Professional Documents
Culture Documents
Foundry Encode
Foundry Encode
Foundry Encode
12.0 Electrical
12.01 Transformer, 2 MVA Available -
12.02 IDMC Switchgear, 600 A, 5kV 2,244,886 -
12.03 IDMC Switchgear, 400 A, 5kV 1,981,370 -
12.04 Distribution transformer Available -
12.05 Transformer, 50 KVA 69,738 -
12.06 Low voltage switchgear 1,700,507 -
12.07 Station battery and charger 726,794 -
12.08 Motor Control Center #1 346,047 -
12.09 Motor Control Center #2 435,403 -
12.1 Substation - 907,716
12.11 Power distribution - 849,795
12.12 Lighting system - 362,305
12.13 Grounding & Splicing - 202,576
12.14 750 KW Furnace parts/rehab - 540,000
Sub- Total 7,504,745 2,862,392
6,977,026 17,302,538
167,901 416,067
346,673 869,866
718,645 1,783,918
104,803 1,838,080
- 3,111,450
8,315,048 25,321,919
112,034 279,245
99,012 300,296
3,840 1,875,976
3,200 8,000
31,922 344,080
16,192 522,616
80,240 389,964
266,664 1,140,005
66,252 167,255
1,520 3,860
65,368 170,995
101,519 261,085
96,036 239,934
Incl. in rehab cost -
943,799 5,703,761
39,804 606,545
5,440 434,130
Incl. in rehab cost -
508,992 1,272,480
171,694 429,235
725,930 2,742,390
- 53,262
- -
302,062 425,811
47,524 67,582
42,246 62,189
Incl. in rehab cost -
391,832 608,844
- -
- -
- -
- -
- -
- -
- -
- -
308,096 767,360
- 60,000
5,180 -
313,276 858,806
230,710 495,895
860,960 2,162,130
413,203 1,152,216
1,267,425 1,627,425
493,400 493,400
2,174,028 2,913,041
- -
- 2,244,886
- 1,981,370
- -
- 69,738
- 1,700,507
- 726,794
- 346,047
- 435,403
100,096 1,007,812
142,994 992,789
71,497 433,802
47,665 250,241
39,883 579,883
402,135 10,769,272
1,436,880 1,436,880
16,411,966 55,174,179
126,000 126,000
2,816,878 2,816,878
135,000 135,000
- 10,000
20,700 20,700
28,000 28,000
3,126,578 3,136,578
19,538,544 58,310,757
TABLE 6
Equipment List
Item QTY
1.0 Foundry plant building area
1.01 Air Compressor 1
1.02 Overhead crane
1
12.0 Electrical
12.01 Power transformer
1
12.02 Medium voltage
switchgear ( For main
Protection)
1
12.03 Medium voltage
switchgear (For furnace)
1
12.04 Distribution
transformer
3
12.05 Lighting transformer
1
12.06 Low voltage
switchgear
1
12.07 Station battery and
1
Automatic Battery charger
for 120 VDC Station battery
1
12.08 Motor control center
no. 1 (Foundry plant)
1
12.09 Motor control centr
no. 2 (Found Plant)
1
TABLE 6
Equipment List
Description
area
Screw type, 420 CFM capacity, 125 PSIG output pressure
Crab type, 10 tons capacity, 18.29 m span, 10.91 m lifting height with pendant control
switch and double box girder type bridge
14" diameter x 20' long complete with bearing and sprocket driven by 5.5 KW motor
10" W Belt x 34" long x 10.45 m high complete with bearings, belt bucket, sprocket,
pulleys and take-up frame driven by 3.5 KW motor
24" W Belt x 18.62 m long complete with bearings, belt, pulleys, idlers, sprockets and
frame driven by 5.5 KW, 60 Hz geared motor
24" W Belt x 6.3 m long complete with bearings, belt, pulleys, idlers, sprockets and
frame driven by 2.2 KW motor
18" W Belt x 4.22 m long complete with bearings, belt, pulleys, rollers, sprockets and
frame driven by 3 KW motor
Crab type, 10 ton capacity, 18.29 m span, 10.91 m lifting height with pendant control
switch and monorail type bridge
750 KW, 440 V inductinig furnace complete with auxiliary motors and controls
750 KW, 2300V inductinig furnace complete with auxiliary motors and controls
1170 li/min capacity with 520 CFM air fan driven by 2.25 KW
Centrifugal type, 150 GPM capacity, 230 TDH, driven by 18.5 KW motor
Crab type, 5 tons capacity, 18.29 m span, 10.91 lifting with pendant control switch and
double box girder type bridge
Mhar brand, 440V, 3 phase with 350 CFM blower, 1/2 HP fuel pump, 7.5 KW bogie
drive and combustion control and accessories
1 Hp drive motor
2500 KVA, 3 phase, 60 Hz, 13,800-2400 for outdoor distribution 90KV BIL HV, 60 kV BIL
LV with +2 - 2-1/2% taps above and below normal voltage. This unit shall be consists of
top mounted HV bushings with connectors for ACSR & side mounted LV cable boxes
with connectors for copper conductor.
