Professional Documents
Culture Documents
Thermal Pation
Thermal Pation
From: Rohit K
Sent: Friday, March 28, 2008 9:48 PM
To: Srinivasan V
Subject: FW: TOTAL POWER PLANT NOTE...
Types of compounding:
1. Tandem compounding.
2. Cross Compounding.
In tandem compounding alternator coupled with same shaft, more than one
cylinder is present.
In Cross compounding more than one alternator is present, cylinder may be
more than one.
Q.Two turbines having different generating capacity, what is the main difference
between twos?
Ans: Only energy introduced to the turbine are different.
110 MW: (Less steam injected).
210 MW: (more steam injected).
Main three factors works on it: pressure, temperature, quantity.
In the pressure, temperature kept constant, only for different steam flow
rates are the different MW generation.(110 MW, 210 MW).
EFFECT OF EXCITION:
Q. What is fouling?
When static part and rotating part touches it is called Fouling.
Fouling in Turbine causes the turbine blade failure.
Q. Why Thrust Pads are should be softer than collar in Thrust Bearing?
Thrust pads are easy to replace from the system.
Difference in LMW AND KWU Turbine:
S LMW KWU
no
1 All Journal and Thrust bearings are One journal cum thrust bearing is
separate. present.
2 No of bearing: (2n+1), n= no of No of bearing: (n+1)
bearing.
3 Cross over present. Cross across present.
4 Bulky, bigger in size. Less in weight and portable.
5 Safety factors more. Safety factors less.
6 Russian made.(OLD) Germany made. (Modern).
7 Flange and stud heating are used. Flange and stud heating not used.
8 HP, IP are single flow. Only HP turbine is single flow.
Only LP Turbine is double flow. IP and LP turbine are single flow.
ANCHORING: It means fixing of total foundation of the system. In turbine total load
of cylinders and casing are carrying by leg to foundation.
Aim: 1.Coupling should be fixed in its position.
2. Generator magnetic centre is always unaltered.
Metallurgy of stator and rotor are changes with increase in temperature.
When rotor expanded it moves towards to Generator and disturbs the magnetic
center. Keeping this in mind Anchoring is introduced.
…………………………………………………………………………………………….
Q. Why Condenser are placed below the LP Turbine only, never below of IPT and
HPT?
Ans: After working of IPT and LPT some available energy remains in the system which
are finally comes for re-generation in condenser through LPT. Final available energy is
totally utilized in condenser i.e. below LPT.
DIFFERENTIAL EXPANSION:
DE is the difference of expansion between the rotor and casing.
Rotor is expanded more than stator.
The surface area to expose to steam is more for rotor than stator.
Rotor is total surrounded by steam.
Mass of rotor is less than mass of casing.
Positive Expansion: If the expansion of rotor is more than that of casing the DE is
positive.
Negative expansion: If the contraction of rotor is more than that of casing the DE is
known as negative expansion.
At the shorting of operation, only rotor expansion occurs, automatically DE
become positive.
At the time of tripping DE is negative due to contraction.
DE is an unavoidable phenomenon but keep it to permissible limit.
Different manufacturer have the different DE value.
Maximum permissible limit is 2.5mm to 3.5mm.
TURBINE CASING:
Single casing:
Double casings:
DE reduced.
Static parts are in inner casing.
It is use in high temperature operation.
For HPT casing and some stages of IPT is double casing, either we go for Flange
and Stud Heating.
LMW CASING:
KWU CASING:
To arrest the first growth of positive expansion Flange and Stud heating is used.
To arrest negative expansion rotor heating is used.
BLADE CONSTRUCTION:
Having uniform curvature is called impulse blading.
No pressure drops, only velocity drops.
Aim of impulse blade to grow the kinetic energy (1/2mv2).
In Reaction turbine pressure energy reduces and velocity of the outlet of the blade
gradually increases (goes up to around 2 Mac number i.e. around 680m/sec
=2×340m/sec).
Turbine blades are distribution is leveled in specification.
Q. What is the function of shroud?
Ans: Just cover the tip of the blade to avoid accident. First effect will come on the
shroud.
Total numbers of blades are depends on the diameter of rotor.
One row contains many blades (160-170 nos.)
