Project: Sugam vanijya Holding pvt Ltd.

,
Bill No.: RA 02
Vendor: M/s BLK & Sons
Nature of work: Block work and Concrete

Sl.No. Description Date No. of Days

1 RA Bill No. 02 received by Synergy June 7, 2011

2 Soft copy of the bill received June 9, 2011 1 day delay

3 Joint measured and certified along with KPK June 11, 2011 2 days

4 Sent mail to KPK for certificate June 11, 2011

5 Certificate from KPK June 16, 2011 4 days

6 Final singature of Synergy (At HO) June 23, 2011

7 Submission of corrected copy along with certificates June 23, 2011


Remarks

Received at 7.00PM

received at 12.00 noon

By mail at 12.30 PM

Received at 4.30PM

Sent to HO on 17.06.2011

Sent to client