APPROVED BUDGET COST

Name of Project: Improvement/Upgrading of Hospital Building, Phase 1


Project Location: Ciriaco S. Tirol Hospital
Owner: Provincial Government of Aklan
Implementing Agency DOH-CHD Western Visayas
MARK-UPS
TOTAL MARK-UP
ITEM ESTIMATED DIRECT IN PERCENT TOTAL INDIRECT
DESCRIPTION QUANTITY UNIT TOTAL COST UNIT COST
No. COST COST
OCM[1] PROFIT % VALUE VAT[3]

-1 -2 (3) -4 -5 -6 -7 -8 -9 -10 -11 -12 -13


(12%[(5)+
(5)X(8) (9)] (9)+(10) (5)+(11) (12)/(3)
I. Stage 1
1.0 Permits Building and Occupancy Permit (Plans
& Other Items only) 1.00 lot 3,145,000.00 - 251,600.00 8.000000 251,600.00 407,592.00 659,192.00 3,804,192.00 3,804,192.00

II. Stage 11 Construction Phase


1.0 General Provisions
1.1 Right of Way 1.00 lot 180,000.00 - 14,400.00 8.000000 14,400.00 23,328.00 37,728.00 217,728.00 217,728.00
1.2 Permits 1.00 lot 72,167.82 - 5,773.43 8.000000 5,773.43 9,352.95 15,126.38 87,294.20 87,294.20
1.3 Temporary Field Office & Facilities
1.3.1 Field Office 25.00 sq.m. 78,968.00 - 6,317.44 8.000000 6,317.44 10,234.25 16,551.69 95,519.69 3,820.79
1.3.2 Office Eqpmt., Furnitures & Fixtures 1.00 lot 101,000.00 - 8,080.00 8.000000 8,080.00 13,089.60 21,169.60 122,169.60 122,169.60
1.4 Utilities (Water and Electrical) 1.00 lot 225,000.00 - 18,000.00 8.000000 18,000.00 29,160.00 47,160.00 272,160.00 272,160.00
1.5 Board Up - Perimeter Protection & Barrier 110.00 lm 68,516.00 5,484.44 5,481.28 16.004611 10,965.72 9,537.81 20,503.53 89,019.53 809.27
2.0 Sitework
2.1 Site Demolition 1.00 lot 266,680.00 21,346.70 21,334.40 16.004611 42,681.10 37,123.33 79,804.43 346,484.43 346,484.43
2.2 Structural Excavation (& other embedded concrete 349.04 cu.m 286,920.00 22,966.83 22,953.60 16.004611 45,920.43 39,940.85 85,861.28 372,781.28 1,068.02
2.3 Backfilling 188.50 cu.m 15,350.00 1,228.71 1,228.00 16.004611 2,456.71 2,136.80 4,593.51 19,943.51 105.80
2.4 Filling Materials 706.00 cu.m 335,330.00 26,841.86 26,826.40 16.004611 53,668.26 46,679.79 100,348.05 435,678.05 617.11
2.5 Base and Sub-base Course 48.75 cu.m 54,215.00 4,339.70 4,337.20 16.004611 8,676.90 7,547.03 16,223.93 70,438.93 1,444.90
2.6 Lay-out, Forms & Scaffoldings 1.00 lot 1,558,330.00 124,738.25 124,666.40 16.004611 249,404.65 216,928.16 466,332.81 2,024,662.81 2,024,662.81
3.0 Concrete /Reinforcement Works
3.1 Foundation
3.1.1 Column Footing 101.69 cu.m. 1,320,911.00 105,733.79 105,672.88 16.004611 211,406.67 183,878.12 395,284.79 1,716,195.79 16,876.74
3.1.2 Footing Tie Beam (FTB) 14.16 cu.m. 306,660.00 24,546.94 24,532.80 16.004611 49,079.74 42,688.77 91,768.51 398,428.51 28,137.61
3.1.3 Wall Footing 13.59 cu.m. 125,073.00 10,011.61 10,005.84 16.004611 20,017.45 17,410.85 37,428.30 162,501.30 11,957.42
3.2 Columns & Vertical Stiffiner
3.2.1 Columns 89.04 cu.m. 2,002,310.00 160,277.12 160,184.80 16.004611 320,461.92 278,732.63 599,194.56 2,601,504.56 29,217.26
3.3 Beams
3.3.1. Ground Floor Beam 14.16 cu.m. 312,184.00 24,989.11 24,974.72 16.004611 49,963.83 43,457.74 93,421.57 405,605.57 28,644.46
3.3.2. Second Floor Beam 31.97 cu.m. 1,093,235.00 87,509.21 87,458.80 16.004611 174,968.01 152,184.36 327,152.37 1,420,387.37 44,428.76

Page 1
APPROVED BUDGET COST
Name of Project: Improvement/Upgrading of Hospital Building, Phase 1
Project Location: Ciriaco S. Tirol Hospital
Owner: Provincial Government of Aklan
Implementing Agency DOH-CHD Western Visayas
3.3.3. Third Floor 32.85 cu.m. 1,095,325.00 87,676.50 87,626.00 16.004611 175,302.50 152,475.30 327,777.80 1,423,102.80 43,321.24
3.3.4. Roof Deck 40.35 cu.m. 841,587.00 67,365.76 67,326.96 16.004611 134,692.72 117,153.57 251,846.29 1,093,433.29 27,098.72
3.4 Floor Slab/Steel Decking
3.4.1. Ground Floor 50.68 cu.m. 488,238.00 39,081.55 39,059.04 16.004611 78,140.59 67,965.43 146,106.02 634,344.02 12,516.65
3.4.2. Steel Decking (2nd Flr and third floor)) 54.00 cu.m. 922,559.00 73,847.26 73,804.72 16.004611 147,651.98 128,425.32 276,077.30 1,198,636.30 22,196.97
3.4.3. Roof Deck with Water Proofing 64.21 cu.m. 811,579.04 64,963.74 64,926.32 16.004611 129,890.07 112,976.29 242,866.36 1,054,445.40 16,421.83
3.5 Ramp and Stairs 20.73 cu.m. 347,471.00 27,813.70 27,797.68 16.004611 55,611.38 48,369.89 103,981.27 451,452.27 21,777.73
3.6 Driveway 12.14 cu.m. 150,898.00 12,078.80 12,071.84 16.004611 24,150.64 21,005.84 45,156.47 196,054.47 16,149.46
3.7 Concrete Counter 3.30 cu.m. 40,963.00 3,278.93 3,277.04 16.004611 6,555.97 5,702.28 12,258.25 53,221.25 16,127.65
4.0 Masonry Works
4.1 Ground Floor 853.00 sq.m. 797,522.00 63,838.53 63,801.76 16.004611 127,640.29 111,019.48 238,659.77 1,036,181.77 1,214.75
4.2 Second Floor 884.00 sq.m. 799,606.00 64,005.35 63,968.48 16.004611 127,973.83 111,309.58 239,283.41 1,038,889.41 1,175.21
5.0. Metal Works
5.1 Metal Works (Stair Railings & Hand Grab Bar) 928.00 sq.m. 408,452.00 32,694.99 32,676.16 16.004611 65,371.15 56,858.78 122,229.93 530,681.93 571.86
6.0 Architectural Finishes
6.1 Cement Plaster Finishes (Wall, Columns 3,727.00 sq.m. 985,880.00 78,915.86 78,870.40 16.004611 157,786.26 137,239.95 295,026.21 1,280,906.21 343.68
& Beams)
6.2 Door and Windows (Ground & Second Floor)
6.2.1 Doors 1.00 lot 929,603.22 74,411.12 74,368.26 16.004611 148,779.38 129,405.91 278,185.29 1,207,788.51 1,207,788.51
6.2.2 Windows 1.00 lot 1,089,888.00 87,241.29 87,191.04 16.004611 174,432.33 151,718.44 326,150.77 1,416,038.77 1,416,038.77
6.3 Tilework 0.00 -
6.3.1 Ground Floor 669.00 sq.m. 895,703.00 71,697.54 71,656.24 16.004611 143,353.78 124,686.81 268,040.59 1,163,743.59 1,739.53
6.3.2 Second Floor 638.00 sq.m. 1,017,113.00 81,415.94 81,369.04 16.004611 162,784.98 141,587.76 304,372.74 1,321,485.74 2,071.29
6.3.3 Counter Tile and Splashboards 39.00 lm 117,628.00 9,415.66 9,410.24 16.004611 18,825.90 16,374.47 35,200.37 152,828.37 3,918.68
(backsplash and side boards)
6.4 Ceiling Work
6.4.1. Ground Floor 547.00 sq.m 383,390.75 30,688.94 30,671.26 16.004611 61,360.20 53,370.11 114,730.31 498,121.06 910.64
6.4.2. Second Floor 541.00 sq.m 347,455.00 27,812.42 27,796.40 16.004611 55,608.82 48,367.66 103,976.48 451,431.48 834.44
6.5 Carpentry Work
6.5.1. Cabinets and Counters 1.00 lot 281,614.00 22,542.10 22,529.12 16.004611 45,071.22 39,202.23 84,273.45 365,887.45 365,887.45
6.6 Painting
6.6.1. Ground Floor 1,749.00 sq.m 427,352.00 34,207.86 34,188.16 16.004611 68,396.02 59,489.76 127,885.79 555,237.79 317.46
7.0 Plumbing Works
7.1 Fixtures and Accessories 1.00 lot 728,398.00 58,305.43 58,271.84 16.004611 116,577.27 101,397.03 217,974.30 946,372.30 946,372.30
7.2 Cold Water Line 1.00 lot 49,510.00 3,963.08 3,960.80 16.004611 7,923.88 6,892.07 14,815.95 64,325.95 64,325.95
7.3 Waste Waterline /Sewer Line and Vent System 1.00 lot 143,972.00 11,524.40 11,517.76 16.004611 23,042.16 20,041.70 43,083.86 187,055.86 187,055.86
7.4 Storm Drainage and Catch Basin 1.00 lot 126,504.00 10,126.15 10,120.32 16.004611 20,246.47 17,610.06 37,856.53 164,360.53 164,360.53
7.5 Septic Tank 2.00 unit 152,342.00 12,194.38 12,187.36 16.004611 24,381.74 21,206.85 45,588.59 197,930.59 98,965.30
8.0 Electrical 1.00 lot 2,370,400.00 189,741.30 189,632.00 16.004611 379,373.30 329,972.80 709,346.09 3,079,746.09 3,079,746.09

Page 2
APPROVED BUDGET COST
Name of Project: Improvement/Upgrading of Hospital Building, Phase 1
Project Location: Ciriaco S. Tirol Hospital
Owner: Provincial Government of Aklan
Implementing Agency DOH-CHD Western Visayas
9.0 Fire Safety & Protection System
9.1 Ground Floor 1.00 lot 305,986.00 24,492.99 24,478.88 16.004611 48,971.87 42,594.94 91,566.81 397,552.81 397,552.81
9.2 Second Floor 1.00 lot 362,922.00 29,050.49 29,033.76 16.004611 58,084.25 50,520.75 108,605.00 471,527.00 471,527.00
9.3 Third Floor (Rough-ins) #NAME? ### #NAME? #NAME?
10.0 Mechanical Works
10.1 Airconditioning Units
10.1.1 Ground Floor 1.00 lot 405,160.00 32,431.48 32,412.80 16.004611 64,844.28 56,400.51 121,244.80 526,404.80 526,404.80
10.1.2 Second Floor 1.00 lot 400,060.00 32,023.25 32,004.80 16.004611 64,028.05 55,690.57 119,718.61 519,778.61 519,778.61
10.1.3 Third Floor (Drainage Piping System) 1.00 lot 35,400.00 2,833.63 2,832.00 16.004611 5,665.63 4,927.88 10,593.51 45,993.51 45,993.51
10.2 Exhaust Fan Piping
10.2.1 Ground Floor 1.00 lot 37,360.00 2,990.52 2,988.80 16.004611 5,979.32 5,200.72 11,180.04 48,540.04 48,540.04
10.2.2 Second Floor 1.00 lot 45,180.00 3,616.48 3,614.40 16.004611 7,230.88 6,289.31 13,520.19 58,700.19 58,700.19
11.0. Electronics & Communication System
11.1 Security & Surveillance (CCTV)
11.1.1 Ground Floor 1.00 lot 16,411.00 1,313.64 1,312.88 16.004611 2,626.52 2,284.50 4,911.02 21,322.02 21,322.02
11.1.2 Second Floor 1.00 lot 12,208.00 977.20 976.64 16.004611 1,953.84 1,699.42 3,653.26 15,861.26 15,861.26
11.2 Fire Detection & Alarm System (FDAS)
11.2.1 Ground Floor 1.00 lot 33,098.00 2,649.37 2,647.84 16.004611 5,297.21 4,607.42 9,904.63 43,002.63 43,002.63
11.2.2 Second Floor 1.00 lot 28,706.00 2,297.80 2,296.48 16.004611 4,594.28 3,996.03 8,590.32 37,296.32 37,296.32
11.3 Paging System / Public Address
11.3.1 Ground Floor 1.00 lot 19,562.00 1,565.86 1,564.96 16.004611 3,130.82 2,723.14 5,853.96 25,415.96 25,415.96
11.3.2 Second Floor 1.00 lot 15,156.00 1,213.18 1,212.48 16.004611 2,425.66 2,109.80 4,535.46 19,691.46 19,691.46
11.4 Communication System (Tel., CATV, Data, Nurse Call, Intercom)
11.4.1 Ground Floor 1.00 lot 187,068.00 14,974.07 14,965.44 16.004611 29,939.51 26,040.90 55,980.41 243,048.41 243,048.41
11.4.2 Second Floor 1.00 lot 138,596.00 11,094.07 11,087.68 16.004611 22,181.75 19,293.33 41,475.08 180,071.08 180,071.08
Total #NAME? 2,124,386.91 #NAME? #NAME? 4,551,720.98 4,187,207.62 8,738,928.60 39,080,604.43

Page 3
DETAILED ESTIMATES

Name of Project: Improvement/Upgrading of Hospital Building, Phase 1


Along Grid Lines 1-6 and A-K
Project Location: Ciriaco S. Tirol Hospital
Boracay Island, Malay, Aklan
Owner: Provincial Government of Aklan
Implementing Agency: DOH-CHD Western Visayas

I Stage 1 1.00 lot


Description Quantity Unit Unit Cost Amount
Architectural and Engineering Services 1.00 lot 3,000,000.00 P 3,000,000.00
Feasibility Studies n/a -
Detailed Architectural and Engineering Design
Survey 1.00 lot 50,000.00 50,000.00
Site Investigation n/a
Soil and Foundation Investigation 1.00 lot 120,000.00 120,000.00

