Foundry Encode

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 115

TABLE 5

CAPITAL COST SUMMARY


Estimated cost, Pesos
Item Description Equipment Material
1.0 Foundry Plant Building Area
1.01 Main Building - 10,325,512
1.02 Office/Change room - 248,166
1.03 Shop/Storage room - 523,193
1.04 Ferro-alloy Storage area - 1,065,273
1.05 Air compressor 1,569,615 163,662
1.06 Overhead Crane, 10 tons 3,111,450 -
Sub- Total 4,681,065 12,325,806

2.0 Sand Handling Area


2.01 Mix Muller Available 167,211
2.02 Air scrubber system 53,125 148,789
2.03 Shake-out machine, 7 T 1,866,376 5,760
2.04 Shake-out machine, 2 T Available 4,800
2.05 Core mix muller 264,516 47,642
2.06 14" dia. X 20' Screw Conveyor 482,976 23,448
2.07 10" W x 34" L Bucket elevator 190,204 119,520
2.08 24" W Conveyor No. 1 473,345 399,996
2.09 24" W Conveyor No. 2 1,625 99,378
2.10 18" W x 20 Single trough conveyor Available 2,160
2.11 Bin No. 1, 15 tons - 105,627
2.12 Bin No. 2, 15 tons - 159,566
2.13 Bin No. 3, 8 tons - 143,898
2.14 Overhead crane bridge, 5 tons Available Incl. in rehab cost
Sub- Total 3,332,167 1,427,795

3.0 Furnace area


3.01 2 Tons furnace Available Incl. in rehab cost
3.02 3 Tons furnace Available 476,511
3.03 Sump & make-up water tank - 94,869
3.04 Burner Laddle Pre-heater Available -
3.05 Cooling tower 507,035 40,128
3.06 Centrifugal Pump 420,530 4,800
3.07 Overhead crane, 2 tons Available Incl. in rehab cost
Sub- Total 927,565 616,308

4.0 Control room/heat treatment area


4.01 Cooling tower 507,035 59,706
4.02 Centrifugal water pump 420,530 8,160
4.03 Overhead crane, 5 T Available Incl. in rehab cost
4.04 Heat treatment oven Available 763,488
4.05 Quenching and water tank - 257,541
Sub- Total 927,565 1,088,895

5.0 Finishing area


5.01 Angle grinder 53,262 -
5.02 Welding Machine Available -
5.03 100" Karatsu Boring machine Available 123,749
5.04 48" Niles boring machine Available 20,058
5.05 Planer/Grinder Available 19,943
5.06 Overhead crane, 5 T Available Incl. in rehab cost
Sub- Total 53,262 163,750

6.0 Office & Change room


6.01 Computer units, 2 units Available -
6.02 Optical emission spectrometer/lab Available -
6.03 Fire extinguisher Available -
Sub- Total - -

7.0 Shop and storage area


7.01 Oven Available -
7.02 Electric drill Available -
7.03 Electric planer Available -
Sub- Total - -

8.0 Water supply


8.01 5.70 x 6.0 m High water tank - 459,264
8.02 Deep well pump 60,000 -
8.03 Water lines - 26,266
Sub- Total 60,000 485,530

9.0 Drainage canal - 2,665,185

10.0 Service road - 1,301,170

11.0 Equipment relocation / rehab


11.01 Equipment rehab - 739,013
11.02 Dismantling cost - -
11.03 Equipment relocation - -
Sub- Total - 739,013

12.0 Electrical
12.01 Transformer, 2 MVA Available -
12.02 IDMC Switchgear, 600 A, 5kV 2,244,886 -
12.03 IDMC Switchgear, 400 A, 5kV 1,981,370 -
12.04 Distribution transformer Available -
12.05 Transformer, 50 KVA 69,738 -
12.06 Low voltage switchgear 1,700,507 -
12.07 Station battery and charger 726,794 -
12.08 Motor Control Center #1 346,047 -
12.09 Motor Control Center #2 435,403 -
12.1 Substation - 907,716
12.11 Power distribution - 849,795
12.12 Lighting system - 362,305
12.13 Grounding & Splicing - 202,576
12.14 750 KW Furnace parts/rehab - 540,000
Sub- Total 7,504,745 2,862,392

13.0 Equipment installation - -

TOTAL 17,486,369 21,275,844

14.0 Construction overhead


14.01 Project management - -
14.02 Overhead cost - -
14.03 Security services - -
14.04 Office supplies - 10,000
14.05 Transportation - -
14.06 Accommodation - -
Sub- Total - 10,000

Grand Total 17,486,369 21,285,844


d cost, Pesos
Labor Total

6,977,026 17,302,538
167,901 416,067
346,673 869,866
718,645 1,783,918
104,803 1,838,080
- 3,111,450
8,315,048 25,321,919

112,034 279,245
99,012 300,296
3,840 1,875,976
3,200 8,000
31,922 344,080
16,192 522,616
80,240 389,964
266,664 1,140,005
66,252 167,255
1,520 3,860
65,368 170,995
101,519 261,085
96,036 239,934
Incl. in rehab cost -
943,799 5,703,761

Incl. in rehab cost -


524,170 1,000,681
63,246 158,115
- -
26,752 573,915
3,200 428,530
Incl. in rehab cost -
617,368 2,161,241

39,804 606,545
5,440 434,130
Incl. in rehab cost -
508,992 1,272,480
171,694 429,235
725,930 2,742,390

- 53,262
- -
302,062 425,811
47,524 67,582
42,246 62,189
Incl. in rehab cost -
391,832 608,844

- -
- -
- -
- -

- -
- -
- -
- -

308,096 767,360
- 60,000
5,180 -
313,276 858,806

230,710 495,895

860,960 2,162,130

413,203 1,152,216
1,267,425 1,627,425
493,400 493,400
2,174,028 2,913,041

- -
- 2,244,886
- 1,981,370
- -
- 69,738
- 1,700,507
- 726,794
- 346,047
- 435,403
100,096 1,007,812
142,994 992,789
71,497 433,802
47,665 250,241
39,883 579,883
402,135 10,769,272

1,436,880 1,436,880

16,411,966 55,174,179

126,000 126,000
2,816,878 2,816,878
135,000 135,000
- 10,000
20,700 20,700
28,000 28,000
3,126,578 3,136,578

19,538,544 58,310,757
TABLE 6
Equipment List
Item QTY
1.0 Foundry plant building area
1.01 Air Compressor 1
1.02 Overhead crane
1

2.0 Sand handling area


2.01 Mix Muller 1
2
2.02 Air scrubber or wet
dust collector
1
2.03 Shake out machine 1
2.04 Shake out machine 1
2.05 Core mix muller 1
2.06 Screw conveyor
1
2.07 Bucket elavator
1
2.08 Belt Conveyor No. 1
1
2.09 Belt Conveyor No. 2
1
2.10 Single trough
conveyor
1
2.11 Overhead crane
1

3.0 Furnace area


3.01 Furnace, 2 tons 1
3.02 Furnace, 3 tons 1
3.03 Burner Laddle Pre-
Heater
2
3.04 Cooling tower 1
3.05 Water Pump
2
3.06 Overhead crane
1

4.0 Control room/heat


treatment area
4.01 Cooling tower 1
4.02 Water pump 2
4.03 Overhead crane
1
4.04 Heat treatment oven
1

5.0 Finishing area


5.01 Angle grinder 4
5.02 Welding machine 2
2
1
5.03 Boring machine
1
5.04 Boring machine
1
5.05 Planer/Grinder
1
5.06 Overhead crane
1

6.0 Office & Change room


area
6.01 Optical emission
spectrometer and
accessories
1
6.02 King Brinell Hardness
tester
1
6.03 Metallurgical
microscope
1

7.0 Shop & storage area


7.01 Electric drill 1
7.01 Electric planer 1

8.0 Water supply


8.01 Deepwell pump 1

12.0 Electrical
12.01 Power transformer

1
12.02 Medium voltage
switchgear ( For main
Protection)

1
12.03 Medium voltage
switchgear (For furnace)

1
12.04 Distribution
transformer

3
12.05 Lighting transformer
1
12.06 Low voltage
switchgear

1
12.07 Station battery and

1
Automatic Battery charger
for 120 VDC Station battery

1
12.08 Motor control center
no. 1 (Foundry plant)

1
12.09 Motor control centr
no. 2 (Found Plant)

1
TABLE 6
Equipment List
Description
area
Screw type, 420 CFM capacity, 125 PSIG output pressure
Crab type, 10 tons capacity, 18.29 m span, 10.91 m lifting height with pendant control
switch and double box girder type bridge

750 kg capacity, Model MS-2FG driven by 30 KW, 220V/440V motor


450 kg capacity, Model1-1/2 FG driven by 15 KW motor
Model FDC-7, with 5.5 KW Exhauster motor, 70mCFM capacity, 250 mm Hg air
pressure, 0.4 KW pump motor and 500 liters water tank capacity
7000 kg capacity, Model SHO-7 driven by 7.5+D25 KW, 220V/440V motor
2000 kg capacity, Model SHO-15 driven by 11 KW, 220V/440V motor
100 kg Model MS-0.5S driven by 2.2 KW, 220V/440V motor

