Professional Documents
Culture Documents
Koc Standard
Koc Standard
Koc Standard
FOREWORD
Early in 1979, it became apparent that many KOC service lines would
be affected by the large road building programme that was underway.
Accordingly, a special technical committed was constituted t o produce a
document that would define KOC requirements t o ensure the protection and
maintenance of all KOC services t o be crossed by the motorways. In May
1979, the publication "Standard Rules and Regulations For The Protection
of KOC Services - Road and Motorway Crossings" was issued.
It had been obvious for sometime that there was a need for the
original document t o be revised and updated in the light of experience in its
application. A decision was taken to redraft the original specification as a
Company Standard.
ANYS E. RASHID
GEN. SUPDT. STANDARDS & INSPECTION DEPT.
February, 1983
KOC STANDARD 3 8 1 / 1 3 PT. 1
FOREWORD
INTRODUCTION
SCOPE
APPLICATION
COMMUNICATION SYSTEMS
5.1 CLASSIFICATION
INTRODUCTION
LINE CLASSIFICATION
GENERAL REQUIREMENTS
6.6.1 BRIDGING
6.6.2 CULVERTS
6.7 DIVERSIONS
7.1 INTRODUCTION
9. FINANCIAL ARRANGEMENTS
10. INTERCOMMUNICATION
1 1 . 2 NATIONAL CODES
Figure 1 - PIPE SUPPORTS 24 - 27
Figure 2 - TYPICAL CROSSING OF 28
PIPELINES WITH STANDARD CLEARANCE
A. 1 FAILURE PROBABILITY 31
A.4 SUMMARY
2. SCOPE
3. APPLICATION
5.1 CLASSIFICATION
KOC RESPONSIBILITY
INTRODUCTION
LINE CLASSIFICATION
6.2.1 P r i n c i ~ aLines
l
6.3.4 For all liquid hydrocarbon and gas lines, the preferred method
of protection is b y bridging or culverting. Accordingly, the Company
is prepared t o consider the diversion of certain lines t o permit their
passage through neighbouring culverts. Unless agreed otherwise all
principal lines shall be bridged or culverted.
I.P.G.
From 3 0 t o 60cm
( 12 t o 24in) 4km (2.5 miles)
From 3 0 t o 6 0 c m
( 12 t o 24in) 3 k m (1.8 miles)
6.6.1 Bridainq
6.6.2 Culverts
Main Culverts
(ii) Access
(b) Entry doors or access traps shall be sized t o permit the passage
of standard maintenance and inspection equipment as advised by
KOC.
(a) Minimum head room above top surface of pipe t o be 1m. (See
also "d" below).
(b) Minimum ground clearance beneath bottom surface of pipe t o be
500mm.
(c) Minimum side clearance between lines or a line and surrounding
structureb) t o be 5 0 0 m m . (See also "d" below).
DIVERSIONS
INTRODUCTION
8.1.2 The HCC shall ensure that all required and relevant safety
regulations and provisions are implemented t o the satisfaction of the
Company.
8.2.3 In the case of Gas or Vapour lines, uncased crossings will not
be permitted even on a temporary basis. These lines will require t o
be bridged, culverted or cased t o prevent traffic loadings being
transmitted t o the pipe walls.
9. FINANCIAL ARRANGEMENTS
Financial cover for all the costs arising to KOC that are directly
attributable to the construction of the highway shall be provided by
the Government Department initiating the work. The sums budgeted
shall be based on the protection standards defined in this
specification, unless authorised otherwise.
KOC will submit cost estimates for all the engineering works
for which it will take full responsibility to the Government Department
concerned for inclusion in the Project Budget.
10. INTERCOMMUNICATION
4. Units may be used without the bolted top cover if a pipe cradle only
is required. In this role, the supporting cradle may be simplified t o a
tubular section covering an arc of 140°, if desired.
In any particular application, the form and fixing of the sliding bearing
pads must be specified and the angle iron guides dimensioned t o suit.
'A'
-I
iPTl 'U'DIA.xV'LC.
DETAIL
(WELDED GUIDES)
HOLES TO S U I T
U3DIA.BOLTS.