Total Cost ---------------------- P 3,170,000.00


II Stage 11 Construction Phase
1.0 General Provisions
1.1 Right of Way 1.00 lot
Description Quantity Unit Unit Cost Amount
Rental of Space for Temporary Field Office, Storage of
Materials/Bunkhouse 12.00 lot 15,000.00 P 180,000.00

Total Cost ---------------------- P 180,000.00

1.2 Permits 1.00 lot


Description Quantity Unit Unit Cost Amount
Demolition Permit 1.00 lot 10,000.00 P 10,000.00
Building Permit 1.00 lot 75,000.00 75,000.00

Total Cost ---------------------- P 85,000.00

1.3 Temporary Field Office & Facilities


1.3.1 Field Office 25.00 sq.m.
a. Materials
Description Quantity Unit Unit Cost Amount
Marine Plywood 1/4" thick 20.00 sheets 452.00 P 9,040.00
Coco Lumber 641.00 BF 26.00 16,666.00
GI Sheets 30.00 sheets 525.00 15,750.00
Lean Concrete Flooring 2.00 kgs 126.00 252.00
Roofing Nails 25.00 sq.m. 315.00 7,875.00
Assrted CWN 7.00 kgs 75.00 525.00
Scaffoldings 1.00 lot 3,500.00 3,500.00

Total Material Cost ------------ P 53,608.00


b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 8 8 600.00 P 4,800.00
Foreman 1 8 8 520.00 4,160.00
Skilled Laborer 3 8 24 350.00 8,400.00
Unskilled Laborer 4 8 32 250.00 8,000.00

Total Labor Cost ------------ P 25,360.00


Summary:
a. Materials Cost 53,608.00
b. Equipment Cost -
c. Labor Cost 25,360.00
Total Item Cost P 78,968.00
Item Unit Cost /sq.m. 3,158.72

1.3.2Office Eqpmt., Furnitures & Fixtures 1.00 lot


Description Quantity Unit Unit Cost Amount
Office Table & Chair (ordinary) 2.00 sets 1,500.00 P 3,000.00
Computer, Type-notebook, 2.3 kgs, Screen size 35-60cm, Std. Memory-8GB,
HDC -750 GB 1.00 unit 70,000.00 70,000.00

Printer - 4 in 1 Brother MFC-J6910DW 1.00 unit 28,000.00 28,000.00

Total Cost ---------------------- P 101,000.00

1.4 Utilities (Water and Electrical) 1.00 lot


Description Quantity Unit Unit Cost Amount
Water and Electric Bills 15.00 mo's 15,000.00 P 225,000.00

Total Cost ---------------------- P 225,000.00

1.5 Board Up - Perimeter Protection & Barrier 110.00 lm


a. Materials
Description Quantity Unit Unit Cost Amount
Coco Lumber 2"x2"x10' 900.00 sheets 26.00 P 23,400.00
Tarpaulin 8' 120.00 BF 156.00 18,720.00
Marine Plywood 13.00 sheets 452.00 5,876.00
CW Nails 20.00 kgs 75.00 1,500.00

Total Material Cost ------------ P 49,496.00

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 6 6 600.00 P 3,600.00
Foreman 1 6 6 520.00 3,120.00
Skilled Laborer 3 6 18 350.00 6,300.00
Unskilled Laborer 4 6 24 250.00 6,000.00

Total Labor Cost ------------ P 19,020.00

Summary:
a. Materials Cost 49,496.00
b. Equipment Cost -
c. Labor Cost 19,020.00
Total Item Cost P 68,516.00
Item Unit Cost /ln.m. 622.87

2.0 Sitework
2.1 Site Demolition
Clearing and Grubbing 1.00 lot
Demolition/Removal of the following existing structures: 820.00 sq.m.

One (1) storey Bldg. (concrete) 480.00 sq.m.


a. Materials None

b. Equipment
No. of Rental Rate /
Designation No. of Hours Total Amount
Equipments Hour
Crawler Mounted Backhoe w/ breaker 1 72 2,500.00 P 180,000.00

Total Operational Cost ------------ P 180,000.00

c. Labor
Manual Labor for clearing/Grubbing 820.00 sq.m.
Disposal of Debris 1.00 lot

Designation No. of No. of Days Man-Days Rate / Day Amount


Personnel
Project Engineer 1 14 14 600.00 P 8,400.00
Foreman 1 14 14 520.00 7,280.00
Skilled Laborer 5 14 70 350.00 24,500.00
Unskilled Laborer 9 14 126 250.00 31,500.00

Sub-Total Labor Cost ------------ P 71,680.00

Removal of X-Ray Machine and other


appurtenances by Philips Co. 1.00 unit
Description Quantity Unit Unit Cost Amount
Labor for Removal of X-ray Machine (LS) 1.00 unit 15,000.00 15,000.00

Sub-Total Cost ---------------------- P 15,000.00

Summary:
a. Materials Cost
b. Equipment Cost 180,000.00
c. Labor Cost 86,680.00
Total Item Cost P 266,680.00
Item Unit Cost /lot 266,680.00

2.2 Structural Excavation 349.04 cu.m


(including other imbedded concrete structures)
a. Materials None

b. Equipment

No. of Rental Rate /


Designation No. of Hours Total Amount
Equipments Hour
Hydraulic Crawler Mounted Backhoe, 1 143.00000 2,500.00 P 357,500.00
0.80HP, 0.70cu.m.

Total Operational Cost ------------ P 357,500.00

c. Labor(Re-shaping/correction)
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 6 6 600.00 P 3,600.00
Foreman 1 6 6 520.00 3,120.00
Skilled Laborer 2 6 12 350.00 4,200.00
Unskilled Laborer 4 6 24 250.00 6,000.00

Total Labor Cost ------------ P 16,920.00

Summary:
a. Materials Cost
b. Equipment Cost 357,500.00
c. Labor Cost 16,920.00
Total Item Cost P 374,420.00
Item Unit Cost /cu.m. 1,072.71

2.3 Backfilling 188.50 cu.m


a. Materials None

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 5 5 600.00 P 3,000.00
Foreman 1 5 5 520.00 2,600.00
Skilled Laborer 2 5 10 350.00 3,500.00
Unskilled Laborer 5 5 25 250.00 6,250.00

Total Labor Cost ------------ P 15,350.00

Summary:
a. Materials Cost -
b. Equipment Cost -
c. Labor Cost 15,350.00
Total Item Cost P 15,350.00
Item Unit Cost /cu.m. 81.43

2.4 Filling Materials 663.00 cu.m


a. Materials
Description Quantity Unit Unit Cost Amount
Item 104 Compacted Volume 706.00 cu.m. 380.00 P 268,280.00

Total Material Cost ------------ P 268,280.00

b. Equipment

No. of Rental Rate /


Designation No. of Hours Total Amount
Equipments Hour

Plate Compactor 1 15 550.00 P 8,250.00

Total Operational Cost ------------ P 8,250.00

c. Labor(Spreading/Hauling)
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 15 15 600.00 P 9,000.00
Foreman 1 15 15 520.00 7,800.00
Skilled Laborer 3 15 45 350.00 15,750.00
Unskilled Laborer 7 15 105 250.00 26,250.00

Total Labor Cost ------------ P 58,800.00

Summary:
a. Materials Cost 268,280.00
b. Equipment Cost 8,250.00
c. Labor Cost 58,800.00
Total Item Cost P 335,330.00
Item Unit Cost /cu.m. 505.78

2.4 Base and Sub-base Course 48.75 cu.m


a. Materials
Description Quantity Unit Unit Cost Amount
Item 200 Compacted Volume 48.75 cu.m. 380.00 P 18,525.00

Total Material Cost ------------ P 18,525.00

b. Equipment

Designation No. of No. of Hours Rental Rate / Total Amount


Equipments Hour

Plate Compactor 1 15 550.00 P 8,250.00

Total Operational Cost ------------ P 8,250.00


c. Labor(Spreading/Hauling)
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 7 7 600.00 P 4,200.00
Foreman 1 7 7 520.00 3,640.00
Skilled Laborer 3 7 21 350.00 7,350.00
Unskilled Laborer 7 7 49 250.00 12,250.00

Total Labor Cost ------------ P 27,440.00

Summary:
a. Materials Cost 18,525.00
b. Equipment Cost 8,250.00
c. Labor Cost 27,440.00
Total Item Cost P 54,215.00
Item Unit Cost /cu.m. 1,112.10

2.5 Lay-out, Forms & Scaffoldings 1.00 lot


a. Materials
Description Quantity Unit Unit Cost Amount
Lay-out/Battering Boards: -
Coco Lumber 2"x3" 1,500.00 bd.ft. 26.00 P 39,000.00
Assorted CW Nails 35.00 kgs. 75.00 2,625.00
Scaffoldings: -
Good Lumber 2"x3" 9,620.00 bd.ft. 48.00 461,760.00
Assorted CW Nails 350.00 kgs. 75.00 26,250.00
Formworks: -
Marine Plywood 6.0mmx1.20mx2.40m 535.00 sheets 415.00 222,025.00
Assorted Good Lumber 8,000.00 bd.ft. 48.00 384,000.00
Assorted CW nails 250.00 kgs. 75.00 18,750.00

Total Material Cost ------------ P 1,154,410.00

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 51 51 600.00 P 30,600.00
Foreman 1 51 51 520.00 26,520.00
Skilled Laborer 8 51 408 350.00 142,800.00
Unskilled Laborer 6 51 816 250.00 204,000.00

Total Labor Cost ------------ P 403,920.00

Summary:
a. Materials Cost 1,154,410.00
b. Equipment Cost
c. Labor Cost 403,920.00
Total Item Cost P 1,558,330.00
Item Unit Cost /cu.m. 1,558,330.00

3.0 Concrete /Reinforcement Works


3.1 Foundation
3.1.1 Column Footing 101.69 cu.m.
a. Materials
Description Quantity Unit Unit Cost Amount
Portland cement 950.00 bags 288.00 273,600.00
Washed Sand 53.00 cu.m. 1,800.00 P 95,400.00
Screened Gravel 106.00 cu.m. 1,900.00 201,400.00
RSB: 20mmØ x9m 400.00 pcs. 900.00 360,000.00
16mmØ x6m 13.00 pcs. 395.00 5,135.00
GI Tie Wire 94.00 kgs. 84.00 7,896.00

Total Material Cost ------------ P 943,431.00

b. Equipment

Designation No. of No. of Days Rental Rate / Total Amount


Equipments Day

Concrete Mixer, 1 bagger 1 18 750.00 P 13,500.00


Concrete Vibrator 1 18 750.00 13,500.00
Bar Cutter 1 10 200.00 2,000.00

Total Operational Cost ------------ P 29,000.00

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 44 44 600.00 P 26,400.00
Foreman 1 44 44 520.00 22,880.00
Skilled Laborer 8 44 352 350.00 123,200.00
Unskilled Laborer 16 44 704 250.00 176,000.00

Total Labor Cost ------------ P 348,480.00

Summary:
a. Materials Cost 943,431.00
b. Equipment Cost 29,000.00
c. Labor Cost 348,480.00
Total Item Cost P 1,320,911.00
Item Unit Cost /cu.m. 12,989.59

3.1.2 Footing Tie Beam (FTB) 14.16 cu.m.


a. Materials
Description Quantity Unit Unit Cost Amount
Portland cement 135.00 bags 288.00 38,880.00
Washed Sand 9.00 cu.m. 1,800.00 P 16,200.00
Screened Gravel 18.00 cu.m. 1,900.00 34,200.00
RSB: 16mmØ x 6m 220.00 pcs. 395.00 86,900.00
10mmØ x 6m 260.00 pcs. 155.00 40,300.00
GI Tie Wire 70.00 kgs. 84.00 5,880.00

Total Material Cost ------------ P 222,360.00

b. Equipment

Designation No. of No. of Days Rental Rate / Total Amount


Equipments Day

Concrete Mixer, 1 bagger 1 3 750.00 P 2,250.00


Concrete Vibrator 1 3 750.00 2,250.00
Bar Cutter 1 3 200.00 600.00

Total Operational Cost ------------ P 5,100.00

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 10 10 600.00 P 6,000.00
Foreman 1 10 10 520.00 5,200.00
Skilled Laborer 8 10 80 350.00 28,000.00
Unskilled Laborer 16 10 160 250.00 40,000.00

Total Labor Cost ------------ P 79,200.00

Summary:
a. Materials Cost 222,360.00
b. Equipment Cost 5,100.00
c. Labor Cost 79,200.00
Total Item Cost P 306,660.00
Item Unit Cost /cu.m. 21,656.78

3.1.3 Wall Footing 13.59 cu.m.


a. Materials cu.m.
Description Quantity Unit Unit Cost Amount
Portland cement 129.00 bags 288.00 37,152.00
Washed Sand 8.00 cu.m. 1,800.00 P 14,400.00
Screened Gravel 16.00 cu.m. 1,900.00 30,400.00
RSB: 10mmØ x 6m 39.00 pcs. 155.00 6,045.00
GI Tie Wire 4.00 kgs. 84.00 336.00

Total Material Cost ------------ P 88,333.00

b. Equipment

No. of Rental Rate /


Designation No. of Days Total Amount
Equipments Day

Concrete Mixer, 1 bagger 1 3 750.00 P 2,250.00


Concrete Vibrator 1 3 750.00 2,250.00
Bar Cutter 1 3 200.00 600.00

Total Operational Cost ------------ P 5,100.00

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 7 7 600.00 P 4,200.00
Foreman 1 7 7 520.00 3,640.00
Skilled Laborer 4 7 28 350.00 9,800.00
Unskilled Laborer 8 7 56 250.00 14,000.00

Total Labor Cost ------------ P 31,640.00

Summary:
a. Materials Cost 88,333.00
b. Equipment Cost 5,100.00
c. Labor Cost 31,640.00
Total Item Cost P 125,073.00
Item Unit Cost /cu.m. 9,203.31

3.2 Columns & Vertical Stiffiner 89.04 cu.m.


a. Materials
Description Quantity Unit Unit Cost Amount
Portland cement 890.00 bags 288.00 256,320.00
Washed Sand 54.00 cu.m. 1,800.00 P 97,200.00
Screened Gravel 108.00 cu.m. 1,900.00 205,200.00
RSB: 20mmØ x9m 720.00 pcs. 900.00 648,000.00
16mmØ x6m 35.00 pcs. 395.00 13,825.00
10mmØ x 6m 1,115.00 pcs. 155.00 172,825.00
GI Tie Wire 325.00 kgs. 84.00 27,300.00

Total Material Cost ------------ P 1,420,670.00

b. Equipment

No. of Rental Rate /


Designation No. of Days Total Amount
Equipments Day

Concrete Mixer, 1 bagger 1 30 750.00 P 22,500.00


Concrete Vibrator 1 30 750.00 22,500.00
Bar Cutter 1 30 200.00 6,000.00

Total Operational Cost ------------ P 51,000.00

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 67 67 600.00 P 40,200.00
Foreman 1 67 67 520.00 34,840.00
Skilled Laborer 8 67 536 350.00 187,600.00
Unskilled Laborer 16 67 1072 250.00 268,000.00