14" diameter x 20' long complete with bearing and sprocket driven by 5.5 KW motor
10" W Belt x 34" long x 10.45 m high complete with bearings, belt bucket, sprocket,
pulleys and take-up frame driven by 3.5 KW motor
24" W Belt x 18.62 m long complete with bearings, belt, pulleys, idlers, sprockets and
frame driven by 5.5 KW, 60 Hz geared motor
24" W Belt x 6.3 m long complete with bearings, belt, pulleys, idlers, sprockets and
frame driven by 2.2 KW motor
18" W Belt x 4.22 m long complete with bearings, belt, pulleys, rollers, sprockets and
frame driven by 3 KW motor
Crab type, 10 ton capacity, 18.29 m span, 10.91 m lifting height with pendant control
switch and monorail type bridge

750 KW, 440 V inductinig furnace complete with auxiliary motors and controls
750 KW, 2300V inductinig furnace complete with auxiliary motors and controls

Low pressure type, Series 580


1170 li/min capacity with 520 CFM air fan driven by 2.25 KW motor
Centrifugal type, 150 GPM capacity, 230 TDH, horizontal, driven by 18.5 KW motor
Trolley type, 2 tons capacity, 6.05 m span, 7.5 lifting with pendant control switch and
double box girder

1170 li/min capacity with 520 CFM air fan driven by 2.25 KW
Centrifugal type, 150 GPM capacity, 230 TDH, driven by 18.5 KW motor
Crab type, 5 tons capacity, 18.29 m span, 10.91 lifting with pendant control switch and
double box girder type bridge
Mhar brand, 440V, 3 phase with 350 CFM blower, 1/2 HP fuel pump, 7.5 KW bogie
drive and combustion control and accessories

8" diameter x 6000 RPM


400 amperes capacity
600 amperes capacity
1500 amperes capacity
Karatsu vertical type boring machine, 100" complete with auxiliaries and controls, 11
KW table motor, 20 HP rail and drive motor, 220V, 3 phase, 60Hz
Niles vertical boring machine, 48' complete with 30 Hp table motor, 15 Hp rail motor
and controls, 440V, 3 phase, 60 Hz
Machine with 20 Hp Hydro pump motor, 25 Hp grinder motor, 5 Hp head motor, all
440V, 3 phase, 60 Hz
Crab type, 5 tons capacity, 18.29 m span, 10.91 lifting with pendant control switch and
doule box girder type bridge
Makita brand electric drill, 1125 RPM, 220V
Electric driven, 220V

1 Hp drive motor

2500 KVA, 3 phase, 60 Hz, 13,800-2400 for outdoor distribution 90KV BIL HV, 60 kV BIL
LV with +2 - 2-1/2% taps above and below normal voltage. This unit shall be consists of
top mounted HV bushings with connectors for ACSR & side mounted LV cable boxes
with connectors for copper conductor.

600 AT/600 AF, 5 kV, 3 PST, 100 KVAIC, Indooor metal clad in NEMA I free standing
enclosure. Breaker shall be either air-insulated (ACB) or vacuum breakers in drawn-out
type mounting. Protective relays & watthour meters shall be draw-out type.
Instruments shall be semi-flushed mounted.

400 AT/400 AF, 5 kV, 3 PST, 100 KVAIC, Indoor metal clad in NEMA I free stNDING
ENCLOSURE. Braker shall be either air-insulated (ACB) or vacuum breakers in drawn-out
type mounting. Protective relays & watthour meters shall be draw-out type. Instrument
shall be semi-flushed mounted.

333 KVA, 1 phase, 60 Hz, 4160Y/2400-460V, for outdoor distribution, 60 kV BIL HV & LV
with +2 - 2-1/2% taps above and below normal voltage. This unit shall consists of top
mounted HV bushings and side mounted LV cable boxes with connectors for copper
conductors.

50 KVA, 460-220/110V, 3 phase, dry type


480V, 3 phase, 60 Hz, 85 KAIC indoor type in NEMA I free standing enclosure. It shall
consists of the following: I -
Instrument, metering & bus entrance compartment I - Main
breaker, 3 pole, 2000 AT/2500 AF with short and long time delay pick-up
5 - Feeder breakers, 800
AT/800 AF, 3 Phase with short and long time delay pick-up
Each breaker shall draw-out mounted
fitted with disconnecting devices. Instrument compartment will consist of ammeter,
voltmeter, kilovar meter, PF meter and kilowatt-hour meter. Breakers shall be manually
operated with stored energy mechanisms. "SEIMENS" model.

120 VDC, nominal voltage, lead acid type in non-transparent plastic container complete
w/ connectors between coils. Battery shall have an 8 hour discharge rating fromfully
charged condition. Includes Hudrometer & thermometer for the electrolyte

230 VAC supply, 1 phase, 60 Hz. Output shall be adjustable from 1 to 10A. When the
battery is fully charged, the charger shall automatically change to trickle charging. It
shall include the following: a) Fused swtich on
AC side b) Pilot light to
indicate as voltage c) Fused switch
on DC side d) DC
ammeter to indicate charging rate e) DC
voltmeter w/ transfer switch to indicate either battery voltage or charger voltage
f) Adjustable resistor
or device operated from the front to adjust charging rate
460V, 3 phase, 60 Hz, indoor type in NEMA I free standing 1
- Instrument, metering & bus entrnace compartment 1-
Main breaker, 3 pole, 600 AT/600 AF, 85 KAIC
Branch circuits:
1 set - Combination circuit breaker & magnetic starter, auto-transformer type, 250
AT/400 AF MCCB, 42 KAIC & NEMA 2 FVNR, for 75 Hp motor 1 set -
Combination circuit breaker & magnetic starter, auto-transformer type, 150 AT/225 AF
MCCB, 42 KAIC & NEMA 3 FVNR, for 40 Hp motor 2 Sets - Combination
circuit breaker & magnetic starter, 60 AT/100 AF MCCB, 42 KAIC & NEMA 2 FVNR, for
15 Hp motor 5 sets - Combination circuit
breaker & magnetic starter, 30 AT/50 AF MCCB, 42 KAIC & NEMA I FVNR, for 7.5 Hp
motor 2 sets - Combination circuit breaker &
magnetic starte, 20 AT/50 AF MCCB, 42 KAIC & NEMA 0 FVNR, for 5.0 Hp motor
1 set - Combination circuit breaker & magnetic
starter, auto-transformer type, 15 AT/50 AF MCCB, 42 KAIC & NEMA 0 FVNR, for 3.0 Hp
motor 2 sets - Combination circuit breaker & magnetic starter,
auto-transformer type, 15 AT/50 AF MCCB, 42 KAIC & NEMA 00 FVNR, for 2.0 Hp motor
1 set - Combination circuit breaker & magnetic starter, auto-transformer
type, 15 AT/50 AF MCCB, 42 KAIC, 3 poles 2
units - Molded case circuit breaker, 60 AT/100 AF, 42 KAIC, 3 poles 2 units -
Molded case sircuit breaker, 150 AT/225 AF, 42 KAIC, 3 poles Instrument
compartment will consists of ammeter, voltmeter, kilowatt-hour meter, associated
transfer switches. Each branch circuit shall consists push buttons and pilot lights.
460V, 3 phase, 60 Hz, indoor type in NEMA I free standing 1
- Instrument, metering & bus entrnace compartment 1-
Main breaker, 3 pole, 600 AT/600 AF, 85 KAIC Branch
circuits: 1 set -
Combination circuit breaker & magnetic starter, auto-transformer type, 250 AT/400 AF
MCCB, 42 KAIC & NEMA 2 RVNR, for 50 Hp motor 2 sets - Combination circuit
breaker & magnetic starter, auto-transformer type, 175 AT/225 AF MCCB, 42 KAIC &
NEMA 3 FVNR, for 50 Hp motor 2 sets - Combination circuit breaker &
magnetic starter, 100 AT/100 AF MCCB. 42 KAIC & NEMA 3 FVNR, for 30 Hp motor
1 set - Combination circuit breaker & magnetic starter, 100
AT/100 AF MCCB, 42 KAIC & NEMA 2 FVNR, for 25 Hp motor
2 sets - Combination circuit breaker & magnetic starter 60 AT/100 AF
MCCB, 42 KAIC & NEMA 2 FVNR, for 15 Hp motor
5 sets - Combination circuit breaker & magnetic starter, auto-transformer type, 40
AT/50 AF MCCB, 42 KAIC & NEMA 1 FVNR, for 10 Hp motor 3 sets -
Combination circuit breaker & magnetic starter, auto-transformer type, 15 AT/50 AF
MCCB, 42 KAIC & NEMA 0 FVNR, for 3.0 Hp motor 4 sets - Combination
circuit breaker & magnetic starter, auto-transformer type, 15 AT/50 AF MCCB, 42 KAIC
& NEMA 0 FVNR, for 1.0 Hp motor 2 units - Molded case circuit breaker,
60 AT/100 AF, 42 KAIC, 3 poles 2 units - Molded case circuikt breaker,
150 AT/225 af, 42 KAIC, 3 poles Instrument compartment will consists of
ammeter, voltmeter, kilowatt-hour meter, associated transfer switches. Each branch
circuit shall consists push buttons and pilot lights.
Remarks

