Main River Flood and Bank Erosion Risk Management Program JFPR - ADB - BWDB

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 218

Technical Assistance Consultant’s Report

Project Number: 44167-012


December 2013

Bangladesh: Main River Flood and Bank Erosion Risk


Management Program
(Financed by the Japan Fund for Poverty Reduction)

Prepared by Northwest Hydraulic Consultants, Canada

In association with Resource Planning and Management Consultants Ltd., Bangladesh

For Bangladesh Water Development Board

This consultant’s report does not necessarily reflect the views of ADB or the Government concerned, and
ADB and the Government cannot be held liable for its contents. (For project preparatory technical
assistance: All the views expressed herein may not be incorporated into the proposed project’s design.
Government of the People's Republic of Bangladesh
 
Bangladesh Water  
Development Board 
 
 

 
Project Preparatory Technical Assistance No. 8054 BAN
 

Main River Flood and Bank Erosion
Risk Management Program

Final Report, Annex F
Design Issues

September 2013

In association with

Resource Planning
& Management
Consultants Ltd.
Asian Development Bank 
Funded by the Japan Fund for Poverty Reduction 

 
Government of the People’s Republic of Bangladesh 
Bangladesh Water Development Board 
 

Project Preparatory Technical Assistance 8054 BAN 

Main River Flood and Bank Erosion 
Risk Management Program 
 

 
Final Report, Annex F 
Design Issues 
 
September 2013 
 
 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
 
 
 
 
 
 
 
 
Document Status 
 
Title:  Designs Issues,  Annex F

  Annex F1 
Geotechnical Investigations 
Principal Author:  Ahsanul Jalil Khan 
Contributions:   
  Annex F2 
Technical Designs for Tranch‐1 Work 
Principal Author:  Mukhles uz Zaman 
Contributions: 
Final version:  August  2013 
 
 
 
 
 
Document Development 
Draft Final  June 2013   
Final  R1, 15 August 2013 Justify  and page setup 
  R2, 21 August 2013 Combined F1 & F2 two doc files and 
page setup 
  R3, 28 August 2013  Inserted Two Appendix 
  R4, 01 September 2013  Format cover page and header and 
footer 
  R5, 22 September 2013  Checked for final print 

  R6, 30 September 2013 Added Annexures page  

  R7, 28 February 2014 Reprinted R6

Reviewed by:     
 
 
 

 
Page ii  September 2013 
F1 Geotechnical Investigations 
 
 
 
 
MAIN REPORT 
 
 
ANNEXES 
 
Annex A  Priority Sub‐reach Selection & Sub‐reach Descriptions 
    Annex A1  Priority Sub‐reach Selection 
    Annex A2  Sub‐reach Description 
Annex B  Background Data 
    Annex B1  National Water Resources Database 
    Annex B2  Socio‐economic Data 
    Annex B3  Surveys and Field Visits 
Annex C  Institutional and Financial Assessment 
Annex D  Hydrology and Flood Modelling  
Annex E  River and Charland Morphology and River Engineering 
Annex F  Design Issues 
    Annex F1  Geotechnical Investigations 
    Annex F2  Technical Designs 
Annex G  Economic Feasibility 
    Annex G1  Project Cost 
    Annex G2  Economic Assessment 
Annex H  Implementation and Procurement Planning 
Annex I  Social Gender Equity Strategy & Action Plan 
Annex J  Environmental Impact Assessment  
Annex K  Involuntary Resettlement 
    Annex K1  Resettlement Framework 
    Annex K2  Resettlement Plan  
 
 
 
 
 
 
 
 
 
 
 

 
  Page iii 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
 
 
 
 
 
 
 
 
 
Page iv  September 2013 
 

Asian Development Bank 
Funded by the Japan Fund for Poverty Reduction 

 
Government of the People’s Republic of Bangladesh 
Bangladesh Water Development Board 
 

Project Preparatory Technical Assistance 8054 BAN 

Main River Flood and Bank Erosion 
Risk Management Program 
 

Final Report, Annex F1 
Geotechnical Investigations 
 
September 2013 
 
 
 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
 

 
Page vi  September 2013 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

 
Table of Contents 
 
1  Introduction ................................................................................................................................... 1 
1.1  Background ........................................................................................................................................ 1 
1.2  Geo‐technical Investigation ............................................................................................................... 2 
2  Study sites with and Soil Data ........................................................................................................ 3 
2.1  Borehole Location .............................................................................................................................. 3 
2.2  Field and Laboratory Tests ................................................................................................................. 7 
2.3  Discussion of Results ........................................................................................................................ 10 
3  Sub‐Soil Profile ............................................................................................................................. 11 
4  Embankment stability: ................................................................................................................. 16 
4.1  Introductory Remarks ...................................................................................................................... 16 
4.2  Stability analysis ............................................................................................................................... 17 
4.3  Settlement (of foundation soil beneath embankment) ................................................................... 18 
4.4  Check for seepage flow .................................................................................................................... 20 
4.5  Check for horizontal sliding/pore water pressure within the embankment ................................... 20 
4.6  Stability against Earthquake/Check for liquefactions ...................................................................... 21 
5  Riverbank Stability ....................................................................................................................... 22 
5.1  Data and calculation method ........................................................................................................... 22 
5.1.1  Slope angles and Soil characteristics .................................................................................... 22 
5.1.2  Calculation method ............................................................................................................... 23 
5.2  Calculated Scenarios ........................................................................................................................ 24 
5.2.1  Existing Riverbank ................................................................................................................. 24 
5.2.2  Designed river bank .............................................................................................................. 25 
5.3  Summary and Conclusion ................................................................................................................ 28 
6  Summery RBP .............................................................................................................................. 29 
6.1  General Geotechnical features ........................................................................................................ 29 
6.2  Flood embankment stability ............................................................................................................ 29 
6.3  Riverbank Protection ....................................................................................................................... 29 
7  References ................................................................................................................................... 30 
 

 
   

  Page vii 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
 
List of Tables 
 
Table 2‐1: Location, Bore‐hole depth & coordinate with ground and ground water elevations (Koizuri‐
Hurasagar section) ....................................................................................................................................... 3 
Table 2‐2: Location, Bore‐hole depth & Coordinate with ground and ground water elevations (Chouhali‐
Nagarpur section) ........................................................................................................................................ 5 
Table 2‐3: Location, Bore‐hole depth & Coordinate with ground and ground water elevations (Jafarganj‐ 
Bachamara section) ..................................................................................................................................... 5 
Table 2‐4: Location, Bore‐hole depth & Coordinate with ground and ground water elevations 
(Enayetpur‐Koizuri section) ......................................................................................................................... 6 
Table 2‐5: KH‐4 Field and Corrected SPT (N’) .............................................................................................. 8 
Table 2‐6: KH‐9 Field and Corrected SPT (N’) .............................................................................................. 8 
Table 2‐7: KH‐40 Field and Corrected SPT (N’) ............................................................................................ 8 
Table 2‐8:  JB‐2 Field and Corrected SPT (N’) ............................................................................................... 8 
Table 2‐9: CN‐10 Field and Corrected SPT (N’) ............................................................................................ 9 
Table 2‐10: CN‐13 Field and Corrected SPT (N’) .......................................................................................... 9 
Table 2‐11: EK‐5 Field and Corrected SPT (N’) ............................................................................................. 9 
Table 2‐12: EK‐10 Field and Corrected SPT (N’) ......................................................................................... 10 
Table 5‐1: Results of the calculation for existing Slopes ............................................................................ 24 
Table 5‐2: Case 1‐ 19 m river bed .............................................................................................................. 26 
Table 5‐3: Case 2‐  39 m river bed ............................................................................................................. 26 
Table 5‐4: Results of calculation for designed slopes ................................................................................ 27 
 
 
Figures 
 
Figure 1‐1 (a&b): Typical Sections of Proposed Flood Embankment ............................................................ 2 
Figure 2‐1: Satellite Image of Project Location ............................................................................................. 6 
Figure 2‐2: Satellite Image of Bore‐Hole Location ........................................................................................ 7 
Figure 3‐1: Bore Hole Log of Koizuri‐Hurashagar (KH) ................................................................................ 12 
Figure 3‐2: Bore Hole Log of Enayetpur‐Koizuri (EK) .................................................................................. 13 
Figure 3‐3: Bore Hole Log of Chauhali‐Nagarpur (CN) ................................................................................ 14 
Figure 3‐4: Bore Hole Log of Jafarganj‐Bachamara (JB) .............................................................................. 15 
Figure 5‐1: Profile of the cross sections at the Jamuna River right bank ................................................... 22 
Figure 5‐2: Profile of the cross sections at the Jamuna River left bank ...................................................... 22 
Figure 5‐3: Safety factor for 35m slopes  Figure 5‐4: Safety factor for 15 m slopes .......................... 23 
Figure 5‐5: Dimensions of existing slopes ................................................................................................... 24 
Figure 5‐6: Typical slip circles at an existing slope ...................................................................................... 25 
Figure 5‐7: Slope dimensions of designed slopes ....................................................................................... 26 
Figure 5‐8: Safety factor for 35m slopes  Figure 5‐9: Safety factor for 15m slopes ........................... 26 
Figure 5‐10: Typical slip circles at a designed slope.................................................................................... 27 
Figure 6‐1: Comparison designed slope to existing river profile ................................................................ 30 
 
 
 

 
Page viii  September 2013 
F1 Geotechnical Investigations 
 

1 Introduction 

1.1 Background 
The  Asian  Development  Bank  (ADB)  is  undertaking  a  feasibility  assessment  of  a  flood  and  riverbank 
erosion  risk  management  program  covering  parts  of  the  main  rivers  of  Bangladesh  financed  by  the 
Japan Fund for Poverty Reduction (JFPR). The objective of the Main River Flood and Bank Erosion Risk 
Management  Program  (MRP)  is  to  reduce  the  riverbank  erosion  and  flood  risks  to  the  adjacent  flood 
plains  while  maximizing  economic  activities  in  a  sustainable  and  environmentally  acceptable  manner.  
Existing flood embankments dominantly fail from riverbank erosion, and as such the stabilization of the 
river pattern is a cornerstone of reducing the flood risk.  The MRP builds on and extends the activities of 
the Jamuna‐Meghna River Erosion Mitigation Project (JMREMP) (ADB, 2002), implemented in different 
phases from January  2003 until  June 2011.  In addition, a  similar project, the Assam Integrated Flood 
and  Riverbank  Erosion  Risk  Management  Investment  Project  (AIFRERMIP;  ADB,  2010)  provides 
important  insight  into  a  number  of  relevant  project  elements  and  processes  especially  integrating 
disaster risk management measures related to flood and riverbank erosion risk management under the 
dictate of the Integrated Water Resources Management (IWRM) framework.   
 
Subsequent to the preliminary assessment of geo‐technical aspects certain analytical evaluations have 
been  made  in  order  to  obtain  important  and  relevant  geo‐technical  parameters.  The  presentation  of 
these parameters is basically on the assumption of fairly uniform sub soil strata and their properties and 
characteristics generally observed in the locality. 
 
The main objective of present study is to formulate parameters for feasibility design of stability of the 
proposed flood embankment/levy/ dykes with some hydraulic structures having regulatory functions. 
 
The  report  also  includes  study  and  design  (stability)  for  River  Bank  protection  measures  separately  in 
the later section. 
 
The following basic data/ information were used as guide line for preliminary analysis of stability – 
(a) HFL – 100 years frequency in Brahmaputra Jamuna 
               50 years frequency in Boral and Hurasagar 
(b) Ground level along the alignment of the proposed embankment 
(c) Geo‐technical data – 
  i) Bore holelogs 
  ii) Field‐lab test results  
  iii) BWDB data  
  iv) Results of PIRDP of JMREMP investigation and analysis  
(d) Proposed options for typical x‐sections of embankment as shown in Figure 1.1. 
 
The comments and observation received from BWDB design office were answered through a note on 
Design Criteria as Appendix‐IV and Comments and Observance as Appendix‐V in Annex F2. 
 
 
 
 

 
  Page 1 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
Typical Cross section of Embankment ( Height- 5m)

Shoulder
Verge
1
Carriage width 1.5
1 2
3
Sand fill
0.75 1.5 5.5
1 3.5
2.5

Sand fill 60 cm excavated

15.0 3.2 3.0 10.0 8.75


39.95
 
 
Typical Cross section of Embankment ( Height- 5m)

Shoulder
Verge
1.0 Temporary Shelter
1
Carriage width 1.5
1
2
2
0.75 1.5 5.5
4.0 1 Sand fill 1 3.5
2
2.5

Sand fill 60 cmexcavated

10.0 8.0 2.0 3.2 3.0 10.0 8.75


44.95
 
 

Figure 1‐1 (a&b): Typical Sections of Proposed Flood Embankment 
 

1.2 Geo‐technical Investigation 
It  is  essential  to  understand  the  nature  and  behavior  of  the  soil  forming  the  river  bank  and  also  bed 
materials for the development of a bank protection work. In the present report relevant geo‐technical 
aspects are studied for analysis of flood embankment along the river bank, some distance apart from 
the existing bank. However, it is to be noted though that the anticipated failure modes of river bank are 
(a) erosion of soil due to wave and/or river current and sliding of slope due to instability induced by bed 
erosion or undercutting below water level. These modes of failure may take place where slope angle is 
not  consistent  with  geo‐technical  conditions  prevailing  at  the  site.  A  soil  exploration  program  was 
therefore  undertaken  to  investigate  the  sub  soil  condition  at  the  selected  project  sites  for  main  river 
flood embankment and bank erosion risk management program. 
 
Accordingly, for the preliminary project formulation and feasibility study; a number of bore‐holes were 
explored through the Ground Water Hydrology Division of BWDB, during November 2011 to February 
2012. 
 
   

 
Page 2  September 2013 
F1 Geotechnical Investigations 
 
2 Study sites with and Soil Data 

2.1 Borehole Location 
 At  right  bank  of  river  Jamuna,  40  Bore  Holes  (BH)  designated  as  KH‐1  to  KH‐40,  at  Koizuri  to 
Hurasagar and Bherakhola to Baghabari port in Sirajganj District. 
 At right bank of river Jamuna, 14 BH designated as EK‐1 to EK‐14, from Enayetpur to Koizuri in 
Sirajganj district. 
 At left bank of river Jamuna, 19 BH designated as CN‐1 to CN‐19 from Chouhali to Nagarpur, in 
Tangail District 
 At left Bank of river Jamuna, 10 BH designated as JB‐1 to JB‐10 from Jafarganj to Bachamara in 
Manikganj District.  
 
Depth of Bore‐hole, locations with co‐ordinates are shown in Table 2.1 and Bore Hole (BH) locations on 
Satellite image with co‐ordinates are shown in Figure 2.2. 
 
Table 2‐1: Location, Bore‐hole depth & coordinate with ground and ground water elevations 
(Koizuri‐Hurasagar section) 
District  Koizuri– Coordinates Upazila Depth  Gr. Elv.  GWT
Hurasagar (KH)  (m)  PWD(m)  PWD(m)
KH1  N24°10´33.6´ E 89°41'28´´ Shajadpur 30 10.34  3.25
N673456  E468943 
KH2  N24°10´21.8´´ E 89°41'17´´ Shajadpur 20 10.25  3.85
N673090  E468625 
KH3  N24°10´04.0´ E 89°41'17´´ Shajadpur 30 10.16  2.87
N672550  E468627 
KH4  N24°9´54.5´´ E 89°41'07´´ Shajadpur 20 10.12  2.998
N672252  E468333 
KH5  N24°9´45.0´´ E 89°40'53´´ Shajadpur 30 10.35  3.28
N671963  E467922 
KH6  N24°9´31.9´´ E 89°40'42´´ Shajadpur 20 9.94  2.64
N671558  E467628 
KH7  N24°9´18.1´´ E 89°40'31´´ Shajadpur 30 10.17  3.28
N671136  E467305 
KH8  N24°9´04.9´´ E89°40'23.5´´ Shajadpur 20 10.35  2.64
Sirajganj 

N670710  E467096 
KH9  N24°8´52.6´´ E89°40'10.8´´ Shajadpur 30 10.15  3.28
N670348  E466732 
KH10  N24°8´39.7´´ E89°40'0.7´´ Shajadpur 20 9.45  3.125
N669947  E466434 
KH11  N24°8´26.9´´ E89°39'57.0´´ Shajadpur 30 10.27  2.64
N669550  E466428 
KH12  N24°8´09.8´´ E 89°40'2.6´´ Shajadpur 20 10.25  2.69
N669044  E466490 
KH13  N24°7´53.1´´ E89°39'58.3´´ Shajadpur 30 10.11  2.82
N668530  E466365 
KH14  N24°6´37.6´´ E89°39'56.9´´ Shajadpur 20 10.05  2.52
N668043  E466328 
KH15  N24°7´20.5´´ E89°39'55.9´´ Shajadpur 30 10.09  2.82
N667521  E466301 
KH16  N24°7´03.7´´ E89°39'52.5´´ Shajadpur 20 9.81  2.52
N667010  E466215 
KH17  N24°6´48.5´´ E89°39'46.9´´ Shajadpur 30 9.43  2.95

 
  Page 3 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
District  Koizuri– Coordinates Upazila Depth  Gr. Elv.  GWT
Hurasagar (KH)  (m)  PWD(m)  PWD(m)
N666539  E466038
KH18  N24°6´33.0´´ E89°39'52.7´´ Shajadpur 20 10.03  2.69
N666063  E466191 
KH19  N24°6´16.4´´ E89°39'01.6´´ Shajadpur 30 10.13  3.115
N665587  E466322 
KH20  N24°6´01.5´´ E89°40'09.4´´ Shajadpur 20 10.06  2.69
N665098  E466464 
KH21  N24°5´47.6´´ E89°40'14.0´´ Shajadpur 30 10.11  3.125
N664665  E466674 
KH22  N24°5´33.3´´ E 89°40'.0´´ Shajadpur 20 10.07  2.62
N664196  E466808 
KH23  N24°5´14.5´´ E89°40'12.0´´ Shajadpur 30 9.87  3.125
N663669  E466759 
KH24  N24°5´04.0´´ E89°40'01.0´´ Shajadpur 20 9.68  2.69
N663313  E466428 
KH25  N24°4´51.6´´ E89°39'55.4´´ Shajadpur 30 9.49  3.125
N662933  E466278 
KH26  N24°4´36.3´´ E89°39'46.6´´ Shajadpur 20 9.56  2.515
N662476  E466023 
KH27  N24°4´20.4´´ E89°39'39.4´´ Shajadpur 30 8.58  3.1
N663669  E466759 
KH28  N24°4´30.4´´ E89°39'24.8´´ Shajadpur 20 7.72  3.4
N662300  E467148 
KH29  N24°4´38.5´´ E89°39'15.1´´ Shajadpur 30 7.45  3.45
N662565  E465128 
KH30  N24°4´45.6´´ E89°38'56.8´´ Shajadpur 20 7.51  2.49
N662763  E464624 
KH31  N24°5´57.2´´ E89°38'33.7´´ Shajadpur 30 9.25  2.82
N663120  E464140 
KH32  N24°5´08.1´´ E89°38'22.3´´ Shajadpur 20 7.95  3.1
N663461  E463652 
KH33  N24°5´20.4´´ E89°38'04.0´´ Shajadpur 30 9.15  2.72
N663831  E463136 
0KH34  N24°5´31.7´´ E89°37'46.9´´ Shajadpur 20 8.31  2.82
N664180  E462651 
KH35  N24°5´44.2´´ E89°37'29.0´´ Shajadpur 30 9.05  3.15
N664568  E462148 
KH36  N24°4´59.8´´ E89°37'11.5´´ Shajadpur 20 8.11  2.95
N665062  E461656 
KH37  N24°4´09.2´´ E89°39'35.4´´ Shajadpur 40 9.07  3.18
N661642  E465689 
KH38  N24°5´34.0´´ E89°39'58.5´´ Shajadpur 40 10.01  3.25
N662408  E466347 
KH39  N24°5´01.2´´ E89°40'21.4´´ Shajadpur 40 10.12  3.10
N663225  E466960 
KH40  N24°5´05.0´´ E89°40'26.1´´ Shajadpur 40 9.81  3.1
N664214  E465417 
 
   

 
Page 4  September 2013 
F1 Geotechnical Investigations 
 
Table 2‐2: Location, Bore‐hole depth & Coordinate with ground and ground water elevations 
(Chouhali‐Nagarpur section) 
District  Chouhali‐ Coordinates Upazila Depth  Gr. Elv.  GWT
Nagarpur  (m)  PWD(m)  PWD(m) 
CN‐1  N24°18´07.3´´ E89°47´42.8´´ Omarpur 40 12.74  3.1
CN‐2  N24°17’38.2´´ E89°48´38.7´´ Norshinghopur 40 12.07  3.1
CN‐3  N24°17´08.9´’ E89°48´20.2´´ Dholabari 40 12.12  3.1
CN‐4  N24°16´44.2´´ E89°47´56.6´´ Kachua 40 11.63  3.1
CN‐5  N24°16´11.2´´ E89°47´51.4´´ Kachua 40 11.07  3.1
CN‐6  N24°15´42.5´´ E89°48´21.6´´ Degreehogra 40 12.14  3.1
CN‐7  N24°15´08.6´´ E89°48´19.5´´ Degreehogra 40 12.6  3.1
CN‐8  N24°14´32.2´´ E89°48´21.2´´ Alokdia 40 12.19  3.05
CN‐9  N24°14´00.0´´ E89°48´25.0´´ Alokdia 40 12.15  3.41
Tangail 

CN‐10  N24°13´29.4´´ E89°48´33.6´´ Ichapara 40 12.1  3.25


CN‐11  N24°12´56.6´´ E89°48´46.9´´ Rashidpur 40 12.07  3.56
CN‐12  N24°12’22.9´´ E89°48´55.3´´ Rashidpur 40 12  3.43
CN‐13  N24°12´14.2´´ E89°47´10.1´´ Chalchar 40 10.9  3.71
CN‐14  N24°11´40.7´´ E89°47´13.5´´ Misrogati 40 10.84  3.56
CN‐15  N24°11´07.6´´ E89°47´26.1´´ Dhalpakhla 40 11.11  3.25
CN‐16  N24°10´33.1´´ E89°47´33.1´´ Mahmoodpur 40 11  3.41
CN‐17  N24°09´58.8´´ E89°47´39.6´´ Mahmoodpur 40 11.02  3.1
CN‐18  N24°09´22.9´´ E89°47´42.7´´ Dolai 40 10.8  3.41
CN‐19  N24°08´45.7´´ E89°48´53.4´´ KhasKaulia 40 10.9  3.71
 
Table 2‐3: Location, Bore‐hole depth & Coordinate with ground and ground water elevations 
(Jafarganj‐ Bachamara section) 
Distric Jafarganj‐  Coordinates Upazila Depth  Gr. Elv.  GWT
t  Bachamara  (m)  PWD(m)  PWD(m)
JB1  N23°53´24.2´´  E89°45´42.3´´ Shibaloy 40 10  4.64
JB2  N23°53´58.4´´  E89°45´21.6´´ Shibaloy 40 9.2  3.71
JB3  N23°54´49´´  E89°45´43.2´´ Daulotpur 40 9  4.01
JB4  N23°55´40.2´´  E89°45´47.5´´ Daulotpur 40 8.5  3.76
Manikganj 

JB5  N23°56´8.2´´  E89°46´4.1´´ Daulotpur 40 8.6  3.168


JB6  N23°57´8.4´´  E89°46´25.7´´ Daulotpur 40 10  3.84
JB7  N23°57´56´´  E89°46´33.4´´ Daulotpur 40 8.8  3.86
JB8  N23°58´33.6´´  E89°46´33.8´´ Daulotpur 40 9.5  4.01
JB9  N23°59´17.4´´  E89°46´17.2´´ Daulotpur 40 10.2  4.47
JB10  N23°59´31.5´´  E89°45´29.8´´ Daulotpur 40 8  4.62
 
 
 
 
  Page 5 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
Table 2‐4: Location, Bore‐hole depth & Coordinate with ground and ground water elevations 
(Enayetpur‐Koizuri section) 
Enayetpur‐ Gr. Elv.  GWT
District  Co‐ordinates  Upazila  Depth 
Koizuri  PWD(m)  PWD(m)
EK‐1  N24°11´28.2´´ E89°41´52.7´´ Enayetpur 40 10.35  3.48
N675136  E475667 
EK‐2  N24°21´08.2´´ E89°42´02.7´´ Enayetpur 40 10.51  3.33
N676359  E469903 
EK‐3  N24°12´43.9´´ E89°78´26.4´´ Enayetpur 40 10.19  3.61
N677461  E470567 
EK‐4  N24°13´17.4´´ E89°71´48.8´´ Enayetpur 40 10.62  3.56
N678488  E471148 
EK‐5  N24°13´58.7´´ E89°43´42.59´´ Enayetpur 40 10.81  3.56
N679750  E571495 
EK‐6  N24°14´37.5´´ E89°43´20.3´´ Enayetpur 40 10.22  3.4045
N680954  E472095 
EK‐7  N24°15´06.1´´ E89°44´47.9´´ Enayetpur 40 10.2  3.43
Sirajganj 

N682100  E473722 
EK‐8  N24°15´14.8´´ E89°45´18.1´´ Enayetpur 40 10.83  3.1
N683100  E475306 
EK‐9  N24°15´47.8´´ E89°45´14.1´´ Enayetpur 40 10.37  4.045
N684073  E475702 
EK‐10  N24°16´19.2´´ E89°45´28.1´´ Enayetpur 40 10.45  3.15
N685034  E475907 
EK‐11  N24°16´50.5´´ E89°45´35.2´´ Enayetpur 40 10.89  3.43
N686075  E476154 
EK‐12  N24°17´24.2´´ E89°45´43.8´´ Enayetpur 40 11.17  3.56
N687047  E476074 
EK‐13  N24°18´32.00´´ E89°45´34.8´´ Enayetpur 40 11.47  3.25
N688150  E475901 
EK‐14  N24°19´21.8´´ E89°45´26.4´´ Enayetpur 40 11.64  3.125
N689701  E475667 
 

 
Figure 2‐1: Satellite Image of Project Location 

 
Page 6  September 2013 
F1 Geotechnical Investigations 
 
 

 
Figure 2‐2: Satellite Image of Bore‐Hole Location 

2.2 Field and Laboratory Tests 
Sub‐soil  investigation  conducted  in  field  presents  bore‐hole  logs  with  ground  level  (GL),  Standard 
Penetration  Tests  (at  every  1.5  meter)  and  stratification  with  lithological  description.  Laboratory  test 
results  include  grain  size  distribution  curves,  atterberg  limit  tests,  consolidation  parameters,  natural 
moisture  contents,  specific  gravity,  density  test  with  OMC  maximum  dry  density,  unconfined 
compression  (U.C)  tests  and  unconsolidated  undrained  (U.U)  triaxial  compression  tests.  Very  brief 
analysis has been made on the result of the above soil investigation reports and some salient feature 
are  presented  in  Tables  2.5  ‐  2.12.  Observation  and  findings  of  previous  investigations  and  study 
conducted under JMREMP in 1992, 1993 and also during 2001 and 2006 were reviewed in the present 
study. 
 
  Page 7 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
Soil constituents (with some parameters) 
 
Table 2‐5: KH‐4 Field and Corrected SPT (N’) 
Depth (m)  C (%)  M (%)  S (%)  Soil Types NMC 
2    70  30  M+FS 0.045 0.009    
5    58  42  CL/ML+FS 0.06 0.01    
7.5    7  93  FS 0.14 0.008    
9    7  93  FS 0.14 0.008    
12.2    8  92  FS 0.135 0.09    
15    8  92  FS 0.149 0.074    
18.3    4  96  FS 0.147 0.085    
 
Table 2‐6: KH‐9 Field and Corrected SPT (N’) 
Depth (m)  C (%)  M (%)  S (%)  Soil Types NMC 
2    66  34.1  SANDYSILT +NP+ML 0.04 0.005    
3    56  44  VFS+MC+NP 0.08 0.006    
7.5    11  89  FS 0.14 0.065    
10    14  86  FS 0.125 0.060    
15    6  94  FS 0.13 0.090    
18.3    8  92  FS 0.125 0.08    
23    6  94  FS 0.140 0.075    
30    4  96  FS 0.149 0.090    
 
Table 2‐7: KH‐40 Field and Corrected SPT (N’) 
Depth (m)  C (%)  M (%)  S (%) Soil Types NMC 
2    88  12 CL+ML 0.01 0.0015  
3    68  32 ML+CL 0.045 0.0092  
5    48  52 ML+FS 0.08 0.0175  
4    18  82 FS 0.10 0.04  
11    16  84 FS 0.125 0.05  
15    15  85 FS 0.125 0.06  
23    8  92 FS 0.140 0.08  
30    16  84 FS 0.12 0.06  
40    2  98 FS 0.149 0.092  
 
Table 2‐8:  JB‐2 Field and Corrected SPT (N’) 
Depth (m)  C (%)  M (%)  S (%) Soil Types NMC
1.5  44    56 0.08  
3  42    58 CH 0.085  
5    30  70 FS+M 0.095  
6    12.1  89 FS 0.15  
6.7    14  86 FS 0.135  
10    9  91 FS 0.163 24.16  2.66 
12    9  91 FS 0.155 24.96  1.66 
15    10  90 FS 0.155  
18.6    9  91 FS 0.155  
23    9  91 FS 0.155  
26    9.5  90.5 FS 0.163  
30    12  88 FS 0.149  
36    12  88 FS 0.155  
 
 
 
Page 8  September 2013 
F1 Geotechnical Investigations 
 
Table 2‐9: CN‐10 Field and Corrected SPT (N’) 
Depth( m)  C(%)  M (%)  S (%) Soil Types NMC 
2    75  25  ML(NP) 0.045 0.01  
3‐4    76  24  ML(NP) 0.037 0.007  
5    72  28  ML+SP 0.04 0.01 20.43  2.665 
6.5    76  24  ML+SP 0.045 0.01 12.1  2.663 
10    14  36  ML 0.155 0.06  
8    78  22  ML 0.0455 0.009  
12.5    70  30  FS 0.052 0.009  
15    10  90  FS 0.18 0.08  
20    30  70  FS 0.12 0.025  
23    28  72  FS 0.125 0.03  
26    10  90  FS 0.18 0.075  
30    9  91  FS 0.175 0.08  
35    8  92  FS 0.18 0.085  
 
Table 2‐10: CN‐13 Field and Corrected SPT (N’) 
Depth (m)  C (%)  M (%)  S (%) Soil Types NMC 
2  74    26 ML 0.04 0.009  
3.5  72    28 ML(NP) 0.052 0.012  
4.5  76    24 ML 0.046 0.009  
6.5  30    70 FS 0.13 0.025  
10  25    75 FS 0.125 0.04  
12  24    76 FS 0.125 0.04  
15  24    76 FS 0.130 0.05  
20  16    84 FS 0.12 0.055  
25  4    96 FS 0.21 0.12  
27  6    94 FS(SP) 0.2 0.10  
30  18    82 FS(SP) 0.125 0.05  
35  16    84 FS(SP) 0.14 0.05  
38  18    82 FS(SP) 0.135 0.055  
 
Table 2‐11: EK‐5 Field and Corrected SPT (N’) 
Depth (m)  C (%)  M (%)  S (%) Soil Types   NMC 
1.5    47  53  FS+M+NP 0.08 0.025  
3    66  34  ML+FS 0.058 0.018  
5    66  34  M+FS 0.058 0.018  
6.5    14  86  FS 0.156 0.06  
8    12  88  FS 0.152 0.10  
10    10  90  FS 0.149 0.07  
11    4  96  FS 0.14 0.092  
12.5    6  94  FS 0.17 0.088  
13.7    4  96  FS 0.125 0.088  
15    2  98  FS 0.135 0.092  
18.5    4  96  FS 0.149 0.085  
22    6  94  FS 0.125 0.08  
24.7    8  92  FS 0.155 0.085  
30    2  98  FS 0.152 0.10  
35    2  98  FS 0.149 0.093  
38    2  98  FS 0.155 0.095  
40    2  98  FS 0.149 0.095  
 
 

 
  Page 9 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
Table 2‐12: EK‐10 Field and Corrected SPT (N’) 
Depth (m)  C (%)  M (%)  S (%) Soil Types   NMC 
1.5    8  92 FS 0.22 0.09  
4.5    2  98 FS 0.149 0.092  
10.5    2  98 FS 0.175 0.10  
12.5    6  94 FS 0.156 0.088  
15    4  96 FS 0.149 0.095  
20    4  96 FS 0.152 0.088  
25    6  94 FS 0.154 0.085  
30    4  96 FS 0.149 0.09  
35    6  94 FS 0.140 0.083  
40    4  94 FS 0.149 0.09  
NOTE:  C= Clay minerals  M= Silt  S= Sand  VFC= Very fine sand 
  FS= Fine sand  NP= Non‐Plastic  ML= Silt low plastic  CL= Clay low Plastic 
  CH= Clay High Plastic  MH= Silt High Plastic 
 

2.3 Discussion of Results 
The BWDB undertook fairly comprehensive sub‐soil investigation all along the proposed alignment for 
flood  embankment  and  river  bank  protection  works.  The  Geotechnical  investigation  performed  by 
BWDB  will  time  bound  program  (carried  and  hurriedly)  resulting  in  some  uncertainties  about  the 
accuracy  of  the  findings.  But  as  mentioned  earlier,  the  sub  soil  composition  in  the  project  location  is 
generally  uniform.  However,  subsoil  data  obtained  and  used  in  the  analysis  appear  to  be  reasonably 
consistent with the past reports and results. Further, it is expected the factor of safety provided would 
compensate for local and general uncertainties  
 
Further due to large distances between the bore‐holes (300m to about 400m), it may be worthwhile to 
undertake  a  limited  number  of  additional  bore‐holes  before  finalizing  the  design  of  embankment  for 
some specific locations only. 
 
 
 
 
 
   

 
Page 10  September 2013 
F1 Geotechnical Investigations 
 
3 Sub‐Soil Profile 
 
Figure  2.2  shows  the  Bore‐hole  from  4  (four)  locations  referred  earlier.  Detailed  bore‐hole  logs  are 
shown in Figure 3.1‐3.4. In each location (KH, EK, CN, JB) It is seen that the upper part of the soil (i.e. 
generally on average above RL +4.00 m PWD) is mostly silt and clay (CL, ML) type with varying quantities 
of fine to very fine sand (Non‐cohesive). This strata is underlain by very fine to fine sand (non‐cohesive) 
with little to trace silt and mica. The above feature is also evident in Table 2‐1  from the plot of  and 
  against  depth  for  different  Bore‐holes  (Presented  in  Tables  2.5‐2.12).  The  SPT"N"  Values  for 
different Boreholes with corrected “ ” values are presented in Appendix 2, Tables A2.1 to A2.4.  
 
The following observation can be highlighted: 
 
 The sub‐surface soil formation consists of two layer system. 

 In general in all four section, the upper layer consists of fine grained soil of low to inter‐mediate 
plasticity  with  few  exceptions  where  in  it  is  referred  to  as  plastic,  semi‐plastic  or  even  non‐
plastic (upto above  EL+4 to+5m PWD). Broadly Classified as CL‐ML type soil 

 The  lower  part  (i.e.  below  +4  to  +5m  PWD)  mainly  consists  of  very  fine  to  fine  to  medium 
grained  sands  upto  depth  of  exploration.  Very  thin  films  of  mica  mineral  in  traces  were  also 
encountered at varying depths. 
 
 
   

 
  Page 11 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 

 
Figure 3‐1: Bore Hole Log of Koizuri‐Hurasagar (KH) 
 
 
Page 12  September 2013 
F1 Geotechnical Investigations 
 

 
Figure 3‐2: Bore Hole Log of Enayetpur‐Koizuri (EK) 
 
 
 
 
 
 
 

 
  Page 13 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 

 
Figure 3‐3: Bore Hole Log of Chouhali‐Nagarpur (CN) 
 
 
 

 
Page 14  September 2013 
F1 Geotechnical Investigations 
 

 
Figure 3‐4: Bore Hole Log of Jafarganj‐Bachamara (JB) 
 

 
 
   

 
  Page 15 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
4 Embankment stability 

4.1 Introductory Remarks 
The  project  areas  are  located  in  the  delta  of  large  rivers  the  Jamuna,  a  part  of  Brahmaputra  river 
system, and the Padma. The terrain is formed by the river sediments of the flood plains. The channels 
frequently shift sideways due to erosion of the river banks or concentrate their discharge in other river 
channels. The river sediments consist of finely grained sand of medium compactness. The sand in all the 
project  sites  originate  from  the  Himalayan  Mountains  and  therefore  consist  of  minerals,  quartz, 
feldspar, rock fragments, trace heavy mineral and mica. 
 
The amount of mica varies at different depths, which are rather inconsistent. Previous documents and 
study  reports  in  the  same  region  suggest  mica  content  from  30%  to  50%  in  some  places.  The  recent 
BUET  studies  however  put  the  figure  between  7%  to  11%,  which  seems  to  be  reasonable  [Special 
Report‐22 (Geotechnical) of Jamuna‐Meghna River Erosion Mitigation Project, Part‐B, November 2006]. 
These  river  sediments  are  more  or  less  horizontally  layered  with  a  very  small  inclination  of  layers  in 
downstream  direction.  The  mica  minerals  and  the  others  particles  have  a  more  stocky  shape.  The 
sedimentation of quartz, feldspar and heavy minerals is much faster than mica minerals. It is observed 
from  previous  studies;  the  mica  minerals  form  a  very  thin  film  of  impermeable  layer  above  more 
compact minerals. 
 
A  generalized  summary  of  drilling  at  the  project  locations  show  a  upper  clay‐silt  or  silt‐clay  layers 
referred to in the this report as CL‐ML (often found to be CH‐MH) which consists of silt clay / clayey silt 
with  low  to  medium  plasticity.  Below  the  upper  clayey  layer  fine  grained  and  poorly  graded  sand, 
referred  to  as  SP/SM  or  FS,  sometimes  very  fine  sand,  VFS  of  medium  compactness  are  present.  The 
sand strata has a general trend of mild increase in density from medium to dense becoming very dense 
at depth around 30m and below.(As evident from BH‐Logs showing SPT plots in Figure 3.1‐3.4. 
 
Geo‐technical  slope  failure  in  clay  is  commonly  calculated  by  circular  failure  planes.  Which  means 
during  failure  rotation  takes  planes.  Sand,  however,  shows  more  or  less  straight  failure  planes; 
therefore translation may take place in case of failure. 
 
Due  to  cohesion,  clay  is  able  to  stand  vertically  up  to  a  certain  depth,  where  as  pure  sand  without 
cementation will not remain stable under normal condition. In a state of low humidity (slightly moist) 
the sand may have a small cohesion due to capillary action which disappears when it is dry or saturation 
is above 70% or so. This apparent cohesion can therefore be considered for calculation of  an existing 
slope, but surely not for new construction. It may be noted that this part of the report deals with new 
flood  protection  embankment  fairly  close  to  existing  river  banks.  In  the  present  study  with  regular 
flooding of the terrain apparent cohesion may be introduced in stability analysis. At lower levels (higher 
depth), due to lithification of salts cementation may result in a low effective cohesion. 
 
The clay  layer on the  surface of  the terrain  is considered  sufficiently resistant.  In  view  of  its effective 
shear strength (without any reduction factor) the clay is able to stand vertically up‐to a certain height 
(around 4m or so). It is to emphasize though that in the case of slope failure, the excess of the stability 
of clay cannot be transferred or related to improve the stability of the sand layer below. 
 
The  survey  carried  during  previous  study  observed  that  the  slopes  for  the  upper  clay  layer  was  fairly 
steep and derived magnitude of unconfined compression strength was found to be Cu=30‐40 kpa. BUET 
study conducted during 2004 also appears to confirm this value. 
 
The observed slope inclination at river in sand is found to be 1:2.5‐1:3 for about 50% of the project area 
which  is  expected  with  limit  equilibrium  condition.  The  angle  of  internal  friction,  which  is  the  shear 
strength of sand in these case, are  28 ‐ 30  with very low effective cohesion estimated at c=2‐4 kpa.  
 
 
Page 16  September 2013 
F1 Geotechnical Investigations 
 
In  view  of  the  uncertainties  associated  with  the  effect  of  cohesion  at  this  stage,  it  is  ignored  in  the 
stability  analysis  as  shown  in  the  later  illustrations.  The  lower  strata  below  the  fine  grained  clay  silt 
formulation predominantly consist of sand (fine sand with little to trace silt) and occasional Mica. The 
layer  generally  is  of  medium  density  as  evident  from  interpretation  of  standard  penetration  'N'  test 
values. There  is mild trend of increase  in density with increase in depth.  Further below the density  is 
found to be medium dense to dense becoming very dense usually below 30‐35m depth of exploration. 
The  above  observation  appears  to  agree  favorably  with  BUET  Report  including  earlier  reports  of 
JMREMP and FAP (Halcrow Feasibility) Studies and those of Jamuna Bridge etc. 
 

4.2 Stability Analysis 
On  the  basis  of  above  information  and  geotechnical  investigation  carried  out  by  BWDB,  some 
preliminary  stability  analysis  may  be  made  for  the  proposed  flood  protection  embankment  and  bank 
erosion.  The  slope  protection  and  erosion  control  of the  vulnerable  river  bank  is not  considered here 
and are addressed separately at a later stage.  
 
For the purpose of analysis the following assumptions are made: 
 Assume dredged fill material for embankment construction 
 Embankment height 4m‐ 6m (i.e. 5m on average)  
 Compacted fine sand with angle of internal friction  =28 to 30_use 30 
 Embankment slope: 1:3 and 1:2.5 
 A factor safely fs≥ 1.4 has been considered as standard in line with previous project designs for 
river bank stability (PIRDP). 
 
Assume: 
 Dredged soil from river bed 
 River bed material mainly fine sand/ very fine sand with silt/ silty fine sand/ silt with very fine 
sand occasional at shallow depths. 
 The Feature of predominant fine particles is observed at shallow depths (5‐7m). 
 Compacted fill material have angle of internal friction φ=28‐30 
 Slope angle  , i.e. slope is 1:3, 1:2.5 and 1:2, considered for trial. 
 
Under normal conditions: Factor of safety (f) against failure  
tan 
f
tan 
,    Dredged fill soil
f = FS = Factor of Safety   
Ø   28° min. to 30°, use 30°     β 5m  
 
For Ø 28°    For Ø 30° 
Slope 1:3,   Slope 1:3,
f = tan 28°/ tan 18.43° = 0.532/0.33= 1.6  f = tan 30°/tan 18.43° = 0.577/0.333 = 1.7 
Slope 1:2.5,  Slope 1:2.5, 
f = tan 28°/tan 21.80° = 0.532/0.40 = 1.33  f = tan 30°/tan 21.80° = 0.577/0.40 = 1.44 
  Slope 1:2, 
f = tan 30°/ tan 26.57° = 0.577/0.50 = 1.15 
 
Under Submerged Condition 

f 
 sub
 tan 

8 * 0.577
 0.778  1.25
 sand
 tan  18 * 0.33
 

 
  Page 17 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
Assumed: 
ɣ 10 /  
 
ɣ 18 /  
 
ɣ_ 8 / ^3 
 
Therefore seepage will occur under submerged condition. 
 
From the above analysis, it would appear that under normal conditions slope provision of 1:3 and 1:2.5 
are  adequate.  Protective  measure  against  seepage  flow  will  be  required  for  construction  of 
embankment considering the fact that the only material available cheaply and in abundant quantity is 
very  fine  sand  with  little  to  some  silt/clay.  It  may  be  mentioned  that  the  upper  layers  of  soil 
stratification  consists  of  plastic  to  semi  plastic  silt  or  clay  upto  about  4m‐7m  with  same  variation  in 
some  locations  as  can  be  seen  in  the  sub‐soil  profile.  It  may  also  be  mentioned  that  most  of  the 
proposed  project  segments  are  fairly  close  to  the  river  bank  and  some‐time  even  within  (which  is 
locally)  known  as  char  areas;  Further  check  for  any  significant  difference  between  the  East  bank  and 
West  bank  was  attempted.  No  significant  difference  was  observed  regarding  sub‐soil  and  soil 
characteristic between east or west side locations being studied. 
 
At  this  stage,  under  the  circumstances  discussed  above  the  proposed  embankment  configuration 
considered from stability and safety consideration can be silty fine sand material with clay‐cladding all 
around as shown in Figure 1‐1. 
 
It is also proposed to consider slope of the embankment as 1:3 as the preferred option. However, it is 
also  possible  to  use  different  slopes  at  riverside  at  the  second  option  for  the  flood  embankment 
configuration as shown in Figure 1‐1.  
 
Considering  that  seepage  may  occur  under  submerged  condition,  clay  on  both  ends  (river  side  and 
country side) should be used in order to protect the embankment from scour and erosion and also to 
retain the finer materials from the embankment. The thickness of the cladding be provided should not 
be less than 60cm (preferably 1m). The material shall be clay silt with very fine sand (trace/little) which 
should  have  a  plasticity  index  of  10‐20%  in  accordance  with  AASHTO  T90.  The  core  material  shall  be 
spread  in  layers  not  exceeding  200mm  loose  and  compacted  by  means  of  suitable  equipment  as 
specified (minimum 95% modified proctor). 
 
A few other aspects of stability of the embankment are analyzed below: 
 

4.3 Settlement (of foundation soil beneath embankment) 
Assuming an average height of embankment‐ 5m 
Slope: 1:2.5 
 
Analysis  from  bore‐hole  logs  and  field  &  laboratory  test  results  tends  to  show  susceptibility  of 
settlement of the embankment sub‐soil formation. The upper layer generally consists of soft low plastic 
clayey‐silt upto a depth of about 4‐7m. Underlain by fine sand with little to no trace of silt which appear 
to continue below upto the depth explored (30m). Some typical geotechnical properties are considered 

 
Page 18  September 2013 
F1 Geotechnical Investigations 
 
for  estimating  probable  settlement  of  the  compressible  layer  underneath  the  proposed  flood 
embankment. 
 
Relevant properties:  
° 0.85 (Initial void ratio) 
Saturated unit weight of soil,ɣ 17.5 / ≅ 18 /  
Submerged Unit weight of soil,ɣ 7.5 / ≅8 /  
Specific gravity of Sand,  2.66 
Compression Index,  0.28 
Coefficient of compressibility,  4 10 /  
Depth of Compressible layer  6m 
30% 
 
18 x 6 108 /  
 q at said‐height =  78 /  
° 17.5 3 54 /  
0.28 54 78
3.0 100 17.6 
1 .85 54
If 1m of top soil is removed/ replaced by compacted:   
0.28 54 78
2.5 100 14.5 
1 .85 54
 
Case‐2 * 
(0.15 2 2.74 100 ≅ 13.1  
° 0.9 
0.28 
2.67 
29.5% 
17.5 5 87.5 
ɣ 17.5 /  
ɣ 7.5 /  
4 10 /  
Estimate for time for consolidation to    and   
0.197 2.5 100 1
35.63  
4 10 60 60 24
0.848 2.5 100
.1157 153 50%, 0.195 
4 10 3600 24
90%, 0.848 
 
The estimated settlement in a condition (h=5cm) is found to be 17.8 cm (average) considering drainage 
from  top  and  bottom  (double  drainage).  But  when  about  1m  of  top  soil  is  removed  and  replaced  by 
quickly  draining  sand,  the  effective  depth  (thickness)  of  compressible  layer  is  reduced  where  in  the 
consolidation settlement becomes 14.4 cm (average). 
 
Similarly  with  embankment  height  (including  freeboard)  of  6m  and  the  thickness,  if  top  compressible 
soil  underneath  is  7m,  the  gross  settlement  becomes  17.36  cm.  Considering  double  drainage  and 

 
  Page 19 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
replacement of 1m of top soil by compacted fine sand, settlement is reduced. These are elaborated in 
sample calculation presented. In addition time for consolidation i.e. and  are also shown. 
 
It would appear from analysis, that considering stage construction (2/3 stages), assuming an allowance 
(consolidation  time,  at  least  up‐to  35‐50  days),  a  total  of  maximum  150  days  will  be  necessary  for 
consolidation  of  full  height  of  embankment  over  a  given  stretch  of  embankment.  Important  here  to 
mention that the above assessment is based on the following considerations 
 
a. Each stage compacted height is 2‐2.5 m 
b. For clay cladding method of construction will follow benching/key type technique at side slopes. 
c. Compressible layer below embankment base is 5‐7 m 
d. Settlement  evaluation  is  based  on  parameters  either  assumed  or  guide  line  reference  from 
limited Laboratory test results available. 
 

4.4 Check for seepage flow 
Assuming,  clay  cladding  is  used  as  protection  against  erosion  due  to  seepage,  possibility  of  seepage 
through underneath the embankment base will be checked. As a first step it is proposed to remove 60 
cm‐100 cm top soil to be replaced by sand (compacted). 
 
According to Terzaghi, minimum width of base should be embankment height (H) times creep ratio (cw). 
The value of creep ratio is taken as 7, according to table 58.1 of Soil Mechanics in Engineering practice 
by Terzaghi, Peck and Mesri, 3rd edition, 1995. 
 
Width minimum = 5m *7 =35 m 
Width provided in two options is greater than 35m. 
 
Provision of compacted sand fill (100 cm) underneath the embankment is also expected to take care of 
seepage pressure substantially and induce flow line towards the toe. 
 

4.5 Check for horizontal sliding/pore water pressure within the embankment 
Earth pressure developed (Drag force):F 0.5 18 6 K ≅ 120KN  
Frictional Resistance force at base along base of triangle  “abc”  
R 0.5 6 2.5 6 17.5 0.42 ≅ 338KN ≫ 120KN  
 
In  order  to  assess  the  stability  of  the  embankment  for  rapid  draw  down  effect  on  the  river  side,  a 
further detailed analysis will be made once more site specific hydrological data are available. 
 
However, the  provision  of clay‐cladding  along with  sand  fill  underneath the  base  of the  embankment 
should adequately bring down the flow (works) line towards the toe‐line. The overall total width of the 
embankment in expected to reduce significantly the little seepage force that may develop.  
 
 
 

 
Page 20  September 2013 
F1 Geotechnical Investigations 
 
4.6 Stability against Earthquake/Check for liquefactions 
The  sand  layer  below  the  upper  clay  layer  consists  of  fine  and  poorly  graded  (sp)  sand.  Sand  of  such 
composition  is  susceptible  to  liquefaction.  Liquefaction  is  a  phenomenon  similar  to  flow  sides,  but 
usually it is related to shock, especially due to Earthquake. 
 
The  project  location  is  situated  at  zone‐2  of  Bangladesh  Earthquake  zone  map  where  in  0.15  is 
recommended by BNBC as factor for maximum horizontal ground acceleration. 
 
The  liquefaction  potential  as  estimated  following  Seed  and  Idriss  method  is  found  to  be  generally 
negligible  or  none  (i.e.  F=R/L  ≥1).  Sample  calculation  for  estimating  the  factor  ‘F’  is  provided  as 
annexure  in  this  report.  The  simplified  method  using  embankment  over  burden  stress,  material 
composition including average size of particle (D50), percentage of fines (f.c) and standard penetration 
test  value  'N'  etc.  demonstrates  that  there  is  practically  little  risk  of  liquefaction  under  normal 
circumstances. However, risks cannot be ignored, particularly in cases of localized lenses of mica. With 
available  data/test  results,  these  locations  cannot  be  identified  specifically  at  this  stage  of  study. 
Equations and sample calculation is presented in Appendix‐1 
 
 
   

 
  Page 21 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
5 Riverbank Stability 

5.1 Data and calculation method 
5.1.1 Slope angles and Soil characteristics 
Analysis of the Jamuna  Cross Sections shows, that  the river  in the project area  is  very  shallow with  a 
maximal depth of approx. 18 m. 
 
The angle of the existing riverbank reaches from 1:5 (11.31°) to 1:1 (45°). The cross sections are shown 
in  Figure  5‐1.  It  shows  that  the  most  slopes  have  an angle  of  1:2  or  flatter. Considering  slopes  flatter 
than 1:3 as safe, the calculation will concentrate on the slopes with an angle from 1:2, 1:2.5 or 1:3. 
 

 
Figure 5‐1: Profile of the cross sections at the Jamuna River right bank 

 
Figure 5‐2: Profile of the cross sections at the Jamuna River left bank 
Figure 5‐1 and Figure 5‐2 show the profiles of the cross sections at the Jamuna River at the left and right 
bank. The exact location of the Boreholes and the corresponding cross sections is shown in . The profiles 
of the cross sections and the location of the boreholes in other areas are similar. 
 
The soil strata were determined by boreholes near the riverbank. The analysis of these boreholes show 
that  the  first  upper  soil  layer  in  most  cases  is  clay.  Under  this  clay,  the  subsoil  consists  of  sand  in 
different densities, but mostly loose. 
 
Page 22  September 2013 
F1 Geotechnical Investigations 
 
 
The thickness of the first layer (clay) ranges  from  2 m to 7 m with an average of 5 m. In  some cases, 
when the  deposit is recent, the  sand  is not covered  by  clay.   This  leads  to  four  different  types of  soil 
distributions: 
 
1. First layer Clay 2m, sand underneath 
2. First layer clay 5m, sand underneath 
3. First layer clay 7m, sand underneath 
4. No clay, complete soil consists of sand 
 
For these soils, following properties were considered:  
 Soil 1 Sand:   γ = 18 kN/m3  Soil 2 Clay:   γ = 18 kN/m3 

  γW = 10kN/m   γW = 10kN/m3 
  φ = 30°    φ = 0 
  c = 0    c = 25 kN/m3 
 
5.1.2 Calculation method 
For the calculation of the safety factor in case of an earthquake, a coefficient of 1.5% g in horizontal and 
vertical  direction  was  considered.  This  equals  an  acceleration  of  0.15  m/s²  and  is  based  on  the 
Bangladesh National Building Code (BNBC). 
 
In  addition,  in  the  calculations  an  earthquake  coefficient  of  5%g  is  considered.  This  consideration  is 
based  on  Herbert  Fedinger’s  Report    (Fedinger,  2006)  and  on  the  paper  of  Md.  Hossain  Ali  (Hossain, 
1998).  The  coefficient  equals  an  acceleration  of  0.5  m/s²  in  horizontal  and  vertical  direction.  This 
correlates to an earthquake with a return period of 200 years, which has a 10% probability of exceeding 
in 50 years lifespan of a structure. 
 
These additional calculations were performed, because although the Bangladesh National Building Code 
(BNBC) implies, to use an earthquake coefficient of 1.5%, the report of Herbert Fedinger (2006) uses a 
higher coefficient in PIRDP. 
 
All  calculations  were  performed  with  the  software  Visual  Slope,  developed  by  Visual  Slope,  Loveland, 
Ohio, USA. The software uses the modified bishop method and for the type of failure, a circular failure 
was  assumed.  For  each case,  three hundred  failure  surfaces were calculated,  to  find the  most critical 
one. 
 
In  the  calculations,  two  different  scenarios  were  considered.  In  the  first  one,  the  existing  river  bank 
slope  is  analyzed,  in  the  second  one  the  final,  designed  one.    In  both  scenarios,  the  most  critical  slip 
circle was assumed to be located in the upper 9 m. This 9 m will be the steepest part of the final river 
bank and, in addition every possible soil change will be located in this area. 

2,500 2,000
2,000
2 m Clay 1,500 2 m Clay
1,500
5 m Clay 5 m Clay
1,000
1,000
7 m Clay 7 m Clay
500 500
Sand only Sand only
0 0
1:2 1:2.5 1:3 1:2 1:2.5 1:3
 
Figure 5‐3: Safety factor for 35m slopes  Figure 5‐4: Safety factor for 15m slopes 

 
  Page 23 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
5.2 Calculated Scenarios 
5.2.1 Existing Riverbank 
In the first scenario, the existing slopes of the river bank were analyzed, by considering three different, 
representative slope angles and four different, representative soil distributions. In each case, the angle 
of  the  slope  does  not  change  on  the  whole  range  of  the  slope.  The  slopes  also  consider  deep  cross 
sections. 
 
This leads to two different depths of the riverbed and the water level. 
1. 15 m water level, 19 m riverbed 
2. 35 m water level, 39 m riverbed 

This leads to 24 different cases, which include the extreme cases (minimum clay; sand only) as well as 
the average cases. 
 

 
 
Figure 5‐5: Dimensions of existing slopes 
 
The results of the calculations are found in Table 5‐1. 
 
Table 5‐1: Results of the calculation for existing Slopes 
No  H  HW  S  First Layer Factor of Safety Remarks 
[m]  [m]  Normal EQ (1.5% g) EQ (5% g)
1  19  15  1:2  2m Clay  1.171 1.130 1.026 Flat circle 
2  19  15  1:2  5m Clay  1.457 1.412 1.319 Big circle, both layer
3  19  15  1:2  7m Clay  1.195 1.144 1.040 Big circle, both layer
4  19  15  1:2  Sand only 1.171 1.130 1.026 Flat circle 
5  19  15  1:2.5  2m Clay  1.456 1.390 1.259 Flat circle 
6  19  15  1:2.5  5m Clay  1.571 1.541 1.399 Big circle, both layer
7  19  15  1:2.5  7m Clay  1.189 1.155 1.079 Big circle, both layer
8  19  15  1:2.5  Sand only 1.470 1.404 1.271 Flat circle 
9  19  15  1:3  2m Clay  1.737 1.653 1.479 Flat circle 
10  19  15  1:3  5m Clay  1.635 1.570 1.433 Big circle, both layer
11  19  15  1:3  7m Clay  1.316 1.269 1.169 Big circle, both layer
12  19  15  1:3  Sand only 1.737 1.653 1.479 Flat circle 
13  39  35  1:2  2m Clay  1.171 1.129 1.026 Flat circle 
14  39  35  1:2  5m Clay  1.556 1.509 1.408 Big circle, both layer
15  39  35  1:2  7m Clay  1.456 1.417 1.334 Big circle, both layer
16  39  35  1:2  Sand only 1.171 1.129 1.026 Flat circle 
 
Page 24  September 2013 
F1 Geotechnical Investigations 
 
No  H  HW  S  First Layer Factor of Safety Remarks 
[m]  [m]  Normal EQ (1.5% g) EQ (5% g)
17  39  35  1:2.5  2m Clay  1.468 1.402 1.270 Flat circle 
18  39  35  1:2.5  5m Clay  1.767 1.700 1.557 Big circle, both layer
19  39  35  1:2.5  7m Clay  1.670 1.611 1.484 Big circle, both layer
20  39  35  1:2.5  Sand only 1.456 1.390 1.259 Flat circle 
21  39  35  1:3  2m Clay  2.011 1.915 1.713 Flat circle 
22  39  35  1:3  5m Clay  1.976 1.894 1.695 Big circle, both layer
23  39  35  1:3  7m Clay  1.754 1.674 1.504 Big circle, both layer
24  39  35  1:3  Sand only 1.736 1.653 1.479 Flat circle 
 
The results for  existing  river  banks according to Table  5‐1  show, as expected, an  increasing  safety for 
flatter  slopes.  The  Safety  factors  of  both  the  1:2.5  and  1:3  slopes  are  sufficient  in  both,  normal  and 
earthquake  case. An  exception  is case  number 7 (19m  1:2.5  7m clay).  In this  case  the  safety factor is 
below the minimum acceptable (normal and earthquake) limit, as it is below 1.2. 
 