600 AT/600 AF, 5 kV, 3 PST, 100 KVAIC, Indooor metal clad in NEMA I free standing
enclosure. Breaker shall be either air-insulated (ACB) or vacuum breakers in drawn-out
type mounting. Protective relays & watthour meters shall be draw-out type.
Instruments shall be semi-flushed mounted.
400 AT/400 AF, 5 kV, 3 PST, 100 KVAIC, Indoor metal clad in NEMA I free stNDING
ENCLOSURE. Braker shall be either air-insulated (ACB) or vacuum breakers in drawn-out
type mounting. Protective relays & watthour meters shall be draw-out type. Instrument
shall be semi-flushed mounted.
333 KVA, 1 phase, 60 Hz, 4160Y/2400-460V, for outdoor distribution, 60 kV BIL HV & LV
with +2 - 2-1/2% taps above and below normal voltage. This unit shall consists of top
mounted HV bushings and side mounted LV cable boxes with connectors for copper
conductors.
120 VDC, nominal voltage, lead acid type in non-transparent plastic container complete
w/ connectors between coils. Battery shall have an 8 hour discharge rating fromfully
charged condition. Includes Hudrometer & thermometer for the electrolyte
230 VAC supply, 1 phase, 60 Hz. Output shall be adjustable from 1 to 10A. When the
battery is fully charged, the charger shall automatically change to trickle charging. It
shall include the following: a) Fused swtich on
AC side b) Pilot light to
indicate as voltage c) Fused switch
on DC side d) DC
ammeter to indicate charging rate e) DC
voltmeter w/ transfer switch to indicate either battery voltage or charger voltage
f) Adjustable resistor
or device operated from the front to adjust charging rate
460V, 3 phase, 60 Hz, indoor type in NEMA I free standing 1
- Instrument, metering & bus entrnace compartment 1-
Main breaker, 3 pole, 600 AT/600 AF, 85 KAIC
Branch circuits:
1 set - Combination circuit breaker & magnetic starter, auto-transformer type, 250
AT/400 AF MCCB, 42 KAIC & NEMA 2 FVNR, for 75 Hp motor 1 set -
Combination circuit breaker & magnetic starter, auto-transformer type, 150 AT/225 AF
MCCB, 42 KAIC & NEMA 3 FVNR, for 40 Hp motor 2 Sets - Combination
circuit breaker & magnetic starter, 60 AT/100 AF MCCB, 42 KAIC & NEMA 2 FVNR, for
15 Hp motor 5 sets - Combination circuit
breaker & magnetic starter, 30 AT/50 AF MCCB, 42 KAIC & NEMA I FVNR, for 7.5 Hp
motor 2 sets - Combination circuit breaker &
magnetic starte, 20 AT/50 AF MCCB, 42 KAIC & NEMA 0 FVNR, for 5.0 Hp motor
1 set - Combination circuit breaker & magnetic
starter, auto-transformer type, 15 AT/50 AF MCCB, 42 KAIC & NEMA 0 FVNR, for 3.0 Hp
motor 2 sets - Combination circuit breaker & magnetic starter,
auto-transformer type, 15 AT/50 AF MCCB, 42 KAIC & NEMA 00 FVNR, for 2.0 Hp motor
1 set - Combination circuit breaker & magnetic starter, auto-transformer
type, 15 AT/50 AF MCCB, 42 KAIC, 3 poles 2
units - Molded case circuit breaker, 60 AT/100 AF, 42 KAIC, 3 poles 2 units -
Molded case sircuit breaker, 150 AT/225 AF, 42 KAIC, 3 poles Instrument
compartment will consists of ammeter, voltmeter, kilowatt-hour meter, associated
transfer switches. Each branch circuit shall consists push buttons and pilot lights.