Total Labor Cost ------------ P 530,640.00

Summary:
a. Materials Cost 1,420,670.00
b. Equipment Cost 51,000.00
c. Labor Cost 530,640.00
Total Item Cost P 2,002,310.00
Item Unit Cost /cu.m. 22,487.76

3.3 Beams 14.16 cu.m.


3.3.1 Ground Floor Beam
a. Materials
Description Quantity Unit Unit Cost Amount
Portland cement 142.00 bags 288.00 40,896.00
Washed Sand 9.00 cu.m. 1,800.00 P 16,200.00
Screened Gravel 18.00 cu.m. 1,900.00 34,200.00
RSB: 16mmØ x 6m 220.00 pcs. 395.00 86,900.00
10mmØ x 6m 260.00 pcs. 155.00 40,300.00
GI Tie Wire 107.00 kgs. 84.00 8,988.00

Total Material Cost ------------ P 227,484.00

b. Equipment

No. of Rental Rate /


Designation No. of Days Total Amount
Equipments Day

Concrete Mixer, 1 bagger 1 3 750.00 P 2,250.00


Concrete Vibrator 1 3 750.00 2,250.00
Bar Cutter 1 5 200.00 1,000.00

Total Operational Cost ------------ P 5,500.00

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 10 10 600.00 P 6,000.00
Foreman 1 10 10 520.00 5,200.00
Skilled Laborer 8 10 80 350.00 28,000.00
Unskilled Laborer 16 10 160 250.00 40,000.00

Total Labor Cost ------------ P 79,200.00

Summary:
a. Materials Cost 227,484.00
b. Equipment Cost 5,500.00
c. Labor Cost 79,200.00
Total Item Cost P 312,184.00
Item Unit Cost /cu.m. 22,046.89

3.3.2 Second Floor Beam 31.97 cu.m.


a. Materials
Description Quantity Unit Unit Cost Amount
Portland cement 320.00 bags 288.00 92,160.00
Washed Sand 20.00 cu.m. 1,800.00 P 36,000.00
Screened Gravel 40.00 cu.m. 1,900.00 76,000.00
RSB: 20mmØ x 6m 277.00 pcs. 900.00 249,300.00
16mmØ x 6m 594.00 pcs. 395.00 234,630.00
10mmØ x 6m 595.00 pcs. 155.00 92,225.00
GI Tie Wire 230.00 kgs. 84.00 19,320.00

Total Material Cost ------------ P 799,635.00

b. Equipment

Designation No. of No. of Days Rental Rate / Total Amount


Equipments Day

Concrete Mixer, 1 bagger 1 10 750.00 P 7,500.00


Concrete Vibrator 1 10 750.00 7,500.00
Bar Cutter 1 7 200.00 1,400.00

Total Operational Cost ------------ P 16,400.00

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 35 35 600.00 P 21,000.00
Foreman 1 35 35 520.00 18,200.00
Skilled Laborer 8 35 280 350.00 98,000.00
Unskilled Laborer 16 35 560 250.00 140,000.00

Total Labor Cost ------------ P 277,200.00

Summary:
a. Materials Cost 799,635.00
b. Equipment Cost 16,400.00
c. Labor Cost 277,200.00
Total Item Cost P 1,093,235.00
Item Unit Cost /cu.m. 34,195.65

3.3.3 Third Floor Beam 32.85 cu.m.


a. Materials
Description Quantity Unit Unit Cost Amount
Portland cement 328.00 bags 288.00 94,464.00
Washed Sand 20.00 cu.m. 1,800.00 P 36,000.00
Screened Gravel 40.00 cu.m. 1,900.00 76,000.00
RSB: 20mmØ x 6m 335.00 pcs. 900.00 301,500.00
16mmØ x 6m 485.00 pcs. 395.00 191,575.00
10mmØ x 6m 550.00 pcs. 155.00 85,250.00
GI Tie Wire 204.00 kgs. 84.00 17,136.00

Total Material Cost ------------ P 801,925.00

b. Equipment

No. of Rental Rate /


Designation No. of Days Total Amount
Equipments Day

Concrete Mixer, 1 bagger 1 10 750.00 P 7,500.00


Concrete Vibrator 1 10 750.00 7,500.00
Bar Cutter 1 6 200.00 1,200.00

Total Operational Cost ------------ P 16,200.00

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 35 35 600.00 P 21,000.00
Foreman 1 35 35 520.00 18,200.00
Skilled Laborer 8 35 280 350.00 98,000.00
Unskilled Laborer 16 35 560 250.00 140,000.00

Total Labor Cost ------------ P 277,200.00

Summary:
a. Materials Cost 801,925.00
b. Equipment Cost 16,200.00
c. Labor Cost 277,200.00
Total Item Cost P 1,095,325.00
Item Unit Cost /cu.m. 33,343.23
3.3.4 Roof Deck 40.35 cu.m.
a. Materials
Description Quantity Unit Unit Cost Amount
Portland cement 400.00 bags 288.00 115,200.00
Washed Sand 25.00 cu.m. 1,800.00 P 45,000.00
Screened Gravel 50.00 cu.m. 1,900.00 95,000.00
16mmØ x 6m 612.00 pcs. 395.00 241,740.00
10mmØ x 6m 593.00 pcs. 155.00 91,915.00
GI Tie Wire 128.00 kgs. 84.00 10,752.00

Total Material Cost ------------ P 599,607.00

b. Equipment

No. of Rental Rate /


Designation No. of Days Total Amount
Equipments Day

Concrete Mixer, 1 bagger 1 7 750.00 P 5,250.00


Concrete Vibrator 1 7 750.00 5,250.00
Bar Cutter 1 9 200.00 1,800.00

Total Operational Cost ------------ P 12,300.00

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 29 29 600.00 P 17,400.00
Foreman 1 29 29 520.00 15,080.00
Skilled Laborer 8 29 232 350.00 81,200.00
Unskilled Laborer 16 29 464 250.00 116,000.00

Total Labor Cost ------------ P 229,680.00

Summary:
a. Materials Cost 599,607.00
b. Equipment Cost 12,300.00
c. Labor Cost 229,680.00
Total Item Cost P 841,587.00
Item Unit Cost /cu.m. 20,857.17

3.4 Floor Slab/Steel Decking


3.4.1 Ground Floor 50.68 cu.m.
a. Materials
Description Quantity Unit Unit Cost Amount
Portland cement 478.00 bags 288.00 137,664.00
Washed Sand 27.00 cu.m. 1,800.00 P 48,600.00
Screened Gravel 54.00 cu.m. 1,900.00 102,600.00
RSB: 10mmØ x 6m 370.00 pcs. 155.00 57,350.00
GI Tie Wire 26.00 kgs. 84.00 2,184.00

Total Material Cost ------------ P 348,398.00

b. Equipment

Designation No. of No. of Days Rental Rate / Total Amount


Equipments Day

Concrete Mixer, 1 bagger 1 8 750.00 P 6,000.00


Concrete Vibrator 1 8 750.00 6,000.00
Bar Cutter 1 5 200.00 1,000.00

Total Operational Cost ------------ P 13,000.00


c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 16 16 600.00 P 9,600.00
Foreman 1 16 16 520.00 8,320.00
Skilled Laborer 8 16 128 350.00 44,800.00
Unskilled Laborer 16 16 256 250.00 64,000.00

Total Labor Cost ------------ P 126,720.00

Summary:
a. Materials Cost 348,398.00
b. Equipment Cost 13,000.00
c. Labor Cost 126,720.00
Total Item Cost P 488,118.00
Item Unit Cost /cu.m. 9,631.37

3.4.2 Steel Decking (2nd Flr and third floor) 1,066.00 sq.m.
a. Materials
Description Quantity Unit Unit Cost Amount
Structural Web Type Steel Decking 1,066.00 sq.m. 966.00 1,029,756.00

Total Material Cost ------------ P 1,029,756.00

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 46 46 600.00 P 27,600.00
Foreman 1 46 46 520.00 23,920.00
Skilled Laborer 8 46 368 350.00 128,800.00
Unskilled Laborer 16 46 736 250.00 184,000.00

Total Labor Cost ------------ P 364,320.00

Summary:
a. Materials Cost 1,029,756.00
b. Equipment Cost -
c. Labor Cost 364,320.00
Total Item Cost P 1,394,076.00
Item Unit Cost /cu.m. 1,307.76

3.4.3 Roof Deck with Water Proofing 64.21 cu.m.


a. Materials
Description Quantity Unit Unit Cost Amount
Pre-Mix Concrete 3,500 psi 65.00 cu.m. 5,000.00 P 325,000.00
Portland cement 207.00 bags 288.00 59,616.00
Sahara Cement 196.00 packs 35.00 6,860.00
Plexi Bond 52.00 gals 825.00 42,900.00
Washed Sand 16.00 cu.m. 1,800.00 28,800.00
RSB: 12mmØ x 6m 369.00 pcs. 240.00 88,560.00
10mmØ x 6m 369.00 pcs. 155.00 57,195.00
GI Tie Wire 26.00 kgs. 84.00 2,184.00

Total Material Cost ------------ P 611,115.00


b. Equipment

No. of Rental Rate /


Designation No. of Days Total Amount
Equipments Day
Concrete Vibrator 1 3 750.00 2,250.00
Bar Cutter 1 20 200.00 4,000.00

Total Operational Cost ------------ P 6,250.00

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 29 29 600.00 P 17,400.00
Foreman 1 29 29 520.00 15,080.00
Skilled Laborer 8 29 232 350.00 81,200.00
Unskilled Laborer 16 29 464 250.00 116,000.00

Total Labor Cost ------------ P 229,680.00

Summary:
a. Materials Cost 611,115.00
b. Equipment Cost 6,250.00
c. Labor Cost 229,680.00
Total Item Cost P 847,045.00
Item Unit Cost /cu.m. 13,191.79

3.5 Ramp and Stairs 20.73 cu.m.


Ramp - Exterior
Stairs - Interior and Exterior
a. Materials
Description Quantity Unit Unit Cost Amount
Portland cement 204.00 bags 288.00 58,752.00
Washed Sand 14.00 cu.m. 1,800.00 P 25,200.00
Screened Gravel 28.00 cu.m. 1,900.00 53,200.00
RSB: 10mmØ x 6m 172.00 pcs. 155.00 26,660.00
12mmØx 6m 97.00 pcs. 240.00 23,280.00
16mmØx 6m 145.00 pcs. 395.00 57,275.00
GI Tie Wire 36.00 kgs. 84.00 3,024.00

Total Material Cost ------------ P 247,391.00

b. Equipment

Designation No. of No. of Days Rental Rate / Total Amount


Equipments Day

Concrete Mixer, 1 bagger 1 8 750.00 P 6,000.00


Concrete Vibrator 1 8 750.00 6,000.00
Bar Cutter 1 5 200.00 1,000.00

Total Operational Cost ------------ P 13,000.00

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 14 14 600.00 P 8,400.00
Foreman 1 14 14 520.00 7,280.00
Skilled Laborer 8 14 84 350.00 29,400.00
Unskilled Laborer 16 14 168 250.00 42,000.00

Total Labor Cost ------------ P 87,080.00

Summary:
a. Materials Cost 247,391.00
b. Equipment Cost 13,000.00
c. Labor Cost 87,080.00
Total Item Cost P 347,471.00
Item Unit Cost /cu.m. 16,761.75

3.6 Driveway 12.14 cu.m.


a. Materials
Description Quantity Unit Unit Cost Amount
Portland cement 121.00 bags 288.00 34,848.00
Washed Sand 7.00 cu.m. 1,800.00 P 12,600.00
Screened Gravel 15.00 cu.m. 1,900.00 28,500.00
12mmØx 6m 122.00 pcs. 240.00 29,280.00
GI Tie Wire 10.00 kgs. 84.00 840.00

Total Material Cost ------------ P 106,068.00

b. Equipment

No. of Rental Rate /


Designation No. of Days Total Amount
Equipments Day

Concrete Mixer, 1 bagger 1 4 750.00 P 3,000.00


Concrete Vibrator 1 4 750.00 3,000.00
Bar Cutter 1 2 200.00 400.00

Total Operational Cost ------------ P 6,400.00

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 9 9 600.00 P 5,400.00
Foreman 1 9 9 520.00 4,680.00
Skilled Laborer 8 9 36 350.00 12,600.00
Unskilled Laborer 16 9 63 250.00 15,750.00

Total Labor Cost ------------ P 38,430.00

Summary:
a. Materials Cost 106,068.00
b. Equipment Cost 6,400.00
c. Labor Cost 38,430.00
Total Item Cost P 150,898.00
Item Unit Cost /cu.m. 12,429.82

3.7 Concrete Counter 3.30 cu.m.


a. Materials
Description Quantity Unit Unit Cost Amount
Portland cement 33.00 bags 288.00 9,504.00
Washed Sand 2.00 cu.m. 1,800.00 P 3,600.00
Screened Gravel 4.00 cu.m. 1,900.00 7,600.00
10mmØx 6m 55.00 pcs. 155.00 8,525.00
GI Tie Wire 6.00 kgs. 84.00 504.00

Total Material Cost ------------ P 29,733.00

b. Equipment

No. of Rental Rate /


Designation No. of Days Total Amount
Equipments Day
Concrete Mixer, 1 bagger 1 1 750.00 P 750.00
Bar Cutter 1 1 200.00 200.00

Total Operational Cost ------------ P 950.00

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 4 4 600.00 P 2,400.00
Foreman 1 4 4 520.00 2,080.00
Skilled Laborer 2 4 8 350.00 2,800.00
Unskilled Laborer 3 4 12 250.00 3,000.00

Total Labor Cost ------------ P 10,280.00

Summary:
a. Materials Cost 29,733.00
b. Equipment Cost 950.00
c. Labor Cost 10,280.00
Total Item Cost P 40,963.00
Item Unit Cost /cu.m. 12,413.03

4.0 Masonry Works


4.1 Ground Floor 853.00 sq.m.
Interior Wall 500.00 sq.m
Exterior Wall 353.00 sq.m
a. Materials
Description Quantity Unit Unit Cost Amount
Portland cement 608.00 bags 288.00 P 175,104.00
CHB 0.10mx0.20 x 0.40m 6,500.00 cu.m. 17.00 110,500.00
CHB 0.15mx0.20 x 0.40m 4,630.00 cu.m. 22.00 101,860.00
Washed Sand 54.00 cu.m. 1,800.00 97,200.00
RSB: 10mmØ x 6m 568.00 pcs. 155.00 88,040.00
GI Tie Wire 52.00 kgs. 84.00 4,368.00