By concept of double flow length of blades reduces (theoretically 50%).
Q. What is diapharm?
Diapharm is nothing but a holder of the nozzle only.
It is resting on the slot providing in the casing.
One row of blade, one row of nozzle, and one rows of diapharm are placed
simultaneously.
Diapharms are thin sheets of divergent convergent manner.
STEAM CHEST:
Almost like human chest.
Many numbers of nozzles are placed on the steam chest. Through steam chest steam is
uniformly distributed. These are two types: Full arc. Half arc.
CRITICAL SPEED: The speed at which the natural frequency of vibration of machine
queenside with the dynamic frequency due to speed, a resonance occur due to this. The
speed at which the resonance of vibration occurs is called critical speed.
Once the position of dynamic and natural frequency is in same phase, the resonance
occurs and critical speed comes.
Vibration occurs, damage found.
Critical speed range passed very fast.
ROLING OPERATION:
Generator will filled up with H2. At first air from generator purged by CO2 gas
and finally CO2 purged by H2 gas and hydrogen filled up to the generator.
At that time boiler totally oil supported because load fluctuate instantly.
ESP will not in service, as system is oil supported, brunt oil sticks the ESP walls.
Then we have to go for rolling that mean turbine speed will increase gradually.
Raise the turbine speed gradually up to 500 rpm, then wait for little time for
SHOCKING (shocking gives differential expansion less). Shocking time here
around 1 to 1 and ½ hours. When positive differential expansion exceeds 1, start
FLANGE and STUD heating. Then again check the Turbo-supervisory
parameters.
Again check Turbo-supervisory parameters. Then speed rises very fast for
overcoming the critical speed of turbine. Speed raise up to around 2900 rpm-2900
rpm (Just below the synchronous speed).
SYNCHRONISATION:
Voltage, Frequency, Phase are should be matched.
Q. Why turbine put on barring gear before rolling or before steam entering to
turbine at least 1 hour before?
Ans: check the straightness or other words eccentricity of turbine have to be checked.
Exhaust hood:
Ring spray is used for maintain exhaust hood temperature, by spraying cooling water.
Exhaust hood temperature: Normal exhaust hood temperature from exhaust hood
remains around 45C.
Q. If exhaust hood temperature increases, what happens?
Ans: Major part of LPT bearing is covers with exhaust hood. By conduction heat
transfer method bearing temperature increases, viscosity of oil for bearing will
decreases. Bearing temperature is here some permissible limit.
One thermocouple present for measuring the temperature.
In modern practice, starting ejector start first( starting ejector start sucking void
and air from the system), when pressure developed up to 50 mm of Hg , then
gland sealing comes in to action.
Both the side of main ejector charged, other wise vacuum will not developed
further.
Pressure now developed 540 mm of Hg column.
Start the HP/LP bypass system.
………………………………………………………………………………………
Q. Why HP evaporation line comes in to action at the starting condition?
Ans: At the starting condition, we have maintained vacuum in the HPT.
Initially IPT becomes vacuum because cross over present over it.
But for initially vacuum pulling in HPT one line (connection) is required known as
HP Evaporation line.
For providing leak of steam to the system at close condition a integrated hole is
present in the control sheet.
Only control valve no2 and 4 have such provision.
The leakage steam passes through turbine always (having pressure 1 ata) and also
bypasses at 1 ata pressure. Turbine rotor not able to rotate by this 1 ata pressure.
………………………………………………………………………………………..
2. To maintain or control steam pressure at preset value in main steam line during start
up.
3. To control the steam temperature down steam of HP bypass or the preset value.
4. To warm up the steam lines.
5. To dump steam from the boiler from the boiler in to condenser in case of the GB
open.
LP Bypass:
1. Control the steam pressure after re-heater.
2. Establish flow of steam from re-heat lines to opening of HP bypass valve.
3. Release the steam entrapped in HPT and re-heater circuit in case of generator
circuit breaker open.
LP/HP bypass system operation started after pressure raising 10-15
kg/cm2. Entrapped air removed.
Condenser must be in vacuum condition in case of HP/LP bypass system.
Condenser must be charged condition and some vacuum have developed by
ejector.