460V, 3 phase, 60 Hz, indoor type in NEMA I free standing 1
- Instrument, metering & bus entrnace compartment 1-
Main breaker, 3 pole, 600 AT/600 AF, 85 KAIC Branch
circuits: 1 set -
Combination circuit breaker & magnetic starter, auto-transformer type, 250 AT/400 AF
MCCB, 42 KAIC & NEMA 2 RVNR, for 50 Hp motor 2 sets - Combination circuit
breaker & magnetic starter, auto-transformer type, 175 AT/225 AF MCCB, 42 KAIC &
NEMA 3 FVNR, for 50 Hp motor 2 sets - Combination circuit breaker &
magnetic starter, 100 AT/100 AF MCCB. 42 KAIC & NEMA 3 FVNR, for 30 Hp motor
1 set - Combination circuit breaker & magnetic starter, 100
AT/100 AF MCCB, 42 KAIC & NEMA 2 FVNR, for 25 Hp motor
2 sets - Combination circuit breaker & magnetic starter 60 AT/100 AF
MCCB, 42 KAIC & NEMA 2 FVNR, for 15 Hp motor
5 sets - Combination circuit breaker & magnetic starter, auto-transformer type, 40
AT/50 AF MCCB, 42 KAIC & NEMA 1 FVNR, for 10 Hp motor 3 sets -
Combination circuit breaker & magnetic starter, auto-transformer type, 15 AT/50 AF
MCCB, 42 KAIC & NEMA 0 FVNR, for 3.0 Hp motor 4 sets - Combination
circuit breaker & magnetic starter, auto-transformer type, 15 AT/50 AF MCCB, 42 KAIC
& NEMA 0 FVNR, for 1.0 Hp motor 2 units - Molded case circuit breaker,
60 AT/100 AF, 42 KAIC, 3 poles 2 units - Molded case circuikt breaker,
150 AT/225 af, 42 KAIC, 3 poles Instrument compartment will consists of
ammeter, voltmeter, kilowatt-hour meter, associated transfer switches. Each branch
circuit shall consists push buttons and pilot lights.
Remarks
New
New
New
Available
New
New
Available
New
New
New
New
New
New
New
New
Available
New
New
New
New
New
New
Available
Available
New
New
Available
Available
Available
Available
Available
New
Available
Available
Available
New
New
New
Available
New
New
Available
New
New
New
New
New
New
Table 3
CASHFLOW PLAN
PROJECTE
ACTIVITIES 1
1 Foundry plant building area 3,514,200
2 Sand handling area -
3 Furnace area -
4 Heat treatment/control room area -
5 Finishing area -
6 Office & change room -
7 Shop & storage area -
8 Ferro-alloy area -
9 Water supply -
10 Drainage canal -
11 Service road -
12 LMD equipment relocation/rehab 728,260
13 Electrical -
14 Equipment purchase/installation 5,828,790
15 Construction/overhead 522,763
TOTAL 10,594,013
Table 3
CASHFLOW PLAN
PROJECTED MONTHLY CASH FLOW (PESOS)
2 3 4 5 6
3,514,200 3,514,201 3,514,201 3,514,201 -
- 592,898 592,898 592,898 592,899
- 411,225 411,225 411,226 -
- 453,706 453,706 453,706 453,707
- - 185,194 185,194 185,194
- - 138,689 138,689 138,689
- 289,955 289,955 289,956 -
- - 289,959 289,959 -
- - 399,403 399,403 -
- - 247,947 247,948 -
- - - 1,081,065 1,081,065
728,260 728,261 728,261 - -
652,905 652,905 652,905 652,906 652,906
5,828,790 6,307,749 478,960 478,960
522,763 522,763 522,763 522,763 522,763
58,310,757
Table 4
Unit cost of construction summary
Description Unit
Reinforced concrete, Class A (installed) Pesos per cubic meter
Plain concrete 1:2:4 (installed) Pesos per cubic meter
Structural steel and tanks (installed) Pesos per kilogram
Excavation Pesos per cubic meter
Perimeter Fence Pesos per meter
Equipment installation Pesos per tonne
Pipe (installed):
400 mm diameter Pesos per linear meter
350 mm diameter Pesos per linear meter
300 mm diameter Pesos per linear meter
250 mm diameter Pesos per linear meter
200 mm diameter Pesos per linear meter
150 mm diameter Pesos per linear meter
100 mm diameter Pesos per linear meter
Painting, installed per coat
Roofing including accessories, installed Pesos per square
Siding, installed meter
Carpentry — ceiling board, installed Pesos per square
Form works meter
Gratings, installation Pesos per square
Gate Valves, Installation cost: meter
350 mm diameter Pesos per square
250 mm diameter meter
150 mm diameter Pesos per square
100 mm diameter meter
Value
8,000
4,000
65
160
2,300
12,000
9,300
7,100
4,600
3,100
2,400
1,850
1,050
33
600
650
510
1,038
27
4,500
2,500
1,900
1,500
TABLE 1A
FINANCIAL ANALYSIS AT VARIABLE SELLING PR
ITEM YEAR 0 YEAR 1 YEAR 2 YEAR 3 YEAR 4
MONTHLY PRODUCTION 0.80 35,000 135,000 200,000 200,000
SELLING COST PER KG(P) 62.50 50.00 50.00 50.00 50.00
PROJECT IRR 5%
PAYBACK PERIOD (YEAR) 7.62
TABLE 1A
NALYSIS AT VARIABLE SELLING PRICE
YEAR 5 YEAR 6 YEAR 7 YEAR 8 YEAR 9 YEAR 10 TOTAL
200,000 200,000 200,000 200,000 200,000 200,000 1,770,000
50.00 50.00 50.00 50.00 50.00 50.00
The manpower requirements of the proposed Foundry Plant during the 1st year of operation is estimated at 23 men.