Total Material Cost ------------ P 577,072.00

b. Equipment

Designation No. of No. of Days Rental Rate / Total Amount


Equipments Day

Concrete Mixer, 1 bagger 1 15 750.00 P 11,250.00


Bar Cutter 1 10 200.00 2,000.00

Total Operational Cost ------------ P 13,250.00

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 35 35 600.00 P 21,000.00
Foreman 1 35 35 520.00 18,200.00
Skilled Laborer 8 35 280 350.00 98,000.00
Unskilled Laborer 8 35 280 250.00 70,000.00

Total Labor Cost ------------ P 207,200.00

Summary:
a. Materials Cost 577,072.00
b. Equipment Cost 13,250.00
c. Labor Cost 207,200.00
Total Item Cost P 797,522.00
Item Unit Cost /cu.m. 934.96

4.2 Second Floor 884.00 sq.m.


Interior Wall 582.00 sq.m
Exterior Wall 302.00 sq.m
a. Materials
Description Quantity Unit Unit Cost Amount
Portland cement 598.00 bags 288.00 P 172,224.00
CHB 0.10mx0.20 x 0.40m 7,600.00 cu.m. 17.00 129,200.00
CHB 0.15mx0.20 x 0.40m 3,960.00 cu.m. 22.00 87,120.00
Washed Sand 53.00 cu.m. 1,800.00 95,400.00
RSB: 10mmØ x 6m 578.00 pcs. 155.00 89,590.00
GI Tie Wire 58.00 kgs. 84.00 4,872.00

Total Material Cost ------------ P 578,406.00

b. Equipment

No. of Rental Rate /


Designation No. of Days Total Amount
Equipments Day

Concrete Mixer, 1 bagger 1 16 750.00 P 12,000.00


Bar Cutter 1 10 200.00 2,000.00

Total Operational Cost ------------ P 14,000.00

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 35 35 600.00 P 21,000.00
Foreman 1 35 35 520.00 18,200.00
Skilled Laborer 8 35 280 350.00 98,000.00
Unskilled Laborer 8 35 280 250.00 70,000.00

Total Labor Cost ------------ P 207,200.00

Summary:
a. Materials Cost 578,406.00
b. Equipment Cost 14,000.00
c. Labor Cost 207,200.00
Total Item Cost P 799,606.00
Item Unit Cost /sq.m. 904.53

5.0 Metal Works


5.1 Metal Works 928.00 sq.m.
Stair Railings Interior/Exterior (Grnd-3rd Floor) 928.00 sq.m.

a. Materials
Description Quantity Unit Unit Cost Amount
2” dia.x 6m Stainless Pipe Sch. 20 33.00 pcs. 4,725.00 P 155,925.00
1/4” dia.x 6m Stainless Pipe Sch. 20 19.00 pcs. 1,180.00 22,420.00
16mm dia.x 6m Steel Square Bar 78.00 pcs. 819.00 63,882.00
16mm dia.x 6m Stainless Round Bar 36.00 pcs. 819.00 29,484.00
30mm dia.Stainless Pipe 6.00 pcs. 1,180.00 7,080.00
Welding Rod(Stainless) 20.00 kgs. 240.00 4,800.00
Cut off wheel Blade 14' 3.00 pcs. 630.00 1,890.00
Metal Primer 3.00 gals 504.00 1,512.00
Paint Thinner 2.00 gals 399.00 798.00
Paint Brush 2” 3.00 pcs. 47.00 141.00
Consumable 1.00 lot 5,000.00 5,000.00
Total Material Cost ------------ P 292,932.00

b. Equipment

Designation No. of No. of Days Rental Rate / Total Amount


Equipments Day

Welding Machine 1 12 350.00 P 4,200.00


Cut off Wheel Machine 1 12 350.00 4,200.00

Total Operational Cost ------------ P 8,400.00

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 26 26 600.00 P 15,600.00
Foreman 1 26 26 520.00 13,520.00
Skilled Laborer 5 26 130 350.00 45,500.00
Unskilled Laborer 5 26 130 250.00 32,500.00

Total Labor Cost ------------ P 107,120.00

Summary:
a. Materials Cost 292,932.00
b. Equipment Cost 8,400.00
c. Labor Cost 107,120.00
Total Item Cost P 408,452.00
Item Unit Cost /sq.m. 440.14

6.0 Architectural Finishes


6.1 Cement Plaster Finishes (Wall, Columns & Beams) 3,727.00 sq.m.
Stair Railings Interior/Exterior (Grnd-3rd Floor) 928.00 sq.m.

a. Materials
Description Quantity Unit Unit Cost Amount
Portland cement 1,680.00 bags 288.00 P 483,840.00
Washed Sand 93.00 cu.m. 1,800.00 167,400.00

Total Material Cost ------------ P 651,240.00

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 47 47 600.00 P 28,200.00
Foreman 1 47 47 520.00 24,440.00
Skilled Laborer 10 47 470 350.00 164,500.00
Unskilled Laborer 10 47 470 250.00 117,500.00

Total Labor Cost ------------ P 334,640.00

Summary:
a. Materials Cost 651,240.00
b. Equipment Cost -
c. Labor Cost 334,640.00
Total Item Cost P 985,880.00
Item Unit Cost /sq.m. 264.52

6.2 Door and Windows (Ground & 2nd Floor)


6.2.1 Doors 1.00 lot
a. Materials
Description Quantity Unit Unit Cost Amount
Ground Floor 78.89 sq.m
D-1 (7.10 x 3.40m.) 1.00 sets 110,985.00 110,985.00
½" THK. TEMPERED GLASS ON POWDER COATED
ALUMINUM FRAME SLIDING DOOR
100x50x1.2mm THK. ALUMINUM FRAME
1"x12" WOOD OR STAINLESS STEEL CLADDING
D-2 (1.60 x 2.40m.) 2.00 sets 20,160.00 40,320.00
½" THK. TEMPERED GLASS ON POWDER COATED
ALUMINUM FRAME DOUBLE SWING DOOR
100x50x1.2mm THK. ALUMINUM FRAME
1"x12" WOOD OR STAINLESS STEEL CLADDING BOTH SIDES
D-3 (1.10 x 2.40m.) 2.00 sets 13,860.00 27,720.00
½" THK. TEMPERED GLASS ON POWDER COATED
ALUMINUM FRAME SWING DOOR
100x50x1.2mm THK. ALUMINUM FRAME
1"x12" WOOD OR STAINLESS STEEL CLADDING
D-4 (1.10 x 2.10m.) 1.00 sets 12,128.00 12,128.00
50mm THK. WOODEN FLUSH DOOR
PAINTED FINISH
150x50mm WOOD STAIN FINISH DOOR JAMB
1"x12" WOOD OR STAINLESS STEEL CLADDING
D-5 (0.70 x 2.10m.) 4.00 sets 7,718.00 30,872.00
50mm THK. WOODEN FLUSH DOOR
PAINTED FINISH
150x50mm WOOD STAIN FINISH DOOR JAMB
USE ⅜" THK. MARINE PLYWOOD
ON 2"x6" DOOR FRAME
D-6 (0.60 x 2.10m.) 2.00 sets 6,615.00 13,230.00
50mm THK. WOODEN FLUSH DOOR
PAINTED FINISH
USE ⅜" THK. MARINE PLYWOOD
ON 2"x6" DOOR FRAME
D-7 (0.80 x 2.10m.) 5.00 sets 8,820.00 44,100.00
50mm THK. WOODEN FLUSH DOOR
PAINTED FINISH
USE ⅜" THK. MARINE PLYWOOD
ON 2"x6" DOOR FRAME
D-8 (0.70 x 2.10m.) 5.00 sets 7,718.00 38,590.00
50mm THK. WOODEN FLUSH DOOR
PAINTED FINISH
USE ⅜" THK. MARINE PLYWOOD
ON 2"x6" DOOR FRAME
D-14 (0.90 x 2.10m.) 1.00 sets 9,923.00 9,923.00
50mm THK. WOODEN FLUSH DOOR
PAINTED FINISH
USE ⅜" THK. MARINE PLYWOOD
ON 2"x6" DOOR FRAME
D-15 (0.90 x 2.10m.) 1.00 sets 9,923.00 9,923.00
50mm THK. LEADER DOOR
PAINTED FINISH
D-16 (0.80 x 2.10m.) 5.00 sets 8,820.00 44,100.00
PANELED TYPE SWING DOOR
w/ 6mm THK. CLEAR GLASS PAINTED FINISH
USE ⅜" THK. MARINE PLYWOOD
150x50mm WOOD STAIN FINISH DOOR JAMB
D-17 (1.50 x 2.10m.) 1.00 sets 16,538.00 16,538.00
50mm PANELED TYPE SWING DOOR
PAINTED FINISH
USE ⅜" THK. MARINE PLYWOOD
150x50mm WOOD STAIN FINISH DOOR JAMB
2nd Floor 56.49 sq.m.
D-6 (0.60 x 2.10m.) 3.00 sets 6,615.00 19,845.00
50mm THK. WOODEN FLUSH DOOR
PAINTED FINISH
USE ⅜" THK. MARINE PLYWOOD
ON 2"x6" DOOR FRAME
D-7 (0.80 x 2.10m.) 5.00 sets 8,820.00 44,100.00
50mm THK. WOODEN FLUSH DOOR
PAINTED FINISH
USE ⅜" THK. MARINE PLYWOOD
ON 2"x6" DOOR FRAME
D-7a (0.70 x 2.10m.) 1.00 sets 7,718.00 7,718.00
50mm THK. WOODEN FLUSH DOOR
PAINTED FINISH
USE ⅜" THK. MARINE PLYWOOD
ON 2"x6" DOOR FRAME
D-8 (0.70 x 2.10m.) 8.00 sets 7,718.00 61,744.00
50mm THK. WOODEN FLUSH DOOR
PAINTED FINISH
USE ⅜" THK. MARINE PLYWOOD
ON 2"x6" DOOR FRAME
D-12 (0.90 x 2.10m.) 1.00 sets 9,923.00 9,923.00
50mm THK. WOODEN FLUSH DOOR
PAINTED FINISH
USE ⅜" THK. MARINE PLYWOOD
ON 2"x6" DOOR FRAME
D-13 (0.80 x 2.10m.) 1.00 sets 8,820.00 8,820.00
PANIC DOOR SERVICE
PRE-PAINTED FINISH
D-16 (0.80 x 2.10m.) 10.00 sets 8,820.00 88,200.00
PANELED TYPE SWING DOOR
w/ 6mm THK. CLEAR GLASS PAINTED FINISH
USE ⅜" THK. MARINE PLYWOOD
150x50mm WOOD STAIN FINISH DOOR JAMB
D-18 (0.70 x 2.10m.) 1.00 sets 7,718.00 7,718.00
½" THK. TEMPERED GLASS ON POWDER COATED
ALUMINUM FRAME SLIDING DOOR
USE ⅜" THK. MARINE PLYWOOD
150x50x1.2mm ALUMINUM FRAME
D-19 (1.60 x 2.10m.) 1.00 sets 17,640.00 17,640.00
½" THK. TEMPERED GLASS ON POWDER COATED
ALUMINUM FRAME SLIDING DOOR
USE ⅜" THK. MARINE PLYWOOD
150x50x1.2mm ALUMINUM FRAME
D-20 (0.80 x 2.10m.) 2.00 sets 7,718.00 15,436.00
½" THK. TEMPERED GLASS ON POWDERCOATED
ALUMINUM FRAME SLIDING DOOR
150x50x1.2mmALUMINUM FRAME
D-21 (1.20 x 2.10m.) 1.00 sets 13,230.00 13,230.00
½" THK. TEMPERED GLASS ON POWDER COATED
ALUMINUM FRAME SLIDING DOOR
150x50x1.2mm ALUMINUM FRAME
1"x12" WOOD OR STAINLESS STEEL CLADDING

Total Material Cost ------------ P 692,803.00

b. Equipment None
c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 40 40 600.00 P 24,000.00
Foreman 1 40 40 520.00 20,800.00
Skilled Laborer 8 40 320 350.00 112,000.00
Unskilled Laborer 8 40 320 250.00 80,000.00

Total Labor Cost ------------ P 236,800.00

Summary:
a. Materials Cost 692,803.00
b. Equipment Cost -
c. Labor Cost 236,800.00
Total Item Cost P 929,603.00
Item Unit Cost /sq.m. 929,603.00