Condensation itself create vacuum. Automatically it sucks steam from LP
Turbine. So no need of ejector. But there is some problem.
When vacuum created, air try to enter the condenser system, air come into
condenser some what amount that is dangerous.
Charges LP bypass first then HP bypass.
By condensation steam sucked from LP/HP.
STD:
BFP OPERATION:
BFP and Booster Pump are coupled with a single motor.
Recirculation line: to safeguard of the BFP thermal distortion.
Temperature increase due to churning effect.
………………………………………………………………………………………………
BOILER CONTROL:
1 Pressure Fuel and Air
2 Steam temperature Spray water/ burner
tilting
3 Drum Level control Feed flow, Steam
Flow, drum level (3-
element control).
4 Furnace draft control ID fan inlet vane
control
5 Mill temperature Control Changing f cold and
Hot damper.
TURBINE CONTROL:
1 Speed Control Regulation of steam
flow by Governor.
2 Gland steam pressure Header. HDR pressure
controller regulates
HDR pressure taken.
3 Oil temperature Control By coil cooler/
regulating cooling
water. (35 C-45C).
4 Hot well Level control Level controller
controls the Hot well
level.
5 PRDS Control Pressure
controller/Temperature
Controller.
6 De-aerator level control By make up water
valve.
7 De-aerator pressure control Pressure controller.
GENERATOR CONTROL:
1 Voltage control Excitation Control
2 Stator current Load Control
3 Field current
4 Power Factor.
5 VAR
6 Frequency
7 Seal oil pressure control
8 H2 pressure Control
9 Stator water Control
………………………………………………………………………………………………
2. To check the boiler mountings or in order- e.g. safety valves (not gauged),
water gauge, Hydra step, Instrument Gauges are in working order.
3. Check that drum air vents are open and all other vents like SH, RH,
Atemperator must be kept open.
6. To check stop valves kept shut and its drains before and after kept open.
7. To check the particularly the water wall header/ bottom header drains are
in close condition.
9. To check the steam valves leading to steam coil in air heater which are in
close condition.
11. The inspection door, manholes and peepholes are kept open.
12. To ensure lubrication and cooling medium of rotary air heater. Its Electrical
and Pneumatic operation driving machines are ready.
13. Ensure that all auxiliary air and fuel air dampers are in working order.
14. Service water, bearing cooling water and pneumatic air and service air are
available.
15. Ensure that internal water reserve for boiler make up water and external
reserve for process cooling and circulating water are in optimum level.
16. To checks that boiler expansion indicators, Buck stay are indoor and to
check its indicating valves. Buck stay to be checked.
17. To check that through seal is filled with water and overflow line is okay.
18. To ensure that Auxiliary boiler is ready to supply the required steam.
6. Fuel oil trip and nozzles are closed. Scanner showing no flame.
Auxiliary Air damper on modulation and fuel oil dampers are closed.
These are the permissive of Purging.
10. Initiate to light up by warm up burners. Check that after firing Igniter
retracted.
11. Observe that oil recirculation valve closed and maintain oil pressure 5-
6kg/cm2 by oil control valve at the panel.
14. Charge the steam coil air heater (from neighboring unit steam supply or
from Auxiliary boiler) to raise air temperature to the extent of 70 Degree to
Air Heater inlet.
15. At about 2-3 Kg/cm2 drum pressure, close drum vents and other vents
like SH, attemperator, at pressure about 4-5 Kg/cm2.
16. Open the start up vents and ensure that final SH drain kept wide open.
17. Please be informed that firing rate is controlled to the extent of 30 Kg/cm2
to protect drum metal. After 30 Kg/cm2 –firing rate is controlled to protect
the metal of SH, RH.
18. Please note that rate of rise of saturation steam temperature must not
exceed 110 C/hour and boiler exit flue gas temperature must not exceed
535 C.
20. Add second group of oil guns and raise the pressure as per guide lines
given by the manufacturer.
4. Charge the PRDS after ensuring all the drains kept open.
10. Charge HP/LP Bypass system. Ensure that all drains of HP/LP Bypass
kept open before charging.
11. After a good amount of steam flow through HP/LP Bypass system, close
start up vent and shut SH drains.
