ITP For Structure Steel Erection Works
ITP For Structure Steel Erection Works
Doc No
SAFCO/IBB MOBILE COATING 005
UNIT POJECT Rev. No. 00
ITP FOR STEEL STRUCTURE ERECTION
Date 25th Jun, 2020
WORKS
Page 1 of 13
No Part of this document or the information it contains may be reproduced or transmitted in any
form or by any means electronic or mechanical, including photocopying, recording, or by any
information storage and retrieval system, without permission in writing from SABIC or NCC
EPM-ITP-BC-
Doc No
SAFCO/IBB MOBILE COATING 005
UNIT POJECT Rev. No. 00
ITP FOR STEEL STRUCTURE ERECTION
Date 25th Jun, 2020
WORKS
Page 2 of 13
TABLE OF CONTENTS
Inspection Responsibility
Sr. Acceptance Verifying Sub-
Inspection Activity Characteristic Verified (4) Reference Document (5)
No Criteria (6) Document (7) Contractor CONTRACTOR COMPANY
/Vendor
1.1 Material inspection Conformance to Specification Test & Visual Check AISC303-05 PART7 ST-001-MRI-1 I W R
1.3 WPS/Welder Qualification Qualification Record AWS D1.1 AWS D1.1 Qualification Record I W W
Inspection Responsibility
Sr. Acceptance Verifying Sub-
Inspection Activity Characteristic Verified (4) Reference Document (5)
No Criteria (6) Document (7) Contractor CONTRACTOR COMPANY
/Vendor
2 Erection
Dimensional Check: Length, size and bolt As per inspection items SES B02-S02
2.1 SES B02-S02 ST-001-2 I W W
condition in the Checklist of QVD IFC Drawing
3 Paint/Touch-up Paint
3.1 Surface preparation As per inspection items SES-B02-S02 IFC Drawings ST-001-5 I W SW
and application of Paint in the Checklist of QVD SES-T01-S01
(if Applicable) SES-B02-S02
Doc No EPM-ITP-BC-005
Inspection Responsibility
Sr. Acceptance Verifying Sub-
Inspection Activity Characteristic Verified (4) Reference Document (5)
No Criteria (6) Document (7) Contractor CONTRACTOR COMPANY
/Vendor
SES-A01-S02
SES-B02-S02
SES-B02-S02
SES-T01-S01
SES-T01-S01
SES B02-S02
Final Inspection of Structural Steel As per inspection items SES B02-S02
4 SES-A01-S02 ST-001-6 I W H
Erection in the Checklist of QVD SES-A01-S02
SES A12-S01
SES A12-S01
SES-A12-S02
SES-A12-S02
IFC Drawings
Legend
(1) ‘Prepared by’ should be the name, signature and COMPANY’s name for the Vendor’s/Sub-Contractor’s representative.
(2) ‘Approved by’ should be the name, signature and COMPANY’s name for the CONTRACTOR’s representative.
(3) ‘Location’, ‘Item Name’ and ‘Tag Number’ shall be used if applicable.
(4) ‘Characteristics Verified’ are the parameters checked during the inspection activity.
(5) ‘Reference Document’ is the Project Specification / Code / Standard / Drawing, Procedure etc. on the basis of which inspection shall be conducted.
(6) ‘Acceptance Criteria’ is the tolerance, reading, value or an outcome derived from reference documents.
(7) ‘Verifying Document’ is the record generated during inspection & Testing using approved forms / checklists.
(8) ‘Inspection Responsibility’ is the role of Vendor / Sub-Contractor, CONTRACTOR and COMPANY for each inspection step. Inspection responsibility shall be ‘I’ for Inspection, ‘R’ for review, ‘A’ for approval, ‘S’ for
Surveillance, “W’ for 100% Witness, ‘SW’ for random witness and ‘H’ for hold.