New
New

New
Available
New

New
Available
New
New

New

New

New

New

New

New
Available
New

New
New

New

New
New
Available

Available

New
New
Available
Available
Available

Available

Available

New

Available

Available
Available

New
New

New

Available

New

New

Available

New
New

New

New
New
New
Table 3
CASHFLOW PLAN
PROJECTE
ACTIVITIES 1
1 Foundry plant building area 3,514,200
2 Sand handling area -
3 Furnace area -
4 Heat treatment/control room area -
5 Finishing area -
6 Office & change room -
7 Shop & storage area -
8 Ferro-alloy area -
9 Water supply -
10 Drainage canal -
11 Service road -
12 LMD equipment relocation/rehab 728,260
13 Electrical -
14 Equipment purchase/installation 5,828,790
15 Construction/overhead 522,763

TOTAL 10,594,013
Table 3
CASHFLOW PLAN
PROJECTED MONTHLY CASH FLOW (PESOS)
2 3 4 5 6
3,514,200 3,514,201 3,514,201 3,514,201 -
- 592,898 592,898 592,898 592,899
- 411,225 411,225 411,226 -
- 453,706 453,706 453,706 453,707
- - 185,194 185,194 185,194
- - 138,689 138,689 138,689
- 289,955 289,955 289,956 -
- - 289,959 289,959 -
- - 399,403 399,403 -
- - 247,947 247,948 -
- - - 1,081,065 1,081,065
728,260 728,261 728,261 - -
652,905 652,905 652,905 652,906 652,906
5,828,790 6,307,749 478,960 478,960
522,763 522,763 522,763 522,763 522,763

11,246,918 13,473,663 9,508,066 9,860,874 3,627,223


TOTAL COST
17,571,003
2,371,593
1,233,676
1,814,825
555,582
416,067
869,866
1,783,918
798,806
495,895
2,162,130
2,913,042
3,264,527
18,923,249
3,136,578

58,310,757
Table 4
Unit cost of construction summary
Description Unit
Reinforced concrete, Class A (installed) Pesos per cubic meter
Plain concrete 1:2:4 (installed) Pesos per cubic meter
Structural steel and tanks (installed) Pesos per kilogram
Excavation Pesos per cubic meter
Perimeter Fence Pesos per meter
Equipment installation Pesos per tonne
Pipe (installed):
400 mm diameter Pesos per linear meter
350 mm diameter Pesos per linear meter
300 mm diameter Pesos per linear meter
250 mm diameter Pesos per linear meter
200 mm diameter Pesos per linear meter
150 mm diameter Pesos per linear meter
100 mm diameter Pesos per linear meter
Painting, installed per coat
Roofing including accessories, installed Pesos per square
Siding, installed meter
Carpentry — ceiling board, installed Pesos per square
Form works meter
Gratings, installation Pesos per square
Gate Valves, Installation cost: meter
350 mm diameter Pesos per square
250 mm diameter meter
150 mm diameter Pesos per square
100 mm diameter meter
Value
8,000
4,000
65
160
2,300
12,000

9,300
7,100
4,600
3,100
2,400
1,850
1,050

33
600
650
510
1,038
27
4,500
2,500
1,900
1,500
TABLE 1A
FINANCIAL ANALYSIS AT VARIABLE SELLING PR
ITEM YEAR 0 YEAR 1 YEAR 2 YEAR 3 YEAR 4
MONTHLY PRODUCTION 0.80 35,000 135,000 200,000 200,000
SELLING COST PER KG(P) 62.50 50.00 50.00 50.00 50.00

MONTHLY REVENUE(P) 1,750,000 6,750,000 10,000,000 10,000,000


YEARLY REVENUE(P) 21,000,000 81,000,000 120,000,000 120,000,000

CAPITAL EXPENDITURE(P) -58,310,757


OPERATING COST
MATERIAL & SUPPLIES COST
SCRAP COST 4.00 4.00 4.00 4.00
FERRO ALLOYS 9.49 9.49 9.49 9.49
MISCELLANEOUS MATLS 8.50 8.50 8.50 8.50
LABOR COST 6.21 3.18 2.35 2.35
POWER COST 5.77/kW-hr 18.00 15.84 20.26 20.26
DELIVERY COST 1.50 1.60 1.50 1.50
SUB-TOTAL 47.70 42.51 46.10 46.10

MONTHLY PRODUCTION COST 1,669,500 5,738,439 9,219,697 9,219,697

YEARLY PRODUCTION COST 20,034,000 68,861,274 110,636,370 110,636,370


DEPRECIATION COST 5,831,076 5,831,076 5,831,076 5,831,076

YEARLY OPERATING COST 25,865,970 74,692,350 116,467,446 116,467,446

NET INCOME BEFORE TAX -4,865,076 6,307,650 3,532,554 3,532,554

INCOME TAX (35%) 1,702,777 -2,207,678 -1,236,394 -1,236,394

NET INCOME -3,162,299 4,099,973 2,296,160 2,296,160

REVENUE AFTER COST -3,162,299 4,099,973 2,296,160 2,296,160

DEPRECIATION 5,831,076 5,831,076 5,831,076 5,831,076


NET CASH FLOW -58,310,757 2,668,777 9,931,049 8,127,236 8,127,236

PROJECT IRR 5%
PAYBACK PERIOD (YEAR) 7.62
TABLE 1A
NALYSIS AT VARIABLE SELLING PRICE
YEAR 5 YEAR 6 YEAR 7 YEAR 8 YEAR 9 YEAR 10 TOTAL
200,000 200,000 200,000 200,000 200,000 200,000 1,770,000
50.00 50.00 50.00 50.00 50.00 50.00

10,000,000 10,000,000 10,000,000 10,000,000 10,000,000 10,000,000


120,000,000 120,000,000 120,000,000 120,000,000 120,000,000 120,000,000 1,062,000,000

4.00 4.00 4.00 4.00 4.00 4.00


9.49 9.49 9.49 9.49 9.49 9.49
8.50 8.50 8.50 8.50 8.50 8.50
2.35 2.35 2.35 2.35 2.35 2.35
20.26 20.26 20.26 20.26 20.26 20.26
1.50 1.50 1.50 1.50 1.50 1.50
46.10 46.10 46.10 46.10 46.10 46.10

9,219,697 9,219,697 9,219,697 9,219,697 9,219,697 9,219,697

110,636,370 110,636,370 110,636,370 110,636,370 110,636,370 110,636,370 973,966,233


5,831,076 5,831,076 5,831,076 5,831,076 5,831,076 5,831,076 58,310,760

116,467,446 116,467,446 116,467,446 116,467,446 116,467,446 116,467,446 1,032,296,993

3,532,554 3,532,554 3,532,554 3,532,554 3,532,554 3,532,554 29,703,007

-1,236,394 -1,236,394 -1,236,394 -1,236,394 -1,236,394 -1,236,394 -10,396,052

2,296,160 2,296,160 2,296,160 2,296,160 2,296,160 2,296,160 19,306,955

2,296,160 2,296,160 2,296,160 2,296,160 2,296,160 2,296,160 19,306,955

5,831,076 5,831,076 5,831,076 5,831,076 5,831,076 5,831,076 58,310,760


8,127,236 8,127,236 8,127,236 8,127,236 8,127,236 8,127,236 77,617,715
MANPOWER REQUIRMENTS

The manpower requirements of the proposed Foundry Plant during the 1st year of operation is estimated at 23 men.
As production increases on the 2nd year, the manpower required will be 51 men. It is expected to reach and normalize
at 60 men on then 3rd to the 10th year depending on the market demand. Table 2 shows the manpower requirement
of the project as well as the manpower distriibution.
TABLE 2
MANPOWER REQUIRMENTS
NO DESIGNATION YEAR 1 YEAR 2
PRODUCTION (TONNE/MONTH) 35 135
1 Foundry manager 1 1
2 Secretary 1 1
3 Salesman 1 1
4 Draftsman/estimator 1 1
5 Warehouseman foundry foreman 1 1
6 Foundry foreman 1 1
7 Foundry shift supervisors 0 2
8 Quality control supervisor 1 1
9 Production planning and control 0 1
10 Quality control technician 1 3
11 Foundry leadman 1 5
12 Foundryman A 8 8
13 Foundryman B 2 10
14 Finishing/heat treatment/machining 0 9
15 Patternmaker 1 3
16 Plant mechanic/electrician
17 Security guard 3 3
SUB-TOTAL 23 51

MANPOWER DISTRIBUTION AT YEAR 1


No. Designation 1st Shift 2nd Shift
1 Foundry manager 1
2 Secretary 1
3 Salesman 1
4 Draftsman/estimator 1
5 Warehouseman 1
6 Foundry foreman 1
7 Foundry shift supervisor 0 0
8 Quality control supervisor 1
9 Production planning and control 0 0
10 Quality control technician 1
11 Foundry leadman 1
12 Foundryman A 8
13 Foundryman B 2
14 Finishing/Heat treatment/Machining 0 0
15 Patternmaker 1
16 Plant mechanic/electrician
17 Security guard 1 1
SUB-TOTAL (Basic) 1 21