 
Figure 5‐6: Typical slip circles at an existing slope 
 
The calculated failure mechanism shows, that the upper clay layer has nearly no effect, if it is just 2 m 
thick, for the critical surfaces and the safety factors are nearly the same as in case of no clay layer.   
For a slope angle of 1:2, the safety factor in most cases does not at is fy the minimum limit. 
 
In  these  cases  the  combination  of  a  5m  clay  layer  with  sand  underneath  seems  to  be  the  ideal  soil 
distribution. 
 
The  analysis  of  the  different  possible  failure  surfaces  show  that  the  upper  clay  layer  has  a  stabilizing 
function  on  the  entire  slope,  as  long  as  the  layer  is  thick  enough.  So  the  safety  factor  increases 
significantly, when the upper layer is 5 m clay, while a 2 m clay layer has no significant effect. If the clay 
layer  is thick  enough, the  most critical failure surface shifts  from near the  surface of the slope to the 
inner part. Further analysis show that most of the critical failure surfaces (up to a safety factor of 1.4) lie 
near the surface of the slope.  
5.2.2 Designed river bank 
For the second scenario, the proposed, designed river bank slopes were considered with 24 different, 
representative cases. These slopes also consider deep cross sections. 
 
This leads to two different depths of the riverbed and the water level. 
1. 5 m water level, 19 m riverbed 
2. 35 m water level, 39 m riverbed 

These slopes will not have the same angle everywhere and in addition, a berm will be built about 1.5 m 
below low water level. 
 
 
  Page 25 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
The slope angle in relation to the depth is shown in Table 5‐2 for case 1: 19m river bed and Table 5‐3 
incase 2: 39m river bed: 
 
Table 5‐2: Case 1‐ 19 m river bed 
Part   Slope Angle  Vertical distance from  Horizontal distance from river bank
river bank (toe) 
  1:2  1:2.5  1:3 5 10 12.5  15
2 m Berm   0  5 12 14.5  17
  1:2  9 20 24.5  29
  1:2.2  14 31 35.5  40
  1:2.5  19 43.5 48  52.5
 
Table 5‐3: Case 2‐  39 m river bed 
Part   Slope Angle  Vertical distance from  Horizontal distance from river bank
river bank 
  1:2  1:2.5  1:3 5 10 12.5  15
2 m Berm   0  5 12 14.5  17
  1:2  9 20 24.5  29
  1:2.2  24 53 57.5  62
  1:2.5  39 90.5 95  99.5
 

 
Figure 5‐7: Slope dimensions of designed slopes 
 
 
2 2
2 m Clay 2 m Clay
1.5 1.5
5 m Clay 5 m Clay
1 1

0.5 0.5

0 0
1:2 1:2.5 1:3 1:2 1:2.5 1:3
   

Figure 5‐8: Safety factor for 35m slopes  Figure 5‐9: Safety factor for 15m slopes 
 

 
Page 26  September 2013 
F1 Geotechnical Investigations 
 
Table 5‐4: Results of calculation for designed slopes 
No.  H  HW  S  First Layer  Factor of Safety Remarks 
[m]  [m]  Normal EQ (1.5% g) EQ (5% g)
1  19  15  1:2  2m Clay  1.358 1.308 1.200 Flat circle under berm 
2  19  15  1:2  5m Clay  1.725 1.670 1.546 Both layers crossed 
3  19  15  1:2  7m Clay  1.379 1.342 1.258 Both layers crossed 
4  19  15  1:2  Sand only  1.174 1.133 1.029 Flat circle at toe of upper slope
5  19  15  1:2.5  2m Clay  1.503 1.439 1.300 Flat circle under berm 
6  19  15  1:2.5  5m Clay  1.638 1.579 1.453 Both layers crossed 
7  19  15  1:2.5  7m Clay  1.455 1.405 1.301 Both layers crossed 
8  19  15  1:2.5  Sand only  1.476 1.411 1.276 Flat circle at toe of upper slope
9  19  15  1:3  2m Clay  1.608 1.532 1.380 Flat circle under berm 
10  19  15  1:3  5m Clay  1.707 1.633 1.478 Both layers crossed 
11  19  15  1:3  7m Clay  1.462 1.407 1.292 Both layers crossed 
12  19  15  1:3  Sand only  1.608 1.532 1.380 Flat circle at toe of upper slope
13  39  35  1:2  2m Clay  1.216 1.173 1.068 Flat circle under berm 
14  39  35  1:2  5m Clay  1.748 1.689 1.563 Both layers crossed 
15  39  35  1:2  7m Clay  1.635 1.583 1.462 Both layers crossed 
16  39  35  1:2  Sand only  1.206 1.064 1.059 Flat circle at toe of upper slope
17  39  35  1:2.5  2m Clay  1.479 1.415 1.282 Flat circle under berm 
18  39  35  1:2.5  5m Clay  1.813 1.747 1.602 Both layers crossed 
19  39  35  1:2.5  7m Clay  1.759 1.694 1.555 Both layers crossed 
20  39  35  1:2.5  Sand only  1.478 1.414 1.278 Flat circle at toe of upper slope
21  39  35  1:3  2m Clay  1.608 1.532 1.380 Flat circle under berm 
22  39  35  1:3  5m Clay  1.795 1.718 1.540 Both layers crossed 
23  39  35  1:3  7m Clay  1.892 1.817 1.658 Both layers crossed 
24  39  35  1:3  Sand only  1.608 1.532 1.380 Flat circle at toe of upper slope
 
The  results  for  the  calculation  of  the  designed  slopes,  as  shown  in  Table  5‐4  show,  that  the  safety 
factors  of  the  slopes  with  an  angle  of  1:2.5  or  1:3  are  sufficient  in  every  case  (soil  combination, 
earthquakes). The slopes with an angle of 1:2 also appear to be stable, as long as the upper layer (clay) 
is big enough.  
 
The results also show that the clay layer only has a supporting function, if it is thick enough. In the case 
of a clay layer of just 2m, the failure surface and the safety factor are nearly the same as in the case of 
no clay layer. 
 

 
Figure 5‐10: Typical slip circles at a designed slope 
 
 
 

 
  Page 27 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
5.3 Summary and Conclusion 
The  results  for  both  scenarios  show,  that  the  soil  combination  is  as  important  as  the  slope  angle.  In 
nearly all cases a slope angle of 1:2.5 or flatter is sufficient, while in case of an angle of 1:2, stability is 
only guaranteed, if the clay layer is big enough (about 5.0 m thick). 
 
The  comparison  of  the  both  scenarios  show,  that  the  designed  slopes  are  an  improvement  to  the 
existing slopes. On the one hand, this results from the berm, which has a supporting effect, and on the 
other hand, it results from the different angles of the slope.  
 
The results show, that the calculated earthquakes have a very small effect on the safety factor. This is 
due  to  the  very  small  coefficient  of  just  1.5%.  Although  this  is  in  accordance  with  the  Bangladesh 
National  Building  Code,  the  coefficient  is  so  small,  that  the  effect  can  be  disregarded.  In  addition, 
Herbert Fedinger used in his study in 2006 a coefficient of 5%, so the calculations may need tobe should 
be adjusted. 
 
In addition, the berm could be extended, for it has on the one side a supporting function, which leads to 
a higher safety of the entire slope. The calculated failure surfaces also show that the berm limits the slip 
circle in case of a slope of sand only. 
 
 
   

 
Page 28  September 2013 
F1 Geotechnical Investigations 
 
6 Summery RBP 

6.1 General Geotechnical features 
The general feature of the sub‐soil formation consists of a total terrain with formation consist of a flat 
terrain with an upper layer of clayey silt and silty clay with fine sand and trace mica underlying by fine 
sand up to the depth of about 40 m from the existing ground surface. The clay‐silt layer (mainly CL‐ML 
group) varies from 2m to 7m in general whereas in some locations clay layer was not encountered. The 
consistencies of cohesive layers are medium to stiff which is soft at upper sections. The non‐cohesive 
sand layer is found to be very fine to fine sand with density increasing from loose to very dense with 
increase in depth. 

6.2 Flood embankment stability 
From this analysis and past experience of previous studies, under normal conditions embankment slope 
between 1:2.5 to 1:3 appears to be adequate. 
 
Average embankment height considered is 5.00m from ground level. A typical section of the proposed 
embankment  is  shown  in  Figure  1‐1  (a&b)  for  two  conditions  (with  and  without  shelter  provisions). 
Considering availability of embankment material, it is proposed to use dredged material from the river 
bed. The dredge materials appear to be permeable and hence susceptible to seepage. 
 
Clay  cladding  of  minimum  60  cm  thick  (as  shown  in  Figure  1‐1  (a&b))  all  around  the  embankment  is 
recommended.   
 
For facilitating the seepage flow and consolidation settlement this following measure as suggested: 
 
(a) The base width of the embankment should be at least 35 m. 
(b) Provision of the compacted sand (60cm‐100cm) fills underneath the embankment by removing 
the existing top soil. 
(c) In order to compensate for settlement stage construction of embankment is recommended. A 
minimum  of  2/3  stages  may  be  required,  each  stage  compacted  height  should  be  2  ‐  2.5m. 
Consolidation time that is interval between each stage should be 35 to 50 days. 
(d) Embankment material shall be free from all grass roots or organic material. The dredge fill shall 
have  clay‐silt  with  very  fine  sand  which  have  a  plasticity  index  of  10‐20%  in  according  with 
AASHTO   
(e)  Method of construction: The materials should be spread in layers not exceeding 200mm loose 
and compacted to a density complying with 95% modified proctor. The edges with clay cladding 
should be constructed using benching method for each layer. 

6.3 Riverbank Protection 
The results of the calculations show that the angle and the soil distribution are equally important. 
‐ A slope angle of 1:2.5 or flatter is sufficient in every case 
‐ A thick upper clay layer has a stabilizing effect on the slope, a slope with a clay layer of 
5m or more is stable even for an angle of 1:2 
‐ The berm has a stabilizing effect on the slope 

The calculation also considered the effects of earthquakes on the slope stability. The results show that 
5% acceleration, in both vertical and horizontal direction, significantly decreases the safety factor. The 
safety factors of the designed slopes are still high enough, as long as the slope angle is 1:2.5 or flatter. 
 
Figure 6.1 shows the comparison of a designed slope to an existing river profile. 

 
  Page 29 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
 

 
 
Figure 6‐1: Comparison designed slope to existing river profile 
 
 

7 References 
1. ADB (2002), Jamuna‐Meghna River Erosion Mitigation Project (JMREMP). 
2. ADB  (2010),  Assam  Integrated  Flood  and  Riverbank  Erosion  Risk  Management  Investment 
Project (AIFRERMIP). 
3. Fedinger, H. (2006), JMREMP Part‐B, Special Report, Geotechnical Report. 
4. Hossain,  M.  A.  (1998).  Earthquake  Database  and  seismic  zoning  of  Bangladesh.  Dhaka: 
Department of Civil Engineering, BUET. 
5. Bangladesh National Building Code (BNBC). 
6. Terzagh, Peck & Mesre. 
7. Soil Mechanics in Engineering Practice, 3rd Edition‐1995. 
8. SOFTWARE: VISUAL SLOPE, LOVE LAW, OHIO, USA. 
9. RHD Standard Road Specification. 

 
 
 
 
 
   

 
Page 30  September 2013 
F1 Geotechnical Investigations 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Appendices 
 
 
 
Appendix 1: Sample Calculations .............................................................................................................. 32 
Appendix 2:  Corrected N’ Values for 4 Locations .................................................................................... 34 
Appendix 3: Standard Penetration Test ................................................................................................... 38 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
  Page 31 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
Appendix 1: Sample Calculations 
 
Check for liquefaction: 
As discussed earlier, project site is located in zone2 according to National Seismic Zone map, referred to 
in the BNBC. Accordingly maximum possible horizontal ground acceleration co‐efficient  0.15 is 
used in the study. 
 
The  method  used  for  assessment  of  liquefaction  potential  consists  of  soil  resulting  from  earth  quake 
ground  acceleration  and  comparing  it  with  the  cycle  resistance  ratio(R).  The  liquefaction  resistance  is 
defined  as .  The  soil  is  likely  to  liquefy  if  the  value  of  ratio        is  less  than  unity(one).  The 
method is popularly known as Seed Method ( Ref. seed &Idris, 1971 and Iwasaki &Tatsuka 1978) 
 
The following Equations are used determination of    
When,  
 
0.65 ´
 

0.0882  
0.7
0.19 0.02 0.05
.
0.225 0.05 0.06  
0.05 0.6 2.0  
 
0 0% 40% 
0.004 . 0.16 40% 100%  
1.0 0.015 ´
 
 
ɣ Stress reduction coefficient 
Maximum horizontal ground acceleration 
Average grain size 
Liquefaction Resistance ratio 
Cyclic resistance ratio 
Cyclic stress ratio 
Standard Penetration test 
Depth of soil element 
. . Fine particle content passing 200 seive 
´
 
 
 
In  most  cases  it  was  found  that  there  is  no  possibility  of  liquefaction  of  the  underneath  the 
embankment.  Although  few  location  appear  to  show  factor  of  safety  either  1  or  marginally  less  than 
one  0.95 . 
 
 
   

 
Page 32  September 2013 
F1 Geotechnical Investigations 
 
SAMPLE CALCULATION FOR CHECK AGAINEST LIQUIFACTION FOR JB‐1 
 
For layer A 
 
1.0 0.015 7 0.895 
0.15 
2.25 

4
0.0882 0.0703  
.8 7 0.7
.
.
0.225 0.254 0.484 
0.004 80 0.16 0.16 2.2 1  
 
Assume total clay layer table 7.5m 
 
84%, 10, 0.026 1.0 0.015 3.75 0.854 
25%, 15 0.1 0.65 0.15 2.25 0.854 0.187 21.9 
18
0.0882 0.0957  
.8 9.75 0.7
.
.
0.225 0.25 
 
0.004 84 0.16 0.176 
0.52 
2.38 1  
 
For layer B 
1.0 0.5 9 0.865
0.65 0.15 2.25 0.865 0.189 0219 
15
0.0882 0.096 
.8 15 0.7
.
.
0.225 0.122 

0.218 0.219 1 
 
 
 
   

 
  Page 33 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
Appendix 2:  Corrected N’ Values for 4 Locations 
Table A2.1:  Corrected N’ Values (Koizuri‐Hurasagar Section) 
 
KH-1 KH-2 KH-3 KH-4 KH-5 KH-6 KH-7 KH-8 KH-9 KH-10 KH-11 KH-12 KH-13 KH-14 KH-15
Conversion
Factor ´ ´ ´ ´ ´ ´ ´ ´ ´ ´ ´ ´ ´ ´ ´
Depth

1.5 1.5 15 18 15 18 1 2 12 15 5 6 3 4 6 7 3 4 5 6 5 6 3 4 2 3 3 4 3 4 2 3
3. 1.5 19 23 18 22 6 7 15 18 4 5 5 6 8 10 4 5 8 10 9 11 6 7 3 4 4 5 7 9 3 4
4.5 1.44 21 26 19 23 5 6 18 22 7 9 7 9 10 12 10 12 18 22 10 12 8 10 4 5 4 5 2 3 3 4
6 1.25 19 23 21 26 6 7 19 23 22 27 14 17 15 18 18 22 28 35 12 15 13 16 12 15 4 5 5 6 9 11
7.5 1.12 18 20 24 27 6 7 22 24 24 27 18 20 14 15 19 22 30 34 18 20 13 14 17 19 3 3 4 5 16 18
9 1.02 40 41 27 27 24 24 23 23 26 26 20 20 16 16 28 29 29 29 18 18 16 16 24 24 11 11 12 12 20 20
10.5 0.945 41 39 31 29 25 24 24 23 27 26 22 21 20 19 30 28 23 22 19 18 16 15 22 21 12 11 15 14 22 21
12 1.105 38 42 34 37 27 30 23 25 27 30 24 26 21 23 40 44 27 30 21 23 18 20 25 27 18 20 17 19 24 26
13.5 1.04 40 41 34 35 27 28 25 26 21 22 26 27 23 24 50 52 29 30 23 24 18 19 25 26 22 23 18 19 24 25
15 0.988 41 41 41 40 29 28 24 24 23 23 28 27 25 24 52 51 30 30 24 24 20 20 29 29 22 22 19 19 26 26
16.5 0.942 42 40 43 40 34 32 26 24 25 24 31 29 27 24 55 52 31 29 27 25 20 19 31 29 25 23 21 20 27 25
18 0.912 43 39 46 40 40 36 31 28 26 24 35 31 31 24 54 49 35 32 29 26 24 22 38 34 28 25 23 21 28 25
19.5 0.866 45 39 47 40 40 35 36 31 26 24 40 32 33 29 57 49 35 30 32 28 25 22 42 36 30 26 26 23 30 26
21 0.834 47 39 43 36 27 24 34 29 37 30 29 24 30 26 29 24 34 28
22.5
24
25.5
27
28.5
30
N=Field Value 
 
Table A2.1: (continued) Corrected N’ Values (Koizuri‐Hurasagar Section)  
 
Conversion

KH-16 KH-17 KH-18 KH-19 KH-20 KH-21 KH-22 KH-23 KH-24 KH-25 KH-26 KH-27 KH-28 KH-29 KH-30
Factor
Depth

´ ´ ´ ´ ´ ´ ´ ´ ´ ´ ´ ´ ´ ´ ´

1.5 1.5 8 10 4 5 4 5 4 5 4 5 3 4 4 5 3 4 3 4 5 6 3 4 2 3 2 3 02 3 4 5
3 1.5 6 7 6 7 4 5 3 4 4 5 3 4 6 7 4 5 5 6 12 15 12 15 7 9 6 7 5 6 4 5
4.5 1.44 13 16 9 11 7 9 5 6 5 6 7 9 12 15 5 6 7 9 18 22 14 17 10 12 7 9 7 9 8 10
6 1.25 18 22 18 22 12 15 7 9 21 26 12 15 26 32 15 18 12 15 18 22 18 22 14 17 9 11 6 7 12 15
7.5 1.12 13 14 18 20 13 15 16 18 22 25 15 17 28 31 18 20 14 16 21 23 18 20 18 20 12 13 8 9 14 16
9 1.02 8 8 18 18 16 16 18 18 23 23 18 18 29 30 20 20 16 17 22 22 22 22 21 21 15 15 7 7 15 15
10.5 0.945 15 14 21 20 16 15 21 20 24 23 23 22 29 27 22 21 18 18 25 24 24 23 23 22 18 17 10 9 18 17
12 1.105 18 20 25 27 18 20 23 25 26 28 24 26 30 33 24 26 21 23 29 32 26 28 26 28 22 24 12 13 25 27
13.5 1.04 23 24 25 26 25 26 26 27 29 30 27 28 31 32 26 28 24 25 31 32 30 31 29 30 23 24 15 16 30 31
15 0.988 25 25 27 26 27 26 27 27 30 30 29 29 34 34 29 29 25 25 33 33 34 34 32 32 26 26 17 17 34 34
16.5 0.942 25 24 28 26 33 31 30 29 31 29 34 32 37 35 33 32 26 24 38 36 36 34 34 32 28 26 21 20 38 36
18 0.912 27 25 30 27 36 33 31 28 34 31 35 32 42 38 35 32 29 26 42 38 40 36 36 33 30 27 24 22 41 37
19.5 0.866 28 24 33 28 40 34 32 28 41 36 33 28 45 39 36 31 36 31 46 40 42 36 38 33 36 31 28 24 48 41
21 0.834 35 29 36 30 38 33 37 31 48 40 38 32 32 27
22.5
24
25.5
27
28.5
30
 
 
   

 
Page 34  September 2013 
F1 Geotechnical Investigations 
 
 
Table A2.1: (continued) Corrected N’ Values (Koizuri‐Hurasagar Section)  
 

Conversion
KH-31 KH-32 KH-33 KH-34 KH-35 KH-36 KH-37 KH-38 KH-39 KH-40

Factor
Depth

´ ´ ´ ´ ´ ´ ´ ´ ´ ´

1.5 1.5 3 4 4 5 4 5 2 3 3 4 3 4 2 3 3 4 2 3 2 3
3 1.5 4 5 6 7 6 7 4 5 7 9 4 5 5 6 5 6 4 5 6 7
4.5 1.44 5 6 4 5 9 11 8 10 10 12 11 14 6 7 6 7 6 7 7 9
6 1.25 7 9 6 7 11 14 11 14 14 17 14 17 7 9 6 7 11 14
7.5 1.12 11 12 9 10 15 17 12 13 18 20 14 16 9 10 10 11 7 8 17 19
9 1.02 15 15 8 8 14 14 14 14 17 17 15 15 12 12 12 12 9 9 17 18
10.5 0.945 17 16 12 11 15 14 16 15 22 21 16 15 12 11 13 12 13 12 20 19
12 1.105 18 20 18 19 17 19 20 22 22 24 18 20 16 18 16 18 15 17 21 23
13.5 1.04 20 21 22 23 19 20 22 23 23 24 22 23 18 19 15 16 22 23 22 23
15 0.988 19 19 27 26 20 20 26 26 24 24 22 22 22 22 18 18 24 24 24 24
16.5 0.942 23 22 30 28 21 17 29 27 25 24 24 23 23 22 22 21 23 22 24 23
18 0.912 25 23 34 31 22 20 32 29 27 25 26 24 25 23 27 25 25 23 26 24
19.5 0.866 28 24 38 33 22 19 34 29 27 23 29 25 26 24 28 24 28 24 28 24
21 0.834 29 24 24 20 29 24 29 24 31 26 29 25 35 29
22.5
24
25.5
27
28.5
30
 
 
   

 
  Page 35 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
Table A2.2: Corrected N’ Values (Chouhali ‐ Nagarpur Section) 
 
CN-1 CN -2 CN -3 CN -4 CN -5 CN -6 CN -7 CN -8 CN -9 CN -10 CN -11 CN -12 CN -13 CN -14 CN -15

on Factor
Conversi
Depth
´ ´ ´ ´ ´ ´ ´ ´ ´ ´ ´ ´ ´ ´ ´

1.5 1.5 4 6 4 5 3 4 4 5 4 5 4 5 3 4 3 4 4 5 6 7 4 5 5 6 4 5 5 6 4 5
3 1.5 5 7 2 3 4 5 2 3 2 7 2 3 7 8 5 6 6 7 8 10 5 6 7 8 4 5 12 15 6 7
4.5 1.44 7 10 9 4 5 6 4 5 4 12 4 5 16 18 9 11 8 10 8 10 11 13 12 15 4 5 14 17 7 8
6 1.25 14 17 7 9 10 12 7 9 7 15 7 9 16 18 12 15 14 17 16 20 12 15 14 17 24 24 15 16 15 18
7.5 1.12 15 16 12 13 11 12 11 12 11 12 11 12 19 21 15 17 15 17 18 20 13 14 18 20 26 26 15 16 18 20
9 1.02 18 18 13 13 11 11 10 10 10 17 15 15 20 20 17 17 18 18 50 20 14 14 18 18 26 26 17 17 19 19
10.5 0.945 20 20 16 15 13 12 13 13 13 20 17 17 20 20 20 20 20 19 24 22 15 14 22 20 27 26 18 18 19 18
12 1.105 20 22 17 19 15 16 13 14 13 22 17 19 22 22 21 23 22 24 24 25 16 18 26 27 27 29 19 21 22 24
13.5 1.04 23 22 18 19 16 16 15 15 15 23 18 18 22 22 25 26 23 24 26 26 15 18 26 27 29 29 21 22 22 23
15 0.988 23 23 22 22 17 17 15 15 15 24 20 20 22 20 25 25 26 25 26 26 21 18 29 28 29 29 22 22 22 22
16.5 0.942 24 23 24 23 22 20 15 15 15 24 20 20 26 24 26 24 26 24 28 25 23 18 29 28 31 29 24 22 24 23
18 0.912 26 25 24 22 22 20 18 17 18 23 20 18 26 23 27 25 29 26 29 26 25 26 31 28 31 32 25 26 24 22
19.5 0.866 27 24 28 25 25 22 19 17 19 23 21 19 26 23 27 22 31 28 34 30 26 26 32 29 33 32 28 26 25 22
21 0.834 29 26 28 25 26 23 18 18 18 25 22 20 28 25 29 26 31 28 36 32 27 26 32 29 34 32 29 26 28 24
22.5 30 27 37 31 42 30 30 27 28 33 37 32 32 30 29 24
24
25.5
27
28.5
30
 
 
Table A2.2: (continued) Corrected N’ Values (Chouhali ‐ Nagarpur Section) 
 
CN-16 CN -17 CN -18 CN-19
Conversion
Factor

´ ´ ´ ´
Depth

1.5 1.5 4 5 2 3 2 3 3 4
3 1.5 4 5 4 5 4 5 4 5
4.5 1.44 9 11 6 7 6 7 8 10
6 1.25 14 17 8 10 9 11 10 13
7.5 1.12 15 17 14 16 16 18 16 18
9 1.02 18 18 16 16 23 23 18 18
10.5 0.945 21 20 22 21 18 17 18 17
12 1.105 23 25 22 24 18 20 22 24
13.5 1.04 25 25 24 25 20 21 22 23
15 0.988 26 28 24 24 20 20 26 26
16.5 0.942 30 28 29 27 25 24 26 24
18 0.912 30 27 29 26 25 24 28 24
19.5 0.866 32 27 31 27 28 24 28 24
21 0.834 32 27 32 27 31 26 28 24
22.5
24
25.5 35 29 36 30 34 30 30 25
27
28.5
30
 
   

 
Page 36  September 2013 
F1 Geotechnical Investigations 
 
Table A2.3: Corrected N’ Values (Enayetpur – Koizuri Section) 
 
EK-1 EK-2 EK-3 EK-4 EK-5 EK-6 EK-7 EK-8 EK-9 EK-10 EK-11 EK-12 EK-13 EK-14

ersion
Depth

Facto
Conv
´ ´ ´ ´ ´ ´ ´ ´ ´ ´ ´ ´ ´ ´

1.5 1.5 2 3 3 4 3 4 5 6 3 4 4 5 3 4 6 7 5 6 7 9 5 6 5 6 5 6 4 5
3 1.5 4 5 4 5 4 5 6 7 5 6 5 6 5 6 8 10 7 9 12 15 6 7 7 9 5 6 5 6
4.5 1.44 10 12 7 9 5 6 8 10 6 7 7 9 8 10 11 14 11 14 13 16 9 11 12 15 10 12 10 12
6 1.25 18 22 15 18 5 6 15 18 15 18 9 11 12 15 12 15 15 18 15 18 14 17 15 18 15 18 12 15
7.5 1.12 22 24 18 20 15 17 18 20 18 20 14 15 15 17 15 14 16 18 17 19 18 20 17 19 18 20 15 17
9 1.02 22 22 20 20 17 17 19 19 21 21 15 15 18 18 19 19 18 18 20 20 22 22 22 22 22 22 17 17
10.5 0.945 24 22 21 20 20 19 21 20 24 23 18 17 18 17 25 24 21 20 23 22 24 23 24 23 26 24 19 18
12 1.105 24 26 23 25 24 26 22 24 27 30 22 24 20 22 29 32 24 26 26 28 25 27 26 28 30 33 21 23
13.5 1.04 26 27 23 24 25 26 23 24 31 32 24 25 20 21 30 31 28 29 29 30 26 27 30 31 30 31 25 26
15 0.988 26 26 26 25 26 26 23 23 34 32 27 27 20 20 32 32 31 30 34 34 30 29 32 32 32 31 27 26
16.5 0.942 28 26 27 25 27 26 27 26 36 34 29 27 22 20 35 33 35 32 37 35 30 28 37 35 32 31 32 30
18 0.912 29 25 28 25 28 26 27 26 29 34 30 27 24 20 38 33 38 35 38 35 32 29 42 38 33 31 34 31
19.5 0.866 30 26 28 24 29 25 27 26 40 35 31 27 24 20 42 35 40 35 40 35 34 29 41 35 34 31 36 31
21 0.834 31 26 29 24 29 25 29 26 46 35 32 27 26 21 46 36 42 35 43 35 38 29 42 35 35 30 38 32
22.5
24
25.5
27
28.5
30
 
 
Table A2.4: Corrected N’ Values (Jafargonj – Bachamara Section) 
 
JB-1 JB-2 JB-3 JB-4 JB-5 JB-6 JB-7 JB-8 JB-9 JB-10
Conversion

´ ´ ´ ´ ´ ´ ´ ´ ´ ´
Factor
Depth

1.5 1.5 4 5 8 10 2 3 4 5 5 6 6 6 7 5 6 4 5 5 6
3 1.5 2 3 12 15 2 5 2 3 10 12 8 12 15 7 9 2 3 10 12
4.5 1.44 3 4 13 16 4 3 4 5 13 15 15 14 17 8 10 9 11 14 17
6 1.25 5 6 15 19 6 7 14 17 17 16 20 13 16 13 16 7 9
7.5 1.12 19 21 17 19 3 4 12 13 15 17 22 18 20 14 16 13 15 8 9
9 1.02 24 24 16 16 3 4 15 15 22 22 25 21 21 16 16 15 15 13 13
10.5 0.945 10 9 20 19 4 4 17 16 24 23 27 22 21 18 17 18 17 14 13
12 1.105 24 26 7 8 17 18 26 29 27 26 28 22 24 24 26 22 24
13.5 1.04 27 28 26 27 15 16 20 21 28 29 27 26 26 22 23 30 31 25 26
15 0.988 31 31 29 29 22 22 18 18 30 30 29 26 26 26 26 34 34 29 29
16.5 0.942 33 22 30 28 28 26 22 21 32 30 296 29 27 27 25 38 36 29 27
18 0.912 34 31 31 28 28 25 23 21 34 31 30 30 27 30 27 40 36 29 26
19.5 0.866 34 32 32 28 33 28 24 21 36 31 31 31 26 32 28 42 34 32 28
21 0.834 37 33 33 287 34 28 27 22 38 33 32 32 26 36 30 48 40 34 28
22.5
24
25.5
27
28.5
30
 
 
 
 
   

 
  Page 37 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
Appendix 3: Standard Penetration Test 
 
As indicated earlier Standard penetration test (SPT) were carried out at an interval of 1.5 m. for the full 
depth of exploration of each bore hole. 
 
The SPT field values are in number of blows/ 300mm penetration. The field results are affected by over 
burden  stress,  energy  losses,  non‐standard  equipment  and  operators.  In  order  to  take  this  into 
consideration  for  assessments  of  liquefaction  and  stability  analysis,  corrected  version  of  N‐values  is 
used.  The  method  of  N  value  correction  is  in  accordance  with  that  described  in  bowels  (1996)  in  the 
present report;  corrected value   has been evaluated using the following equation: 
 
 
1.14  
, , 1  
96.76 .
 
 
The  N‐  Value  corrected  values  are  estimated  accordingly  to  the  above  equation.  The  values  N’  are 
presented as annexure in table. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Page 38  September 2013 
 

Asian Development Bank 
Funded by the Japan Fund for Poverty Reduction 
 
Government of the People’s Republic of Bangladesh 
Bangladesh Water Development Board 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Project Preparatory Technical Assistance 8054 BAN 

Main River Flood and Bank Erosion 
Risk Management Program 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Final Report, Annex F2 
Technical Designs for Tranche‐1 Work 
 
September 2013 
 
 

 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
 

 
Page 40  September 2013 
Technical Designs for Tranch‐1 Work 
 
Table of Content 
1  Introduction ................................................................................................................................... 1 
1.1  Background ........................................................................................................................................ 1 
1.2  Geo‐technical Investigation ............................................................................................................... 2 
2  Study sites with and Soil Data ........................................................................................................ 3 
2.1  Borehole Location .............................................................................................................................. 3 
2.2  Field and Laboratory Tests ................................................................................................................. 7 
2.3  Discussion of Results ........................................................................................................................ 10 
3  Sub‐Soil Profile ............................................................................................................................. 11 
4  Embankment stability .................................................................................................................. 16 
4.1  Introductory Remarks ...................................................................................................................... 16 
4.2  Stability Analysis .............................................................................................................................. 17 
4.3  Settlement (of foundation soil beneath embankment) ................................................................... 18 
4.4  Check for seepage flow .................................................................................................................... 20 
4.5  Check for horizontal sliding/pore water pressure within the embankment ................................... 20 
4.6  Stability against Earthquake/Check for liquefactions ...................................................................... 21 
5  Riverbank Stability ....................................................................................................................... 22 
5.1  Data and calculation method ........................................................................................................... 22 
5.1.1  Slope angles and Soil characteristics .................................................................................... 22 
5.1.2  Calculation method ............................................................................................................... 23 
5.2  Calculated Scenarios ........................................................................................................................ 24 
5.2.1  Existing Riverbank ................................................................................................................. 24 
5.2.2  Designed river bank .............................................................................................................. 25 
5.3  Summary and Conclusion ................................................................................................................ 28 
6  Summery RBP .............................................................................................................................. 29 
6.1  General Geotechnical features ........................................................................................................ 29 
6.2  Flood embankment stability ............................................................................................................ 29 
6.3  Riverbank Protection ....................................................................................................................... 29 
7  References ................................................................................................................................... 30 
1  Introduction and Background ....................................................................................................... 45 
1.1  PPTA Outline .................................................................................................................................... 45 
1.2  Physical Environment ....................................................................................................................... 45 
1.3  Design Issues and Principles ............................................................................................................ 46 
1.4  Locations of selected interventions ................................................................................................. 47 
1.4.1  The Priority Works under Tranche‐1 ..................................................................................... 47 
1.4.1.1  Jamuna Right Bank‐1 (JRB‐1) ............................................................................................ 47 
1.4.1.2  Jamuna Left Bank‐2 & Padma Left Bank‐1 (JLB‐2 & PLB‐1) ............................................... 48 
1.5  Components under the Planned Program ....................................................................................... 48 
2  Embankments .............................................................................................................................. 49 
2.1  Embankment Location ..................................................................................................................... 49 
2.2  Subsoil Conditions ............................................................................................................................ 49 
2.2.1  General Soil Characteristics in Bangladesh ........................................................................... 49 
2.2.2  Subsoil Investigations Conducted by BWDB ......................................................................... 49 
2.2.3  Sub‐soil Profiles ..................................................................................................................... 51 
2.3  Stability Analysis for Embankments ................................................................................................. 51 
2.3.1  Outline of Analysis ................................................................................................................ 51 
2.3.2  Assumptions for Embankment Material ............................................................................... 51 
2.3.3  Results of Analysis ................................................................................................................. 52 
2.3.4  Embankment Alignment and Cross Sections ........................................................................ 52 
2.3.5  Crest level of Embankment ................................................................................................... 54 
2.3.6  Set Back ................................................................................................................................. 55 
2.3.7  New Embankment ................................................................................................................. 55 
2.3.8  Re‐Sectioning of Embankment .............................................................................................. 55 

 
  Page 41 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

2.3.9  Road over the embankment ................................................................................................. 56 
3  Drainage Provisions ...................................................................................................................... 57 
3.1  Drainage Channels/Khals ................................................................................................................. 57 
3.2  Drainage Structures ......................................................................................................................... 57 
3.3  Design Criteria for Hydraulic Structures .......................................................................................... 58 
3.3.1  General .................................................................................................................................. 58 
3.3.2  Design Flood Frequency ........................................................................................................ 58 
3.3.3  Crest level of Structure ......................................................................................................... 59 
3.3.4  Design of hydraulic structures (Drainage cum flushing Regulator) ...................................... 59 
3.3.5  Setting out Invert Level of Structure ..................................................................................... 59 
3.3.6  Hydrological Design ............................................................................................................... 59 
3.3.7  Fixation of Vent Size and Design Discharge .......................................................................... 60 
3.3.8  Drainage capacity of regulators ............................................................................................ 61 
3.3.9  Hydraulic Design ................................................................................................................... 62 
3.3.10  Energy dissipation arrangement ........................................................................................... 63 
3.3.11  Structural Design ................................................................................................................... 64 
4  Riverbank Protection Works ......................................................................................................... 65 
4.1  Proposed Works ............................................................................................................................... 65 
4.2  Hydrological Observations ............................................................................................................... 65 
4.3  Data for Bank/Slope Protection ....................................................................................................... 66 
4.4  Elements of Slope Protection .......................................................................................................... 67 
4.5  Design Discharges ............................................................................................................................ 67 
4.5.1  Total River Discharges and Number of Channels .................................................................. 67 
4.5.2  Flow Distribution in anabranches ......................................................................................... 68 
4.6  Design Water Level .......................................................................................................................... 69 
4.7  Flow Velocity .................................................................................................................................... 69 
4.7.1  Requirements ........................................................................................................................ 69 
4.7.2  Brahmaputra‐Jamuna River .................................................................................................. 70 
4.7.3  Padma River .......................................................................................................................... 70 
4.8  Size of bed material ......................................................................................................................... 71 
4.8.1  Bed material for Brahmaputra‐Jamuna ................................................................................ 71 
4.8.1.1  Scour at Brahmaputra‐Jamuna ......................................................................................... 71 
4.8.2  Bed material for Padma ........................................................................................................ 72 
4.8.2.1  Scour at Harirampur .......................................................................................................... 72 
4.9  Waves ............................................................................................................................................... 72 
4.10  Design Cross Section ........................................................................................................................ 72 
4.11  Selection of Type of Bank Protection ............................................................................................... 73 
4.12  Size and thickness of protection element: ....................................................................................... 73 
4.13  Size of Elements for Bank Protection ............................................................................................... 74 
4.13.1  Slope Protection above av.LWL: ........................................................................................... 74 
4.13.2  Under Water Slope Protection: ............................................................................................. 74 
4.13.3  Launching Apron: .................................................................................................................. 74 
5  Estimate ....................................................................................................................................... 75 
6  Alternate Approach for Protection ............................................................................................... 76 
1  Design Criteria ............................................................................................................................ 133 
1.1  Design Life ...................................................................................................................................... 133 
1.2  Standards and Design Guidelines .................................................................................................. 133 
1.3  General Approach .......................................................................................................................... 134 
1.4  Hydrology and Hydraulic Parameters ............................................................................................ 134 
1.4.1  River Discharge and Flood Level ......................................................................................... 134 
1.4.2  Flow velocity ....................................................................................................................... 136 
1.4.3  Wind‐Generated Waves ...................................................................................................... 136 
1.4.4  Freeboard ............................................................................................................................ 138 
1.5  Scour .............................................................................................................................................. 138 
 
Page 42  September 2013 
Technical Designs for Tranch‐1 Work 
 
1.6  Design of Erosion Protection Counter‐Measures .......................................................................... 138 
1.6.1  Slope Protection – River Currents ....................................................................................... 138 
1.6.2  Scour Protection Apron ....................................................................................................... 138 
1.6.3  Erosion Protection Waves ................................................................................................... 139 
1.7  Slope Stability................................................................................................................................. 139 
2  Drainage and Flushing Structures ............................................................................................... 140 
2.1  Draining Capacity ........................................................................................................................... 140 
2.2  Hydraulic and Structural Details .................................................................................................... 140 
1.  General ...................................................................................................................................... 143 
2.  Generation of Waves: ................................................................................................................ 146 
3.  Transition zone (Shoaling and Refraction) .................................................................................. 152 
4.  Wind Conditions in Bangladesh .................................................................................................. 153 
4.1  General ........................................................................................................................................... 153 
4.2  Previous Studies ............................................................................................................................. 153 
4.3  JMREMP Study ............................................................................................................................. 154 
5.  Waves on Rivers ......................................................................................................................... 165 
6.  Waves at PIRDP and MDIP .......................................................................................................... 166 
 
 
Appendices 
 
Appendix I:  Sample Design Calculation for Bank Protection Works at Chouhali .................................. 78 
Appendix II:  Sample Design Calculation for Regulator at Gala (4V‐ 1.5m x 1.8m) ................................. 93 
Appendix III:  The Preliminary Estimates for Tranch‐1, Tranch‐2 and Tranch‐3 .................................... 122 
Appendix IV:  Design Criteria .................................................................................................................. 131 
Appendix V:  Road on the Land‐Side of Rehabilitated or Reconstructed Embankment ....................... 172 
Appendix VI:  Comment Matrix ............................................................................................................. 198 
          (In Separate Volume). 
 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
  Page 43 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

Tables 
 
Table 3‐1: Provides key design considerations for this feasibility level study: .......................................... 58 
Table 3‐2:  Conditions of flow .................................................................................................................... 60 
Table 4‐1:  Bankfull Discharge of Major Rivers .......................................................................................... 67 
Table 4‐2:  The Simulated flow distribution along anabranches of the Jamuna under hydrological 
condition (a) & (b) ...................................................................................................................................... 68 
Table 4‐3:  Measured Velocity in Bahadurabad, Jamuna .......................................................................... 70 
Table 4‐4:  Limits of Standard Bank Protection Structures ........................................................................ 70 
Table 4‐5:  Empirical multiplying factors for maximum scour depth......................................................... 71 
Table 4‐7  Quantities adopted for the design ......................................................................................... 75 
Table 4-1: Wind speed and direction reported by Halcrow (1994)4: ...................................................... 153 
Table 4-2: Average Wind Speed from 1996-2005 ................................................................................... 155 
Table 6-1: Wave height calculation for several wind speeds and fetch length ........................................ 166 
Table 6-2: Wave estimation for PIRDP site ............................................................................................. 168 
Table 6-3: Wave estimation for MDIP site .............................................................................................. 170 
 
 
 
Figures 
Figure 2‐1  Location of BWDB boreholes ............................................................................................ 50 
Figure 2‐2:  Embankment section with and without Temp Settlement area....................................... 54 
Figure 2‐3  Long section of embankment alignment showing the 100 yr. HWL and embankment crest 
level  ........................................................................................................................................... 54 
Figure 3‐1  Showing the location of all proposed regulators under Tranch‐1 (JRB‐1) ........................ 62 
Figure 3‐2  Long section of Regulator showing water levels in R/S and C/S ....................................... 63 
Figure 3‐3  Long section of Regulator showing basin and flexible protection at end ......................... 64 
Figure 4‐1  Showing Locations of Bank Protection Works under Tranch‐1 ........................................ 65 
Figure 4‐2  Envelope cure of measured cross‐sections ....................................................................... 73 
 
 
 
 
 
 
 
 

 
Page 44  September 2013 
Technical Designs for Tranch‐1 Work 

1 Introduction and Background 

1.1 PPTA Outline 
The  Asian  Development  Bank  (ADB)  is  undertaking  a  feasibility  assessment  of  a  flood  and  riverbank 
erosion risk management program covering parts of the main rivers of Bangladesh, funded by the Japan 
Fund  for  Poverty  Reduction  (JFPR).  The  objective  of  the  Main  River  Flood  and  Bank  Erosion  Risk 
Management  Program  (MRP)  is  to  reduce  the  riverbank  erosion  and  flood  risks  to  the  adjacent  flood 
plains  while  maximizing  economic  activities  in  a  sustainable  and  environmentally  acceptable  manner.  
Existing flood embankments dominantly fail from riverbank erosion, and as such the stabilization of the 
river pattern is a cornerstone of reducing the flood risk.  The MRP builds on and extends the activities of 
the Jamuna‐Meghna River Erosion Mitigation Project (JMREMP) (ADB, 2002), implemented in different 
phases from January 2003 until June 2011.  In addition, a similar project, the Assam Integrated Flood 
and  Riverbank  Erosion  Risk  Management  Investment  Project  (AIFRERMIP)  (ADB,  2010)  provides 
important  insight  into  a  number  of  relevant  project  elements  and  processes  especially  integrating 
disaster risk management measures related to the flood and riverbank erosion risk under the dictate of 
the Integrated Water Resources Management (IWRM) framework. 
 

1.2 Physical Environment 
The topography of Bangladesh is mainly comprised of the fertile alluvial floodplains of three large rivers 
namely  Ganges,  Brahmaputra  and  Meghna  with  over  92%  of  their  catchments  situated  outside  the 
country. These three rivers combine within the country to form the Lower Meghna, which drains into 
the  Bay  of  Bengal  via  a  constantly  changing  network  of  estuaries,  tidal  creeks  and  active  deltaic 
coastline of the Bay. More than fifty other mid‐sized rivers also flow through Bangladesh and drain into 
the Bay of Bengal.  Out of this river network the planned program envisages to cover the main rivers 
from Jamuna Bridge to Chandpur. 
 
Past efforts to mitigate flood damages by building  flood embankments  along some of the main rivers 
had limited success.  A major contributing factor to failure was the ongoing channel instability and river 
bank erosion that caused embankments to fail by breaching or required the embankments be retired.  
Brahmaputra  Right  Flood  Embankment  (BRE)  built  in  late  1960s  for  a  length  of  about  217  km  (from 
Kaunia, Rangpur to Bherakhola, Pabna) needed retirement for about 70 km in different places. Even at 
present  about  16.00  km  of  embankment  is  still  open.  Existing  flood  embankments  failed  due  to 
riverbank  erosion,  and  as  such  the  stabilization  of  the  river  pattern  is  a  cornerstone  for  reducing  the 
flood risk. To add stability to the embankment an integrated approach, involving channel stabilization 
and flood mitigation, is required. 
 
Riverbank erosion is one of the major natural disasters in Bangladesh causing untold miseries every year 
to thousands of people living along the banks of major rivers of Bangladesh. Bank erosion has rendered 
millions homeless and is a major social hazard.  In 2011, the Brahmaputra‐Jamuna, the Ganges and the 
Padma eroded about 3600 ha of land, 400 ha of settlement, 2240 m of active flood embankment, 2070 
m  of  district  road,  115m  m  of  upazila  road  and  4320  m  of  rural  road  (CEGIS,  April  2012).  Only  along 
Jamuna about 2000 ha of land was eroded in 2011. Brahmaputra Right Embankment, originally built to 
provide  flood  control  to  117,400  ha  during  the  period  1963‐64  to  1967‐68  has  failed  to  serve  the 
intended goal due to erosion.  
 
The need of river training and bank protection in Bangladesh arises from the fact that most rivers of the 
country are unstable, i.e. they are not in a state of equilibrium with the governing physical processes. 
Both,  river  training  and  bank  protection  measures  have  the  objective  to  ensure  a  safe  and  efficient 
transport of water and sediments through a certain defined stretch of the river.  
 

 
  Page 45 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

In  order  to  prevent  or  minimize  the  loss  of  valuable  land,  several  stretches  of  the  river  banks  might 
need  suitable  protection  against  erosion.  In  this  context  it  has  to  be  emphasized,  that  in  case  of 
planning  local  protection  measures,  the  consequences  must  be  taken  into  account,  against  a  certain 
response  of  the  river,  i.e.  morphological  changes  in  the  vicinity  or  even  further  away  from  a 
countermeasure,  are  to  be  expected.  Protection  of  one  place  will  possibly  influence  erosion  and 
bankline  shifting  at  other  locations.  From  that  point  of  view,  only  absolutely  necessary  measures  are 
considered.  
 
In addition to loss of valuable land by erosion, the damages are caused to crops due to high flood depth 
and  early  flood  in  the  lower  flood  plains,  deposition  of  sand  on  the  agricultural  fields  and  sediment 
deposition on river route are the additional hazards due to erosion associated with flood.  
 

1.3 Design Issues and Principles 
The  project  builds  on  and  extends  the  activities  of  Jamuna‐Meghna  River  Erosion  Mitigation  Projects 
(JMREMP) (ADB, 2002), implemented from January 2003 to June 2011. In addition to taking account of 
the  experiences  from  JMREMP,  the  project  records  the  earlier  efforts  made  by  BWDB  in  controlling 
flood and takes account of experience gained under earlier and recent attempts for stabilizing the river 
and reducing the flood damages.  
 
In the recent days flood damages are on the rise in Bangladesh due to increase in population density 
and  increased  infrastructure  in  vulnerable  areas.  It  is  observed  that  the  reliable  structural  and  non‐
structural measures reduces flood and erosion damages and retains benefit to the local population.  
 
The experience gained under different projects through interventions on major rivers, documented in 
the Guidelines for River Bank Protection, 2010, also point to a vision to be chosen for stabilization of the 
river. Experience gained from different ongoing and past initiatives in this respect has also been and is 
being taken into consideration in formulating the design under this project. 
 
BWDB, under JMREMP, has built 10.0 km of riverbank protection from Koizuri towards the Hurasagar 
River. JMREMP  originally provided  7.0  km  of  protection along the bank of Brahmaputra‐Jamuna  from 
Kaitala  to  Mohanpur.  The  executed  bank  protection  along  the  two  reaches  has  contributed  to  the 
stabilization  of  navigation  channel  towards  Baghabari  Port.    Substantial  reduction  of  the  annual 
dredging  volume  for  the  channel  access  to  the  Baghabari  Port  may  be  due  to  the  protection  work 
executed under JMREMP. 
 
The introduction of low cost and sustainable bank protection technology along with flood management 
applications in JMREMP (ADB, 2002) shall be the major tool for accruing benefit from the gift of nature 
i.e. the river. 
 
The  present  project  is  intended  to  build  on  JMREMP  designs,  Guideline  for  Bank  Protection,  2010 
approved and lessons from Padma Bridge design. 
 
Activities  to  date,  have  concentrated  on  arresting  riverbank  erosion  along  one  bank,  while  future 
activities  need  to  focus  on  river  stabilization  and  consequently  both  banks  at  the  same  time.    The 
systematic  river  stabilization  provides  Bangladesh  also  with  the  long  cherished  opportunity  to  regain 
some of the lost floodplain land, while at the same time providing additional natural zones to improve 
the stressed river habitats. 
 
The  PPTA  consultant  team  assessed  the  vulnerability  of  each  location  along  the  major  rivers  and 
prioritized the work to be taken under the project. After collecting the data from the field the following 
criteria was prepared to rank the intervention for the priority investment program under tranch‐1.  
 Embankment breach length and location  
 
Page 46  September 2013 
Technical Designs for Tranch‐1 Work 

 Erosion length  
 Existing rate of bank erosion  
 Requirement of Bank Protection Work  
 Location within a risk zone  
 Drainage congestion area 
 Flood area  
 Opinion of stakeholder in terms of vulnerability  
 Estimated Rehabilitation cost of each intervention  
 

1.4 Locations of selected interventions 
The  program  will  focus  on  the  selected  reaches  of  the  main  rivers‐Brahmaputra‐Jamuna,  Ganges  and 
Padma River. The primary focus of the program is riverbank erosion and flood risk management along 
the  Jamuna  River  downstream  of  Bangabandhu  (Jamuna)  Bridge,  Padma  River  from  the  Jamuna 
confluence  to  Upper  Meghna  confluence  and  the  Ganges  River  downstream  of  proposed  Ganges 
Barrage. The data for the whole affected reaches (erosion, flood, sand casting etc.) were collected from 
primary and secondary sources. The activities under the project has been grouped under three tranches 
namely  Tranch‐1,  Tranch‐2  and  Tranch‐3.  Priority  selection  under  tranch‐1  has  been  made  on  multi 
criteria analysis (MCA) conducted on all the problems identified on the whole reach.  
 
1.4.1 The Priority Works under Tranche‐1 
Right Bank of Brahmaputra‐Jamuna (JRB1) 
(i)  Embankment from Koizuri to Hurasagar outfall (new): 12.50 km 
(ii) Embankment from Hurasagar outfall to Shahjadpur (rehabilitation): 16.50 km 
(iii) Bank protection near Hurasagar (Benotia) Outfall: 1.00 km 
 
Left Bank of Brahmaputra‐Jamuna (JLB‐2) 
(iv) Bank Protection in Chouhali‐Nagarpur: 5.0 km 
(v) Bank Protection in Jafarganj‐Bachamara: 2.0 km 
 
Left Bank of Padma (PLB‐1) 
(vi) Bank Protection in Harirampur area: 7.0 km 

1.4.1.1 Jamuna Right Bank‐1 (JRB‐1) 
(right bank of Jamuna River downstream of Jamuna Bridge) 
 
The  Brahmaputra‐Jamuna  flows  as  straight  channel  downstream  of  Jamuna  Bridge  for  about  15  km 
along the left bank.  As  a consequence an  about 15 km  long and 5 km wide stable attached char has 
formed along the right bank.  The channel bifurcates into a western and eastern branch near Enayetpur, 
the eastern one presently being dominant.  This bifurcation appears to be stable.  
 
The  major  area  in  the  right  bank  downstream  of  Enayetpur  was  protected  by  the  Brahmaputra  Right 
Embankment (BRE), which has been eroded over a length of around 12 km at the downstream end. The 
breach  has  brought  the  once  protected  area  back  to  the  natural  cycle  of  flooding,  with  substantial 
deposition of sand along the riverbanks. 
 
In the study area the reach severely affected by flood and sand deposition is the zone from Koizuri to 
Hurasagar off take along Brahmaputra‐Jamuna River, where BRE is already eroded and the zone from 
Hurasagar off take to Shahjadpur along Hurasagar River, where the existing embankment is eroded in 
several reaches and in very bad shape in some other reaches.  The embankment along Jamuna in this 
reach  is  to  be  reconstructed  and  the  embankment  along  Hurasagar  and  Karotoa  River  need  to  be 
rehabilitated in some reaches and reconstructed in other reaches.  
 
  Page 47 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

 
The  reconstruction  and  rehabilitation  of  the  embankment  along  the  area  mentioned  will  lead  to 
reconstruction  of  regulators  already  eroded  and  also  meet  the  deficiency  of  drainage  and  flushing 
requirement felt during the project operation period. 
 
A major portion of the bankline of this reach along Jamuna river is protected against bank erosion under 
JMREMP. 

1.4.1.2 Jamuna Left Bank‐2 & Padma Left Bank‐1 (JLB‐2 & PLB‐1) 
(JLB2:  left  bank  of  Jamuna  River  downstream  of  Dhaleshwari  offtake  to  Jamuna‐Ganges  confluence; 
PLB1: left bank of Padma River just downstream of Jamuna‐Ganges confluence) 
 
The other areas of interest are in the left bank of Brahmaputra‐Jamuna and left bank of Padma affected 
by erosion, flood and sand deposition. Bank protection in all these areas is given preference over flood 
management measures, which are planned to commence in Tranche‐2.  
 
The  remaining  area  affected  by  flood,  sand  deposition  and  erosion  will  likely  be  included  under  the 
project through studies conducted under different tranches and prioritization fixed through MCA. 
 

1.5 Components under the Planned Program 
In general, the following works are involved in the project under tranche1:  
 
 Embankments: 
o Construction of embankment 
o Re‐sectioning of embankment  
o Repair of existing drainage structure (if repairable) 
o Replacement/Construction of drainage cum flushing regulators 
o Alternative drainage/flushing structures. 
 Bank Protection and River Training works  
o Underwater works consisting of geobags 
o above water works (wave protection) consisting of concrete blocks/slabs 
o buoys for navigation purposes along the protected riverbanks and protection of fish 
 
   

 
Page 48  September 2013 
Technical Designs for Tranch‐1 Work 

2 Embankments 

2.1 Embankment Location 
The embankment in the right bank of Brahmaputra‐Jamuna river from Koizuri to Hurasagar outfall will 
be  reconstructed  following  a  retired  alignment.  The  embankment  under  Hurasagar  sub‐project,  from 
Bherakhola  to  Karotoa  river  also  need  to  be  rehabilitated  and  reconstructed  as  needed  to  serve  the 
project  requirement.  The  preliminary  design  of  the  embankment  along  Brahmaputra‐Jamuna  is 
prepared  to  protect  the  area  against  flood  with  a  free  board  of  1.5m  on  100  year  HF  and  that  along 
Hurasagar is designed on 100 year HFL with 1.0m free board.  
 
In designing the embankment emphasis on the impact of HWL as well as climate change scenario have 
been considered. During the design of embankments, due consideration on the causes of its failure has 
also been given. 
 

2.2 Subsoil Conditions 
2.2.1 General Soil Characteristics in Bangladesh 
Bangladesh  consists  primarily  of  deltaic  alluvial  sediments  of  the  big  rivers  Ganges,  Padma, 
Brahmaputra/ Jamuna, Meghna and their tributaries. The basins of the Brahmaputra/Jamuna  and the 
Ganges are bounded to the tectonically highly active Himalayas mountain ranges, which are subject to 
severe erosion contributing to the heavy sediment  load in the Ganges and the Brahmaputra/ Jamuna 
river.  The  entire  country  of  Bangladesh  is  a  part  of  the  Bengal  basin,  filled  in  the  tertiary  quaternary 
geological period. The basin is an area of subsidence, which is balanced by the deposition of sediments 
supplied by its river system.  
 
The floodplain of the main rivers consist of recently deposited sediments. The oscillation zone of these 
rivers consists of alluvial sand and is covered by alluvial silt or deltaic silt.  In general, alluvial sediments 
ranges  from  fine  silt  to  gravel,  whereas  a  large  part  (about  60  to  85%  of  the  total  volume)  of  the 
sediment  load  in  all  rivers  of  Bangladesh  consists  of  silty  materials.  The  recent  sediments  near  the 
present courses of the major rivers can physically be classified as: 
 Alluvial sand,  
 Alluvial silt,   
 Alluvial silt and clay,   
 Marsh and clay peat, 
 Deltaic sand and  
 Deltaic silt. 
 
2.2.2 Subsoil Investigations Conducted by BWDB 
A soil exploration program was undertaken to investigate the sub soil condition at the selected project 
sites for Main River Flood and Bank Erosion Risk Management Program.  
 
Accordingly, for the preliminary project formulation and feasibility study; a number of bore‐holes were 
explored through the Ground Water Hydrology Division of BWDB, during November 2011 to February 
2012. 
 
The locations of executed bore holes are (Figure 2‐1): 
 At  right  bank  of  river  Jamuna  from  Bherakhola  to  Baghabari  port  and  Benotia  Bazar  to 
Bherakhola a total of 40BH designated as KH‐1 to KH‐40 in Sirajganj District. 
 At right bank of Jamuna from Enayetpur to Koizuri, a total of 14 BH designated as EK‐1 to EK‐14 
in Sirajganj District. 

 
  Page 49 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

 At  left  bank  of  Jamuna  in  Chouhali‐Nagarpur,  19  BH  designated  as  CN.1  to  CN.19,  in  Tangail 
District 
 At left  Bank  of Jamuna  in  Jafarganj  ‐  Bachamara,  a  total of  10 BH designated as JB‐1 to JB‐10 
under Manikganj District.  
 

 
Figure 2‐1: Location of BWDB boreholes 

Depth  of  Bore‐hole,  locations  with  co‐ordinates  and  BH  locations  on  satellite  images  are  shown  in 
Annex F1. 
 
 

 
Page 50  September 2013 
Technical Designs for Tranch‐1 Work 

2.2.3 Sub‐soil Profiles 
The general observation on soil strata is: 
 The sub‐surface soil formation is a two layer system. 
 In general in all four section, the upper layer consists of fine grained soil of low to inter‐mediate 
plasticity  with  few  exceptions  where  in  it  is  referred  to  as  plastic,  semi‐plastic  or  even  non‐
plastic (up‐to above RL+ 4 to+ 5m PWD). Broadly Classified as CL‐ML type soil 
 The  lower  part  (i.e.  below  +  4  to  +  5m  PWD)  mainly  consists  of  very  fine  to  fine  to  medium 
grained  sands  up‐to  depth  of  exploration.  Very  thin  film  of  mica  mineral  in  traces  were  also 
encountered at varying depths. 
 