6.2.2 Windows 1.00 lot

a. Materials
Description Quantity Unit Unit Cost Amount
Ground Floor 78.89 sq.m
W-1 (2.85x0.60 & 2.35x1.25m.) 1.00 sets 23,436.00 23,436.00
ALUMINUM FIXED WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-2 (3.70 x 2.60m.) 1.00 sets 48,485.00 48,485.00
ALUMINUM FIXED WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-3 (1.80 x 1.60m.) 2.00 sets 14,515.00 29,030.00
ALUMINUM FIXED WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-4 (1.20 x 0.60m.) 5.00 sets 3,629.00 18,145.00
ALUMINUM FIXED WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-5 (0.60 x 0.60m.) 1.00 sets 1,814.00 1,814.00
ALUMINUM FRAME AWNING WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-6 (3.80 x 0.60m.) 1.00 sets 11,491.00 11,491.00
ALUMINUM FRAME AWNING WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-7 (1.80 x 0.60m.) 1.00 sets 5,443.00 5,443.00
ALUMINUM FRAME AWNING WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-8 (1.80 x 0.60m.) 1.00 sets 5,443.00 5,443.00
ALUMINUM FRAME AWNING WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-9a (3.00 x 1.60m.) 1.00 sets 24,192.00 24,192.00
ALUMINUM FRAME AWNING WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-15 (1.20 x 1.20m.) 3.00 sets 7,258.00 21,774.00
ALUMINUM FRAME SLIDING WINDOW
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-16 (1.80 x 1.60m.) 1.00 sets 10,886.00 10,886.00
ALUMINUM FRAME SLIDING WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-17 (1.20 x 1.60m.) 1.00 sets 9,677.00 9,677.00
ALUMINUM FRAME FIXED GLASS WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-19 (1.20 x 1.20m.)
W-19 (1.20 x 1.20m.) 1.00 sets 7,258.00 7,258.00
ALUMINUM FRAME FIXED GLASS WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-20 (0.70 x 1.20m.) 1.00 sets 4,234.00 4,234.00
ALUMINUM FRAME SLIDING WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-21 (0.90 x 1.20m.) 1.00 sets 5,443.00 5,443.00
ALUMINUM FRAME FIXED/SLIDING WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-22 (1.80 x 1.20m.) 4.00 sets 10,886.00 43,544.00
ALUMINUM FRAME FIXED/SLIDING WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
2nd Floor 112.51 sq.m.
W-3 (1.80 x 1.60m.) 2.00 sets 14,515.00 29,030.00
ALUMINUM FIXED WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-5 (0.60 x 0.60m.) 1.00 sets 1,814.00 1,814.00
ALUMINUM FRAME AWNING WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-7 (1.80 x 0.60m.) 1.00 sets 5,443.00 5,443.00
ALUMINUM FRAME AWNING WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-8 (1.80 x 0.60m.) 1.00 sets 5,443.00 5,443.00
ALUMINUM FRAME AWNING WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-13 (2.40 x 1.20m.) 1.00 sets 14,515.00 14,515.00
ALUMINUM FRAME SLIDING WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-15 (1.20 x 1.20m.) 1.00 sets 7,258.00 7,258.00
ALUMINUM FRAME SLIDING WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-17 (1.20 x 1.60m.) 1.00 sets 9,677.00 9,677.00
ALUMINUM FRAME FIXED GLASS WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-19 (1.20 x 1.20m.) 1.00 sets 7,258.00 7,258.00
ALUMINUM FRAME FIXED GLASS WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-20 (0.70 x 1.20m.) 1.00 sets 4,234.00 4,234.00
ALUMINUM FRAME SLIDING WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-21 (0.90 x 1.20m.) 1.00 sets 5,443.00 5,443.00
ALUMINUM FRAME FIXED/SLIDING WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-23 (1.80 x 1.20m.) 2.00 sets 10,886.00 21,772.00
ALUMINUM FRAME FIXED WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-24 (3.60 x 1.60m.) 1.00 sets 29,030.00 29,030.00
ALUMINUM FRAME SLIDING WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-25 (1.20 x 1.60m.) 3.00 sets 9,677.00 29,031.00
ALUMINUM FRAME SLIDING WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-26 (1.90 x 1.60m.) 1.00 sets 15,322.00 15,322.00
ALUMINUM FRAME SLIDING WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK.POWDER COATED ALUMINUM FRAME
W-28 (1.80 x 1.40m.) 1.00 sets 12,700.00 12,700.00
ALUMINUM FRAME AWNING WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-29 (3.60 x 1.40m.) 1.00 sets 25,402.00 25,402.00
ALUMINUM FRAME AWNING WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-30 (2.70 x 1.40m.) 1.00 sets 19,051.00 19,051.00
ALUMINUM FRAME AWNING WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-31 (2.40 x 3.30m.) 1.00 sets 39,917.00 39,917.00
ALUMINUM FRAME AWNING/FIXED WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-37 (1.20 x 1.60m.) 1.00 sets 9,677.00 9,677.00
ALUMINUM FRAME SLIDING/FIXED WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-38 (0.60 x 1.60m.) 2.00 sets 4,838.00 9,676.00
ALUMINUM FRAME SLIDING/FIXED WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-39 (6.20 x 3.95m.) 1.00 sets 123,430.00 123,430.00
ALUMINUM FRAME AWNING/FIXED WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-39a (1.35 x 3.95m.) 2.00 sets 26,863.00 53,726.00
ALUMINUM FRAME AWNING/FIXED WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-40 (9.90 x 2.05m.) 1.00 sets 49,896.00 49,896.00
ALUMINUM FRAME AWNING/FIXED WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME
W-41 (1.50 x 1.20m.) 4.00 sets 9,072.00 36,288.00
ALUMINUM FRAME FIXED WINDOW
3/16" THK. GLASS ON
100x50x1.2mm THK. POWDER COATED ALUMINUM FRAME

Total Material Cost ------------ P 835,328.00

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 43 43 600.00 P 25,800.00
Foreman 1 43 43 520.00 22,360.00
Skilled Laborer 8 43 344 350.00 120,400.00
Unskilled Laborer 8 43 344 250.00 86,000.00

Total Labor Cost ------------ P 254,560.00

Summary:
a. Materials Cost 835,328.00
b. Equipment Cost -
c. Labor Cost 254,560.00
Total Item Cost P 1,089,888.00
Item Unit Cost /sq.m. 1,089,888.00

6.3 Tilework
6.3.1 Ground Floor 669.00 sq.m.
a. Materials
Description Quantity Unit Unit Cost Amount
Floor Tiles 515.00 sq.m
0.60m x 0.60m Synthetic Granite Tiles 1,214.00 pcs. 295.00 358,130.00
(Off White)
0.60m x 0.60m Synthetic Granite Tiles 123.00 pcs. 295.00 36,285.00
(Non Slip)
0.60m x 0.60m Synthetic Granite Tiles 26.00 pcs. 295.00 7,670.00
0.30m x 0.30m Ceramic Tiles 290.00 pcs. 68.00 19,720.00
Tile Grout 46.00 kgs. 53.00 2,438.00
Portland Cement 184.00 Bags 288.00 52,992.00
Washed Sand 15.00 cu.m. 1,800.00 27,000.00
Consumable 1.00 lot 5,000.00 5,000.00
Wall Tiles 154.00 sq.m
0.30m x 0.40m Glazed Ceramic Tiles 1,345.00 pcs. 80.00 107,600.00
Tile Grout 16.00 kgs. 53.00 848.00
Tile Trim 8' 30.00 pcs. 158.00 4,740.00
Portland Cement 75.00 Bags 288.00 21,600.00
Washed Sand 6.00 cu.m. 1,800.00 10,800.00
Consumable 1.00 lot 4,000.00 4,000.00

Total Material Cost ------------ P 658,823.00

b. Equipment

No. of Rental Rate /


Designation No. of Days Total Amount
Equipments Day

Sanding Machine 1 20 300.00 P 6,000.00

Total Operational Cost ------------ P 6,000.00

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 39 39 600.00 P 23,400.00
Foreman 1 39 39 520.00 20,280.00
Skilled Laborer 8 39 312 350.00 109,200.00
Unskilled Laborer 8 39 312 250.00 78,000.00

Total Labor Cost ------------ P 230,880.00

Summary:
a. Materials Cost 658,823.00
b. Equipment Cost 6,000.00
c. Labor Cost 230,880.00
Total Item Cost P 895,703.00
Item Unit Cost /sq.m. 1,338.87

6.3.2 Second Floor 638.00 sq.m.


a. Materials
Description Quantity Unit Unit Cost Amount
Floor Tiles 486.00 sq.m
0.60m x 0.60m Synthetic Granite Tiles 1,060.00 pcs. 295.00 312,700.00
(Off White)
0.60m x 0.60m Synthetic Granite Tiles 278.00 pcs. 295.00 82,010.00
Anti- Static Anti-Bacterial Homogenous 117.00 sq.m 893.00 104,481.00
Vinyl with Welded Joint
0.30m x 0.30m Ceramic Tiles 326.00 pcs. 68.00 22,168.00
Tile Grout 41.00 kgs. 53.00 2,173.00
Portland Cement 175.00 Bags 288.00 50,400.00
Washed Sand 15.00 cu.m. 1,800.00 27,000.00
Consumable 1.00 lot 2,500.00 2,500.00
Wall Tiles 152.00 sq.m
0.30m x 0.40m Glazed Ceramic Tiles 1,334.00 pcs. 80.00 106,720.00
Tile Grout 19.00 kgs. 53.00 1,007.00
Tile Trim 8' 31.00 pcs. 158.00 4,898.00
Portland Cement 77.00 Bags 288.00 22,176.00
Washed Sand 6.00 cu.m. 1,800.00 10,800.00
Consumable 1.00 lot 1,000.00 1,000.00

Total Material Cost ------------ P 750,033.00

b. Equipment

Designation No. of No. of Days Rental Rate / Total Amount


Equipments Day

Sanding Machine 1 22 300.00 P 6,600.00

Total Operational Cost ------------ P 6,600.00

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 44 44 600.00 P 26,400.00
Foreman 1 44 44 520.00 22,880.00
Skilled Laborer 8 44 352 350.00 123,200.00
Unskilled Laborer 8 44 352 250.00 88,000.00

Total Labor Cost ------------ P 260,480.00

Summary:
a. Materials Cost 750,033.00
b. Equipment Cost 6,600.00
c. Labor Cost 260,480.00
Total Item Cost P 1,017,113.00
Item Unit Cost /sq.m. 1,594.22

6.3.3 Counter Tile and Splashboards (backsplash and side boards) 39.00 lm
a. Materials
Description Quantity Unit Unit Cost Amount
Tile Slab 16mm thick 39.00 lm 2,100.00 81,900.00
Portland Cement 5.00 bags 288.00 1,440.00
Clear Sealant 1.00 tube 368.00 368.00

Total Material Cost ------------ P 83,708.00


b. Equipment

No. of Rental Rate /


Designation No. of Days Total Amount
Equipments Day

Sanding Machine 1 6 300.00 P 1,800.00

Total Operational Cost ------------ P 1,800.00

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 11 11 600.00 P 6,600.00
Foreman 1 11 11 520.00 5,720.00
Skilled Laborer 3 11 33 350.00 11,550.00
Unskilled Laborer 3 11 33 250.00 8,250.00

Total Labor Cost ------------ P 32,120.00

Summary:
a. Materials Cost 83,708.00
b. Equipment Cost 1,800.00
c. Labor Cost 32,120.00
Total Item Cost P 117,628.00
Item Unit Cost /sq.m. 3,016.10

6.4 Ceiling Work


6.4.1 Ground Floor 547.00 sq.m
a. Materials
Description Quantity Unit Unit Cost Amount
Interior Ceiling 463.00 sq.m
3/16" Thk Marine Plywood 19.00 shts. 440.00 8,360.00
600mm x 1200mm Acoustic ceiling Board 142.00 shts. 440.00 62,480.00
6mm Fiber Cement Board 123.00 shts. 440.00 54,120.00
0.40mm x 25mm Wall angle 146.00 pcs. 158.00 23,068.00
0.40mm x 19mm x 50mm Furring Channel 204.00 pcs. 210.00 42,840.00
0.80mm x 12mm x 38mm Carrying Channel 138.00 pcs. 184.00 25,392.00
W-Clip (Double) 1,455.00 pcs. 7.00 10,185.00
Hardi Screw 3/4” 8,225.00 box 0.75 6,168.75
Blind Rivets 5/32x1/2” 17.00 kgs. 420.00 7,140.00
Concrete Nails 1” 15.00 pcs. 105.00 1,575.00
Drill Bit 3/16” 6.00 lot 100.00 600.00
Hanger 0.50mmx25mm Furring Channel 1.00 pcs. 3,000.00 3,000.00
Consumable 1.00 kgs. 1,800.00 1,800.00
Exterior Ceiling and Ventilation 84.00 sq.m
6mm Fiber Cement Board 32.00 shts. 440.00 14,080.00
0.50mm x 25mm Wall angle 21.00 pcs. 158.00 3,318.00
0.50mm x 25mm x25mm Furring Channel 30.00 pcs. 210.00 6,300.00
0.80mm x 12mm x 38mm Carrying Channel 17.00 pcs. 184.00 3,128.00
W-Clip (Double) 263.00 pcs. 7.00 1,841.00
Hardi Screw 3/4” 2,304.00 pcs. 0.75 1,728.00
Blind Rivets 5/32x1/2” 3.00 box 420.00 1,260.00
Concrete Nails 1” 3.00 kgs. 105.00 315.00
Drill Bit 3/16” 1.00 pcs. 100.00 100.00
# 16 G.I. Tie Wire 3.00 kgs. 84.00 252.00
Hanger 0.50mmx25mm Furring Channel 1.00 lot 2,500.00 2,500.00
Consumable 1.00 lot 1,200.00 1,200.00

Total Material Cost ------------ P 282,750.75

b. Equipment None
c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 17 17 600.00 P 10,200.00
Foreman 1 17 17 520.00 8,840.00
Skilled Laborer 8 17 136 350.00 47,600.00
Unskilled Laborer 8 17 136 250.00 34,000.00

Total Labor Cost ------------ P 100,640.00

Summary:
a. Materials Cost 282,750.75
b. Equipment Cost -
c. Labor Cost 100,640.00
Total Item Cost P 383,390.75
Item Unit Cost /sq.m. 700.90

6.4.2 Second Floor 541.00 sq.m


a. Materials
Description Quantity Unit Unit Cost Amount
Interior Ceiling 481.00 sq.m
3/16" Thk Marine Plywood 28.00 shts. 440.00 12,320.00
600mm x 1200mm Acoustic ceiling Board 135.00 shts. 440.00 59,400.00
6mm Fiber Cement Board 122.00 shts. 440.00 53,680.00
0.40mm x 25mm Wall angle 136.00 pcs. 158.00 21,488.00
0.40mm x 19mm x 50mm Furring Channel 189.00 pcs. 210.00 39,690.00
0.80mm x 12mm x 38mm Carrying Channel 108.00 pcs. 184.00 19,872.00
W-Clip (Double) 1,338.00 pcs. 7.00 9,366.00
Hardi Screw 3/4” 8,960.00 box 0.75 6,720.00
Blind Rivets 5/32x1/2” 16.00 kgs. 420.00 6,720.00
Concrete Nails 1” 14.00 pcs. 105.00 1,470.00
Drill Bit 3/16” 6.00 lot 100.00 600.00
# 16 G.I. Tie Wire 14.00 kgs. 84.00 1,176.00
Hanger 0.50mmx25mm Furring Channel 1.00 pcs. 2,500.00 2,500.00
Consumable 1.00 kgs. 1,500.00 1,500.00
Exterior Ceiling and Ventilation 60.00 sq.m
6mm Fiber Cement Board 23.00 shts. 440.00 10,120.00
0.50mm x 25mm Wall angle 15.00 pcs. 45.00 675.00
0.50mm x 25mm x25mm Furring Channel 21.00 pcs. 100.00 2,100.00
0.80mm x 12mm x 38mm Carrying Channel 12.00 pcs. 120.00 1,440.00
W-Clip (Double) 263.00 pcs. 7.00 1,841.00
Hardi Screw 3/4” 1,656.00 pcs. 0.75 1,242.00
Blind Rivets 5/32x1/2” 2.00 box 400.00 800.00
Concrete Nails 1” 2.00 kgs. 100.00 200.00
Drill Bit 3/16” 1.00 pcs. 95.00 95.00
# 16 G.I. Tie Wire 2.00 kgs. 70.00 140.00
Hanger 0.50mmx25mm Furring Channel 1.00 lot 2,500.00 2,500.00
Consumable 1.00 lot 1,000.00 1,000.00

Total Material Cost ------------ P 258,655.00

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 15 15 600.00 P 9,000.00
Foreman 1 15 15 520.00 7,800.00
Skilled Laborer 8 15 120 350.00 42,000.00
Unskilled Laborer 8 15 120 250.00 30,000.00