OT/VL/SL/13TH MP/BONUS/COLA/PAG-IBIG/SSS/ECC/MED/OTHER BENEFITS

TOTAL LABOR COST


LABOR COST PER KG

MANPOWER DISTRIBUTION AT YEAR 2


No. Designation 1st Shift 2nd Shift
1 Foundry manager 1
2 Secretary 1
3 Salesman 1
4 Draftsman/estimator 1
5 Warehouseman 1
6 Foundry foreman 1
7 Foundry shift supervisor 1 0
8 Quality control supervisor 1
9 Production planning and control 0 0
10 Quality control technician 1
11 Foundry leadman 1
12 Foundryman A 6 6
13 Foundryman B 2 2
14 Finishing/Heat treatment/Machining 3 3
15 Patternmaker 1 1
16 Plant mechanic/electrician
17 Security guard 1 1
SUB-TOTAL (Basic) 14 23

OT/VL/SL/13TH MP/BONUS/COLA/PAG-IBIG/SSS/ECC/MED/OTHER BENEFITS

TOTAL LABOR COST


LABOR COST PER KG

MANPOWER DISTRIBUTION AT YEAR 3 TO 10


No. Designation 1st Shift 2nd Shift
1 Foundry manager 1
2 Secretary 1
3 Salesman 1
4 Draftsman/estimator 1
5 Warehouseman 1
6 Foundry foreman 1
7 Foundry shift supervisor 1 0
8 Quality control supervisor 1
9 Production planning and control 0 1
10 Quality control technician 1
11 Foundry leadman 1
12 Foundryman A 6 6
13 Foundryman B 4 4
14 Finishing/Heat treatment/Machining 3 3
15 Patternmaker 1 1
16 Plant mechanic/electrician
17 Security guard 1 1
SUB-TOTAL (Basic) 16 25

OT/VL/SL/13TH MP/BONUS/COLA/PAG-IBIG/SSS/ECC/MED/OTHER BENEFITS

TOTAL LABOR COST


LABOR COST PER KG
on is estimated at 23 men.
cted to reach and normalize
he manpower requirement

YEAR 3
200
1
1
1
1
1
1
2
1
1
3
5
8
19
9
3

3
60

3rd Shift Total Basic rate Monthly total


1 20,000.00 20,000.00
1 6,000.00 6,000.00
1 8,500.00 8,500.00
1 7,500.00 7,500.00
1 6,500.00 6,500.00
1 12,000.00 12,000.00
0 0- -
1 10,00.00 10,00.00
0 0- -
1 6,500.00 6,500.00
1 5,850.00 5,850.00
8 5,070.00 40,560.00
2 4,810.00 9,620.00
0 0- -
1 5,200.00 5,200.00
0- -
1 3 4,805.83 4,805.83
1 23 152,647.49

42.30% 64,569.89

217,217.38
6.21

3rd Shift Total Basic rate Monthly total


1 20,000.00 20,000.00
1 6,000.00 6,000.00
1 8,500.00 8,500.00
1 7,500.00 7,500.00
1 6,500.00 6,500.00
1 12,000.00 12,000.00
1 2 8,500.00 17,00.00
1 10,00.00 10,00.00
0 0- -
1 6,500.00 6,500.00
1 5,850.00 5,850.00
6 18 5,070.00 91,260.00
2 6 4,810.00 28,860.00
3 9 4,810.00 43,290.00
1 3 5,200.00 15,600.00
0- -
1 3 4,805.83 14.417.49
14 51 301,777.49

42.30% 127,652.00

429,429.49
3.18

3rd Shift Total Basic rate Monthly total


1 20,000.00 20,000.00
1 6,000.00 6,000.00
1 8,500.00 8,500.00
1 7,500.00 7,500.00
1 6,500.00 6,500.00
1 12,000.00 12,000.00
1 2 8,500.00 17,00.00
1 10,00.00 10,00.00
0 1 8,500.00 8,500.00
1 6,500.00 6,500.00
1 5,850.00 5,850.00
6 18 5,070.00 91,260.00
4 12 4,810.00 57,720.00
3 9 4,810.00 43,290.00
1 3 5,200.00 15,600.00
0- -
1 3 4,805.83 14,417.49
16 57 330,637.49

42.30% 139,860.00

470,497.49
2.35
CAPITAL EXPENDITURE

The total capital requirement of the Foundry Project is FIFTY EIGHT MILLION THREE HUNDRED TEN THOUSAND EIGHT HUNDR

Equipment = P17,486,369.00
Material = 21,286,844.00
Labor = 19,538,544.00
Total = P58,310,800.00

The project capital cost were estimated based on the general layout, flowsheets, specifications, quotations from suppliers, in-h

The projected monthly cash flow requirements for the six months construction period is shown in Table 3.

Table 4 shows the unit cost of construction used in the cost estimate. The equipment list is shown in table 5.

The capital cost summary is shown in Table 6. The equipment cost is shown in Table 7. The material and labor cost estimate is
D TEN THOUSAND EIGHT HUNDRED PESOS(P 58,310,800.00) summarized as follows:

ns, quotations from suppliers, in-house knowledge of construction cost and productivities experienced in the foundry and construction ind

wn in Table 3.

hown in table 5.

aterial and labor cost estimate is shown in Tbale 8. The Equipment capital and installation cost estimate is shown in Table 9.
e foundry and construction industry.

hown in Table 9.
ITEM DESCRIPTION QUANTITY
14.0 CONSTRUCTION OVERHEAD
PROJECT MANAGEMENT (6 MONTHS)
14.01
Manager = 15% x P100,000.00 x 6 months
Others = 15% x P40,000.00 x 6 months

14.02 OVERHEAD COST


Installation permit 42 units
DENR inspection 6 days
Construction power 505,920 kW-hr

14.03 SECURITY SERVICES


6 months x 30 days/month x P750.00/day

14.04 OFFICES SUPPLIES


1 lot x P10,000.00

14.05 TRANSPORTATION
Rental 18 days

14.06 ACCOMMODATION
Lodging
Meals 20 times
20 tmes

TOTAL CONSTRUCTION OVERHEAD

B. LABOR COST
1 - Electrical supervisor 10 days
1 - Electrical capataz 10 days
5 - Lineman/electrician 10 days
4 - Project employee 10 days
Total labor cost

5. 750 KW FURNACE PARTS/REHAB


A. MATERIAL COST
Station contact, 148-6203-7 10 pcs
Contact tip, 148-6204-5 10 pcs
Primary capacitor, 19-F-487 1 pc
Secondary fine trq capacitor 2 pcs
Capacitor course, 300 KVAR 2 pcs
Capacitor switches, No. 1490108 1 pc
Main connector tips, No. 316B-948 6 pcs
Main line fuse, 390A, No. 1F161 2 pcs
Fuse, 10A, 250V, No. 161-03 12 pcs
Micro switch, 250W, 15A 3 pcs
Fuse, 15A, 250V, No. 161-02 12 pcs
Fuse, 16A, 600V, No. 161-06 10 pcs
Lamp, 10W, 230V, No. 165-06 3 pcs
Overvoltage, No. 155-1041-5 1 pc
Tip kit, 461A 759017 1 pc
Rectifier, 6A, 230V 2 pcs
Micro switch, 15A 1 pc
Contactor coils, 148 2 pcs
CR9500 solenoid assembly AC & DC service, GE 2 pcs
CR9500 C100CA51A, pull type, coil, 115V 2 pcs
Throat mounted, stroke, 60 Hz, 1-inch max PN 128 2 pcs
Total material cost 1 lot

B. LABOR COST
1 - Electrical capataz 20 days
3 - Lineman/electrician 20 days

TOTAL ELECTRICAL

13.0 EQUIPMENT INSTALLATION

TOTAL MATERIAL AND LABOR COST


UNIT COST TOTAL COST

P 90,000.00
36,000.00
P 126,000.00

170 P 7,140.00
2,000.00 12,000.00
5.53 2,797,738.00
P 2,816,878.00

P 135,000.00

P 10,000.00

1,150.00 P 20,700.00

900.00 18,000.00
500.00 10,000.00
p 28,000.00

P 3,136,578.00

963.00 P 9,630.00
510.27 5,103.00
494.64 24,732.00
205.00 8,200.00
P 47,665.00
540,000.00 P 540,000.00

510.27 P 10,205.00
494.64 29,678.00
P 39,883.00
p 3,264,527.00

p 1,436,880.00

P 37,622,046.00
Table 9
Equipment capital and Installation cos

EXTENDED
UNIT COST COSTMEX- OCEAN
EX-WORKS WORKS (US FREIGHT
ITEM DESCRIPTION QTY (US $) $) (US $)

1 FOUNDRY PLANT BUILDING AREA


Compressor, 400 CFM, 100 PSIG 1
Overhead crane, crab type, 10 tons 1 48,100 3,615
Sub-total 2
2 SAND HANDLING AREA
Mix muller, 900 kg capacity 1 34,000 3,400
Air scrubber fan, 1-1/2 Hp 1
Shake-out machine, 7000 kg capacity 1 28,300 2,830
Shake-out machine, 2000 kg capacity 1
Core mixer muller, 100 kg capacity 1 4,000 400
14" dia x 20' Screw conveyor 1
10" W x 34" Bucket elevator 1
24" W Conveyor no. 1 1
24" W Conveyor no. 2 1 3,760
18" W Single trough conveyor 1
Overhead crane, crab type, 5 tons 1
Sub-total 11 70,060 6,630
3 FURNACE AREA
Furnace, 2 tons 1
Furnace, 3 tons 1
Burner laddle pre-heater 2
Cooling tower 1
Centrifugal water pump 2 3,500
Overhead crane, crab type, 2 tons 1
Sub-total 8 3,500
4 HEAT TREATMENT AREA
Cooling tower 1
Centrifugal water pump 2 3,500
Overhead crane, 5T 1
Heat treatment oven 1
Sub-total 5 3,500 0