As production increases on the 2nd year, the manpower required will be 51 men. It is expected to reach and normalize
at 60 men on then 3rd to the 10th year depending on the market demand. Table 2 shows the manpower requirement
of the project as well as the manpower distriibution.
TABLE 2
MANPOWER REQUIRMENTS
NO DESIGNATION YEAR 1 YEAR 2
PRODUCTION (TONNE/MONTH) 35 135
1 Foundry manager 1 1
2 Secretary 1 1
3 Salesman 1 1
4 Draftsman/estimator 1 1
5 Warehouseman foundry foreman 1 1
6 Foundry foreman 1 1
7 Foundry shift supervisors 0 2
8 Quality control supervisor 1 1
9 Production planning and control 0 1
10 Quality control technician 1 3
11 Foundry leadman 1 5
12 Foundryman A 8 8
13 Foundryman B 2 10
14 Finishing/heat treatment/machining 0 9
15 Patternmaker 1 3
16 Plant mechanic/electrician
17 Security guard 3 3
SUB-TOTAL 23 51
YEAR 3
200
1
1
1
1
1
1
2
1
1
3
5
8
19
9
3
3
60
42.30% 64,569.89
217,217.38
6.21
42.30% 127,652.00
429,429.49
3.18
42.30% 139,860.00
470,497.49
2.35
CAPITAL EXPENDITURE
The total capital requirement of the Foundry Project is FIFTY EIGHT MILLION THREE HUNDRED TEN THOUSAND EIGHT HUNDR
Equipment = P17,486,369.00
Material = 21,286,844.00
Labor = 19,538,544.00
Total = P58,310,800.00
The project capital cost were estimated based on the general layout, flowsheets, specifications, quotations from suppliers, in-h
The projected monthly cash flow requirements for the six months construction period is shown in Table 3.
Table 4 shows the unit cost of construction used in the cost estimate. The equipment list is shown in table 5.
The capital cost summary is shown in Table 6. The equipment cost is shown in Table 7. The material and labor cost estimate is
D TEN THOUSAND EIGHT HUNDRED PESOS(P 58,310,800.00) summarized as follows:
ns, quotations from suppliers, in-house knowledge of construction cost and productivities experienced in the foundry and construction ind
wn in Table 3.
hown in table 5.
aterial and labor cost estimate is shown in Tbale 8. The Equipment capital and installation cost estimate is shown in Table 9.
e foundry and construction industry.
hown in Table 9.