A  generalized  summary  of  drilling  at  the  project  locations  show  a  upper  clay‐silt  or  silt‐clay  layers 
referred to in the this report as CL‐ML (often found to be CH‐MH) which consists of silt clay / clayey silt 
with  low  to  medium  plasticity.  Below  the  upper  clayey  layer  fine  grained  and  poorly  graded  sand, 
referred to as SP/SM or FS sometimes very fine sand, VFS of medium compactness. The sand strata has 
general trend of mild increase in density from medium to dense becoming very dense at depth around 
30m and below. (As evident from BH Logs) 
 
The observed slope inclination at river in sand is found to be 1:2.5‐1:3 for about 50% of the project area 
which  is  expected  with  limit  equilibrium  condition.  The  angle  of  internal  friction,  which  is  the  shear 
strength of sand in these case are   28 ‐ 30  with very low effective cohesion estimated at c=2‐4 kpa. 

2.3 Stability Analysis for Embankments 
2.3.1 Outline of Analysis 
On the basis of the result of geotechnical investigation carried out by BWDB, some preliminary stability 
analysis  was  carried  for  the  proposed  flood  protection  embankment  and  bank  slope.  The  slope 
protection and erosion control of the vulnerable  river bank is not considered here and are addressed 
separately at a later stage.  
For the purpose of analysis the following assumptions are made: 
 dredged fill material for embankment (core) construction 
 embankment height 4m‐ 6m (i.e. 5m on average)  
 compacted fine sand with angle of internal friction  = 28 to 30; used 30 
 
 embankment slope:  1V:3H and 1V:2.5H 
 a factor safely fs ≥ 1.4 has been considered as standard in line with previous project designs for 
river bank stability (PIRDP). 
 
2.3.2 Assumptions for Embankment Material 
To ensure least usage of valuable land, specially the top soil, borrow pits are avoided. In this case bulk 
fill material is river sand. Because of scarcity of land, especially agricultural land, embankment core is 
proposed to be built with dredged river sand. Minimum 60 cm thick clay cladding over the core surface 
shall  protect  the  embankment  against  weather  action.  The  clay  material  is  proposed  to  be  collected 
from  base  excavation  or  from  local  selected  soil  or  carried  far  away  from  construction  area.  So  no 
borrow pits are proposed.  
 Dredged soil from river bed 
 River bed material mainly fine sand/ very fine sand with silt/ silty fine sand/ silt with very fine 
sand occasional at shallow depths. 
 The feature of predominant fine particles is observed at shallow depths (5‐7m). 
 Compacted fill material have angle of internal friction φ=28‐30 
 Slope angle  , i.e. slope 1V:3H, 1V:2.5H and 1V:2H 
 
 
  Page 51 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

2.3.3 Results of Analysis  
tan 
Under normal conditions: Factor of safety against failure, fs =  ; Ø   28° to 30°,  use 30°  
tan 
For Ø 28° , F.S (for 1:3) = 1.6  and  for Ø 30°, F.S (for 1:3) = 1.7  
For Ø 28° , F.S (for 1:2.5) = 1.33  and  for Ø 30°, F.S (for 1:2.5) = 1.44  
 
From the analysis, it would appear that although under normal conditions slope provision of 1V:3H and 
1V:2H  are  adequate,  protective  measure  against  seepage  flow  will  be  required  for  construction  of 
embankment considering the fact that the only material available cheaply and in abundant quantity is 
very fine sand with little to some silt/clay. 
 
At  this  stage,  under  the  circumstances  discussed  above  the  proposed  embankment  configuration 
considered from stability and safety consideration can be silty fine sand materials with clay‐cladding all 
around as shown in fig.1 (a). 
 
It is also proposed to consider slope of the embankment as 1:3 as the preferred option. However, it is 
also  possible  to  use  different  slopes  at  riverside  at  the  second  option  for  the  flood  embankment 
configuration as shown in fig.1 (b). 
 
2.3.4 Embankment Alignment and Cross Sections  
The  alignment  of  an  embankment  is  governed  mainly  by  technical,  economical  and  morphological 
considerations.  Economically  the  best  alignment  is  that,  which  can  be  built  efficiently,  requiring  least 
land  acquisition,  causes  minimum  social  impact,  uses  locally  available  suitable  material  and  protects 
land  area  as  much  as  possible.  For  this  project,  the  following  points  have  been  kept  in  consideration 
while finalizing the alignment of the embankment:  
 As far as possible, it has been kept in consideration that the existing alignment of embankment, 
wherever  available,  is  followed  to  avoid  additional  land  acquisition  and  relocation  of  existing 
infrastructure and settlements.  
 Set  back  is  carefully  fixed  considering  available  bank  protection  and  erosion  rate  of  the  river 
bank.  
 The alignment is preferred to pass over the area, where bulk of fill material/earth is available 
for construction of the embankment.  
 Sharp corners (bends) in the alignment is avoided not at last for improved road communication.  
The minimum radius of curves shall be 250m.   
 Due attention is given for avoiding blockage of the existing transportation system.  
 Alignment  is  preferred  to  run  as  far  as  possible  along  the  higher  ground  elevation  and  not 
across depressions. 
 
The following technical aspects were considered for the embankments:  
 Along the protected bankline the setback distance is as minimal as possible. Minimum setback 
distance is 35m, in consideration of not to impose any additional load on the bank slope and to 
have sufficient setback distance if local failures occur.  
 Mechanical compaction is proposed in embankment construction/ re‐construction. 
 The core of embankment will be constructed with dredged sand/silt (dredged from the nearby 
river).  The  selection  of  dredged  soil  as  fill  material  is  made  as  per  provision  of  BWDB  Design 
Manual  and  Govt.  decision.  The  section  has  been  designed  accordingly  to  save  valuable 
agricultural land. 

 
Page 52  September 2013 
Technical Designs for Tranch‐1 Work 

 A  clay  cladding  (minimum  60  cm  thick)  around  the  exposed  surfaces  shall  be  provided  to 
protect  the  embankment  against  rain  cut  and  weathering  action.  The  amount  of  clay  for  clay 
cladding shall be available from the base excavation of the embankment. 
 10m wide roadway to accommodate a 5.5 carriage way (2‐lane rural road) with paved shoulder 
and grass verge as per specification of RHD shall be constructed on embankment.  
 an  RCC  road  (2.8m  wide)  will  be  constructed  on  3.2  m  wide  crest  for  plying  non  motorized 
vehicle (NMV). The RCC road will also be used for maintenance of the flood embankment. The 
crest allows raising of embankment height due to climate change without disturbing the normal 
traffic along the roadway. 
 
Embankment section is designed to fulfill the following criteria: 
 The side slope of embankment on country side should remain stable during steady seepage at 
design high water level  
 The side slope of embankment on river side must be stable during rapid drawdown conditions, 
where these prevails  
 Phreatic line i.e. top hydraulic gradient line should be well within the downstream face so that 
no sloughing of the slope takes place.  
 Sufficient  'Free  Board'  must  be  provided  to  avoid  the  possibility  of  over  topping  during  the 
design flood.  
 The  u/s  and  d/s  slope  should  be  flat  enough,  so  as  to  provide  sufficient  base  width  at  the 
foundation  level,  such  that  the  maximum  shear  stress  developed  remains  well  below  the 
corresponding maximum shear strength of the soil. For this a suitable factor of safety should be 
provided.  
 River side slope is stable against wave run up in case no treatment is anticipated  
 
On  the  whole  the  embankment  section  itself  shall  be  stable  against  imposed  hydraulic,  seismic  and 
other anticipated external loads. 
 
For comparison the recommended section in BRE is : 
 
Fulchari‐Sirajganj:  (top  width;  24.0  ft  =  7.3m,  Side  slope:1V:  3H  both  side);  Sirajganj‐  Bherakhola 
(Sirajganj): top width: 14.0 ft (4.3m), Side Slope: 1V:3H. Very recently the crest width of embankment 
from Sirajganj to Enayetpur is extended to accommodate a two lane road with some provision of non‐
motorized vehicle (NMV). 
 
The  designed  section  shall  also  withstand  toe  scour  and  slope  erosion  due  to  incident  waves  during 
stormy  weather.  The  climate  computations  are  based  on  IPCC  predictions  for  2050;  0.50m  sea  levels 
rise.  
 
The  design  has  been  carried  out  considering  the  technical  feasibility,  satisfying  the  requirements  of 
economic  viability, social  and  environmental  acceptability. In selected  locations  a  berm  is  provided  at 
the  river  side  of  embankment  allowing  some  provision  of  temporary  shelter  for  erosion  and  flood 
victims. The selected cross sections are depicted in Figure 2‐2. 
 

 
  Page 53 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

 
Figure 2‐2: Embankment section with and without Temp Settlement area.  
 
A long section showing the elevation (DEM) along the embankment alignment is shown in Figure 2.3. 
 

 
Figure 2‐3: Long section of embankment alignment showing the 100 yr. HWL and 
embankment crest level 
 

2.3.5 Crest level of Embankment  
The  embankment  is  designed  to  keep  selected  flood  heights  (100  year  HFL  with  incident  waves)  and 
overtopping water out of the project area.  
 

 
Page 54  September 2013 
Technical Designs for Tranch‐1 Work 

As per Design Manual (BWDB) the embankment along all the major rivers shall be constructed with 100 
year HFL+ 1.5 m free board.  Accordingly the embankments along Brahmaputra‐Jamuna and Padma is 
proposed with a crest level of 100 year HFL+1.5 m Free Board.  
 
The  embankments  along  Hurasagar  upto  a  length  of  5.5km    from  the  outfall  of  Hurasagar  at  Jamuna 
shall have 1.5m free board over 100 year HFL (100 year HFL in Jamuna is 13.30 and that at Baghabari in 
Baral is 13.60m PWD). The embankment along Hurasagar Baral at Baghabari shall have free board of 1.0 
m over 50 year HFL (13.20m PWD) and the rest embankment along Karotoa river shall have a free board 
of 1.0 m over 50 year HFL (13.20m PWD). The crest level of embankment from 5500m to 9500 m along 
Hurasagar shall have smooth transition. 
 
2.3.6 Set Back  
Set  back  is  the  distance  between  river  bank  and  river  side  toe  of  the  embankment.  The  setback  has 
been determined considering the following criteria;  
 At places where erosion has taken place over past years, a setback is based on the erosion rate. 
An  extra  margin  equivalent  to  10  years  of  the  present  erosion  rate  is  added  to  the  minimum 
setback to be applied, if immediate bank protection is not intended.  
 At  places  where  a  bank  protection  is  provided  or  already  exists,  set  back  selection    takes 
account  only  to  avoid  surcharge  due  to  embankment  loading  and  allowance  for  emergency 
repair of protection works.  
 Where embankments are to be provided on both sides of a river, the minimum setback should 
be  determined  from  the  floodway  requirement  to  pass  the  design  flood  under  confined 
conditions.  
 If the above criteria cannot be attained, a minimum setback (as per standard norm) from the 
eroded bank are kept, but bank protection works are proposed to be provided.  
 
2.3.7 New Embankment  
A  new  embankment  run  along  a  new  track  further  inland  from  the  old  (damaged  by  erosion) 
embankment. The alignment of this embankment will merge smoothly with the existing portion of the 
old embankment. At certain locations of the existing embankment, where embankment has already got 
breached or threatened to be breached in near future due to river action, there is a need to construct a 
new embankment. 
 
The  new  embankment  proposed  under  the  project  (Tranche  1)  is  from  Koizuri  to  Hurasagar  outfall 
(about 12.5 km) along right bank of Brahmaputra‐Jamuna, and 6.0 km along left bank of Hurasagar at 
different  stretches  (already  eroded)  from  Hurasagar  outfall  to  Korotoa  outfall.  The  embankment  as 
described earlier accommodates a 5.5m carriage way plus 1.50m wide shoulders inside the protected 
area and a 2.8m RCC road along the crest for non‐motorized vehicle (NMV). 
 

2.3.8 Re‐Sectioning of Embankment  
Due  to  lowering  of  embankment  by  weathering  action  or  by  wave  erosion  or  due  to  settlement  the 
existing  embankment  sections  have  become  under  designed  section  at  many  locations.  Also  due  to 
various past natural calamities and non‐maintenance for a long time, the existing embankment sections 
have deteriorated at many locations. The consideration for global warming and climate change, added 
need  to  safeguard  areas  against  selected  flood  events.  In  addition  to  create  a  provision  for  a  2‐lane 
carriage  way  the  re‐design  of  embankments  is  necessary.  Therefore,  design  for  re‐sectioning  of  the 
existing damaged or deteriorated embankment has been carried out to serve the present need and safe 
guard the project area. 
 
 
  Page 55 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

The  re‐sectioning  of  embankment  is  proposed  for  a  length  of  about  10.5  km  along  the  left  bank  of 
Hurasagar  and  left  bank  of  Karotoa.  The  re‐sectioning  mostly  follows  the  old  Hurasagar  sub‐project 
embankment. The embankment shall be rehabilitated to accommodate the 5.5m carriage way and NMV 
as provided for the new embankment. 
 
2.3.9 Road over the embankment 
Rural Road: On the inner top of embankment a rural road having 5.5m carriage way plus 2x1.5m paved 
shoulder and 2x0.75m verge is proposed to be constructed. The rural road will have a flexible pavement 
with  0.2m  sub‐grade,  0.2m  sub‐base,  0.15m  aggregate  base  type‐II  and  base  course,  prime  coat  and 
bituminous tack coat as per rural road standard specification.   
 
NMV Road: On the crest of embankment a 2.8m wide RCC carriageway shall be built for non motorised 
vehicle  (NMV).  This  road  is  proposed  to  be  used  also  for  maintenance  of  the  embankment  during 
emergency without disturbing the regular traffic.  
 
Gras stone: This is a concrete slab (40x40x15cm) with 4 holes of size 12.5x12.5cm. The gras stone blocks 
will be placed along both the slope of the crest up to 1.2 m below crest in the country side and 1.5m 
below  crest  in  the  river  side  of  the  embankment.  The  gras  stone  will  allow  grass  to  grow  through  its 
holes but resist any damage attempt by the people. 
 
   

 
Page 56  September 2013 
Technical Designs for Tranch‐1 Work 

3 Drainage Provisions 

3.1 Drainage Channels/Khals  
The  main  function  of  the  drainage  channel/  khal  is  to  safely  drain  out  the  design  discharge  or  the 
drainage basin runoff generated by 5‐day duration storm of 1 in 10 year frequency. In addition to that 
increase for precipitation (13% by 2040) for climate change need to be taken in to account.   
 
The  design  of  drainage channel  leading to inlet structure  is  the  design capacity of  that  structure. The 
design discharge of other channels is calculated as follows:  
 
 Design discharge:  Catchment area of channel x unit discharge from drainage modulus. 
 Capacity of Channel: The capacity of channel is computed using Manning’s formula. 
 

3.2 Drainage Structures   
The  objective  of  constructing  flood  embankment  and  associated  structures  is  to  protect  agricultural 
lands from high flood and to drain out excess precipitation from the area through designed opening i.e. 
drainage  sluices.  The  farmers  use  to  take  water  into  the  project  during  winter  and  also  during  post‐
monsoon for irrigation. In view of above need, the sluices are designed for both drainage and flushing. 
So a two way regulators for both drainage and flushing have been designed. 
 
The total area under the Hurasagar sub‐project is 7895 Ha (R1 area = 10,882 acre, R2 area = 8618 acre, 
Total (R1+R2) = 19500 acre = 7895 Ha). Total drainage facility provided under the project was 12 vents‐
1.5mx1.8m and  3 vents‐1.5mx1.5m. Out of total number of structures constructed under the project, 
1V‐1.5mx1.8m,  2  nos  and  1V‐1.5mx1.5m‐  3  nos    were  totally  damaged  during  1998  and  subsequent 
floods. The fixation of invert level was also higher in the opinion of local people. To compensate for the 
higher  invert  elevation,  damaged  structure  and  anticipated  future  climate  change,  the  provision  of 
additional 7 vents has been kept under the study. In addition to that a 6‐vent (1.5mx1.8 m) structure is 
proposed at the outfall of khal connecting Kadai Badla Bil to Jamuna with outfall at Koizuri hat.  
 
The existing regulators of the Hurasagar sub‐project shall be repaired to serve the project. 3 regulators 
are assumed to be repaired to accommodate the project need. In addition 3 regulators shall be added 
to the project (1‐6 vent 1.5mx1.8m, at outfall of Hurasagar at Jamuna right bank, 1‐1 vent, 1.5mx1.8m 
at offtake of new Hurasagar, entering the project area and 1‐4vent, 1.5mx1.8m additional at Hurasagar 
outfall).   
 
In  using  the  existing  regulators  (repaired  and  rehabilitated)  of  Hurasagar  sub‐project  within  the 
extended  embankment  as  proposed  under  the  project  (MRP),  the  embankment  may  need  to  be    re‐
designed at certain stretches to accommodate the proposed embankment section. 
 
Runoff  from  the  catchment  area  (runoff  isohyets)  under  consideration  is  30  mm/day.  The    runoff 
specified  in  IECO  Master  Plan  (1964)  plus  20%  increase  over  that  to  account  for  climate  change  is 
considered for calculating the runoff volume of the area under consideration. 
 
The following table provides key design considerations for regulators for this feasibility level study: 
 
 
 
 
 
 

 
  Page 57 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

Table 3‐1: Provides key design considerations for this feasibility level study: 
Location  Catchment area (Ha/ventage)  Location   Outfall River
[Northing and Easting] 
Lochna  Existing (4 vent, add 2 vent); 1750 ha  461392E; 665068N  Hurasagar/Boral 
Gala  Existing (4 vent; add 4 vent) 3550 ha 465114E; 662557N Hurasagar/Boral
Koizuri, Gopalpur  5570 (6 vent‐new)  468742E; 673594N  Jamuna 
Gudhibari  850 (1 vent‐new)  467619E; 671008N  Jamuna 
 

3.3 Design Criteria for Hydraulic Structures 
3.3.1 General  
For designing the new or rehabilitating damaged hydraulic structures falling along the alignment of an 
embankment  or  along  the  alignment  of  drainage  canals/  khals,  the  Internationally  accepted  standard 
design criteria including the USBR standards and standard design manual formulated by BWDB (Volume 
‐I: Standard Design Criteria) have been used.  
 
Before  starting  the  detail  design  of  the  hydraulic  structures,  a  detail  field  survey  and  stakeholder 
consultation was carried out in order to find prevailing drainage problems and assess the effectiveness 
of  drainage  system  under  different  hydrological  condition.  In  addition,  the  information  about  the 
existing  hydraulic/  water  control  structures  are  collected  during  field  survey  campaign  which  is  very 
important for development of drainage model.  
 
The various types of existing hydraulic structures under the project is given below:  
 Drainage regulators  
 Drainage‐cum‐flushing regulators  
 Flushing inlets  
 Bridges/Culverts  
 
A  drainage  regulator  in  any  basin  area  is  generally  designed  to  drain  the  excess  runoff  from  the 
catchment area up to design drainage level. The dimension/ opening vent size of a drainage regulator is 
calculated based on the average design discharge. The maximum allowable storage level in the project 
area  is  assumed  as  30  cm  above  the  design  drainage  level.  The  drainage  level  is  selected  in 
consideration of the lowest level in the basin.   
 
During certain period of the year, the drainage regulator is also used as flushing inlet to let in the river 
water into the project area as required for the crop field. The project water level during these stages is 
assumed to be lower than the design drainage level. All the regulators are therefore designed with the 
dual purpose of flushing and drainage. 
 
3.3.2 Design Flood Frequency  
Generally for the normal flood protection works, the frequency of occurrence of floods that needs to be 
selected  for  the  design  of  a  particular  embankment  depends  on  the  acceptable  extent  of  damage  by 
inundation in the locality. Considering  likely agricultural damage to important installations and loss of 
human lives, the following flood frequencies are usually adopted in Bangladesh;  
 
1:20 years flood, where agricultural damage is predominant.  
1:100 years flood, where loss of human lives, properties and installations are predominant.  
 
For  the  purpose  of  this  feasibility  level  study,  the  crest  level  was  set  equal  to  the  embankment  crest 
level. 

 
Page 58  September 2013 
Technical Designs for Tranch‐1 Work 

3.3.3 Crest level of Structure  
All the structures i.e. the regulators are the integrated parts of the embankment system, the crest level 
of all the regulators are maintained same as the embankment crest at the location where it is placed.  
 
3.3.4 Design of hydraulic structures (Drainage cum flushing Regulator) 
In general, the design of a hydraulic structure is carried out in three steps;  
 
First step: hydrological analysis is carried out, which determines the design discharge of the hydraulic 
structure.  
Second  step:  hydraulic  designs  are  carried  out  to  determine  the  optimal  location,  configuration  of 
components  of  the  structure,  waterway  requirement,  protection  against  scour,  seepage  and  uplift 
pressures, energy dissipation arrangements etc.  
Third  step:  structural  designs  carried  out  for  evaluating  the  forces/  stresses  on  each  component  of 
structures  on  account  of  dead  loads,  dynamic  loads,  seismic  loads  and  earth  pressures  and  each 
component is designed to resist the forces and bending moments caused by all these loads. 
 
3.3.5 Setting out Invert Level of Structure  
The  invert  level  of  all  the  regulators  are  fixed  mainly  on  the  basis  of  drainage  requirement  and  the 
retention level desired to be maintained within the catchment. In most of the cases the need for energy 
dissipation  through  a  designed  stilling  basin  at  the  both  end  of  the  structure  dictates  the  invert  level 
below av. LWL in the outfall river during the drainage period.  
 
Generally, the invert level of the drainage‐cum‐flushing regulator structure is kept 0.30 to 0.60 m higher 
than the project side drainage channel/ Khal bed level. The consideration of slightly higher invert level 
will help to retain water in the polder area and also it will improve the structure operation conditions by 
reducing  the  possibility  of  sediment  deposition  in  the  structure  conduit  and  secure  tail  water  depth 
during the initial stage of flushing. 
 

3.3.6 Hydrological Design 
For obtaining the design discharge of a drainage‐cum‐flushing regulator, a 5‐day duration storm of 1 in 
10‐years return period expected over the catchment area has been considered, accounting the variable 
country side or river side water levels during considered period. The design discharge is computed on 
the  basis  of  unit  discharge  for  draining  the  catchment  area  with  the  set  of  drainage  structures  in 
anticipated climate change condition. 
 
The preliminary design of drainage‐cum‐flushing regulator has been carried out on the basis of drainage 
and flushing requirement assumed for the project.  
 
For the right bank of Jamuna, WL Gauges considered for the water level in the outfall rivers are Sirajganj 
(SW  49),  records  available  from  January  1945  to  September  2012  and  Mathura  (SW50.3),  records 
available  from  August  1964  to  September  2012.  The  WL  gauges  are  maintained  by  BWDB  along  the 
right bank of Brahmaputra‐Jamuna.  
 
The  interpolated  100  year  HWL,  HWL  (observed),  LLWL  and  Av.  LWL  in  the  area  of  interest  (Koizuri‐
Hurasagar) along the Brahmaputra‐Jamuna  is 13.30 m PWD,12.90 m PWD, 3.60 m PWD, 4.20 m PWD 
respectively. 
 
Similarly for the left bank of Jamuna, WL Gauges considered for the water level in the outfall rivers are 
Bangabandhu  Bridge,  records  available  from  October  1994  to  January  2013  and  Aricha  (SW  50.6), 
 
  Page 59 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

records available from August 1964 to August 2012. The Bangabandhu Bridge WL gauge is maintained 
by BBA and Aricha gauge is maintained by BWDB.   
 
The interpolated 100 year HWL, HWL (observed), LLWL and Av. LWL in the area of interest (Chouhali‐
Nagarpur) along the Brahmaputra‐Jamuna  is 13.95 m PWD,13.10 m PWD, 4.50 m PWD, 4.95 m PWD 
respectively, and those in Jafarganj‐Bachamara is 11.80 m PWD, 11.25 m PWD, 2.50 m PWD and 3.00 m 
PWD respectively. 
 
In selecting the details of drainage cum flushing regulators the av.LWL, av.HWL and average low level of 
the basin are the guiding factors. 
 

3.3.7 Fixation of Vent Size and Design Discharge  
The opening size of the regulator for the drainage‐cum‐flushing regulator has been fixed in such way so 
that it can safely pass the design discharge computed from the hydrological analysis. The flow through a 
regulator  is  mainly  dependent  on  the  upstream  and  downstream  water  levels  and  invert  level.  The 
discharge  through  a  vent  or  orifice  depends  on  discharge  coefficient  and  the  discharge  coefficient 
mainly depends on the entrance coefficient, Ke. The generalized formulae for calculating the discharge 
through  the  square  ended  entrance  in  the  various  types  of  flow  conditions  are  presented  in  table 
below:  
 
Table 3‐2:  Conditions of flow 
Sl. No  Flow Type  Flow Conditions Discharge by the formula
1  Submerged/drowned orifice  H1 > H2 > V ht  Q = 0.802*(B*Vht)*(2*9.81*ΔH) (0.5) 
(Flow Type‐1) 
2  Free orifice   H1 ≥ 1.5 * V ht   Q = 0.60*(B*Vht)*(2*9.81*h) (0.5) 
(Flow Type‐3)  & H2 ≤ V ht 
3  Submerged/drowned weir  H1 < 1.5 * V ht   Q = 0.816*(B*d)*(2*9.81*Δh) (0.5) 
(Flow Type‐4)  & H2 > H c 
4  Free over flow weir   H1 < 1.5 * V ht   Q = 0.305*(B*H1)*(2*9.81*H1) (0.5) 
(Flow Type‐5)  & H2 ≤ H c 
Ref: Standard design manual (BWBD) 
 
Where,  
H1 = Upstream water depth above invert level  
H2 = Downstream water depth above invert level 
Hc = Critical water depth = (q2/g) (1/3) ; q is the discharge intensity (m3/s/m)  
Vht = Vent height of the barrel  
ΔH = H1 – H2  
h = Measured height at the orifice center line = H1 ‐ Vht / 2  
d = Depth of flow within culvert  
Δh = Difference between upstream and downstream water levels within culvert = H1‐d 
B = Total opening width of the barrel  
 
For  the  drowned/  submerged  weir  type  flow  condition,  the  tail  water  rating  curve  for  the  outfall 
drainage canal may be developed and the upstream water depth H1 is known. The two unknowns ‘Q’ 
and ‘d’ can be calculated by trial and error.  
 

 
Page 60  September 2013 
Technical Designs for Tranch‐1 Work 

In the analysis, it is assumed that the only flow conditions Type‐3 and Type‐5 generate hydraulic jumps 
and that necessitate a stilling basin depending upon the Froude No. (F1).  
 

3.3.8 Drainage capacity of regulators 
For  computing  the  preliminary  design  capacity  of  a  regulator  the  procedure  followed  are  described 
below: 
 
Assumed runoff (30mm/day) with 20% increase due to climate change a basin of 850 ha area produces 
a design discharge of 3.54 m3/sec. A regulator, 1V‐1.5mx1.8m, with invert at 7.00 m PWD and basin WL 
at 8.5m PWD can drain 4.30 m3/sec with a head difference of 1.0m. The Basin WL is the minimum WL to 
be  drained.  Under  this  condition  the  regulator  can  drain  only  21.38%  higher  than  the  total  discharge 
generated in the basin.  
 
In another exercise under the similar topographic and hydrologic condition a 3600 ha basin produces a 
design discharge of 15.0 m3/sec. A regulator 4V‐1.5mx1.8m with invert at 7.00 m PWD and basin WL at 
8.5 m PWD can drain 17.20 m3/sec with head difference of 1.0m. Under this condition the regulator can 
drain  14.64%  higher  than  the  generated  discharge.  The  lowest  basin  level  being  at  +8.0  m  to  +9.0  m 
PWD. 
 
The  outfall  water  level  (average)  being  at  6.30  m  PWD  in  April,  7.90  m  PWD  in  May,  9.80  m  PWD  in 
October and 7.60 m PWD in November allows drainage in different period when necessitates. 
 
The  head  difference  is  assumed  to  be  1.0m  with  basin  WL  and  corresponding  river  WL  during  the 
drainage period. On the basis presented above a regulator of size 1V‐1.5mx1.8m is proposed for a basin 
area of 850 ha or less. Ventage of a regulator for a catchment area may be approximately calculated as 
1V‐1.5mx1.8m for each 850 ha of catchment plus one vent for any part of 850 ha for the project under 
consideration.  
 
The  regulators  proposed  under  the  project  on  restored  BRE,  from  Koizuri  to  Hurasagar  (Bherakhola), 
and on the flood embankment of Hurasagar sub‐project (from Bherakhola to Shahjadpur) are: 
 
i) 6V‐1.5mx1.8m‐2 nos at Koizuri (outfall at Jamuna) 
ii) 1V‐1.5mx1.8m‐1 no at Gudhibari (outfall at Jamuna)  
iii) 4V‐1.5mx1.8m‐ 1 no at Gala (outfall at Hurasagar/Boral) 
iv) 2V‐1.5mx1.8m‐1 no at Lochna (outfall at Hurasagar/Boral) 
 
The locations of proposed regulators (JRB 1, Tranch‐1 ) are shown in Figure 3.1. 
 
In  addition  to  that  3  existing  regulators  at  Bherakhola,  Andermanik  and  Lochna  shall  be  repaired  and 
rehabilitated under the project.  
 
However,  the  selection  of  size  shall  be  finalized  after  detail  survey  conducted  during  detail  design 
phase. 
 

 
  Page 61 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

 
Figure 3‐1: Showing the location of all proposed regulators under Tranch‐1 (JRB‐1) 
 

3.3.9 Hydraulic Design  
The hydraulic design of a structure mainly fixes the profile/dimension of the structure, which can safely 
dissipate  the  hydraulic  energy,  counteract  the  seepage  and  uplift  pressure,  the  scouring  activity  etc. 
Generally, hydraulic structures are subjected to seepage of water beneath the structures and the water 
seeping below the body of the structures that endangers its stability and may cause its failure, either 
by:  
 
 Piping or undermining  
 by direct uplift  
 by scour  
 
The  purpose  of  the  hydraulic  design  is  to  provide  necessary  measures  which  will  ensure  its  safety 
against failure caused due to the above reasons. 
 
 
 
Page 62  September 2013 
Technical Designs for Tranch‐1 Work 

Figure 3.2 below explains the basic assumption for calculating the exit gradient and creep. 

C/S R/S
- - - - - -

(1) (2)

(2) (1)
d1

d2
- - -
Cutoff wall
b'
b

Figure 3‐2: Long section of Regulator showing water levels in R/S and C/S 

Total Floor Length (b): 57.90 m; Length of floor from u/s cutoff to d/s cutoff: 57.0 m 
(1) Drainage Condition:  
  (a) C/S water Level: 8.50 m PWD 
(b) R/S water level: 7.5 m PWD;  
Exit Gradient: 0.029 < 1/7 = 0.143; OK 
 
(2) Flushing Condition: 
  (a) C/S Water Level: 8.00 m PWD 
  (b) R/S water Level: 9.00 m PWD 
Exit Gradient: 0.033 < 1/7 = 0.143; OK 
 
On  operating  allowable  creep  is  6.00,  available  creep  is  27.87;  again  with  the  extreme  condition 
generated during highest  high  flood the creep  generated  is  13.20,  which  is  also much  lower then the 
available value. 
 

3.3.10 Energy dissipation arrangement 
The energy of flow through a regulator is normally dissipated through the formation of a hydraulic jump 
within a designed stilling basin. Whereas, the length of a stilling basin is generally determined from the 
length of hydraulic jump required to be confined within the length of the stilling basin.  
 
An energy dissipation arrangement of a structure requires following components to be provided:  
 
 A sloping glacis, generally sloping downward at a slope of not steeper than 1V:3H.  
 A stilling basin, with sufficient length for dissipation of energy  
 A  cutoff  wall  at  the  end  of  floor  of  stilling  basin.  The  depth  of  cutoff  wall  is  kept  below  the 
maximum possible scour level for the designed discharge intensity of flow.  
 Protection work at exit end of the structure as flexible floor in graded inverted filter beyond the 
end of stilling basin  
 Launching apron in two layers of loose cement concrete blocks beyond the end of flexible floor.  
 
 

 
  Page 63 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

A typical longitudinal section is given below in Figure 3.3 to explain the detail 
 

 
Figure 3‐3: Long section of Regulator showing basin and flexible protection at end 
 

3.3.11 Structural Design  
 
The structural  design of all the components of a structure shall be carried out following the standard 
code of practice, Standard Design manual of BWDB and using the specified type of materials.  
 
(Typical design calculation and drawing for a 4V‐1.5mx1.8m flushing cum drainage regulator is enclosed 
in Appendix) 
 
 
   

 
Page 64  September 2013 
Technical Designs for Tranch‐1 Work 

4 Riverbank Protection Works  

4.1 Proposed Works 
The bank protection work has been proposed at the location where there is active bank erosion.  The 
stretches where the eroding bank is very near the existing valuable infrastructures or settlements, are 
also selected under Tranch‐1 for immediate bank protection.  
 
The stretches considered for bank protection under Tranch‐1 are  
 
(i) 1 km in Benotia at the right bank of Brahmaputra‐Jamuna 
(ii) 5 km at Chouhali at the left bank of Brahmaputra‐Jamuna 
(iii) 2 km at Jafarganj at the left bank of Brahmaputra Jamuna 
(iv) 7 km at Harirampur at the left bank of Padma. 
 
Locations of all protection works under Tranch 1 (JRB1, JLB2 and PLB1) are shown in Figure 4.1. 
 
In designing bank protection structures the experience gained and lessons learned from the protection 
works  executed  in  JMREMP  has  been  followed.  In  JMREMP  revetment  for  a  long  reach  using  geobag 
under water and cc block above low water has proved to be very economic and sustainable. The same 
system and technology has been followed in designing the bank protection structures.   
 

 
Figure 4‐1: Showing Locations of Bank Protection Works under Tranch‐1 

4.2 Hydrological Observations 
The Brahmaputra/ Jamuna drains an estimated volume of 620 109 m³ of water per year into the Bay of 
Bengal  with  an  annual  average  discharge  of  19,600  m³/s.  Each  year  the  river  reaches  a  bankfull 
discharge at about 48,000 m³/s. Maximum discharge of about 100,000 m³/s were observed during the 
1988 flood. The Brahmaputra/ Jamuna shows the largest sediment grain sizes and transports the largest 
sediment load. The median diameter of the bed material decreases from 220 mm near Chilmari to 165 
mm near Aricha. The median diameter just downstream of Bangabandhu (Jamuna) Bridge is about 180 
mm. The river stage varies by about 6.0 to 7.0 m. 

 
  Page 65 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

 
The Padma, which is draining the combined flow of the Brahmaputra/Jamuna and the Ganges and the 
lower reach of which is weakly influenced by the tide during the period from December to April, has an 
annual  average  discharge  of  about  28,000  m³/s.  The  seasonal  water  level  variation  is  about  6  m.  The 
bed material sediment of the Padma varies from 140 mm in the upper reaches to 90 mm in the lower 
reaches. 
 
For the major rivers of Bangladesh the statistical return period of the bank full discharge is between one 
and one and a half years.  
 
Bristow (1987) proposed a classification of river channels into different orders. The entire channel is the 
first order channel and comprises a number of smaller second order channels. The latter have slightly 
different characteristics and as a result they show a different behaviour in terms of water level slopes as 
well  as  the  discharge  and  sediment  capacities.  The  shifting  characteristics  of  the  river  can  be  divided 
according to the order of the channel. The rate of shifting of the first order channel is 75 to 150 m per 
year. The second order channels change their course continuously. Larger channels are abandoned and 
new ones develop in a few years only. A bank erosion rate of the second order channels of 250 to 300 m 
per year is common, but in extreme cases it can be more than 800 m per year. 
 
Bank erosion rates of the three main rivers are very similar. However, at Ganges and Padma, the bank 
erosion  is  restricted  to  the  boundary  of  the  active  corridor,  which  consists  of  alluvial  and  deltaic  silt 
deposits, whereas the floodplain outside of it is more resistant to erosion. At the Brahmaputra/ Jamuna 
the flow attacks any of the banks and new channel courses outside the active flood plain are created 
frequently. 
 
The  driving  forces  for  erosion  are  the  high  shear  stresses  by  current  flow,  which  exceed  the  shear 
strength of the soil. The bed erosion at the toe in vertical direction will cause bank erosion and a self‐
induced  adaptation  to  a  slope  which  is  milder  than  the  critical  one.  For  the  design  of  a  protection 
structure, the importance of scouring is evident and consequently has to be taken into account in the 
design  phase.  The  hydraulic  design  parameters,  e.g.  design  water  level  and  design  flow  depth,  act  as 
boundary  conditions  for  the  morphological  parameters.  The  scouring  to  a  certain  scour  depth  is  the 
decisive phenomenon and consequently the main parameter for the design. However, an estimation of 
the  flow  velocities  is  needed  to  optimise  the  size  of  protection  element,  construction  phase  of  the 
protection work, placing of materials and protection elements. 
 

4.3 Data for Bank/Slope Protection  
For designing the protection works, the following hydraulic parameters are required to be established/ 
obtained:  
 
 Water level corresponding to maximum/dominant discharge  
 Maximum discharge / dominant discharge  
 River cross sections  
 Flow velocity  
 Significant wave height  
 Silt factor of river bed material  
 Observed/anticipated maximum scour 
 Wind speed and duration  
  Wave characteristics (fetch length, wave height and wave period  
 
 

 
Page 66  September 2013 
Technical Designs for Tranch‐1 Work 

4.4 Elements of Slope Protection 
Slope  protection  consists  of  a  layer  of  hard  cover  and  a  filter  layer  over  the  slope  along  the  reach  of 
embankment or river bank above LWL. The cover layer must be able to resist hydraulic impacts (current 
and  waves)  while  the  filter  layer  in  between  cover  layer  and  core  materials  is  responsible  to  prevent 
migration of subsoil particles out of the bank  slope (retention criteria)  and  at the same time to allow 
movement  of  water  through  the  designed  filter  (permeability  criteria).  The  revetment  used  for  bank 
protection works must have the following qualities and characteristics:  
 
 The  surface  of  individual  elements  of  the  cover  layer  should  be  sufficiently  resistant  against 
abrasion by wave and current attack  
 The  individual  element should  have  sufficient  weight so  that  it  cannot be  dislodged/  lifted by 
uplift forces  
 The  filter  layer  should  prevent  migration  of  soil  due  to  seepage  pressure  typical  in  tidal 
condition.  
 Should be stable to withstand the forces against sliding in low tide condition and residual pore 
pressure present in itself and other adverse hydraulic conditions.  
 Bank  slope  and  embankment  slope  constructed  by  earth  need  to  be  stable  against  seepage, 
drawdown under normal condition etc. for any type of protection to be applied.  
 
Hand pitched cc blocks are the recommended protection system for the slopes of standard revetment 
structures  above the average  low water  level  (av.LWL). Concrete blocks  are  more durable than bricks 
and less attractive to pilferage. If well dimensioned, they are able to suit any flow condition. Sizes of 20‐
40 cm have proven to be sufficient to withstand the hydraulic loads occurring at the Jamuna river. 
 

4.5 Design Discharges 
4.5.1 Total River Discharges and Number of Channels 
The  protection  work  means  protection  of  river  bank  itself  and  the  protection  of  river  side  slope  of 
embankment. The purpose of protection is to stabilize its slope and achieving protection against erosion 
and scour.  
 
The discharge of  a specific river is obtained  from the analysis of  hydrological data, especially through 
extrapolation of stage discharge relations at water level stations, where also discharge measurements 
have been executed regularly.  
 
The bankfull discharge can be taken from Table below. 
 
Table 4‐1:  Bankfull Discharge of Major Rivers   
River  Bankfull discharge Return period of bankfull  Braiding Index (‐) 
(m3/s)  discharge (years) 
Jamuna  48,000  1.0 4 – 5 
Ganges  43,000  1.4 1 
Padma  75,000  1.05 1 
 
Discharge  characteristics  for  major  rivers  of  Bangladesh  (Source:  Guidelines  and  Design  Manual  for 
Standardized Bank Protection Structures (FAP‐21) 
 
The design discharge Qch for a channel can be calculated by: 
Qch = C1/Cb. 2. Qb 
and Bankful discharge for a canal can be calculated by  
 
  Page 67 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

Q b,ch = Qb/Cb 
 
Where, Qch = design discharge, Canal (m3/sec) 
  Q b.ch = bankful discharge, canal (m3/sec) 
  Qb = bankful discharge, river (m3/sec) 
  C1 = safety factor for extreme canal discharge (C1 =1.5) 
  Cb = Braiding Index (for Jamuna, Cb = 4 to 5, Padma, Cb =1.0) 
 
The design discharge Qch for the left channel of Jamuna according to this approach is  
  Qch = 1.5/4x2x48,000  m3/sec = 36,000 m3/se 
 
4.5.2 Flow Distribution in anabranches 
(a) Brahmaputra‐Jamuna 
The forecasted flow distributions along the anabranches under hydrological condition (a) and (b) at the 
erosion vulnerable  area  at  Chouhali  are shown  in  Table below,  [Source:  Chouhali‐Nagarpur  Feasibility 
Study, IWM]. 
 Hydrological Condition (a) 2003 monsoon  2004 monsoon  2005 monsoon (assume that last 
three years monsoon will repeat for 2006, 2007 and 2008 respectively). 
 Hydrological  Condition  (b)  2001  monsoon    1998  monsoon    2001  monsoon  (assume  that 
average dry year of 2001 for 2006 monsoon, extreme flood year of  1998 for 2007 monsoon and 
again average dry year of 2001 for  2008 monsoon  respectively). 
 
Table  4‐2:    The  Simulated  flow  distribution  along  anabranches  of  the  Jamuna  under 
hydrological condition (a) & (b) 
Channel  Flow distribution in % 
Hydrological Condition (a)  Hydrological Condition (b) 
2006  2007  2008  2006  2007  2008 
Right Channel  71%  65% 69% 75% 62%  60%
Left Channel (Chouhali)  29%  35%  31%  25%  38%  40% 
 
In this case the designer is mainly concerned with the left channel (Chouhali channel). In all cases the 
model has generated a maximum of 40% of flow through the left channel. 
 
Under this condition (as per model Study, IWM), 
 
with Q (100 yr) = 100,000 m3/sec 
Qch = 100,000 x 0.4 = 40,000 m3/sec 
 
In calculating the scour in the left channel (Chouhali) of Jamuna, the channel discharge (calculated by 
model study)  used by IWM (Nagarpur‐Chouhali Project, FS) is 30,129 m3/sec. 
 
Considering the different approach of calculating the discharge through the canal under consideration, 
the Qdesign is taken as 36,000 m3/sec 
 
(b) Padma 
Discharge measurements conducted in Mawa by BWDB show that out of 321 observations from 1994 to 
2012,  maximum  discharge  (Qmax)  is  116,000    m3/sec,  average  discharge  (Qav)  is  55,900  m3/sec, 
maximum velocity (Vmax) is 4.35 m/sec and average velocity (Vav) is 2.67 m/sec. Analysis conducted by 
Padma Bridge Study team  recommends a bankful discharge of 70,000 m3/sec at about EL 5.5m PWD, 
but at higher elevation bankull discharge is higher.   
 
Page 68  September 2013 
Technical Designs for Tranch‐1 Work 

 
Using  the  Regime  type  relations  derived  for  the  major  rivers  of  Bangladesh  by  different  studies 
(Klaassen and Vermeer, 1988; Delft Hydraulics and DHI, 1996),  related channel bankfull width (W) and 
section‐averaged bankfull depth (d) to bankfull discharge (Qb) is expressed as: 
 
W = aQbC 
 
Where a and c are the coefficient and exponent of Qb. Magnitude of 'a' varies in a very wide range, but 
the magnitude of 'c' is found to be very close to 0.5. 
 
Thus, W  aQb0.5   or  Qb  1/a W2 
 
For preliminary assessment of bankfull discharge of any anabrach of a braided or anabranching channel 
bankfull discharge could be distributed based on the ratio of square of bankfull width of the channels.   
 
The discharge in anabranch along the Harirampur can be maximum 70% of the total. To this effect the 
Qdesign for dominant discharge is 52,500 m3/sec.  
 

4.6 Design Water Level 
A stage discharge relation (rating curve) established at the location of the planned structure from long 
term monitoring of daily averaged water levels and corresponding discharges can be used. For selected 
locations, data is available from the BWDB. From the average daily water level the average low water 
level  (av.LWL),  average  high  water  level  (av.HWL)  and  100  yr  HWL  are  calculated.  The  DWL  (Design 
Water Level) is generally above the Flood Plain Level (FPL) and the return period of bankfull discharge 
for Jamuna, Ganges and Padma is between 1.0 and 1.4 years. 
 
100 year HWL, Observed HHWL, Av. LWL and LLWL for Jamuna River at Koizuri, Benotia, Chouhali and 
Zafarganj are given in section 6.2.4 of this report.  
 
For  calculating  Water  level  of  Padma  river  at  Harirampur,  WL  gauges  considered  are  Baruria  Transit 
(91.9L)  and  Mawa  Transit  (93.5L).  The  interpolated  100  year  HWL  at  Harirampur  is  8.70  m  PWD, 
observed maximum HWL is 8.50 m PWD, average LWL is 1.50m PWD and LLWL is 1.00 m PWD. 
 
An example of design water levels with respect to embankment crest levels is provided in Figure 2.3. 
 

4.7 Flow Velocity 
4.7.1 Requirements 
To get basic design data, also the prevalent flow velocities should be recorded, providing horizontal and 
vertical  velocity  profiles.  If  possible,  velocity  measurements  should  be  done  during  monsoon  season 
(bankfull discharge), otherwise extrapolation is needed, to estimate the design conditions. 
 
It has  to  be  taken  into account  that, maximum  flow velocities occur a  few  days before the  maximum 
water level is reached. Therefore, it is physically more accurate, to consider a peak flow instead of the 
design discharge for the evaluation of the design flow velocities. 
 
The design flow velocities in the approach flow of a planned protection structure can be determined in 
various  ways.  It  should  not  be  estimated  only  for  the  deepest  point  of  the  approach  channel  cross 
section but also along the whole bank through: 
 
 Statistical analysis of observed flow velocities; 
 
  Page 69 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

 Simulation in a 2D (depth averaged) mathematical model or in a physical model; 
 Theoretical calculation methods. 
 
4.7.2 Brahmaputra‐Jamuna River 
In  the  case  of  Brahmaputra‐Jamuna  river  the  recorded  measurements  from  BWDB  and  the 
recommendation from Guidelines and Manual for Standardized Bank Protection Structures (FAP‐21) is 
followed 
 
Flow Velocity measured by BWDB at Bahadurabad Transit during: 1990 to 2009. 
Total number of observations: 1695 
 
Table 4‐3:  Measured Velocity in Bahadurabad, Jamuna 
Range of Velocity (m/s)  nos %
0.0 to 1.0  187  11.03 
1.0 to 2.0  1115  65.78 
2.0 to 3.0  356 21.00
3.0 to 3.5  4  0.23 
 
Maximum observed = 3.68 m/sec 
Minimum observed =  0.59 m/sec 
 
The mathematical model study conducted under Chouhali‐Nagarpur FS shows that an erosive near bank 
velocity (> 1.2 m/s) would be generated at Chouhali bank under both hydrological condition (a) and (b). 
The  strong  eroding  velocity  (around  2  m/s)  would  occur  in  future  due  to  confinement  effect  of  the 
channel which might influence the river bed degradation and bank erosion. 
 
Again  the  recommendation  from  the  Guidelines  and  Manual  for  Standardized  Bank  Protection 
Structures (FAP‐21) is as follows: 
 
Table 4‐4:  Limits of Standard Bank Protection Structures 
Structure Category  Depth Averaged Flow  Design Wave  Total Scour/Water 
Expected Impact  Velocity, u [m/s]  Height, Hs [m]  Depth [m] 
Light  <1  <0.25  <10 
Moderate  >1.0 ‐ 2.0 0.25 ‐ 0.5 10‐20 
High  >2.0 ‐ 3.0  0.5‐1.0  20‐30 
Very High  >3.0  >1.0  >30 
 
From the above observations a flow velocity of 3.00 m /sec is selected for the design of straight to areas 
under medium bends, for acute bends and protrusions a velocity of 3.5 m/sec is considered for design. 
 
4.7.3 Padma River 
Depth averaged maximum velocity varies from 2.1 to 2.7 m/ sec with an average of 2.5 m/sec. (USDR, 
Padma  Bridge  Design  Report).    Model  study  conducted  by  IWM  on  Haimchar  Design  states  that,  the 
simulated maximum near bank depth integrated speed appears near Haimchar within the range of 2.75 
to  3.00  m/sec  during  moderate  condition,  3.00  to  3.25  m/sec  during  extreme  and  longer‐term 
conditions. So in case of revetment design for Padma river at Harirampur, the design velocity is taken as 
3.0 m/sec and for protrusions it is taken as 3.5 m/sec. 
 

 
Page 70  September 2013 
Technical Designs for Tranch‐1 Work 

In Chandpur adjacent to Puran bazar  (Ibrahimpur Sakua) and in Haimchar in Lower Meghna river and in 
Sureswar in Padma River depth averaged highest design velocity considered is 3.0 m/sec. The executed 
work from 2007‐08 appear to be stable after several years of observation. 
 

4.8 Size of bed material 
4.8.1 Bed material for Brahmaputra‐Jamuna 
The  Guidelines  and  Manual  for  Standardized  Bank  Protection  Structures  (FAP‐21)  describes  that  the 
median diameter of the bed material of Brahmaputra‐Jamuna decreases from m220 mm near Chilmari 
to m165 mm near Aricha. The average size being about 0.20 mm. In Chouhali‐Nagarpur FS the size of 
average bed material used is 0.18 mm (IWM).  
 
In this case average size of bed material used is 0.18mm (i.e. d50 = 0.18mm) 

4.8.1.1 Scour at Brahmaputra‐Jamuna 
The scour depth has been assessed from Lacey’s formula by applying appropriate scour multiplication 
factor. 
 
Lacey's Regime Equation 
 
R = 0.47 (Q/f)1/3 
 
Where: R = Regime scour depth (m) 
  Q = Design discharge (m3/sec) 
  f = silt factor = 1.76 (dm)1/2 
  dm = average diameter (d50)  
 
Using  the  100  yr  maximum  discharge  (Q100  yr),  Qch  (design)  and  dm  as  100,000  m3/sec,  36,000  m3/sec 
and 0.18mm respectively, the regime scour depth (R) is 17.11m 
 
The eroding area being located in an moderate bend, total scour is 1.5*17.11 = 25.66 m Say 26.0 m 
HWL (High Water Level) at 13.10 m PWD 
 
So the level (depth) of maximum scour at (13.10 m PWD‐26.00 m PWD) ‐12.90 m PWD. However, for 
additional safety, the scour is assumed at ‐16.00 m PWD 
 
The computed scour shall be checked with the observed scour at similar locations and during different 
time  period  of  the  year.  In  general  a  long  series  of  scour  observations  in  similar  locations  is  more 
representative of actual situation than the computed theoretical scour.  
 
Table 4‐5:  Empirical multiplying factors for maximum scour depth 
 
  Nature of Location  Factor 
1  Straight reach Straight reach of Channel  1.25 
2  Moderate Bend  1.50 
3  Severe Bend  1.75 
4  Right angle or abrupt turn  2.00 
5  Noses of piers  2.00 
6  Alongside cliff and walls  2.25 
7  Noses of Guide banks  2.75 
 

 
  Page 71 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

4.8.2 Bed material for Padma 
The  bed  material  sediment  of  the  Padma  varies  from  140  mm  in  the  upper  reaches  to  90  mm  in  the 
lower reaches. The Updated Scheme Design Report (USDR) of Padma Bridge Study suggests 0.13mm as 
the size of bed material.  

4.8.2.1 Scour at Harirampur 
Using the design discharge, Qdesign = 52,500 m3/sec and dm = 0.13 mm  in   
Lacey's Regime equation:  R = 0.47 (Q/f)1/3 , f = 0.63  R = Regime depth = 20.50 m. 
 
The eroding area being located at moderate bend, the scour depth is 1.5x20.50m = 30.75 m  
 
With  WL  at  5.75  m  PWD,  the  scour  level  calculated  is  ‐25.00  m  PWD.  Observed  bed  levels  in  Four  x‐
section measured (from 1971 to 2007) at Padma (RMP 2, 3,4 and 5) show maximum scour depth of ‐
14.5 to ‐37.0 m PWD and an average lowest bed level of ‐9.60 to ‐16.90 m PWD. So a maximum scour at 
‐30.00 m PWD is assumed for the design. 
 

4.9 Waves 
The  maximum  wave  heights  are  generally  caused  by  maximum  wind  speed  over  the  longest  fetch 
length. From observations it is concluded that the maximum wave height with a return period of 100 
years  for  the  design  of  bank  protection  structures  along  the  Brahmaputra‐Jamuna  River  should  be 
about 1.3 m. For a return period of 25 years a design wave height of 1.0 m is commonly used for major 
rivers  of  Bangladesh.  In  this  case  a  wave  height  of  1.3m  is  used.  (Guidelines  and  Manual  for 
Standardised Bank Protection Structures, FAP‐21) 
 

4.10 Design Cross Section  
A morphological analysis of measured cross‐section serves as the best approach to derive information 
on the expected water depths and the cross sectional shape. The bankfull channel width and the bend 
curvature is also available from satellite images and planform analysis. Data of the Jamuna River consist 
of yearly measured standard cross sections recorded during the lean season.  
 
To estimate the outer bank profile and the maximum water depth in the thalweg, an envelope curve of 
measured cross sections (with superimposed cross‐sections) is used.  Figure 4.2 represents on envelope 
of x‐section measured along LB of Jamuna at Chouhali. 
 
From surveyed cross sections of the respective channel a protection structure is planned/designed. Only 
representative cross sections, which are not affected by any river training structure has been used. 
 

 
Page 72  September 2013 
Technical Designs for Tranch‐1 Work 

 
Figure 4‐2: Envelope cure of measured cross‐sections 
 

4.11 Selection of Type of Bank Protection 
The  stability  of  unprotected  river  banks  depends  on  a  number  of  factors  which  have  to  be  assessed 
carefully in the process of selection and design of suitable protection measures. A reliable assessment 
of potential causes of bank failure is indispensable for the success of any measures, i.e. for the integrity 
of the selected bank protection system and thus the stability of the river bank. 
 
Passive bank protection measures are primarily armored structures or armor layers preventing a bank 
line from erosion but which do not create significant interference with the flow. The hydraulic influence 
on  the  local  flow  condition  is  limited  to  changes  in  bed  roughness.  So,  in  this  case  the  selection  of  a 
passive bank protection method is the primary choice.  
 
Typical passive measures are revetment structures, which are built more or less parallel to the flow to 
form an artificial sloped river bank.  
 
Hand pitched cc blocks are the recommended protection system for the slopes of standard revetment 
structures above the water line. If well dimensioned, they are able to suit any flow condition. 
 
Geotextile  sand  containers  (geobags),  which  can  be  tailored  locally,  are  simple  to  be  installed  and 
proposed to be used for areal coverage below LLWL (Lowest Low Water Level) for protection of bank 
slope and revetment toe. 
 
The  experience  gained  from  implementation  and  monitoring  of  the  protection  work  executed  in 
JMREMP has been followed in designing bank protection measures under the project. 
 

4.12 Size and thickness of protection element:  
The  size  of  cover  layer  material  have  been  calculated  by  Pilarczyk  formulae  and  checked  with  USACE 
and JMBA equation considering stability against velocity and wave.  
 
 

 
  Page 73 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

4.13 Size of Elements for Bank Protection 
The  following  various  elements  of  revetment  have  been  selected/calculated  based  on  design  criteria 
and design data. 
4.13.1 Slope Protection above av.LWL: 
Top  Level  of  Revetment:  The  top  level  of  revetment  is  set  at  existing  bank  level  or  flood  plain  level 
where the flood embankment is not provided or the flood embankment is not affected by wave erosion. 
In case of any wave attack on flood embankment, slope protection is provided against anticipated wave. 
The bank slope above LWL and the river side of embankment is protected by CC blocks placed over a 
filter. The size of protection element is the higher size against wave and flow velocity.  The top level of 
revetment works at Chouhali is at flood plain level i.e. at 11.00 m PWD.  
 
Low Water Berm: At a level of about 2.00 m below av.LWL (about +3.5 m PWD in Chouhali) about 5.0 m 
wide berm is proposed to increase the stability of the bank slope.  
 
The bank slope/Revetment slope from LWL berm to the top (Flood Plain Level) shall be 1V:3H. 
 
Protection  Element  above  av.LWL:  For  slope  protection  above  av.LWL,  two  rows  of  cc  blocks  of  size 
400x400x200 mm, followed by one row of cc blocks of size 400x400x300 mm shall be placed on dressed 
and compacted bank slope.  
 
Filter Materials: Minimum 3 mm thick needle punched geo‐textile filter is used over minimum100 mm 
compacted sand (FM≥1.5) fill. The geotextile filter shall be placed at least 1.0m beyond the outer edge 
of LW berm at lower end and at least 1.0 m extra beyond the cc block on flood plain, at upper end, and 
keyed to the ground. 
4.13.2 Under Water Slope Protection: 
Protection Element on LW berm: The LW berm and slope from LW berm to av.LWL shall be protected 
with 2 layers of 300x300x300mm cc block laid on 1 layer of 125 kg geobag over the geotextile filter. 
 
Protection  element  for  areal  coverage:  The  areal  coverage  shall  extend  from  outer  edge  of  LW  berm 
towards deep river for a length of about 30.0 m. The areal coverage shall be composed of minimum 3 
layers of 125kg geobags. The thickness of areal coverage shall be minimum 0.52 m. In protrussion 250 
kg geobags has been proposed to be used in Jamuna and also in Padma.  
 
Performance of 125 kg geobags used in Jamuna as protection element under normal condition and in 
moderate bends is quite satisfactory. 250 kg geobags used in Sureswar in Padma and Ibrahimpur‐Sakua 
and in Haimchar in Lower Meghna river is found to be quite effective as protection element. 
 
However,  dumping  process  followed  in  case  of  areal  coverage  executed  through  manual  labour  and 
properly positioned barge prefers 125 kg geobags as maximum unit size. 
4.13.3 Launching Apron: 
Design  scour  level:  The  design  scour  levels  of  revetment  is  calculated  on  the  basis  of  Lacey's  regime 
theory. The scour calculated in Chouhali is ‐16.0 m PWD.  (Ref. Appendix I for scour computation). 
 
Apron Setting Level: The length of launching apron normally depends on the apron setting level and the 
maximum anticipated scour level. In case of construction in river proper apron setting level varies place 
to  place  depending  on  bed  levels  just  before  construction.  However,  in  the  present  case  the  extent/ 
length of areal coverage is decided in a way that any scour at the end of areal coverage shall not affect 
the slope immediately. 
 