5 FINISHING AREA
Angle grinder 4 214
Welding machine 2
100" Karatsu boring machine 1
48" Niles boring machine 1
Planer/grinder 1
Overhead crane, 5 tons 1
Sub-total 10 214
6 OFFICE & CHANGE ROOM
Optical emiision spectrometer 1
Computer 2
Fire extinguisher 1
Sub-total 4
7 SHOP & STORAGE AREA
Oven 1
Computer 1
Fire extinguisher 1
Sub-total 3
8 WATER SUPPLY
Deep well pump 1
Sub-total 1
9 ELECTRICAL
Power transformer, 2.5 MVA 1
IDMC Switchgear, 600 A, 5 KV 1 34,000 34,000 3,400
IDMC Switchgear, 400 A, 5 KV 1 30,000 30,000 3,000
Distribution transformer, 333 KVA, 1 Ph 3
Transformer, 50 KVA, 460V/220V, 3 Ph 1 1,154 1,154
Low voltage switchgear 1 28,302 28,302
Station battery and charger 1 11,000 11,000 1,100
Motor control center #1, Foundry plant 1 5,705 5,705
Motor control center #2, Foundry plant 1 7,197 7,197
Sub-total 11 117,358 117,358 7,500

TOTAL 55 194,632 117,358 14,130


Equipment spares
GRAND TOTAL
Table 9
t capital and Installation cost estimate

TAXES & TOTAL W/


TOTAL FOREX DUTIES TAXES & FREIGHT TO LANDED
C&F MLA 1US$=P TOTAL (PESOS) DUTIES WEIGHT SITE COST
(US $) 53.00 (PESOS) @ 13% (PESOS) (TONNES) P2,500/Mt (PESOS)

26,000 1,378,000 179,140 1,557,140 4.99 12,475 1,569,615


51,815 2,746,195 357,005 3,103,200 3.30 8,250 3,111,450
77,815 4,124,195 536,145 4,660,340 20,725 4,681,065

Available 1.20 Available


1,000 53,000 53,000 0.05 125 53,125
31,130 1,694,890 214,486 1,864,376 0.80 2,000 1,866,376
Available 0.35 Available
4,400 233,200 30,316 263,516 0.40 1,000 264,516
7,950 421,350 54,776 476,126 2.74 6,850 482,976
3,568 189,104 189,104 0.44 1,100 190,204
8,865 469,845 469,845 1.40 3,500 473,345
5,175 274,275 0.65 1,625 1,625
Available Available
Available 2.93 Available
62,088 3,290,664 299,577 3,315,966 16,200 3,332,166

Available 7.60 Available


Available 11.40 Available
Available Available
9,520 504,560 504,560 0.99 2,475 507,035
7,000 371,000 48,230 419,230 0.26 1,300 420,530
Available 1.17 Available
16,520 875,560 48,230 923,790 3,775 927,565

9,520 504,560 504,560 0.99 2,475 507,035


7,000 371,000 48,230 419,230 0.26 1,300 420,530
Available 2.93 Available
Available 5.00 Available
16,520 875,560 48,230 923,790 3,755 927,565

854 45,262 45,262 0.80 8,000 53,262


Available 0.08 Available
Available 20.10 Available
Available 3.13 Available
Available 2.60 Available
Available 2.93 Available
854 45,262 45,262 8,000 53,262

Available Available
Available Available
Available Available

Available Available
Available 0 Available
Available 0 Available
- -

60,000 60,000 0.08 60,000


60,000 60,000 60,000

Available 8.37 Available


37,400 1,982,200 257,686 2,239,886 2.00 5,000 2,244,886
33,000 1,749,000 227,370 1,976,370 2.00 5,000 1,931,370
Available 6.00 Available
1,154 61,162 7,951 69,113 0.25 625 69,738
28,302 1,500,006 195,001 1,695,007 2.20 5,500 1,700,507
12,100 641,300 83,369 724,669 0.85 2,125 726,794
5,705 302,365 39,307 341,672 1.75 4,275 346,047
7,197 381,441 49,587 431,028 1.75 4,375 435,403
124,858 6,617,474 860,272 7,477,746 27,000 7,504,746

298,655 15,888,715 1,792,454 17,406,894 79,475 17,486,369


INSTALLATION
COST P12,000/Mt

59,880
39,600
99,480

14,400
600
9,600
4,200
4,800
32,880
5,280
16,800
7,800

35,160
131,520

91,200
136,800

11,880
6,240
14,040
260,160

11,880
6,240
35,160
60,000
113,280

38,400
1,920
241,200
37,560
31,200
35,160
385,440

960
960

100,440
24,000
24,000
216,000
3,000
26,400
10,200
21,000
21,000
446,040

1,436,880
TABLE 8 MATE
ITEM
1
1.01

B.

2
3

1.02

7
B.

1.03

4
5

B.

1.04

A.

1
2

6
7

1.05

4
5

2.01

2.02

2.03
A

2.04

2.05

2.06
A

B
A

2.09

2.1

2.11
A

2.12

2.12

3
3.01-3.02

3.03

3.04

3.05

B
A

3.06

B
4.01

4.02

4.03

4.04

4.05

5
5.01

5.02

5.03

5.04

5.05

B
6.0

7.0

8.0
1
1
5
4
1
1
5
4
1
1
5
4
TABLE 8 MATERIAL AND LAB
DESCRIPTION
FOUNDRY PLANT BUILDING AREA:
MAIN BUILDING

MATERIAL COST

EARTHWORKS
Excavation
Backfill
Fill Material

CONRETE & MASONRY WORKS


Heavy reinforced concrete, Class A
Light reinforced concrete, Class A
Masonry works (4" x 8" x 16" CHB)

STRUCTURAL STEELS, A36


Weight

CARPENTRY WORKS
Area

TINSMITHRY WORKS
Roof
Cladding

PAINTING WORKS
Area

CYCLONE WIRE WALLS


Area

LABOR COST

EARTHWORKS
Excavation
Backfill
Fill Material

CONRETE & MASONRY WORKS


Heavy reinforced concrete, Class A
Light reinforced concrete, Class A
Masonry works (4" x 8" x 16" CI•IB)
STRUCTURAL STEELS, A36
Weight

CARPENTRY WORKS
Area

TINSMITHRY WORKS
Roof
Cladding

PAINTING WORKS
Area

CYCLONE WIRE WALLS


Area

OFFICE/CHANGE ROOM:
A. MATERIAL COST

EARTHWORKS
Excavation
Backfill

CONRETE & MASONRY WORKS


Reinforced concrete, Class A
Masonry works (4" x 8" x 16" CHB)
Masonry works (6" x 8" x 16" CHB)
Glazing, Ceramic Tiles

STRUCTURAL STEELS, A36


Weight

CARPENTRY WORKS
Area

PAINTING WORKS
Area

STEEL CASEBIENT WINDOWS


Area

COMFORT ROOM SHOWCASE (complete with


Rough Plumbing and Waterlines)
Area
LABOR COST

EARTHWORKS
Excavation
Backfill

CONRETE & MASONRY WORKS


Reinforced concreter Class A
Masonry works (4" x 8" x 16" CHB)
Masonry works (6" x 8" x 16" CHB)
Glazing, Ceramic Tiles

STRUCTURAL STEELS, A36


Weight

CARPENTRY WORKS
Area

PAINTING WORKS
Area

STEEL CASEMENT WINDOW INSTALLATION


Area

COMFORT ROOM SHOWCASE INSTALLATION


(complete with Rough Plumbing and Waterlines)
Area

PATTERN SHOP/CORE ROOM LABORATORY

MATERIAL COST

EARTHWORKS
Excavation
Backfill

CONRETE & MASONRY WORKS


Reinforced concrete, Class A
Masonry works (4" x 8" x 16" CHB)

STRUCTURAL STEELS, A36


Weight

CARPENTRY WORKS
Area

TINSMITHRY WORKS
Roofing
Cladding

STEEL CASEMENT WINDows


Area

PAINTING WORKS
Area

LABOR COST

EARTHWORKS
Excavation
Backfill

CONRETE & MASONRY WORKS


Reinforced concrete, Class A
Masonry works (4" x 8" x 16" CHB)

STRUCTURAL STEELS, A36


Weight

CARPENTRY WORKS
Area

TINSMITHRY WORKS
Roofing
Cladding

STEEL CASEMENT WINDOWS


Area

PAINTNG WORKS
Area

FERRO-ALLOY STORAGE AND FURNACE

MATERIAL COST

EARTHWORKS
Excavation
Backfill

CONRETE & MASONRY WORKS


Reinforced concrete, Class A
Masonry works (4" x 8" x 16" CHB)