ITEM DESCRIPTION QUANTITY
14.0 CONSTRUCTION OVERHEAD
PROJECT MANAGEMENT (6 MONTHS)
14.01
Manager = 15% x P100,000.00 x 6 months
Others = 15% x P40,000.00 x 6 months
14.05 TRANSPORTATION
Rental 18 days
14.06 ACCOMMODATION
Lodging
Meals 20 times
20 tmes
B. LABOR COST
1 - Electrical supervisor 10 days
1 - Electrical capataz 10 days
5 - Lineman/electrician 10 days
4 - Project employee 10 days
Total labor cost
B. LABOR COST
1 - Electrical capataz 20 days
3 - Lineman/electrician 20 days
TOTAL ELECTRICAL
P 90,000.00
36,000.00
P 126,000.00
170 P 7,140.00
2,000.00 12,000.00
5.53 2,797,738.00
P 2,816,878.00
P 135,000.00
P 10,000.00
1,150.00 P 20,700.00
900.00 18,000.00
500.00 10,000.00
p 28,000.00
P 3,136,578.00
963.00 P 9,630.00
510.27 5,103.00
494.64 24,732.00
205.00 8,200.00
P 47,665.00
540,000.00 P 540,000.00
510.27 P 10,205.00
494.64 29,678.00
P 39,883.00
p 3,264,527.00
p 1,436,880.00
P 37,622,046.00
Table 9
Equipment capital and Installation cos
EXTENDED
UNIT COST COSTMEX- OCEAN
EX-WORKS WORKS (US FREIGHT
ITEM DESCRIPTION QTY (US $) $) (US $)
5 FINISHING AREA
Angle grinder 4 214
Welding machine 2
100" Karatsu boring machine 1
48" Niles boring machine 1
Planer/grinder 1
Overhead crane, 5 tons 1
Sub-total 10 214
6 OFFICE & CHANGE ROOM
Optical emiision spectrometer 1
Computer 2
Fire extinguisher 1
Sub-total 4
7 SHOP & STORAGE AREA
Oven 1
Computer 1
Fire extinguisher 1
Sub-total 3
8 WATER SUPPLY
Deep well pump 1
Sub-total 1
9 ELECTRICAL
Power transformer, 2.5 MVA 1
IDMC Switchgear, 600 A, 5 KV 1 34,000 34,000 3,400
IDMC Switchgear, 400 A, 5 KV 1 30,000 30,000 3,000
Distribution transformer, 333 KVA, 1 Ph 3
Transformer, 50 KVA, 460V/220V, 3 Ph 1 1,154 1,154
Low voltage switchgear 1 28,302 28,302
Station battery and charger 1 11,000 11,000 1,100
Motor control center #1, Foundry plant 1 5,705 5,705
Motor control center #2, Foundry plant 1 7,197 7,197
Sub-total 11 117,358 117,358 7,500
Available Available
Available Available
Available Available
Available Available
Available 0 Available
Available 0 Available
- -
59,880
39,600
99,480
14,400
600
9,600
4,200
4,800
32,880
5,280
16,800
7,800
35,160
131,520
91,200
136,800
11,880
6,240
14,040
260,160
11,880
6,240
35,160
60,000
113,280
38,400
1,920
241,200
37,560
31,200
35,160
385,440
960
960
100,440
24,000
24,000
216,000
3,000
26,400
10,200
21,000
21,000
446,040
1,436,880
TABLE 8 MATE
ITEM
1
1.01
B.
2
3
1.02
7
B.
1.03
4
5
B.
1.04
A.
1
2
6
7
1.05
4
5
2.01
2.02
2.03
A
2.04
2.05
2.06
A
B
A
2.09
2.1
2.11
A
2.12
2.12
3
3.01-3.02
3.03
3.04
3.05
B
A
3.06
B
4.01
4.02
4.03
4.04
4.05
5
5.01
5.02
5.03
5.04
5.05
B
6.0
7.0
8.0
1
1
5
4
1
1
5
4
1
1
5
4
TABLE 8 MATERIAL AND LAB
DESCRIPTION
FOUNDRY PLANT BUILDING AREA:
MAIN BUILDING
MATERIAL COST
EARTHWORKS
Excavation
Backfill
Fill Material
CARPENTRY WORKS
Area
TINSMITHRY WORKS
Roof
Cladding
PAINTING WORKS
Area
LABOR COST
EARTHWORKS
Excavation
Backfill
Fill Material
CARPENTRY WORKS
Area
TINSMITHRY WORKS
Roof
Cladding
PAINTING WORKS
Area
OFFICE/CHANGE ROOM:
A. MATERIAL COST
EARTHWORKS
Excavation
Backfill
CARPENTRY WORKS
Area
PAINTING WORKS
Area
EARTHWORKS
Excavation
Backfill
CARPENTRY WORKS
Area
PAINTING WORKS
Area
MATERIAL COST
EARTHWORKS
Excavation
Backfill
CARPENTRY WORKS
Area
TINSMITHRY WORKS
Roofing
Cladding
PAINTING WORKS
Area