Total Labor Cost ------------ P 88,800.00

Summary:
a. Materials Cost 258,655.00
b. Equipment Cost -
c. Labor Cost 88,800.00
Total Item Cost P 347,455.00
Item Unit Cost /sq.m. 642.25

6.5 Carpentry Work


6.5.1 Cabinets and Counters 1.00 lot
a. Materials
Description Quantity Unit Unit Cost Amount
3/4” Marine Plywood 52.00 shts. 1,200.00 62,400.00
Good Lumber 2” x 4” x 8' 156.00 shts. 252.00 39,312.00
Assorted CWN 10.00 shts. 75.00 750.00
Cabinet Handle 182.00 pcs. 84.00 15,288.00
Concealed Hinges 182.00 pcs. 47.00 8,554.00
Concrete Nails 3” 2.00 pcs. 105.00 210.00
Consumable 1.00 pcs. 1,550.00 1,550.00
Painting 259.00 box 250.00 64,750.00

Total Material Cost ------------ P 192,814.00

b. Equipment None

c. Labor

Designation No. of No. of Days Man-Days Rate / Day Amount


Personnel
Project Engineer 1 15 15 600.00 P 9,000.00
Foreman 1 15 15 520.00 7,800.00
Skilled Laborer 8 15 120 350.00 42,000.00
Unskilled Laborer 8 15 120 250.00 30,000.00

Total Labor Cost ------------ P 88,800.00

Summary:
a. Materials Cost 192,814.00
b. Equipment Cost -
c. Labor Cost 88,800.00
Total Item Cost P 281,614.00
Item Unit Cost /sq.m. 281,614.00

6.6 Painting
6.6.1 Ground Floor 1,749.00 sq.m
a. Materials
Description Quantity Unit Unit Cost Amount
Ceiling Surfaces Ground 547.00 sq.m
Neutralizer 6.00 gal. 462.00 2,772.00
Latex, Flat 46.00 gal. 535.00 24,610.00
Masonry Putty 22.00 gal. 367.00 8,074.00
Concrete Primer 22.00 gal. 535.00 11,770.00
Sand Paper 150 43.00 pcs. 25.00 1,075.00
Sand Paper 100 10.00 m. 250.00 2,500.00
Roller / Brush 5.00 pcs. 150.00 750.00
Consumables 1.00 lot 5,000.00 5,000.00
Wall Surfaces Exterior Ground 304.00 sq.m
Neutralizer 4.00 gal. 462.00 1,848.00
Latex, Flat 12.00 gal. 535.00 6,420.00
Latex, Gloss 24.00 gal. 630.00 15,120.00
Masonry Putty 12.00 gal. 367.00 4,404.00
Concrete Primer 12.00 pcs. 535.00 6,420.00
Sand Paper 150 34.00 pcs. 25.00 850.00
Sand Paper 100 7.00 m. 250.00 1,750.00
Roller / Brush 3.00 pcs. 150.00 450.00
Consumables 1.00 lot 3,500.00 3,500.00
Wall Surfaces Interior Ground 617.00 sq.m
Neutralizer 6.00 gal. 462.00 2,772.00
Latex, Flat 26.00 gal. 535.00 13,910.00
Masonry Putty 26.00 gal. 367.00 9,542.00
Latex, Semi Gloss 52.00 gal. 630.00 32,760.00
Concrete Primer 26.00 gal. 535.00 13,910.00
Sand Paper 150 17.00 pcs. 25.00 425.00
Sand Paper 100 7.00 m. 250.00 1,750.00
Roller / Brush 5.00 pcs. 150.00 750.00
Consumables 1.00 lot 5,000.00 5,000.00
Wood Surfaces Ground 56.00 sq.m
Enamel, Flatwall 6.00 gal. 650.00 3,900.00
Glazing Putty 6.00 gal. 750.00 4,500.00
Enamel, Semi Gloss 12.00 gal. 735.00 8,820.00
Paint Thinner 18.00 gal. 604.00 10,872.00
Sand Paper 150 30.00 pcs. 25.00 750.00
Sand Paper 100 15.00 m. 250.00 3,750.00
Roller / Brush 4.00 pcs. 150.00 600.00
Consumables 1.00 lot 1,500.00 1,500.00
Steel Surfaces Ground 225.00 sq.m
Enamel, Flatwall 9.00 gal. 650.00 5,850.00
Glazing Putty 9.00 gal. 750.00 6,750.00
Enamel, Semi Gloss 18.00 gal. 735.00 13,230.00
Paint Thinner 27.00 gal. 604.00 16,308.00
Sand Paper 150 14.00 pcs. 25.00 350.00
Sand Paper 100 7.00 m. 250.00 1,750.00
Roller / Brush 3.00 pcs. 150.00 450.00
Consumables 1.00 lot 10,000.00 10,000.00

Total Material Cost ------------ P 267,512.00

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 27 27 600.00 P 16,200.00
Foreman 1 27 27 520.00 14,040.00
Skilled Laborer 8 27 216 350.00 75,600.00
Unskilled Laborer 8 27 216 250.00 54,000.00

Total Labor Cost ------------ P 159,840.00

Summary:
a. Materials Cost 267,512.00
b. Equipment Cost -
c. Labor Cost 159,840.00
Total Item Cost P 427,352.00
Item Unit Cost /sq.m. 244.34

7.0 Plumbing Works


7.1 Fixtures and Accessories 1.00 lot
a. Materials
Description Quantity Unit Unit Cost Amount
Water Closet, Close coupled, Soft Closing 16.00 sets 11,550.00 184,800.00
with fittings & accessories
Urinal with fittings and accessories 5.00 sets 4,200.00 21,000.00
Under Counter Type Lav., Oval, white 16.00 sets 4,040.00 64,640.00
with fittings & accessories
Stainless Steel sink, deep type 5.00 sets 6,300.00 31,500.00
(+/-) 0.20mx0.50mx 1mm
Stainless Steel sink, deep type 6.00 sets 12,600.00 75,600.00
(+/-) 0.30mx0.50mx 1mm (Laboratory)
Scrub-up Stainless Steel sink, knee operated 1.00 set 47,250.00 47,250.00
& soap dispenser, (+/-) 0.30mx0.50mx 1mm
Gooseneck Faucet, stainless coated, heavy duty 11.00 sets 2,415.00 26,565.00
Lavatory Faucet, stainless coated, with hot & cold 16.00 set 1,575.00 25,200.00
Floor Drain 4"x4", stainless 16.00 set 340.00 5,440.00
Mirror, Frameless
0.60mx0.90m 10.00 set 2,467.00 24,670.00
1.20mx0.90m 6.00 set 2,047.00 12,282.00
Toilet Paper Holder stainless type 16.00 set 735.00 11,760.00
Flexible Hoose 1/2" dia 43.00 set 157.00 6,751.00
Consumables 1.00 lot 1,500.00 1,500.00

Total Material Cost ------------ P 538,958.00

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 32 32 600.00 P 19,200.00
Foreman 1 32 32 520.00 16,640.00
Skilled Laborer 8 32 256 350.00 89,600.00
Unskilled Laborer 8 32 256 250.00 64,000.00

Total Labor Cost ------------ P 189,440.00

Summary:
a. Materials Cost 538,958.00
b. Equipment Cost -
c. Labor Cost 189,440.00
Total Item Cost P 728,398.00
Item Unit Cost /unit 728,398.00

7.2 Cold Water Line 1.00 lot


a. Materials
Description Quantity Unit Unit Cost Amount
PE Pipe: 3/4" dia 200.00 lm 53.00 10,600.00
1/2" dia 50.00 lm 42.00 2,100.00
Fittings:
PE Tee 3/4" dia 45.00 pc 147.00 6,615.00
PE Reducer 3/4" x 1/2" dia 45.00 pc 139.00 6,255.00
PE Adaptor 1/2" dia 35.00 pc 100.00 3,500.00
PE Elbow 3/4" dia 40.00 pc 68.00 2,720.00
GI Elbow 1/2" dia 35.00 pc 32.00 1,120.00
Consumables 1.00 lot 2,000.00 2,000.00

Total Material Cost ------------ P 34,910.00

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 5 5 600.00 P 3,000.00
Foreman 1 5 5 520.00 2,600.00
Skilled Laborer 3 5 15 350.00 5,250.00
Unskilled Laborer 3 5 15 250.00 3,750.00

Total Labor Cost ------------ P 14,600.00

Summary:
a. Materials Cost 34,910.00
b. Equipment Cost -
c. Labor Cost 14,600.00
Total Item Cost P 49,510.00
Item Unit Cost /unit 49,510.00

7.3 Waste Waterline /Sewer Line and Vent System 1.00 lot
a. Materials
Description Quantity Unit Unit Cost Amount
VSTR
2" dia x3.0PVC Pipe w/ hub 40.00 pcs. 336.00 13,440.00
PVC Coupling 2" dia 36.00 pcs. 50.00 1,800.00
Downspouts
2" dia x3.0PVC Pipe w/ hub 100.00 pcs. 336.00 33,600.00
PVC Elbow 2" dia 40.00 pcs. 44.00 1,760.00
Waste Water Line
100mm dia PVC Pipe w/ hub 40.00 pcs. 735.00 29,400.00
50mm dia PVC Pipe w/ hub 12.00 pcs. 473.00 5,676.00
PVC Tee Reducer
4"x4"x2" 10.00 pcs. 89.00 890.00
PVC Elbow
4"dia 36.00 pcs. 63.00 2,268.00
2"dia 56.00 pcs. 44.00 2,464.00
PVC Wye reducer
4"x2" 28.00 pcs. 79.00 2,212.00
PVC Wye 4" dia 46.00 pcs. 89.00 4,094.00
PVC Wye 4" dia 10.00 pcs. 68.00 680.00
P Trap
Chrome Plated w/ extended Pipe 28.00 pcs. 189.00 5,292.00
1-3/4"dia 35.00 pcs.
PVC Clean-out 12.00 pcs. 68.00 816.00
Consumables 1.00 lot 2,500.00 2,500.00

Total Material Cost ------------ P 106,892.00

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 9 9 600.00 P 5,400.00
Foreman 1 9 9 520.00 4,680.00
Skilled Laborer 5 9 45 350.00 15,750.00
Unskilled Laborer 5 9 45 250.00 11,250.00

Total Labor Cost ------------ P 37,080.00

Summary:
a. Materials Cost 106,892.00
b. Equipment Cost -
c. Labor Cost 37,080.00
Total Item Cost P 143,972.00
Item Unit Cost /unit 143,972.00

7.4 Storm Drain and Catch Basin 1.00 lot


a. Materials
Description Quantity Unit Unit Cost Amount
4" CHB 400.00 pcs. 17.00 6,800.00
Portland Cement 45.00 bags 288.00 12,960.00
Washed sand 4.00 cu.m. 1,800.00 7,200.00
Gravel 2.00 cu.m. 1,900.00 3,800.00
10mmx6m bars 62.00 pcs. 155.00 9,610.00
#16 Tie Wire 6.00 kls 84.00 504.00
0.15m x 1.0m RCP 25.00 pcs. 262.00 6,550.00
0.30m x 1.0m RCP 80.00 pcs. 525.00 42,000.00

Total Material Cost ------------ P 89,424.00

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 9 9 600.00 P 5,400.00
Foreman 1 9 9 520.00 4,680.00
Skilled Laborer 5 9 45 350.00 15,750.00
Unskilled Laborer 5 9 45 250.00 11,250.00

Total Labor Cost ------------ P 37,080.00

Summary:
a. Materials Cost 89,424.00
b. Equipment Cost -
c. Labor Cost 37,080.00
Total Item Cost P 126,504.00
Item Unit Cost /unit 126,504.00

7.5 Septic Tank (incldg. Excavation works) 2.00 unit


a. Materials
Description Quantity Unit Unit Cost Amount
Portland cement 90.00 pcs. 288.00 25,920.00
CHB 0.10mx0.20,0.40m 650.00 bags 17.00 11,050.00
Washed Sand 10.00 cu.m. 1,800.00 18,000.00
Screened Gravel 10.00 cu.m. 1,900.00 19,000.00
RSB: 12mmØ x 6m 90.00 pcs. 240.00 21,600.00
PVC Tee 100mm dia 8.00 kls 103.00 824.00
Clean out 100mm dia 8.00 pcs. 90.00 720.00
PVC Glue 4.00 pint 79.00 316.00
GI Tie Wire 8.00 kgs 84.00 672.00

Total Material Cost ------------ P 98,102.00

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 12 12 600.00 P 7,200.00
Foreman 1 12 12 520.00 6,240.00
Skilled Laborer 5 12 48 350.00 16,800.00
Unskilled Laborer 5 12 96 250.00 24,000.00

Total Labor Cost ------------ P 54,240.00

Summary:
a. Materials Cost 98,102.00
b. Equipment Cost -
c. Labor Cost 54,240.00
Total Item Cost P 152,342.00
Item Unit Cost /unit 76,171.00

8.0 Electrical
8.1 Ground Floor (Complete) 1.00 lot
a. Materials
Description Quantity Unit Unit Cost Amount
Ground Floor
a. Lighting and Other Fixtures
20 W LED Circular Lamp 43.00 set 1,545.00 66,435.00
5W red incandescent lamp w/ 4"Ø ceiling socket 1.00 set 100.00 100.00
5W LED lamp w/ 4"Ø ceiling socket 9.00 set 320.00 2,880.00
10W LED lamp w/ 4"Ø ceiling socket 2.00 set 450.00 900.00
Pinlight w/ 10W LED lamp 7.00 set 850.00 5,950.00
Pinlight w/ 7W LED lamp 4.00 set 750.00 3,000.00
Pinlight w/ 5W LED lamp 4.00 set 680.00 2,720.00
Chandelier 1.00 set 16,500.00 16,500.00
0.60MmX1.20m Recessed type lighting fixture w/ mirrorized aluminum 9.00 set 1,795.00 16,155.00
reflector & louver
0.30mX1.20m type diffuser
Recessed and 2x16w
type lighting fixtureT8w/LED tubeT8
2x16w lamps
LED tube lamps and 16.00 set 2,250.00 36,000.00
prismatic glass diffuser

LED Emergency Light 15.00 set 1,650.00 24,750.00

Lighted Exit Sign w/ Back-up Battery 2.00 set 1,800.00 3,600.00

Lighted Directional Exit Sign w/ Back-up Battery 2.00 set 2,000.00 4,000.00
Exhaust Fan, Filtered 4.00 set 6,900.00 27,600.00
Exhaust Fan,Room
Emergency Ceiling Mounted,
Lighted 12"x12"
Signage- Single Face Panaflex, 0.225m high red 9.00 set 1,650.00 14,850.00
letters " E MRoom
Emergency E R GLighted
E N C Y Signage-
" on 0.30m x 2.00m
Single Face white background
Panaflex, & ga.#18
0.125m high greenS/S 1.00 set 18,500.00 18,500.00
casing
letters for wall mounting
" EMERGENCY ROOM " on 0.175m x 1.00m white background & ga.#18 1.00 set 4,500.00 4,500.00
S/S casing for wall mounting
Out-patient Lighted Signage- Single Face Panaflex, 0.175m high green letters "
OUT-PATIENT DEPT. " on 0.20m x 1.00m white background & ga.#18 S/S 1.00 set 5,000.00 5,000.00
casing for wall mounting