14. With increase the firing rate Boiler Pressure would increase and the steam
would increase because of increase mass flow from boiler through HP/LP
Bypass system.
15. Please note that HP bypass pressure setting is to be kept 5% lower than
boiler pressure so as to keep continuous flow of steam through SH, The
temperature set point would be 50 Degree C higher than cold reheat
temperature. (The limiting temperature of HP Bypass is 380 C).
16. During heavy oil firing heavy oil firing temperature to be kept around 100
to110 C for efficient combustion.
22. Pay due attention on the performance of mill. To maintain ideal fuel air
ratio. Mill outlet temperature to be kept around 75 C to85 C. To keep
notice on the PA mill Differential so that mill neither be off loaded nor
plugged.
23. During cold starting of boiler, firing to initiate from lower elevation to get
uniform heat absorption for even expansion of the whole boiler.
3. After tripping, accept the annunciations and identify the cause of tripping.
4. Cancel the annunciation. Here we will find that only one annunciation is
persisting for which the unit got tripped.
5. The sequence of starting is the same like cold boiler starting. This is
mentioned below:
Rotary air heater----ID Fan------ FD Fan------Purge permissive
obtained-------- To purge the Boiler-------- After completion of Boiler.
7. Open the start up vent and maintained drum level and furnace draft.
10. To open the HP/LP Bypass system to get the required steam temperature.
For matching turbine metal temperature would be around 485 C.
11. When all the criteria pertaining to turbine rolling would be fulfilled, the
machine would be put on rolling and to be speeded up to full speed.
2. Should the boiler be required to shut down for its maintenance work, then
boiler pressure is to be reduced to the permissive limits of turbine
requirement by controlling fuel and steam flow.
4. Reduce coal feeder loading. Then reduce steam flow when pressure tends
to decrease.
5. Continue fuel reduction in all the running mills to the extent of 50 % fuel
reduction.
6. Provide all support at the top elevation. Adjust the PA differential to suit
coal air ratio. When CF loading reaches minimum. Shut the coal feeder
gate. Run the mill, until it get empty. Observe mill outlet temperature, mill
differential, mill ampere which would indicate that there is no coal left in
the mill.
7. Stop coal feeder. Stop mill. Switch of PA Fan and its inlet and outlet
dampers. Stop seal air fan.
8. Stop the successive mills (from top to bottom) one after another in the
similar way mentioned above.
9. Maintain drum level, steam temperature (By spray and burner tilting),
furnace draft and total airflow as per fuel flow.
15. Continue to run rotary air heater till flue gas temperature goes down to the
extent of 150 C.
18. Cut the scanner fans, igniters fan and seal air fan.
2. Turbine oil coolers to charge and the cooler would remain stand by and
would be used to control oil temperature and when required.
3. Air cooler and Hydrogen gas cooler to be kept ready and the water flow
would be established after synchronization.
5. Condensing system has been taken in service with CEP would run on
recirculation with normal hot well level.
6. DM water line to hot well has been loin up and make up should be
available when required.
7. Condensate line from hot well to de-aerator has made through by charging
LP heater and opening the valve before De-aerator.
8. Feed system from de-aerator to economizer inlet duly checked.
10. Bearing cooling water pump, acts pumps, and booster pump are in
service.
11. To check main oil tank level and drain valves operated on remote water.
12. Starting oil pump / AC oil pump put in service.
14. Emergency oil/ DC lub oil pump tested and the pump duly tested when lub
oil pressure apparently decreased from the relay(Oil pressure drop relay-
OPDR).
20. Main steam line drains, steam chest drains, stop valves and control valve
drains are kept wide open.
23. Gland sealing system and air extraction system checked with special
reference to vacuum breaker.
24. Governor has been duly operated to check the opening and closing of
ESV, control valve and interceptor valve.
3. Reheat pressure is kept around 6-8 Kg/cm2 and hot reheats steam
temperature to be kept around 260-300 C.
10. To reset the governor by closing both load limiting device and speeder
gear.
11. To observe auxiliary trip oil pressure, emergency oil pressure, governor oil
pressure.
14. Please note that in #1 1and 2, runways top valve is opened manually and
the steam admission is controlled either by manual operation runway stop
valve or by limiting device is controlled of to restrict the secondary oil
pressure.
