Professional Documents
Culture Documents
GreenSpan Mall - Structural Report - R1
GreenSpan Mall - Structural Report - R1
SEPTEMBER, 2020
INVESTIGATED AND REPORTED BY:
CONTENTS
1 INTRODUCTION ....................................................................................................................... 3
1 INTRODUCTION
1.1 INTRODUCTION
This report presents the results of a structural analysis exercise carried out for the
existing 2-storey (Ground + 2 Floors) building located along Savannah road at
approximately 2.2 kilometres from Total Donholm Service station, along Outer ring
road, Nairobi County. A team of registered professional engineers carried out the
structural site survey on the 22nd day of September 2020, having been duly
commissioned by Tesla.
Staircase view
2 STRUCTURAL INVESTIGATION
PROPOSED 12M
STUB TOWER
EXISTING 900mm ON STEEL PLATFORM
PARAPET WALL TO SE DETAILS
6400
EXISTING
300x300mm 500 4300 900 500
RC COLUMN EXISTING
300x300mm
900 500
RC COLUMN
4800
STRUCTURAL GRILLAGE TO
3300
ENGINEER'S DETAILS
+11.60m
EXISTING
EXISTING 300x300mm
300x300mm RC COLUMN
RC COLUMN
PROPOSED GREENSPAN SITE
LAYOUT
The proposed site location is over the existing staircase facing the external Power
room to the back of the complex.
3 INTEGRITY ANALYSIS
All foundations are supported on firm ground with not less than
100Kn/m2 in bearing capacity. It is also assumed that all black
cotton soil was removed from site during construction and
replaced with approved hard core, laid in layers not exceeding
300mm and compacted to 95% MDD modified AASHTO.
All walls are founded on a continuous reinforced concrete strip
footing, supported on firm ground of bearing capacity not less
than 100Kn/m2.
Steel reinforcement bars are of consistent sizing (Diameter) and
spaced to BS 8110 guidelines.
That the structural configuration has been defined in such a way as
to ensure that a localized structural failure does not lead to overall
collapse of the entire building.
The proposed equipment in this project has negligible surface
area, and all horizontal forces are resisted by the building core in
which the stair cases are located.
Worst case scenarios for beams and slabs considers simple spans
(No continuities whatsoever)
RC Column Design
Live Loads
4. 1.0Qk = 2.0Kn/m2 …………………………. (1)
4.1 CONCLUSIONS
Based on the investigations and detailed assessments performed on the subject
building, we hereby deduce the following conclusions;
That the said building is NOT fit-for-use in the support of the
proposed grillage, heavy cabinets and a lattice tower. It is riddled
with age-related structural deterioration, including structural
cracking, water ingress, corrosion, moulding wear and tear. Water
ingress into reinforced concrete highly impacts its quality by
compromising the integrity of steel reinforcement.
4.2 RECOMMENDATIONS
From the above conclusions, the following recommendations are hereby made;
The Engineer finds building not sufficiently capable of supporting
the proposed grillage, heavy equipment cabinets and a lattice
tower.
PROPOSED 12M
STUB TOWER
6400
EXISTING
300x300mm 500 4300 900 500
RC COLUMN EXISTING
300x300mm
900 500
305x165x40Kg/m UB RC COLUMN
254x146x31Kg/m UB
305x165x40Kg/m UB
305x165x40Kg/m UB
305x165x40Kg/m UB
305x165x40Kg/m UB
4800
3300
+11.60m
EXISTING
EXISTING 300x300mm
300x300mm RC COLUMN
RC COLUMN
PROPOSED GREENSPAN
DETAILED SITE LAYOUT
5 APPENDICES