X-ray Room Lighted Signage- Single Face Panaflex, 0.10m high green letters "
X-RAY ROOM. " on 0.15m x 0.50m white background & ga.#18 S/S casing for 1.00 set 3,000.00 3,000.00
wall mounting

Decorative Ceiling Fan, rotary w/ selector switch 3.00 set 4,800.00 14,400.00

Hand Dryer 6.00 set 6,500.00 39,000.00

b. Switches and Outlets


One Gang Switch 17.00 set 150.00 2,550.00
Two Gang Switch 10.00 set 18,000.00 180,000.00
Three Gang Switch 10.00 set 110.00 1,100.00
Three Way Switch 4.00 set 280.00 1,120.00
Three Gang- Three WaySwitch 4.00 set 550.00 2,200.00
One Gang Convenience Outlet 32.00 set 550.00 17,600.00
Grounding Type Duplex Convenience Outlet 55.00 set 350.00 19,250.00
c. Wires and Conduits
1.6mm TW Wire 6.00 box 2,800.00 16,800.00
3.5 sq.mm. THHN Wire 20.00 box 3,900.00 78,000.00
5.5 sq.mm. THHN Wire 12.00 box 5,850.00 70,200.00
20mmØ uPVC Elect. PNS 14 650.00 pc 76.00 49,400.00
20mmØ uPVC Elect. Elbow 300.00 pc 15.00 4,500.00
20mmØ uPVC Elect. Adaptor w/ Locknut & Bushing 400.00 pc 18.00 7,200.00
40mmØ uPVC Elect. Conduit PNS 14 2.00 pc 220.00 440.00
40mmØ uPVC Elect. Adaptor w/ Locknut & Bushing 2.00 pc 60.00 120.00
50mmØ uPVC Elect. Conduit PNS 14 2.00 pc 260.00 520.00
50mmØ uPVC Elect. Adaptor w/ Locknut & Bushing 4.00 pc 75.00 300.00
65mmØ uPVC Elect. Conduit PNS 14 12.00 pc 520.00 6,240.00
65mmØ uPVC Elect. Elbow 2.00 pc 360.00 720.00
65mmØ uPVC Elect. Adaptor w/ Locknut & Bushing 1.00 pc 80.00 80.00
80mmØ uPVC Elect. Conduit PNS 14 6.00 pc 640.00 3,840.00
80mmØ uPVC Elect. Elbow 2.00 pc 410.00 820.00
80mmØ uPVC Elect. Adaptor w/ Locknut & Bushing 1.00 pc 95.00 95.00
c2. Temporay Power Supply for MDP1
#2 AWG Bare ACSR 55.00 m 35.00 1,925.00
#4/0 AWG Poly AAC 150.00 m 220.00 33,000.00
250MCM Solderless connector 4.00 pc 750.00 3,000.00

d. Distribution Panels
MDP1: Main-500AT,3P,250V
Branches: 1-100AT,3P; 1-125AT,3P;2-200AT,3P
1.00 set 81,950.00 81,950.00
NEMA 1, Ga#18 Pre Painted Enclosure
with Ground Terminal, Surface Mounting
LP1: Main-125AT,3P,250V
Branches: 24-20AT, 2P
1.00 set 27,940.00 27,940.00
NEMA 1, Ga#18 Pre Painted Enclosure
with Ground Terminal, Surface Mounting
PP1: Main-200AT,3P,250V
Main-200AT,3P,250V
1.00 set 31,240.00 31,240.00
NEMA 1, Ga#18 Pre Painted Enclosure
with Ground Terminal, Surface Mounting
PP1A: Main-200AT,3P,250V
Branches: 24-30AT,2P
1.00 set 31,240.00 31,240.00
NEMA 1, Ga#18 Pre Painted Enclosure
with Ground Terminal, Surface Mounting
PXR: Enclosed Circuit Breaker
200AT, 2P, 250V
1.00 set 6,500.00 6,500.00
NEMA 1, Ga#18 Pre Painted Enclosure
with Ground Terminal, Surface Mounting

e. Miscellaneous
Wire Gutter with front hinged cover, Ga.#18, NEMA 1, Pre-painted 2.00 set 5,200.00 10,400.00
PVC Solvent Cement 6.00 ltr 420.00 2,520.00
Electrical Tape (big) 50.00 roll 30.00 1,500.00
Rubber Tape (big) 100.00 roll 120.00 12,000.00
#16 GI Tie Wire 5.00 kg 75.00 375.00
Assorted Hangers, Bolts,Screws,Clamps,Etc. 1.00 lot 12,000.00 12,000.00
Junction Box with cover, PVC 120.00 pc 30.00 3,600.00
Utility Box,PVC 150.00 pc 26.00 3,900.00

Second Floor
a. Lighting and Other Fixtures
20 W LED Circular Lamp 47.00 set 1,545.00 72,615.00
5W LED lamp w/ 4"Ø ceiling socket 9.00 set 320.00 2,880.00
10W LED lamp w/ 4"Ø ceiling socket 2.00 set 450.00 900.00
Pinlight w/ 10W LED lamp 12.00 set 850.00 10,200.00
0.60MmX1.20m Recessed type lighting fixture w/ mirrorized aluminum
13.00 set 1,795.00 23,335.00
reflector & louver type diffuser and 2x16w T8 LED tube lamps
LED Emergency Light 15.00 set 1,650.00 24,750.00

Lighted Exit Sign w/ Back-up Battery 1.00 set 1,800.00 1,800.00

Lighted Single Face Directional Exit Sign w/ Back-up Battery 2.00 set 2,000.00 4,000.00
Lighted Double Face Directional Exit Sign w/ Back-up Battery 1.00 set 2,200.00 2,200.00
Exhaust Fan, Filtered 3.00 set 6,900.00 20,700.00
Exhaust Fan, Ceiling Mounted, 12"x12" 14.00 set 1,650.00 23,100.00

b. Switches and Outlets


One Gang Switch 16.00 set 180.00 2,880.00
Two Gang Switch 14.00 set 220.00 3,080.00
Three Gang Switch 5.00 set 260.00 1,300.00
One Gang Convenience Outlet 36.00 set 180.00 6,480.00
Grounding Type Duplex Convenience Outlet 68.00 set 260.00 17,680.00
Grounding Type Duplex Convenience Outlet w/ weatherproof cover 10.00 set 950.00 9,500.00
ACU Outlet 5.00 set 380.00 1,900.00

c. Wires and Conduits


1.6mm TW Wire 6.00 box 2,800.00 16,800.00
3.5 sq.mm. THHN Wire 22.00 box 3,900.00 85,800.00
5.5 sq.mm. THHN Wire 14.00 box 5,850.00 81,900.00
20mmØ uPVC Elect. PNS 14 680.00 pc 76.00 51,680.00
20mmØ uPVC Elect. Elbow 300.00 pc 15.00 4,500.00
20mmØ uPVC Elect. Adaptor w/ Locknut & Bushing 400.00 pc 18.00 7,200.00
40mmØ uPVC Elect. Conduit PNS 14 2.00 pc 220.00 440.00
40mmØ uPVC Elect. Adaptor w/ Locknut & Bushing 2.00 pc 60.00 120.00
50mmØ uPVC Elect. Conduit PNS 14 2.00 pc 260.00 520.00
50mmØ uPVC Elect. Adaptor w/ Locknut & Bushing 4.00 pc 75.00 300.00
80mmØ uPVC Elect. Conduit PNS 14 8.00 pc 640.00 5,120.00
80mmØ uPVC Elect. Elbow 2.00 pc 410.00 820.00
80mmØ uPVC Elect. Adaptor w/ Locknut & Bushing 1.00 pc 95.00 95.00

c2. Temporay Power Supply for MDP2


#2 AWG Bare ACSR 50.00 m 35.00 1,750.00
#4/0 AWG Poly AAC 135.00 m 220.00 29,700.00
250MCM Solderless connector 4.00 pc 750.00 3,000.00

d. Distribution Panels
MDP2: Main-500AT,3P,250V
Branches: 1-100AT,3P; 1-125AT,3P;2-200AT,3P
1.00 set 81,950.00 81,950.00
NEMA 1, Ga#18 Pre Painted Enclosure
with Ground Terminal, Surface Mounting
LP2: Main-125AT,3P,250V
Branches: 24-20AT, 2P
1.00 set 27,940.00 27,940.00
NEMA 1, Ga#18 Pre Painted Enclosure
with Ground Terminal, Surface Mounting
PP2: Main-200AT,3P,250V
Branches: 10-20AT, 2P; 14-30AT,2P
1.00 set 31,240.00 31,240.00
NEMA 1, Ga#18 Pre Painted Enclosure
with Ground Terminal, Surface Mounting
PP2A: Main-200AT,3P,250V
Branches: 24-30AT,2P
1.00 set 31,240.00 31,240.00
NEMA 1, Ga#18 Pre Painted Enclosure
with Ground Terminal, Surface Mounting

e. Miscellaneous
Wire Gutter with front hinged cover, Ga.#18, NEMA 1, Pre-painted 2.00 set 7,500.00 15,000.00
Assorted Hangers, Bolts,Screws,Clamps,Etc. 1.00 lot 12,000.00 12,000.00
PVC Solvent Cement 7.00 ltr 420.00 2,940.00
Electrical Tape (big) 100.00 roll 30.00 3,000.00
#16 GI Tie Wire 5.00 kg 75.00 375.00
Junction Box with cover, PVC 95.00 pc 30.00 2,850.00
Utility Box,PVC 175.00 pc 26.00 4,550.00
Concrete Pull Box w/ Cover 1.00 lot 5,000.00 5,000.00

Third Floor (Rough-ins only)


a. Conduits, Accessories,& Boxes
20mmØ uPVC Elect. PNS 14 400.00 pc 76.00 30,400.00
20mmØ uPVC Elect. Elbow 220.00 pc 15.00 3,300.00
20mmØ uPVC Elect. Adaptor w/ Locknut & Bushing 300.00 pc 18.00 5,400.00
65mmØ uPVC Elect. Conduit PNS 14 10.00 pc 52.00 520.00
65mmØ uPVC Elect. Elbow 1.00 pc 360.00 360.00
65mmØ uPVC Elect. Adaptor w/ Locknut & Bushing 3.00 pc 80.00 240.00
Junction Box with cover, PVC 120.00 pc 30.00 3,600.00
Utility Box,PVC 130.00 pc 26.00 3,380.00

b. Miscellaneous
PVC Solvent Cement 4.00 ltr 220.00 880.00
Electrical Tape (big) 10.00 roll 30.00 300.00
#16 GI Tie Wire 10.00 kg 75.00 750.00
Rough-ins for Elevator & Dumbwaiter
a. Conduits
20mmØ uPVC Elect. PNS 14 18.00 pc 75.00 1,350.00
40mmØ uPVC Elect. Conduit PNS 14 18.00 pc 220.00 3,960.00
20mmØ uPVC Elect. Elbow 1.00 pc 15.00 15.00
40mmØ uPVC Elect. Elbow 1.00 pc 60.00 60.00

b. Miscellaneous
PVC Solvent Cement, 60cc 2.00 can 75.00 150.00
Electrical Tape (big) 1.00 roll 30.00 30.00
#16 GI Tie Wire 2.00 kg 75.00 150.00

Total Material Cost ------------ P 1,828,000.00

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 120 120 600.00 P 72,000.00
Foreman 1 120 120 520.00 62,400.00
Skilled Laborer 4 120 480 350.00 168,000.00
Unskilled Laborer 8 120 960 250.00 240,000.00

Total Labor Cost ------------ P 542,400.00

Summary:
a. Materials Cost 1,828,000.00
b. Equipment Cost -
c. Labor Cost 542,400.00
Total Item Cost P 2,370,400.00
Item Unit Cost /sq.m. 2,370,400.00

9.0 Fire Safety & Protection System


(Fire Sprinkler System)
9.1 Ground Floor (Complete) 1.00 lot
a. Materials
Description Quantity Unit Unit Cost Amount
Sprinkler Head 1/2" NTP, Pendent, Wet Type, Quick Response, 165°F, Bulb 40.00 pcs 500.00 20,000.00
Type W/ Escutcheon Plate
GI Pipe s.40 25mm x 6m 13.00 pcs 950.00 12,350.00

GI Pipe s.40 30mm x 6m 8.00 pcs 950.00 7,600.00

GI Pipe s.40 50mm x 6m 8.00 pcs 1,650.00 13,200.00


GI Pipe s.40 75mm x 6m 9.00 pcs 492.00 4,428.00
Bell Reducer Threaded 25 x 12 40.00 pcs 60.00 2,400.00
GI Elbow Threaded 25mm x 90° 26.00 pcs 61.00 1,586.00
GI Elbow Threaded 30mm x 90° 6.00 pcs 61.00 366.00
GI Elbow Threaded 50mm x 90° 3.00 pcs 61.00 183.00
GI Elbow Threaded 75mm x 90° 3.00 pcs 61.00 183.00
GI Tee Threaded 25mm x 25mm 13.00 pcs 60.00 780.00
GI Tee Threaded 30mm x 30mm 6.00 pcs 60.00 360.00
GI Tee Threaded 25mm x 50mm x 50mm 13.00 pcs 60.00 780.00
GI Tee Threaded 30mm x 50mm x 50mm 5.00 pcs 60.00 300.00
Nipple Threaded 1x 3 36.00 pcs 250.00 9,000.00
Bolts and Nuts with Washer 5/8 x 2 1/2 110.00 pcs 75.00 8,250.00
Bolt and Nuts 1/2 x 2 1/2 35.00 pcs 600.00 21,000.00
Bolt and Nuts 1/2 x 2 35.00 pcs 900.00 31,500.00
Angle Valve 2 1/2'' Ø 2.00 pcs 4,500.00 9,000.00
Angle Valve 1 1/2'' Ø 1.00 pcs 3,500.00 3,500.00
Gate Valve 2'' Ø 1.00 pcs 5,500.00 5,500.00
Gate Valve 1'' Ø 2.00 pcs 1,500.00 3,000.00
Sight Glass 1'' 1.00 pcs 950.00 950.00
Union Patente 1'' 1.00 pcs 150.00 150.00
Fire Hose 1.00 pcs 18,000.00 18,000.00
U Bolt 1/4"φ x 65mm 66.00 pcs 110.00 7,260.00
Plain Round Bar 3/8 x 6m 12.00 pcs 280.00 3,360.00
B. I. Flange 3'' 8.00 pcs 550.00 4,400.00
Angle Bar 3/16 x 1 1/2 x 1 1/2 x 6 8.00 pcs 550.00 4,400.00
Flat Bar 3/16 x 1 x 6m 8.00 pcs 350.00 2,800.00
Consumable Materials such as Welding Rod, Oxy / Accy, Red Primer, Paint 1.00 lot 15,000.00 15,000.00
Brush, etc