15. To observed the speed rise and would have to maintain between 700-
1000 rpm.
18. To sock the turbine for heating flux stator and rotor.
2. To maintain vacuum.
12. Normalize the system following instructions given in cold start up.
…………………………………………………………………………………………..
Some times in power plant dangerous abnormal situation arise for which certain
measures need to be adopted quickly and precisely to control the situation.
Corrective actions are required to safe guard various equipments. Reliable and
faithful protection is there, yet the persons in charge of Power station would have
to rise to the occasion. It the system tends to go beyond controlling limits.
In every shift----
DG Sets to be tested.
DC Seal oil pump to be tested.
Battery to be tested.
Normally it is kept on floating by rectifier. Float changer and boost
changer to be tested.
(In many power stations turbine bearings got damaged during total power
failure due to no lub oil available at that at time.
4. FIRE HAZARD: Many power stations incurred heavy damage due to fire
hazard. One such victim is standing in Oaria power station (DVC).
Particularly in turbine house needs serious attention during fire. Activities:
a) To trip turbine, if not trips from fire protection device.
b) Ensure that only DC lub oil pump running.
High pressure oil lines must not be in changed condition. Flame
detectors inside battery house in control panel, to check its functioning.
Around turbine main oil tank and around transformer, sprinkler system should
be tested on mock trial method.
6. Turning gear or barring gear failure: When turning tuning gear fails to
rotate the machine. Then the uniform cooling of the rotor deviates. It’s a
result finding of the rotor can not be ruled out. In such situation, we should
checks the followings:------
a) Lub oil temperature and pressure.
b) Hot well level.
c) Undue chilling effect in glands.
d) Any interference in moving and static parts.
e) Fault in turning gear mechanism.
f) Loss of pressure in Jacking Oil system. (This is required in high
capacity machines).
Despite all parameters being made normal, if the situation
does not improve then rotate the shaft 90 degree manually with the help of crow
bar at an interval of half an hour till such time the problem be shorted out. Please
note that turbine rotor is treated hot till the MP casing top temperature does not
drop below 100C.
3. LOAD REDUCTION:
a) Partial b) House load c) Total Load
a) Partial load Reduction: This situation arises when one of the auxiliaries
trips (like ID, FD, PA, Mill, CF, condensate Pump, CW Pump, BFP). The
main effort would be to stabilize the system by controlling -----
Furnace draft.
Steam pressure and temperature.
Steam flow
Drum level
Feed Flow
Oil support.
C) Total load through off: Due to internal or external fault in generator breaker
opens, due to high system frequency turbine rejected load.
In such situation only Turbine would continue to run without any residential
load.
Main activity would be:
To control exhaust hood temperature by spray.
To control boiler parameter.
Activity:
To reduce firing rate to control pressure.
To increase spray flow.
To decrease total air if it was kept high.
If situation permits, take lower elevation mill.
9d) Steam temperature low:
Spray water flow high than required.
Sudden drop of boiler pressure.
Excess air flow low.
Lower elevation mill run.
Deposit over SH and RH element.
Ideal feed temperature not available.
ACTIVITY:
Boiler pressure kept optimum.
Spray flow to control if it becomes high.
Total air flow to increase after checking the O2 meter.
Shoot blowing of SH and RH are carried out.
When steam temperature is very low, then and there stop
the Turbine.
ACTIVITY:
To decrease steam flow.
Provide oil support.
Control the fuel on manual mode.
Establishing at the burner mouth start another mill.
To keep on eye on drum level and in steam temperature.
9f) FURNACE DRAFT HIGH:
Off the two, any one ID fan tripped.
Problem in suction or discharge damper.
Ideal fuel air ratio not maintained.
Combustion disturbed and there is delayed combustion.
Checks the dampers on flue path.
Check the regulation of the inlet vane control.
Check outlet damper.
Reduce air flow.
Control air fuel ratio.
When ever such situation occurs, momentarily reduce fuel and
air flow.
In some stations there are some interlocks in both ID and FD
fans. In such system furnace does not get pressurized or
depressurized.
ACTIVITY:
Reduce steam temperature.
Increase load.