STRUCTURAL STEELS, A36


Weight

INSMITHRY WORKS
Roofing
Cladding

PAINTING WORKS
Area

CYCLONE WIRE WALLS


Area

CARPENTRY
Area

B. LABOR COST

EARTHWORKS
Excavation
Backfill

CONRETE & MASONRY WORKS


Reinforced concrete, Class A
Masonry works (4" x 8" x 16" CID)

STRUCTURAL STEELS, A36


Weight

TINSMITHRY WORKS
Roofing
Cladding

PAINTING WORKS
Area

CYCLONE WIRE WALLS


Area
CARPENTRY WORKS
Area

AIR COMPRESSOR

A. MATERIAL COST

EARTHWORKS
Excavation
Backfill

CONRETE WORKS
Area

STRUCTURAL STEELS, A.36


Weight

TINSMITHRY WORKS
Roofing
Cladding

PAINTING WORKS
Area

PIPE INSTALLATION
2" dia. x 20' long Sch. 40 Bl Pipe
2" dia. Gate Vlave
2" dia. x 900 Elbow
2" dia. BI Tee

B. LABOR COST

EARTHWORKS
Excavation

CONRETE WORKS
Ärea

STRUCTURAL STEELS, A36


Weight

TINSMITHRY WORKS
Roofing
Cladding
PAINTING WORKS
Area

PIPE INSTALLATION
2" dia. x 20' long Sch. 40 Bl Pipe

TOTAL FOUNDRY PLANT BLDG. AREA

SAND HANDLING AREA

MIX MULLERS

MATERIAL COST
Concrete Works
Steelworks
Painting Works

LABOR COST
Concrete Works
Steelworks
Painting Works
Excavation
Backfill

AIR SCRUBBER SYSTEM

MATERIAL COST
Concrete Works
Steelworks
Painting Works
Gl Pipe, 1" dia. x 20'
Gl Elbow, 1" dia. x 900
Gate Valve, 1" dia.

LABOR COST
Concrete Works
Steelworks
Painting Works
Excavation and Backfill
I 't Pipe Installation

SHAKE-OUT MACHINE, 7 Tons


MATERIAL COST
Concrete Works

LABOR COST
Concrete Works

SHAKE-OUT MACHINE, 2 Tons

MATERIAL COST
Concrete Works

LABOR COST
Concrete Works

CORE MIX MULLER, 100 kg

MATERIAL COST
Concrete Works
Steelworks
Painting Works

LABOR COST
Concrete Works
Steelworks
Painting Works
Excavation and Backfill

14" DIA. X 20' SCREW CONVEYOR


MATERIAL COST
Concrete Works
Steelworks
Painting Works

LABOR COST
Concrete Works
Steelworks
Painting Works
Excavation and Backfill

2.07 10" W x 34" LONG BUCKET ELEVATOR

A. MATERIAL COST
Concrete Works
Steelworks
Painting Works

B. LABOR COST
Concrete Works
Steelworks
Painting Works
Excavation and Backfill

2.08 24" W CONVEYOR NO. 1

MATERJAL COST
Concrete Works
Steelworks
Painting Works

LABOR COST
Concrete Works
Steelworks
Painting Works

24" W CONVEYOR NO. 2

MATERIAL COST
Concrete Works
Steelworks
Painting Works

LABOR COST
Concrete Works
Steelworks
Painting Works

18" W x 200 SINGLE TROUGH CONVEYOR

MATERIAL COST
Concrete Works

LABOR COST
Concrete Works
Excavation and Backfill

BIN NO. 1, 15 Tons


MATERIAL COST
Concrete Works
Steelworks
Painting Works
Excavation and Backfill
4" dia. x 24-1/2" long Air Cylinder Gate

LABOR COST
Concrete Works
Steelworks
Painting Works
Cylinder Installation

BIN No. 2, 15 Tons

MATERIAL COST
Concrete Works
Steelworks
Painting Works
4" dia. x 24-1/2"

LABOR COST
Concrete Works
Steelworks
Painting Works
long Air Cylinder Gate
Excavation and Backfill
4" dia. Cylinder Installation

BIN NO. 3, 8 Tons

MATERIAL COST
Concrete Works
Steelworks
Painting Works

LABOR COST
Concrete Works
Steelworks
Painting Works
Excavation and Backfill

FURNACE SECTION
FURNACE, 2 Tons and 3 Tons

MATERIAL COST
Concrete Works/Foundation
Steelworks/Platforms

LABOR COST
Concrete Worksmoundation
Steelworks/Platforms
Earthworks
Excavation
Backfill
Freight
Dismantling

3.03 SUMP AND MAKE-UP WATER TANK

MATERIAL COST
Concrete Works
Steelworks

LABOR COST
Concrete Works
S teelworks

3.04 BURNER LADDLE PRE-HEATER

COOLING TOWER

MATERIAL COST
Concrete Works

LABOR COST
Concrete Works

CENTRIFUGAL

MATERIAL COST
Concrete Works

LABOR COST
Concrete Works

CONTROL ROOM/HEAT TREATMENT AREA


4.01 COOLING TOWER

A, MATERIAL COST
Concrete Works
Steelworks

B. LABOR COST
Concrete Works
Steelworks

4.02 CENTRIFUGAL WATER PUMP

MATERIAL COST
Concrete Works

LABOR COST
Concrete Works

4.03 5 TONS OVERHEAD CRANE

4.04 HEAT TREATMENT OVEN

MATERIAL COST
Concrete Works
Steelworks

LABOR COST
Concrete Works
Steelworks

QUENCHING AND WATER TANK

MATERIAL COST
Concrete Works
Steelworks

LABOR COST
Concrete Works
Steelworks

TOTAL CONTROL ROOM/ HEAT TREATMENT AREA

FINISHING AREA
ANGLE GRINDER

WELDING MACHINE

100" KARATSU BORING MACHINE

MATERIAL COST
Concrete Works
Steelworks
Carpentry Works

LABOR COST
Concrete Works
Steelworks
Carpentry Works
Excavation
Backfill
Freight
Dismantling

48" NILES BORING MACHINE

MATERIAL COST
Concrete Works
Steelworks
Carpentry Works

LABOR COST
Concrete Works
Steelworks
Carpenty Works
Excavation
Freight
Dismantling

PLANER/GRINDER

MATERIAL COST
Concrete Works
Steelworks
Carpentry Works

LABOR COST
Concrete Works
Steelworks
Carpentry Works
Excavation
Freight
Dismantling

OFFICE & CHANGE ROOM

SHOP & STORAGE AREA

WATER SUPPLY

8.01 5.70 X 6.0 M HIGH WATER TANK

A. MATERIA!, COST
1. EARTHWORKS
Excavation
2. CONRETE WORKS
Volume
3. STRUCTURAL STEELS, A36
Weight
4. PAINTING WORKS
Area

B. LABOR COST
1. EARTHWORKS
Excavation
2. CONRETE WORKS
Volume
3. STRUCTURAL STEELS, A36
Weight
4. PAINTING WORKS
Area

8.02 DEEP WELL PUMP

8.03 WATER LINES

MATERIAL COST
2" dia. x 20' long Sch. 40 Bl Pipe
2" dia. x 90˚ BI elbow
2" dia. Gate valve
2" dia. x Bl Tee
I " dia. x 20' long Sch. 40 Bl Pipe
l" dia. x 900 Gl Elbow
1" dia Gate valve
3/4" dia. x 20' long Sch. 40 GI Pipe
3/4" dias x 90 Gl Elbow
3/4" dia. Gate Valve
3/4" dia. GI Coupling

LABOR COST
2" dim x 20' long Sch. 40 BI Pipe
l" dia. x 20' long Sch. 40 BI Pipe
3/4" dia. x 20' long Sch. 40 GI Pipe

TOTAL WATER SUPPLY

DRAINAGE CANAL

A. MATERIAL COST

1. EARTHWORKS
Excavation
Backfill

2. CONRETE AND MASONRY WORKS


Reinforced concrete, Class A
Masonry works (6" x 8" x 16" CHB)

LABOR COST

1. EARTHWORKS
Excavation
Backfill

2. CONRETE AND MASONRY WORKS


Reinforced concrete, Class A
Masonry works (6" x 8" x 16" CHB)
SERVICE ROAD
Length

MATERIAL COST

1. EARTHWORKS
Excavation
Backfill
Gravel Ballast

2. CONRÉTE WORKS
Reinforced concrete, Class A

LABOR COST

1. EARTHWORKS
Excavation
Backfill
Gravel Ballast

2. CONRETE AND MASONRY WORKS


Reinforced concrete, Class A

TOTAL SERVICE ROAD


EQUIPMENT RELOCATION / REHAB

11.01 EQUIPMENT REHAB COST

MATERIAL COST

MIX MULLERS, 2 Tons


Painting Works

18" W X 200 SINGLE TROUGH CONVEYOR


Mechanical Patts
Steelworks
Paintinig Works

3. OVERHEAD CRANE, 5 Tons


Steelworks, Bridge
Painting Works

'FURNACE, 2 Tons
Parts
FURNACE, 3 Tons
Parts

B, LABOR COST

MIX MULLERS, 2 Tons


Paintinig Works

18" w x 20 SINGLE TROUGH CONVEYOR


Mechanical Patts
St.eelworks
Paintinig Works

3. OVERHEAD CRANE, 5 Tons - 3 units


Steelworks, Bridge
Painting Works

4. OVERHEAD CRANE, 2 Tons


Steelworks, Bridge
Painting Works

FURNACE, 2 Tons
1 - Electiical Capaiaz
3 - Electrician

FURNACE, 3 Tons
I - Electrical Capataz
3 - Electrician

11,02 EQUIPMENT DISMANTLING

A. MATERIAL COST
B. LABOR COST

Mix Muller, 900 kgs


Shake-out Machine, 2 Tons
Overhead Crane, 5 Tons (3 t 'nits)
Overhead Crane, 2 Tons
Fumace, 2 Tons
Burner Laddle Pre-heater
Heat Treatment Oven
100" Karatsu Boring Machine
48" Niles Boring Machine
Planer/Grinder

