DIESEL ENGINES

Since construction details and auxiliary equipment can vary widely from
Manufacturer to Manufacturer, it is important to consult Manufacturer's instruction
manual for any additional pre-commissioning checks not mentioned below.
1. Check whether the crankcase, oil pump and lubricating lines have been
properly flushed and are clean. Check that the crankcase can be vented.
2. Check the cleanliness of oil filters and oil coolers.
3. Check that the fuel oil system is in accordance with Manufacturer's drawing.
(01 Feb)
4. Check that the entire fuel oil system has been properly flushed and is clean.
5. Check filter and separators.
6. Check that cooling water lines are installed in accordance with Manufacturer's
drawings. (31 Jan)
7. Check that the entire cooling water system is properly flushed and is clean.
8. Check the line-up of starting equipment. If an electric starting system is fitted,
check electrical installation and battery condition. (Wednesday 02.Feb)
9. If an air starting system is fitted, check the line-up of compressor, starting-air
vessel, and all pipe connections in accordance with the Manufacturer's
instructions.
10. Check that the starting-air vessel is equipped with a safety/relief valve (and
check the set pressure) and that the vessel can be drained.
11. Check that an air inlet filter is installed.
12. Check that the oil sump (karter za ulje) contains oil up to the correct level.
13. Check that the barring functions correctly (ovo se odnosi na turbine).
14. If a lubricator is installed, check that it contains oil up to the correct level and
check for proper supply to all lubricated points by rotating the crank by hand.
15. Check that the fuel oil tank is filled with fuel oil.
16. Initial run
1) Consult Manufacturer's instruction manual for start-up procedure of engine.
2) Regular observations should be made of temperatures, luboil pressure,
speed regulation, vibration, etc.
3) Check whether noise exceeds specified limits.
4) Make hot check of the coupling alignment, if necessary.

No Activity Date
1 Providing all necessary drawings, manuels etc Monday, 31 Jan
2 Check model MTU and manufacturer – on the site
Check that cooling water lines are installed in
3 Monday, 31 Jan
accordance with Manufacturer's drawings
Check that the fuel oil system is in accordance with
Thuesday 01 Feb
Manufacturer's drawing.

Check the line-up of starting equipment. If an electric


starting system is fitted, check electrical installation Wednesday 02 Feb
and battery condition