To wait to stabilize the expansion.
ACTIVITY:
Increase steam temperature.
Hold the load.
To wait till rotor expansion start increasing.
Normally DE deviates during starting of cold machine. Here
rotor expansion become +ve. During starting of hot machine DE is
becomes –ve.
This problem is best tackled by ideal choice of steam
temperature and by steam flow variation.
REASON:
If casing drains, steam lines and extraction lines drains remain open
during power generation.
Improper draining and excess draining cause casing temperature
difference.
The problem may also occur, it causing drains remain open during
power generation.
Improper lagging also causes the problem due to uneven heat
dissipation.
Ingress of water through extraction line is also the source of problem.
To increase the top half temperature, steam flow to increase.
Maximum temperature difference not to exceed by 20 C.
ACTIVITY:
To check the lub oil pressure and its temperature.
To check the bearing oil outlet temperature.
To check the oil strainer pressure difference.
In every thing is normal, and then it is available to trip the
machine before it exceeds the operating limits.
NB (Bearing metal temperature must not exceed 90C.) One thing
should be borne in mind that sudden rise in bearing temperature is not
caused by shortage of lubricant. So never try to run the machine when
bearing temperature rises suddenly.
EFFECT:
Vibration will increase.
Noise( Unusual)
MEASURES:
To follow the ideal operational procedure.
Drains of casing and steam lines to keep wide open before starting cold
turbine.
Sufficient shocking time to give.
TO KEEP LUB OIL TEMPERATURE NORMAL.
To keep normal bearing temperature.
To keep on barring gear for long time.
To run turbine 3-4 hours at low speed.
………………………………………………………………………………………
1. Before starting oil system check whether the main oil tank is full of oil.
3. Open oil cooler inlet valve and charge the oil cooler, after opening the de-
aerator vents.
6. Isolate one oil cooler by closing down inlet and outlet valve.
7. Keep the other two coolers in service by keeping the inlet and outlet valve
open.
10. Check whether lub oil heater, drain valve in close condition.
11. Start ac EOP and charge the lub oil line slowly by opening. After attaining 1
ata of lub oil pressure, open the delivery valve fully and start oil vapor exhauster
fan immediately.
12. Keep the suction and delivery valve of dc EOP fully open.
15. Put oil centrifuge in operation (With heater if required) to raise the oil
temperature to minimum to 35C.
16. Keep the water inlet and outlet valve of oil coolers in fully close
condition. Also keep the seal oil coolers isolated on water side (charged and
when required).
17. Put the ac seal oil pump in service, switch on the seal oil pump supply to
keep it on stand by.
18. Pressurised the generator with air at 500 mm of water column or with H2
as specified in the manual.
19. Start the CW pump and charge the condenser after keeping the vents fully
open. Monitor the condenser pressure of cooling water at pump water.
20. Switch on the supply of the barring gear motor and JOP. Check the lamp
indication.
The bearing temperature recorder in UCB should be switch on. Check
whether the instruments for oil pressure and temperature are available in UCB.
21. Start JOP after ensuring that lub oil valve for barring gear is open fully.
23. a) Ensure fully engagement of the barring gear, which will be the identical by
the pointer which swings to vertical position with fully engagement.
b) In case of engagement is not full, then put the handle to the square
head and rotate it downward ‘CLOCKWISE’ and confirm full engagement.
g) Follow the barring temperature carefully and observe for an unusual noise
on the center machine. In such case barring gear have to be stopped. Do not
flash the boiler without turbine being on barring gear.
24. Check the hot well level and start the condensate extraction pump and put
in recirculation.
25. Fill up de-aerator to required level and put the CEP in recirculation.
26. Checks for all conditions on feed pump availability and keep the pump.
27. Start BFP and put it in recirculation. Now boiler can be flashed only if all
protections of turbine are checked and found healthy.
28. Open all the drains on piping’s. The following valves should be checks.
Steam to ejector line drain ----open fully.
Staring/ Main ejector exhaust Fan ----open fully.
HP gland steam line drain ----open fully.
LP gland steam line drain ----open fully.
HP flash tank line to sump ----open fully.
HP flashes tank line to sump ---- to atmosphere.
