PADDING STONE REPAIR SCHEDULE

No Pier No. Mileage Treatment February

9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 P112 DK134+563.7 TIM BOBOK 1 TIM BESI + BEGISTING + COR 1

2 P113 DK134+596.46 TIM BOBOK 2 TIM BESI + BEGISTING + COR 2


Bobok Habis & Cor Ulang
3 P114 DK134+629.23 TIM BOBOK 3 TIM BESI + BEGISTING + COR 3

4 P115 DK134+662. TIM BOBOK 1 TIM BESI + BEGISTING + COR 1

5 P129 DK135+119.95 TIM BOBOK 1 TIM BESI + BEGISTING + COR 1


Bobok Habis & Cor Ulang
6 P130 DK135+144.65 TIM BOBOK 2 TIM BESI + BEGISTING + COR 2

7 P131 DK135+169.36 TIM BOBOK 3 TIM BESI + BEGISTING + COR 3

8 P132 DK135+202.08 TIM BOBOK 1 TIM BESI + BEGISTING + COR 1


Bobok Habis & Cor Ulang
9 P133 DK135+226.8 TIM BOBOK 2 TIM BESI + BEGISTING + COR 2

10 P134 DK135+251.53 TIM BOBOK 3 TIM BESI + BEGISTING + COR 3

11 P146 DK135+644.55 TIM BOBOK 2 TIM BESI + BEGISTING + COR 2

12 P153 DK135+873.53 Bobok Habis & Cor Ulang TIM BOBOK 3 TIM BESI + BEGISTING + COR 3

13 P154 DK135+906.23 TIM BOBOK 1 TIM BESI + BEGISTING + COR 1


Chipping Area Base Plate
14 P162 DK136+160.02 TIM BOBOK 1
Bearing
15 P200 DK137+364.51 TIM BOBOK 1 TIM BESI + BEGISTING + COR 1

16 P211-1 DK137+716.91 TIM BOBOK 2 TIM BESI + BEGISTING + COR 2


Bobok Habis & Cor Ulang
17 P211-2 DK137+743.81 TIM BOBOK 3 TIM BESI + BEGISTING + COR 3

18 P230 DK138+377.19 TIM BOBOK 2 TIM BESI + BEGISTING + COR 2

19 P270 DK139+663.45 TBD TIM BOBOK 3 TIM BESI + BEGISTING + COR 3