Professional Documents
Culture Documents
TVL 11 IA Carpentry NC II Q2
TVL 11 IA Carpentry NC II Q2
IA-CARPENTRY NCII
Guided Learning Activity Kit
Strip Formworks of Building Components
Quarter 2- Week 1
1|Page
IA-CARPENTRY – Grade 11
Guided Learning Activity Kit
Strips Formworks of Building Components
Quarter 2- Week 1
Republic Act 8293, section 176 states that: No copyright shall subsist in any work of
the Government of the Philippines. However, prior approval of the government agency or
office wherein the work is created shall be necessary for exploitation of such work for profit.
Such agency or office may, among other things, impose as a condition the payment of
royalties.
Borrowed materials (i.e., songs, stories, poems, pictures, photos, brand names,
trademarks, etc.) included in this module are owned by their respective copyright holders.
Every effort has been exerted to locate and seek permission to use these materials from their
respective copyright owners. The publisher and authors do not represent nor claim ownership
over them.
Introduction
Learning Competency
1|Page
Objectives
At the end of this guided learning activity kit, you should be able to:
1. identify the functions and main factors of curing;
2. determine the different types of form and its removal time; and
3. give importance to the procedure in removing concrete formworks.
Review
2. 5.
3.
PREASSESSMENT
Modified True or False
Directions: Write TRUE if the statement is correct and FALSE if it is incorrect.
Then write the correct answer.
1. Curing plays an important role on strength development and durability of
concrete.
2. Ponding is typically used to cure flat surfaces on smaller jobs.
3. Spraying and fogging are used when the ambient temperatures are well above
freezing and the humidity is High.
4. Membrane-forming curing compounds are used to retard or reduce evaporation
of moisture from concrete.
5. Impervious paper and plastic sheets can be applied on thoroughly wetted
concrete.
2|Page
Discussion
3|Page
There are three main functions of curing:
1) Maintaining mixing water in concrete during the early hardening process
Ponding and immersion
Ponding is typically used to cure flat surfaces on smaller jobs. Care should be
taken to maintain curing water temperature at not more than 20 degrees Fahrenheit
cooler than the concrete to prevent cracking due to thermal stresses. Immersion is
mainly used in the laboratory for curing concrete test specimens.
4|Page
Heating coils
Heating coils are usually used as embedded elements near the surface of
concrete elements. Their purpose is to protect concrete from freezing during cold
weather concreting.
Electrical heated forms or pads
Electrical heated forms or pads are primarily used by precast concrete
producers.
Concrete blankets
Concrete insulation blankets are used to cover and insulate concrete surfaces
subjected to freezing temperatures during the curing period. The concrete should be
hard enough to prevent surface damage when covering with concrete blankets.
Other forms of curing include internal moist curing with lightweight
aggregates or absorbent polymer particles. For mass concrete elements (usually
thicker than 3 feet), a thermal control plan is usually developed to help control
thermal stresses. Additional information can be found in ACI Committee 308
report Guide to Curing Concrete3. For specialty concretes, it is recommended to refer
to other ACI reports as follows:
• Refractory concrete ACI 547.1R
• Refractory concrete ACI 547.1R
• Insulating concrete ACI 523.1R
• Expansive cement concrete ACI 223
• Roller-compacted concrete ACI 207.5R
• Architectural concrete ACI 303R
• Shotcrete ACI 506.2
• Fiber-reinforced concrete ACI 544.3R
• Vertical slipform construction ACI 313
5|Page
The removal of concrete formwork also called as strike-off or stripping of
formwork should be carried out only after the time when concrete has gained
sufficient strength, at least twice the stress to which the concrete may be subjected
to when the formworks are removed
Forms should not be removed until the concrete has sufficiently hardened in
order that it can carry safely its own weight and any other live loads it is subjected
to.
The supporting period (period between placing of concrete in forms and removal of
forms) differ according to the type of cement used and the design of formwork. In
general structures carrying construction loads, side timbers shall not be removed
within 7 days and supporting timbers within 28 days of placing of concrete.
In no circumstances shall forms be stuck until the concrete reaches’ strength
of at least twice the stress to which the concrete may be subjected at the time of
striking.
The strength referred to shall be that of concrete using the same cement and
aggregates, with the same proportions, and cured under conditions of temperature
and moisture like those existing on the work. Where possible, the formwork should
be left longer, as it would assist the curing.
In normal circumstances (generally where temperatures are above 20 0C), and
where ordinary cement is used, forms may be struck after expiry of following periods.
Type of Form Removal Time Period
Walls, columns, and vertical sides of 24 to 48 hours as may be decided by the
beams engineer-in-charge.