HP gland steam Askania valve----- Close Fully.
MP gland steam Askania valve ----- Close Fully.
LP gland steam Askania valve ----- Close Fully.
Bypass line to HP/LP valve----- Close Fully.
MS drain valve---- Open.
HRH drains ----open fully.
MS dynamic separator drain ----open fully.
HRH dynamic separator drain ----open fully.
All E3 expander drain----open fully.
All E2 expander drain----open fully.
Turbine HP drains to flash tank ----open fully.
Expander to condenser ----open fully.
LP Heater (3, 4, and 5) drain to sump----- Closed.
29. Charge PRDS and maintain 11 ata and 6 ata header purpose.
30. Open starting ejector steam valve slightly and warm up the line, after 15 mm
open, the steam valve fully.
31. Start chimney steam exhauster fan with open delivery and closed suction,
keep the fan running with closed suction.
32. Open air valve of staring ejector and note the raise in vacuum.
33. All 100 m Hg vacuum, start sealing the gland. Seal the LP gland first and
then the HP glands and maintain the pressure of about 300 mm WC.
34. Open the suction valve of chimney steam exhaust fan and maintain vacuum
will be attained by opening the suction valve, by about 3-4 turns and not more.
35. Check weather the ‘amperes’ of Chimney steam exhaust fan is less than 6
amps.
36. Prepare for cutting in the main ejector in the Main Ejector, Open the steam
valve of M.E. slightly and maintain a pressure of about 2kg/cm2 immediately
open the first stage and second stage boiler.
37. Open the front drains and check whether the 1 st stage and second stage
drain for the remaining half ejector are in close condition.
40. Close the starting ejector air valve after attaining a vacuum of about 0.85
kg/cm2.
42. Charge re-heater after checking for the fully opening of re-heater vents.
43. Charge main steam and open the electrically operated valve fully.
45. As re-heater and MS line are charged, observe the rise of temperature on the
turbine causing temperature recorder and flange to pipe differential on differential
temperature recorder.
46. Reset the turbine and warm up the HP control valve chambers.
47. Achieve the MS and RS parameters such that the steam temperature is at
least 50C higher than metal temperature.
48. Maintain steam pressure of about 50 kg/cm2 and 9 kg/cm2 reheat pressure.
51. Check whether all the lamp indication for the driving system is not glowing.
53. Check whether the control gear oil pressure is about 10 kg/cm2.
54. Check whether the dc supply is ON for protection circuit and supply is ON for
relay magnet.
58. Check whether LUB OIL PRESSURE before barring gear is above 1kg/cm2.
60. Turn the divider right. Check whether the dividing lamp glowing.
61. Bring back the divider to natural position. Check whether the divider lamp
goes off after some time lag.
62. Similarly turn the divider to left and perform the test. Divider should always be
in natural position.
65. Check whether the SECONDARY OIL PRESSURE gauge starts reading and
it should be in between 0.3 to 0.5 kg/cm2.
66. Check physically whether all FOUR QUICK CLOSING VALVE are in full open
position.
67. Check whether all the CONTROLL VALVE AND INTERSEPTING VALVES in
full open (Confirm by pressing the testing magnet provided in each valve).
68. Check whether barring ear continues to run with engaged condition.
69. After the completion of pipe line warming up, slowly rotate the limiter handle
in anti clock wise direction till the secondary oil pressure increase to 0.7/0.9
kg/cm2.
70. Check whether the interceptor valve (right and left) open little by pruning the
test magnet.
71. Check whether the speed of turbine increased above baring gear speed and
the barring gear.
73. Rise in the secondary oil pressure slightly above but not exceeding 1 kg/cm2
by opening the limiter handle and observe the speed rise.
74. Maintain the same speed achieved, if it is in between 500-700 rpm as per the
time indicated in starting curve.
75. Increase the secondary oil pressure to 1.10 kg/cm2 by the limiter and check
whether CV-1&2 opened and CV-3&4 are in close condition.
76. Observed the speed rise and keep the secondary oil pressure constant to
warm up the MS line.
77. Maintain the speed between 1200-1300 rpm 1s per starting curve.
78. Gradually raise the speed by limiter and cross the critical speed.
80. Check whether main oil pump has taken over at 2700rpm. (Confirmed
discharge is 9.0-9.5 kg/cm2 pressure gauge.