 
Page 74  September 2013 
Technical Designs for Tranch‐1 Work 

Launching Apron: The length of launching apron at the end of areal coverage shall be 15.0 m. Thickness 
of  launching  apron  is  proposed  to  be  minimum  3  layers  of  125  kg  geobags.  In  protrussions  design 
proposes  use  of  125  kg  and  250  kg  geobags  as  protection  element.  The  15.0  m  launching  apron  can 
protect a scour of 15.0 m with only 5‐7m of the apron is launched. In Brahmaputra‐Jamuna the scour in 
one season, in an area protected by revetment can be in general maximum 15.0 m.  
 
(Design Calculation and Design drawings for revetment works at Chouhali is enclosed in Appendix‐I) 
 

4.14 Summary Quantities 
The quantities adopted for key protection work and elements are provided in Table 4‐7. 
 
Table 4‐6  General quantities adopted for Jamuna and Padma 
  Jamuna Padma
Under water 
Length of slope  30 m  35 m 
No. of 125kg geobags on slope  240 (in 3 layers plus 1)  280 (in 3 layers plus 1) 
Length of apron  15 m 15
No. of 125 kg geobags apron  120 (in 3 layers plus 1)  120 (in 3 layers plus 1) 
 
 
Table 4‐7  Quantities adopted for the design 
  JRB‐1  JLB‐2 Chowhali  JLB‐2 Jaffarganj  PLB‐1 
Under water 
125kg geobags [No]  379,000 1,760,000 684,000  1,449,000
250kg geobags [No]  0 102,300 51,000  1,169,000
Above water 
Earth cutting [m³]  143,900 544,700 258,000  460,000
Geotextile sheet [m²]  38,200 188,400 72,000  150,700
Filter sand [m²]  2,500 11,000 4,100  Tranche‐2
Loosely dumped blocks [No]   
40x40x30 cm  43,000 215,000 80,000 
40x40x20 cm  113,500 567,500 218,000  Tranche‐2
30x30x30 cm  190,000 950,000 380,000 
 
 

5 Estimate  
The estimated cost for different interventions proposed under Tranch1 are formulated as per prevailing 
market rates of construction materials, skilled labour, unskilled labour and hire charge of equipments. 
In analysing the unit rate for items of works standard analysis format of BWDB has been used.  
 
Estimate for embankment: For construction of embankment in JRB‐1, the rate used under Bogra Circle 
for construction of embankment by dredged sand/earth from the river has been used with a multiplying 
factor of 25%. The clay lining  in embankment is also taken from Bogra Circle and  is applied with  25% 
increase. 
 
Estimate for Revetment works and structures: The estimate for the revetment works has been formed 
on  the  basis  of  analysed  rate  as  per  present  market  rate  of  cement,  stone  chips,  geotextile  fabrics, 
geobags, filling sand, hire charge of equipments and wage of unskilled and skilled labours. The unit rate 

 
  Page 75 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

for under water dumping of geobags for areal coverage and construction of launching apron is attained 
following the method and sequence of JMREMP.  
 
Finally  the  rate  per  meter  of  protection  in  Jamuna  river  attained  was  55%  to  60%  higher  than  the 
average cost incurred in case of JMREMP protection. The applied rate for Jamuna protection was 75% 
above  the  average  rate  achieved  in  JMREMP  work  in  Kaitala‐Mohanpur  (2003‐04).  Again  in 
consideration of additional scour the applied rate for Padma protection is considered 15% higher than 
that of Jamuna. 
 
The estimated rate of regulator was taken from the analysed rate used in CEIP work presently (2013) 
under process.  
 
Estimated cost for Total Physical Work is : 
 
Total Physical Works  BDT  US$ 
Tranch‐1  4,668,390,449 58,354,881 
Tranch‐2  7,183,026,277  89,787,828 
Tranch‐3  7,998,558,187  99,981,977 
Total  19,849,974,913  248,124,686 
 
 Note:  For  calculating  cost  of  embankment  construction  in  Tranch‐2  and  Tranch‐3,  1m  of  excavation  below  embankment 
base is kept unchanged to accommodate any future change in drainage cost. 
 
The Land Acquisition area has been calculated through the Land Acquisition and Resettlement plan. The 
total  cost for  the  project will therefore be  the amount adding  the  Land Acquisition and Resettlement 
cost plus engineering and investigation plus logistics. 
 
The preliminary estimates for Tranch‐1, Tranch‐2 & Tranch‐3 and some of the basic rates of elements 
used in the estimate is placed as Appendix‐III. 
 
 

6 Alternate Approach for Protection  
 
The  embankment  along  Jamuna  and  also  along  Hurasagar/Boral  might  be  affected  by  wave  action  at 
certain stretches. To take measure against wave erosion the stretches vulnerable to wave action shall 
need to be protected. In doing so two types of protection may be used from HWL+0.50m to toe+1.0m 
(Horizontal).  The  protection  measure  by  400x400x200mm  and  400x400x300mm  CC  block  over  a 
geotextile filter (measure‐I) and by gras‐stone as used along embankment side slope (measure‐II) may 
be  used  from  Tranch‐2  onwards  to  observe  its  affectivity.  The  cost  under  measure‐I  is  about  BDT 
2480.00  per  m2  and  that  under  measure‐II  is  about  BDT  1700.00  per  m2.  In  another  alternative 
(measure‐III) grout filled mattress may be placed against wave protection. In that case the cost per m2 
for a 0.20m thick grout filled mattress shall be about BDT 3420.00 per m2. 
 
However,  it  is  proposed  to  provide  2  km  of  protection  under  Tranch‐1  as  per  measure‐I  in  most 
vulnerable  stretches and another 2 km is proposed under measure‐II to other vulnerable stretches to 
finalise the applicability of any of the measure under subsequent tranches. 
 
 
 
   

 
Page 76  September 2013 
Technical Designs for Tranch‐1 Work 

 
 
 
 
 
 
 
Appendices 
 
Appendix I:  Sample Design Calculation for Bank Protection Works at Chouhali .................................. 78 
Appendix II:  Sample Design Calculation for Regulator at Gala (4V‐ 1.5m x 1.8m) ................................. 93 
Appendix III:  The Preliminary Estimates for Tranch‐1, Tranch‐2 and Tranch‐3 ................................ 122 
Appendix IV:  Design Criteria .............................................................................................................. 131 
Appendix V:  Road on the Land‐Side of Rehabilitated or Reconstructed Embankment ....................... 172 
Appendix VI:  Comment Matrix .......................................................................................................... 198 
 
 
 
   

 
  Page 77 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

Appendix I:  Sample Design Calculation for Bank Protection Works at Chouhali 
 
Design of Bank and Slope Protection Works  on left bank of Jamuna River 

Name of the Project: Main River Flood and Bank Erosion Risk Management Program(FBERMP)
Reach under consideratuin:   Chouhali‐Nagarpur in Tangail District.

Note (i): The section of embankment (crest level, side slope, crest width) stated below is proposed as per frequency of 
hydrological data and stability analysis coducted on proposed embankment section.

Reach / Design under consideration
Name of work : Bank protection work in Chouhali‐Nagarpur along the left bank of Brahmaputra‐Jamuna River.

Embankment Crest Level  15.50 m PWD


HFL (100 yr): 14.00 m PWD
Maxm flood level observed 13.10 m PWD
Average HFL 12.20 m PWD
LLW observed: 4.50 m PWD
Average LWL 5.00 m PWD
Average bank level: 11.00 m PWD (From Survey)

Note (ii): The WL (100yr, Highest observed, av.HWL, av.LWL and LLWL) are interpolated WL from the WL gauges at 
Bangabandhu (Jamuna) Bridge and Aricha. The Ground level is taken fron the survey conducted on the bore‐hole 
location along the left Bank of the River in the stretch mentioned. The bore‐holes for sub‐soil exploration were conducted 
by BWDB under the project from November 2011 to February 2012.

DESIGN DATA

Bankfull Discharge of the River (Qb) => 48,000 m3/sec [From FAP‐24, and Design guidelunes FAP‐21 ]


100 yr discharge of the River (Q100) 100,000 m3/sec
Design Discharge of the Channel (Qch) 36,000 m3/sec (Design Guidelines)
Highest Water Level ‐ Observed (HWL) => 13.10 m PWD
Average Low Water Level (LWL) => 5.00 m PWD
Average Flow Velocity (V) => 3.00 m/sec Suggested flow velocity is  3.00 m/sec

The design discharge Qch for a channel can be calculated by:
3
Qch = C1/Cb. 2. Qb 36,000 m /sec with C1 = 1.5 (FAP‐21 Guidelines)
Cb = 4 (Braiding index)

Note (iii): Channel Discharge (Qch) is calculated from the 100 yr maximum discharge and the distribution of flow in a 
channel suggested by Design Guidelines and Manuals (FAP‐21). The ditribution of flow and the selection of design 
flow (Qch) in the channel is again checked through the results obtained by model study made by IWM in conducting 
the FS of Nagarpur‐Chouhali Project.

Water Surface Slope => 6.00 cm/km (assumed, WL Gauge record analysis)


Average Bed level (near bank) 0.00 m PWD
Maxm scour observed ‐3.00 m PWD
Average size of river bed materials => 0.18 mm (FAP‐24, and Nagarpur‐Chouhali Protection, IWM)
 

 
Page 78  September 2013 
Technical Designs for Tranch‐1 Work 

Existing Embankt slope River side (V:H)  => (  1   : 3 ) (Field office data)


Proposed Slope of  Bank to Avg.LWL. => (  1   : 3 )
Bank slope below av.LWL (V:H) = > (  1   : 2 )

Fetch Length => 7.00 km  (From Model) Use =  7.00 km


Wave Height =>  1.30 m (100 yr wave in Jamuna, FAP‐21 Guidelines)
Wave period  = > 2.45 sec (Guidelines for River Bank Protection,
BWDB‐BUET)
Location of vulnerable area in the River => Moderate bend
Proposed Length of slope + bank Protection => 5000 m (on the left bank of Jamuna River)

A. Design for size of Revetment Materials :

1.0 Against Velocity and Shear:

A‐1. Using Neill's method

D = 0.034 V2 0.306 m  = 306 mm

Note: Neill's equation uses only the velocity. Other variables for a stream are not considered.

A‐2. Using JMBA  equation 

Data:

Flow Velocity ( V ) => 3.00 m/sec (Observed data and Guidelines 


Ratio of water depth and Revetment size (h/D) = 5 FAP‐21)

Slope of Bank 1V:3H ( Θ ) => 18.43 °
Angle of Repose of Revetment Materials, CC Block (Φ ) 40.0 °

Sp.Gravity of Revt.Material, cc block ( Ss )=> 2.40 [‐]


Acceleration due to gravity (g) => 9.81 m/sec2

2
0 .7 v 2
D 
n
2 

s s 

 1  g log 6 h / D 2 . 1  Sin  / Sin  2 
0 .5

0.241 m 241 mm

Note (iv): The JMBA equation is developed for cc blocks. In this case for slope protection cc blocks is pro[osed to be 
used. For bank protection several approach will be tried. However, for this project the JMREMP method, that uses sand 
filled geobags below LLWL, will be preferred.  

 
  Page 79 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

A‐3. Pilarczyk equation

0.035  u 2 φsc K  K h
Dn  Δm  2 g

K s Ψ cr

Dn = Nominal thickness of protection unit  D [m] = size of rock = [m]
u  = average flow velocity = 3.00 m/s
∆m = Relative density of submerged material = (ρs‐ρw)/ρw = [‐]

ρw = Density of water = 1000 kg/m

ρs =  Density of stone boulders/Rocks  =  2650 kg/m

ρs =  Density of concrete (stone aggregate), cc block  =  2400 kg/m

g = accleration due to gravity =  9.81 m/s
φsc = stability factor (for current) = [‐]
θ = Angle of repose (rocks) =  °
Ψcr = critical shear stress parameter (Shields)= [‐]
Kτ = Turbulance factor = 1.5, for mild outer bends of rivers 1.5 [‐]
‐0.2 
Kh = depth factor = (h/Dn+1) =  [‐]
2 1/2;
Ks = Bank normal slope factor = [1‐(sinα/sinθ) ] (specific material)  [‐]
α = slope angle of bank structure = 1V:3H (above LWL) 18.43 °
α = slope angle of bank structure = 1V:2H (below LWL) 26.57 °
h/Dn = [‐]
h= average water depth  ( average depth of water at bankfull stage) 6.00 [m]
Dn = Nominal size of protection unit  (assumed) =  [m]
2 1/2 
Ks = [1‐(sinα/sinθ) ] =  [‐]
Dn = m mm

Note: (v) Logarithmic velocity profiles exist for long stretches with constant bed roughness. For most engineering works 
on slope or bottom protection, non‐developed velocity profile is usually present, (Pilarczyk, 2000).
(vi) In this case non‐developed velocity profile is considerd. 

Non‐Developed Velocity Profile

(1) CC blocks, concrete with stone aggregate (multi‐layer):
Kh = depth factor (for non‐developed vel. profile) = (h/Dn+1)‐0.2 = 0.540
Dn = nominal size of protection element (assumed) = (cc block) 0.29 m
 
 

 
Page 80  September 2013 
Technical Designs for Tranch‐1 Work 

h/Dn = 20.69
∆m = (ρs‐ρw)/ρw =  1.40 [‐]
α = slope angle of bank structure = 1V:2H (below LWL) 26.57 °
α = slope angle of bank structure = 1V:3H (at or above LWL) 18.43 °
θ = Angle of repose (cc blocks) =  40 °
Ks = [1‐(sinα/sinθ)2]1/2 =   (below LWL) 0.718 [‐]
2 1/2     
Ks = [1‐(sinα/sinθ) ] = (at or above LWL) 0.871 [‐]
φsc = stability factor (cc block, randomly placed, multi layer) = 0.80 [‐]
Ψcr = critical shear stress parameter (Shields) = 0.035 [‐]
Dn = 0.296 m = 296 mm (below LWL)
Dn = 0.244 m = 244 mm (at or above LWL)

(2) Rocks:
Kh = depth factor (for non‐developed vel. profile) = (h/Dn+1)‐0.2 = 0.529
Dn = nominal size of protection element (assumed) = (cc block) 0.26 m
h/Dn = 23.08
∆m = (ρs‐ρw)/ρw = 1.65 [‐]
α = slope angle of bank structure = 1V:2H (below LWL) 26.57 °
α = slope angle of bank structure = 1V:3H (at or above LWL) 18.43 °
θ = Angle of repose (rocks) =  35 °
Ks = [1‐(sinα/sinθ)2]1/2 =   (below LWL) 0.626 [‐]
2 1/2     
Ks = [1‐(sinα/sinθ) ] = (at or above LWL) 0.834 [‐]
φsc = stability factor (broken riprap and boulders) = 0.75 [‐]
Ψcr = critical shear stress parameter (Shields) = 0.035 [‐]
Dn = 0.264 m = 264 mm (below LWL)
Dn = 0.198 m = 198 mm (at or above LWL)

(3) CC blocks, concrete with stone aggregate, hand placed/single layer
h = depth of water infront of hand placed cc blocks revetment = 4.00 m
Kh = depth factor (for non‐developed vel. profile) = (h/Dn+1)‐0.2 = 0.497
Dn = nominal size of protection element (assumed) = (cc block) 0.13 m
h/Dn = 32.00
∆m = (ρs‐ρw)/ρw = 1.40 [‐]
α = slope angle of bank structure = 1:3 (above DLW) 18.43 °
θ = Angle of repose =  40 °
Ks = [1‐(sinα/sinθ)2]1/2 =  0.871 [‐]
φsc = stability factor (application type) =  0.65 [‐]
Ψcr = critical shear stress parameter (Shields) 0.05 [‐]
Dn = 0.128 m = 128 mm
 
 

 
  Page 81 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

(4) Geo‐textile bags (sand filled geobag)
Kh = depth factor (for non‐developed vel. profile) = (h/Dn+1)‐0.2 = 0.569
Dn = nominal size of protection element (assumed) = (A1‐type bag) 0.38 m
h/Dn = 16

ρs =  Density of sand bag =  1800 kg/m

ρw =  Density of water =  1000 kg/m
∆m = (ρs‐ρw)/ρw = 0.80 [‐]
α = slope angle of bank structure = 1:2  (below DLW) 26.57 °
θ = Angle of repose (geobags) =  30 °
Ks = [1‐(sinα/sinθ)2]1/2 =  0.447 [‐]
φsc = stability factor  =  0.50 [‐]
Ψcr = critical shear stress parameter (Shields), gabions 0.05 [‐]
Dn = 0.383 m = 383 mm

Recommendation: Recommended size against velocity is =  125 kg

1/3 
Equivalent thickness of bags = (abc)
3
Type Wt (kg) Vol (m ) Eq. Dn
A3‐type 250 0.167 551 mm (Equivalent block size)
A4‐type 175 0.117 489 mm (Equivalent block size)
A5‐type 125 0.083 438 mm (Equivalent block size)
B2‐type 78 0.052 373 mm (Equivalent block size)

3
Unit weight of sand=  1500 kg/m

A‐4. Using Corps of Engineers Relationship (Maynord's Equation, 1991):

1.25
 2

D
 S C C C  V 
 s  1 k 1 g y 
f S v T
Y

(the formula has been developed for rocks)

where;
D = nominal rock size = D30 = (m)
V = Local depth averaged flow velocity = 3.0 m/s
Y = local depth near the bank = 6.0 m
Sf = Safety factor = 1.2 (‐)
Cs = Stability coefficient = 0.30 (‐)
Cv = Vertical velocity distribution coeficient = 1.1 (‐)
CT = Thickness coefficient =  1.2 (‐)
s = dry rock density = 2.65 (‐)
K1 = side slope factor = 1V:2H = 0.9 (‐)
K1 = side slope factor = 1V:3H = (above Low Water Level) 1.0 (‐)

g = accleration due to gravity =  9.81 m/s  
 
 
 
 
 

 
Page 82  September 2013 
Technical Designs for Tranch‐1 Work 

D =D30 = 0.166 m 166 mm (on 1V:2H slope)


D50 = 0.208 m 208 mm
D =D30 = 0.146 m 146 mm (on 1V:3H slope)
D50 = 0.182 m 182 mm

The nominal size D30 may be conveted to a mean diameter D50 by using the equation
D50 = D30x(D85/D15)1/3,  where (D85/D15)1/3 is equql to 1.25 for tyical well graded riprap.

Note (vii). (a) D50 is typically about 25% larger than D30,(b) V is the depth averaged velocity  at a point inshore from 
the slope (c) Y  is the local  flow depth, rock  size  given by the formula is relatively  sensitive  to depth, it is more 
conservative to underestimate  the depth,  (d) minimum value for safety factor (Sf) is 1.1, higher value is suggested 
where there is ice or debris impact, (e) suggested values for  Cv  (vertical velocity distribution factor)  for straight 
channels are 1, and 1.25 at downstream of concrete lined sections and at the end of dykes, (f) values for stability 
 co‐efficient Cs is 0.30 for angular rock and 0.36 for rounded rock. (g) basic value for thickness co‐efficient CT is 
1xD100 or 1.5xD50, whichever is higher, (h)  recommended values for side slope factor K1 is = 1, for slope 1V:3H or 
flatter, K1 = 0.9 for slope 1V:2H, K1 = 0.8, for slope 1V:1.75H, and K1= 0.7 for slope 1V:1.5H. 

2.0 AGAINST WAVE:

Fetch Length => 7.00 km
Wave Height ( Hs ) => 1.30 m (Guidelines for Bank Protection, 
Wave Period (Tm) => 2.45 sec BWDB‐BUET)
Slope of Bank 1V:3H ( θ ) => 18.43 °
Specific gravity of protection materials, rock (Ss)= 2.65 [‐]
Specific gravity of protection materials, cc block (Ss)= 2.40 [‐]

A‐5. Using  Pilarczyk Equation :

H ξ
b

D 
s z

Δ Ψ Φ
n
m u sw
 cosα

Dn = Revetment material size (single unit) [m] [m]
Hs = significant wave height [m] 1.30 m
3
ρw = Density of water = 1000 kg/m
3
ρs = Density  of rocks = 2650 kg/m
3
ρs = Density  of concrete (stone chips, cc block) = 2400 kg/m
∆m = Relative density of submerged material = (ρs‐ρw)/ρw = [‐]
g = accleration due to gravity [m/s2]=  9.81 m/s

Ψu = system specific stability upgrading factor = [‐]
Φsw = stability factor for wave loads, hard rocks  [‐] = [‐]
α = slope angle of bank structure = 1:3 = 18.43 °
 
 

 
  Page 83 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

ξz = wave similarity parameter [ tanα.(1.25Tm/Hs^0.5) 0.90 [‐]


Tm = mean wave period [s] = 2.45 secs
b = wave structure inter action coefficient = [‐]

Protection Element Dn = m ≈

(1) CC blocks with stone aggregate as protection element
(CC blocks, cubical shape, hand placed in single layer)
Ψu = system specific stability upgrading factor [‐] = 2.00 [‐]
Φsw = stability factor for wave loads [‐] = 2.25 [‐]
b = wave structure inter action coefficient [‐] = 0.87 [‐]
∆m = Relative density of submerged material =  1.40 [‐]
Dn = 0.198 m ≈ 198 mm

(2) CC blocks cubical shape, randomly placed multi layer
Ψu = system specific stability upgrading factor [‐] = 1.40 [‐]
Φsw = stability factor for wave loads [‐] = 2.50 [‐]
b = wave structure inter action coefficient [‐] = 0.50 [‐]
∆m = Relative density of submerged material =  1.40 [‐]
Dn = 0.265 m ≈ 265 mm

(3) Broken rocks/boulders, randomly placed
Ψu = system specific stability upgrading factor [‐] = 1.33 [‐]
Φsw = stability factor for wave loads [‐] = 2.50 [‐]
b = wave structure inter action coefficient [‐] = 0.50 [‐]
∆m = Relative density of submerged material =  1.65 [‐]
Dn = 0.236 m ≈ 236 mm

In using CC block (hand placed) for slope protection (above LLW), two rows of 400x400x200 mm cc blocks followed by 
one row of 400x400x300 mm cc blocks will be placed on slope alternately. In consideration of wave height the required  
block thickness (>198mm) can be satisfied with the size 400x400x200 mm. The minimum thickness used by BWDB 
is 200 mm.
Recommended thickness of block is = 200 mm

The protection is considered seperately for (i) the embankment slope from toe to  crest level or upto HHWL (ii) upper part;
of bank slope (from Design low water level (DLWL) to the top of existing bankline or Flood Plain Level (FPL), and (iii) areal 
 coverage of underwater slope and falling apron/launching apron to protect the lower portion of bank section against vertical 
scour induced by stream flow.

3.0 Size of Protection Element

3.1 Size of Protection Element for upper slope (above LWL)  

 
Page 84  September 2013 
Technical Designs for Tranch‐1 Work 

3.1.1 Size of Hard rock as Protection Element (above LWL)

The element size (hard rock) for the upper slope (above LWL) by Pilarczyk formula is 198 mm (at or above LWL) against 
flow velocity and 236mm againt anticipated wave (Hs = 1.30m). By USACE formula the element size on 1V:3H is 182 mm.

Recommended size : Dn = 200 mm

Approximate gradation of pitching stone shall be as below:

Minimum 40% of the stone shall be in the range of  200 mm to 300 mm, 60% will be 300 mm to 400 mm.

3.1.2  Size of CC block as Protection Element (above LWL)

Required thickness of hand placed cc block by Pilarczyk formula against velocity is 128 mm, and that against wave 
is 198mm. The dominant size in this case (hand placed cc block) is 198 mm. 

Recommended (thickness) of cc block = 200 mm

3.2 Size of Protection Element for protection for lower slope (below av.LWL)

3.2.1 Size of Rock as Protection Element (below LWL)

The size of protection element for stability against stream flow velocity is 264 mm by Pilarczyk equation and 208 mm by
USACE equation. so the higher size from both the equation is recommended for protection of lower slope (bank slope 
below av. LWL). D50 size of protection element is 264mm. Shall not be less than 260mm; recommended  size is 260mm.

Dn = 260 mm
Size of 40% of the rocks will be in the range of 200 mm to 300 mm and 60% of the rocks will be in the range of 300 mm 
to 400mm.

3.2.2 Size of CC Block as Protection Element (below LWL)

The size (thickness) of protection element, (randomly placed cc block) by Pilarczyk equation is 296 mm and that by 
JMBA equation is 241 mm. In this case the higher size of protection element through both the equation may be selected 
as protection element. Minimum size (thickness) of cc block is therefore, 296 mm.

The size with standardization is selected as = 300 mm

3.2.3 Size of geobag as protection Element (below LWL)

The size (thickness) of protection element, (randomly placed geobag) by Pilarczyk equation is 383 mm against flow
velocity. The recommended size is 125 kg (geobag), equivalent thickness is 438mm.

Recommended size of geobags is  125 kg Equivalent thickness  438 mm  


 

 
  Page 85 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

4.0 Summary for Pitching Thickness (T):

A. Riprap thickness:

(i) U.S. Army Corps of Engineers (1991), recommends that thickness of protec on should not  less then th spherica
diameter of the upper limit W100 (percent finer by weight) stone or less than 1.5 times the spherical diameter of the
 upper limit W50 stone, whichever results in greater thickness.

(ii) California Highway Division (1991) recommended that there should be at least twolayers of overlapping stones
so that slight loss of materials does not cause massive failure.

(iii) ESCAP (1973) recommends that the thickness of protection should be at least 1.5D, where D is the diameter 
of the normal size rock specified.

(iv) Inglis (1949) recommended following formula to compare thickness of protection required on the slope of revetment:

Where, t (m) = thickness of stone riprap
and Q (m3/s) is  Discharge
Note: the Inglis formula apparently gives excessive thickness for higher discharge.

(v) Indian Standard :    (IS 14262 : 1996)

Minimum thickness of protection layer is required to withstand the negative head created by velocity. 
This may be determined by the following relationship:

Where,
T  =  thickness of protection layer in m
V  = velocity in m/s
g = accleration due to gravity (m/s2) and
Ss = Specific gravity of stones

For safety purposes, two layers of stones according to the size obtained in 3.4 above should be provided.

The formula results in  T= 0.278 m 278 mm

Since the thicknes should not be less than 2 layers, so the recommendation by Califotrnia Highway may be 
accdepted for the design i.e. T=> 2D.  

 
Page 86  September 2013 
Technical Designs for Tranch‐1 Work 

(vi) Using  Inglish formula :
 T= 0.06 Q1/3 = 7.120 ft = 2170 mm

(vii) According  to Spring, on the basis of river slope & river  bed Materials :

River bed  Remarks
materials  Thickness in inches for river slope in 
classified  inches per mile
by Spring 9 12 18 24
Very coarse 19 22 25 28
Coarse 25 28 31 34
Medium 31 34 37 40
Fine 37 40 43 46
Very fine 43 46 49 52

River Bed Materials assumed=> Very fine 
River Slope considered => 3.80 inch/mile
From Chart, Thickness  T => 31 inch = 787.4 mm

(viii) According  to Gales ,  on the basis of discharge:

River Discharge from 0.25  Q' from 0.75 to  Q' from 


to 0.75 million  1.50 million cusecs 1.5 to 2.5 
Body and  Body and  million 
Head
Parts of Guide Bund Head tail tail Head
Pitching Stone 3'‐6'' 3'‐6'' 3'‐6'' 3'‐6'' 3'‐6''
Thickness of soling bal 7'' 7'' 8'' 8'' 9''
Total thickness 4'‐1'' 4'‐1'' 4'‐2'' 4'‐2'' 4'‐3''

Discharge of the River ( Q ) => 1,270,352 Cusec


From Chart, Pitching Thickness ( T ) =>  3'‐6" 3.50 ft 1067 mm

A‐1. Thickness of Protection (Upper slope, slope above LWL)

(a) Based on Stone Size:
(i) U.S. Army Corps of Engineers
T = 1.5xW50 = 300 mm (minimum)

(ii) California Highway Division
T = 2xD = 400 mm

(iii) According  to ESCAP
T = 1.5xD = 300 mm

(iv) Indian Standard
T = 2D = 400 mm  

 
  Page 87 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

(b) Based on Stream flow properties

As per Inglish, T = 2170 mm


As  per  Spring, T = 787 mm
As  per Gales, T = 1067 mm
A.1.1 Thickness of Rock as Protection Element (above LWL)

Considering major eroding forces and other characteristics of the river the minimum thickness suggested by size of 
protection element appears reasonable for pitching. As there will be filter below the pitching, so the thickness suggested 
by recent practices on size of protection material, appears to be  justified.

the thicknes of prtection should not be less than 2 layers of protection element, so the recommendation by California 
Highway Division may be accdepted for the design i.e. T=> 2D.

Above LWL protection thickness, T= 400 mm

Filter: Under the pitching a filter fabric (minimum 3mm thick geotextile filter) shall be provided from top of bank to at 
least 1 m below LWL. Below the filter fabric 100 mm thick sand (FM≥1.0) shall be placed with proper compaction.

A.1.2 Thickness of CC block as Protection Element (above LWL)

The thicknes of cc block above low water is 128 mm (hand placed) against flow velocity and that against wave is 198mm.
The higher thickness of the two i.e. the thickness required against wave is selected for the protection. Recommended 
thickness of cc block is 200 mm.

Thickness of stone (minimum 2 layers) on slope (1V:3H) above LWL, against significant wave is 400 mm. But against 
the same wave height, the thickness of hand placed cc block is 198 mm (Pilarczyk equation). The cc blocks can also 
be arranged in different sequence for breaking waves more eficiently.

So cc blocks of size 400x400x200 mm (2 rows) and 400x400x300 mm (1 row) is proposed to be placed over the slope 
up to bank level+1.50m horizontal on flood plan and keyed to the flood plain. 

Protrussion on a slope is observed to be more efficient than a rough slope for breaking wave. In that consideration cc 
block can be more effectively arranged to create sudden protrussion. With that aim CC block, stable against anticipated 
wave height is recommended to be used on bank and embankment slope.

A‐2. Thickness of Protection (Lower slope, bank slope below LWL)

(a) Based on Stone Size:
(i) U.S. Army Corps of Engineers
T = 1.5xW50 = 390 mm (minimum)

(ii) California Highway Division


T = 2xD = 520 mm  

 
Page 88  September 2013 
Technical Designs for Tranch‐1 Work 

(iii) According  to ESCAP
T = 1.5D = 390 mm

(iv) Indian Standard
T = 2D = 520 mm

(b) Based on Stream flow properties

As per Inglish, T = 2170 mm


As  per  Spring, T = 787 mm
As  per Gales, T = 1067 mm

A.2.1 Thickness of Hard Rock as Protection Element

Considering flow velocity as major eroding force and other characteristics of the river the minimum thickness suggested 
by size of protection element (hard rock) appears reasonable for dumping. As the protection material will be dumped 
under water, so the thickness of dumping need to be 50% more than that required for pitching. 

the thicknes of prtection should not be less than 2 layers of protection element, so the recommendation by Califotrnia 
Highway Division may be accdepted for the design i.e. T=> 2D.

Thickness of pitching required above water (placing) = 2D = 520 mm

Below LWL protection thickness, T= 780 mm
(50% additional due to under water dumping)

For protection below LWL use of hard rock as protection element is the most sustainable solution. Being very costly and 
scarcity of stone in Bangladesh, cc block as protection element (below LWL) is calculated as alternative protection 
element.

A.2.2  Thickness of CC Block as Protection Element (below LWL)

Size of CC block (protection element) against flow velocity is Dn = 300 mm
Considering minimum thickness of protection element below LWL (as in case of rock) as 2D+50% additional (for under 
water dumping), the thickness of protection becomes = 2.5D = 750 mm
However, in case of using cc block the minimum thickness should be 3D (considering winnowing effect) +50%.

The suggested thickness is therefore, 4.5 D = 1350 mm

For protection below the LLWL project intends to use geobag as practiced in JMREMP.  A LWL berm shall be made at 
El, +3.00 m PWD (width about 5.0 m). The slope from av LWL (+ 5.0 m PWD) to the river side end of LWL berm (+3.0m PWD) shall be
protected with two layers of 300mm cube cc blocks  over geotextile filter and one layer of geobag (125kg).

A.2.3 Thickness of Geobag as protection Element (below LWL)

Size of geobag as protection element against flow velocity is 125 mm Equivalent thickness is = 438 mm

Actual size of 125 kg geobag is 930x530x170 mm, 
2
L = 930 mm B = 530 mm t = 170 mm Area = 0.49 m
Suggested actual thickness is = 0.17 m  

 
  Page 89 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

5.0 Design of areal coverage and Launching Apron:
Assumed:
(1) Apron will launch in 1V: 2H slope.
(2) A multiplication factor will be used as per river bend condition.

Table ‐B
(Emperical multiplying factors for 
Data: maxm scoure depth)
Design Discharge ( Q) => 36,000 m3/sec (Jamuna Left Channel)
Highest Water Level (HWL) => 13.10 m new PWD Nature of location Factor
Av. Low Water Level (av.LWL) = 5.00 m new PWD Straight reach of channel 1.25
River bed level at flatter slope   0.00 m new PWD  Moderate Bend 1.50
(assumed av. River bed level) Severe Bend 1.75
Maximum Observed Scour = ‐3.00 m new PWD Right angle or abrupt turn 2.00
Size of av.Bed material (dm) 0.18 mm Noses and Piers 2.00
Silt factor, f = 1.76 (dm)1/2 0.75 Alongside Cliff and Walls 2.25
Noses of Guidebanks 2.75

Note: scour depth for the river is not available. Rather the channel discharge and size of bed material is available 
from different sources (FAP‐24 and Nagarpur‐Chouhali FS). So in this case theoretical scour calculation appear to be
more reliable. The x‐sections are available for only one observation, which is not completely dependable for scour 
calculation.

Scour
1/3
Regime Depth; R = 0.47 (Q/f)  = 17.11 m
The eroding area situated on a moderate bend, so scour depth = 
R*1.5 = 25.66 m Say 26.00 m
Maximum depth of Scour (scour Level) =                    ‐12.90 m PWD Apply ‐13.00 m

Calculations: (materials for bank protection)

The areal coverage shall be placed from av.LWL (+3.0 m PWD) to a level of 0.00 m PWD. Length of areal coverage shall 
be 30.00 m. The falling apron/launching apron material is proposed to be placed at the end of areal/slope coverage. 
The length of launching apron shall be 15.00 m:

Ds = Depth of scour = Av. River bed level ‐ scour level =  13.00 m

Length of launching apron = 1.5xDs = 19.50 m say 20.00 m (Theoretical)

The falling apron is proposed to be placed at the end of areal coverage i.e. on reasonably flat bed. The areal coverage will  be 
placed from av.LWL (+3.0m PWD) to av. river bed level (0.0m PWD). Length of areal coverage shall be 30.0m.

The length of slope surface from (+3.0m) to av. River bed (0.00 m PWD) is  6.71 m
(bank slope below +3.00 is 1V:2H)
The distance along the desired slope surface (slope 1V:2H) from LWL berm to average river bed level 
(from +3.0m to 0.0 m PWD) is  6.71 m
The theoretical launching apron length is =  20.00 m
Minimum coverage needed = 26.71 m

So the length of areal coverage (30 m) and additionally 15.0 m launching apron takes care of all uncertainties including
abnormal scour. The 30.0 m areal coverage is proposed in line with work done under JMREMP in PIRDP area.  

 
Page 90  September 2013 
Technical Designs for Tranch‐1 Work 

Recommended stretch of protection after the LWL Berm

Areal Coverage 30.0 m
Launching Apron 15.0 m

I. Using hard rock as Protection element for Bank Protection

Thickness of hard rock (pitching) = T = 520 mm
Thickness of hard rock below LWL = T1 = 1.5T= 780 mm
Thickness at end of areal cover = T1 =1.5T = 780 mm

3
Volume of rock from av. GL (+11.0 m  to 5.0 m PWD) to av. LWL 11.95 m /m
3
Av. LWL to River side end of berm (5.0m berm) below LWL 8.83 m /m
3
Volume of rock from LWL berm to av. River bed level = 23.40 m /m
3
Volume of rock as apron (15.0m) 11.70 m /m
3
Total element for bank protection per m 55.88 say 56.00 m /m

II. Using cc block above av.LWL, on Transition (LWL Berm to av.LWL) and geobag below LWL

Thickness of cc block (pitching) = T = 200 mm (above LWL, hand placed over a geotextile filter)


Thickness of cc block (pitching) = T = 300 mm (above LWL, hand placed over a geotextile filter)
Size of cc block below LWL = D =  300 mm (coverage, on LWL berm and slope above berm)
Thickness of 125 kg beobag 0.17 m
Thickness  of areal cover (geobag)= 3t= 0.51 m (125 kg geobag, thickness = 0.17m)

Volume of cc blocks
3
From av. GL (+11.0 m to + 5.00 m PWD) to av. LWL  4.42 m /m (slope 1V:3H)
3
From av. LWL to berm (5.0 m) below LWL = 6.79 m /m (300 mm cube, 2 layers)
3
(200 mm and 300mm thick) on flood plain (2.4m +2.0 m below Flood plain) 0.88 m /m
3 3
Total cc blocks (400x400x200 mm and 300 mm cube) 12.10 m /m Adopt 12.10 m /m

3
Volume of geobag (1 layer) on LW berm and slope from Berm to LWL 1.93 m /m
3
Volume of geobags (3 layers) as areal coverage (30.0 m)+33% 20.35 m /m
3
Volume of geobags (3 layers) as launching apron (15.0 m)+33% 10.17 m /m
3 3
Total geobags (125 kg) as areal covrage+ launching apron 32.45 m /m Adopt 32.40 m /m

Design Recommendation

(i) The section under considerstion shall be modified to create a LWL berm. A berm (5.0 m wide) shall be made at about 
El. 3.0 m PWD, the bank slope above that (about 3.00 m to 11.0m PWD) shall be prepared in a slope of 1V:3H.
 

 
  Page 91 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

(ii) Bank protection  (for about 5000m)  with cc block (thickness 200 mm ) is recommended. The reach of protection 
mentioned shall be reviewed with cross‐section measured along the affected reach before execution of the protection work.

(iii) Geotextile filter (thickness>=3.0mm, needle punched) shall be placed below the cc block on slope, and LWL berm 
over minimum 100 mm thick compacted sand (FM>1.5) cushion (above LWL). The geotextile filter shall be extended 
at least 1.0 m beyond the LWL berm at the lower end and 1.5m beyond the cc block on flood plain.

(iv) The berm below LWL and the slope from berm to av.LWL (+3.00 m PWD to +5.0 m PWD) shall be protected with 
2 (two) layers of cc block (300 mm cube) dumped over one (1) layer 125 kg geobag placed over the geotextile filter.

(v) The bank section  from outer end of LWL berm (for an width of about 30m) shall be covered with minimum 3 (three)  
layers of 125kg geobags, dumped from a properly positioned and anchored barge. 

(vi) At the outer end of areal coverage a launching apron (15.0 wide) shall be prepared with minimum 3 layers of 125 kg 
geobags dumped from a properly positioned and anchored barge.

(vii) The coverage of minimum 3 layers of geobag shall be ensured through provision of  an additional one layer of 
geobags i.e. 33% extra over the designed thickness.

(viii) The protection work shall be performed in the sequence as (a) areal coverage, (b) LWL berm and slope preparation
and coverage by designed element and filter, © Launching apron, and (d) flood plain cover as per design.  
 
 
 
 
 
   

 
Page 92  September 2013 
Technical Designs for Tranch‐1 Work 

Appendix II:  Sample Design Calculation for Regulator at Gala (4V‐ 1.5m x 1.8m) 
 
Design Data
Name Of Project: Main River Flood and Bank Erosion Risk Management Program
Name of Sluice: Drainage Sluice at Gala, Kaizuri (Regulator # 3)
Location:  Gala Boral/Hurasagar Size: 4V‐1.5mx1.8m

3 Embankment type:  Composite Section with road at side
(a) Crest Level: 15.60 m PWD
(b) Road Level: 14.10 m PWD
(b) Crest width: 16.20 m 
© Side Slope:  R/S  (1V:xH) 1 3.0
C/S (1V:xH) 1 2.5
4 (a) Highest Water Level (100 yr): 14.10 m PWD (100 yr)
(b) Highest WL (observed) 13.70 m PWD
© Av. HWL 12.40 m PWD
(d) Lowest Water Level (LLW) 4.50 m PWD
(e) Av. Low Water level (av.LWL) 5.20 m PWD
(f) Av. WL (April, 15‐30) 6.81 m PWD
(g) Av. WL (May, 1‐15) 7.50 m PWD
(h) Av. WL (October, 15‐31) 9.40 m PWD
(i) Av. WL (November, 1‐15) 8.12 m PWD

5 Drainage area: 3550 ha
6 Lowest Basin Level 8.50 m PWD
7 Av. ground level around structure 10.50 m PWD
8 Bottom Level of drainage channel m PWD (near outfall)

10 Angle of Internal Friction of soil (φ) 20.00 °  
 
 
 
 
 
 
 
 
 
 
 
 

 
  Page 93 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

SIZING OF REGULATOR/SLUICE (NON TIDAL)

Name of sub‐project :  Main River Flood and Bank Erosion Risk Management Program
Upazila :  Shahzadpur District : Sirajganj
Name of Regulator/Sluice :   Drainage Sluice at Gala, Kaizuri (Regulator # 3)
Size:  4V‐1.5mx1.8m

Flow Considerations:
When Hw > Hv  and Htw > Hv  , Flow Type I QI = 0.80xNxBwxHvx(2x9.81xh')0.5
When Hw > 1.5Hv  and Htw < Hv  , Flow Type III QIII = 0.60xNxBvxHvx{2x9.81x(Hw‐Hv/2)}0.5
When Hw < 1.5Hv  and Htw >2Hv/3  , Flow Type IV QIV = 0.83xNxBvx(Hw‐h')x(2x9.81xh')0.5
When Hw < 1.5Hv  and Htw <2Hv/3  , Flow Type V QV = 1.56xNxBvxHw3/2

Where: Hw = Upstream Water Depth N = Vent Nos.


Htw = Tail Water Depth h' = Head Difference
Hv = Vent Hieght Q = Flow through Regulator
Bv = Vent Width

Input Data:
N = 4 nos. RWL 7.50 mPWD
BV = 1.50 m Basin WL = 8.50 mPWD
HV = 1.80 m Design Q = 14.79 m3/Sec
Sill Level = 7.00 mPWD

RWL HW HTW h' Flow Type Q


3
(mPWD) (m) (m) (m) m /Sec

7.5 1.50 0.50 1.00 V 17.20


17.20 OK

Catchment Area  = Subproject area : 3550 ha


Drainage area outside 0 ha

Total 3550 ha

Drainage rate  (  Monsoon)   = 30 mm/day
Discharge =  12.33 cumec
For structure dischage adding 20% 14.79 cumec

Total = 14.79 cumec

Capacity of Regulator to drain = 16.25%

Provide:  4Vent‐1.50m x 1.80m ; Sill Level: 7.00 m pwd  

 
Page 94  September 2013 
Technical Designs for Tranch‐1 Work 

Name of Project: Main River Flood and Bank Erosion Risk Management Program
Regulator/Structure: Drainage Sluice at Gala, Kaizuri (Regulator # 3)
District: Sirajganj DRAINAGE MODE Size: 4V-1.5mx1.8m

OUTLET (D/S) STILLING BASIN DESIGN R/S


REQUIRED INPUT DATA

Design U/S Water Level --> 8.50 m from field data 5


Design D/S Water Level --> 7.50 m from out fall river level analysis.
(Mean low water Level/ tide level )
No. of Vents --> 4
Inside Barrel Height (Hb)--> 1.80 m [Pre-monsoon drainage is assumed
Inside Barrel Width (Bb) --> 1.50 m for 1st fortnight of May]
Barrel Invert Level --> 7.00 m PWD
Distance between abutments (Ba) 7.80 m

D/S Basin Invert Level --> 6.00 m, PWD


U/S Basin Invert Level --> 6.50 m, PWD
Gate Clearance Side (Cs) --> 0.00 m
Gate Clearance Bottom(Cb) -> 0.00 m
Glacis Length (Gl) --> 3.00 m
Basin Flare Angle (ø) --> 7.50 °
Pier Thickness 0.60 m
Protective Apron Side Slope; (Ss) --> (1 : 2.00 ) Vertical:Horizontal
Ground Level (near Structure) 10.50 m

U/S
8.50

D/S

7.50
1.80
7.00
0.00
6.00
//\\//\ //\\//\
3.00
Barrel Glacis Basin

STRUCTURE SECTION

STRUCTURE PLAN
Protective
Appron side
Slope1: 2.0

7.50 °
0.00

1.50 Protective
7.80 Pier Glacis Basin Apron

 
  Page 95 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

Final Result 
Drainage Sluice at Gala, Kaizuri (Regulator # 3)
Size: 4V‐1.5mx1.8m DRAINAGE MODE

Total discharge = 17.20 m³/sec Flow Condition= 5

Basin Level adjacent to Barrel  7.00 m PWD


Basin Level (D/S) 6.00 m PWD

Critical depth (dc) = 0.94 m
Value of d1 = 0.31 m
Subsequent d1 = 0.31 m

Froude no  (F1) = 3.78
Basin Type: Indian Standard Stilling Basin I

TWD (available) = 1.50 m
TW min 1.49 m
Value of d2 = 1.49 m

Length of Jump = 6.85 m
Glacis Length (Gl) = 3.00 m
Use basin length (L) = 8.50 m Value of X = 1.48 m
Value of X used = 1.50 m
Flaring angle 7.50 °
Height of Chute = 0.31 m
Vale of B3 = 10.80 m Used value = 0.50 m
Velocity V3 = 0.83 m/sec
Value of A3 20.70 m²

Silt Factor = 0.68
Scour depth (Regime) =  2.08 m

U/S scour depth = 2.60 m
D/S scour depth = 3.12 m

U/S cut off wall= 0.60 m Use  3.00 m


D/S Cut‐off wall= 1.63 m Use  4.00 m

C/S block Prot. = 3.00 m Use 5.00 m


C/S Loose apron = 4.50 m Use 5.00 m

R/S Block Prot.= 6.00 m Use  6.00 m


R/S Loose apron = 6.00 m Use  6.00 m  
 
 
 

 
Page 96  September 2013 
Technical Designs for Tranch‐1 Work 

Name of Project: Main River Flood and Bank Erosion Risk Management Program
Regulator/Structure: Drainage Sluice at Gala, Kaizuri (Regulator # 3) Size: 4V‐1.5mx1.8m
District: Sirajganj
FLUSHING MODE
INLET (U/S) STILLING BASIN DESIGN C/S
REQUIRED INPUT DATA

Design U/S Water Level   ‐‐> 8.00 m from field data 5


Design D/S Water Level   ‐‐> 9.00 m from out fall river level analysis.
(Mean low water Level/ tide level )
No. of Vents             ‐‐> 4
Inside Barrel Height (Hb)‐‐> 1.80 m
Inside Barrel Width (Bb) ‐‐> 1.50 m
Barrel Invert Level      ‐‐> 7.00 m PWD
Dist.between box Abutments(Ba)‐> 7.80 m

D/S Basin Invert Level   ‐‐> 6.00 m, PWD


U/S Basin Invert Level   ‐‐> 6.50 m, PWD
Gate Clearance Side (Cs) ‐‐> 0.00 m
Gate Clearance Bottom(Cb) ‐> 0.00 m
Glacis Length (Gl)       ‐‐> 1.50 m
Basin Flare Angle (ø)    ‐‐> 7.50 °
Thickness of pier 0.60 m
Protective Apron Side Slope; (Ss) ‐‐> (1 : 2.00 ) Vertical:Horizontal
Ground Level (near structure) 10.50 m PWD

D/S
8.00

U/S

9.00
1.80
7.00
0.00
6.50
//\\//\ //\\//\
1.50
Barrel Glacis   Basin

STRUCTURE SECTION

STRUCTURE PLAN
Protective 
Appron side
Slope1: 2.0

7.50 °
0.00

1.50   Protective
7.80  Pier Glacis Basin     Apron

 
  Page 97 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

Final Result  Drainage Sluice at Gala, Kaizuri (Regulator # 3)
Size: 4V‐1.5mx1.8m FLUSHING MODE

Total discharge  (Qd)= 26.47 m³/sec Flow Type = 5

Level Adjacent to Barrel 7.00 m PWD


Basin Level (U/S) 6.50 m PWD

Critical depth  (dc)= 1.25 m
Value of d1 = 0.54 m
Subsequent d1 = 0.52 m

Froude no  (F1) = 2.76
Basin Type: Indian Standard Stilling Basin I

TWD (available) = 2.00 m
TW min 1.78 m
Value of d2 = 1.78 m

Use co‐efficient= 1.00 Indian Standard Stilling Basin I

Length of Jump = 6.80 m
Glacis Length (Gl) ‐‐>  1.50 m
Use basin length (L) = 8.50 m Value of X = 1.78 m
Value of X used = 1.80 m
Flaring angle 7.50 °
Height of Chute = 0.52 m
Vale of B3 = 10.40 m Used value = 0.50 m
Velocity V3 = 0.92 m/sec
Value of A3 28.80 m²

Silt Factor  (f) = 0.68

Scour depth (Regime) =  2.84 m

U/S scour depth = 3.55 m
D/S scour depth = 4.26 m

U/S cut off wall= 1.05 m Use  3.00 m


D/S Cut‐off wall= 2.47 m Use  4.00 m

C/S block Prot. = 3.00 m Use 5.00 m


C/S Loose apron = 4.50 m Use 5.00 m

R/S Block Prot.= 6.00 m Use  6.00 m


R/S Loose apron = 6.00 m Use  6.00 m
 

 
Page 98  September 2013 
Technical Designs for Tranch‐1 Work 

NANE OF PROJECT: Main River Flood and Bank Erosion Risk Management Program
Name of Structure: Drainage Sluice at Gala, Kaizuri (Regulator # 3)
Sirajganj Size: 4V-1.5mx1.8m
2.0 STRUCTURAL ANALYSIS OF BARREL

2.1 REQUIRED INPUT DATA

Embankment Crest Level --> 15.60 m PWD


Road Level (inside) --> 14.10 m PWD
Embankment Crest width 16.20 m Top slab level=
Top Slab Level --> 9.25 m PWD = Invert levl+Vent ht+Top slab thick
9.25 m PWD
Maximum Water Level (monsoon) - 14.10 m PWD
Maximum Water Level --> 9.50 m PWD Operating Deck Level =Max WL+0.5
(maintenance period) 14.50 m PWD
Operating Deck Slab level 14.50 m PWD
Live Vehicle Loading(H10 or H20) -> H20

Unit Weight of Steel --> 77.00 KN/m³


Unit Weight of Concrete --> 23.60 KN/m³
Unit Weight of Soil --> 18.90 KN/m³
Unit Weight of Water --> 9.81 KN/m³

Angle of Internal Friction (ø) --> 20 °


Coeff. of Active Earth Pressure (Ca) = (1-sinø) = 0.66

Top Slab Thickness --> 450 mm


Bottom Slab Thickness --> 500 mm Embankment side slope
Abutment Top Thickness (Barrel)--> 450 mm (a) R/S, 1V:xH 1 2.5
Abutment Bottom Thickness (Barrel)- 500 mm (b) C/S; 1V:xH 1 3.0
Pier Thickness --> 600 mm

No. of Vents --> 4


Inside Height of Barrel --> 1.80 m
Inside Width of Barrel --> 1.50 m
Invert Level 7.00 m PWD
Length of Barrel --> 20.00 m Length of Barrel = 20.00 m
Barrel Ext.Length (C/S) --> 1.80 m
Barrel Ext.Length (R/S) --> 1.80 m

STRUCTURAL DESIGN OF BARREL

Ultimate Flexural Strength of Steel (fy) --> 4.14E+05 KN/m² 60,044 psi
Ultimate Flexural Strength of Concrete(fc') 2.20E+04 KN/m² 3,191 psi

Allowable Flexural Strength of Steel (fs) = 0.45* fy = 1.86E+05 KN/m²


Allowable Flexural Strength of Concrete(fc) = 0.4* f'c = 8.80E+03 KN/m²

Allowable Shear Stress of Concrete(v) = 2.89*(fc')^0.5 = 4.29E+02 KN/m²

Modulus of Elasticity of Steel (Es) --> 1.96E+08 KN/m²


Modulus of Elasticity of Concrete (Ec) --> 1.98E+07 KN/m²

Coverage + 1/2 Dia.Reinforcement (c) --> 75 mm

SCHEMATIC VIEW OF BARREL


15.60 m
\\\///\\\///\\\///
450 mm
9.25 m

450 mm

1.80 m

500 mm
500 mm 600 mm
|:: 1.50 m  

 
  Page 99 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

Drainage Sluice at Gala, Kaizuri (Regulator # 3)


Size: 4V-1.5mx1.8m
STRUCT2 : DESIGN ABSTRUCTS

STRUCTURAL ANALYSIS OF BARREL

TOP SLAB
Design Moment M= 48.83 KNm
Reqd. depth dr(mom) = 197 mm
Design Shear V= 138.87 KN
Reqd. depth dr(shear) = 324 mm
Reqd.Thickness tr = 399 mm
Provided thickness ta = 450 mm

SHRINKAGE REINF (top slab).

Ast (reqd. exp.face) = 950 mm²


Ast (provided)
Bar dia. (ø) = 16 mm
Bar spacing c/c = 200 mm
Ast (Actual) = 1005 mm²
Ast(reqd, earth face) 570 mm²
Ast provided
Bar dia. (ø) = 12 mm
Bar spacing c/c = 175 mm
Ast (Actual) = 646 mm²

TOP REINF (Top Slab).

Ast (mom.) = 782 mm²


Ast (shrinkage) = 380 mm²

Ast (provided) 782 mm²


Bar dia. (ø) = 16 mm
Bar spacing c/c = 250 mm
Ast (Actual) = 804 mm²

BOTTOM REINF.(Top slab)

Ast (mom.) = 391 mm²


Ast (shrinkage) = 760 mm²
Ast (provided) 760 mm²
Bar dia. (ø) = 16 mm
Bar spacing c/c = 250 mm
Ast (Actual) = 804 mm²

BOTTOM SLAB

Design Moment M= 53.63 KNm


Reqd. depth dr(mom) = 207 mm
Design Shear V= 152.68 KN
Reqd. depth dr(shear) = 356 mm
Reqd.Thickness tr = 431 mm
Provided thickness ta = 500 mm
 
 

 
Page 100  September 2013 
Technical Designs for Tranch‐1 Work 

SHRINKAGE REINF (Bottom Slab).

Ast (reqd. exp.face) = 950 mm²


Ast (provided)
Bar dia. (ø) = 16 mm
Bar spacing c/c = 200 mm
Ast (Actual) = 1005 mm²
Ast (reqd.earth face) = 570 mm²
Ast (provided)
Bar dia. (ø) = 12 mm
Bar spacing c/c = 175 mm
Ast (Actual) = 646 mm²

TOP REINF.(Bottom Slab)

Ast (mom.) = 379 mm²


Ast (shrinkage) = 760 mm²
Ast (provided)= 760 mm²
Bar dia. (ø) = 16 mm
Bar spacing c/c = 250 mm
Ast (Actual) = 804 mm²

BOTTOM REINF (Bottom Slab).

Ast (mom.) = 758 mm²


Ast (shrinkage) = 380 mm²
Ast (provided) 758 mm²
Bar dia. (ø) = 16 mm
Bar spacing c/c = 250 mm
Ast (Actual) = 804 mm²

ABUTMENTS

Design Moment(Top) M = 44.37 KNm


Reqd. depth dr(mom) = 188 mm
Design Shear(Top) V= 114.53 KN
Reqd. depth dr(shear) = 267 mm
Reqd.Thickness tr = 342 mm
Provided thickness ta = 450 mm

Design Moment(Bottom) M = 48.78 KNm


Reqd. depth dr(mom) = 197 mm
Design Shear(Bottom) V = 129.13 KN
Reqd. depth dr(shear) = 301 mm
Reqd.Thickness tr = 376 mm
Provided thickness ta = 500 mm  
 
 
 

 
  Page 101 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

SHRINKAGE REINF (Abutment).

Ast (exp.face) = 950 mm²


Ast (provided)
Bar dia. (ø) = 16 mm
Bar spacing c/c = 200 mm
Ast (Actual) = 1005 mm²

Ast (earth face) = 570 mm²


Ast (provided)
Bar dia. (ø) = 12 mm
Bar spacing c/c = 175 mm
Ast (Actual) = 646 mm²

EXPOSED FACE REINF.(Abutment)

Design moment M= 22.72 KNm


Top thickness ta(top) = 450 mm
Bottom thickness ta(bot) = 500 mm
Length of member l= 2.28 m
Depth at zero shear d(zs)= 1.14 m
Actual thickness ta(zs) = 475 mm

Ast (mom) = 341 mm²


Ast (shrinkage) = 760 mm²
Ast (provided) 760 mm²
Bar dia. (ø) = 16 mm
Bar spacing c/c = 250 mm
Ast (Actual) = 804 mm²

EARTH FACE REINF (Abutment, contd).