LABOR COST
EARTHWORKS
Excavation
Backfill
CARPENTRY WORKS
Area
TINSMITHRY WORKS
Roofing
Cladding
PAINTNG WORKS
Area
MATERIAL COST
EARTHWORKS
Excavation
Backfill
INSMITHRY WORKS
Roofing
Cladding
PAINTING WORKS
Area
CARPENTRY
Area
B. LABOR COST
EARTHWORKS
Excavation
Backfill
TINSMITHRY WORKS
Roofing
Cladding
PAINTING WORKS
Area
AIR COMPRESSOR
A. MATERIAL COST
EARTHWORKS
Excavation
Backfill
CONRETE WORKS
Area
TINSMITHRY WORKS
Roofing
Cladding
PAINTING WORKS
Area
PIPE INSTALLATION
2" dia. x 20' long Sch. 40 Bl Pipe
2" dia. Gate Vlave
2" dia. x 900 Elbow
2" dia. BI Tee
B. LABOR COST
EARTHWORKS
Excavation
CONRETE WORKS
Ärea
TINSMITHRY WORKS
Roofing
Cladding
PAINTING WORKS
Area
PIPE INSTALLATION
2" dia. x 20' long Sch. 40 Bl Pipe
MIX MULLERS
MATERIAL COST
Concrete Works
Steelworks
Painting Works
LABOR COST
Concrete Works
Steelworks
Painting Works
Excavation
Backfill
MATERIAL COST
Concrete Works
Steelworks
Painting Works
Gl Pipe, 1" dia. x 20'
Gl Elbow, 1" dia. x 900
Gate Valve, 1" dia.
LABOR COST
Concrete Works
Steelworks
Painting Works
Excavation and Backfill
I 't Pipe Installation
LABOR COST
Concrete Works
MATERIAL COST
Concrete Works
LABOR COST
Concrete Works
MATERIAL COST
Concrete Works
Steelworks
Painting Works
LABOR COST
Concrete Works
Steelworks
Painting Works
Excavation and Backfill
LABOR COST
Concrete Works
Steelworks
Painting Works
Excavation and Backfill
A. MATERIAL COST
Concrete Works
Steelworks
Painting Works
B. LABOR COST
Concrete Works
Steelworks
Painting Works
Excavation and Backfill
MATERJAL COST
Concrete Works
Steelworks
Painting Works
LABOR COST
Concrete Works
Steelworks
Painting Works
MATERIAL COST
Concrete Works
Steelworks
Painting Works
LABOR COST
Concrete Works
Steelworks
Painting Works
MATERIAL COST
Concrete Works
LABOR COST
Concrete Works
Excavation and Backfill
LABOR COST
Concrete Works
Steelworks
Painting Works
Cylinder Installation
MATERIAL COST
Concrete Works
Steelworks
Painting Works
4" dia. x 24-1/2"
LABOR COST
Concrete Works
Steelworks
Painting Works
long Air Cylinder Gate
Excavation and Backfill
4" dia. Cylinder Installation
MATERIAL COST
Concrete Works
Steelworks
Painting Works
LABOR COST
Concrete Works
Steelworks
Painting Works
Excavation and Backfill
FURNACE SECTION
FURNACE, 2 Tons and 3 Tons
MATERIAL COST
Concrete Works/Foundation
Steelworks/Platforms
LABOR COST
Concrete Worksmoundation
Steelworks/Platforms
Earthworks
Excavation
Backfill
Freight
Dismantling
MATERIAL COST
Concrete Works
Steelworks
LABOR COST
Concrete Works
S teelworks
COOLING TOWER
MATERIAL COST
Concrete Works
LABOR COST
Concrete Works
CENTRIFUGAL
MATERIAL COST
Concrete Works
LABOR COST
Concrete Works
A, MATERIAL COST
Concrete Works
Steelworks
B. LABOR COST
Concrete Works
Steelworks
MATERIAL COST
Concrete Works
LABOR COST
Concrete Works
MATERIAL COST
Concrete Works
Steelworks
LABOR COST
Concrete Works
Steelworks
MATERIAL COST
Concrete Works
Steelworks
LABOR COST
Concrete Works
Steelworks
FINISHING AREA
ANGLE GRINDER
WELDING MACHINE
MATERIAL COST
Concrete Works
Steelworks
Carpentry Works
LABOR COST
Concrete Works
Steelworks
Carpentry Works
Excavation
Backfill
Freight
Dismantling
MATERIAL COST
Concrete Works
Steelworks
Carpentry Works
LABOR COST
Concrete Works
Steelworks
Carpenty Works
Excavation
Freight