Total Labor Cost

11.03 EQUIPMENT RELOCATION

A. MATERIAL COST
B. LABOR COST
Mix Muller, 900 kgs
Shake-out N/lachine,. 2 Tons
Overhead Crane, 5 Tons (3 units)
Overhead Crane, 2 Tons
Furnace, 2 Tons (LMD)
Furnace, 2 Tons ('Ex, AG&P)
3 Tons (Ex, AG P)
Bumer Laddle Pre-healer
100" Karatsu Boring Machine
48" Niles Boring Machine
Planer/Grinder
Power Transformer
Distribution Transformer

TOTAL EQUIPMENT RELOCATION/REHAB

ELECTRICAL

12.01 SUBSTATION

A. MATERIAL COST

Air break switch, manually group operated, 200 A,


14.4 k V class, continuous ratings 3 PST outdoor type
Power fuse, 200 A, 14.4 kv class, 400 MVAIC, outdoor installation
Power fuse, 300 A, 5 kv class, 400 MVAIC, outdoor installation
Lightning arrester, station type, 14.4 KV class, outdoor mounting
Lightning arrester, station type, 5 KV class, outdoor mounting
Power cable, 300 MCM, 5 type MV-90, XLPE insulated single
Power cable, 4/0 AWG, 5 KV, MV-90, XLPE insulated single
Stranded copper conductor , 100mm² THW 600 VAC single Insulated
Rigid Steel Conduit coupline, 80 mm dia. x 3 m
Rigid Steel Conduit Elbow , 80 mm dia x 90°
Rigid Steel Conduit Locknut and Bushing 80 mm dia
Terminal kit, for 200-400 MCM power cable outdoor use cold shrink

Terminal lug, compression type, long barrel, 1 hole 300 MCM cable
Terminal lug, compression type, long barrel, 1 hole for 4/0 AWG cable
Top pole insulator, 14 KV class, outdoor mounting
Bolt & nut, stainless steel, 3/8" dia. x 1-1/2" L complete with lock washer
Cable ties, standard, 0.18" W x 12" long, 100 pcs/bag
Nikolite Soldering Bar, 50/50
Soldering Paste
Weatherproof service entrance cap, 80 mm hub size

LABOR COST
Electrical Supervisor
Electrical Capataz
Lineman/Electrician
Project Employee

12.02 POWER DISTRIBUTION

A. MATERIAL COST

Stranded copper conductor, 150 mm2 THW, 600 VAC, single insulated
Stranded copper conductor, 125 mm2 THW, 600 VAC, single insulated
Stranded copper conductor, 38 mm2 THW, 600 VAC, single insulated 150m/roll
Stranded copper conductor, 22 mm2 THW, 600 VAC, single insulated 150m/roll
Stranded copper conductor, 14 mm2 THW, 600 VAC, single insulated 150m/roll
Power cable, 400 MCM, 5 kV XLPE insulated,
PVC jacketed, single conductor
Royal cable, 80 mm2, 3/C, 600 VAC, 75 m/roll
Royal cable, 5.5 mm2, 3/C, 600 VAC, 75 m/roll
Royal cable, 3.5mm2 3/C, 600 VAC, 75 m/roll
Control cable, stranded, AWG/6C, 600 VAC, colored, 300 m/roll
Rigid steel conduit w/ coupling, 15 mmdia. x 3 m
Rigid steel conduit w/ coupling, 25 mmdia. x 3 m
Rigid steel conduit w/ coupling, 40 mmdia. x 3 m
Rigid Steel Conduit, elbow, 15 mm dia. x 90 degrees
Rigid Steel Conduit, elbow, 25 mm dia. x 90 degrees
Rigid Steel Conduit, elbow, 40 mm dia. x 90 degrees
Rigid Steel Conduit, locknut & bushing, 15 mm dia-
Rigid Steel Conduit, locknut & bushing, 25 mm dia.
Rigid Steel Conduit, locknut & bushing, 40mm dim
Liquid tight flexible conduit w/ PVC cover, 15 mm dia.
Liquid tight flexible conduit w/ PVC cover, 25 mm dia-
Liquid tight flexible conduit w/ PVC cover, 40 mm dia.
Liquid tight flexible conduit connector, straight type, 15 mm C
Liquid tight flexibie conduit connector, straight type, 25 mm
Liquid tight flexible conduit connector, straight type, 40 mm
Condulet bodies, form 85 series, aluminum, threaded type,type LL. 15 mm hub size
Condulet bodies, form 85 series, aluminum, threaded type,type LL. 25 mm hub size
Condulet bodies, form 85 series, aluminum, threaded type,type LL. 40 mm hub size
Terminal lug, compression type, long barrel, one hole in pad for 250 MCM 300 MCM copper
Terminal lug, compression type, long barrel, one hole in pad for #6 - # I AWG copper
Cable ties, miniature, 0.1" width x 6" long, 100 pcs/bag
Cable ties, standard, 0.18" width x 12" long, 100 pcs/bag
Pushbutton station, start-stop w/ indicating light, in NEMA 3R enclosure
Pullbox, GL 4" x 4" x 2" c/w cover & screws
Pullbox, GI, 8" x 8" x 4" c/w cover & screws
Pullbox, GI, 12" x 12" x 6" c/w cover & screws
U-bolt, 1/4" dia. hot dip galvanized steel, for 1/2" dia. pipe complete with nuts & washers
U-bolt, 1/4" dia. hot dip galvanized steel, for 1" dia. pipe complete with nuts & washers
U-bolt, 1/4" dia. hot dip galvanized steel, for 1-1/2" dia. pipe complete with nuts & washers
Cable tray system, Ga. 12 hot dip galvatized steel extruded in channel side rails & structural cross ratngs; it shall include the following

Ladder type tray, 14" W x 4" D x 10' long - 20 lgths.


Vertical bend, 90 degrees
Vertical bend, 45 degrees
Horizontal bend, 90 degrees
Horizontal bend, 45 degrees
Horizontal tee
Barrier strip, 4" D
Complete assembly shall be furnished w/ splice plates, tray covers, bolts, nuts and washers
Cable tray, channel type, slotted bottom, Ga. # 16 hot dip galva steel, 4" width x 2" depth x 10' long wd/ cover and splice plate

LABOR COST

Electrical Supervisor
Electrical Capataz
Lineman/Electrician
Project Employee

12.03 LIGHTING SYSTEM

MATERIAL COST
Lighting panelboard, 300V, 2PST, main breaker: 125A, 2 PSI
Wall mounted lumiaire, 400W, 220 V, 60 Hz, Mogul base,high pressure sodium GE-WM7M17MTA1 SN4DB complete HPS lamp
EHB high bay luminaire, open type, pendant mounting, 400W 220V, 60 Hz, Mogul base, metal halide, GE-EHBA25MTA5V6 complete wit
Fluorescent fixture, double, 40W, 220V, 60 Hz, industrial type rapid start c/w reflector & tubes rapid start c/w reflector & tubes
Rigid steel conduit w/ coupling, 15 mm dia. x 3 m
Rigid Steel Conduit, elbow, 15 mm dia. x 90 degrees
Rigid Steel Conduit, locknut & bushing, 15 mm dia.
Royal cable, #12/2c, 600V, 75 m/roll
Junction box, GI 4" x 4" x 2" w/ 1/2" dia. knockcut, complete cover & screws
Watertight strain relief cord grips & connectors, straight type, 15 mm hub size

LABOR COST
Electrical Supervisor
Electrical Capataz
Lineman/Electrician
Project Employee

GROUNDING & SPLICING

A. MATERIAL COST
Grounding conductor, 2/0 AWG bare copper, soft drawn
Ground rod, copperweld, 1/2" dia. x 8'
Ground connector, cable to rod
Ground connector, cable to bar
Vinyl electrical tape, 3/4" x 66', 3M-Super 33+D, 10 pcs/carto
Rubber splicing tape, 3/4" x 30" 3M-23, 50 pcs/cartoon
Varnished cambric tape, 3/4N x 60', 3M-2510, 10 pcs/cartoon
Wire marker
QUANTITY UNIT COST TOTAL COST

469 m³
103 m³
469 m³

469 m³
469 m³
469 m³
8.36 cubic meter 4,800.00 P 40,128.00
502 kgs 39.00 19,578.00
P 59,706.00