Moment at top M(top) = 44.37 KNm


Reinf.top Ast(top,mom) = 711 mm²
Moment at bottom M(bot) = 48.78 KNm
Reinf.botm. Ast(bot,mom) = 689 mm²
Shrinkage reinf. Ast(sk) = 380 mm²
Ast (provided) 711 mm²
Bar dia. (ø) = 16 mm
Bar spacing c/c = 275 mm
Ast (Actual) = 731 mm²

PIERS

Design Moment M= 11.12 KNm


Reqd. depth dr(mom) = 94 mm
Design Shear V= 22.77 KN
Reqd. depth dr(shear) = 53 mm
Reqd.Thickness tr = 169 mm
Provided thickness ta = 600 mm  

 
Page 102  September 2013 
Technical Designs for Tranch‐1 Work 

REINFORCEMENTS (Pier)

Ast (mom.) = 127 mm²


Ast (shrinkage) = 760 mm²
Ast (provided) 760 mm²
Bar dia. (ø) = 16 mm
Bar spacing c/c = 250 mm
Ast (Actual) = 804 mm²

Dimension of the Structure:


Box bottom width (outside) 8.80 m

Length of Barrel i/c extensions: 23.60 m


D/S Floor length i/c glacis 11.80 m
U/S Floor length i/c glacis 10.30 m
D/S Floor extension (Return wall toe) 1.80 m
U/S Floor extension (Return wall toe) 1.60 m
Total Floor Length: 49.10 m  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
  Page 103 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

Name of Project: Main River Flood and Bank Erosion Risk Management Program
Regulator/Structure: Drainage Sluice at Gala, Kaizuri (Regulator # 3)
WINGWALL AND APRON (R/S) Sirajganj Size: 4V-1.5mx1.8m
Structure details

Embankment Crest El 15.60 m PWD


Elevation of Operating Deck 14.50 m PWD
El of Wing top adjacent to Barrel Extension 13.90 m PWD
El of Wing top just above Glacis End 12.80 m PWD
El of wing wall at end (top)/GL(River side) 10.50 m PWD
Barrel Invert Level/Sill Level 7.00 m PWD
El of Wing bottom adjacent to Barrel Extension 7.00 m PWD
El of wing bottom at glacis end 6.00 m PWD

Barrel Extension R/S" 1.80 m


Barrel Extension C/S" 1.80 m

Length of wing wall from Op Deck end to GL 10.50 m


Glacis length (1V:3H) 3.00 m
Wing wall top surface slope to GL (1V:xH) 1 3
Length of wing wall (Lw)-total 11.80 m
Flat /Horizontal floor adjacent to barrel extension 0.3 m

1.0 REQUIRED INPUT DATA

SECTION LENGTH WINGWALL APRON WINGWALL APRON


from (S1) Thick(mm) Height Thick Width Height Width
(m) (Top) (Bot) (m) (mm) (m) (m) (m)
S L Tt Tb H Ta B H' B'
1-1 3.00 300 750 6.90 800 8.51 7.30 9.26
2-2 6.50 300 750 5.73 800 9.43 6.13 10.18
3-3 8.50 300 650 5.07 700 9.96 5.42 10.61
4-4 10.00 300 500 4.57 600 10.35 4.87 10.85
5-5 11.80 300 500 4.50 600 10.83 4.80 11.33

H' = Height of Wingwall from Apron c/l


B' = Width of Apron from c/l of Wingwalls

Length of Wingwall = (L² + ((B - B1)/2)²)^0.5 = 11.86 m


3
Unit Weight of Steel (γst) --> 77.0 KN/m³ 490 lb/ft
3
Unit Weight of Concrete (γc) --> 23.6 KN/m³ 150 lb/ft
3
Unit Weight of Soil (γs) --> 18.8 KN/m³ 120 lb/ft

Angle of Internal Friction (ø) --> 20 °


Coeff. of Active Earth Pressure (Ca) = (1-sinø)/(1+sinø) = 0.490

Ultimate Flexural Strength of Steel (fy) --> 4.14E+05 KN/m² 60,044 psi
Ultimate Flexural Strength of Concrete(fc') 2.20E+04 KN/m² 3,191 psi

Allowable Flexural Strength of Steel (fs) = 0.45*fy = 1.86E+05 KN/m²


Allowable Flexural Strength of Concrete(fc) = 0.4*f'c = 8.80E+03 KN/m²
 

 
Page 104  September 2013 
Technical Designs for Tranch‐1 Work 

5.4 SUMMARY OF DESIGN INFORMATION Drainage Sluice at Gala, Kaizuri (Regulator # 3)


WINGWALL AND APRON (R/S)
Size: 4V-1.5mx1.8m
DEPTH Of SECTION

Wing Wall Apron


Member dr (req) tr (req) ta (Prov) dr (req) tr (req) ta (Prov)

1-1 635 710 750 672 747 800


2-2 481 556 750 512 587 800
3-3 399 474 650 425 500 700
4-4 342 417 500 365 440 600
5-5 334 409 500 357 432 600

REINFORCEMENT

SHRINKAGE REINFORCEMENT
EXPOSED EARTH
MEMBER Ast (req) φ (dia) Spacing Ast (act) Ast (req) φ (dia) Spacing Ast (act)
2 2 2 2
(mm ) (mm) (mm) (mm ) (mm ) (mm) (mm) (mm )
WINGWALL
1-1 950 16 200 1005 570 12 200 565
2-2 950 16 200 1005 570 12 200 565
3-3 950 16 200 1005 570 12 200 565
4-4 950 16 200 1005 570 12 200 565
5-5 950 16 200 1005 570 12 200 565

APRON
1-1 950 16 200 1005 570 12 200 565
2-2 950 16 200 1005 570 12 200 565
3-3 950 16 200 1005 570 12 200 565
4-4 950 16 200 1005 570 12 200 565
5-5 950 16 200 1005 570 12 200 565

Main Reinforcement
Top/Exposed Bottom/Earth
Ast (req) φ (dia) Spacing Ast (act) Ast (req) φ (dia) Spacing Ast (act)
2 2 2 2
(mm ) (mm) (mm) (mm ) (mm ) (mm) (mm) (mm )
Wingwall
1-1 760 16 250 804 4490 25 100 4909
2-2 760 16 250 804 2576 25 150 3273
3-3 760 16 250 804 2087 25 175 2805
4-4 760 16 250 804 2067 20 150 2094
5-5 760 16 250 804 1978 20 150 2094

Apron
1-1 950 16 200 1005 4694 25 100 4909
2-2 950 16 200 1005 2722 25 150 3273
3-3 950 16 200 1005 2175 25 175 2805
4-4 950 16 200 1005 1907 20 150 2094
5-5 950 16 200 1005 1827 20 150 2094

 
  Page 105 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

MEMBER THICKNESS, BOND AND BAR CURTAILMENT WINGWALL AND APRON (R/S)

Member Thickness Bond


Member Reqd. Act. Design Allowable Act Design.
2 2
tr (mm) ta (mm) OK/Not OK (KN/m ) (KN/m ) OK/not OK
WINGWALL
1-1 710 750 OK 673 463 OK
2-2 556 750 OK 673 480 OK
3-3 474 650 OK 673 513 OK
4-4 417 500 OK 841 604 OK
5-5 409 500 OK 841 587 OK

APRON
1-1 747 800 OK - - -
2-2 587 800 OK - - -
3-3 500 700 OK - - -
4-4 440 600 OK - - -
5-5 432 600 OK - - -

Bar Curtailment
Height or Width (B/2) 1st curtailment 2nd Curtailment
(m) Loc (m) Yes/No Loc (m) Yes/No
Wing Wall
1-1 6.90 2.13 Yes 3.38 Yes
2-2 5.73 1.24 Yes 2.43 Yes
3-3 5.07 1.29 Yes 2.27 Yes
4-4 4.57 1.45 Yes 2.22 Yes
5-5 4.50 1.37 Yes 2.15 Yes

APRON
1-1 4.26 4.26 No 4.26 No
2-2 4.72 2.80 Yes 4.72 No
3-3 4.98 2.36 Yes 4.98 No
4-4 5.18 2.41 Yes 5.43 Yes
5-5 5.41 2.31 Yes 5.66 Yes

USER DEFINED REINFORCEMENT

MEMBER
SHRINKAGE REINFORCEMENT
EXPOSED FACE EARTH FACE
Ast(req) φ (bar dia) spacing Ast(act) Ast(req) φ (bar dia) spacing Ast(act)
2 2 2 2
(mm ) (mm) (mm) (mm ) (mm ) (mm) (mm) (mm )
WINGWALL
1-1 950 16 200 1005 570 12 200 565
2-2 950 16 200 1005 570 12 200 565
3-3 950 16 200 1005 570 12 200 565
4-4 950 16 200 1005 570 12 200 565
5-5 950 16 200 1005 570 12 200 565

APRON
1-1 950 16 200 1005 570 12 200 565
2-2 950 16 200 1005 570 12 200 565
3-3 950 16 200 1005 570 12 200 565
4-4 950 16 200 1005 570 12 200 565
5-5 950 16 200 1005 570 12 200 565

 
Page 106  September 2013 
Technical Designs for Tranch‐1 Work 

WINGWALL AND APRON (R/S)


Size: 4V-1.5mx1.8m

MAIN REINFORCEMENT
TOP/ EXPOSED BOTTOM/ EARTH
Ast(req) φ (bar dia) spacing Ast(act) Ast(req) φ (bar dia) spacing Ast(act)
2 2 2 2
(mm ) (mm) (mm) (mm ) (mm ) (mm) (mm) (mm )
WINGWALL
1-1 760 16 250 804 4490 25 100 4909
2-2 760 16 250 804 2576 25 150 3273
3-3 760 16 250 804 2087 25 175 2805
4-4 760 16 250 804 2067 20 150 2094
5-5 760 16 250 804 1978 20 150 2094

APRON
1-1 950 16 200 1005 4694 25 100 4909
2-2 950 16 200 1005 2722 25 150 3273
3-3 950 16 200 1005 2175 25 175 2805
4-4 950 16 200 1005 1907 20 150 2094
5-5 950 16 200 1005 1827 20 150 2094

Sec # Sec Dist Sec sec


(m) Width (m) height (m)
Sec 0-0, W0 0.00 7.80 6.90
Sec 1-1, W1 3.00 8.51 6.90
Sec2-2,W2 6.50 9.43 5.73
Sec3-3,W3 8.50 9.96 5.07
Sec4-4,W4 10.00 10.35 4.57
Sec 5-5,W5 11.80 10.83 4.50
 
 
 
 
 
 
 
 
 
 
 
 

 
  Page 107 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

Name of Project: Main River Flood and Bank Erosion Risk Management Program
Regulator/Structure: Drainage Sluice at Gala, Kaizuri (Regulator # 3) Size: 4V-1.5mx1.8m
WINGWALL AND APRON (C/S) Sirajganj

Structure details
Creset level of Embankment 15.60 m PWD
Operation Deck Elevation 14.50 m PWD
El of Wing Top adjacent to Barrel Extension 13.38 m PWD
El of Wing Top just above Glacis End 12.66 m PWD
El of wing wall at end (top)/GL (Country side) 10.50 m PWD
Barrel Invert Level/Sill Level 7.00 m PWD
El of Wing bottom adjacent to Barrel Extension 7.00 m PWD
El of wing bottom at glacis end 6.50 m PWD

Barrel Extension R/S" 1.80 m


Barrel Extension C/S" 1.80 m

Length of wing wall from OP deck end to Glacis end 7.50 m


Glacis length (1V:3H) 1.50 m
Embankment slope (C/S), 1V:xH 1 2.5

Length of wing wall (Lw) 10.30 m


Flat /Horizontal floor adjacent to barrel extension 0.30 m

1.0 REQUIRED INPUT DATA

SECTION LENGTH WINGWALL APRON WINGWALL APRON


from (S1) Thick(mm) Height Thick Width Height Width
(m) (Top) (Bot) (m) (mm) (m) (m) (m)
S L Tt Tb H Ta B H' B'
1-1 1.50 300 650 6.38 700 8.12 6.73 8.77
2-2 3.50 300 650 5.48 700 8.64 5.83 9.29
3-3 6.50 300 550 4.28 600 9.43 4.58 9.98
4-4 9.30 300 500 4.00 550 10.17 4.28 10.67
5-5 10.30 300 450 4.00 500 10.43 4.25 10.88

H' = Height of Wingwall from Apron c/l


B' = Width of Apron from c/l of Wingwalls

Length of Wingwall = (L² + ((B - B1)/2)²)^0.5 = 10.36 m


3
Unit Weight of Steel (γst) --> 77.0 KN/m³ 490 lb/ft
3
Unit Weight of Concrete (γc) --> 23.6 KN/m³ 150 lb/ft
3
Unit Weight of Soil (γs) --> 18.8 KN/m³ 120 lb/ft
Angle of Internal Friction (ø) --> 20 °
Coeff. of Active Earth Pressure (Ca) = (1-sinø)/(1+sinø) = 0.490

Ultimate Flexural Strength of Steel (fy) --> 4.14E+05 KN/m² 60,044 psi
Ultimate Flexural Strength of Concrete(fc') 2.20E+04 KN/m² 3,191 psi

Allowable Flexural Strength of Steel (fs) = 0.45*fy = 1.86E+05 KN/m²


Allowable Flexural Strength of Concrete(fc) = 0.4*f'c = 8.80E+03 KN/m²

Allowable Shear Stress of Concrete(v) =2.89*f'c^0.5 = 4.29E+02 KN/m²  

 
Page 108  September 2013 
Technical Designs for Tranch‐1 Work 

Drainage Sluice at Gala, Kaizuri (Regulator # 3)


5.4 SUMMARY OF DESIGN INFORMATION WINGWALL AND APRON (C/S)
Size: 4V-1.5mx1.8m
DEPTH Of SECTION

Wing Wall Apron


Member dr (req) tr (req) ta (Prov) dr (req) tr (req) ta (Prov)

1-1 564 639 650 597 672 700


2-2 449 524 650 477 552 700
3-3 310 385 550 330 405 600
4-4 280 355 500 298 373 550
5-5 280 355 450 297 372 500

REINFORCEMENT

MEMBER SHRINKAGE REINFORCEMENT


EXPOSED EARTH
Ast (req) φ (dia) Spacing Ast (act) Ast (req) φ (dia) Spacing Ast (act)
2 2 2 2
(mm ) (mm) (mm) (mm ) (mm ) (mm) (mm) (mm )
WINGWALL
1-1 950 16 200 1005 570 12 200 565
2-2 950 16 200 1005 570 12 200 565
3-3 950 16 200 1005 570 12 200 565
4-4 950 16 200 1005 570 12 200 565
5-5 950 16 200 1005 570 12 200 565

APRON
1-1 950 16 200 1005 570 12 200 565
2-2 950 16 200 1005 570 12 200 565
3-3 950 16 200 1005 570 12 200 565
4-4 950 16 200 1005 570 12 200 565
5-5 950 16 200 1005 570 12 200 565

Main Reinforcement
Top/Exposed Bottom/Earth
Ast (req) φ (dia) Spacing Ast (act) Ast (req) φ (dia) Spacing Ast (act)
2 2 2 2
(mm ) (mm) (mm) (mm ) (mm ) (mm) (mm) (mm )
Wingwall
1-1 760 16 250 804 4167 25 100 4909
2-2 760 16 250 804 2640 20 100 3142
3-3 760 16 250 804 1523 20 150 2094
4-4 760 16 250 804 1389 20 150 2094
5-5 760 16 250 804 1575 20 150 2094

Apron
1-1 950 16 200 1005 4285 25 100 4909
2-2 950 16 200 1005 2741 20 100 3142
3-3 950 16 200 1005 1559 20 150 2094
4-4 950 16 200 1005 1403 20 150 2094
5-5 950 16 200 1005 1558 20 150 2094
 

 
  Page 109 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

WINGWALL AND APRON (C/S)


MEMBER THICKNESS, BOND AND BAR CURTAILMENT Size: 4V-1.5mx1.8m

Member Thickness Bond


Member Reqd. Act. Design Allowable Act Design.
2 2
tr (mm) ta (mm) OK/Not OK (KN/m ) (KN/m ) OK/not OK
WINGWALL
1-1 639 650 OK 673 465 OK
2-2 524 650 OK 841 429 OK
3-3 385 550 OK 841 475 OK
4-4 355 500 OK 841 463 OK
5-5 355 450 OK 841 525 OK

APRON
1-1 672 700 OK - - -
2-2 552 700 OK - - -
3-3 405 600 OK - - -
4-4 373 550 OK - - -
5-5 372 500 OK - - -

Bar Curtailment
Height or Width (B/2) 1st curtailment 2nd Curtailment
(m) Loc (m) Yes/No Loc (m) Yes/No
Wing Wall
1-1 6.38 1.76 Yes 2.95 Yes
2-2 5.48 1.24 Yes 2.33 Yes
3-3 4.28 1.04 Yes 1.87 Yes
4-4 4.00 0.83 Yes 2.00 Yes
5-5 4.00 0.94 Yes 1.69 Yes

APRON
1-1 4.06 4.06 No 4.06 No
2-2 4.32 3.00 Yes 4.32 No
3-3 4.72 1.92 Yes 4.72 No
4-4 5.08 1.78 Yes 5.33 Yes
5-5 5.22 1.90 Yes 5.44 Yes

USER DEFINED REINFORCEMENT

MEMBER
SHRINKAGE REINFORCEMENT
EXPOSED EARTH
Ast(req) φ (bar dia) spacing Ast(act) Ast(req) φ (bar dia) spacing Ast(act)
2 2 2 2
(mm ) (mm) (mm) (mm ) (mm ) (mm) (mm) (mm )
WINGWALL
1-1 950 16 200 1005 570 12 200 565
2-2 950 16 200 1005 570 12 200 565
3-3 950 16 200 1005 570 12 200 565
4-4 950 16 200 1005 570 12 200 565
5-5 950 16 200 1005 570 12 200 565

APRON
1-1 950 16 200 1005 570 12 200 565
2-2 950 16 200 1005 570 12 200 565
3-3 950 16 200 1005 570 12 200 565
4-4 950 16 200 1005 570 12 200 565
5-5 950 16 200 1005 570 12 200 565
 

 
Page 110  September 2013 
Technical Designs for Tranch‐1 Work 

WINGWALL AND APRON (C/S)

MAIN REINFORCEMENT
member TOP/ EXPOSED BOTTOM/ EARTH
Ast(req) φ (bar dia) spacing Ast(act) Ast(req) φ (bar dia) spacing Ast(act)
2 2 2 2
(mm ) (mm) (mm) (mm ) (mm ) (mm) (mm) (mm )
WINGWALL
1-1 760 16 250 804 4167 25 100 4909
2-2 760 16 250 804 2640 20 100 3142
3-3 760 16 250 804 1523 20 150 2094
4-4 760 16 250 804 1389 20 150 2094
5-5 760 16 250 804 1575 20 150 2094

APRON
1-1 950 16 200 1005 4285 25 100 4909
2-2 950 16 200 1005 2741 20 100 3142
3-3 950 16 200 1005 1559 20 150 2094
4-4 950 16 200 1005 1403 20 150 2094
5-5 950 16 200 1005 1558 20 150 2094

Section Sec dist width (m) Height (m)


(m)
Sec 0-0, W0 0.00 7.80 6.38
Sec 1-1, W1 1.50 8.12 6.28
Sec2-2,W2 3.50 8.64 5.48
Sec3-3,W3 6.50 9.43 4.28
Sec4-4,W4 9.30 10.17 4.00
Sec 5-5,W5 10.30 10.43 4.00
 
 
 
 
 
 
 
 
 
 
 
 
 

 
  Page 111 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

Name of Project: Main River Flood and Bank Erosion Risk Management Program
Regulator/Structure: Drainage Sluice at Gala, Kaizuri (Regulator # 3)
RETURN WALL (D/S)
Sirajganj Size: 4V-1.5mx1.8m
1.0 REQUIRED INPUT DATA

3
Unit Weight of Steel (γst) --> 77.00 KN/m
3
Unit Weight of Concrete (γc) --> 23.60 KN/m
3
Unit Weight of Soil (γs) --> 18.90 KN/m
Unit Weight of Water (γw) --> 9.81 m/sec/sec

Angle of Internal Friction (ø) --> 20 °


Coeff. of Active Earth Pressure (Ca) = (1-sinø)/(1+sinø) = 0.49
Coeff. of Friction (f) --> 0.50

Return Wall Top Level --> 10.50 m PWD


Bottom Slab Level --> 6.00 m PWD

Return Wall Top Thick --> 300 mm


Return Wall Bottom Thick -> 500 mm
Bottom Slab Thickness --> 600 mm

Height of Return Wall (H) = 4.50 m


Height of Return Wall i/c base (H') = 5.10 m

Length of Return Wall --> 9.50 m


Length of Heel --> 2.00 m P1 = 70.36
Length of Toe --> 1.80 m P2 = 60.79
Total Length (width) of B.Slab = 4.30 m 84.31%

Ultimate Flexural Strength of Steel (fy) = 4.14E+05 KN/m² 60,044 psi


Ultimate Flexural Strength of Concrete(f'c) = 2.20E+04 KN/m² 3,191 psi

Allowable Flexural Strength of Steel (fs) = 0.45*fy = 1.86E+05 KN/m²


Allowable Flexural Strength of Concrete(fc) = 0.4*f'c = 8.80E+03 KN/m²

1/2
Allowable Shear Stress of Concrete(v) = 2.89* f'c = 4.29E+02 KN/m²

1/2 2
Allowable Bond Stress (bs(allow)) = 113.40*f'c /d = 1.68E+04 /d KN/m

(d = Bar Diameter, mm) OR --> 1103 KN/m² (whichever is less)

Modulus of Elasticity of Steel (Es) --> 1.96E+08 KN/m²


Modulus of Elasticity of Concrete (Ec) --> 1.98E+07 KN/m²

Coverage + 1/2 Dia.Reinforcement (c) --> 75 mm

b = Unit Width of Member = 1.00 m


n = Modular Ratio = Es / Ec = 9.90
r = fs /fc = 21.17
k = n/(n + r) = 0.319
j = Lever Arm Coefficient = 1 - k/3 = 0.894
R = Resisting Moment Coefficient = fc*j*k/2 = 1.25E+03 KN/m²

 
Page 112  September 2013 
Technical Designs for Tranch‐1 Work 

Drainage Sluice at Gala, Kaizuri (Regulator # 3)


USER DEFINED REINFORCEMENT RETURN WALL (D/S) Size: 4V-1.5mx1.8m

MEMBER SHRINKAGE REINFORCEMENT


EXPOSED EARTH
Ast (req) φ (dia) spacing Ast (act) Ast (req) φ (dia) spacing Ast (act)
(mm2) (mm) (mm) (mm2) (mm2) (mm) (mm) (mm2)

STEM 950 16 200 1005 570 12 200 565

HEEL 950 16 200 1005 570 12 200 565

TOE 950 16 200 1005 570 12 200 565

MAIN REINFORCEMENT
TOP/EXPOSED BOTTOM/EARTH
Ast (req) φ (dia) spacing Ast (act) Ast (req) φ (dia) spacing Ast (act)
(mm2) (mm) (mm) (mm2) (mm2) (mm) (mm) (mm2)

STEM 570 12 200 565 1989 20 125 2513

HEEL 1425 16 125 1608 - - - -

TOE - - - - 1279 16 125 1608

STABILITY

LOADS AND MOMENTS


Total weight = 281.97 KN
Resisting moment = 796.37 KNm
Over turning moment = 204.87 KNm

F.S (over turning) = 3.89 Should be > 1.5


F.S (sliding) = 1.17 Should be > 1.5

FOUNDATION PRESSURE
Resultant action point from toe = 2.10 m
Ecentricity e = 0.05 m

Pressure at toe, P1 = 70.36 KN/m²


Pressure at heel, P2 = 60.79 KN/m²

MEMBER THICKNESS
Member thickness
Member Moment Shear Required Provided
dr(mom) dr(shear) tr(req) ta(act)
(KNm) (KN) (mm) (mm) (mm) (mm)
STEM 140.73 93.82 335 219 410 500
HEEL 124.55 126.03 315 294 390 600
TOE 111.82 123.04 299 287 374 600

Note: Heel: top tension and shear downward


Toe : bottom tension and shear upward
 
 

 
  Page 113 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

REINFORCEMENTS RETURN WALL (D/S)

Member Ast requird


moment shrink Bar dia Spacing Ast
ø @ provided
(mm²) (mm²) (mm) (mm c/c) (mm²)
STEM Ver exp face 570 12 200 565
Ver earth face 1989 - 20 125 2513
Hor exp face 950 16 200 1005
Hor earth face 570 12 200 565

HEEL Hor main(top) 1425 - 16 125 1608


Hor.top(long) 950 12 200 565
Hor botm(short) 380 12 300 377
Hor botm(long) 570 12 200 565

TOE Hor main(botm) 1279 - 16 125 1608


Hor.top(long) 950 16 200 1005
Hor top(short) 380 12 300 377
Hor botm(long) 570 12 200 565

BAR CURTAILMENTS

Member Curt. ht. Depth of Curt. pt.


from top sectn.at 24ø above bot Ast Ast
h curt.pt. slab, x momt. shrink
(m) da (mm) (mm) (m) (mm²) (mm²)
STEM 1st curtailment 3.76 392 480 1.22 1257 380
2nd curtailment 2.88 353 480 2.10 628 380

BOND
Bar Bond Max(allow Design Total bar Bond
Member dia. allowab able)bond shear perimeter develop
ø bs(allow) stress V tp bs(ac.)
(mm) (KN/m²) (KN/m²) (KN) (mm) (KN/m²)

STEM 20 841 1103 93.82 503 491


HEEL 16 1051 1103 -126.03 402 -668
TOE 16 1051 1103 123.04 402 249

Note:
0.00  
 
 
 
 

 
Page 114  September 2013 
Technical Designs for Tranch‐1 Work 

Name of Project: Main River Flood and Bank Erosion Risk Management Program
Regulator/Structure: Drainage Sluice at Gala, Kaizuri (Regulator # 3)
RETURN WALL (C/S) Size: 4V-1.5mx1.8m
Sirajganj
1.0 REQUIRED INPUT DATA

3
Unit Weight of Steel (γst) --> 77.00 KN/m
3
Unit Weight of Concrete (γc) --> 23.60 KN/m
3
Unit Weight of Soil (γs) --> 18.90 KN/m
Unit Weight of Water (γw) --> 9.81 m/sec/sec

Angle of Internal Friction (ø) --> 20 °


Coeff. of Active Earth Pressure (Ca) = (1-sinø)/(1+sinø) = 0.49
Coeff. of Friction (f) --> 0.50

Return Wall Top Level --> 10.50 m PWD


Bottom Slab Level --> 6.50 m PWD

Return Wall Top Thick --> 300 mm


Return Wall Bottom Thick -> 450 mm
Bottom Slab Thickness --> 500 mm

Height of Return Wall (H) = 4.00 m


Height of Return Wall i/c base (H') = 4.50 m

Length of Return Wall --> 8.50 m


Length of Heel --> 1.80 m P1 = 60.08 psf
Length of Toe --> 1.60 m P2 = 55.54 psf
Total Length (width) of B.Slab = 3.85 m 85.56%

Ultimate Flexural Strength of Steel (fy) = 4.14E+05 KN/m² 60,044 psi


Ultimate Flexural Strength of Concrete(f'c) = 2.20E+04 KN/m² 3,191 psi

Allowable Flexural Strength of Steel (fs) = 0.45*fy = 1.86E+05 KN/m²


Allowable Flexural Strength of Concrete(fc) = 0.4*f'c = 8.80E+03 KN/m²

1/2
Allowable Shear Stress of Concrete(v) = 2.89* f'c = 4.29E+02 KN/m²

1/2 2
Allowable Bond Stress (bs(allow)) = 113.40*f'c /d = 1.68E+04 /d KN/m

(d = Bar Diameter, mm) OR --> 1103 KN/m² (whichever is less)

Modulus of Elasticity of Steel (Es) --> 1.96E+08 KN/m²


Modulus of Elasticity of Concrete (Ec) --> 1.98E+07 KN/m²

Coverage + 1/2 Dia.Reinforcement (c) --> 75 mm

b = Unit Width of Member = 1.00 m


n = Modular Ratio = Es / Ec = 9.90
r = fs /fc = 21.17
k = n/(n + r) = 0.319
j = Lever Arm Coefficient = 1 - k/3 = 0.894
R = Resisting Moment Coefficient = fc*j*k/2 = 1.25E+03 KN/m²  
 

 
  Page 115 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

Drainage Sluice at Gala, Kaizuri (Regulator # 3)


USER DEFINED REINFORCEMENT RETURN WALL (C/S) Size: 4V-1.5mx1.8m

MEMBER SHRINKAGE REINFORCEMENT


EXPOSED EARTH
Ast (req) φ (dia) spacing Ast (act) Ast (req) φ (dia) spacing Ast (act)
(mm2) (mm) (mm) (mm2) (mm2) (mm) (mm) (mm2)

STEM 570 12 200 565 380 12 300 377

HEEL 570 12 200 565 380 12 300 377

TOE 570 12 200 565 380 12 300 377

MAIN REINFORCEMENT
TOP/EXPOSED BOTTOM/EARTH
Ast (req) φ (dia) spacing Ast (act) Ast (req) φ (dia) spacing Ast (act)
(mm2) (mm) (mm) (mm2) (mm2) (mm) (mm) (mm2)

STEM 570 12 200 565 1583 20 150 2094

HEEL 1288 16 150 1340 - - - -

TOE - - - - 1075 16 150 1340

STABILITY

LOADS AND MOMENTS


Total weight = 222.58 KN
Resisting moment = 563.59 KNm
Over turning moment = 140.73 KNm

F.S (over turning) = 4.00 Should be > 1.5


F.S (sliding) = 1.19 Should be > 1.5

FOUNDATION PRESSURE
Resultant action point from toe = 1.90 m
Ecentricity e = 0.03 m

Pressure at toe, P1 = 60.08 KN/m²


Pressure at heel, P2 = 55.54 KN/m²

MEMBER THICKNESS
Member thickness
Member Moment Shear Required Provided
dr(mom) dr(shear) tr(req) ta(act)
(KNm) (KN) (mm) (mm) (mm) (mm)
STEM 98.84 74.13 281 173 356 450
HEEL 91.13 101.89 270 238 345 500
TOE 76.10 94.62 246 221 321 500

Note: Heel: top tension and shear downward


Toe : bottom tension and shear upward  
 

 
Page 116  September 2013 
Technical Designs for Tranch‐1 Work 

REINFORCEMENTS RETURN WALL (C/S) Size: 4V-1.5mx1.8m

Member Ast requird


moment shrink Bar dia Spacing Ast
ø @ provided
(mm²) (mm²) (mm) (mm c/c) (mm²)
STEM Ver exp face 570 12 200 565
Ver earth face 1583 - 20 150 2094
Hor exp face 570 12 200 565
Hor earth face 380 12 300 377

HEEL Hor main(top) 1288 - 16 150 1340


Hor.top(long) 570 12 300 377
Hor botm(short) 380 12 300 377
Hor botm(long) 380 12 300 377

TOE Hor main(botm) 1075 - 16 150 1340


Hor.top(long) 570 12 200 565
Hor top(short) 380 12 300 377
Hor botm(long) 380 12 300 377

BAR CURTAILMENTS

Member Curt. ht. Depth of Curt. pt.


from top sectn.at 24ø above bot Ast Ast
h curt.pt. slab, x momt. shrink
(m) da (mm) (mm) (m) (mm²) (mm²)
STEM 1st curtailment 3.41 353 480 1.07 1047 380
2nd curtailment 2.63 324 480 1.85 524 380

BOND
Bar Bond Max(allow Design Total bar Bond
Member dia. allowab able)bond shear perimeter develop
ø bs(allow) stress V tp bs(ac.)
(mm) (KN/m²) (KN/m²) (KN) (mm) (KN/m²)

STEM 20 841 1103 74.13 419 528


HEEL 16 1051 1103 -101.89 335 -800
TOE 16 1051 1103 94.62 335 237

Note:
0.00  
 
 
 
 
 
 

 
  Page 117 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

Name of Project: Main River Flood and Bank Erosion Risk Management Program
Location: Kaizuri
Name of Structure: Drainage Sluice at Gala, Kaizuri (Regulator # 3)
Size: 4V-1.5mx1.8m

EXIT GRADIENT AND UPLIFT PRESSURE (Non Tidal Zone)

REQUIRED INPUT DATA

Maximum Water Level C/S & R/S


Highest High Water Level (observed) 13.70 m PWD
Maximum Water Level C/S 11.50 m PWD (Average ground level+ 1.0 m)

Drainage Mode (R/S Floor Thickness)


Design C/S Water Level --> 8.50 m PWD
Design R/S Water Level 7.50 m PWD

Flushing Mode (C/S Floor Thickness)


Design C/S Water Level --> 8.00 m PWD Monsoon WL
Design R/S Water Level --> 9.00 m PWD 1 in 20 year WL
IL 4.45
U/S Apron Level --> 6.50 m PWD C/S Dr. 0.60
D/S Apron Level --> 6.00 m PWD R/S Dr. 0.60

Elevation at bottom of U/S Cutoff Wall --> 3.50 m


Elevation at bottom of D/S Cutoff Wall --> 2.00 m

3.00 Cut off depth,c/s


4.00 Cut off depth,r/s

Elevation underneath apron at U/S Cutoff Wall-> 6.00 m PWD


Elevation underneath apron at D/S Cutoff Wall -> 5.40 m PWD

Appron End Thickness


Provided (U/S) 0.50 0.14 Required
Provided (D/S) 0.60 0.17 Required

Total Floor Length (b) --> 49.10 m


Distance between U/S and D/S Cutoff Walls (b')-> 48.20 m

Intermediate Points where Floor Thickness is Desired:


Section Length (m) from
Section 1 (U/S)
-------------- -------------- -------------- ----
1 (U/S) 0.00
2 10.05
3 11.85 SCHEMATIC VIEW OF STRUCTURE
4 35.35
5 38.65 Drainage Mode Water Levels ---------
6 (D/S) 48.20 Flushing Mode Water Levels - - - - -

1.00 9.90 1.40 1.40 12.40 1.00

8.50 m 8.50 9.00 m


0.70 -*----- -------------- -*- - - -------
7.80 Barrel 7.80 =Bank 0.70
U/S D/S
8.00 m 7.50 m
1.30 -*- - - ------- -*----- -------------- 1.80
4.45
B3 = 4.00 6.50 m 0.00 6.00 m Apron 4.00 =B3
0.50 0.50 0.60 0.00 0.00
6.00 m 5.40
2 3 4 5 6 <-- Cutoff
3.00 1.00 9.50 1.80 23.50 3.30 10.50 1.00 Wall
4.00
3.50 m 2.00
48.20 m
49.10 m

EXIT GRADIENT  

 
Page 118  September 2013 
Technical Designs for Tranch‐1 Work 

Exit gradient is calculated using Khosla's equation.

Drainage Mode

Ge = Exit Gradient = H/d*(1/pi*r^0.5)

H = Design Head = U/S Water Level - D/S Water Level = 1.00 m

d = Length (depth) of D/S Cutoff Wall


= D/S Channel Level - Elevation at bottom of D/S Cutoff Wall 4.00 m

b = Total Floor Length = 49.10 m

a = b/d = 12.28

r = (1 + (1 + a^2)^0.5)/2 = 6.66

Ge = 0.031 <›_ Maximum Permitted Gradient (1/7)

Floor and D/S Cutoff Wall Length is O.K.

Flushing Mode

Ge = Exit Gradient = H/d*(1/pi*r^0.5)

H = Design Head = 1.00 m

d = Length (depth) of U/S Cutoff Wall = 3.00 m

a = b/d = 16.37

r = (1 + (1 + a^2)^0.5)/2 = 8.70

Ge = 0.036 <›_ Maximum Permitted Gradient (1/6 to 1/7) 0.143

Floor and D/S Cutoff Wall Length is O.K.

UPLIFT PRESSURE

The method used to determine the percentage uplift at various key points underneath the structure was
developed by Khosla. The key points at the U/S and D/S cut-off walls are defined in the figure below.

U/S D/S

E1 C1 E6 C6

D1 D6

Drainage Mode

Upstream Cutoff Wall

b = Total Floor Length = 49.10 m


d = Length (depth) of U/S Cutoff Wall = 3.00 m

a = b/d = 16.37
r = (1 + (1 + a^2)^0.5)/2 = 8.70

øE1 = 100%

øC1 = 100% - acos((r-2)/r)/pi = 77.98%

øD1 = 100% - acos((r-1)/r)/pi = 84.59%

øC1 must be corrected for the following conditions:


c1 = correction due to effect of D/S Cutoff Wall
c2 = correction due to thickness of floor

c1 = 19 * (d"/b')^0.5 * (d'+d")/b

b = Total Floor Length = 49.10 m  

 
  Page 119 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

b' = Distance between U/S and D/S Cutoff Walls = 48.20 m

d' = Elevation underneath apron at U/S Cutoff Wall minus


Elevation at bottom of U/s Cutoff Wall 2.50 m

d" = Elevation underneath apron at D/S Cutoff Wall minus


Elevation at bottom of D/S Cutoff Wall 3.40 m

c1 = 60.64% (+ve)

c2 = [(øD1 - øC1)*Tc1]/d1

Tc1 = Thickness of Concrete at Section 1 (U/S)


= U/S Apron Level - Elev. underneath apron at U/S Cutoff Wall = 0.50 m

d1 = Depth of U/s Cutoff Wall =


U/S Apron Level - Elevation at bottom of U/S Cutoff Wall = 3.00 m

c2 = 1.10% (+ve)

øC1 (corrected) = øC1 + c1 + c2 = 139.72%

Downstream Cutoff Wall

a = b/d = 12.28

r = (1 + (1 + a^2)^0.5)/2 = 6.66

øC6 = 0%

øE6 = acos((r-2)/r)/pi = 25.34%

øD6 = acos((r-1)/r)/pi = 17.67%

øE6 must be corrected for the effect of the U/S Cutoff Wall (c1) and thickness of floor (C2)

c1 = 19 * (d"/b')^0.5 * (d'+d")/b = 19.00 0.20 0.108 = 0.41% (-ve)

c2 = [(øE6 - øD6)* Tc6]/d6 1.15%

øE6 (corrected) = øE6 + c1 + c2 = 23.78%

Required Concrete Thickness

Design Head (H) = U/S Water Level - D/S Water Level = 1.00 m

u = submerged unit weight of concrete= unit weight of concrete / unit weight of water = 1.41

Concrete Thickness (m) = H* φ /u

Section Length from φ% Concrete Uplift Pressure Used (t)


upstream end (m) Thickness (m) (Kn/m2) R/S (m)
1 U/S 0.00 139.72% 0.99 13.71
2 10.05 115.54% 0.82 11.33
3 11.85 111.21% 0.79 10.91
4 35.35 54.69% 0.39 5.36 0.80
5 38.65 46.75% 0.33 4.59 0.70
6 D/S 48.20 23.78% 0.17 2.33 0.60

Flushing Mode

Upstream Cutoff Wall

a = b/d = 16.37

r = (1 + (1 + a^2)^0.5)/2 = 8.70

øC1 = 0%

øE1 = acos((r-2)/r)/pi = 22.02%

øD1 = acos((r-1)/r)/pi = 15.41%

øE1 must be corrected for the effect of the D/S Cutoff Wall (c1) and the thickness of floor (c2)  

 
Page 120  September 2013 
Technical Designs for Tranch‐1 Work 

c1 = 19 * (d"/b')^0.5 * (d'+d")/b = 19.00 0.29 0.13 = 0.72%

c2 = [(øE1 - øD1)*Tc1]/d1 = 1.10% (-ve)

øE1 (corrected) = øE1 + c1 + c2 = 20.20%

Downstream Cutoff Wall

a = b/d = 12.28

r = (1 + (1 + a^2)^0.5)/2 = 6.66

øE6 = 100%

øC6 = 100% - acos((r-2)/r)/pi = 74.66%

øD6 = 100% - acos((r-1)/r)/pi = 82.33%

øC6 must be corrected for the effect of the U/S Cutoff Wall (c1) and thickness of the wall (c2)

c1 = 19 * (d"/b')^0.5*(d'+d")/b = 19.00 0.20 0.11 = 0.41%

c2 = ((øD6 - øC6)*Tc6)/d6 = 1.15%

øC6 (corrected) = øC6 + c1 + c2 = 76.22%

Required Concrete Thickness

Design Head (H) = U/S Water Level - D/S Water Level = 1.00 m

u = submerged unit weight of concrete= unit weight of concrete/ unit weight of water = 1.41

Concrete Thickness (m) = H*φ / u

Length from ø% Concrete Used


section U/S end (m) thick (m)
1 U/S 0.00 20.20% 0.14 0.50
2 10.05 31.88% 0.23 0.60
3 11.85 33.97% 0.24 0.70
4 35.35 61.28% 0.44
5 38.65 65.12% 0.47
6 D/S 48.20 76.22% 0.54

Checking of Total Floor Length Against Under Seepage:

C= 6.00 H = 1.00 CXH= 6.00 m, Required Creep Length


Creep Length Provided = 27.87 m > 6.00 m OK

Considering HHWL (observed) River Side and Maximum Water Level inside project

C= 6.00 H = 2.20 CXH= 13.20 m, Required Creep Length


Creep Length Provided = 27.87 m > 13.20 m OK
 
 
 
 
 
   

 
  Page 121 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

Appendix III:  The Preliminary Estimates for Tranch‐1, Tranch‐2 and Tranch‐3 
Estimate for Tranch‐1 
 
Estimate for proposed intervention (Tranch1)   05.08.2013
I. River: Brahmaputra‐Jamuna

A. Embankment
(Composite section with provision of selected Settlement, wide mid part) 

A1. Right Bank of Jamuna River (D/S of Jamuna Bridge)
Length Ht of Embk Cost/m Est amnt
(km) (m) BDT
(i). Enayetpur‐Kaijuri        (NS) 10.5 5.0 28,620 300,510,193
(Tranch‐1) (S) 2.0 5.0 33,962 67,924,037
Sub‐total 12.5 km BDT 368,434,230 US$ 4,605,428

(iii). Hurasagar‐shahzadpur (NS) 6.0 4.5 24,647 147,882,003


(Tranch‐1) (NS) 1.5 4.0 20,674 31,010,974
(NS) 3.0 3.0 13,712 41,136,137
Sub‐total 10.5 km BDT 220,029,113 US$ 2,750,364

Sub‐total‐(RB Embankment) 23.0 BDT 588,463,343 US$ 7,355,792

Note: (i) The embankment section [marked 'S'] includes a 10 m wide Road Section (5.5m carriage way+ 
2x1.5m paved shoulder+2x0.75m verge) in C/S, 8.0 wide re‐settlement area in R/S , 3.2 m wide Crest 
(mid portion) and 1V:2.5H slope in both side (to GL) for section with Selllement.
(ii) The other section [marked 'NS'] includes a 10.0 m wide road section (5.5m carriage way+ 2x1.5m 
paved shoulder+2x0.75m verge) in C/S, 3.2m wide crest in R/S, no re‐settlement area and 1V:3H
slope in R/S and 1V:2.5H in C/S.

B. Road  (Enayetpur‐Kaizuri)
1. Rural Road (5.5m carriage way+2x1.5m Shoulder)
5.00 km 25,000,000 km 125,000,000 US$
2. RCC road for NMV (2.8m, 100 mm thick)
5.00 km 4,500,000 km 22,500,000 US$
3. Grass stone along the slope of crest of embankment (13 km)
5.0 6261 m2/km 39,131 nos/km
each 270.00 52,827,106 US$

Total (Road)  200,327,106 US$ 2,504,089

C. Structures
C1: Structures along the Right Bank (Jamuna)
(i) RCC Regulators (1 vent) BDT BDT
1 no 19,700,000 19,700,000
(ii) RCC Regulator (2 vent)
1 no 26,300,000 26,300,000
(ii) RCC Regulators (4 vent)
1 nos 37,700,000 37,700,000
(iii) RCC Regulator (6 vent)
1 no 50,900,000 50,900,000

Cost of new structures: BDT 134,600,000 US$ 1,682,500

C2. Repair of Structures
(i) RCC Regulators
3 nos LS 2,000,000 6,000,000 US$ 75,000

Total Cost of Structures (new & repair) BDT 140,600,000 US$ 1,757,500  


 

 
Page 122  September 2013 
Technical Designs for Tranch‐1 Work 

D. Proposed Protection length (Jamuna River) 

D1. Left Bank
(i) Chouhali to Nagarpur 5.00 km 255,500,000 1,277,500,000
(ii) Zaffarganj‐ Bachamara
2.00 km 255,500,000 511,000,000

Sub‐total (LB pr work): 7.00 km BDT 1,788,500,000 US$ 22,356,250

C2. Right Bank
(i) About 1.0 km around Benotia
1.00 km 255,500,000 255,500,000 US$ 3,193,750

Total Protection Work (both bank) BDT 2,044,000,000 US$ 25,550,000

D. Land Acquisition
(D1) Embankment
Length  land/km T.land 
(km) (Ha) (Ha)
(I). Right Bank
(i). Enayetpur‐Kaijuri      (NS) 10.5 4.50 47.25
(S) 2.0 5.00 10.00
57.25 ha

(ii) Hurasagar ‐Shahjadpr  (NS) 6.0 4.23 25.35 ha

(Repair) (S) 1.5 1.19 1.78 (30% of required land to be acquired)


(Repair) (NS) 3.0 1.02 3.06 (30% of required land to be acquired)
4.84 ha
Land for RB Embankment 23.0 87.44 ha

Cost of land acquisition for RB embankment (Jamuna)
87.44 ha  7,400,000 BDT 647,037,500 US$ 8,087,969

(D2) Bank Protection
(i) Left Bank
(a) Chouhali‐Nagarpur 5.00 km 15.00 ha
(b) Zaffarganj‐Bachamara 2.00 km 6.00 ha
sub‐Total (LB) 7.00 km 21.00 ha

(ii) Right Bank
(a). 1.0 km around Benotia
1.00 km 3.00 ha
Total Land for LB & RB Protection
8.0 km 24.00 ha
Land Acquisition (For Bsnk Protection):
24.0 ha 6,910,000.00 BDT 165,840,000 US$ 2,073,000

(D3) Structure no ha
1 Vent: 1 0.82
2 Vent 1 0.93
4 Vent 1 1.17
6 Vent 1 1.29
4.21 7,400,000 BDT 31,154,000 US$ 389,425  

 
  Page 123 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

E. Land Reclamation
E1: Left Bank
2
(i) Doulatpur‐Zaffarganj 30.0 km

I. River: Brahmaputra‐Jamuna BDT
(i) Embankment construction & repair BDT 588,463,343
(ii) Road Construction BDT 200,327,106
(iii) Structures,(new + repair)  BDT 140,600,000
(iv) Bank protection (revetment) BDT 2,044,000,000
Sub‐total Physical work BDT 2,973,390,449 US$ 37,167,381

Land Acquisition
(i) Embankment  BDT
(a)Kaizuri‐ Verakhola 57.25 ha 423,650,000
(b) Hurasagar‐Baghabari 25.35 ha 187,590,000
(c ) Baghabari 4.84 ha 35,797,500
(ii) Bank Protection 24.00 ha 165,840,000
(iii) Structures 4.21 ha 31,154,000
Sub‐Total for Land Acquisition 115.65 ha 844,031,500 US$ 10,550,394

II. River: Padma

1. Protetion work in Left Bank (Harirampur) Temp above LWL and Geobag below LWL
7.00 km 185,000,000 BDT 1,295,000,000 US$ 16,187,500
Total for Physical work (Revetment) =
7.00 km BDT 1,295,000,000 US$ 16,187,500

3. Land Acquisition for Bank Protection
(i) Left Bank 7.0 km 24.5 ha

Cost of Land Acquisition
24.5 ha 6,910,000 BDT 169,295,000 US$ 2,116,188

III. Adaptation Work:
Repair and strengthening 
5.0 km LS BDT 400,000,000 US$ 5,000,000

Padma 
(i) Bank Protection Work  BDT 1,295,000,000 US$ 16,187,500

(ii) Land acquisition 24.5 ha BDT 169,295,000 US$ 2,116,188

Grand Total
Physical work
I. Physical work for Brahmaputra‐Jamuna: BDT 2,973,390,449
II. Physical Works for Padma BDT 1,295,000,000
III. Adaptation Work and mass dumping BDT 400,000,000
Total Physical works BDT 4,668,390,449 US$ 58,354,881

Land acquisition
I. For Brahmaputra‐Jamuna: (115.65 ha) BDT 844,031,500
II. For Padma (24.5 ha) BDT 169,295,000
Total Land acquisition BDT 1,013,326,500 US$ 12,666,581

Grand Total i/c land acquisition  BDT 5,681,716,949 US$ 71,021,462

Exchange Rate (US$ to BDT) 1 US$ BDT 80.00

Note: (i) Temporary (Geobag) protection is assumed in upper slope (slope above LWL) of Padma  
(ii) The land acquisition cost estimated in this package has been superseded in the estimates for
Land acquisition and resettlement.   
   
 
Page 124  September 2013 
Technical Designs for Tranch‐1 Work 

Estimate for Tranch‐2 
 
Estimate for proposed intervention (Tranch2)   29.05.2013

A. Embankment Length Ht of Embk Cost/m


1. Jamuna
(i). Hurasagar‐Shahzadpur   (km) (m)
(Tranch‐2) (NS) 1.0 3.0 22,279 22,279,395
(NS) 1.0 3.0 22,279 22,279,395
(NS) 4.0 3.5 25,662 102,649,780
Sub‐total (Jamuna, RB) 6.0 BDT 147,208,570 US$ 1,840,107

(ii) Aricha‐Zionpur (Rehabilitation) (40% 0f 4.0 m high embankment)
12.0 4.0 10,361 124,327,584
Sub‐total (Jamuna, LB) 124,327,584 US$ 1,554,095
2. Padma
(ii) Dhaka SW Project Embankment (Rehabilitation and strengthening), LB of Padma
17.00 km 10,361 176,130,744
(40% of new construction, 4.0m high embankment)
(iii) Dhaka SW Project Embankment (New construction), LB of Padma
8.00 km 4.0 25,902 207,212,640
(4.0m high, new embankment)
Sub‐total (Padma) 383,343,384

B. Road 
1. Rural Road (5.5m carriage way+2x1.5m Shoulder) BDT BDT
16.00 km 45,000,000 720,000,000
2. RCC road for NMV (2.8m, 100 mm thick)
16.00 km 4,500.00 72,000,000
3. Grass stone along the slope of crest of embankment (16 km)
2
16.0 6261 m /km 39,131 nos/km
270.00 each 169,046,739
Total (Road)  961,046,739

C. Bank Protection Works
1. Bank Protection Works (Jamuna)
(i) Enayetpur(Jamuna, Right Bank)
11.00 km 255,500,000 2,810,500,000
(ii) Chouhali, (Jamuna, Left Bank)
3.00 km 255,500,000 766,500,000
(iii) Zaffarganj (Jamuna, Left Bank)
2.00 km 255,500,000 511,000,000
Sub‐total (Jamuna, Protection) 4,088,000,000

2. Bank Protection Works (Padma)
(iv) Harirampur (Padma, Left Bank), Protection above LWL and on Berm (cc blocs on filter)  
7.00 km 145,000,000 1,015,000,000
Sub‐total (Padma Protection) 1,015,000,000

D. Adoptation Work 5.00 km LS 400,000,000 5,000,000

E. Structures

1. Structures along the left Bank of Padma
(i) RCC Regulators (1 vent)
3 nos 19,700,000 59,100,000  

 
  Page 125 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

2. Repair of Structures
(i) RCC Regulators 2 nos 2,500,000 5,000,000
Total Cost of Structures (new & repair) 64,100,000

E. Land Acquisition
(E1) Embankment
Length  land/km T.land 
(km) (Ha) (Ha)
(1)  Jamuna (RB)
(i) Hurasagar‐Shahzadpur 1.0 1.02 1.02 (30% land required)
1.0 1.02 1.02 (30% land required)
4.0 1.10 5.10 (30% land required)
7.14 ha
(2) Jamuna (LB)
(ii)Aricha‐Zionpur (100% of land considered for rehabilitation, Old FFW)
12.0 3.25 39.00 ha
Land acquisition for embankment (Jamuna)
46.14 ha 7,400,000 341,454,500
(I). Left Bank (Padma)
(i). SW embankment (Rehabilitation and strengthening)       (40% of original land for 4.0m emb.)
17.00 1.30 22.10
(ii) SW Project embankment extension, new)
8.00 3.25 26.00
Land for embankment‐Padma 48.10 ha
Land acquisition for embankment (Padma)
48.10 ha 7,400,000 355,940,000
(E2) Bank Protection
(1) Right Bank (Jamuna)
(i) Enayetpur 11.00 km 33.00
(2) Left Bank (Jamuna)
(ii) Chouhali 3.00 km 9.00
(iii) Zaffarganj  2.00 km 6.00
Land for protection  16.00 km 48.00 ha

Land acquisition (Bank Protection, Jamuna)
48.00 ha 6,910,000 331,680,000
(3) Left Bank (Padma)
(iv) Harirampur  (already taken care under Tranch1)

(E3) Land for Structure
RCC Regulator (1V) 3 nos 0.82 2.46 ha

2.46 ha 7,400,000 18,204,000

 
Page 126  September 2013 
Technical Designs for Tranch‐1 Work 

I. Brahmaputra‐Jamuna BDT US$


(i) Embankment  (Hurasagar‐Shahzadpur) 147,208,570
(ii) Embankment Rehabilitation (Aricha‐Zionpur) 124,327,584
(iii) Road construction & ancillary works 961,046,739
(iv) Bank Protection Works  4,088,000,000
Sub‐total Physical work 5,320,582,893 66,507,286

Land Acquisition (Jamuna)
(i) Embankment (jamuna)
46.14 ha 341,454,500
(ii) Bank Protection (jamuna)
48.00 ha 331,680,000
Land acquisition (Jamuna) 673,134,500 8,414,181

II. River: Padma
(i) Embankment Rehabilitation 176,130,744
(ii) Embankment Construction (new) 207,212,640
(iii) Bank Protection work in Left Bank 1,015,000,000
(iv) Structure 64,100,000
Physical work for Padma 1,462,443,384 18,280,542

Land Acquisition (Padma)
(i) Embankment 48.10 ha 355,940,000
(ii) Bank Protection  (nil)
(iii) Regulators 2.46 ha 18,204,000
Land for embankment (Padma) 374,144,000 4,676,800

III. Adoptation Work (Bank Protection) 400,000,000 5,000,000

Grand Total
Physical work
I. Physical work for Brahmaputra‐Jamuna: BDT 5,320,582,893
II. Physical Works for Padma BDT 1,462,443,384
III. Adoptation Work BDT 400,000,000
Total Physical works BDT 7,183,026,277 US$ 89,787,828

Land acquisition
I. For Brahmaputra‐Jamuna: BDT 673,134,500
II. For Padma BDT 374,144,000
Total Land acquisition BDT 1,047,278,500 US$ 13,090,981

Total physical infrastructure + land   BDT 8,230,304,777 US$ 102,878,810

Exchange Rate (US$ to BDT) 1 US$ BDT 80.00

Note: 
(i) The land acquisition cost estimated in this package has been superseded in the estimates for
Land acquisition and resettlement.   
 
   

 
  Page 127 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

Estimate for Tranch‐3 
 
Estimate for proposed intervention (Tranch3)   29.05.2013

A. Embankment Rate/BDT BDT


(i) Dhaleswary‐ Aricha Embankment (New construction), Left bank of Jamuna
23.00 km 32,649 750,933,187
(5.0m high, new embankment)
Total (Embankment) 750,933,187

B. Bank Protection Works
1. Bank Protection Works (Jamuna)
(i) Chouhali, (Jamuna, Left Bank)
5.00 km 255,500,000 1,277,500,000
(ii) Zaffarganj (Jamuna, Left Bank)
2.00 km 255,500,000 511,000,000
Sub‐total (Jamuna, Protection) 1,788,500,000

2. Bank Protection Works (Padma)
(iii) Protection works in Dohar (Padma, Left Bank)
5.00 km 293,825,000 1,469,125,000
(iv)  Protection in Louhajang (Padma, Left bank)
2.00 km 293,825,000 587,650,000
(v) Protection in Sureswar (Padma, right Bank)
10.00 km 293,825,000 2,938,250,000
Sub‐total (Padma Protection)‐Padma 4,995,025,000

C. Structures

1. Structures along the left Bank of Jamuna
(i) RCC Regulators (1 vent)
3 nos 19,700,000 59,100,000
2. Repair of Structures
(i) RCC Regulators 2 nos 2,500,000 5,000,000
Total Cost of Structures (new & repair) 64,100,000

D. Adoptation and Strengthening
5.00 km 80,000,000 400,000,000

E. Land Acquisition
(E1) Embankment
Length  and/km T.land 
(km) (Ha) (Ha)
(i) Dhaleswary‐Aricha embankment extension, (new)
23.00 3.80 87.40
Land for embankment 87.40 7,400,000 646,760,000

(E2) Bank Protection
(1) Left Bank (Jamuna)
(i) Chouhali 5.00 km 15.00
(ii) Zaffarganj  2.00 km 6.00
Land for protection (Jamuna) 21.00 ha
21.00 6,910,000 145,110,000
 

 
Page 128  September 2013 
Technical Designs for Tranch‐1 Work 

(2) Left and Right Bank (Padma)
(iii) Dohar 5.00 km 17.50
(iii) Louhajang  2.00 km 7.00
(iv) Sureswar 10.00 km 35.00
Sub‐total (land)‐Padma Protection 59.50 ha
Land for Protection (Padma) 59.50 6,910,000 411,145,000

(E3) Structure
(i) RCC Regulator (1‐Vent) 
3.00 nos 0.82 2.46 ha

2.46 ha 7,400,000 18,204,000

I. River: Brahmaputra‐Jamuna
(i) Embankment  23.00 km 750,933,187
(ii) Protection Work 7.00 km 1,788,500,000
(iii) Structures 64,100,000
Sub‐total ‐Physical infrastructures 2,603,533,187
Land
(i) Embankment  87.40 ha 646,760,000
(ii) Protection Work 21.00 ha 145,110,000
(iii) Structures 2.46 ha 18,204,000
810,074,000
II. River: Padma
(i) Bank Protection works 17.00 km 4,995,025,000

Land
(i) Bank Protection works 59.50 ha 411,145,000

III. Adoptation 400,000,000

Total Estimated Cost for Tranch‐3
BDT US$
1. Embankment (Jamuna) 750,933,187
2. (a) Bank Protection (Jamuna) 1,788,500,000
(b) Bank Protection (Padma) 4,995,025,000
3. Structure 64,100,000
4. Adotation & Strengthening 400,000,000
Sub‐total Physical Infrastructure 7,998,558,187 99,981,977
5. Cost of Land 
(i)  Embankment (Jamuna) 87.40 ha 646,760,000
(ii) Bank Protection (Jamuna) 21.00 ha 145,110,000
(iii) Bank Protection (Padma) 59.50 ha 411,145,000
(iv) Structure/Regulators 2.46 ha 18,204,000
Sub‐total for land 170.36 ha 1,221,219,000 15,265,238
Total physical Infrastructure + Land 9,219,777,187 115,247,215

Exchange Rate (US$ to BDT) 1 US$ BDT 80.00

 
 
 
   

 
  Page 129 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

 
Basic Element rates used for the estimate (Sample) 
 
1.  Base (embankment) Excavation  BDT  166.00  m3 
 
2.  Dredged Sand/Earth from River for embankment construction   BDT  191.00  m3 
 
3.  Clay lining  BDT  238.00  m3 
 
4.  Supply, fill, sewing and staking geobags (125 kg)  BDT   209.00  each 
 
5.  Supply, fill, sewing and staking geobags (250 kg)  BDT   390.00  each 
 
6.  Dumping geobag from properly positioned barge  BDT  387.00  m3 
 
7.  CC block (200x200x300mm)  BDT  379.00  each 
 
8.  CC block (200x200x200mm)  BDT  257.00  each 
 
9.  CC block (300x300x300mm)  BDT  215.00  each 
 
10.  CC block dumping/ placing  BDT  1395.00  m3 
 
11.  Structural Concrete (18 N/mm2)  BDT  8200.00  m3 
 
12.  Gras‐stone (400x400x150mm with 4‐holes)   BDT  270.00  each 
 
13.  2 Lane Road (5.5m carriage way + 2 – 1.5 m paved shoulder)  BDT  45,000.00  m 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Page 130  September 2013 
Technical Designs for Tranch‐1 Work 

Appendix IV:  Design Criteria 
 

Main River Flood and Bank Erosion Risk 
Management Program (MRP) 
 
 
 
 
 
 
RIVER BANK PROTECTION, EMBANKMENT AND 
DRAINAGE WORKS 
 
 
 
 
 
 
Design Criteria 
 
 
 
 
 
 
September 2013 
 
 
 
 
  Page 131 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

Contents
1  Design Criteria ......................................................................................................................... 133 
1.1  Design Life .................................................................................................................................. 133 
1.2  Standards and Design Guidelines .............................................................................................. 133 
1.3  General Approach ...................................................................................................................... 134 
1.4  Hydrology and Hydraulic Parameters ........................................................................................ 134 
1.4.1  River Discharge and Flood Level ..................................................................................... 134 
1.4.2  Flow velocity ................................................................................................................... 136 
1.4.3  Wind‐Generated Waves .................................................................................................. 136 
1.4.4  Freeboard ........................................................................................................................ 138 
1.5  Scour .......................................................................................................................................... 138 
1.6  Design of Erosion Protection Counter‐Measures ...................................................................... 138 
1.6.1  Slope Protection – River Currents ................................................................................... 138 
1.6.2  Scour Protection Apron ................................................................................................... 138 
1.6.3  Erosion Protection Waves ............................................................................................... 139 
1.7  Slope Stability............................................................................................................................. 139 
2  Drainage and Flushing Structures ............................................................................................ 140 
2.1  Draining Capacity ....................................................................................................................... 140 
2.2  Hydraulic and Structural Details ................................................................................................ 140 
 
 
 
 

 
Page 132  September 2013 
Technical Designs for Tranch‐1 Work 
 

1 Design Criteria 

1.1 Design Life 
 
The specified design life of the river bank protection, embankments and drainage and flushing works is 
30  years.    This  does  not  mean  the  all  the  drainage  structures  and  river  training  works  will  operate 
without  maintenance  over  this  period  of  time;  periodic  repair  of  drainage  infrastructure  and/or 
upgrading  of  protective  works  will  be  required.  The  definition  of  a  design  life  pre‐supposes  the 
establishment of a comprehensive monitoring and maintenance program.  
 