Dismantling
PLANER/GRINDER
MATERIAL COST
Concrete Works
Steelworks
Carpentry Works
LABOR COST
Concrete Works
Steelworks
Carpentry Works
Excavation
Freight
Dismantling
WATER SUPPLY
A. MATERIA!, COST
1. EARTHWORKS
Excavation
2. CONRETE WORKS
Volume
3. STRUCTURAL STEELS, A36
Weight
4. PAINTING WORKS
Area
B. LABOR COST
1. EARTHWORKS
Excavation
2. CONRETE WORKS
Volume
3. STRUCTURAL STEELS, A36
Weight
4. PAINTING WORKS
Area
MATERIAL COST
2" dia. x 20' long Sch. 40 Bl Pipe
2" dia. x 90˚ BI elbow
2" dia. Gate valve
2" dia. x Bl Tee
I " dia. x 20' long Sch. 40 Bl Pipe
l" dia. x 900 Gl Elbow
1" dia Gate valve
3/4" dia. x 20' long Sch. 40 GI Pipe
3/4" dias x 90 Gl Elbow
3/4" dia. Gate Valve
3/4" dia. GI Coupling
LABOR COST
2" dim x 20' long Sch. 40 BI Pipe
l" dia. x 20' long Sch. 40 BI Pipe
3/4" dia. x 20' long Sch. 40 GI Pipe
DRAINAGE CANAL
A. MATERIAL COST
1. EARTHWORKS
Excavation
Backfill
LABOR COST
1. EARTHWORKS
Excavation
Backfill
MATERIAL COST
1. EARTHWORKS
Excavation
Backfill
Gravel Ballast
2. CONRÉTE WORKS
Reinforced concrete, Class A
LABOR COST
1. EARTHWORKS
Excavation
Backfill
Gravel Ballast
MATERIAL COST
'FURNACE, 2 Tons
Parts
FURNACE, 3 Tons
Parts
B, LABOR COST
FURNACE, 2 Tons
1 - Electiical Capaiaz
3 - Electrician
FURNACE, 3 Tons
I - Electrical Capataz
3 - Electrician
A. MATERIAL COST
B. LABOR COST
A. MATERIAL COST
B. LABOR COST
Mix Muller, 900 kgs
Shake-out N/lachine,. 2 Tons
Overhead Crane, 5 Tons (3 units)
Overhead Crane, 2 Tons
Furnace, 2 Tons (LMD)
Furnace, 2 Tons ('Ex, AG&P)
3 Tons (Ex, AG P)
Bumer Laddle Pre-healer
100" Karatsu Boring Machine
48" Niles Boring Machine
Planer/Grinder
Power Transformer
Distribution Transformer
ELECTRICAL
12.01 SUBSTATION
A. MATERIAL COST
Terminal lug, compression type, long barrel, 1 hole 300 MCM cable
Terminal lug, compression type, long barrel, 1 hole for 4/0 AWG cable
Top pole insulator, 14 KV class, outdoor mounting
Bolt & nut, stainless steel, 3/8" dia. x 1-1/2" L complete with lock washer
Cable ties, standard, 0.18" W x 12" long, 100 pcs/bag
Nikolite Soldering Bar, 50/50
Soldering Paste
Weatherproof service entrance cap, 80 mm hub size
LABOR COST
Electrical Supervisor
Electrical Capataz
Lineman/Electrician
Project Employee
A. MATERIAL COST
Stranded copper conductor, 150 mm2 THW, 600 VAC, single insulated
Stranded copper conductor, 125 mm2 THW, 600 VAC, single insulated
Stranded copper conductor, 38 mm2 THW, 600 VAC, single insulated 150m/roll
Stranded copper conductor, 22 mm2 THW, 600 VAC, single insulated 150m/roll
Stranded copper conductor, 14 mm2 THW, 600 VAC, single insulated 150m/roll
Power cable, 400 MCM, 5 kV XLPE insulated,
PVC jacketed, single conductor
Royal cable, 80 mm2, 3/C, 600 VAC, 75 m/roll
Royal cable, 5.5 mm2, 3/C, 600 VAC, 75 m/roll
Royal cable, 3.5mm2 3/C, 600 VAC, 75 m/roll
Control cable, stranded, AWG/6C, 600 VAC, colored, 300 m/roll
Rigid steel conduit w/ coupling, 15 mmdia. x 3 m
Rigid steel conduit w/ coupling, 25 mmdia. x 3 m
Rigid steel conduit w/ coupling, 40 mmdia. x 3 m
Rigid Steel Conduit, elbow, 15 mm dia. x 90 degrees
Rigid Steel Conduit, elbow, 25 mm dia. x 90 degrees
Rigid Steel Conduit, elbow, 40 mm dia. x 90 degrees
Rigid Steel Conduit, locknut & bushing, 15 mm dia-
Rigid Steel Conduit, locknut & bushing, 25 mm dia.
