Method Statement For Derrick Structure00
Method Statement For Derrick Structure00
: FMC-ASS-Pr-24-00
Page : 1 of 3
Rev. : 00
Date: 26 / 12 / 2019
(Owner)
ADNOC REFINING
(Sub-Contractor)
Ferrometalco Steel Construction
Mariout Engineering and Construction
(FMC Job No.)
907/100
Sign.: Sign.: Sign.: Sign.: Sign.:
Revised to
00 ASME Code 23/09/2019
Edd 2017 Name: Name: Name: Name: Name:
1. PROPOSE: -
The purpose of this procedure is to provide the minimum requirements Supply and Fabrication of
Derrick Structure to meet the specific contractual specification requirements of standards and client
specifications.
2. REFERENCES
AS per Client Specifications.
3. PROCEDURE
3.1. SEQUENCE OF WORK.
• Delivery of Derrick structure items to assembly area.
• Offloading of material on assembly area.
• Power Requirement.
• Appointed Person.
• Assembly of Derrick Structure Items.
• Q.C Check.
• Dismantle Derrick structure Items.
All Derrick Structure Items will be inspected visually at Plant Area and Assembly Area by
supervisors.
3.2. PREPARTION
• CONCRETE SUPPORTES
• PLEATS DIFFERENT THICKNESS
• MOBILE CRANE
• POWER SOURCE
• ASSEMBLY TOOLS
3.7. ASSEMBLY
a. Face B from Level +0.0 to Level +76.300 (Tier 1 till Tier 5):
1. Install concrete supports with level and dimension.
2. Main pipes top of concrete support Length 77 meters from level +0.0 to +76.300
horizontal.
3. Assembly all vertical and horizontal bracings of Face B by bolts -or studs- and nuts.
4. Check main dimensions.
5. Dismantle all bracings and release for painting process.
b. Face C from Level +0.0 to Level +76.300 (Tier 1 till Tier 5):
1. Install concrete supports with level and dimension.
2. Main pipes top of concrete support Length 77 meters from level +0.0 to +76.300
horizontal.
3. Assembly all vertical and horizontal bracings of Face B by bolts -or studs- and nuts.
4. Check main dimensions.
5. Dismantle all bracings and shared column between Face B and C and release for painting
process.
c. Face A from Level +0.0 to Level +76.300 (Tier 1 till Tier 5) including guide rails:
1. Install concrete supports with level and dimension.
2. Main pipes top of concrete support Length 77 meters from level +0.0 to +76.300
horizontal.
3. Assembly all vertical and horizontal bracings of Face B by bolts -or studs- and nuts.
4. Check main dimensions.
5. Flush all guide rails internal splice welding.
6. Check Guide rails alignment and spacing (using fabricated frame with same dimension of
Riser Guide arms) for assembled length.
7. Dismantle all bracings, Guide rails and column and release for painting process.