1.2 Standards and Design Guidelines 
The following design standards and guidelines are used for specific aspects of the RTW design, as listed 
below: 
 
Hydraulic Design 
 Standard Design Manual; Chief Engineer, Design, BWDB 
 Guide Lines and Design Manual for Standardised Bank Protection Structures; Jamuna Test Work 
Consultants, December 2001 
 Bureau  of  Research  Testing  and  Consultancy  (BRTC),  Bangladesh  University  of  Engineering  & 
Technology  2010:  Guidelines  for  Riverbank  Protection.  Prepared  for  Bangladesh  Water 
Development  Board,  financed  through  Jamuna‐Meghna  River  Erosion  Mitigation  Project 
(subsequent referred to as BRTC‐2010). 
 US  Army  Corps  of  Engineers  (USACE),  1994,  Hydraulic  Design  of  Flood  Control  Channels, 
Engineering Manual EM 1110‐2‐1601. 
 Final report, Main Volume, River Survey Project, FAP‐24, November 1996 
 Flood  Control  Embankment  and  River  Bank  Protection  of  the  Left  Bank  of  Jamuna  River  at 
Nagarpur and Chouhali; Final Report; Directorate of Planning‐1, BWDB and IWM, June 2007 
 Brahmaputra Flood Embankment Project; (Phulchari to Sirajganj); Definite Project Report; East 
Pakistan  Water  and  Power  Development  Authority;  leedshill‐DeLeuw  Engineers,  November 
1965. 
 Jamuna Padma Left Bank Project; Final Report; Directorate of Planning‐1, BWDB, July 2007. 
 Quality  Control,  Monitoring  and  Impact  Assessment  of  Pilot  Dredging  of  Jamuna  River  at  two 
Locations, from Sirajganj Hard Point to Dhaleswary Offtake (20km) and near Nalin Bazar (2 km); 
draft Final Report; IWM. 
 
Geotechnical Design 
 Joseph E. Bowles, 1997: Foundation Analysis and Design, 5th edition, McGraw Hill.  
 Stephen L. Kramer, 1996: Geotechnical Earthquake Engineering, Prentice Hall. .    
 Terzaghi/Peck/Mesri, 1996: Soil Mechanics in Engineering Practice. 3rd edition, John Wiley & 
Sons.  
 ASTM Standards (Status Dec. 2009): Soil and Rock  
 
In  addition,  a  range  of  specialized  technical  publications  on  scour  and  bank  protection  design  were 
consulted including: 
 Przedwojski,  Błažejewski,  R.  and  K.  Pilarczyk  1995:  River  Training  Techniques.  A.A.  Balkema, 
Rotterdam. 
 Pilarczyk, K. 1990: Coastal Protection, Delft University of Technology. 
 Maynord, S., Ruff, J.F. and Abt,, S.R., 1989: Riprap design. Journal of Hydraulic Engineering 
(ASCE), 115, 7, 937‐949. 
 
 
  Page 133 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

1.3 General Approach 
 
The design flood for the river training works has a return period of 100 years. The RTW must be capable 
of experiencing the design condition without experiencing significant damage. Under design conditions, 
the stability of the cover layer and scour protection measures must meet or exceed the required factors 
of safety specified in US Army Corps of Engineers guideline EM 1110‐2‐1601 (USACE, 1994).  
 

1.4 Hydrology and Hydraulic Parameters 
1.4.1 River Discharge and Flood Level 
 
(a)  River Discharge 
 
The design flood discharge was determined as the 100‐year discharge based on the historic record of 
maximum  annual  discharges  at  the  Bahadurabad  gauge  for  Brahmaputra‐Jamuna  and  Mawa  gauge 
station.  
 
In Main River Flood and Bank Erosion Risk Management Program (MRP),  
 
The frequency analysis for discharge was calculated on observed discharge for Bahadurabad (Jamuna) 
and Mawa (Padma) for 1976‐2006.  
 
 

Frequency Analysis of Maximum Discharge by Log 
110
Pearson Method:Bahadurabad
105
Discharge(Thousand m3)

100 RP-2 67,086


95 RP-5 79,835
90 RP-10 87,094
85 RP-20 93,391
80 RP-50 100,804
75 RP-100 105,936
70
65
60
0 20 40 Return Period
60 80 100 120
 
 
Discharge at Bahadarabad (Brahmaputra‐Jamuna) 
 
 
 

 
Page 134  September 2013 
Technical Designs for Tranch‐1 Work 
 

Frequency Analysis of Maximum Discharge by Log Pearson 
Method:Mawa
140

130
Dischage(Thousands m3)

RP-2 88,732
120
RP-5 101,432
RP-10 108,875
110
RP-20 115,478

100 RP-50 123,445


RP-100 129,093
90

80
0 20 40 60 80 100 120
Return Period  
 
Discharge at Mawa (Padma) 
 
(b) Flood Level 
 
The design flood level is based on the 100‐year estimate from frequency analysis of annual maximum 
water levels at Sirajganj (SW 49) and Mathura (SW 50.3) for left bank of Jamuna River and Bangabandhu 
Bridge and Aricha (SW 50.6) in the right bank for Jamuna River. All levels are still water levels and do not 
account for wave runup. 
 
WL  from  June  1945  to  September  2012  for  Sirajganj,  April  1964  to  September  2012  for  Mathura, 
January  2000  to  January  2013  for  Bangabandhu  (Jamuna)  Bridge  and  April  1964  to  August  2012  has 
been considered for calculating 100 year WL for different stations of Brahmaputra‐Jamuna River.  
 
River: Brahmaputra‐Jamuna 
Station  HWL  LWL  2 year  10 year  50 year  100 year 
observed  observed  HWL  HWL  HWL  HWL 
Sirajganj  15.11  6.05 14.57 13.85 15.20  15.46
Mathura  11.90  2.44  10.18  11.08  11.87  12.20 
Bangabandhu Bridge  14.12  5.41  13.19  13.98  14.68  14.97 
Aricha  10.76  1.94  9.47  10.26  10.95  11.25 
 
Again  WL  from  April  1965  to  August  2012  for  Baruria  and  April  1968  to  September  2012  for  Mawa 
stations has been considered for calculating 100 year WL for different locations along Padma River. 
 
River: Padma 
Station  HWL  LWL  2 year  10 year  50 year  100 year 
observed  observed  HWL  HWL  HWL  HWL 
Baruria  9.89  1.31  8.31  9.10  9.79  10.08 
Mawa  7.09  0.78  6.03  6.68  7.25  7.49 
 
The results are finally verified with the publications available.  
 
 
 

 
  Page 135 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

1.4.2 Flow velocity 
 (i) Brahmaputra‐Jamuna  
Observed  flow  velocity  in  Brahmaputra‐Jamuna  at  Bahadurabad  transit  from  1990  to  2009  is  1695 
numbers. Out of all these  measurements of velocity in Bahadurabad the highest of 99.77% is selected 
as design velocity. The data are placed in the design report. 
 
(ii) Padma 
The  maximum  velocity  from  all  the  339  discharge  observation  at  Mawa  from  January2001  to  March 
2013 was selected. Out of all these maximum observed velocities the highest of 84.7% is selected as the 
design velocity for selection of the size of protection element. 
 
The analysis is placed below. 
 
1
0.9
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0
0 0.35 to 1.00 1.0 to 2.00 2.0 to 3.0 3.0 to 4.0 4.0 to 5.0
 
 
Observed velocity  Number of  % of each group Cumulative % 
(m/sec)  observation 
0.35 ‐1.00  107  31.6%  31.6% 
1.00 ‐ 2.00  79  23.3%  54.9% 
2.00‐ 3.00  101  29.8%  84.7% 
3.00‐4.00  48  14.2% 98.8% 
4.00‐5.00  4  1.2%  100.0% 
Total  339     
 
1.4.3 Wind‐Generated Waves 
Slope  protection  at  the  river  training  works  is  designed  to  withstand  the  100‐year  significant  wave 
condition.   
 
The  wave  height  was  calculated  by  Dennis  Grosser  from  hourly  wind  data  recorded  at  Chandpur, 
Comilla, Bogra and Ishurdi in JMREMP.  
 
The  analysis  of  available  wind  data  reveals  that  in  Pabna  Irrigation  and  Rural  Development  Project 
(PIRDP) the wave height do not exceed 0.6m. The expected wave period is 2.5 secs. 

The available wind data indicate that wave heights at the Meghna‐Dhonagoda Irrigation Project (MDIP) 
would be in the order of 1 m. The expected wave period is then 3.9 s. 
 
Page 136  September 2013 
Technical Designs for Tranch‐1 Work 
 
 
In  Padma  Multipurpose  Bridge  Design  Project,  wave  hindcasting  was  carried  out  using  the  simplified 
procedures described in the US Army Corps of Engineers Coastal Engineering Manual EM 1110‐2‐1100, 
2008. The maximum wave heights at the site are limited by the available fetch. The fetch distance varies 
with bank  location, water  level  and channel bank position  which  varies over time due  to erosion and 
accretion  of  the  adjacent  chars.  It  was  assumed  that  shallow  vegetated  floodplain  areas  will  not 
contribute to wave generation.  
 
Wave runup is the maximum elevation of wave uprush above the still water level and depends on the 
deep water wave climate, angle of approach, near‐shore topography, bank type and bank slope. Wave 
runup (Ru%) is described statistically as the runup level exceeded by i per cent of the incident waves. A 
value  of  2%  exceedance  is  generally  used  for  design  of  coastal  structures  (USACE,  2008).  This  means 
that under a 100‐year storm condition, 2% of the incident waves would equal or exceed a value of Ru2%. 
Wave runup was computed for the case of irregular waves approaching to an impermeable 1V:3H bank 
slope using relations described in River Training Techniques; K.W.Pilarczyk, 1995 
 
Effective Runup is given by  
R = τrp. rβ . Rn 
where, τrp  is the reduction factor due to slope roughness and permeability 
  rβ  is the reduction factor due to oblique wave attack  and 
  Rn  is the runup on smooth plane slope defined as the vertical wave height above  
  still water level. 
 
Again, Rn 2% = (1.5‐1.75) ξp Hs   for ξp < 2.5 
  Rn 2% = (3.0 ‐ 3.5) ξp Hs  for ξp > 2.5 
 
where, Rn 2%   = runup which exceeds by 2% waves (for wind waves) 
  ξp  = Wave breaking parameter = 1.25 Tp.Tanα. Hs ‐0.5   
  Hs  = significant wave height (m) 
  Tp   = wave period (sec) 
  α  = slope angle (°) 
 
The Section of embankment 
 
Crest Level : 14.80 m PWD 
100 year HWL: 13.90 m PWD 
R/S slope: 1V:3H 
C/S slope: 1V:2.5H 
 
In MRP 
 
Wave height is assumed for a 7.5 km fetch, 20 m/sec wind speed [Guideline for River bank Protection; 
BRTC, BUET and BWDB] and checked with FAP 21 guideline and FAP‐1 documents. 
 
wave height = 1.3 m  
wave period = 2.3 sec 
 
(Halcrow reported maximum wind speed of 18.0 m/sec in Faridpur, Sirajganj, Bogra and Mymensingh, 
1994) 
 
(In  JMREMP  Dennis  Grosser  analysed  wave  for  the  period  1996  to  2005.  The  maximum  wind  speed 
recorded was 18.0 m/sec. Record stations are Comilla, Bogra, Ishurdi and Chandpur.) 
 
 
  Page 137 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

The  calculation  showing  the  runup  is  enclosed  as  Appendix‐1  and  the  analysis  conducted  by  Dennis 
Grosser is enclosed in Appendix‐2. 
1.4.4 Freeboard 
The  crest  elevation  of  all  embankments  that  are  not  intended  to  be  overtopped  were  determined  as 
follows: 
 
Crest El. = Design maximum elevation of wave uprush (Ru2%) or 1.5 m freeboard whichever is higher. In 
all the calculation 100 year HWL has been used. 
 
Note: (No flood in the past has attained the 100 year flood limit, 1988 flood attained a return period of 
65 year in Jamuna and in Padma, again 1998 flood attained a return period of 40 year in Jamuna and 
about 50 year in Padma.) 
 

1.5 Scour 
Scour was determined under a range of discharges and channel pattern scenarios in order to envelope 
the  worst  conceivable  scour  condition  at  the  site.  These  channel  pattern  scenarios  were  based  on  a 
careful  review  of  historical  data  spanning  the  last  1995‐2012  period  and  compared  with  standard 
literature.  
  
MRP Activities 
Scour levels were based partly on a record from 1995 to 2011/2012 and surveyed bed elevations in the 
general vicinity of the work site in October 2012 and March 2013. 
 
Design Scour 
Scour  was  estimated  for  a  range  of  discharges  including  bankfull  discharge  up  to  the  100‐year  flood. 
Brahmaputra‐Jamuna  being  a  braided  river,  attention  is  given  to  assess  the  flow  along  a  particular 
channel.  The  Padma  river  near  Baruria  and  opposite  to  Faridpur  flowing  in  multiple  channel  is  also 
assessed accordingly.  
 

1.6 Design of Erosion Protection Counter‐Measures 
1.6.1 Slope Protection – River Currents 
The  bank  slopes  will  be  protected  against  erosion  from  river  currents  to  prevent  damage  to  the 
underlying  fine  material.  The  design  of  the  slope  protection  (including  cover  layer,  filter  layer  or 
geotextile) will be in accordance with accepted methods described in BRTC‐2008.  
 
The  stable  size  of  protection  element  (cover  layer)  against  river  currents  is  determined  using  the 
Pilarczyk equation as suggested in Guideline for River bank Protection; BRTC, BUET and BWDB. 
1.6.2 Scour Protection Apron 
Scour protection aprons will be provided at all river training structures to prevent undermining of the 
revetment  slopes.  The  design  approach  will  reflect  general  uncertainties  associated  with  launching 
aprons  and  the  lack  of  a  complete  understanding  of  the  self  launching  of  different  scour  protection 
elements. The size and type of materials used in the aprons will be determined using site conditions and 
design requirements on the Jamuna and Padma River in Bangladesh as prescribed in BRTC‐2008 and the 
additional experience gained at Jamuna Bridge and other major river training works in Bangladesh.   
 
The nominal volume of geobags required in the apron is determined by assuming the geobags launch 
on a slope 1V:2H and provide single layer coverage after initial launching.  Safety factors is applied to 

 
Page 138  September 2013 
Technical Designs for Tranch‐1 Work 
 
cover uncertainties. Therefore, the factor of safety for launching apron volumes will be 1.5 for selected 
design scour conditions. 
1.6.3 Erosion Protection Waves 
The  stable  block  size  for  slopes  exposed  to  wave  attack  is  determined  by  Pilarczyk’s  relation  (CIRIA 
2007):  
 
b
Hs  ξ z
Dn   
Δm  Ψu  Φsw  cosα

In  which,  Dn  is  the  nominal  thickness  of  the  protection  element  [m],  Hs  is  the  significant  wave  height 

ξ
b
[m],   is the wave similarity parameter (=tan α * 1.25Tm/Hs1/2), α is the slope angle, Tm is the mean 
z
wave period [s], Δm is the relative buoyant density of the protection unit [‐], Ψu is the system specific 
stability  upgrading  factor  [‐],  and  φsm  is  the  stability  factor  for  wave  loads.  The  assumed  design 
parameters for hand placed cc blocks over geotextile filter are as follows: 
 
 The system specific stability upgrading factor (Ψu) is 2.00. 
 Stability factor (φsm) is 2.25 which is the low end of the range between 2.25 and 3.0. 
 

1.7 Slope Stability 
Slope stability analysis is carried out at the main RTW structures to locate critical sections of the river 
banks  and  to  ensure  the  RTW  slope  protection  will  be  geotechnically  stable  under  various  loading 
scenarios.  The  slope  stability  analysis  will  distinguish  two  cases:  (i)  slopes  formed  by  self  launching 
aprons, (ii) overall slopes to deepest scour level. 
 
Four loading cases (LC) on the RTW structures will be analyzed: 
 LC1:  dead  load,  traffic  load,  lateral  earth  pressure,  hydraulic  pressure  (including  regular 
percolation); 
 LC2: Additional rare occurrences or temporary conditions during construction will be added to 
LC1; 
 
The  safety  factors  that  will  be  adopted  against  failure  for  loading  condition  on  the  RTW  slopes  will 
reflect  the  importance  and  the  risk  of  exposure  of  the  upper  dredged  slopes  and  the  deeper  slopes 
formed  by  self‐launching  aprons.    For  the  upper  dredge  slopes  and  the  overall  slope  stability  safety 
factors are indicated below. 
 
Table 1: Safety factors for geotechnical assessment of river training works 
 
Loading Case  LC1 LC2
Factor of Safety  1.4  1.3 
 
The  slopes  formed  by  self‐launching  aprons  are  commonly  at  the  limit  state  of  stability  and 
consequently  cannot  be  treated  in  the  same  way.    The  analysis  of  slope  stability  will  determine  the 
factor of safety and the limit conditions after which failure is expected. Limit state of stability means the 
factor of safety is close to 1 for the highest loading conditions. To prevent a slip plane encroaching into 
the slope section above, the apron have to leave wide berms after launching. The launched slopes need 
to be monitored regularly in order to be able to provide reinforcement (adaptation) in a timely manner. 
 
 

 
  Page 139 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

2 Drainage and Flushing Structures 

2.1 Draining Capacity 
 
The  size  of  a  regulator  is  fixed  on  the  expected  runoff  1  in  10  year.  In  the  present  case  the  runoff 
suggested in IECO publication has been used as check with 20% increase over the suggested runoff. 
 

2.2 Hydraulic and Structural Details 
As per BWDB design Guidelines. 
 
 
 
Attachments 
 
Attachment‐1: Overtopping of Embankment 
Attachment‐2: Wave Analysis 
 
 
 

 
Page 140  September 2013 
Technical Designs for Tranch‐1 Work 
 
Attachment‐1: Overtopping of Embankment 
 
Embankment Crest in Kaizuri‐Hurasagar
Overtopping of embankment 

Section of Embankment
Crest Level : 14.80 m new PWD (suggested by Technical Committee,
R/S Slope : 1V:3H on recommendation of model study)
C/S Slope: 1V:2.5H

Effective run‐up, R =τrp.rβ.Rn [River Training Techniques; KWPilarczyk, 1995]


(Page‐446)
where
τrp is the reduction factor due to slope roughness and permeability
rβ is the reduction factor due to oblique wave attack
Rn is the run‐up on smooth plane slope defined as the vertical wave 
height above still water level
Again
Rn2%  = (1.5 ‐ 1.75)ξp Hs for ξp < 2.5 and
Rn2%  = (3.0 ‐ 3.5) Hs for ξp > 2.5
Rn2%  = the run‐up which is exceeded by 2% waves (for wind waves)
ξp   = Wave breaking parameter = 1.25xTp tanα Hs‐0.5
Hs  = Significant wave height [m]
Tp  = Wave period [sec]
α  = side slope angle [°]

Data
W = 13.3 m new PWD (still water level, Model generated)
Hs = 1.3 m (Wave height and Wave period from BUET‐BRTC)
Tp = 2.3 sec
α = 18.43 ° For slope of embankment 1V:3.0H

ξp   = 1.25xTp tanα Hs‐0.5 0.834 [‐] (slope 1V:3H)


Rn2%  run‐up exceeded by 2% of waves

Therefore, (run‐up exceeded by 2% of waes)
Rn2%  = (1.5 ‐ 1.75)ξp Hs = 1.63 m (with slope of 1V:3H)
(higher numerical value is used for the calculation)

Considering smooth surface ( τrp = 1.0) and  angle of wave attack (β = 30°):
R =τrp.rβ.Rn = 1.50 m (With slope of 1V:3H, and  β =30°)

 
 
 
 
  Page 141 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 

Reduction Factor for Slope Surface Roughness and permeability
(Table: 6.27, Page‐448,  River Training Techniques; Pilarczyk)
Cover layer τrp
Asphalt, smooth concrete 1.00
Concrete blocks, Open stone asphalt, grouted stone, grass mats 0.95
Pitched stone 0.9
Rough, permeable block mats, gravel, gabion mattress 0.7 ‐ 0.8
Riprap (minimum thickness 2Dn50) 0.5 ‐ 0.6

Reduction Factor for oblique wave attack, after SNIP (1983)
(Table: 6.28, Page‐448,  River Training Techniques; Pilarczyk)
Angle β° 0 10 20 30 40 50 60
rβ 1.00 0.98 0.96 0.92 0.87 0.82 0.76

 
 
 
 
 

 
Page 142  September 2013 
Technical Designs for Tranch‐1 Work 
 
Attachment 2: 
Wave Analysis by Dennis Grosser 
 

1. General 

When wind blows over water the water surface starts to move and form waves.  Waves are the result of 
shear stress between moving air (wind) and water surface.  The energy of the moving air is transferred 
to water particles. These water particles start to move in the same direction the wind blows. 
 
Waves  are  defined  by  wave  height  H,  wave  period  T,  wave  lengths  L,  and  direction  (see  Figure  1‐1).  
Waves are often generated far from the place where they are observed.  However, related wind speed 
and  duration  can  be  derived  from  the  observed  wave  height,  wave  period  and  wave  direction.  
Uncertainties  in  the  relationship  between  wind  and  waves  result  from  the  fact  that  waves  can  be 
transferred and reflected during travelling.  If the waves are travelling through areas with shallow water 
they  are  in  contact  with  the  bottom  and  start  changing  direction  and  height  called  shoaling  and 
refraction.  The calculation remains simple as long as the waves travel in the deep‐water zone (d > 2  L, 
where d is the water depth and L the wave length).  Due to refraction and shoaling the wave height is 
decreasing and the wavelength is changing.  The wave period remains the same. 

Figure 1-1: Definition of terms – elementary, sinusoidal, progressive wave (CEM Figure II-
1-9)

Waves observed in oceans, lakes, or rivers are not single regular waves. Observed waves in nature are 
the results of a superimposing process of different single waves generated on different locations with 
different wind speed and durations. They form a spectrum of waves with different wave height, wave 
periods and wavelength. This wave spectrum is described by a significant wave height Hs (the average of 
the upper third of all observed waves). The wave spectrum contains of different waves with different 
energy density (see Figure 1‐2).  

 
  Page 143 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 

Figure 1‐2: Sketches of wave spectral energy and energy density(CEM Figure II‐1‐35,  
Chakrabarti 19871 
 
The  frequency  at  the  peak  is  called  the  peak  frequency  fp.  The  wave  peak  period  Tp  is  then  1/fp.  The 
mean wave direction  is then the mean value of the directions and describes the mean direction of the 
wave spectrum. Figure 1‐3 shows a schematic for a two‐dimensional wave spectrum. 
 
JONSWAP  (Joint  North  Sea  Wave  Project,  Hasselmann  et  al.,  19732)  developed  a  wave  spectrum  for 
fetch‐limited seas, which can be expressed by the following formulae: 

It can be assumed for observed waves with periods between 3 and 25 seconds that they are generated 
by wind.  The following Figure 1‐4 shows some equations related to waves: 

                                                            
1
Chakrabarti, S.K., “Hydrodynamics of Offshore Structures”, WIT Press, Southampton, UK. 
2
  Hasselmann  et  al.,  1973,  „Measurements  of  Wind‐Wave  Growth  and  Swell  Decay  During  the  Joint  North  Sea 
Wave Project (JONSWAP)”, Deutsche Hydrograph. Zeit., Ergänzungsheft Reihe A (8°), No. 12. 
 
Page 144  September 2013 
Technical Designs for Tranch‐1 Work 
 

Figure 1-3: A schematic for a two-dimensional wave spectrum (E(f, ) (CEM Figure II-1-
33))

Figure 1-4: Summary of linear (Airy) wave theory – wave characteristics (CEM Figure II-
1-9)
 
  Page 145 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 

Figure 1‐5 shows the different wave phases, the velocity and the acceleration of water particles of the 
waves for deep water conditions.  If the waves are entering the transition zone they start to transform 
and become more elliptic because the particles are influenced by the bottom.  

Figure 1-5: Wave phases

2. Generation of Waves: 
 
The generation of waves depends on  fetch length,  wind speed and duration of wind event. The fetch 
length is the length of the water surface, for example of a lake or an ocean the wind is blowing across. It 
is the length of the water surface, where the wind can transfer energy to the water. Wave generation 
can be limited by (i) the duration of the occurring wind (duration limited) or (ii) the length of the water 
surface of ocean/lake (fetch limited). Wind must blow for a certain time to develop the full wave height 
for  the  given  fetch  length.  Only  after  some  time  of  blowing  across  the  surface,  sufficient  energy  is 
transferred into the water surface to generate the full wave height. 
 
The  time  it  takes  for  waves  to  travel  the  fetch  length  can  be  calculated  with  the  following  formulae 
(CEM, II‐2‐35): 
X 0.67
t x ,u  77.23  
u 0.34 g 0.33
 
where X is the fetch length and uw is the wind speed. 
 
Figure 2‐1 shows the minimum time for different wavelength and different wind speeds.  It shows for 
example  that  a  two  km  wide  water  surface  requires  minimum  25  m/s  wind  speed  for  30  min  to 
generate the full wave height.  For a five km wide water surface is requires about 55 minutes of 20 m/s 
wind.   

 
Page 146  September 2013 
Technical Designs for Tranch‐1 Work 
 

Figure 2‐1: Equivalent duration for wave generation as a function of fetch and wind speed 
(CEM figure II‐2‐3) 
 
JONSWAP (Joint North Sea Wave Project, Hasselmann et al., 19733) gives formulas to calculate the have 
heights and wave period: 
~ ~
H s  0.00178  F 0.5  
~ ~
T p  0.352  F 0.3  
 
where the non‐dimensional parameters are: 
~
H s  gH s / U W2  
~
F  gF / U W2  
~
T p  gT p / U W2  
 
where Uw is the wind speed, F is the fetch length, Hs the significant wave height, and Tp is the peak wave 
period.  
 
Figure  2‐2  to  Figure  2‐5  show  the  diagrams  for  estimating  wave  height  and  period  for  known  wind 
speed and duration.  Figure 2‐6 and Figure 2‐7 summarize these diagrams for some wave heights and 
wave periods for fetch and duration limited wave climates, while Figure 2‐8 gives some wave heights for 
fetch limited wave climate for six different wind speeds.  It shows for example that the generated wave 
for a 5 km wide water surface and 15 m/s wind speed is 60 cm high.  However, this wave only occurs if 
the wind blows for a minimum of 45 minutes (see Figure 2‐1).  

                                                            
3
 Hasselmann et al., 1973, „Measurements of Wind‐Wave Growth and Swell Decay During the Joint North Sea 
Wave Project (JONSWAP)”, Deutsche Hydrograph. Zeit., Ergänzungsheft Reihe A (8°), No. 12. 
 
  Page 147 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 

Figure 2-2: Fetch-limited wave heights (CEM Figure II-2-23)

Figure 2-3: Fetch-limited wave periods (CEM Figure II-2-24)

 
Page 148  September 2013 
Technical Designs for Tranch‐1 Work 
 

Figure 2-4: Duration-limited wave heights (CEM Figure II-2-25)

Figure 2-5: Duration-limited wave periods (CEM Figure II-2-26)

 
  Page 149 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 

Figure 2-6: Wave heights and period for fetch limited waves

 
Page 150  September 2013 
Technical Designs for Tranch‐1 Work 
 

Figure 2-7: Wave heights and period for duration limited waves

 
  Page 151 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
Wave height fetch limited
35 m/s
3 30 m/s

2.5 25 m/s
20 m/s
Wave height [m]

2 15 m/s
10 m/s
1.5

0.5

0
0 5 10 15 20
Fetch length [km]

Figure 2-8: Wave heights for fetch limited wave climate

3. Transition zone (Shoaling and Refraction) 

As already mentioned above, the water depth influences waves.  If the water depth becomes less than 
0.5 H, wave height and wavelength are changing. If waves are not already running perpendicular to the 
bank line the wave direction will turn towards a direction perpendicular to the bank line.  This change in 
direction  is  called  refraction  and  is  caused  when  waves  come  into  contact  with  the  bottom  and 
consequently slow down their movement. At the same time and for the same reason the wave height 
will change. This is called shoaling. The formula for calculating the wave height is: 

 
where Ks and Kr are the coefficient for shoaling and refraction.  Both coefficients are smaller than unity 
and reduce the wave height.  The wave period remains unchanged. 
 
At a certain point the waves are breaking.  The breaker criteria for shallow water conditions is: 

 
It  means  that  the  wave  particles  at  the  crest  are  faster  than  the  wave  itself  and  the  wave  becomes 
unstable.  The angle of the wave crest is less than 120°. 
 
However, waves can also break in deep water. The criteria are the same than for shallow water, but the 
water depth has no influence in the wave breaking. The formulae is  

 
Wave breaking on deep water condition can also occur as white capping, where the wave itself remains 
stable and only the upper part of the wave breaks.  This might happen with strong winds on high waves, 
where the wind accelerates only the upper part of the wave and this part is detached from the lower 
part of the wave.  

 
Page 152  September 2013 
Technical Designs for Tranch‐1 Work 
 
4. Wind Conditions in Bangladesh 
 
4.1 General
Figure  4‐1  shows  the  distribution  of  heavy  thunderstorms  around  the  world.    It  can  be  seen  that 
Bangladesh is located in an area with a higher risk of thunderstorms. These thunderstorm can generate 
fast winds, but will only create high waves, if the duration of the storm is long enough and the direction 
is sufficient to have a long fetch to generate high waves.  

Figure 4-1: Distribution of heavy thunderstorms around the world

4.2 Previous Studies


Halcrow  (1994)4  investigated  wind  data  in  1994.  The  maximum  wind  speed  equal  to  or  exceeding  30 
knots recorded was as followed: 

Table 4-1: Wind speed and direction reported by Halcrow (1994)4:


Location  Wind speed [knots]  Wind speed [m/s]  Direction [°] 
Faridpur  35 18.0 340 
Faridpur  30  15.4  150 
Sirajganj  35  18.0  150 
Bogra  30 15.4 200 
Bogra  30  15.4  360 
Bogra  30  15.4  130 
Mymensingh  30 15.4 50 

The following wind frequency chart (see Figure 4‐2) shows a 10‐hour wind measurement.  It can be seen 
that wind of 30 knots (15 m/s) blows for 30 minutes.  Halcrow estimated a maximum wave height of 1.0 
m with a period of 3.0 s.  Unfortunately Halcrow gives no information about the duration of the wind 
speed.  
 

                                                            
4
 (Sir William Halcrow & Partner ltd., River Training Studies of the Brahmaputra River, Master Plan Report, 1994, Technical Annexes, Annex 4 
Design and Construction) 
 
  Page 153 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
To generate wave heights of 1.0 m as reported by Halcrow a wind of 30 knots/15 m/s blowing over 20 
km fetch length for about 3 hours is necessary.  A wind of 15 knots/8 m/s is necessary for about 9 hours. 
The wave period is then 3.5 s. 

Figure 4-2: Wind measurement recorded by Halcrow (1994)4

4.3 JMREMP Study


We have received some wind data from the Bangladesh Meteorological Department for the four wind 
stations  at  Bogra,  Ishurdi,  Chandpur,  and  Comilla  (see  Figure  4‐3).    The  data  sets  contain  10  years  of 
measurements.  Measurements were taken 8 times a day for 10 minutes and the average was recorded. 
 
We have analysed the data as follows: 
1. In a first step we have divided the wind data for each side into 4 sectors: North, East, South and 
West.  We have plotted the monthly measured wind speeds per sector in Figure 4‐4 to Figure 4‐
7. The relevant JMREMP subproject is plotted in the centre.  This allows relating wind direction 
and orientation of riverbank protection work build under JMRMEP.  
2. In a second step the data were analysed for each 10°‐section. Figure 4‐8 to  Figure 4‐11 shows 
the  results  with  the  number  of  samples  for  every  section,  the  maximum  wind  speed  in  knots 
and the average of the upper third of the measurements (not taking the “0”‐measurements into 
account). 
 
The findings are: 
1. During the dry season the wind comes mainly from North‐Western directions,  while the wind 
during the monsoon season comes from South‐Eastern directions. 
2. The  riverbank  protection  work  at  both  sites  is  largely  oriented  in  north‐south  direction  and 
would be directly hit only through westerly winds (MDIP) and easterly winds (PIRDP). 
3. In general winds from northerly directions occur during the dry season from September to June. 
During this period water levels are mostly low.  Winds from southerly directions normally can 
be observed during the monsoon seasons.  

 
Page 154  September 2013 
Technical Designs for Tranch‐1 Work 
 
4. The maximum observed wind speed for Comilla was 31 knots (15 m/s), for Bogra and Ishurdi 35 
knots (18 m/s), and for Chandpur 36 knots (18 m/s).  Table 4‐2 shows the average wind speeds 
for the four locations.   
5. There are  substantial  periods when no wind was measured.  These  periods  occur all  over the 
year  and  are  not  limited  to  the  monsoon  or  dry  season.  During  the  whole  period  of 
measurements (10 years) 61% of all measurements at Chandpur were measurements without 
wind, 33% at Comilla, 34% at Ishurdi and 51% at Bogra. 

Table 4-2: Average Wind Speed from 1996-2005


  Chandpur  Comilla  Bogra  Ishurdi 
   Average wind speed 1996‐2005 with zero‐values 
16 May ‐ 31 October  1.15 3.22 1.97 2.39
1 November ‐ 15 May  0.95 1.97 1.52 1.89
  Average wind speed 1996‐2005 without zero‐values 
16 May ‐ 31 October  2.69 4.06 3.63 3.40
1 November ‐ 15 May  2.70 3.62 1.96 3.04

 
  Page 155 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 

Figure 4-3: Location of Wind Stations and Sites

 
Page 156  September 2013 
Technical Designs for Tranch‐1 Work 
 

 
Figure 4‐4: Wind in Bogra from 1996 to 2005 

 
  Page 157 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 

 
Figure 4‐5: Wind in Ishurdi from 1996 to 2005 

 
Page 158   September 2013 
Technical Designs for Tranch‐1 Work 
 

 
Figure 4‐6: Wind in Chandpur from 1996 to 2005 
 

 
  Page 159 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 

 
Figure 4-7: Wind in Comilla from 1996 to 2005

 
Page 160   September 2013 
Technical Designs for Tranch‐1 Work 
 

Bogra, Wind Direction 0


35012000 10
340 20 Bogra
330 30
10000
320 40 Direction Samples Percent aver(1/3) max
310 8000 50 0 530 2 5.06 18
300 6000 60 10 6 0 3.57 4
290 4000 70 20 6 0 7.00 9
280 2000 80 30 21 0 4.29 6
40 12 0 8.75 12
270 0 90
50 903 3 5.45 18
260 100
60 1 0 2.00 2
250 110
70 3 0 4.00 6
240 120 80 9 0 4.00 4
230 130 90 3,597 12 6.08 34
220 140 100 3 0 6.00 6
210 150
200 160 110 1 0 10.00 10
190 170
180 Samples 120 7 0 3.00 4
130 3,646 12 5.26 17
140 6 0 4.00 4
150 12 0 5.00 7
160 3 0 8.00 8
Bogra, Wind Speed 0

340
350 40 10
20
170 1 0 2.00 2
330 30
35 180 1,546 5 5.19 15
320 40
30
310 50
190 2 0 4.00 4
25
300 20 60 200 - - 0.00 0
290 15 70
210 60 0 4.95 8
280
10
80
220 23 0 4.25 6
5
230 991 3 5.73 23
270 0 90
240 1 0 2.00 2
260 100
250 1 0 3.00 3
250 110
260 1 0 2.00 2
240 120
270 1,284 4 4.27 25
230 130
280 - - 0.00 0
220 140
210 150 290 - - 0.00 0
200 160
190 170 aver(1/3) 300 - - 0.00 0
180
max 310 1,590 5 4.83 28
320 - - 0.00 0
330 10 0 4.00 5
340 4 0 3.00 4
350 10 0 2.00 2
360 530 2 5.06 18
Samples 14,290 49
Average/day 3.92
0-values 14,910
0-value % 51.1
Figure 4-8: Wind Speed and Direction at Bogra
(1996-2005)

 
  Page 161 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 

Ishurdi, Wind Direction 0


35012000 10
340 20
330 30
10000
320 40 Ishurdi
310 8000 50
Direction Samples Percent aver(1/3) max
300 6000 60
0 2,407 8 4.36 16
290 4000 70
10 5 0 3.50 4
280 80
2000 20 3 0 2.00 2
270 0 90 30 32 0 9.13 14
260 100 40 122 0 4.21 12
250 110 50 512 2 4.77 17
240 120 60 11 0 5.00 7
230 130 70 4 0 2.00 2
220 140 80 9 0 2.67 4
210 150
200 160 90 1,448 5 6.16 17
190 170
180
Samples 100 1 0 10.00 10
110 - - 0.00 0
120 1 0 4.00 4
130 4,401 15 6.12 18
Ishurdi, Wind Speed
140 38 0 5.92 10
0

340
350 40 10
20
150 4 0 3.00 4
330 30
35 160 11 0 5.75 10
320 40
30
310 50
170 - - 0.00 0
25
300 20 60
180 4,807 16 5.45 15
290 15 70
190 4 0 8.00 8
10 200 3 0 4.00 4
280 80
5
210 94 0 5.28 10
270 0 90
220 406 1 5.24 12
260 100
230 998 3 5.42 35
250 110 240 6 0 8.00 8
240 120 250 6 0 2.00 2
230 130 260 5 0 5.00 6
220 140
210 150
270 1,793 6 5.05 25
200
190 170
160 aver(1/3) 280 27 0 4.11 10
180
max 290 1 0 2.00 2
300 15 0 4.50 5
310 1,691 6 12.50 16
320 239 1 5.36 14
330 162 1 5.78 15
340 6 0 3.50 4
350 1 0 2.00 2
360 2,407 8 4.36 16
Samples 19,273 66
Average/day 5.28
0-values 9,927
Figure 4-9: Wind Speed and Direction at Ishurdi 0-value % 34.0
(1996-2005)

 
Page 162   September 2013 
Technical Designs for Tranch‐1 Work 
 

Com illa, Wind Direction 0


350
12000 10
340 20
330 30
10000
320 40 Comilla
310 8000 50
Direction Samples Percent aver(1/3) max
300 6000 60
0 2,494 9 5.00 31
290 4000 70
10 6 0 5.50 6
280 2000 80
20 1 0 4.00 4
270 0 90
30 21 0 3.25 4
260 100 40 48 0 5.88 15
250 110 50 513 2 5.68 15
240 120 60 9 0 4.00 2
230 130 70 5 0 3.50 4
220 140
210 150
80 32 0 5.54 8
200
190 170
160 90 805 3 3.38 25
180
Samples 100 11 0 4.00 5
110 5 0 3.00 4
120 10 0 3.00 3
130 1,624 6 5.69 15
Com illa, Wind Speed 0
140 184 1 5.66 10
350 40 10
340 20 150 115 0 8.32 19
330 35 30
320 30 40 160 21 0 7.00 18
310
25
50
170 35 0 6.00 10
300 20 60
180 10,260 35 7.60 27
290 15 70
10
190 6 0 5.00 5
280 80
5 200 21 0 5.50 8
270 0 90
210 304 1 8.26 14
260 100
220 31 0 7.84 16
250 110
230 526 2 5.07 15
240 120
240 7 0 5.00 8
230 130
220 140
250 8 0 4.00 6
210 150
aver(1/3) 260 2 0 4.00 4
200 160
190 170
180 max 270 790 3 5.57 27
280 6 0 3.50 4
290 14 0 3.60 5
300 21 0 4.00 6
310 1,053 4 4.47 24
320 51 0 4.18 10
330 8 0 3.67 4
340 261 1 4.59 15
350 3 0 4.00 4
360 2,494 9 5.00 31
Samples 19,311 66
Average/day 5.29
0-values 9,889
0-value % 33.9

Figure 4-10: Wind Speed and Direction at


Comilla (1996-2005)

 
  Page 163 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 

Chandpur, Wind Direction 0


350
12000 10
340 20
330 30
10000
320 40

310 8000 50 Chandpur


300 6000 60
Direction Samples Percent aver(1/3) max
290 4000 70 0 1,146 4 3.65 16
280 2000 80 10 6 0 7.00 9
270 0 90 20 66 0 28.55 36
260 100
30 28 0 18.78 36
40 8 0 27.00 30
250 110
50 150 1 5.30 31
240 120
60 5 0 2.00 2
230 130

220 140
70 8 0 3.00 5
210 150 80 6 0 4.00 4
200 160
190 170
180
Samples
90 251 1 4.88 25
100 4 0 2.00 2
110 77 0 2.67 6
120 73 0 4.13 5
130 2,085 7 11.88 22
Chandpur, Wind Speed
0
140 247 1 6.32 15
350 40 10
340 20 150 28 0 3.60 5
330 35 30
320
30
40 160 166 1 3.36 6
310 50
25 170 7 0 2.00 2
300 20 60
180 3,794 13 4.49 20
290 15 70
10
190 5 0 3.00 3
280 80
5 200 29 0 3.82 8
270 0 90
210 316 1 3.35 11
260 100 220 129 0 3.67 9
250 110 230 565 2 4.90 12
240 120 240 - - 0.00 0
230 130
250 9 0 3.67 5
220 140
210 150 260 9 0 3.67 5
200 160 aver(1/3)
190
180
170
max
270 155 1 4.72 20
280 1 0 1.63 2
290 8 0 2.00 2
Note: The max for Chandpur 310° were taken out, because it 300 3 0 2.00 2
looked wrong (too high, max was 60 and the second highest 310 1,748 6 4.14 25
was 25). The max for Chandpur were taken out, because there
320 27 0 3.33 9
it looked wrong (too high, max was 90 and the second highest
was 20) 330 5 0 3.00 4
  340 143 0 2.33 6
  350 - - 0.00 0
  360 1,146 4 3.65 16
  Samples 11,307 39
  Average/day 3.10
0-values 17,893
Figure 4-11: Wind Speed and Direction at 0-value % 61.3
Chandpur (1996-2005)

 
Page 164   September 2013 
Technical Designs for Tranch‐1 Work 
 
The  Coastal  Engineering  Manual  (CEM)  provides  a  figure  to  transfer  wind  measurement  from  a  10 
minutes measurement to a 1 hr measurement, which is used for calculation of wave heights (see Figure 
4‐12).  It shows that the wind speed measured for 10 min is 5% higher than the 1‐hr wind.  The duration 
of  winds  still  remains  uncertain.    Due  to  this  it  is  very  difficult  to  estimate  the  relevant  design  wave 
height  and  wave  period.    It  would  be  very  helpful  to  have  frequency  duration  curves  for  both  sub‐
projects. 

Figure 4-12: Ratio of wind speed of any duration ut to 1-hr wind speed U3600 (Figure II-2-1)

5. Waves on Rivers 

The  flow  velocity  of  rivers  has  to  be  taken  into  account  for  calculating  the  wave  height.    The  wind  is 
transferring energy into the water based on the sheer stress.  If the wind speed and the flow velocity 
have  the  same  direction  the  sheer  stress  becomes  less,  because  the  difference  in  velocity  is  less.    To 
calculate the wave heights for these cases the flow velocity has to be deducted from the wind speed if 
they both have the same direction.  If the direction is opposed to each other the velocities need to be 
summed up.  
 
For  the  major  rivers  in  Bangladesh  the  highest  measured  flow  velocities  over  longer  areas  are  2  m/s 
close to the surface even though locally peaks of up to 4m/s can be observed.  Assuming a fetch length 
of 5 km and a constant wind of 17 m/s acting for 20 minutes on the river surface, the generated wave 
will  have  a  height  of  0.7  m,  a  wave  period  of  2.8  s  and  a  wavelength  of  12.5  m.  The  transition  zone 
begins at a depth of 6.25 m.  Superimposing the flow velocity v = 17 m/s and the wind speed of w = 2 
m/s and calculation the wave height result is a height of 0.8 m with a period of 3 s.  The wave length is 
then 13.6 m and the transition zone starts at 6.8 m, which is a 0.1 m higher and 1 m longer wave.  If the 
wind comes from the same direction then the current the wave height is 0.6 m with a period of 2.7 s.  
The wave length is 11.3 m.  
 
 
 

 
  Page 165 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
6. Waves at PIRDP and MDIP 
 
The characteristics of the rivers on front of both sub‐projects are very different.  The Jamuna River at 
PIRDP  is  dominated  by  chars  and  channels  whereas  the  Meghna/Padma  River  at  MDIP  is  a  large 
channel,  in  places  up  to  5  km  wide.    The  single  channels  of  Jamuna  River  are  500  –  800  m  wide  and 
change width and depth during every monsoon season. Table 6‐1 summarizes our wave collection for 
different parameters. 
 
Table 6-1: Wave height calculation for several wind speeds and fetch length
Jonswap
Fetch [m] uw [m/s] tx,u [s] Hs [s] Tm [s] Tp Lo
150,000 7 918 1.5 4.8 5.5 47.2
100,000 7 700 1.3 4.3 4.9 37.0
100,000 5 785 0.9 3.7 4.3 28.3
50,000 6 464 0.8 3.3 3.7 21.6
20,000 16 180 1.3 3.7 4.2 27.3
20,000 14 188 1.1 3.5 4.0 24.5
20,000 12 198 1.0 3.3 3.8 21.7
20,000 10 211 0.8 3.0 3.5 18.7
20,000 9 219 0.7 2.9 3.3 17.2
20,000 7 238 0.6 2.6 3.0 14.1
20,000 5 267 0.4 2.3 2.6 10.8
20,000 4 288 0.3 2.1 2.4 9.0
20,000 3 318 0.2 1.9 2.2 7.2
15,000 16 148 1.1 3.4 3.9 23.0
15,000 9 180 0.6 2.7 3.1 14.5
10,000 17 111 1.0 3.0 3.5 18.9
10,000 8 143 0.5 2.3 2.6 10.3
5,000 19 67 0.8 2.6 3.0 13.6
5,000 17 70 0.7 2.5 2.8 12.5
5,000 15 73 0.6 2.4 2.7 11.3
5,000 10 83 0.4 2.0 2.3 8.2
2,000 17 38 0.4 1.9 2.2 7.2
2,000 14 40 0.4 1.7 2.0 6.2
2,000 10 45 0.3 1.5 1.7 4.7
2,000 8 49 0.2 1.4 1.6 3.9
Uw = wind speed, tx_u = necessary time needed for full wave height, Hs = significant wave height, Tm = Mean
Period, Tp = Peak Period, L0 = Wave length (deep water conditions)

PIRDP:

Due to the occurrence of channels and chars the wave climate is characterized by cross‐seas.  Waves 
are travelling through channels and interact.  Observations have shown that waves are normally short 
and quiet steep and break (see Figure 6‐1). The maximum fetch length for northern and eastern winds is 
5  km  during  the  monsoon  season  and  the  water  depth  is  then  7  m  or  more,  depending  on  the 
morphological  changes  in  the  river  from  year  to  year  (the  location  and  size  of  the  chars  can  vary).  
During  the  dry  season  the  maximum  fetch  from  these  directions  is  2  km.    The  maximum  fetch  for 
southern directions parallel to the bank can become 20 km depending on the water levels.  During the 
dry season the fetch is 10 km.  

 
Page 166   September 2013 
Technical Designs for Tranch‐1 Work 
 

Figure 6-1: Fetch length PIRDP

Table  6‐2  shows  the  calculated  maximum  wave  height  for  different  direction  for  the  dry  and  the 
monsoon season.  The table also shows the time required for full energy transfer.  The maximum wave 
height for the dry season is 0.45 m coming from South with a period of 2.3 s. The transition zone starts 
at a depth of 5.2 m.  During monsoon season the wave height is 0.7 m with a period of 2.8 s also coming 
from South.  The transition zone starts at a water depth of 6.3 m.  The required wind duration for its 
generation  is  92  minutes.    This  wind  with  a  speed  of  24  knots  was  only  recorded  one  time  within  10 
years  of  data.    The  next  lowest  wind  speed  was  18  knots.    This  wind  would  generate  a  wave  with  a 
height of 0.4 m and a period of 2.3 s. 
 
For  a  wind  speed  of  8  m/s  and  a  fetch  length  of  2  km  the  calculation  of  the  wave  height  is  like  the 
following bases an the formulae given in section: 
 
20000.67
t x ,u  77.23 0.34  49 min  
8 9.810.33
~
F  gF / UW2  
~
F  g  2000/ UW2  306.6  
~
H s  0.00178 306.60.5  0.03m  

 
  Page 167 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
~ ~
Tp  0.352  F 0.3  0.352 306.60.3  2.0  
 
where the dimensional parameters are: 
~
H s  H s UW2 / g  0.03 82 / 9.81 0.2m  
~
Tp  Tp UW / 9.81  2  8 / 9.81  1.6s  

Table 6-2: Wave estimation for PIRDP site


  North  East  South  West 
Dry season fetch length (km)  2  2  10     ‐ 
Max. 1 hr Wind Speed (knots(m/s))  18 (8) 35 (17) 15 (8) 35 (17) 
Max. Wave height (m)  0.20 0.43 0.45    ‐ 
Wave Period Tp (s)  1.6  2.2 s  2.3   
Wave Length Lo (m)  3.9 7.2 10.3  
Time required for full energy transfer  49 min 38 min 143 min   
         
Monson season fetch length (km)  5 5 20    ‐ 
Max. Wind Speed (knots (m/s))  20 (10) 35 (17) 10 (5) 35 (17) 
Max. Wave height (m)  0.4  0.7  0.4     ‐ 
Wave Period Tp  (s)  2.3  2.8  2.6   
Wave Length Lo (m)  8.2 12.5 10.8  
Time required for full energy transfer  23 min  19 min  2 h   

The available wind data indicate that wave heights at PIRDP do not exceed 0.6 m. The expected wave period is then 2.5 s.  

MDIP: 
 
There  are  no  chars  in  the  Meghna  and  Padma  River  at  the  MDIP.    The  fetch  length  depends  on  the 
direction of the wind: If the wind is blowing from northern direction parallel to the bank the fetch is 20 
km.  The fetch from southern directions is more difficult to estimate.  Although the Lower Meghna River 
is much wider than the upper Meghna River and the Padma River the Lower Meghna there is a bend 
south of Chandpur.  A conservative estimate for the fetch would be 20 km.  This is a reasonable fetch 
for waves from SSW.  The fetch can also be assumed to be more than 50 km by assuming there will be 
defraction  and  refraction  and  the  waves  may  travel  all  the  way  up  towards  Chandpur.    However,  for 
waves travelling all the way up from the south the waves will hit the bankline on the opposite site bank 
of  the  Meghna  River.    Observed  waves  were  very  uniform,  long  crested,  non‐breaking  and  significant 
higher than in PIRDP.  The highest waves seem to come from southern directions.   
 
The  confluence  of  Padma  and  upper  Meghna  could  influence  the  development  of  waves.    Figure  6‐3 
shows ACDP (Acoustic Current Doppler Profiler) measurements with the flow velocity at the confluence 
of  the  Upper  Meghna  and  the  Padma  River.    It  can  be  seen  that the  fast  current  of  the  Padma  flows 
under the slower current of the Meghna. The water of the Upper Meghna is lighter than the water of 
the Padma, because it contains less sediment.   
 
Another  issue  for  the  wave  estimation  for  MDIP  is  the  influence  of  tide.    The  highest  waves  will 
probable be generates during low tide with a high flow velocity and wind from southern directions. The 
sum of these two velocities (flow + wind) is the wind speed to be used for the wave height estimation. 
 

 
Page 168   September 2013 
Technical Designs for Tranch‐1 Work 
 

Figure 6-2: Fetch length MDIP

t = 3.26, 26 July 2001, Q = 22,000, Left Bank to Right Bank

Figure 6-3: Flow velocity at MDIP (confluence Meghna/Padma)

On 11 March the Chandpur Metrological Station measured 31 knots at 15:00 UTC and 18:00 UTC.  On 13 
March  1998  the  station  measured  31  knots  at  03:00  UTC  and  06:00  UTC.    On  14  March  1998  they 
measured 31 knots at 03:00 and 06:00 UTC and 36 knots at 09:00 UTC, which indicated a wind of 16 m/s 
can be assumed for 6 h or more with all these winds coming from North (20°).  The Upper Meghna is 
meandering very much with a main direction of 20°, but the characteristic of the river is changing about 
20 km upstream of the project area.  From thereon the river is not meandering anymore and if flows 
strait to the south.  Due to this the fetch length has to be reduced to a very small amount.  Taking  a 
fetch  of  2  km  into  account  the  wave  height  is  0.35  m,  but  in  fact  there  will  be  no  waves  from  this 
direction in front of the project.  The highest observed wind from 360° is 9 m/s.  The resulting wave is 
0.55 m high with a period of 2.9 s. and a wave length of 13.2 m.  
 
  Page 169 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
 
Between 26 July 2003 at 09:00 UTC and 27 July 2003 at 03:00 UTC the Chandpur Metrological Station 
recorded 6 knots or more coming  from 180° (see Figure  6‐4).  Assuming a  fetch of 150 km (the fetch 
reaches from the Bay of Bengal all the way up to Chandpur) and taking the flow velocity into account 
the generated wave is 1.1 m high with a period of 4.8 s and a wave length of 36 m.  The wind would 
have to blow for 17 hours.  This value is very high.  The resulting wave would be 1 m/s at the eastern 
bank.  There are no wave measurements available and it is suggested to verify this value by a numerical 
wave model and wave measurements.  Table 6‐3 shows the calculated waves for the three sectors.  The 
highest wave is 1.1 m high coming from South, but this calculation takes a fetch of 150 km into account 
and a wind for 17 h.  A wave with a height of 1 m can be generated from western directions with a wind 
of 13 m/s for 3 hours. 

Figure 6-4: Wind speed measured at Chandpur July 2003

Table 6-3: Wave estimation for MDIP site


  North East South West 
Dry season fetch (km)  15     ‐  20  20 
Max. 1 hr Wind Speed (knots (m/s))  18 (9)  31(15)  9 (5)  25 (13) 
Adjusted wind speed (current) (m/s)  8 15 7 13 
Max. Wave height (m)  0.55     ‐  0.56  1 
Wave Period Tp (s)  2.9    3.0 s  3.9 
Wave Length Lo (m)  13 14 23.1 
Time needed for full energy transfer  180 min    238 m  193 min 
         
Monson season fetch (km)  15   ‐ 20 20 
Max. Wind Speed (knots (m/s))  18 (9)  35 (17)  4 (2)  6 (3) 
Adjusted wind speed (current) (m/s)  9  15  4  3 
Max. Wave height (m)  0.63   ‐ 0.32 0.2 
Wave Period Tp (s)  3.1    2.4  2.2 
Wave Length Lo (m)  14.5    9   
Time needed for full energy transfer  180 min 288 min  318 min

For  a  wind  speed  of  20  m/s  and  a  fetch  of  10  km  it  would  need  105  minutes  of  wind  to  fulfil  the 
conditions for a fetch limited wave climate.  The wave would then have a height of 1.1 m with a wave 
period of 3.7 seconds. The wave length is then 21 m and the transition zone starts at a depth of 10.5 m, 
with is about 25 m in front of the bank line (slope: 1H : 2.5V). With a fetch of 20 km at the same wind 
speed it needs 167 minutes to generate a fetch limited wave climate.  The generated wave would have 
a height of 1.6 m and a period of 4.6 seconds. The wavelength would be 32 m. 
 
Page 170   September 2013 
Technical Designs for Tranch‐1 Work 
 
 
During  low  water  the  waves  will  break  close  to  the  toe  on  the  dumped  cc‐blocks.  During  high  water 
level the waves will break at the crest (see Figure 6‐5). 

Figure 6-5: Water depth at PIRDP (A) and MDIP (B)

The available wind data indicate that wave heights at the MDIP would be in the order of 1 m. The 
expected wave period is then 3.9 s. 

 
  Page 171 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
Appendix V:  Road on the Land‐Side of Rehabilitated or Reconstructed Embankment 
 
  BOQ of the Proposed Road cum Flood Embankment cum Road   
                                     (As per Specification & Unit Rate of RHD)                                  

Main  River  Flood  and  Bank  Erosion  Risk  Management  Program  include  construction  of  two  roads  r 
under tranche‐1 as shown in Table‐1: 
Table‐1:  Roads under  Trenche‐1 
Serial  Start point  End point  Length  Location 

1  Verakhola  Kaijuri  13.00 KM         Land‐side Bank of Jamuna River 


2  Verakhola  Baghabari  10.00 KM         Land‐side Bank Hurasagar River 

The proposed roads would have 5.5 meter bituminous pavement with 1.5 meter hard shoulder in each 
side.  The  road  would  be  designed  to  function  not  only  as  part  of  flood  embankment  and  shelter  for 
flood  effected  population  but  would  also  provide  connectivity  to  growth  centers,  river  ports,  local 
government institutions situated in the adjoining area of the proposed flood embankments of  Pabna, 
Sirajganj districts. It is obvious that the both roads would be connected to the nearby national highways 
to meet the growing demand of the traffic in future and to facilitate better connectivity of population.  
 