81. While crossing above 2900 rpm the secondary oil pressure may start
dropping slowly.
82. Check whether speed is 2930 rpm after complete rotation of limiter in anti
clockwise direction.
83. Raise the speed to 3000 rpm by rotating the SPEED CHANGER.
PROTECTION OF BOILER:
Boiler lock out relay will be energized through FSSS.
1. Loss of 220 Volt DC supply to FSSS.
2. Less than fire ball.
3. Loss of ac supply to any elevation.
4. Fuel supply cut off.
5. Loss of flame.
6. Very low drum level -175 mm of Water column.
7. Very high drum level +175 mm of Water column.
8. Furnace pressure high/low +200mm water column / -200 mm water
column.
9. Air flow less than 30%.
10.Boiler load less than 10%.
11.Both ID and FD tripped.
12.Re-heater protection-Furnace outlet temperature more than 540 C and
there is no flow through Re-heater.
PURGE PERMISSIVES:
1. No boiler trip.
2. Air flow not less than 30%.
3. Drum level normal.
4. AC/DC supply available.
5. All trip valve and nozzle valves of fuel oil are close condition.
6. Scanner showing no air flame.
7. ID and FD fan are running.
8. All mills, PA fans are off and all hot air and cold air damper are
shut.
Loss of fuel trip will energize MFR through FSSS if following conditions
are not fulfilled-
a) AC supply to FSSS available.
b) Three igniters are on.
c) Igniter trip valve close.
d) Heavy oil trip valves and nozzle valves close.
e) Warm up oil trip valve close.
…………………………………………………………………………
…………………………………………………….
PERMISSIVES AND TRIPPING OF ID, FD, PA Fans, Mills,
COAL FEEDER:
SEQUENTIAL INTERLOCK:
Rotary Air heater……..ID…….FD…….SAF…….PA
Fan…….Mill……….CF.
Permissive: trip valves and nozzles valves.
a) Oil pressure normal 10kg/cm2, nozzle valves closed, no boiler
trip, purge completed.
b) Tripping: Oil pressure low(1.5 kg/cm2), nozzle valve open.
Differential pressure between steam and oil is low, oil
temperature low (-100 C).
HO recirculation valve opening permissive--- N&T valve
closed.
TRIPPING OF PULVERISER:
1. PA Fan if trips.
2. Boiler if trips.
3. Lub oil pressure low.
4. Motor overload protection acts.
5. PA pressure falls below 650mm of water column.
6. Mill outlet valves if close.
7. Ring compression pressure (Nitrogen pressure for loading the ring)
becomes low.
Boiler trip is Energized through MFR (through FSSS) give signal to shut
down sequence of boiler.
Spray valves of SH and RH valve closed.
A) SOP: (20 kg/cm2). SOP trips when turbine speed reaches to 2800rpm and
INJECTOR-I pressure is greater than 3kg/cm2.
Multistage/ Centrifugal:
MOP Intake (INJECTOR-I, reduces to pressure to 1 kg/cm2).
GS
Bearing Header (INJECTOR-II, after lower pressure 3 kg).
B) Start to suck oil when turbine speed reaches 2800rpm.
C) MOP: Its discharge pressure 20kg/cm2, 1500 rpm, Single stage centrifugal pump.
GS
Bearing header (INJECTOR-II, pressure: 3kg).
D) LOP (AC): Whenever header pressure reduced to 0.6 kg/cm2 the LOP (AC) will
start.
LOP (AC), 3 kg-----------OIL COOLER----------BEARING HEADER.
LOP (DC) start when there is any Load shedding or OIL header pressure becomes
below 0.5 kg/cm2 in spite of running LOP (AC).
E) OPDR------0.6 kg/cm2 (AC LOP)---------0.5 kg/cm2 (DC LOP/Power
off)------------0.3 kg/cm2( Trip the turbine).
H) JOP: Its discharge pressure is 120 kg/cm2. It has 8 discharge ports. Gear pump is used
here.
………………………………………………………………………………
……..
Switchyard layout diagram…
For 110MW and 210 MW Power Plant…