
(e)Stack Height (in m) 3.5

Land Ownership Pattern:


(a)Forest Land 00
20. (b)Private Land 00
(c)Government Land 00

6 of 9 8/10/2020, 6:54 PM
Report Part 1 http://environmentclearance.nic.in/state/FB_ECGeneral_Report.aspx?pi...

(d)Revenue Land 00
(e)Other Land 16.9166
Total Land 16.9166

Present Land Use Breakup of the Study Area in Ha:


(a)Agriculture Area 00
(b)Waste/Barren Land 00
(c)Grazing/ Community Land 00
(d)Surface Water Bodies 00
(e)Settlements 00
21.
(f)Industrial 16.9166
(g)Forest 00
(h)Mangroves 00
(i)Marine Area 00
(j)Others : MIDC 00
Total 16.9166

22. Land Requirement for Various Activities

S. Description of Activity /
Others Land Requirement Remarks
No. Facility / Plant / Others

(1.) Main Plant 0.6556

(2.) Green belt 5.5839

Raw material,
(3.) Others 10.6771
utility,roads,other areas

Total 16.9166

Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas;
23.
ESZs-Eco Sensitive Zones :

23.1. Details of Ecological Sensitivity :

S. Details of Ecological
Name Distance from the Project (Km) Remarks
No. Sensitivity

(1.) Wildlife Corridors no area 00 there is no Ecological sensitive area

(2.) ESZs no area 00 there is no Ecological sensitive area

(3.) Corridors no area 00 there is no Ecological sensitive area

The notification regarding ESA village still in


(4.) ESAs Matwan village 2.7
Draft stage

(5.) WLS no area 00 there is no Ecological sensitive area

(6.) Critically Polluted Area no area 00 there is no Ecological sensitive area

(7.) NPA no area 00 there is no Ecological sensitive area

23.2. Details of Environmental Sensitivity :

S. Details of Environmental Other Details of


Name Distance from the Project (Km) Remarks
No. Sensitivity Environmental Sensitivity

There is no
Environmental
(1.) Forest no area 00
sensitive area within
10 KM radiu

There is no
Environmental
(2.) Archaeological Sites no area 00
sensitive area within
10 KM radius

There is no
Environmental
(3.) Others No area No such area 00
sensitive area within
10 KM radius

There is no
Environmental
(4.) Defence Installations no area 00
sensitive area within
10 KM radius

(a)Whether Noc / Permission from the competent authority is


No
23.3. required?
(b)Whether NBWL recommendation is required? No

Forest Land:
24.
Whether any Forest Land involved? No

Tree Cutting:
25. (a)No. of Trees Cut for the Project (if Forest Land not Involved) 00

7 of 9 8/10/2020, 6:54 PM
Report Part 1 http://environmentclearance.nic.in/state/FB_ECGeneral_Report.aspx?pi...

(b)Details of Tree Cutting and Planting of Trees Not Applicable

Land Acquisition Status:


(a)Acquired Land(Ha) 16.9166
26.
(b)Land yet to be acquired(Ha) 00
(c)Status of Land acquisition if not acquired 00

Rehabilitation and Resettlement (R&R):


(a)No. of Villages 00
(b)No. of Households 00
27. (c)No. of PDFs (Project Displaced Families) 00
(d)No. of PAFs (Project Affected Families) 00
(e)Funds Allocated for R&R(in Rs) 00
(f)Status of R&R Completed

Details of Presence of Schedule-I Species:


(a)Whether there is Presence of Schedule-I Species ? No

28. (b)Whether conservation plan for Schedule-I Species has been


No
prepared ?
(c)Whether conservation plan for Schedule-I Species has been
No
approved by competent authority ?

Details of Presence of Water Bodies in Core Area:


(a)Whether there is Presence of Water Bodies in Core Area ? No
29. (b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent
No
authority ?

Details of Presence of Water Bodies in Buffer Area:


(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
30. (i)Details of Water Bodies in Buffer Area Savitri river
(ii)Direction of Water Bodies in Buffer Area South West
(iii)Distance of Water Bodies in Buffer Area 6.75

Manpower Requirement:
(a)Permanent Employment-During Construction 00
(b)Permanent Employment-During Operation 229
31. (c)Temporary Employment- During Construction 28
(d)Temporary Employment- During Operation 42
(e)No. of working days 26
(f)Total Manpower 299

Green Belt in Ha:


(a)Total Area of Green Belt (in hectare) 5.5839
(b)Percentage of Total Project Area 33.01
32.
(c)No. of Plants to be Planted 00
(d)Funds Allocated for Plantation 800000
(e)Uploaded Green Belt plan Copy of Green Belt Plan

33. Project Benefits

S.
Type of Project Benefits Details of Project Benefits
No.

(1.) Financial 299

34. CRZ Specific Details : Not Applicable

35. Sector Specific Details : NOT APPLICABLE

35. Sector Specific Details For Industrial Projects - 2

S.
Item Details
No.

S.
Item Details
No.

Details of Court Cases:


36. (a)Whether there is any Court Cases pending against the
project and/or land in which the project is proposed to be set up No
?

Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention &
37. Control of Pollution) Act:

8 of 9 8/10/2020, 6:54 PM
Report Part 1 http://environmentclearance.nic.in/state/FB_ECGeneral_Report.aspx?pi...

(a)Whether any Direction issued under EPA Act/Air Act/Water


No
Act ?

Details of EIA Consultant:


(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/SA074
(ii)Name of the EIA Consultant GoldFINCH ENGINEERING SYSTEM PRIVATE LIMITED
Plot No. A-288, Road No. 16 Z, Opp. Agriculture Office Bus-stop, Thane Industrial Area,
(iii)Address
MIDC, (Wagle Estate), Thane (W)
38. (iv)Mobile No. 9821812132
(v)Landline No. 0222088555
(vi)Email Id anad.apte@goldfinchengg.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 04 Dec 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation

Documents to be Attached:
(a)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(b)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(c)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project
Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report
Report(DPR) /Detailed Engineering Report /Detailed Conceptual
/Detailed Conceptual Plan /Approved Mining Plan
39. Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the
Copy of documents in support of the competence/authority of the person making this
competence/authority of the person making this application to
application to make application on behalf of the User Agency
make application on behalf of the User Agency
(i)Uploaded Additional File NA
(f)Uploaded Updated Form1 NA

Essential Details Sought

S. No. EDS Sought Date EDS Sought Letter

NO Record
Addtional Details Sought

S. No. ADS Sought Date ADS Sought Letter

NO Record

Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and
belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected
and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no
activity/ construction/ expansion has since been taken up.

Name of Applicant Sagar Jadhav


Designation CMO
Name of Company (Applicant Name should not be given
PIDILITE INDUSTRIES LIMITED
here)
Ramkrishna Mandir Road, Near Off. Sir Mathuradas Vasanji Road, Kondivita, Andheri
Address
(E),Mumbai,400059

Print