Rigid Steel Conduit, locknut & bushing, 40mm dim
Liquid tight flexible conduit w/ PVC cover, 15 mm dia.
Liquid tight flexible conduit w/ PVC cover, 25 mm dia-
Liquid tight flexible conduit w/ PVC cover, 40 mm dia.
Liquid tight flexible conduit connector, straight type, 15 mm C
Liquid tight flexibie conduit connector, straight type, 25 mm
Liquid tight flexible conduit connector, straight type, 40 mm
Condulet bodies, form 85 series, aluminum, threaded type,type LL. 15 mm hub size
Condulet bodies, form 85 series, aluminum, threaded type,type LL. 25 mm hub size
Condulet bodies, form 85 series, aluminum, threaded type,type LL. 40 mm hub size
Terminal lug, compression type, long barrel, one hole in pad for 250 MCM 300 MCM copper
Terminal lug, compression type, long barrel, one hole in pad for #6 - # I AWG copper
Cable ties, miniature, 0.1" width x 6" long, 100 pcs/bag
Cable ties, standard, 0.18" width x 12" long, 100 pcs/bag
Pushbutton station, start-stop w/ indicating light, in NEMA 3R enclosure
Pullbox, GL 4" x 4" x 2" c/w cover & screws
Pullbox, GI, 8" x 8" x 4" c/w cover & screws
Pullbox, GI, 12" x 12" x 6" c/w cover & screws
U-bolt, 1/4" dia. hot dip galvanized steel, for 1/2" dia. pipe complete with nuts & washers
U-bolt, 1/4" dia. hot dip galvanized steel, for 1" dia. pipe complete with nuts & washers
U-bolt, 1/4" dia. hot dip galvanized steel, for 1-1/2" dia. pipe complete with nuts & washers
Cable tray system, Ga. 12 hot dip galvatized steel extruded in channel side rails & structural cross ratngs; it shall include the following
LABOR COST
Electrical Supervisor
Electrical Capataz
Lineman/Electrician
Project Employee
MATERIAL COST
Lighting panelboard, 300V, 2PST, main breaker: 125A, 2 PSI
Wall mounted lumiaire, 400W, 220 V, 60 Hz, Mogul base,high pressure sodium GE-WM7M17MTA1 SN4DB complete HPS lamp
EHB high bay luminaire, open type, pendant mounting, 400W 220V, 60 Hz, Mogul base, metal halide, GE-EHBA25MTA5V6 complete wit
Fluorescent fixture, double, 40W, 220V, 60 Hz, industrial type rapid start c/w reflector & tubes rapid start c/w reflector & tubes
Rigid steel conduit w/ coupling, 15 mm dia. x 3 m
Rigid Steel Conduit, elbow, 15 mm dia. x 90 degrees
Rigid Steel Conduit, locknut & bushing, 15 mm dia.
Royal cable, #12/2c, 600V, 75 m/roll
Junction box, GI 4" x 4" x 2" w/ 1/2" dia. knockcut, complete cover & screws
Watertight strain relief cord grips & connectors, straight type, 15 mm hub size
LABOR COST
Electrical Supervisor
Electrical Capataz
Lineman/Electrician
Project Employee
A. MATERIAL COST
Grounding conductor, 2/0 AWG bare copper, soft drawn
Ground rod, copperweld, 1/2" dia. x 8'
Ground connector, cable to rod
Ground connector, cable to bar
Vinyl electrical tape, 3/4" x 66', 3M-Super 33+D, 10 pcs/carto
Rubber splicing tape, 3/4" x 30" 3M-23, 50 pcs/cartoon
Varnished cambric tape, 3/4N x 60', 3M-2510, 10 pcs/cartoon
Wire marker
QUANTITY UNIT COST TOTAL COST
469 m³
103 m³
469 m³
469 m³
469 m³
469 m³
8.36 cubic meter 4,800.00 P 40,128.00
502 kgs 39.00 19,578.00
P 59,706.00
12 cubic meter
P 2,162,130.00
P 2,913,041.00
P 849,795.00