The geometric features and function of the roads are similar to regional roads. Roads having  3.6 meter 
pavement  width with 1.5 meter hard shoulders are  zilla road under Roads and Highways Department 
connecting  District HQ  with Upazila HQ and Feeder Road‐Type B Under Local Government Engineering 
Department  connecting    Upazilas  and    Growth  Centers.  The  functions  and  the  specification  of  the 
proposed  roads  are  not  similar  to  Zilla  Road  and  Feeder  Road‐B.  The  geometric  features  of  the  road 
particularly,  pavement  width  of  5.5  meter  with  1.5  meter  hard  shoulder  on  each  side  and  projected 
traffic  on  completion  of  the  road  are  similar  to  the  specification  of  regional  road.  Hence  the  roads 
would be built as regional roads to meet the growing of projected traffic of the future  
 
Geometric Features and Pavement Components of the Proposed Roads 
The  following  standards  and  specifications,  also  applicable  for  regional  roads  have  been  followed  in 
designing of geometric and structural components of proposed roads: 

Table‐2:   Standards and Specifications of Regional Roads 
Serial       Item    Value
1  AADT    1500 
2  Traffic Growth rate  7% per annum 
3  Axle load considered for Pavement  Design 4‐5 million axle Load 
4  Pavement width  5.5 meter 
5  Pavement Type  Bituminous  
6  Pavement Life  20 years
7  Bituminous Carpeting  40mm 
8  Seal oat  12 mm 
9  Base  200mm
10  Sub base  200mm
11  Improved Sub Grade  200mm 
Source: Pavement Design Guide for Roads & Highways Department, April 2005

The feasibility level design of the pavement and geometric elements of the road have been proposed as 
per minimum requirement of standards and specifications of the Regional Roads. The cross‐section of 
pavement  of  the  proposed  road  showing  the  thickness  of  different  layer  of  pavement  components  is 
given in figure‐4. 
 

 
Page 172   September 2013 
Technical Designs for Tranch‐1 Work 
 
U‐shaped  surface  drain  of  350.00mm  wide  along  with  storm  water  catch  pit  of  900.00 
X900.00mmX1000.00  at  200.00mm  apart  have  proposed  to  drain  off  storm/rain  water  from  road 
surface.  In  addition,  500.00.mm  diameter  RCC  pipe  has  been  proposed  to  provide  cross‐  wise 
underneath  the  pavement  for  each  catch  pit  to  drain  off  the  water  to  the  outer  side  of  the  road 
crest.The plan ofdrain,The cross‐section of the drain, storm water catch pit, have been shown in Figure‐
1 ,Figure‐2 , Figure‐3 and Lay out Plan of R.C. C Pipe, Embankment Slope Drain and Spill Way are shown 
in Figure‐5.ely. 
 
Bill of Quantities for the Construction of Proposed Roads 
The  standards  and  speculations  and  the  rate  schedule  of  regional  roads  of  RHD  have  been  primarily 
used  in  preparation  of  Bill  of  Quantities  (BOQ)  items  of  pavement  works.  In  case  of  R.C.C  and  Brick 
works, standards and speculations of and schedule of rates of LGED have been used. The BOQ cost of 
Verakhola  ‐  Kaijuri  road  and  Verakhola  –  Baghabari  road  are  TK.  29,  73,  65,474.51  and  TK.  22,  93, 
07,128.89  respectively.  The  BOQ  of  Verakhola  ‐  Kaijuri  road  and  Verakhola  –  Baghabari  road  are 
annexed as Annexure‐A and Annexure‐B 

Verakhola‐
Verakhola‐Kaijuri 
Baghabari Road           Total 
SL   Description of Items  Road (in Taka) 
(in Taka)          (3+ ‐4) 
 
 

1  2  3  4  5 

1  Construction of Pavement  22,37,82,260.00  17,21,40,200.00  39,59,22,460.00 

2  Protection of the Slope of the Embankment    2,46,48,000.00  1,89,60,000.00  4,36,08,000.00 

3  Surface Drain and Cross Drain 

3.1  Construction of 400 mmX550mm Surface Drain  3,73,50,274.49  2,87,30,908.38  6,60,81,254.87 

Construction of 750mmX750mm X 750mm Storm 
3.2  9,29,279.62  7,18,079.72  16,47,359.33 
Water Catch Pit at 200.00 Meter Apart 
Supplying and Fitting and Fixing of  500.mm R.C.C 
3.3  Pipe at 200 meter Apart along the Alignment  of  33,48,162.88  31,11,166.17  64,59,329.05 
the Drain 
Construction of RCC Drain on the Slope of the 
3.4        73,07,497.52        56,46,702.63  1,29,54,200.15 
Embankment 

Total Cost of Two Roads  29,73,65,474.51  22,93,07,128.89  52,66,72,603.40 

Verakhola-Baghabari Road
Length: 10 Kilometer

Bill of Quantities
…………………………..Annexure-B………………………..
Rate 
Item Code  Amount 
Item Description  Measurement Quantity  Unit   (in 
No  (in Taka) 
Taka) 
Construction of Pavement 
02/07/02‐ Preparation of Sub‐grade  10000.00m x 5.50m  
Sqm  85.00    46,75,000.00 
RHD  (450mm depth)  =55,000.00 Sqm           

 
  Page 173 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
02/08/01‐ 10000.00m x 5.50m x0.200m  
Improved Sub‐Grade     Cum  804.00    88,44,000.00 
RHD  =11,000 .00 Cum           

02/11/01‐ 2 x10000.00m x1.50m x0.200m 
Construction of Hard Shoulders  Cum  4068.00  2,44,08,000.00 
RHD  = 6000.00 Cum           

03/02/01‐ Sub ‐ base        10000.00m x 5.50m x0.200m 


Cum  3953.00  4,34,83,000.00 
RHD     =11,000.00Cum           
03/03/02‐
Aggregate base   10000.00m x 5.50m x0.200m  
RHD  Cum  4275.00  4,70,25,000.00 
  = 11,000.00 Cum           
 
03/06/01(b
Bituminous Prime coat (Hand  10000.00m x 5.50m 
) ‐RHD  Sqm  87.00   47,85,000.00 
place)   =55,000.00 Sqm           
 
03/07/01(b
Bituminous Tack coat   10000.00m x 5.50m 
) ‐RHD  Sqm  22.00   12,10,000.00 
(Labor intensive work)   =55,000.00 Sqm           
 
03/11/01(a Premixed Bituminous Carpeting   10000.00m x 5.50m x0.040m   13191.0
Cum   2,90,20,200.00 
) ‐RHD    40mm thick (Av.)  =2,200.00 Cum            0 

03/12/02‐ 2mm compacted‐ premix  10000.00m x 5.50m 


Sqm  126.00      69,30,000.00 
RHD        Bituminous Seal Coat.    =55,000.00 Sqm           

03/13/01‐  2 x 10000.00m   Lin.      


Brick on end edging     88.00 
RHD  =20,000.00 Lin. M    M  17,60;000,00.00 
Sub Total=  17,21,40,200.00 
2.Protection  Work of the Slope of the Embankment 
*  600mm thick blanket of earth cladding with   10,000.00mX12.00 
specified cohesive soil on the side slope of  m  Sqm  110.00  1,32,00,000.00 
embankment    =1,20,000.00 Sqm 
**  Supplying and planting vertiver (Binna) grass in  10,000.00mX12.00 
bunch of 2 to 3 stem @ of 225 mm all over the  m  Sqm  48.00    57,60,000.00 
side slope  =1,20,000.00 Sqm 
                                                                                                                                                      Sub Total=  1,89,60,000.00 

3.Surface Drain and Cross Drain 
3.1 Construction of 400 mmX550mm Surface Drain

1.15 X 0.7X 
Earthwork in excavation of drains etc. by  10,000.00  
5.02.01‐ excavating earth to the lines, grades and  = 0.8050X10,000 
Cum  78.42  6,31,281.00 
LGED  elevation as per  drawing, carrying and  = 8,050.00 cubic 
disposing of all excavated materials;  meter 
 
Single brick flat soling with 1st class/ PJ bricks, 
true to level, camber, super elevation and 
5.03.01‐ 1.15mX 10,000.00    
grade in/c filling the joints with sand (FM  Sqm  251.04  28,86,960.00 
LGED  =11,500.00 Sqm 
0.50) in/c cost of all materials complete as per 
direction of the Engineer‐in‐Charge 
Brick work with 1st class bricks with 6mm 
(2X0.375mX0.25m
thick cement mortar (1.4) for guard wall of 
X1.m+2X 
drain, foot path and median, filling the 
0.30mmX0.250mX 
interstices tightly with mortar, raking out 
5.02.03‐ 1m )X 10,000.00 
joints, cleaning and soaking bricks at least for  Cum  4665.16  1,92,43,785.50 
LGED  =0.4125X10,000.0
24 hours before use, washing of sand, curing 

for requisite period, cost of all materials, etc. 
 =4,125.00 Cubic 
all complete as per direction of the Engineer‐
Meter 
in‐ Charge. (Minimum F.M. of sand: 

 
Page 174   September 2013 
Technical Designs for Tranch‐1 Work 
 
Cement concrete (1:2:4) with Portland 
cement, coarse sand    (F.M 1.80), First class/  1.15mX075mX 
PJ brick chips (25mm to 5mm down‐ graded),  10,000.00 
5.03.05‐
cost of materials and shuttering, mixing by  =0.08625X10,000. Cum  6362.15  54,87,354.38 
LGED 
concrete mixer machine, casting, laying,  00 
curing for the requisite period, etc. as per  = 862.50 Cum 
direction of the Engineer‐in Charge 
12 mm thick cement plaster (1:4) in drain  (0.300m+0.250m+
including cost of materials, washing of sand,  0.550m+0.600m+0
curing for requisite period, maintaining  .250m+0.850m)X1
5.12.01‐
proper curvatures of corners, side wall and  0,000.00  Sqm  172.00  4,81,600.00 
LGED 
bottom, costs of all materials, etc. complete,  =0.280m  X 
as per direction of the Engineer‐in‐charge.  10,000.00   
(Minimum F.M. of sand: 1.2  = 2,800.00Sqm 
Sub Total=    2,87,30,908.38 
3.2 Construction of 750mmX750mm X 750mm Storm Water Catch Pit at 200.00 Meter Apart 
1.050m X 1.050mX 
Earthwork in excavation of drains etc. by 
0.975m X 51 
5.02.01‐ excavating earth to the lines, grades and 
=1.0749X51  Cum  78.42  4,299.13 
LGED  elevation as per  drawing, carrying and 
=54.82 Cubic meter
disposing of all excavated materials; 
 
Single brick flat soling with 1st class/ PJ bricks, 
1.050m X 1.050mX  
true to level, camber, super elevation and 
5.03.01‐ 51 
grade in/c filling the joints with sand (FM  Sqm  251.04  14,115.35 
LGED  =1.1025 SqmX51 
0.50) in/c cost of all materials complete as per 
=56.227 Sqm 
direction of the Engineer‐in‐Charge 
Reinforced Cement Concrete in drain work 
Portland cement , sand (minimum F.M 1.80) 
20mm down well graded crushed 1st class 
brick/picked brick chips (LAA value not 
exceeding 40) including shuttering, mixing by 
concrete mixture machine casting , laying, 
compacting, curing for 28 days, breaking Ist  0.325 Cubic meter 
class/ picked brick chips  etc complete in all  RCC in each catch 
4.1.10.02.2 
respect as per design drawing, design and  pit X 51  Cum  7270.00  1,20,314.87 
LGED 
drawing , and direction of Engineer in Charge”  = 16.55 Cubic 
and cylinder  crushing strength of concrete  meter 
should not be less than 170 kg/cm2 
(suggested mix proportion 1:2:4) excluding 
reinforcement and fabrication, but  including 
cost of all materials, reinforcement, and its 
fabrication shuttering, casting curing for 28 
days and all incidental charges ,  
6.051‐ Supplying and Fabrication of M.S high 
LGED  strength deformed bar/Twisted bar 
reinforcement of size and length for all types 
of RCC work including straightening the rod, 
removing ruts, cleaning, cutting, hooking, 
bending, binding, with supply of 22 B.W.G. GI 
wire, placing in position, including lapping, 
spacing and securing them in position by 
concrete blocks (1:1), metal chairs, etc.  167.97kg of MS 
complete including cost of all materials, labor,  road in each catch 
kg  67.63  5,79,,350.37 
local handling, laboratory test, incidentals  pit X51 
necessary to complete the work as per   =8,566.47 kg 
specifications, drawings and direction of the 
Engineer. Laboratory test for physical, 
strength, elongation % & bend to be 
performed as peer ASTM. (Measurement will 
be based on standard weight of 490 lbs./ft3 
Chairs, laps and separators will be measures 
for payment. The cost of these will be 
included in the unit rate). 
 
  Page 175 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
Sub Total=  7,18,079.72 
3.3 Supplying and Fitting and Fixing of  500.mm R.C.C Pipe at 200 meter Apart along the Alignment  of the Drain 
Supplying precast RCC pipes(500 mm internal 
dia,50mm thick) with 12mm downgraded 
dust free 1st class brick chips (1:2:4)including 
12 meter long RCC 
6.096‐ pipe joint gap filling in neat cement slurry 
pipeX51 =792.00  meter  2910.83  23,05,377.36 
LGED  casting, curing, laying in position, from 
meter 
finished type by steel form works as per 
design , specifications complete as per 
direction of Engineer‐in Charge 
Single brick flat soling with 1st class/ PJ bricks, 
true to level, camber, super elevation and  3.00 m X 1.50mX.6 
5.03.01‐
grade in/c filling the joints with sand (FM  =4.5 SqmX51  Sqm  251.04  57,613.68 
LGED 
0.50) in/c cost of all materials complete as per  =229.50 Sqm 
direction of the Engineer‐in‐Charge 
Cement concrete (1:2:4) with Portland 
cement, coarse sand    (F.M 1.80), First class/ 
PJ brick chips (25mm to 5mm down‐  3.00mX1.50mX0.0
5.03.05‐ graded)in the foundation of guide wall, cost  75m X51 
Cum  6362.15  1,09,,508.58 
LGED  of materials and shuttering, mixing by  =0.3375 SqmX51 
concrete mixer machine, casting, laying,  = 17.212Cum 
curing for the requisite period, etc. as per 
direction of the Engineer‐in Charge 
Brick work with 1st class bricks with 6mm 
thick cement mortar (1.4) for guide wall of 
R.C.C pipe filling the interstices tightly with  2.00mX2.50mX0.5
mortar, raking out joints, cleaning and  0m X 51 
5.02.03‐
soaking bricks at least for 24 hours before  = 2.50 CumX51  Cum  4665.16  5,94,806.63 
LGED 
use, washing of sand, curing for requisite   =127.50 Cubic 
period, cost of all materials, etc. all complete  Meter 
as per direction of the Engineer‐in‐ Charge. 
(Minimum F.M. of sand: 
12 mm thick cement plaster (1:4) in guide 
wall including cost of materials, washing of  (2X1.00mX2.00m+ 
sand, curing for requisite period, maintaining  2X 0.25mX1.00m+ 
5.12.01‐
proper curvatures of corners, side wall and  0.25m X2m)X51  Cum  172.0015  43,860.00 
LGED 
bottom, costs of all materials, etc. complete,  =5.00 CumX51 
as per direction of the Engineer‐in‐charge.  = 255.00 Cum 
(Minimum F.M. of sand: 1.2 
Sub Total=  31,11,166.17 
3.4 Construction of RCC Drain on the Slope of the Embankment  
0.7 m X 0.675mX 
Earthwork in excavation of drains etc. by  11m X51 
5.02.01‐ excavating earth to the lines, grades and  =5,197X51 
Cum  78.42  20,784.99 
LGED  elevation as per  drawing, carrying and  =265.07cubic 
disposing of all excavated materials;  meter 
 
Single brick flat soling with 1st class/ PJ bricks, 
true to level, camber, super elevation and  0.70m X 11X.51 
5.03.01‐
grade in/c filling the joints with sand (FM  =7.7 SqmX51  Sqm  251.04  98,583.41 
LGED 
0.50) in/c cost of all materials complete as per  =392.70 Sqm 
direction of the Engineer‐in‐Charge 
Reinforced Cement Concrete in drain with 
Portland cement , sand (minimum F.M 1.80) 
20mm down well graded crushed 1st class  0.2310 Cubic 
brick/picked brick chips (LAA value not  meter RCC  in per 
exceeding 40) including shuttering, mixing by  running meter of  . 
4.2.04.02. 
concrete mixture machine casting , laying,  drain X 11m X51  Cum      7270.00  9,42,126.57 
LGED 
compacting, curing for 28 days, breaking Ist  = 2.541X51   
class/ picked brick chips  etc complete in all  =129.591 Cubic 
respect as per design drawing, design and  meter 
drawing , and direction of Engineer in Charge” 
and cylinder  crushing strength of concrete 
 
Page 176   September 2013 
Technical Designs for Tranch‐1 Work 
 
should not be less than 170 kg/cm2 
(suggested mix proportion 1:2:4) excluding 
reinforcement and fabrication, but  including 
cost of all materials, reinforcement, and its 
fabrication shuttering, casting curing for 28 
days and all incidental charges ,  

Supplying and Fabrication of M.S High 
strength deformed bar/Twisted bar 
reinforcement of size and length for all types 
of RCC work including straightening the rod, 
removing ruts, cleaning, cutting, hooking, 
bending, binding, with supply of 22 B.W.G. GI 
wire, placing in position, including lapping, 
spacing and securing them in position by  119.57 kg of MS 
concrete blocks (1:1), metal chairs, etc.  road in per running 
6.051‐ complete including cost of all materials, labor,  meter of R.C.C 
kg  67.63  45,36,537.22 
LGED  local handling, laboratory test, incidentals  drain X11mX51 
necessary to complete the work as per   =1315.27kgX51 
specifications, drawings and direction of the  =67078..77 kg 
Engineer. Laboratory test for physical, 
strength, elongation % & bend to be 
performed as peer ASTM. (Measurement will 
be based on standard weight of 490 lbs. /ft3 
Chairs, laps and separators will be measures 
for payment. The cost of these will be 
included in the unit rate). 
Cement concrete (1:2:4) in Spill way with 
Portland cement, coarse sand    (F.M 1.80), 
First class/ PJ brick chips (25mm to 5mm  1.00mX1.00mX0.1
5.03.05‐ down‐ graded), cost of materials and  50m.X 51 
Cum  6362.15  48,670,.45 
LGED  shuttering, mixing by concrete mixer  =0.150CumX51 
machine, casting, laying, curing for the  = 7.65 Cum 
requisite period, etc. as per direction of the 
Engineer‐in Charge 
Sub Total=        56,46,702.63 

Total=  22,93,07,128.90 

Verakhola-Kaijuri Road
Length: 13 Kilometer

Bill of Quantities Annexure-A


Rate 
Item Code  Amount 
Item Description  Measurement Quantity  Unit   (in 
No  (in Taka) 
Taka) 
Construction of Pavement 
02/07/02‐ Preparation of Sub‐grade  13,000.00m x 5.50m  
Sqm  85.00     60,77,500.00 
RHD  (450mm depth)  =71,500.00 Sqm           

02/08/01‐ 13,000.00m x 5.50m x0.200m  
Improved Sub‐Grade     Cum  804.00  1,14,97,200.00 
RHD  =14,300 .00 Cum           
2 x13000.00m x1.50m 
02/11/01‐
Construction of Hard Shoulders  x0.200m   Cum  4068.00  3,17,30,400.00 
RHD 
= 7800.00 Cum           
03/02/01‐ Sub ‐ base        13,000.00m x 5.50m x0.200m 
Cum  3953.00  5,65,27,900.00 
RHD     =14,300.00Cum           

 
  Page 177 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
03/03/02‐
Aggregate base   13,000.00m x 5.50m x0.200m  
RHD  Cum  4275.00  6,11,32,500.00 
  = 14,300.00 Cum           
 
03/06/01(b
Bituminous Prime coat (Hand  13,000.00m x 5.50m 
) ‐RHD  Sqm  87.00   62,20,500.00 
place)   =71,500.00 Sqm           
 
03/07/01(b
Bituminous Tack coat   13,000.00m x 5.50m 
) ‐RHD  Sqm  22.00   15,73,000.00 
(Labor intensive work)   =71,500.00 Sqm           
 
03/11/01(a Premixed Bituminous Carpeting   13,000.00m x 5.50m x0.040m   13191.0
Cum   3,77,26,260.00 
) ‐RHD    40mm thick (Av.)  =2,860.00 Cum            0 

03/12/02‐ 2mm compacted‐ premix  13,000.00m x 5.50m 


Sqm  126.00     90,09,000.00 
RHD        Bituminous Seal Coat.    =71,500.00 Sqm           

03/13/01‐  2 x13,000.00m  
Brick on end edging     Lin. M  88.00      22,88,000, 00 
RHD  =26,000.00 Lin. M   
Sub Total=  22,37,82,260.00 
2. Protection  of the Slope of the Embankment 
*  600mm thick blanket of earth cladding with   13,000.00mX12.0
specified cohesive soil on the side slope of  0 m  Sqm  110.00  1,71,60,000.00 
embankment    =1,56,000.00 Sqm 
**  Supplying and planting vertiver (Binna) grass in  13,000.00mX12.0
bunch of 2 to 3 stem @ of 225 mm all over the  0 m  Sqm  48.00    74,88,000.00 
side slope  =1,56,000.00 Sqm 
                                                                                                                                                        Sub Total=  2,46,48,000.00 

3.Surface Drain and Cross Drain 
3.1 Construction of 400 mmX550mm Surface Drain
1.15 X 0.7X 
Earthwork  in  excavation  of  drains  etc.  by 
13000.00  
5.02.01‐ excavating  earth  to  the  lines,  grades  and 
= 10,465.00 cubic  Cum  78.42  8,20,,665.30 
LGED  elevation  as  per    drawing,  carrying  and 
meter 
disposing of all excavated materials; 
 
Single brick flat soling with 1st class/ PJ bricks, 
true  to  level,  camber,  super  elevation  and 
5.03.01‐ 1.15X 13,000.00    
grade  in/c  filling  the  joints  with  sand  (FM  Sqm  251.04  37,53,048.00 
LGED  =14,9500.00Sqm 
0.50) in/c cost of all materials complete as per 
direction of the Engineer‐in‐Charge 
Brick  work  with  1st  class  bricks  with  6mm 
thick  cement  mortar  (1.4)  for  guard  wall  of  (2X0.375mX0.25
drain,  foot  path  and  median,  filling  the  mX1.m+2X 
interstices  tightly  with  mortar,  raking  out  0.30mmX0.250m
5.02.03‐
joints, cleaning and soaking bricks at least for  X 1m )X 13,000.00  Cum  4665.16  2,50,16,920.50 
LGED 
24 hours before use, washing of sand, curing  =0.412513,000.00 
for requisite period, cost of all materials, etc.   =5,362.50 Cubic 
all complete as per direction of the Engineer‐ Meter 
in‐ Charge. (Minimum F.M. of sand: 
Cement  concrete  (1:2:4)  with  Portland 
cement, coarse sand    (F.M 1.80), First class/  1.15X0.075X 
PJ brick chips (25mm to 5mm down‐ graded),  13,000.00 
5.03.05‐
cost  of  materials  and  shuttering,  mixing  by  =0.08625X13000. Cum  6362.15  71,33,560.69 
LGED 
concrete  mixer  machine,  casting,  laying,  00 
curing  for  the  requisite  period,  etc.  as  per  = 1121.25 Cum 
direction of the Engineer‐in Charge 
12  mm  thick  cement  plaster  (1:4)  in  drain  (0.300m+0.250m
including  cost  of  materials,  washing  of  sand,  +0.550m+0.600m
5.12.01‐ curing  for  requisite  period,  maintaining  +0.250m+0.850m
Sqm  172.00  6,26,080.00 
LGED  proper  curvatures  of  corners,  side  wall  and  )X13,000.00 
bottom,  costs  of  all  materials,  etc.  complete,  =0.280m  X 
as  per  direction  of  the  Engineer‐in‐charge.  13,000.00   

 
Page 178   September 2013 
Technical Designs for Tranch‐1 Work 
 
(Minimum F.M. of sand: 1.2  = 3,640.00Sqm 

Sub Total=    3,73,50,274.49 
3.2 Construction of 750mmX750mm X 750mm Storm Water Catch Pit at 200.00 Meter Apart 
1.050m X 
1.050mX 0.975m 
Earthwork in excavation of drains etc. by 
X 66 
5.02.01‐ excavating earth to the lines, grades and 
=1.0749X66  Cum  78.42  5,563.58 
LGED  elevation as per  drawing, carrying and 
=70.946 Cubic 
disposing of all excavated materials; 
meter 
 
Single brick flat soling with 1st class/ PJ bricks, 
1.050m X 
true to level, camber, super elevation and 
5.03.01‐ 1.050mX  66 
grade in/c filling the joints with sand (FM  Sqm  251.04  18,266.93 
LGED  =1.1025 SqmX66 
0.50) in/c cost of all materials complete as per 
=72.765 Sqm 
direction of the Engineer‐in‐Charge 
Reinforced Cement Concrete in drain work 
Portland cement , sand (minimum F.M 1.80) 
20mm down well graded crushed 1st class 
brick/picked brick chips (LAA value not 
exceeding 40) including shuttering, mixing by 
concrete mixture machine casting , laying, 
0.325 Cubic 
compacting, curing for 28 days, breaking Ist 
meter RCC in 
class/ picked brick chips  etc complete in all 
4.1.10.02.2  each catch pit X 
respect as per design drawing, design and  Cum  7270.00  1,55,701.59 
LGED  66 
drawing , and direction of Engineer in Charge” 
= 21.42 Cubic 
and cylinder  crushing strength of concrete 
meter 
should not be less than 170 kg/cm2 
(suggested mix proportion 1:2:4) excluding 
reinforcement and fabrication, but  including 
cost of all materials, reinforcement, and its 
fabrication shuttering, casting curing for 28 
days and all incidental charges ,  
6.051‐LGED  Supplying and Fabrication of M.S high 
strength deformed bar/Twisted bar 
reinforcement of size and length for all types 
of RCC work including straightening the rod, 
removing ruts, cleaning, cutting, hooking, 
bending, binding, with supply of 22 B.W.G. GI 
wire, placing in position, including lapping, 
spacing and securing them in position by 
concrete blocks (1:1), metal chairs, etc.  167.97kg of MS 
complete including cost of all materials, labor,  road in each 
kg  67.63  7,49,,747.53 
local handling, laboratory test, incidentals  catch pit X66 
necessary to complete the work as per   =11,086.02 kg 
specifications, drawings and direction of the 
Engineer. Laboratory test for physical, 
strength, elongation % & bend to be 
performed as peer ASTM. (Measurement will 
be based on standard weight of 490 lbs./ft3 
Chairs, laps and separators will be measures 
for payment. The cost of these will be 
included in the unit rate). 
Sub Total=  9,29,279.62 

3.3 Supplying and Fitting and Fixing of  500.mm R.C.C Pipe at 200 meter Apart along the Alignment  of the Drain 

 
  Page 179 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
Supplying precast RCC pipes(500 mm internal 
dia,50mm thick) with 12mm downgraded 
dust free 1st class brick chips (1:2:4)including 
12 meter long 
pipe joint gap filling in neat cement slurry 
6.096‐LGED  RCC pipeX66  meter  2910.83  23,05,377.36 
casting, curing, laying in position, from 
=792.00 meter 
finished type by steel form works as per 
design , specifications complete as per 
direction of Engineer‐in Charge 

Single brick flat soling with 1st class/ PJ bricks, 
3.00 m X 
true to level, camber, super elevation and 
5.03.01‐ 1.50mX.6 
grade in/c filling the joints with sand (FM  Sqm  251.04  74,558.88 
LGED  =4.5 SqmX66 
0.50) in/c cost of all materials complete as per 
=297.00 Sqm 
direction of the Engineer‐in‐Charge 

Cement concrete (1:2:4) with Portland 
cement, coarse sand    (F.M 1.80), First class/ 
PJ brick chips (25mm to 5mm down‐  3.00mX1.50mX0.
5.03.05‐ graded)in the foundation of guide wall, cost  075m X66 
Cum  6362.15  1,41,716.8 
LGED  of materials and shuttering, mixing by  =0.3375 SqmX66 
concrete mixer machine, casting, laying,  = 22.275.5Cum 
curing for the requisite period, etc. as per 
direction of the Engineer‐in Charge 
Brick work with 1st class bricks with 6mm 
thick cement mortar (1.4) for guide wall of 
R.C.C pipe filling the interstices tightly with  2.00mX2.50mX0.
mortar, raking out joints, cleaning and  50m X 66 
5.02.03‐
soaking bricks at least for 24 hours before  = 2.50 CumX66  Cum  4665.16  7,69,749.75 
LGED 
use, washing of sand, curing for requisite   =165.00 Cubic 
period, cost of all materials, etc. all complete  Meter 
as per direction of the Engineer‐in‐ Charge. 
(Minimum F.M. of sand: 
12 mm thick cement plaster (1:4) in guide 
(2X1.00mX2.00m
wall including cost of materials, washing of 
+ 2X 
sand, curing for requisite period, maintaining 
5.12.01‐ 0.25mX1.00m+ 
proper curvatures of corners, side wall and  Cum  172.0015  56,760.00 
LGED  0.25m X2m)X66 
bottom, costs of all materials, etc. complete, 
=5.00 Cum 
as per direction of the Engineer‐in‐charge. 
= 330.00 Cum 
(Minimum F.M. of sand: 1.2 
Sub Total=  33,48,162.88 
3.4 Construction of RCC Drain on the Slope of the Embankment  
0.7 m X 0.675mX 
Earthwork in excavation of drains etc. by  11m X66 
5.02.01‐ excavating earth to the lines, grades and  =5,197X66 
Cum  78.42  26,898.22 
LGED  elevation as per  drawing, carrying and  =343.02cubic 
disposing of all excavated materials;  meter 
 
Single brick flat soling with 1st class/ PJ bricks, 
true to level, camber, super elevation and  0.70m X 11X.66 
5.03.01‐
grade in/c filling the joints with sand (FM  =7.7 SqmX66  Sqm  251.04  1,27,578.53 
LGED 
0.50) in/c cost of all materials complete as per  =508.20 Sqm 
direction of the Engineer‐in‐Charge 
Reinforced Cement Concrete in drain with 
Portland cement , sand (minimum F.M 1.80) 
st
20mm down well graded crushed 1  class  0.2310 Cubic 
brick/picked brick chips (LAA value not  meter RCC  in per 
exceeding 40) including shuttering, mixing by  running meter of  . 
4.2.04.02. 
concrete mixture machine casting , laying,  drain X 11m X66  Cum      7270.00  12,19,222.62 
LGED 
compacting, curing for 28 days, breaking Ist  = 2.541X66   
class/ picked brick chips  etc complete in all  =167.706 Cubic 
respect as per design drawing, design and  meter 
drawing , and direction of Engineer in Charge” 
and cylinder  crushing strength of concrete 
 
Page 180   September 2013 
Technical Designs for Tranch‐1 Work 
 
should not be less than 170 kg/cm2 
(suggested mix proportion 1:2:4) excluding 
reinforcement and fabrication, but  including 
cost of all materials, reinforcement, and its 
fabrication shuttering, casting curing for 28 
days and all incidental charges ,  

Supplying and Fabrication of M.S High 
strength deformed bar/Twisted bar 
reinforcement of size and length for all types 
of RCC work including straightening the rod, 
removing ruts, cleaning, cutting, hooking, 
bending, binding, with supply of 22 B.W.G. GI 
wire, placing in position, including lapping, 
119.57 kg of MS 
spacing and securing them in position by 
road in per 
concrete blocks (1:1), metal chairs, etc. 
running meter of 
complete including cost of all materials, labor, 
6.051‐LGED  R.C.C drain  kg  67.63  58,70,812.87 
local handling, laboratory test, incidentals 
X11mX66 
necessary to complete the work as per 
 =1315.27kgX66 
specifications, drawings and direction of the 
=86807.82 kg 
Engineer. Laboratory test for physical, 
strength, elongation % & bend to be 
performed as peer ASTM. (Measurement will 
be based on standard weight of 490 lbs. /ft3 
Chairs, laps and separators will be measures 
for payment. The cost of these will be 
included in the unit rate). 
Cement concrete (1:2:4) in Spill way with 
Portland cement, coarse sand    (F.M 1.80), 
First class/ PJ brick chips (25mm to 5mm  1.00mX1.00mX0.
5.03.05‐ down‐ graded), cost of materials and  150m.X 66 
Cum  6362.15  62,985.29 
LGED  shuttering, mixing by concrete mixer  =0.150CumX66 
machine, casting, laying, curing for the  = 9.90 Cum 
requisite period, etc. as per direction of the 
Engineer‐in Charge 
Sub Total=       73,07,497.52 

Total=  29,73,65,474.51 

 
  Page 181 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 

Figure-1: Section and Plan of Drain

Section of 400 mmX550 mm Drain

250mm

300mm  250mm

300mm 400mm 300mm 


550mm 
700mm  700mm 

375mm 375mm 250mm 


75mm 
75mm 

1150mm 

Figure‐2:  400mmX400mmX500mm RCC Drain of the Side Slope of


Plan of 400mmX550mm Drain
Embankment

Section of 450mmX400mmX400mm RCC Drain

125mm 250mm 400mm 250mm 125mm 1000.00mm


150mm  700mm 150mm 

400mm

1150mm
675 mm

 
Page 182   September 2013 
Technical Designs for Tranch‐1 Work 
 
Plan of 700mmX400mmX400mm RCC Drain

700mm

400mm 150mm 

150mm 

700mm
400mm
Quantity of R.C.C and Reinforcement in R.C.C Drain of the Embankment Slope
SL Description Item Measurement Quantity
0.2310 Cum
Reinforce Cement 2X525mX150mm+700mmX700mmX150mm
1 = 8.134 cubic
Concrete(RCC) = 0. 2310Cum; 0.2310 X35.218= 7.87Cubic feet
feet
2.
Amount of Reinforcement
and Fabrication considering 8.134Cubic feet X0.03X490=119.57 kg 119.57 kg
3% of 19.792 Cum of R.C.C

Figure-3: Section and Plan of 750 mmX750mmX750mm


RCC Storm Water Catch Pit

Section of 750 mmX750mmX750mm RCC Storm Water Catch Pit

150mm  1050mm 150mm 

750mm

600.00mm Diameter 
75mm thick R.C.C Pipe 
 
750 mm
975 mm

 
  Page 183 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 

Plan of 1000mmX900mmX900mm RCC Storm Water Catch Pit

1050mm

750mm 150mm 

150mm 

1050 mm
750 mm
 

Quantity of R.C.C and Reinforcement in Each Storm Water Catch PIT 
SL  Description Item  Measurement Quantity
2X750mmX150mm+1050mmX1050mmX150mm  ‐
Reinforce Cement  3.14X(375mm)2X150mm  0.3245 Cum 

Concrete(RCC)  =0.390.75 ‐0.06624= 0.3245 Cum; 0.3245X35.218= 11.427  = 11.427 cubic feet 
Cubic feet  
2. 
Amount of Reinforcement 
and Fabrication considering  11.427  Cubic feet X0.03X490=167.97kg  167.97 kg 
3% of 19.792 Cum of R.C.C 

Figure-4: Pavement Details

SHOULDER CARRIAGEWAY SHOULDER


1.5 5.5 1.5
3% 3%
5% 5%

SURFACING (SEAL COAT (0.12M)+ BITUMINOUS


CARPEIING (0.40M)
BASE 0.200 M
BRICK ON
END EDGING SUB-BASE 0.200 M

IMPROVED SUB-GRADE 0.200 M

 
Page 184   September 2013 
Technical Designs for Tranch‐1 Work 
 

Figure-5: Lay out Plan of R.C. C Pipe, Embankment Slope Drain and Spill Way

600mm Cladding Layer

2000mmX2500mmX500mm 
Guide Wall  2000m

1000mm
700mmX400mmX400mm 
RCC Drain  
12 meter X600mm diameter, X50mm thick R.C. Pipe 

2500mm
1500mm 
700mmX400mmX400mm RCC Drain 
3000mmX1500mm   Embedded in Cladding Layer 
Cement Concrete (C.C) 

3000m

1000mmX1000mmX75mm CC   
Spill way

 
  Page 185 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
Main River Flood Embankment and Erosion Risk Management Program  
Road on the Land‐Side of Rehabilitated or Reconstructed Embankment  
 
BOQ of the Proposed Road cum Flood Embankment cum Road   
                                      (As per Specification & Unit Rate of LGED) 

Main River Flood and Bank Erosion Risk Management Program include construction of two roads r under
tranche-1 as shown in Table-1:

Table‐1:  Roads under  Trenche‐1  
Serial  Start point  End point Length Location 

1  Verakhola  Kaijuri  13.00 KM         Land‐side Bank of Jamuna River 


2  Verakhola  Baghabari  10.00 KM         Land‐side Bank Hurasagar River 

The proposed roads would have 5.5 meter bituminous pavement with 1.5 meter hard shoulder in each 
side.  The  road  would  be  designed  to  function  not  only  as  part  of  flood  embankment  and  shelter  for 
flood  effected  population  but  would  also  provide  connectivity  to  growth  centers,  river  ports,  local 
government institutions situated in the adjoining area of the proposed flood embankments of  Pabna, 
Sirajganj districts. It is obvious that the both roads would be connected to the nearby national highways 
to meet the growing demand of the traffic in future and to facilitate better connectivity of population 
 
 
The roads may be designed as Upazila road of Type design ‐4 of LGED as road classification system of 
LGED approved by The Planning Commission of Bangladesh which define ownership and responsibilities 
of  the  road  system  of  the  country.  According  to  the  classification  LGED  will  be  responsible  for 
construction,  development  and  maintenance  of  three  classes  of  roads,  which  has  been  named  as 
Upazila  Road,  Union  Road  and  Village  Road  in  collaboration  with  Local  Government  Institution  (LGI). 
Road type with definition and the ownership and responsibility are furnished in Table 2. below: 

Table‐2: Road Network Classification with Definition  
 
Serial  Type  Definition  Ownership and 
Number  Responsibility 

1.  National  Highways connecting National capital with Divisional HQs or sea ports or  RHD  


Highway   land ports or Asian Highway  
2.  Regional  Highways connecting District HQs or main river or land ports or with each  RHD  
Highway   other not connected by national Highways.  
3.  Zilla Road   Roads  connecting  District  HQ/s  with  Upazila  HQ/s  or  connecting  one  RHD  
Upazila  HQ  to  another  Upazila  HQ  by  a  single  main  connection  with 
National /Regional Highway, through shortest distance/ route. 
4.  Upazila  Roads  connecting  Upazila  HQ/s  with  Growth  Center/s  or  one  Growth  LGED/LGI**  
Road   Center  with  another  Growth  Center  by  a  single  main  connection  or 
(UZR)   connecting  Growth  Center  to  Higher  Road  System,*  through  shortest 
distance/route. (Former Feeder Road Type‐B)  
5.  Union Road   Roads  connecting  union HQ/s with Upazila  HQs, Growth Centers  or  local  LGED/LGI  
(UNR)   markets or with each other. (Former Rural Road Class‐1 (R1)  
6.  Village Road   a) Roads connecting Villages with Union HQs, local markets, farms and  LGED/LGI 
(VR)   ghats or with each other. (Former Rural Road Class‐2 (R2)  
 
b) Roads within a Village. (Former Rural Road Class‐3 (R3)  

 
Page 186   September 2013 
Technical Designs for Tranch‐1 Work 
 
* Higher Road System‐ National Highway, Regional Highway, and Zila Roads;  
** LGI‐ Local Government Institutions;.  
The  design  standards  relate  the  width  of  the  road  (geometric  design)  and  thickness  of  various  layers 
(pavement)  to  the  classification  of  the  road.  It  has  been  recommended  that  there  should  be  6  basic 
geometric design types for Zilla, Upazila and Union Roads all based on traffic criteria. Design types 5 ‐ 8 
have  been  based  primarily  on  forecasts/  survey  of  commercial  vehicles  (applicable  for  LGED).  Design 
types 3 and 4 are based primarily on forecasts of peak hour passenger car units (pcu’s). The approved 
geometric design for each type of road is summarized in Table 3 

Table 3: Approved Geometric Design Standards 
 
Road Class   Design Type   Carriageway (m)/(ft)   Hard  Shoulder  Verge  Crest  Width 
(m)/(ft)   (m)/(ft)   (m)/(ft)  

Union Road   8   3.0/10  0/0  1.25/4   5.5/18  

7   3.7/12  0/0  0.90/3   5.5/18  


Upazila Road   6   3.7/12   0/0   1.8/6   7.3/24  

5   3.7/12   0.9/3   0.9/3   7.3/24  


4   5.5/18  0/0  2.15/7   9.8/32 
Zila Road   5   3.7/12  0.9/3  0.9/3   7.3/24  

4   5.5/18   0/0   2.15/7   9.8/32  


3   5.5/18   1.2/4   0.95/3   9.8/32  

For Types 8, 7, 6 and 5 the criterion should be daily commercial vehicles. For Types 4 and 3 the criterion 
should be  
peak hour pcu’s. Traffic criteria for each design type are shown in Table 4 below: 

Table: 4 Traffic Criteria for Design Purposes 
Design Type  Daily Commercial Vehicles (CVD) 

8  Up to 50 
7  51‐100
6  101‐200 
5  201‐300 
4  301‐600 

 
It been mentioned in Road Design Standards,  Standard Designs and Costing for Zilla, Upazila and Union 
Roads, Bridges and Culverts of LGED  that Design type‐4 of Upazila roads of LGED  is suitable traffic of 
4300 ‐ 600 commercial vehicle per day or traffic of 290‐530 pcu.. The widened (18ft) carriageway allows 
a  better  distribution  on  the  pavement  for  this  high  level  of  traffic,  increasing  the  design  life  of  the 
pavement. 
 

 
  Page 187 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
Table-5: Pavement of Different Layers of Type Design-4 of Upazila Road of LGED 

The feasibility level design of the pavement and geometric elements of the road have been proposed as 
per standards and specifications of Upazila Road of LGED‐Type‐4. The cross‐section of pavement of the 
proposed road showing the thickness of different layer of pavement components is given in figure‐1. 
U‐shaped  surface  drain  of  350.00mm  wide  along  with  storm  water  catch  pit  of  900.00 
X900.00mmX1000.00  at  200.00mm  apart  have  proposed  to  drain  off  storm/rain  water  from  road 
surface.  In  addition,  500.00.mm  diameter  RCC  pipe  has  been  proposed  to  provide  cross‐  wise 
underneath the pavement for each catch pit to drain off the water to the outer side of the road crest. 
The cross‐section of the road side drain, storm water catch pit, Cross drain, have been shown in Figure‐
2, Figure‐3, Figure‐4 and Figure‐5. 
 
Bill of Quantities for the Construction of Proposed Roads 
The  standards  and  speculations  and  the  rate  schedule  of  regional  roads  of  RHD  have  been  primarily 
used  in  preparation  of  Bill  of  Quantities  (BOQ)  items  of  pavement  works.  In  case  of  R.C.C  and  Brick 
works, standards and speculations of and schedule of rates of LGED have been used. The BOQ cost of 
Verakhola  ‐  Kaijuri  road  and  Verakhola  –  Baghabari  road  are  TK.  28,  33,  75,736.50  and  TK.  21,  60, 
72,756.90 respectively. BOQ cost of two roads is TK. 49, 94, 48,493.40. The BOQ of Verakhola ‐ Kaijuri 
road and Verakhola – Baghabari road are annexed as Annexure‐A and Annexure‐B 
 
Verakhola‐
Verakhola‐Kaijuri 
Baghabari Road           Total 
SL   Description of Items  Road (in Taka) 
(in Taka)          (3+ ‐4) 
 
 

1  2  3  4  5 

1  Construction of Pavement  20,97,92,522.00  15, 89,05,900.00  36,86,98,422.00 

2  Protection of the Slope of the Embankment    2,46,48,000.00  1,89,60,000.00  4,36,08,000.00 

3  Surface Drain and Cross Drain 
3.1  Construction of 400 mmX550mm Surface Drain  3,73,50,274.49  2,87,30,908.38  6,60,81,182.87 

Construction of 750mmX750mm X 750mm Storm 
3.2  9,29,279.62  7,18,079.72  16,47,359.33 
Water Catch Pit at 200.00 Meter Apart 
3.3  Supplying and Fitting and Fixing of  500.mm R.C.C  33,48,162.88 31,11,166.17  64,59,329.05

 
Page 188   September 2013 
Technical Designs for Tranch‐1 Work 
 
Pipe at 200 meter Apart along the Alignment  of 
the Drain 
Construction of RCC Drain on the Slope of the 
3.4        73,07,497.52        56,46,702.63  1,29,54,200.15 
Embankment 

Total Cost of Two Roads  28,33,75,736.50  21,60,72,756.90  49,94,48,493.40 

Based on Specification and Rate Schedule of LGED 
Verakhola‐
Verakhola‐Kaijuri           Total 
SL   Description of Items  Baghabari Road (in 
Road (in Taka)          (3+ ‐4) 
Taka) 
1  2  3  4  5 

1  Construction of Pavement  20,97,92,522.00  15, 89,05,900.00  36,86,98,422.00 

2  Protection of the Slope of the Embankment    2,46,48,000.00  1,89,60,000.00  4,36,08,000.00 

3  Surface Drain and Cross Drain 

3.1  Construction of 400 mmX550mm Surface Drain  3,73,50,274.49  2,87,30,908.38  6,60,81,182.87 

Construction of 750mmX750mm X 750mm Storm 
3.2  9,29,279.62  7,18,079.72  16,47,359.33 
Water Catch Pit at 200.00 Meter Apart 
Supplying and Fitting and Fixing of  500.mm R.C.C 
3.3  Pipe at 200 meter Apart along the Alignment  of  33,48,162.88  31,11,166.17  64,59,329.05 
the Drain 
Construction of RCC Drain on the Slope of the 
3.4        73,07,497.52        56,46,702.63  1,29,54,200.15 
Embankment 

Total Cost of Two Roads  28,33,75,736.50  21,60,72,756.90  49,94,48,493.40 

Based on Specification and Rate Schedule of RHD 
Verakhola‐
Verakhola‐Kaijuri 
Baghabari Road (in           Total 
SL   Description of Items  Road (in Taka) 
Taka)          (3+ ‐4) 
 
 
1  2  3  4  5 

1  Construction of Pavement  22,37,82,260.00  17,21,40,200.00  39,59,22,460.00 

2  Protection of the Slope of the Embankment    2,46,48,000.00  1,89,60,000.00  4,36,08,000.00 

3  Surface Drain and Cross Drain 
3.
Construction of 400 mmX550mm Surface Drain  3,73,50,274.49  2,87,30,908.38  6,60,81,254.87 

3. Construction of 750mmX750mm X 750mm Storm 
9,29,279.62  7,18,079.72  16,47,359.33 
2  Water Catch Pit at 200.00 Meter Apart 
Supplying and Fitting and Fixing of  500.mm R.C.C 
3.
Pipe at 200 meter Apart along the Alignment  of  33,48,162.88  31,11,166.17  64,59,329.05 

the Drain 
3. Construction of RCC Drain on the Slope of the 
      73,07,497.52        56,46,702.63  1,29,54,200.15 
4  Embankment 

Total Cost of Two Roads  29,73,65,474.51  22,93,07,128.89  52,66,72,603.40 

 
  Page 189 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
Verakhola‐Baghabari Road 
Length: 10 Kilometer 
                                                     Bill of Quantities                           
  Annexure‐B 
Rate 
Amount 
Item Code No  Item Description  Measurement Quantity  Unit   (in 
(in Taka) 
Taka) 
Construction of Pavement 
3.1.08  of Schedule of Rate,  Preparation of Sub‐
10000.00m x 5.50m  
Pabna and, Serajganj districts  grade (450mm  Sqm  74.08  40,74,400.00 
=55,000.00 Sqm           
of LGED, July’2012  depth) 
3.1.086 of Schedule of Rate,  10000.00m x 5.50m 
Improved Sub‐
Pabna and, Serajganj districts  x0.200m   Cum  558.98  88,44,000.00 
Grade    
of LGED, July’2012  =11,000 .00 Cum           
3.2.02.01 of Schedule of Rate,  10000.00m x 5.50m 
Sub ‐ base       
Pabna and, Serajganj districts  x0.200m  Cum  2887.84  3,17,66,240.00 
 
of LGED, July’2012   =11,000.00Cum           
3.2.03.02  of Schedule of Rate,  10000.00m x 5.50m 
Aggregate base  
Pabna and, Serajganj districts  x0.200m   Cum  4717.36  5,18,90,960.00 
 
of LGED, July’2012  = 11,000.00 Cum           
3.2.25.01  of Schedule of Rate, 
Bituminous Prime  10000.00m x 5.50m 
Pabna and, Serajganj districts  Sqm  112.04  61,62,200.00 
coat (Hand place)   =55,000.00 Sqm           
of LGED, July’2012 
Bituminous Tack 
3.2.24.05  of Schedule of Rate, 
coat   10000.00m x 5.50m 
Pabna and, Serajganj districts  Sqm  52.45  28,84,750.00 
(Labor intensive   =55,000.00 Sqm           
of LGED, July’2012 
work) 
Premixed 
3.2.30.2 of Schedule of Rate, 
Bituminous  10000.00m x 5.50m  
Pabna and, Serajganj districts  Sqm  702.10  3,86,15,500.00 
Carpeting  40mm  =55,000.00 Sqm           
of LGED, July’2012 
thick (Av.) 
3.1.08  of Schedule of Rate,  2mm compacted‐ 
10000.00m x 5.50m 
Pabna and, Serajganj districts  premix Bituminous  Sqm  228.91  1,25,90,050.00 
 =55,000.00 Sqm           
of LGED, July’2012  Seal Coat.  
3.2.15.01  of Schedule of Rate, 
 2 x 10000.00m   Lin. 
Pabna and, Serajganj districts  Brick on end edging    73.89  14,77,800.00 
=20,000.00 Lin. M    M 
of LGED, July’2012 
15,89,05,900.0
Sub Total= 

2.Protection  Work of the Slope of the Embankment 
*  600mm thick blanket of earth cladding with  
10,000.00mX12.00 m 
specified cohesive soil on the side slope of  Sqm  110.00  1,32,00,000.00 
=1,20,000.00 Sqm 
embankment   
**  Supplying and planting vertiver (Binna) grass in 
10,000.00mX12.00 m 
bunch of 2 to 3 stem @ of 225 mm all over the  Sqm  48.00    57,60,000.00 
=1,20,000.00 Sqm 
side slope 
                                                                                                                                                        Sub Total=  1,89,60,000.00 

3.Surface Drain and Cross Drain 
3.1 Construction of 400 mmX550mm Surface Drain 
1.15 X 0.7X 10,000.00 
Earthwork in excavation of drains etc. by 
= 0.8050X10,000 
5.02.01 excavating earth to the lines, grades and 
= 8,050.00 cubic  Cum  78.42  6,31,281.00 
‐LGED  elevation as per  drawing, carrying and disposing 
meter 
of all excavated materials; 
 
Single brick flat soling with 1st class/ PJ bricks, 
true to level, camber, super elevation and grade 
5.03.01 1.15mX 10,000.00    
in/c filling the joints with sand (FM 0.50) in/c cost  Sqm  251.04  28,86,960.00 
‐LGED  =11,500.00 Sqm 
of all materials complete as per direction of the 
Engineer‐in‐Charge 

 
Page 190   September 2013 
Technical Designs for Tranch‐1 Work 
 
Brick work with 1st class bricks with 6mm thick 
cement mortar (1.4) for guard wall of drain, foot  (2X0.375mX0.25mX1.
path and median, filling the interstices tightly  m+2X 
with mortar, raking out joints, cleaning and  0.30mmX0.250mX 
5.02.03
soaking bricks at least for 24 hours before use,  1m )X 10,000.00  Cum  4665.16  1,92,43,785.50 
‐LGED 
washing of sand, curing for requisite period, cost  =0.4125X10,000.00 
of all materials, etc. all complete as per direction   =4,125.00 Cubic 
of the Engineer‐in‐ Charge. (Minimum F.M. of  Meter 
sand: 
Cement concrete (1:2:4) with Portland cement, 
coarse sand    (F.M 1.80), First class/ PJ brick chips 
1.15mX075mX 
(25mm to 5mm down‐ graded), cost of materials 
5.03.05 10,000.00 
and shuttering, mixing by concrete mixer  Cum  6362.15  54,87,354.38 
‐LGED  =0.08625X10,000.00 
machine, casting, laying, curing for the requisite 
= 862.50 Cum 
period, etc. as per direction of the Engineer‐in 
Charge 
12 mm thick cement plaster (1:4) in drain 
(0.300m+0.250m+0.5
including cost of materials, washing of sand, 
50m+0.600m+0.250
curing for requisite period, maintaining proper 
5.12.01 m+0.850m)X10,000.0
curvatures of corners, side wall and bottom, costs  Sqm  172.00  4,81,600.00 
‐LGED  0 
of all materials, etc. complete, as per direction of 
=0.280m  X 10,000.00  
the Engineer‐in‐charge. (Minimum F.M. of sand: 
= 2,800.00Sqm 
1.2 
  
Sub Total= 
2,87,30,908.38 
3.2 Construction of 750mmX750mm X 750mm Storm Water Catch Pit at 200.00 Meter Apart 
1.050m X 1.050mX 
Earthwork in excavation of drains etc. by 
0.975m X 51 
5.02.01 excavating earth to the lines, grades and 
=1.0749X51  Cum  78.42  4,299.13 
‐LGED  elevation as per  drawing, carrying and disposing 
=54.82 Cubic meter 
of all excavated materials; 
 
Single brick flat soling with 1st class/ PJ bricks, 
1.050m X 1.050mX  
true to level, camber, super elevation and grade 
5.03.01 51 
in/c filling the joints with sand (FM 0.50) in/c cost  Sqm  251.04  14,115.35 
‐LGED  =1.1025 SqmX51 
of all materials complete as per direction of the 
=56.227 Sqm 
Engineer‐in‐Charge 
Reinforced Cement Concrete in drain work 
Portland cement , sand (minimum F.M 1.80) 
20mm down well graded crushed 1st class 
brick/picked brick chips (LAA value not exceeding 
40) including shuttering, mixing by concrete 
mixture machine casting , laying, compacting, 
curing for 28 days, breaking Ist class/ picked brick  0.325 Cubic meter 
4.1.10.
chips  etc complete in all respect as per design  RCC in each catch pit 
02.2  Cum  7,270.00  1,20,314.87 
drawing, design and drawing , and direction of  X 51 
LGED 
Engineer in Charge” and cylinder  crushing  = 16.55 Cubic meter 
strength of concrete should not be less than 170 
kg/cm2 (suggested mix proportion 1:2:4) 
excluding reinforcement and fabrication, but  
including cost of all materials, reinforcement, and 
its fabrication shuttering, casting curing for 28 
days and all incidental charges ,  

 
  Page 191 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
6.051‐ Supplying and Fabrication of M.S high strength 
LGED  deformed bar/Twisted bar reinforcement of size 
and length for all types of RCC work including 
straightening the rod, removing ruts, cleaning, 
cutting, hooking, bending, binding, with supply of 
22 B.W.G. GI wire, placing in position, including 
lapping, spacing and securing them in position by 
concrete blocks (1:1), metal chairs, etc. complete 
167.97kg of MS road 
including cost of all materials, labor, local 
in each catch pit X51  kg  67.63  5,79,,350.37 
handling, laboratory test, incidentals necessary to 
 =8,566.47 kg 
complete the work as per specifications, drawings 
and direction of the Engineer. Laboratory test for 
physical, strength, elongation % & bend to be 
performed as peer ASTM. (Measurement will be 
based on standard weight of 490 lbs./ft3 Chairs, 
laps and separators will be measures for 
payment. The cost of these will be included in the 
unit rate). 
Sub Total=  7,18,079.72 
3.3 Supplying and Fitting and Fixing of  500.mm R.C.C Pipe at 200 meter Apart along the Alignment  of the Drain 
Supplying precast RCC pipes(500 mm internal 
dia,50mm thick) with 12mm downgraded dust 
free 1st class brick chips (1:2:4)including pipe  12 meter long RCC 
6.096‐ mete
joint gap filling in neat cement slurry casting,  pipeX51 =792.00  2910.83  23,05,377.36 
LGED  r 
curing, laying in position, from finished type by  meter 
steel form works as per design , specifications 
complete as per direction of Engineer‐in Charge 

Single brick flat soling with 1st class/ PJ bricks, 
true to level, camber, super elevation and grade  3.00 m X 1.50mX.6 
5.03.01
in/c filling the joints with sand (FM 0.50) in/c cost  =4.5 SqmX51  Sqm  251.04  57,613.68 
‐LGED 
of all materials complete as per direction of the  =229.50 Sqm 
Engineer‐in‐Charge 

Cement concrete (1:2:4) with Portland cement, 
coarse sand    (F.M 1.80), First class/ PJ brick chips 
3.00mX1.50mX0.075
(25mm to 5mm down‐ graded)in the foundation 
5.03.05 m X51 
of guide wall, cost of materials and shuttering,  Cum  6362.15  1,09,,508.58 
‐LGED  =0.3375 SqmX51 
mixing by concrete mixer machine, casting, 
= 17.212Cum 
laying, curing for the requisite period, etc. as per 
direction of the Engineer‐in Charge 
Brick work with 1st class bricks with 6mm thick 
cement mortar (1.4) for guide wall of R.C.C pipe 
filling the interstices tightly with mortar, raking  2.00mX2.50mX0.50m 
5.02.03 out joints, cleaning and soaking bricks at least for  X 51 
Cum  4665.16  5,94,806.63 
‐LGED  24 hours before use, washing of sand, curing for  = 2.50 CumX51 
requisite period, cost of all materials, etc. all   =127.50 Cubic Meter 
complete as per direction of the Engineer‐in‐ 
Charge. (Minimum F.M. of sand: 
12 mm thick cement plaster (1:4) in guide wall 
including cost of materials, washing of sand,  (2X1.00mX2.00m+ 2X 
curing for requisite period, maintaining proper  0.25mX1.00m+ 
5.12.01 172.001
curvatures of corners, side wall and bottom, costs  0.25m X2m)X51  Cum  43,860.00 
‐LGED  5 
of all materials, etc. complete, as per direction of  =5.00 CumX51 
the Engineer‐in‐charge. (Minimum F.M. of sand:  = 255.00 Cum 
1.2 
Sub Total=  31,11,166.17 
3.4 Construction of RCC Drain on the Slope of the Embankment  
0.7 m X 0.675mX 11m 
Earthwork in excavation of drains etc. by 
X51 
5.02.01 excavating earth to the lines, grades and 
=5,197X51  Cum  78.42  20,784.99 
‐LGED  elevation as per  drawing, carrying and disposing 
=265.07cubic meter 
of all excavated materials; 
 