1
1-
IlOLES TO SUIT
h t 1 2 UOL'I'S.
* S E E GENERAL NOTE 6 DETAIL
'F'
-I I- 'N' -
-
KUWAIT OIL COMPANY (K.S.C.)
FIGURE 1 SHEET 2
1 P I P E SUPPORTS
- --
PACP Nn ?El
During installation, the initial position of the moving support on the
bearing track must be correctly adjusted to permit the direction and
range of expansion movement anticipated to be accommodated.
7. In normal use, direct contact between the pipe and support clamp will
be avoided by the application of suitable, resilient sleeves or
wrappings appropriate t o the operating temperature. It remains the
responsibility of the Supervising Engineer to ensure that the diameter
of the clamp ring and the outer diameter of the sleeved or wrapped
pipe are such as will provide a secure fit. For general purposes, it is
suggested that an appropriate tolerance for the clamp ring would be:
10. Unless specified otherwise, all steel parts shall be given a good
quality paint finish suitable for the working conditions. For normal
applications, the steel shall be blast-cleaned to SA 2 % . For surface
temperatures not exceeding 150°C, t w o zinc Chromate priming coats,
giving a minimum, overall DFT of 5 0 microns, followed by an
aluminium top coats, or coats, giving a minimum DFT of 35 microns,
would be required.
DE'IAIL
(VELUED GUIDES)
7.5tE,5
--! I--
,f-FLAT BAR WELDED
TO 5Ox50x5RSA.
hi12 BOL'SS.
DETAIL
(BOLTED GUIDES)
-? 1-
7.51L,S
-
/- PLAT BAR WELDED
1'0 B l l \ t i u ~ l O R S A .
C. 'F'
-I (BOLTED GUIDES)
DE'I'AIL
(WEIJIED G U I D E S )
I1
-IIOLES T O SUIT
-
DETAIL 1124 BOLTS.
(DOibED GUIDES)
NOTES:
(A) UIMENSIONS SYhlhiETRICALLY DISPOSED
ABOUT VERTICAL CENTRE LINES UNLESS
1NI)ICA'I'ISD O'I'III:'ItIYISI?'.
I '9"
',I'
4 1 SEE OILAWING NOTE 'i.
SEE DRAWING NOTE 'C'
(F) NOMINAL IIEIGII'I' HAY IjE ADJUSTED U P OR
HOWN 'KO SUlrI' A I'k~IU'ICULAl? AIJIJL1CA'I'ION
I?' S I I O U I D NO'I' 11E INCREASED,IIOWEVER,
BY MORE THAN YO"/, WI'I'IIOUT T H E APPROVAL
O F 1'IIE SUPEIiVISING ENGINEER.
PIPE SUPPORT WITH FIXED BASE
(SEE DRAWING NOTES 'cS&'D') ( G l T H E LIh,iITING SIJAN FOR T H I S RANGE OF
P I P E SUPPORTS IS 10.lM.(33FT) UNLESS
AUTIIORISED OTHERWISE BY THE
SUPERVISING ENGINEEl{.
F- 1 ISSUE
8 0 0 TO 1 5 0 0 m m .
: DKCEbIBiR ,962
PACE NO. 27
I
$ EXISTING PIPELINE
*-*----
I
I iL GREATER
1 3 0 m m OR
LESS THAN
I MINIMUlvf DEPTH
750mm.
\ r-T------ 4 -,CABLE
1250mm.
---
-------------
'L- DUCT
A. 1 FAILURE PROBABILITY
INCIDENT SEVERITY
AND
APPENDIX '8'
STATEMENT OF INDEMNITY
permitting
t o proceed with its excavation and other
work on or in the vicinity of Kuwait Oil
Company services lines and other
property, I
for and on behalf of the
said shall take
full responsibility for the care of said
services lines and property and shall be
liable for and in respect of an indemnity
and keep indemnified Kuwait Oil
Company, its employees and agents
against all losses and claims for injuries
or damage t o any person or property or
in connection with any work taking place
as a result of this permit. Damages for
Loss of profit and loss of use by this
Company are excluded from this
indemnity.
Signature