Slabs (props left under) 3 days
Beam soffits (props left under) 7 days
Removal of props to slabs (Spanning up 7 days
to 4.5 m)
Removal of props to slabs (Spanning 14 days
over 4.5 m)
Removal of props to beams and arches 14 days
(Spanning up to 6 m)
Removal of props to beams and arches 21 days
(Spanning over 6 m)
For rapid hardening cement, 3/7 of the above period will be sufficient in all
cases except vertical sides of slabs, beams and columns which should be retained
for 24 hours.
All formworks should be removed without shock or vibration as this would
damage the reinforced concrete. Before the soffit and struts are removed, the
concrete surface should be exposed, where necessary to ascertain that the concrete
has sufficiently hardened. Proper precautions should be taken to allow for the
decrease in the rate of hardening that occurs with all elements in the cold weather.
6|Page
Procedure for form work removal
1. Allow the concrete to dry before removing the forms. ...
2. Remove forms starting at the top of sloping slabs. ...
3. Remove the stakes from the ground that support the forms with a stake
puller to avoid damaging the stakes or the forms.
4. Pull the forms away from the sides of the concrete slab using as little force as
necessary.
Activities
Guided Practice 1
Directions: Put the correct removal time period for each given type of form. Write
your answers on your answer sheet.
Guided Practice 2
Direction: Enumerate the following and Write your answers on your answer sheet.
1.What are the three main functions of curing?
2. What are the main factor to follow regarding the adequate length of curing?
3.Give the procedures on how to remove the form work.
7|Page
Assessment
Directions: Identify the following and write your answers on your answer sheet.
_____________1. Are used to retard or reduce evaporation of moisture from concrete.
They can be clear or translucent and white pigmented.
_____________2. Is typically used to cure flat surfaces on smaller jobs. Care should
be taken to maintain curing water temperature at not more than 20
degrees Fahrenheit cooler than the concrete to prevent cracking due
to thermal stresses.
_____________3. Should not be removed until the concrete has sufficiently hardened
in order that it can carry safely its own weight and any other live
loads it is subjected to.
_____________4. Are used to cover and insulate concrete surfaces subjected to
freezing temperatures during the curing period
_____________5. usually provide satisfactory protection against moisture loss for
formed concrete surfaces. The forms are usually left in place if the
construction schedule allows.
_____________6. Also called as strike-off or stripping of formwork.
_____________7. Are usually used as embedded elements near the surface of concrete
elements. Their purpose is to protect concrete from freezing during
cold weather concreting.
_____________8. Are primarily used by precast concrete producers.
_____________9. Should be used after concrete has hardened enough to prevent
surface damage.
_____________10. Are used when the ambient temperatures are well above freezing
and the humidity is low.
Reflection
Directions: Read and reflect on the following questions, then write your answers on
your answer sheet.
1. What is the important role of curing?
2. Why is it important to follow the procedure in removing concrete formwork?
8|Page
References
Teve Kosmatka et al, Design and Control of Concrete Mixtures, 15th Edition,
EB001, PCA Engineering Bulletin EB 001, Portland Cement Association , Skokie, IL
2002
CIVILBLOG.ORG
WWW.TESDA.com
9|Page
Key to Corrections
REVIEW
1. chalkline
2. wrench
3.plumbob
4. hammer
5. level hose
PRE-TEST
1. T
2. T
3. T
4. T
5. T
GUIDED PRACTICE 1
1. 7 days
2. 3 days
3. 24 to 48 hours
4. 14 days
5. 7 days
6. 14 days
7. 21 days
GUIDED PRACTICE 2
1. 2
2. 1
3. 4
4. 3
ASSESSTMENT
1. applying membrane
2. ponding and immersion
3. form
4. concrete blanket
5. left in place
6. formwork
7. heating coil
8. electrical heated
9. spraying and fogging
10 | P a g e
Acknowledgment
The Schools Division of Zambales would like to express its heartfelt gratitude
to the following, who in one way or the other, have contributed to the successful
preparation, development, quality assurance, printing, and distribution of the
Quarter 2 Guided Learning Activity Kits (GLAKs) in all learning areas across grade
levels as a response to providing the learners with developmentally-appropriate,
contextualized and simplified learning resources with most essential learning
competencies (MELCs)-based activities anchored on the principles of guided learning
and explicit instruction:
First, the Learning Resources (LR) Development Team composed of the writers
and graphic artists for devoting much of their time and exhausting their best efforts
to produce these indispensable learning kits used for the implementation of learning
delivery modalities.
Finally, the parents and other home learning facilitators for giving the learners
the needed guidance and support for them to possibly accomplish the tasks and for
gradually helping them become independent learners.
ACADEMIC TRACK
TECHNICAL-VOCATIONAL-
LIVELIHOOD (TVL) TRACK
SPORTS TRACK