EPM-ITP-BC-
Doc No
SAFCO/IBB MOBILE COATING 005
UNIT POJECT Rev. No. 00
ITP FOR STEEL STRUCTURE ERECTION
Date 25th Jun, 2020
WORKS
Page 6 of 13
2 Supplier
□ Satisfied
5 Visual Inspection
□ Unsatisfied
6 Remarks
Submitted by:
Review and approval Status:
□ (A) Approved without comments.
□ (B) Approved with comments.
□ (C) Disapproved.
Comments:
Name
Signature
EPM-ITP-BC-
Doc No
SAFCO/IBB MOBILE COATING 005
UNIT POJECT Rev. No. 00
ITP FOR STEEL STRUCTURE ERECTION
Date 25th Jun, 2020
WORKS
Page 7 of 13
Date
EPM-ITP-BC-
Doc No
SAFCO/IBB MOBILE COATING 005
UNIT POJECT Rev. No. 00
ITP FOR STEEL STRUCTURE ERECTION
Date 25th Jun, 2020
WORKS
Page 8 of 13
Signature
Date
4.0 Checklist-Plumbing & Level Inspection Record
ST-001-2
PLUMBING & LEVEL INSPECTION RECORD Record No
Date
Drawing
Location IBB/SAFCO
No
Inspection Result
Item Description of Check Result
Yes No N/A
01 Correct dimension and size Y
02 Match of member Y
03 Correct grade & length of bolts Y
04 Correct size & bolts condition Y
Correct Installed the Beam and bracing
05 alignment, diagonal to meet the required Y
elevation
Allow.
Actual Reading Actual Reading Difference Result
Length (N/S-Direction) Tolerance
Column No (E/W-Direction) Tolerance Result
(mm) (mm) (mm) (mm)
(mm) Accept Reject
Name
Signature
EPM-ITP-BC-
Doc No
SAFCO/IBB MOBILE COATING 005
UNIT POJECT Rev. No. 00
ITP FOR STEEL STRUCTURE ERECTION
Date 25th Jun, 2020
WORKS
Page 10 of 13
Date
ST-001-3
BOLT TIGHTENING RECORD Record No
Date
Area
Project No SP-173100119 Page of
No
Location IBB/SAFCO
Drawing Bolt Tightening
No. Method
Calibration Record
Name
Signature
Date
ST-001-4
GROUT/POUR CARD Record No
Date
BLOTS
Grout
GROUTING PARTS BASE PLATES
Material
PERIPHERY
INSPECTION RESULTS
DESCRIPTION REMARKS
Yes No N/A
1. Pre-grouting Inspection
1.1 Chipped
2. Grout Inspection
Name
Signature
Date
ST-001-5
PAINTING/TOUCH-UP INSPECTION
Record No
RECORD
Date
Application
Brand Name
Method
Location IBB/SAFCO
Inspection Results
Item Description of Check Remarks
Yes No N/A
Ensure that the area has been prepared, clean and it was dry/free from
1 condensation prior to the application of paint/coating
Verify that the color of the paint applied was in accordance with the
3 requirements of relevant project specification.
Verify that the correct number of coat has been applied in accordance
4 with the requirements of relevant paint code.
Verify that the paint application has not fouled any moving parts (i.e.
5 valve spindle)
Verify that all defects have been repaired & touch-up in accordance
7 with the approved manufacturer’s instruction.
NOTES :
Name
Signature
Date
IBB RELIABILITY IMPROVEMENT Doc No
PROJECT 1478-M-
SNEC
00000-QQM-
Doc No.
PL04-004A
ITP FOR STRUCTURE STEEL ERECTION Date 25 Sep, 2018
WORKS Page 13 of 13
9.0 Checklist-Final Inspection of Structural Steel Erection
ST-001-6
FINAL INSPECTION OF STRUCTURAL
Record
STEEL ERECTION No
Date
Are Drawing
Project No. SP-173100119 a No.
No
Location IBB/SAFCO
Inspection Results
Description of Check Remarks
Item
Yes No N/A
Structural elements (main structure, handrails, grating, kick plates,
01
ladders or staircases)- installed and checked against drawings
Corre
07 Welded connections checked
REMARKS :
Name
Signature
Date