 
Page 192   September 2013 
Technical Designs for Tranch‐1 Work 
 
Single brick flat soling with 1st class/ PJ bricks, 
true to level, camber, super elevation and grade  0.70m X 11X.51 
5.03.01
in/c filling the joints with sand (FM 0.50) in/c cost  =7.7 SqmX51  Sqm  251.04  98,583.41 
‐LGED 
of all materials complete as per direction of the  =392.70 Sqm 
Engineer‐in‐Charge 
Reinforced Cement Concrete in drain with 
Portland cement , sand (minimum F.M 1.80) 
st
20mm down well graded crushed 1  class 
brick/picked brick chips (LAA value not exceeding 
40) including shuttering, mixing by concrete 
0.2310 Cubic meter 
mixture machine casting , laying, compacting, 
RCC  in per running 
curing for 28 days, breaking Ist class/ picked brick  . 
4.2.04. meter of drain X 11m 
chips  etc complete in all respect as per design      
02.  X51  Cum  9,42,126.57 
drawing, design and drawing , and direction of  7270.00 
LGED  = 2.541X51 
Engineer in Charge” and cylinder  crushing   
=129.591 Cubic 
strength of concrete should not be less than 170 
meter 
kg/cm2 (suggested mix proportion 1:2:4) 
excluding reinforcement and fabrication, but  
including cost of all materials, reinforcement, and 
its fabrication shuttering, casting curing for 28 
days and all incidental charges ,  
Supplying and Fabrication of M.S High strength 
deformed bar/Twisted bar reinforcement of size 
and length for all types of RCC work including 
straightening the rod, removing ruts, cleaning, 
cutting, hooking, bending, binding, with supply of 
22 B.W.G. GI wire, placing in position, including 
lapping, spacing and securing them in position by  119.57 kg of MS road 
concrete blocks (1:1), metal chairs, etc. complete  in per running meter 
6.051‐ including cost of all materials, labor, local  of R.C.C drain 
kg  67.63  45,36,537.22 
LGED  handling, laboratory test, incidentals necessary to  X11mX51 
complete the work as per specifications, drawings   =1315.27kgX51 
and direction of the Engineer. Laboratory test for  =67078..77 kg 
physical, strength, elongation % & bend to be 
performed as peer ASTM. (Measurement will be 
based on standard weight of 490 lbs. /ft3 Chairs, 
laps and separators will be measures for 
payment. The cost of these will be included in the 
unit rate). 
Cement concrete (1:2:4) in Spill way with 
Portland cement, coarse sand    (F.M 1.80), First 
1.00mX1.00mX0.150
class/ PJ brick chips (25mm to 5mm down‐ 
5.03.05 m.X 51 
graded), cost of materials and shuttering, mixing  Cum  6362.15  48,670,.45 
‐LGED  =0.150CumX51 
by concrete mixer machine, casting, laying, curing 
= 7.65 Cum 
for the requisite period, etc. as per direction of 
the Engineer‐in Charge 
      
Sub Total= 
56,46,702.63 
Total=  21,60,72,756.80
 
Verakhola‐Kaijuri Road 
Length: 13 Kilometer 
                                             Bill of Quantities  Annexure‐A 
Rate 
Amount 
Item Code No  Item Description  Measurement Quantity  Unit   (in 
(in Taka) 
Taka) 
Construction of Pavement 

3.1.08  of Schedule of Rate,  Preparation of Sub‐
13,000.00m x 5.50m  
Pabna and, Serajganj  grade (300mm  Sqm  74.08     52,96,420.00 
=71,500.00 Sqm           
districts of LGED, July’2012  depth) 

 
  Page 193 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
3.1.086 of Schedule of Rate,  13,000.00m x 5.50m 
Pabna and, Serajganj  Improved Sub‐Grade    x0.200m   Cum  558.98  1,14,97,200.00 
districts of LGED, July’2012  =14,300 .00 Cum           

3.2.02.01 of Schedule of  13,000.00m x 5.50m 
Sub ‐ base       
Rate, Pabna and, Serajganj  x0.200m  Cum  2887.84  4,,12,90,964.00 
 
districts of LGED, July’2012   =14,300.00Cum           

3.2.03.02  of Schedule of  13,000.00m x 5.50m 
Aggregate base  
Rate, Pabna and, Serajganj  x0.200m   Cum  4717.36  6,74,58,248.00 
 
districts of LGED, July’2012  = 14,300.00 Cum           
3.2.25.01  of Schedule of 
Bituminous Prime  13,000.00m x 5.50m 
Rate, Pabna and, Serajganj  Sqm  112.04   80,10,860.00 
coat (Hand place)   =71,500.00 Sqm           
districts of LGED, July’2012 

3.2.24.05  of Schedule of  Bituminous Tack coat 
13,000.00m x 5.50m 
Rate, Pabna and, Serajganj  (Labor intensive  Sqm  52.45   37,50,175.00 
 =71,500.00 Sqm           
districts of LGED, July’2012  work) 

3.2.30.2 of Schedule of Rate,  Premixed Bituminous 
13,000.00m x 5.50m  
Pabna and, Serajganj  Carpeting  40mm  Sqm  702.10   5,02,00,150.00 
=71,000.00 Sqm           
districts of LGED, July’2012  thick (Av.) 
3.1.08  of Schedule of Rate,  12mm compacted‐ 
13,000.00m x 5.50m    
Pabna and, Serajganj  premix Bituminous  Sqm  228.91 
 =71,500.00 Sqm            1,63,67,065.00 
districts of LGED, July’2012  Seal Coat.  
3.2.15.01  of Schedule of 
 2 x13,000.00m   Lin. 
Rate, Pabna and, Serajganj  Brick on end edging     73.89      19,21,140.00 
=26,000.00 Lin. M    M 
districts of LGED, July’2012 
20,97,92,522.0
Sub Total= 

 
*  600mm thick blanket of earth cladding with  
13,000.00mX12.00 m 
specified cohesive soil on the side slope of  Sqm  110.00  1,71,60,000.00 
=1,56,000.00 Sqm 
embankment   
**  Supplying and planting vertiver (Binna) grass in 
13,000.00mX12.00 m 
bunch of 2 to 3 stem @ of 225 mm all over the  Sqm  48.00    74,88,000.00 
=1,56,000.00 Sqm 
side slope 
    2,46,48,000.00 

3.Surface Drain and Cross Drain 
3.1 Construction of 400 mmX550mm Surface Drain 

Earthwork in excavation of drains etc. by  1.15 X 0.7X 13000.00  
5.02.01 excavating earth to the lines, grades and  = 10,465.00 cubic 
Cum  78.42  8,20,,665.30 
‐LGED  elevation as per  drawing, carrying and disposing  meter 
of all excavated materials;   
Single brick flat soling with 1st class/ PJ bricks, 
true to level, camber, super elevation and grade 
5.03.01 1.15X 13,000.00    
in/c filling the joints with sand (FM 0.50) in/c cost  Sqm  251.04  37,53,048.00 
‐LGED  =14,9500.00Sqm 
of all materials complete as per direction of the 
Engineer‐in‐Charge 
Brick work with 1st class bricks with 6mm thick 
cement mortar (1.4) for guard wall of drain, foot  (2X0.375mX0.25mX1.
path and median, filling the interstices tightly  m+2X 
with mortar, raking out joints, cleaning and  0.30mmX0.250mX 
5.02.03
soaking bricks at least for 24 hours before use,  1m )X 13,000.00  Cum  4665.16  2,50,16,920.50 
‐LGED 
washing of sand, curing for requisite period, cost  =0.412513,000.00 
of all materials, etc. all complete as per direction   =5,362.50 Cubic 
of the Engineer‐in‐ Charge. (Minimum F.M. of  Meter 
sand: 

 
Page 194   September 2013 
Technical Designs for Tranch‐1 Work 
 
Cement concrete (1:2:4) with Portland cement, 
coarse sand    (F.M 1.80), First class/ PJ brick chips 
1.15X0.075X 
(25mm to 5mm down‐ graded), cost of materials 
5.03.05 13,000.00 
and shuttering, mixing by concrete mixer  Cum  6362.15  71,33,560.69 
‐LGED  =0.08625X13000.00 
machine, casting, laying, curing for the requisite 
= 1121.25 Cum 
period, etc. as per direction of the Engineer‐in 
Charge 
12 mm thick cement plaster (1:4) in drain 
(0.300m+0.250m+0.5
including cost of materials, washing of sand, 
50m+0.600m+0.250
curing for requisite period, maintaining proper 
5.12.01 m+0.850m)X13,000.0
curvatures of corners, side wall and bottom, costs  Sqm  172.00  6,26,080.00 
‐LGED  0 
of all materials, etc. complete, as per direction of 
=0.280m  X 13,000.00  
the Engineer‐in‐charge. (Minimum F.M. of sand: 
= 3,640.00Sqm 
1.2 
  
Sub Total= 
3,73,50,274.49 
3.2 Construction of 750mmX750mm X 750mm Storm Water Catch Pit at 200.00 Meter Apart 
1.050m X 1.050mX 
Earthwork in excavation of drains etc. by 
0.975m X 66 
5.02.01 excavating earth to the lines, grades and 
=1.0749X66  Cum  78.42  5,563.58 
‐LGED  elevation as per  drawing, carrying and disposing 
=70.946 Cubic meter 
of all excavated materials; 
 
Single brick flat soling with 1st class/ PJ bricks, 
1.050m X 1.050mX  
true to level, camber, super elevation and grade 
5.03.01 66 
in/c filling the joints with sand (FM 0.50) in/c cost  Sqm  251.04  18,266.93 
‐LGED  =1.1025 SqmX66 
of all materials complete as per direction of the 
=72.765 Sqm 
Engineer‐in‐Charge 
Reinforced Cement Concrete in drain work 
Portland cement , sand (minimum F.M 1.80) 
20mm down well graded crushed 1st class 
brick/picked brick chips (LAA value not exceeding 
40) including shuttering, mixing by concrete 
mixture machine casting , laying, compacting, 
curing for 28 days, breaking Ist class/ picked brick  0.325 Cubic meter 
4.1.10.0
chips  etc complete in all respect as per design  RCC in each catch pit 
2.2  Cum  7270.00  1,55,701.59 
drawing, design and drawing , and direction of  X 66 
LGED 
Engineer in Charge” and cylinder  crushing  = 21.42 Cubic meter 
strength of concrete should not be less than 170 
kg/cm2 (suggested mix proportion 1:2:4) 
excluding reinforcement and fabrication, but  
including cost of all materials, reinforcement, and 
its fabrication shuttering, casting curing for 28 
days and all incidental charges ,  
6.051‐ Supplying and Fabrication of M.S high strength 
LGED  deformed bar/Twisted bar reinforcement of size 
and length for all types of RCC work including 
straightening the rod, removing ruts, cleaning, 
cutting, hooking, bending, binding, with supply of 
22 B.W.G. GI wire, placing in position, including 
lapping, spacing and securing them in position by 
concrete blocks (1:1), metal chairs, etc. complete 
167.97kg of MS road 
including cost of all materials, labor, local 
in each catch pit X66  kg  67.63  7,49,,747.53 
handling, laboratory test, incidentals necessary to 
 =11,086.02 kg 
complete the work as per specifications, drawings 
and direction of the Engineer. Laboratory test for 
physical, strength, elongation % & bend to be 
performed as peer ASTM. (Measurement will be 
based on standard weight of 490 lbs./ft3 Chairs, 
laps and separators will be measures for 
payment. The cost of these will be included in the 
unit rate). 
Sub Total=  9,29,279.62 
3.3 Supplying and Fitting and Fixing of  500.mm R.C.C Pipe at 200 meter Apart along the Alignment  of the Drain 

 
  Page 195 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
Supplying precast RCC pipes(500 mm internal 
dia,50mm thick) with 12mm downgraded dust 
free 1st class brick chips (1:2:4)including pipe  12 meter long RCC 
6.096‐ mete 2910.8
joint gap filling in neat cement slurry casting,  pipeX66 =792.00  23,05,377.36 
LGED  r  3 
curing, laying in position, from finished type by  meter 
steel form works as per design , specifications 
complete as per direction of Engineer‐in Charge 

Single brick flat soling with 1st class/ PJ bricks, 
true to level, camber, super elevation and grade  3.00 m X 1.50mX.6 
5.03.01
in/c filling the joints with sand (FM 0.50) in/c cost  =4.5 SqmX66  Sqm  251.04  74,558.88 
‐LGED 
of all materials complete as per direction of the  =297.00 Sqm 
Engineer‐in‐Charge 

Cement concrete (1:2:4) with Portland cement, 
coarse sand    (F.M 1.80), First class/ PJ brick chips 
3.00mX1.50mX0.075
(25mm to 5mm down‐ graded)in the foundation 
5.03.05 m X66  6362.1
of guide wall, cost of materials and shuttering,  Cum  1,41,716.8 
‐LGED  =0.3375 SqmX66  5 
mixing by concrete mixer machine, casting, 
= 22.275.5Cum 
laying, curing for the requisite period, etc. as per 
direction of the Engineer‐in Charge 
Brick work with 1st class bricks with 6mm thick 
cement mortar (1.4) for guide wall of R.C.C pipe 
filling the interstices tightly with mortar, raking  2.00mX2.50mX0.50m 
5.02.03 out joints, cleaning and soaking bricks at least for  X 66  4665.1
Cum  7,69,749.75 
‐LGED  24 hours before use, washing of sand, curing for  = 2.50 CumX66  6 
requisite period, cost of all materials, etc. all   =165.00 Cubic Meter 
complete as per direction of the Engineer‐in‐ 
Charge. (Minimum F.M. of sand: 
12 mm thick cement plaster (1:4) in guide wall 
including cost of materials, washing of sand,  (2X1.00mX2.00m+ 2X 
curing for requisite period, maintaining proper  0.25mX1.00m+ 
5.12.01 172.00
curvatures of corners, side wall and bottom, costs  0.25m X2m)X66  Cum  56,760.00 
‐LGED  15 
of all materials, etc. complete, as per direction of  =5.00 Cum 
the Engineer‐in‐charge. (Minimum F.M. of sand:  = 330.00 Cum 
1.2 
Sub Total=  33,48,162.88 
3.4 Construction of RCC Drain on the Slope of the Embankment  
0.7 m X 0.675mX 11m 
Earthwork in excavation of drains etc. by 
X66 
5.02.01 excavating earth to the lines, grades and 
=5,197X66  Cum  78.42  26,898.22 
‐LGED  elevation as per  drawing, carrying and disposing 
=343.02cubic meter 
of all excavated materials; 
 
Single brick flat soling with 1st class/ PJ bricks, 
true to level, camber, super elevation and grade  0.70m X 11X.66 
5.03.01
in/c filling the joints with sand (FM 0.50) in/c cost  =7.7 SqmX66  Sqm  251.04  1,27,578.53 
‐LGED 
of all materials complete as per direction of the  =508.20 Sqm 
Engineer‐in‐Charge 
Reinforced Cement Concrete in drain with 
Portland cement , sand (minimum F.M 1.80) 
st
20mm down well graded crushed 1  class 
brick/picked brick chips (LAA value not exceeding 
40) including shuttering, mixing by concrete 
0.2310 Cubic meter 
mixture machine casting , laying, compacting, 
RCC  in per running 
curing for 28 days, breaking Ist class/ picked brick  . 
meter of drain X 11m 
4.2.04.0 chips  etc complete in all respect as per design      
X66  Cum  12,19,222.62 
2. LGED  drawing, design and drawing , and direction of  7270.00 
= 2.541X66 
Engineer in Charge” and cylinder  crushing   
=167.706 Cubic 
strength of concrete should not be less than 170 
meter 
kg/cm2 (suggested mix proportion 1:2:4) 
excluding reinforcement and fabrication, but  
including cost of all materials, reinforcement, and 
its fabrication shuttering, casting curing for 28 
days and all incidental charges ,  
 
Page 196   September 2013 
Technical Designs for Tranch‐1 Work 
 
Supplying and Fabrication of M.S High strength 
deformed bar/Twisted bar reinforcement of size 
and length for all types of RCC work including 
straightening the rod, removing ruts, cleaning, 
cutting, hooking, bending, binding, with supply of 
22 B.W.G. GI wire, placing in position, including 
lapping, spacing and securing them in position by  119.57 kg of MS road 
concrete blocks (1:1), metal chairs, etc. complete  in per running meter 
6.051‐ including cost of all materials, labor, local  of R.C.C drain 
kg  67.63  58,70,812.87 
LGED  handling, laboratory test, incidentals necessary to  X11mX66 
complete the work as per specifications, drawings   =1315.27kgX66 
and direction of the Engineer. Laboratory test for  =86807.82 kg 
physical, strength, elongation % & bend to be 
performed as peer ASTM. (Measurement will be 
based on standard weight of 490 lbs. /ft3 Chairs, 
laps and separators will be measures for 
payment. The cost of these will be included in the 
unit rate). 
Cement concrete (1:2:4) in Spill way with 
Portland cement, coarse sand    (F.M 1.80), First 
1.00mX1.00mX0.150
class/ PJ brick chips (25mm to 5mm down‐ 
5.03.05 m.X 66 
graded), cost of materials and shuttering, mixing  Cum  6362.15  62,985.29 
‐LGED  =0.150CumX66 
by concrete mixer machine, casting, laying, curing 
= 9.90 Cum 
for the requisite period, etc. as per direction of 
the Engineer‐in Charge 
      
Sub Total= 
73,07,497.52 
28,33,75,736.5
Total= 

 
 
 
 

 
  Page 197 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
Appendix VI:  Comment Matrix 
Comments from BWDB and Observance 
Summary
• JMREMP Manual should be followed for design of Protective Work.
• Data & Information of Design Manual of FAP21/22 was not authenticated by its author. So, Designer should be 
careful in using Data & Information of this manual. 
• Actual & current Data should be used for design instead of assumed & old data. 
• All Calculation sheet including Hydrological & Metrological analysis should be enclosed with Design Report. 
• Design Criteria should be selected carefully. 
• The River Section at Chouhali, Zafargonj & Harirampur used in this Design Report does not represent the actual 
River Section. Actual Section should be used for design of Protective Work. 
• River Sections are not drawn correctly from data printed in Technical Drawing. River Section should be drawn 
correctly as per field survey data. 
• Before implementation of Harirampur Protective Work, the adjoining area should carefully be studied. It should 
be  checked,  whether  there  are  any  conflicts  between  Harirampur  Protective  Work  &  Regulator  (proposed)  at 
Kaishakhali Closure point. 
• Drainage Discharge of Regulators of Hurasagar FCD Project should be determined carefully. Because there are 
no proposal of embankment was found on the northern & western side in this report. 
•  All  Design  Report  &  computation  sheet  should  be  clear  &  self‐explanatory  with  reference  (where  required). 
These Reports should be preserved in Design Library for ready reference. 
•  "Annex  B  Data  &  Survey",  "Annex  D  :  Hydrology  &  Flood  Modeling"  and  "Annex  E  River  Hydraulics  & 
Morphology" should be send to this office 
Article or item wise comments are given below
1. Annex F2 Chapter 4 : River Bank Protection Work(Page 21‐30)
In this report, in most cases Design Data are collected from FAP21/22 Manual & some other sources which are 
not  updated  with  up‐to‐date  Hydrological  &  Metrological  Data.  Design  calculation  should  be  done  considering 
up‐to‐date  Hydrological  &  Metrological  Data  and  respective  design  calculation  should  incorporate  in  Design 
Report 
 
COMMENT  REPLY 
•  HFL,  LWL  &  Discharge  (  Art  4.5  &  4.6,  Page  23‐25): Current HFL, LWL and Discharge were analysed. The 
In this report, all data of HFL, LWL & Discharge are assumed  results are shown in the design criteria, section .1.4. 
or  collected  from  some  previous  report.  As  those  reports 
are  very  old,  they  do  not  contain  current  data.  e,g  Q  of 
Jamuna  (1:100  year  )  =1,00,000cumec  was  mentioned  in 
this  report.  But  if  we  consider  current  data  then  Q  of 
Jamuna  at  Bahadurabad  (1:100  year)  will  be  1,12,865 
cumec.  For  effective  design,  analyses  with  current 
Hydrological  Data  are  required.  Current  primary  data  are 
available in Hydrology Directorate of BWDB. So, to address 
current  hydrological  scenario  primary  Hydrological  Data 
(including current Data upto 2013) should be collected and 
analyze it for Design .HFL, Design LWL & Design Discharge. 
These  Hydrological  Calculations  should  be  enclosed  in 
Design Report 
•  Flow  Velocity  (Art  4.7,  Page  25) Flow velocity collected from BWDB measurement is 
Flow Velocity is a key factor to determine stability & size of  presented  in  the  design  criteria  section  1.4.  Flow 
protection  clement.  In  this  report,  Velocity  data  are  velocity measured at Bahadurabad in Brahmaputra‐
assumed or collected from some previous old report. Flow  Jamuna  River  and   that  at  Baruria  in  Padma  have 
Velocity  of  Padma  at  Harirampur  was  determined  on  the  been used. The selection criteria is explained in the 
basis  of  velocity  of  Meghna  at  Haimchar  &  Chandpur.  For  Design note. 
effective  design,  site  specific  velocity  is  essential  and 
Designer  should  be  more  careful  in  selecting  Design 
Velocity.  Some  Velocity  Data  are  given  below  for 
information 

 
Page 198   September 2013 
  Technical Designs for Tranch‐1 Work 
 
COMMENT  REPLY 
 
Hydrology,BWDB Padma Bridge
 
Velocity (m/s) Bahadurabad Baruria Transit Mawa Mawa (1:100)
Max = 3.68 Max =4.23 Max =4.35 Max = 4.60
June
To Min =3.00 Min =3.00 Min =3.02 Min =
September
Average=3.28 Average =3.37 Average=3.45 Average =

 
Maximum Velocity: 
JMREMP Manual, P‐122: (as per FAP 24) 
Jamuna:  Kamarjani = 3.2 m/s 
  Bahadurabad = 3.7 m/s 
 
Ganges:  Gorai offtake = 4.0 m/s 
•  Bed  Material  Size  &  Silt  Factor  (  Art  4.8,  Page  27) Size of bed material has been taken from FAP24 and 
Bed  Material  Size,  D50  is  a  Key  factor  to  determine  Scour  FAP  1  report,  checked  with  FAP‐21  Design  Manual 
Depth.  For  effective  design  site  specific  &  correct  D50  and IWM report on Flood Control Embankment and 
should  be  used.  But  in  this  report,  some  assumed  value  River  Bank  Protection  of  the  Left  Bank  of  Jamuna 
from  previous  report  has  been  used.  So,  site  specific  &  River at Nagarpur and Chouhali; There are no recent 
actual  D50  should  be  used.  D50  for  each  site  may  be  measurements. 
determined from field sample. 
•  Waves  (  Art  4.9,  Page  28) Wave  height  has  been  taken  from  the  Special 
Waves  i.e.  Wave  Height  &  Wave  Period  is  a  Key  factor  to  Report  23,  design  brief  for  Riverbank  Protection 
determine  size  of  protection  element.  In  this  report,  implemented under JMREMP (update),Dec 2006 and 
assumed  Data  of  Wave  Height  &  Wave  Period  are  copied  verified  with  JMREMP  Design  Manual  and  FAP‐21 
from  FAP  21  Manual  (2001).  That  report  is  also  an  older  design  Manual.  Finally  the  highest  wave  suggested 
one.  Instead  of  assuming  Design  Data,  primary  Data  by FAP‐21 Design Manual for 100 year return period 
(including  current  Data  upto  2013)  from  Metrological  is  selected.  The  base  paper  prepared  by  Dennis 
Department  can  be  collected  and  analyzed  it  for  Design  Grosser is enclosed as Appendix‐IV (Attachment‐2). 
Wind Speed & Design Wind Duration. Design Wave Height 
& Wave 'Period can be calculated from Wind Speed. Wind 
Duration  and  Fetch  Length.  These  Calculations  should  be 
enclosed in Design Report 
•  Scour  Depth  (Art  4.811,  Page  27) The scour value has been assumed from the survey 
Discharge,  bed  material  size  &  Lacey's  Factor  are  key  data  conducted  under  the  project.  The  selection  of 
element for calculation of Scour Depth. in this report Scour  data  is  site  specific.  The  design  being  a  feasibility 
Level  at  Chouhali  was  calculated  as  ‐12.90m(PWD)  by  level one, generalised data received from the survey 
considering  Q=  36000  m3/s,  (D50  =0.18mm  &  Lacey's  has  been  used.  The  general  scour  has  also  been 
Factor = 1.5. But observed Lowest Scour level at. Chouhali  verified  with  the  historical  data  taken  from  BWDB 
is  ‐31.34  m(PWD)  as  per  BWDB  Field  data.  It  reveals  that  cross‐section. 
value  of  Discharge,  Bed  material  size  &  Lacey's  Factor  are  In using the Lacey's scour formula attention is given 
not considered properly. In this report Q= 36000 m3is has  on  the  share  of  discharge  carried  by  the  particular 
been  considered  instead  of  actual  discharge  of  Jamuna  is  channel.  Limitation  of  applying  Lacey's  formula  is 
1,12,865 cumec (100year). Near Chouhali Upazila Complex,  also considered in applying in a braided channel.  
tere is a right angle turn in river bank. In this case Lacey's 
Factor will be 2.00. If we :x.‐aisider Q= 1.12,865 m3/s, d50  During  the  detail  design  the  specific  area  has  to  be 
=0.18mm & Lacey's Factor = 2.00 then Scour Level comes to  addressed with the scour measured in that area plus 
‐36.07  m(PWD)  which  is  closer  to  observed  one. an allowance.  
From this report it is also found that Calculated Scour Level 
at  Harirampur  is  ‐  25.00  m(PWD),  but  observed  lowest 
Scour  Level  is  ‐37.00  m(PWD).
Some .more Observed Scour Level are described as below 
  Location Sirajgonj Sailabari Mawa
  Observed scour level(m PWD) -33.00,-44.00 -40.00 -50.33

 
Moreover  during  design  it  may  be  found  that  there  is 
Moderate  Bend  in  River bank  and flow  is  parallel  to Bank. 

 
  Page 199 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
COMMENT  REPLY 
Under this situation Designer may consider Lacey's Factor = 
1.5. But during or after execution, it may happen that there 
is an oblique flow due to formation of a char or change in 
river  bank  from  moderate  bend  to  severe  bend  or  right 
angle. In this changed situation Lacey's Factor will  be 1.75 
or  2.00.
So,  Discharge,  Bed  material  size  &  Lacey's  Factor  should 
carefully be selected during design. 
• Size & thickness of protection Element (Art 4.12, Page 29) In  calculating  geobag  size  and  thickness  Pilarczyk 
It  is  to  be  noted  here  that  USACE  Equation  &  JMBA  equation and JMREMP manual has been followed. 
Equation is not applicable for Geobag 
•  Khoa  Filter  (  Art  4.13.1,  Page  29) Geotextile  filter  has  a  filter  quality  both  along  and 
From this report and Drawing it is found that Geotextile &  across  the  fabric.  Moreover  geotextile  is  laid  on  a 
sand has been used as filter. But Khoa Filter does not used.  50mm  thick  sand  bed  which  will  act  as  additional 
BWDB  Manual,  JMREMP  Manual  and  other  manual  filter  as  well  as  it  will  protect  gotextile  against 
suggested  for  using  Khoa  Filter.  So,  explanation  is  needed  clogging. 
for not using Khoa Filter above Geotextile.  In JMREMP work in general no khoa filter was used. 
Khoa Filter does not comply with the Terzaghi Filter 
rule. 
•  Size  of  Geobag  (  Art  4.13.2  &  4.13.3,  Page  30) Flow  velocity  considered  for  selecting  size  of 
From this report it is found that 125kg Geobag will be used  protection  element  (geobag)  is  sufficient  for  the 
in Area Coverage & Launching Apron, 250kg Geobag will be  stability of 125 kg geobag. 250 geobag shall be used 
used in protrusion. But JMREMP Manual recommended for  only if there is higher velocity, which normally is not 
using  of  single  size  of  Geobag.  Moreover  supporting  expected during execution of the work. It is required 
calculation  for  250  kg  Geobag  has  not  been  furnished.  only to meet the emergency. 
Supporting  calculation  should  be  enclosed  for  250  kg 
Geobag 
•  Sequence  of  Implementation The  active  erosion  zone  and  its  extent  at  present 
Sequence of Implementation of Protective Work for a large  has been selected for providing protection under the 
reach  like  5.00km  in  Chouhali  and  7.00km  in  Harirampur  project.  The  probability  of  continued  erosive  attack 
may be discussed here  has  also  been  considered  through  morphological 
studies. 
Annex F2: Appendix ‐1 Sample Calculation for Chouhali (Page 79‐93) 
• HFL, LWL & Discharge (Page 35) :  Response placed above
Comments same as above in Sl no. 1  
•  Velocity  (Page  35) Selection of velocity is explained above
here  Average  Flow  Velocity  has  been  considered  as  3.00 
m/s.  But  there  is  no  supporting  explanation  for 
determination  of  such  velocity.  From  JMREMP  Manual 
Velocity of Jamuna at Kamarjani is 3.20m/s & Bahadurabad 
is  3.70  m/s,  Moreover  according  to  Data  of  Hydrology 
Directorate, Velocity of Jamuna is as below 
  Velocity (m/s) Bahadurabad Baruria Transit
June Max= 3.68 Max= 4.23
 
To Min= 3.00 Min= 3.00
  September Average=3.28 Average=3.37

Velocity  of  Jamuna  at  Chouhali  can  also  be  measured  at 
site.  Velocity  is  a  very  important  Design  Data,  because  it 
determines  the  size  of  protection  element.  So,  Design 
Velocity  should  be  carefully  selected.
In page 26, Art 4,7.2, it is mentioned that 3.00 m/s velocity 
has been considered in straight reach and 3.50 m/s velocity 
has  been  considered  for  acute  bend  and  protrusion.  But 
3.50  m/s  velocity  has  not  been  used  during  calculation  of 
size of CC block or Geobag. 
•  Bed  Material  Size,  D50  (Page  35) Bed material selection is explained above
 
Page 200   September 2013 
  Technical Designs for Tranch‐1 Work 
 
COMMENT  REPLY 
As  it  was  discussed  in  Art  4.8,  Page  27  of  this  report,  Bed 
Material  Size  0,18mm  is  assumed  from  some  previous 
report.  For  effective  design,  site  specific  &  actual  D50 
should  be  used.  Actual  D50  Data  are  essential  for  correct 
Scour Depth. D50 for each site should be determined from 
field sample 
 
Padma Halcrow jamuna,jmremp manual JMREMP Manual
 
Bridge For Jamuna
1:100 1:25 PIRDP MDIP

Hs(m)= 1.40 1.00 1.30 1.00 1.00 1.25

Tm(sce)= 3.40 3.00 3.40 4.20

•  Wave  Data  (Page  36) Wave data and its method of calculation is 


Here  Wave  Height  =  1.30  m  has  been  used  from  FAP21  explained above and reference appended. 
Manual  (200l).  This  is  an  old  data.  Wave  Period  2.45sec 
used has been used from JMREMP Manual (2010). Updated 
Metrological  Data  should  be  used  for  determination  of 
Design  Wind  Speed  &  Design  Wind  Duration  and 
subsequently  Wave  Height  &  Wave  Period.  Calculation 
sheet in this regard should be enclosed with Design Report. 
Some Data of Wave  height  & Wave Period from  previous 
manual are given below for information 
•  Lacey's  Factor  (Page  36) Explained above
Here  River  Bank  has  been  taken as  Moderate  Bend.  Some 
part  of  River  Bank  may  be  have  Moderate  Bend  at  U/S 
Location.  But  at  present,  at  Chouhali  Upazila  Complex, 
there is a sharp right angle turn. At D/S of Chouhali Upazila 
Complex,  there  is  severe  Bend.  So,  Lacey's  Factor  should 
carefully be selected. Moreover Drawing of this Protective 
Work  should  contain  a  Plane  Table  Survey  &  current 
Satellite Image showing Bank Line 
•  Scour  Level  (Page  35,47) Selection of scour depth explained above. 
Here it is mentioned that maximum observed Scour Level is 
‐3.00m(PWD).  Calculated  maximum  Scour  Level  is  ‐
12.90m(PWD).  But  in  the  attached  Technical  Drawing, 
maximum observed Scour Level is ‐9.87 m(PWD). Moreover 
according to Data supplied from field office to Design Circle 
‐1  ,  maximum  observed  Scour  Level  is  ‐31.34m(PWD).  So, 
Discharge,  Bed  material  size  &  Lacey's  Factor  should 
carefully be considered during calculation of Scour depth. 
•  JM  BA  Equation  (Page  36) JMBA equation suggests to use h/d = 5.  
Here h/d= 5 has been assumed. Valid justification should be  For  geobag  size  selection  JMBA  equation  has  not 
provided  for  this  assumption.  It  is  to be  noted  that ,JMBA  been used. 
Equation is not applicable for Geobag 
•  Dn  in  Pilarezyk  Equation  (Page  37) Geobag  is  not  a  cubical  element,  so  equivalent 
In.1  JMREMP  Manual  Dn  has  been  defined  as  "Equivalent  cubical  size  is  used  as  an  unit  of  size.  Finally 
Diameter".  But  in  this  report  Dn  has  been  defined  as  equivalent diameter has been used in calculation.  
"Nominal thickness of protection unit". This matter Should 
he clarified. 
•  Average  Water  Depth  in  Pilarczyk  Equation  (Page  37) 6.0 m being the average depth over the protection 
Here  average  Water  Depth,  h  =  6.00  m  has  been  element  used  for  areal  coverage  and  launching 
considered.  How h  =  6.00m  has  been  selected,  supporting  apron.  The  lower  depth  is  chosen  as  it  provides  a 
calculation should be given. In JMREMP Manual h' defined  moderately higher size of protection elements. And 
as  "water  level  at  toe  of  slope".  But  in  this  report  h'  has  therefore is on the safer side. 
been  defined  as  "Average  Water  Depth".  This  matter 

 
  Page 201 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
COMMENT  REPLY 
should be clarified 
• Angle of Repose used in Pilarczyk Equation (Page 37‐39) The  protection  element  in  areal  coverage  and 
Value of Angle of Repose for different protection element is  launching  apron  is  not  supported  by  any  type  of 
mentioned in FAP21 Manual & JMREMP Manual. But in this  filter.  Hand  placed  cc  blocks  proposed  for  slope 
report those values are not used in all cases. Some  protection above LWL is placed on filter. 
examples are given Below  Considering  all  these  factors  the  angle  of  repose 
 Protection Used in FAP21 Manual JMREMP Manual suggested  by  Pilarczyk  for  Geobag,  Inglish  for  rocks 
Element
 CC
this Report Geotextile Granular and  worked  out  example  in  FAP‐21  Manual  for  CC 
40° 30° 35° - -
Block,multi block  has  been  consulted  for  selection  of  angle  of 
 -layer
Rock 35° 20° 25° Riprap 40° repose of a protection element and its use. 
 CCblock 40° 20° 25° - -
hand placed

 Single layer
Geobag 30° Sand filled 30°-40°
  system

 
Source of value of Angle of Repose used in this report should be 
mentioned 
•  Thickness  of  protection  above  LW  L(Page  44‐45) Protection  thickness  was  decided  in  consideration
In  this  report,  Maximum  Thickness  of  Protection  was  of  2  layers  of  dominant  size  of  protection  element. 
calculated  as  400mm  from  stone  size  consideration  and  This is already explained in the design sheet.  
Maximum  Thickness  of  Protection  was  calculated  as   
2170mm  from  stream  flow  consideration.  But  Protection 
thickness  was  selected  as  400  mm.  The  explanation  for 
selecting lower thickness is not clear 
•  Thickness  of  CC  Block  Protection  Below  LWL  (Page  46)  ‘BERT te Slaa’ in ”River Training Works for 
In art A.2.2 it is mentioned that Thickness of Protection by  a  Bridge  acrossthe  Brahmaputra  River, 
CC Block should be 3D to accommodate winnowing effect. 
Basis  of  such  assumption  or  source  should  be  mentioned 
Bangladesh”, stated  that the total thickness of 
here.  an  "all  in"  filter  should  be  approximately  five 
In  writing,  it  is  mentioned  Thickness  of  Protection  by  CC  times the diameter of a single rock which can just 
Block  should  be  3D  +50%.  But  calculation  was  made  as  withstand the current forces.  
Thickness  =  4.5D. So,  Clarification  or  correction is  needed.   
Moreover this calculated thickness i.e. 3.5D or 4.5D has not  3D+  50%  additional  shall  be  (3+1.5)D  =  4.5D,  no 
been  used  in  drawing.  drawing has been produced with cc blocks in areal 
In calculation, it is written that 2 layer of CC block should be  coverage or in launching apron. 
dumped over Geobag. For 2 layer, 22.22 nos/sqm CC Block   
should  be  dumped.  But  in  drawing  it  is  written  as  The  statement  is  made  to  cover  the  eroding 
16nos./sqm. So, Clarification or correction is needed  surface  by  material  of  uniform  size  on  a  geobag 
filter.  Under  this  state  the  cover  by  minimum  2 
layers of cc block has been made on top of a filter 
layer.  The  void  in  this  case  will  be  around  40%, 
but  in  this  case  a  very  conservative  assessment 
has  been  made  with  a  void  of  about  28% 
percentage. 
 
All other inconsistencies will be taken care during 
detail design. 
•  Flatter  slope  in  River  Bed  Level  (Page  47) Slope after ‐3.00 is slightly flatter than 1V:5H
Here  it is  considered that  after  0.00  m(PWD),  River  Bed is 
Flat. From Section it is prevails that it is not correct 
•  Areal  Coverage  &  Falling  Apron(Page 47) Length  of  areal  coverage  is  the  main  factor.  It  is 
Here  Length  of  Areal  Coverage  &  Falling  Apron  selected  selected  in  a  way  that any  scour  cannot  occur  near 
arbitrarily.  Areal  Coverage  are  considered  from  3.00  the bank to induce any slope failure.  15 m apron is 
m(PWD)  to  0.00  m(PWD)  &  Length  of  Areal  Coverage  was  proposed to take care of any scour that can occur in 
selected  as  30m.  But  as  per  enclosed  cross  section  of  a season.  
Chouhali,  inclined  length  from  3.00  m(PWD)  to  0.00  In  Jamuna  river  it  is  observed  that  a  maximum  of 
in(PWD) is about 12.37m & 4.42m. Length of Falling Apron  15,0 m of scour can occur in front of a revetment in 

 
Page 202   September 2013 
  Technical Designs for Tranch‐1 Work 
 
COMMENT  REPLY 
was selected as 15m. Selection of Length & Description of  90 days i.e. in one monsoon season. Please Refer to 
Apron  written  here  does  not  comply  with  section  &  Padma Bridge Design Report, Annex E.  
calculated of Scour Depth of this report. So, Clarification or 
correction is needed. 
• Volume of Rock above LWL(Page 48)  The material is calculated on 1V:3H slope, this also 
From Page 45, Thickness of Protection above LWL = 400  accounts for 1,5m  horizontal cover on the flood 
mm So, Volume of Rock above LWL = (11‐5) V 10 x 0.4 =  plain. 
7.59 m3/m But this Volume is written here as 11.95 m3/m.
So, Clarification or correction is needed 
• Volume of Rock in Falling Apron In Page 47‐ 48, it is 
written that  Launching takes place normally in single layer. This 
o Areal Coverage will be provided from LWL (+3.00 in,  has to be upgraded in subsequent stages. Proper 
PWD) to 0.00 m(PWD)  monitoring and follow up is needed to take care of 
further upgrading after initial launching of material. 
o Falling Apron/Launching Apron is proposed to be placed 
at the end of Areal Coverage. 
o Calculated Scour Level is ‐13.00 m(PWD).
o Thickness of Protection (pitching), T = 520mm
o Thickness of Protection, 1.5T = 780mm
o Volume provided in Falling Apron = 15 x 0.78 = 
11.70m3/m 
o D = 0.00‐ (‐13.00) = 13m 
o Apron will be Launch in 1V:2H slope. 
Launched slope Length ( if it Launched in IV:2H slope ) =13 x 
2.24 = 29.12m. In that case, thickness of protection after 
launching will be =11.70 / 29.12 = 0.402 m. This thickness is 
less then Design thickness (0.520 m). Whether this 
thickness is acceptable. Clarification or correction is needed
• Volume of Geobag in Falling Apron 
In addition to above, in Page 48, it is written that  Placed apron thickness is 510mm i.e. 3 layers of 
o Thickness of Protection by Geobag, 3 Layer = 510 m/m 125kg geobags.  
o To ensure 3 layer, additional 1 layer should be used.   
o Volume provided in Falling Apron = 15 x 0.51 x 1.33 =  Explained above 
10.17 m3/m   
Launched slope Length ( if it Launched in 1V:2H slope ) =13   
x 2.24 = 29.12m. In this case, thickness of protection after 
launching will be =10.17 / 29.12 = 0.349 m. This thickness is 
less then Design thickness (0.510 m). Whether this 
thickness is acceptable. JMREMP Manual recommended 
that, "Systematic coverage by minimum 3 layer Geobag 
may provide a dependable protection." Clarification or 
correction is needed. 
• Extra Volume of Geobag 
In Page 48‐ 49, 33 % extra Geobag has been considered in 
Areal Coverage & Falling Apron. Basis of such assumption 
or source should be mentioned hare. In JMREMP Manual it 
was recommended that 
o Systematic coverage by minimum 3 layer Geobag may 
provide a dependable protection. 
o To ensure 2 layer at least 4 layer Geobag needed to be 
placed systematically 
So,  by  logic,  from  the  above  recommendation  it  reveals  The  recommendation  is  given  as  per  achieved  in 
that to ensure 3 layers, at least 5 or 6 layer geobag needed  JMREMP.  3  layers of  geobag  if  properly  placed  can 
 
  Page 203 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
COMMENT  REPLY 
to be dumped systematically. It will be helpful, if the matter  serve  the  purpose.  No  need  of  extra  coverage.  so 
is clarified.  provision  of  4  layers  is  made  to  take  care  of  any 
uncertainty.  Reference  is  available  in  Padma  Bridge 
Final Design Report Annex E 
•  End  Termination The work is proposed to be extended in next tranch. 
End  Termination  at  both  ends  of  Protective  Work  has  not  So end termination is not proposed. In JMREMP also 
been  considered.  How  both  end  will  be  protected  against  no  end  termination  has  been  provided,  rather  the 
out flanking. It will be helpful, if the matter is clarified.  protection limit is extended beyond the critical zone.
From the Design Computation of Chouhali‐Nagarpur following question arises
• How Areal Coverage & Falling Apron will be differentiate  Already  explained  above.  Moreover,  designers 
or  identified  in judgment  shall  be  applied  in  case  of  varying  the 
different River Section.  width of areal coverage.  
• How Length of Areal Coverage will be determined. Explained
• How Length of Falling Apron will be determined. Explained
•  How  Volume  of  material  in  Falling  Apron  will  be  Explained
determined.  Does  this  volume  will  be  calculated  on  the 
basis of Lowest Scour Level. 
•  JMREMP  suggested  3  layer  of  Geobag.  How  this  3  layer  Explained
will  be  ensured  during  dumping  at  different  depth, 
different flow condition etc 
3. Annex F2: Appendix VI : Technical Drawing
Chouhali‐Nagarpur 
• In the Drawing LWL = 5.50m(PWD) has been used. But in  Shall be taken care in detail design. This has been 
calculation LWL = 5.00m (PWD) has been used (Page 35,46).  corrected in the report. 
It should be corrected 
• Original River sections are not visible 
• Drawing of Chouhali‐Nagpur, Section‐1  & Section‐2 does  These are Feasibility level designs. Shall be taken 
not  match  with  the  RL,  written  there  (copy  enclosed).  It  care after a detail survey during final design stage. 
should  be  corrected.  Moreover  these  section  are 
incomplete,  Because  Elevations  are  written  from  0.00  m 
(PWD) to towards River Bed. In the design sheet (Page 35), 
Average  Bank  level  was  Written  as  11.00  m(PWD).  So, 
Elevation  should  be  written  at  least  from  Average  Bank 
level  i.e.  11.00  m(PWD)  to  towards  Lowest  River  Bed  and 
section should be drawn correctly in 1H: 1V scale. 
• The Section‐1 & Section‐2 enclosed in Technical Drawing  The sections are based on river surveys in 2011 and 
does  not  represent  the  actual  River  section.  Design  &  2012 flood season. 
Drawing  should  be  made  on  the  basis  actual  section. 
Estimate should be prepared on the basis of that drawing 
•  At  Chouhali  Upazila  Complex,  different  buildings  are  The Buildings are currently eroding. 
situated  just  at  the  bank  line.  If  during  design,  it  was 
attempt  to  make  a  1:3  slope  line  above  LWL  then  this 
building have to be demolished. But it will be very difficult 
to  demolish  those  building.  This  critical  matter  should  be 
addressed carefully during design & implementation 
Zafargonj: Original River sections are not visible. Moreover  The river bank will be surveyed during the detailed 
these  section  are  incomplete,  elevations  are  written  from  design.  
0.00  m(PWD)  to  towards  River  Bed.  Elevation  should  be 
written at least from Average Bank level to towards Lowest 
River Bed 
In Section‐3 it was found that 2 layer 250kg Geobag will be  The base layers consisting of smaller sizes dumps 
dumped over 1 layer 125kg geobag. During dumping, how,  assures that there are less gaps in the critical area. 
position  of  2  layer  250kg  Geobag  will  be  ensured  over  I 
layer 125kg Geobag. Moreover ,IMREMP Manual suggested 
 
Page 204   September 2013 
  Technical Designs for Tranch‐1 Work 
 
COMMENT  REPLY 
for using Single Size of geobag, 
The  Section‐I,  Section‐2  &  Section‐3  enclosed  in  Technical  The sections  are based on river surveys in 2011 and 
Drawing does not represent the actual River section. Design  2012 flood season 
&  Drawing  should  be  made  on  the  basis  actual  section 
Estimate should be prepared on the basis of that drawing.
Al  Zafargonj Bazar,  different  shops  are situated just at  the 
bank  line.  If  during  design,  it  was  attempt  to  make  a  1:3 
slope  line  above  LWL  then  this  shops  have  to  be 
demolished.  But  it  will  be  very  difficult  to  demolish  those 
shops.  This  critical  matter  should  be  addressed  carefully 
during design & implementation 
Benotia  The sections  are based on river surveys in 2011 and 
Original  River  sections  are  not  visible.  Drawing  of  Benotia,  2012 flood season 
Section‐1 does not match with the RL written there. In the
Drawing,  Elevation  of  Flood  Plane  is  9.60  m(PWD).  But  in 
the  drawing,  RL  is  written  from  4.78  m(PWD)  to  ‐0.86 
m(PWD).  So,  Elevation  should  be  written  at  least  from 
Average Bank level to towards Lowest River Bed. Design & 
Drawing  should  be  made  on  the  basis  actual  section. 
Estimate should be prepared on the basis of that drawing 
Harirampur  The sections  are based on river surveys in 2011 and 
Original  River  sections  are  not  visible.  Drawing  of  2012 flood season 
Harirampur, Section‐1 does  not match with the RL  written 
there (copy enclosed). Elevation should be written at least 
from Average Bank level to towards Lowest River Bed. From 
the  section  it  is  found  that  LWL=  +2.00  m(PWD).  But 
Existing RL is written from ‐1.39 m(PWD) to ‐2.74 m(PWD). 
These  RL  does  not  reflect  a  section.  Design  &  Drawing 
should  be  made  on  the  basis  actual  section.  Estimate 
should be prepared on the basis of that drawing 
In Section‐I it was found that 2 layer 250kg Geobag will be  See earlier explanations.
dumped over 2 layer 125kg Geobag. During dumping, how, 
position  of  2  layer  250kg  Geobag  over  2  layer  125kg 
Geobag  will  be  ensured.  Moreover  JMREMP  Manual 
suggested for using Single Size of Geobag 
From  Index  map,  it  was  found  that  location  of  protective  There are no plans to close the offtake. 
work at Harirampur is at the oftake of Ichamati River. From 
Index map in  Technical Drawing, it seems that Harirampur 
Protective Work will close the oftake. It is to be mentioned 
here  that  previously  Ichamati  River  was  closed  by 
Kaishakhali  Closure.  Kaishakhali  Closure  is  approximately 
7.00  to  8.00  km  D/S  of  Harirampur  Protective  Work. 
Presently  people  of  Dhohar  &  Nawabgonj  are  demanding 
for opening the Kaishakhali Closure and they demand for a 
regulator  at  that  point.  So,  before  implementation  of 
Harirampur  Protective  Work,  the  adjoining  area  should 
carefully  be  studied.  It  should  be  checked,  whether  there 
are  any  conflicts  between  Harirarnpur  Protective  Work  & 
Regulator  at  Kaishakhali  Closure,  point  and  some  other  3 
Flushing Gate in that area. 
I, Annex F2: Chapter 2 Embankment (Page 49‐56)
In  Art  2.3.1,  Page  7,  Factor  of  Safety  =1.4  has  been  The  FS  has  been  considered  in  line  with  the 
considered  for  slope  stability.  But  normally  this  Factor  of  standards followed in JMREMP. 
Safety  is  considered  as  1.5.  Moreover  Bishop  Method  or 
Jamboo Method is used for calculating Slope Stability 
•  5.30  in  Carriage  way  has  been  provided  on  C/S  slope  of  Road  section  as  per  type‐5,  (minimum  width  of  2 
embankment.  In  page  9,  it  was  mentioned  that  lane  carriage  way,  Ref:  Geometric  Design  of  RHD 
 
  Page 205 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
COMMENT  REPLY 
specification  of  Rural  Road  of  RHD  has  been  used  for  this  Roads‐2005) is 5.5m carriage ay + 2x1.2 m shoulder 
Carriage way. According to a Praggapan  of Road Transport  + 2x0.95m verge, in total 9.8m; this has been made 
Wing  of  planning  Commission,  Road  Class  :  Rural  Road‐1  10.0m  with  2x1.5m  paved  shoulder  and  2x0.75  m 
has  been  replaced  by  Design  Type  8.  But  the  Drawing  of  verge. 
Carriage  way  (Detail  'D')  as  enclosed  in  Technical  Drawing 
does  not  match  with  Design  Type  8,  So,  Clarification  or 
correction is needed. 
•  As  the  fill  material  of  embankment  is  dredge  fill  soil,  The  seepage  issue  has  been  addressed  in  the 
attention  should  be  given  to  Seepage  analysis.  In  some  geotechnical assessment 
Book Slope of seepage line for sand was mentioned as 1:15,
•  In  Annex  Fl,  Page  25,  value  or  initial  void  ratio  eo,  The values were taken from the laboratory analysis 
Compression Index, Cc, Sp gravity Gs & Unit Weight etc. has  on  the  selected  sample.  As  a  feasibility  study 
been assumed for settlement calculation. But these values  analysis  selected  area  has  been  analysed.  Further, 
of  each  layer  of  foundation  soil  should  be  obtained  from  elaborate  study  will  be  made  during  detail  design 
laboratory test report or field soil sample  stage.  
Annex F2: Appendix VI Technical Drawing (Embankment)
•  Details  of  10cm  RCC  at  Crest  of  Embankment  has  not  RCC  road  detail  will  be  shown  during  detail  design 
been  shown.  This  RCC  Work  may  be  avoided.  This  work  is  stage.  
duplication  with  US  carriage  way.  Embankment  can  be 
monitored by this carriage way. Moreover if RCC was road 
was  constructed  over  crest  then  it  will  be  difficult  to  rise 
the embankment height in future (if needed). 
•  Details  or  Verge  &  Shoulder  (Detail  ‘D')  have  not  been  The  drawings    have  been  expanded  with  these 
shown. Moreover same item has been shown for Shoulder  details. 
& Road. 
• C/S Slope has been considered as 1:2 when height is 4.00  River  side  slope  is  1V:3H  and  country  side  slope  is 
m  and  1:2.5  when  height  is  3.00  m.  So,  Clarification  or  1V:2.5H 
correction is needed 
Crest width of Embankment (3.20m or 3.21m), Width of R/S  3.20 m is the crest width, width of slope shall be as 
slope (10m or 8 m) should be corrected  per slope provided. 
•  At  the  bottom  of  embankment  1.00  base  stripping  has  The  cladding  will  reach  to  the  bottom  of  the 
been  considered.  This  1.00  m  will  be  filled  by  dredge  fill  excavation to avoid this. 
soil.  If  the  embankment  and  &  WS  end  of  base  cannot  be 
covered properly by clay cladding (Detail E) or other similar 
method, then there is a possibility of seepage through this 
base. This may be a cause of failure of embankment 
Annex F2: Appendix II: Gala Regulator (Page: 94‐122)
• In page 51, it is mentioned that Drainage area outside the  The Hurasagar subproject (proposed to be restored) 
catchment Area is 0.00. But from the project map (Page 18)  is  protected  against  flood  by  embankment  along 
it  is  found  that  there  are  embankment  on  eastern  side  &  Brahmaputra‐Jamuna,  Hurasagar‐Baral  and  part  of 
southern  side,  no  embankment  on  northern  &  western  Karotoa river. 
side.  How  intrusion  of  flood  water  from  northern  & 
western side will be prevented. So, Catchment area as well 
as Discharge should be considered carefully 
• For Drainage & Flushing condition inside WL & outside WL  As a feasibility level design the selection of runoff is 
should  be  selected  carefully  from  Hydrological  Analysis.  described. 
Hydrological Analysis should be incorporate in this report 
•  Foundation  Design  has  not  been  enclosed  here.  Will  taken  care  of  in  detail  design  stage.  Based  on 
Foundation Design is very important for correct estimation  survey analysis. 
Annex Fl: Chapter 5: River Bank Stability (Page 22‐28) 
•  In  Page  28,  here  it  is  mentioned  that  maximum  river  Statement  made  on  cross‐section  surveyed  under 
depth  is  18  m  and  river  slope  is  1:5  to  1:1.  But  at  some  the project and the observation is site specific.  
places  river  depth  is  more  than  18  m.  In  many  case  side 
slope is very steep and slope less than 1:1. 

 
Page 206   September 2013 
  Technical Designs for Tranch‐1 Work 
 
COMMENT  REPLY 
In Slope Stability Analysis, pure Clay & pure Sand have been  With the presence of cohesive properties the soil 
considered. But from the Bore log in Table 2‐5 to 2‐12, Clay  sample is considered as clayee material. The 
mixed  with  Fine  Sand  was  found  in  2  (two)  Bore  hole.  In  properties are assumed from the laboratory 
most bore hole, soil is a mixture of Fine Sand & Silt. In no  analysis. 
Bore log there are pure Sand or pure Clay. Moreover in all 
Bore log, Soil Type Was defined mostly as Fine Sand 
Soil Type describes in Table 2‐5 to 2‐12 should match with  Noted, shall be taken care in the detail design stage. 
Bore  Log  shown  in  Fig  3‐1  to  3‐4.  Moreover  Soil  Type 
describes  in  Table  2‐5  to  2‐12  should  match  with  soil 
composition stated there 
•  In  Page  29,  Unit  Weight,  Angle  of  Internal  Friction  &  Explained above
Cohesion for each layer has been assumed for pure Sand & 
pure  Clay  for  Slope  Stability  analysis.  But  value  of  Unit 
Weight, Angle of Internal Friction & Cohesion for each layer 
should  be  obtained  from  laboratory  test  of  field  soil 
sample. 
In Page 29, ordinate of Fig 5.3 & 5.4 is not clear Ordinate shows the safety factor 

•  Here.  two  depths  (19m,  39m)  of  River  Bed  have  been  One  low  and  one  high  (i.e.  two  extremes)  are 
considered  for  Slope  Stability.  It  will  helpful  for  design,  if  analysed. 
some  more  depth  such  as  25m,  30m,  50m  etc  may  he 
analyzed for Slope Stability. 
•    Here Allowable Factor Safety for Slope Stability was not  Explained earlier
clearly  mentioned.
According  to  BWDB  Manual  &  other  literature,  Allowable 
Factor Safety is 1.5. 
•  It  is  not  clear  how  FS  =  1.5%  g  and  FS  =  5%  g  has  been  Earthquake  impact  is  calculated  as  per
calculated. A sample calculated may be attached.  recommendation  of  BNBC  and  also  a  higher  factor 
like 5%g in line with JMREMP 
• It will he better to understand, if Range of Starting Point  noted
&  Range  of  End  Point  i.e.  limit  of  different  Slip  Circle  are 
mentioned in this Report. 
•  Findings  from  Table  5‐1  &  5.4  may  be  described  in  a  noted
bullet form, some are mentioned as below. 
o FS increases with the increase of River Depth 
o  FS  increases  with  the  increase  of  thickness  of  top  clay 
layer  upto  5.00m.  If  thickness  of  top  clay  layer  exceeds 
5.00m, then FS decreases. 
o  When  side  slope  is  1:2,  then  FS  cannot  meet  the 
minimum limit 
o  When  side  slope  is  1:3,  then  FS  satisfies  the  allowable 
limit, during design condition 
Moreover  it  will  be  helpful  for  designer,  if  this  report  can 
make  a  strong  recommendation  regarding  the  design  side 
slope in Protection work 
•  An  analysis  may  be  incorporate  here,  regarding  the  Will be addressed in Detail Design Stage 
stability  of  Slope  when  it  builds  with  local  earth  or  gunny 
bag  or  synthetic  bag.  This  is  a  common  phenomenon  in 
River Bank Protection Work. 
• In Page 29, it was mentioned that Slope Stability analysis  Software was down loaded from internet 
was done by software Visual Slope, developed by Loveland, 
Ohio,  USA.  As  a  part  of  Technology  Transfer  this  software 
may be supplied to Design Office. 
N It is to be mentioned here that Only "Annex F" has been  These  annexes  were  handed  over  during  the 
 
  Page 207 
PPTA 8054: Main River Flood and Bank Erosion Risk Management Program 
 
COMMENT  REPLY 
sent for comment. Data & Information of "Annex B Data &  meeting  with  the  design  team,  in  the  office  of  the 
Survey",  "Annex  D  :  Hydrology  &  Flood  Modeling"  and  Project Director on 28 July 2013. 
"Annex E : River Hydraulics & Morphology" are required for 
better  understanding  of  "Annex  F",  So,  "Annex  B  :  Data  & 
Survey",  "Annex  D  :  Hydrology  &  Flood  Modeling"  and 
"Annex F; : River Hydraulics & Morphology" should be send 
to this office, 
Comments on Draft Final Report of Technical Design and Drawings for "Main River Flood and 
Bank Erosion Risk Management Program" 
 
The  stretch  from  Sirajganj  to  Enayetpur  is  already 
1.    The  proposed  embankment  is  designed  with 
under  extension.  The  top  width  is  6.0m  and  has  a
carriage  way  and  short  top  width  e.g.3.21m,  3.5m 
additional carriage way for NMV. 
and  a  berm  of  5.2m  for  a  length  of  12.5km.  On  the 
other hand the total length of embankments on right 
bank  of  Brahmaputra  is  about  220km  (designed  by 
BWDB)  and  the  designed  cross  section  is  top  width‐
5.00m and side slopes 1:3. As the new embankment is 
to  be  connected  with  the  old  embankments  and 
the  old  embankment  section  is  enough  to 
withstand the water pressure and seepage, hence the 
embankment  section  may  be  provided  which  is 
compatible  with  the  embankment  implemented  by 
BWDB. 
 
2.  In  the  design,  standard  and  extended  section  is  The point is not clearly understood. 
mentioned,  which  is  not  clear.  The  basis  of  extended 
section is not specified in the design 

3. Statistical analysis and simulation of 2D model result  2D model results have not been used, as the design 
is not clearly discussed.  was based on observed river condition. 
 
4.      The  analysis  for  the  sea  level  rise  is  not  In  BRE  sea  level  rise  has  not  been  considered.  It  is 
incorporated  in  the  calculation.  This  should  be rather left with 1.5m free board on 100 year HFL. 
incorporated in the Draft Final Report 
 
 
 
 
 
 

 
Page 208   September 2013 

You might also like