8.36 cubic meter 3,200.00 P 26,752.00


502 kgs. 26.00 13,052.00
P 39,804.00

1.70 cubic meter 4,800.00 8,160.00


P 8,160.00
3,200.00 5,440.00
1.70 cubic meter P 5,440.00

21.65 cubic meter 4,800.00 P 103,920.00


16,912 kgs 39.00 659,568.00
P 763,488.00

21.65 cubic meter 3,200.00 P 69,280.00


16,912 kgs 26.00 439,712.00
P 508,992.00

44.40 cubic meter 4,800.00 P 213,120.00


1,139 kgs 39 44,421.00
P 257,541.00

44.40 cubic meter 3,200.00 P 142,080.00


1,139 kgs 26 29,614.00
P 171,694.00
P 1,814,825.00
25.00 cubic meter 4,800.00 P 120,000.00
75 kgs 39 2,925.00
206 bdft. 4 824
P 123,749.00

25.00 cubic meter 320.00 P 8,000.00


75 kgs 26.00 1,950.00
206 bdft. 2.50 515.00
78 cubic meter 1.50 117.00
20 cubic meter 1.50 30.00
20.1 mt 2,500.00 50,250.00
20.1 mt 12,000.00 241,200.00
P 302,062.00

3.90 cubic meter 4,800.00 P 18,720.00


30 kgs 39.00 1,170.00
42 bdft 4.00 168.00
P

3.90 cubic meter 320.00 P 1,248.00


30 kgs 26.00 780.00
42 bdft 2.50 105.00
4 cubic meter 1.50 6.00
3.13 mt 2500.00 7,825.00
3.13 mt 12,000.00 37,560.00
P 47,524.00

3.20 cubic meter 4,800.00 P 15,360.00


109 kgs 39 4,251.00
83 bdft 4 332.00
P 19,943.00

3.20 cubic meter 320.00 P 1,024.00


109 kgs 26.00 2,834.00
83 bdft 2.50 208.00
3 cubic meter 160.00 480.00
2.60 mt 2500.00 6,500.00
2.60 mt 12000.00 31,200.00
P 42,246.00
P 555,582.00

12 cubic meter

18.0 cubic meter 4,800.00 P 86,,400.00

9,520 kgs 39.00 P 371,280.00

240 square meters 6.60 P 1,584.00


P 459,264.00

12 cubic meter 160.00 P 1,920.00

18.0 cubic meter 3200.00 P 57,600.00

9,520 kgs 26.00 P 247,520.00

240 square meters 4.40 P 1,056.00


P 308,096.00
16 lgths 878.00 P 14,048.00
10 pcs 143.00 1,430.00
12 pcs 300.00 3,600.00
8 pcs 100.00 800.00
10 lgths 370.00 3,700.00
3 pcs 15.00 45.00
2 pcs 145.00 290.00
8 ;gths 250.00 2,000.00
4 pcs 11.00 44.00
3 pcs 87.00 261.00
6 pcs 8.00 48.00
P 26,266.00

16 lgths 170.00 P 2,720.00


10 lgths 150.00 1,500.00
8 lgths 120.00 960
P 5,180.00

275 cubic meter


62 cubic meter

32.2 cubic meter 4,800.00 P 154,560.00


295.0 square meter 375.00 110,625.00
P 265,185.00

275 cubic meter 160.00 P 44,000.00


62 cubic meter 160.00 9,920.00

332.2 cubic meter 3200.00 P 103,040.00


295.0 square meter 250.00 73,750.00
P 230,710.00
190 m

171 cubic meter


410 cubic meter 237.00 P 97,170.00
200 cubic meter 500.00 100,000.00

230 cubic meter 4,800.00 1,104,000.00


P 1,301,170.00

171 cubic meter 160.00 P 27,360.00


410 cubic meter 160.00 65,600.00
200 cubic meter 160.00 32,000.00

230.0 cubic meter 3,200.00 736,000.00


P 860,960.00

P 2,162,130.00

120 square meter

1 lot 165,000.00 165,000.00


1,210 kgs 39.00 47,190.00
10 square meter 6.60 66.00

10,910 kgs 39.00 425,490.00


72 square meter 6.60 475.00

1 lot 50,000.00 50,000.00


1 lot 50,000.00 50,000.00
P 739,013.00

10 square meter 4.40 P 44.00

284 kgs 12.00 3408.00


1,210 kgs 26.00 31460.00
10 square meter 2.40 44.00

10,910 kgs 26.00 283,660.00


72 square meter 4.40 317.00

2,086 kgs 26.00 54236.00


26 square meter 4.40 317.00

10 days 511.00 5,110.00


10 days 495.00 14,850.00

10 days 511.00 5,110.00


10 days 495.00 14,850.00
P 413,203.00

120.00 mt 7,500.00 P 900,000.00


0.35 mt 7,500.00 2,625.00
8.79 mt 7,500.00 65,925.00
1.17 mt 7,500.00 8,775.00
7.60 mt 7,500.00 57,000.00
0.25 mt 7,500.00 1,875.00
5.00 mt 7,500.00 37,500.00
20.10 mt 7,500.00 150,750.00
3.13 mt 7,500.00 23,475.00
2.60 mt 7,500.00 19,500.00
P 1,267,425.00

120.00 mt 2,500.00 P 300,000.00


0.35 mt 2,500.00 875
8.79 mt 2,500.00 21,975.00
1.17 mt 2,500.00 2,925.00
7.60 mt 2,500.00 19,000.00
7.60 mt 2,500.00 19,000.00
11.40 mt 2,500.00 28,500.00
0.25 mt 2,500.00 625
20.10 mt 2,500.00 50,250.00
3.13 mt 2,500.00 7,825.00
2.60 mt 2,500.00 6,500.00
8.37 mt 2,500.00 20,925.00
6.00 mt 2,500.00 15,000.00
P 493,400.00

P 2,913,041.00

1 set 72,000.00 P 72,000.00

3 units 56,000.00 168,000.00


3 units 45,000.00 135,000.00
3 units 30,000.00 90,000.00
3 units 20,000.00 60,000.00
300 m 400.00 120,000.00
100 m 250.00 25,000.00
300 m 190.00 57,000.00
10 lgths 562.00 5,620.00
2 pcs 376.00 752.00
6 pcs 52.00 312.00
5 kits 7,000.00 35,000.00

12 pcs 849.00 10,188.00


56 pcs 749.00 41,944.00
12 pcs 6,000.00 72,00.00
40 pcs 9.00 360.00
40 bags 11.00 440.00
4 bags 500.00 2,000.00
50 pcs 220.00 11,000.00
6 pcs 50.00 300.00
2 pcs 400.00 800.00
P 907,716.00

21 days 963.00 P 20,223.00


21 days 510.27 10,716.00
21 days 494.64 51,937.00
21 days 205.00 17,220.00
P 11,096.00

400 m 274 P 109,600.00


460 m 231 106,260.00
4 rolls 12,200.00 48,800.00
3 rolls 6,200.00 18,600.00
5 rolls 4,400.00 22,000.00
250 m 600.00 150,000.00

1 roll 6,237.00 6,237.00


5 rolls 3,517.00 17,585.00
16 rolls 2,740.00 43,840.00
8 rolls 10,000.00 80,000.00
200 lgths 92.00 18,400.00
40 lgths 146.00 5,840.00
20 lgths 250.00 5,000.00
50 pcs 25.00 1,250.00
12 pcs 48.00 576.00
8 pcs 121.00 968.00
150 pcs 18.00 2,700.00
30 pcs 25.00 750.00
12 pcs 37.00 444.00
40 m 65.00 2,660.00
6m 97.00 582.00
3m 219.00 657.00
100 pcs 46.00 4,600.00
20 pcs 75.00 1,500.00
10 pcs 265.00 2,650.00
45 pcs 92.00 4,140.00
25 pcs 110.00 2,750.00
4 pcs 168.00 672.00
48 pcs 849.00 40,752.00
30 pcs 500.00 15,000.00
6 bags 300.00 1,800.00
18 bags 500.00 9,000.00
45 pcs 220.00 9,900.00
38 pcs 85.00 3,230.00
18 pcs 148.00 2,664.00
6 pcs 178.00 1,068.00
300 pcs 5.00 1,500.00
60 pcs 8.00 480.00
40 pcs 10.00 400.00
1 lot 85,000.00 85,000.00

8 lgths 2,500.00 P 20,000.00

P 849,795.00

30 days 963.00 P 28,890.00


30 days 510.27 15,308.00
30 days 494.64 74,196.00
30 days 205.00 24,600.00
P 142,994.00
1 assy 12,500.00 P 12,500.00
6 sets 8,500.00 51,000.00
22 sets 10,000.00 220,000.00
30 sets 870.00 26,100.00
90 lgths 92.00 8,280.00
25 pcs 25.00 625.00
50 pcs 18.00 900.00
20 rolls 2,026.00 40,520.00
70 pcs 16.00 1,120.00
70 pcs 18.00 1,260.00
P 362,305.00

15 days 963.00 P 14,445.00


15 days 510.27 7,654.00
15 days 494.64 37,098.00
15 days 215.00 12,300.00
P 71,497.00

180 m 120.00 P 21,600.00


15 lgths 498.00 7,470.00
28 pcs 56.00 1,568.00
24 pcs 62.00 1,488.00
40 ctn 1760.00 70,400.00
3 ctn 19850.00 59,550.00
25 ctn 1380.00 34,500.00
5 sets 1200.00 6,000.00
P 202,576.00

You might also like