Total Material Cost ------------ P 211,586.00

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 20 20 600.00 P 12,000.00
Foreman 1 20 20 520.00 10,400.00
Skilled Laborer 6 20 120 350.00 42,000.00
Unskilled Laborer 6 20 120 250.00 30,000.00

Total Labor Cost ------------ P 94,400.00

Summary:
a. Materials Cost 211,586.00
b. Equipment Cost -
c. Labor Cost 94,400.00
Total Item Cost P 305,986.00
Item Unit Cost /sq.m. 305,986.00

9.2 Second Floor (Complete) 1.00 lot


a. Materials
Description Quantity Unit Unit Cost Amount
Sprinkler Head 1/2" NTP, Pendent, Wet Type, Quick Response, 165°F, Bulb
44.00 pcs 500.00 22,000.00
Type W/ Escutcheon Plate
GI Pipe s.40 25mm x 6m 8.00 pcs 950.00 7,600.00

GI Pipe s.40 30mm x 6m 6.00 pcs 950.00 5,700.00

GI Pipe s.40 40mm x 6m 2.00 pcs 1,200.00 2,400.00


GI Pipe s.40 50mm x 6m 6.00 pcs 1,650.00 9,900.00
GI Pipe s.40 75mm x 6m 8.00 pcs 492.00 3,936.00
Bell Reducer Threaded 25 x 12 44.00 pcs 60.00 2,640.00
GI Elbow Threaded 25mm x 90° 67.00 pcs 61.00 4,087.00
GI Elbow Threaded 30mm x 90° 20.00 pcs 61.00 1,220.00
GI Elbow Threaded 40mm x 90° 5.00 pcs 61.00 305.00
GI Elbow Threaded 50mm x 90° 10.00 pcs 61.00 610.00
GI Elbow Threaded 75mm x 90° 9.00 pcs 61.00 549.00
GI Tee Threaded 25mm x 25mm 12.00 pcs 60.00 720.00
GI Tee Threaded 30mm x 30mm 8.00 pcs 60.00 480.00
GI Tee Threaded 40mm x 50mm x 50mm 6.00 pcs 60.00 360.00
GI Tee Threaded 25mm x 50mm x 50mm 13.00 pcs 60.00 780.00
Nipple Threaded 1x 3 40.00 pcs 250.00 10,000.00
Bolts and Nuts with Washer 5/8 x 2 1/2 100.00 pcs 75.00 7,500.00
Bolt and Nuts 1/2 x 2 1/2 60.00 pcs 600.00 36,000.00
Bolt and Nuts 1/2 x 2 60.00 pcs 900.00 54,000.00
Angle Valve 2 1/2'' Ø 2.00 pcs 4,500.00 9,000.00
Angle Valve 1 1/2'' Ø 1.00 pcs 3,500.00 3,500.00
Gate Valve 2'' Ø 1.00 pcs 5,500.00 5,500.00
Gate Valve 1'' Ø 2.00 pcs 1,500.00 3,000.00
Sight Glass 1'' 1.00 pcs 950.00 950.00
Union Patente 1'' 1.00 pcs 85.00 85.00
Fire Hose 1.00 pcs 18,000.00 18,000.00
U Bolt 1/4"φ x 65mm 85.00 pcs 110.00 9,350.00
Plain Round Bar 3/8 x 6m 9.00 pcs 280.00 2,520.00
B. I. Flange 4'' 8.00 pcs 550.00 4,400.00
Angle Bar 3/16 x 1 1/2 x 1 1/2 x 6 8.00 pcs 550.00 4,400.00
Flat Bar 3/16 x 1 x 6m 9.00 pcs 350.00 3,150.00
Consumable Materials such as Welding Rod, Oxy / Accy, Red Primer, Paint
1.00 lot 15,000.00 15,000.00
Brush, etc

Total Material Cost ------------ P 249,642.00

b. Equipment None

c. Labor

Designation No. of No. of Days Man-Days Rate / Day Amount


Personnel
Project Engineer 1 24 24 600.00 P 14,400.00
Foreman 1 24 24 520.00 12,480.00
Skilled Laborer 6 24 144 350.00 50,400.00
Unskilled Laborer 6 24 144 250.00 36,000.00

Total Labor Cost ------------ P 113,280.00

Summary:
a. Materials Cost 249,642.00
b. Equipment Cost -
c. Labor Cost 113,280.00
Total Item Cost P 362,922.00
Item Unit Cost /sq.m. 362,922.00

9.3 Third Floor (Complete) 1.00 lot


a. Materials
Description Quantity Unit Unit Cost Amount
Sprinkler Head 1/2" NTP, Pendent, Wet Type, Quick Response, 165°F, Bulb
47.00 pcs 500.00 23,500.00
Type W/ Escutcheon Plate
GI Pipe s.40 25mm x 6m 22.00 pcs 950.00 20,900.00

GI Pipe s.40 30mm x 6m 6.00 pcs 950.00 5,700.00

GI Pipe s.40 40mm x 6m 9.00 pcs 1,200.00 10,800.00


GI Pipe s.40 50mm x 6m 8.00 pcs 1,650.00 13,200.00
GI Pipe s.40 75mm x 6m 10.00 pcs 492.00 4,920.00
Bell Reducer Threaded 25 x 12 47.00 pcs 60.00 2,820.00
GI Elbow Threaded 25mm x 90° 25.00 pcs 61.00 1,525.00
GI Elbow Threaded 30mm x 90° 10.00 pcs 61.00 610.00
GI Elbow Threaded 40mm x 90° 4.00 pcs 61.00 244.00
GI Elbow Threaded 75mm x 90° 4.00 pcs 61.00 244.00
GI Tee Threaded 25mm x 25mm 10.00 pcs 60.00 600.00
GI Tee Threaded 30mm x 30mm 6.00 pcs 60.00 360.00
GI Tee Threaded 40mm x 40mm 8.00 pcs 60.00 480.00
GI Tee Threaded 40mm x 65mm x 65mm 4.00 pcs 60.00 240.00
Nipple Threaded 1x 3 45.00 pcs 250.00 11,250.00
Bolts and Nuts with Washer 5/8 x 2 1/2 100.00 pcs 75.00 7,500.00
Bolt and Nuts 1/2 x 2 1/2 70.00 pcs 600.00 42,000.00
Bolt and Nuts 1/2 x 2 70.00 pcs 900.00 63,000.00
Angle Valve 2 1/2'' Ø 2.00 pcs 4,500.00 9,000.00
Angle Valve 1 1/2'' Ø 1.00 pcs 3,500.00 3,500.00
Gate Valve 2'' Ø 1.00 pcs 5,500.00 5,500.00
Gate Valve 1'' Ø 2.00 pcs 1,500.00 3,000.00
Sight Glass 1'' 1.00 pcs 950.00 950.00
Union Patente 1'' 1.00 pcs 85.00 85.00
Fire Hose 1.00 pcs 18,000.00 18,000.00
U Bolt 1/4"φ x 65mm 85.00 pcs 110.00 9,350.00
Plain Round Bar 3/8 x 6m 17.00 pcs 280.00 4,760.00
B. I. Flange 4'' 13.00 pcs 550.00 7,150.00
Angle Bar 3/16 x 1 1/2 x 1 1/2 x 6 8.00 pcs 550.00 4,400.00
Flat Bar 3/16 x 1 x 6m 17.00 pcs 350.00 5,950.00
Consumable Materials such as Welding Rod, Oxy / Accy, Red Primer, Paint 1.00 lot 15,000.00 15,000.00
Brush, etc

Total Material Cost ------------ P 296,538.00

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 29 29 600.00 P 17,400.00
Foreman 1 29 29 520.00 15,080.00
Skilled Laborer 6 29 174 350.00 60,900.00
Unskilled Laborer 6 29 174 250.00 43,500.00

Total Labor Cost ------------ P 136,880.00

Summary:
a. Materials Cost 296,538.00
b. Equipment Cost -
c. Labor Cost 136,880.00
Total Item Cost P 433,418.00
Item Unit Cost /sq.m. 433,418.00

10.0 Mechanical Works


10.1. Airconditioning Units
10.1.1 Ground Floor 1.00 lot
a. Materials
Description Quantity Unit Unit Cost Amount
Equipments
a. 1.0 HP Inverter Split Type wall Mounted ACU 2.00 sets 36,295.00 72,590.00
b. 1.5 HP Inverter Split Type wall Mounted ACU 1.00 sets 39,995.00 39,995.00
c. 2.0 HP Inverter Split Type wall Mounted ACU 2.00 sets 49,695.00 99,390.00
d. 2.5 HP Inverter Split Type wall Mounted ACU 1.00 sets 58,495.00 58,495.00
REFREGIRANT PIPING SYSTEM
a. Refrigerant Pipelines
Copper Pipe 1/4 3.00 pcs 650.00 1,950.00
Copper Pipe 3/8 2.00 pcs 950.00 1,900.00
b. Insulation
Rubber Insulation 1/4 x 1 6.00 pcs 200.00 1,200.00
Rubber Insulation 3/8 x 1 4.00 pcs 295.00 1,180.00
c. Fittings and other Consumable Materials 1.00 lot 3,500.00 3,500.00
DRAINAGE PIPING SYSTEM
a. Blue Pipe
PVC Pipe 3/4 x 3m length 20.00 pcs 190.00 3,800.00
PVC Pipe 1mm Ø x 3m length 4.00 pcs 250.00 1,000.00
b. Insulation
Rubber Insulation 1 1/8 x 3/8 10.00 pcs 400.00 4,000.00
Rubber Insulation 7/8 x 3/4 40.00 pcs 378.00 15,120.00
c. Fittings and other Consumable Materials 1.00 lot 1,000.00 1,000.00
ELECTRICAL WORKS
a. Conduits & Fittings 1.00 lot 1,500.00 1,500.00
b. Wires & Cables (Indoor to Outdoor) 1.00 lot 5,000.00 5,000.00
c. MISC. CONSUMABLES & HANGER/SUPPORT 1.00 lot 750.00 750.00
d. Enclosed Circuit Breaker , 30AT, 2P 7.00 sets 750.00 5,250.00
OTHER ITEMS
a. Fabricated Concrete Slab and Bracket (ACCU) 7.00 pcs 2,500.00 17,500.00

Total Material Cost ------------ P 335,120.00

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 17 17 600.00 P 10,200.00
Foreman 1 17 17 520.00 8,840.00
Skilled Laborer 5 17 85 350.00 29,750.00
Unskilled Laborer 5 17 85 250.00 21,250.00

Total Labor Cost ------------ P 70,040.00


Summary:
a. Materials Cost 335,120.00
b. Equipment Cost -
c. Labor Cost 70,040.00
Total Item Cost P 405,160.00
Item Unit Cost /sq.m. 405,160.00

10.1.2 Second Floor 1.00 lot


a. Materials
Description Quantity Unit Unit Cost Amount
Equipments
a. 1.0 HP Inverter Split Type wall Mounted ACU 2.00 sets 36,295.00 72,590.00
b. 1.5 HP Inverter Split Type wall Mounted ACU 2.00 sets 39,995.00 79,990.00
c. 2.0 HP Inverter Split Type wall Mounted ACU 1.00 sets 49,695.00 49,695.00
d. 2.5 HP Inverter Split Type wall Mounted ACU 1.00 sets 58,495.00 58,495.00
REFREGIRANT PIPING SYSTEM
a. Refrigerant Pipelines
Copper Pipe 1/4 2.00 pcs 650.00 1,300.00
Copper Pipe 3/8 2.00 pcs 950.00 1,900.00
b. Insulation
Rubber Insulation 1/4 x 1 20.00 pcs 200.00 4,000.00
Rubber Insulation 3/8 x 1 20.00 pcs 295.00 5,900.00
c. Fittings and other Consumable Materials 1.00 lot 1,500.00 1,500.00
DRAINAGE PIPING SYSTEM
a. Blue Pipe
PVC Pipe 3/4 x 3m length 20.00 pcs 190.00 3,800.00
PVC Pipe 1mm Ø x 3m length 3.00 pcs 250.00 750.00
b. Insulation
Rubber Insulation 1 1/8 x 3/8 8.00 pcs 400.00 3,200.00
Rubber Insulation 7/8 x 3/4 50.00 pcs 378.00 18,900.00
c. Fittings and other Consumable Materials 1.00 lot 1,000.00 1,000.00
ELECTRICAL WORKS
a. Conduits & Fittings 1.00 lot 1,500.00 1,500.00
b. Wires & Cables (Indoor to Outdoor) 1.00 lot 5,000.00 5,000.00
c. MISC. CONSUMABLES & HANGER/SUPPORT 1.00 lot 1,000.00 1,000.00
d. Enclosed Circuit Breaker , 30AT, 2P 6.00 sets 750.00 4,500.00
OTHER ITEMS
a. Fabricated Concrete Slab and Bracket (ACCU) 6.00 pcs 2,500.00 15,000.00

Total Material Cost ------------ P 330,020.00

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 17 17 600.00 P 10,200.00
Foreman 1 17 17 520.00 8,840.00
Skilled Laborer 5 17 85 350.00 29,750.00
Unskilled Laborer 5 17 85 250.00 21,250.00

Total Labor Cost ------------ P 70,040.00

Summary:
a. Materials Cost 330,020.00
b. Equipment Cost -
c. Labor Cost 70,040.00
Total Item Cost P 400,060.00
Item Unit Cost /sq.m. 400,060.00

10.1.3 Third Floor (Drainage Piping System) 1.00 lot


a. Materials
Description Quantity Unit Unit Cost Amount
Equipments
a. Blue Pipe
PVC Pipe 3/4 x 3m length 10.00 pcs 190.00 1,900.00
PVC Pipe 1mm Ø x 3m length 3.00 pcs 250.00 750.00
b. Insulation
Rubber Insulation 1 1/8 x 3/8 7.00 pcs 400.00 2,800.00
Rubber Insulation 7/8 x 3/4 15.00 pcs 378.00 5,670.00
c. Fittings and other Consumable Materials 1.00 lot 15,000.00 15,000.00

Total Material Cost ------------ P 26,120.00

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 4 4 600.00 P 2,400.00
Foreman 1 4 4 520.00 2,080.00
Skilled Laborer 2 4 8 350.00 2,800.00
Unskilled Laborer 2 4 8 250.00 2,000.00

Total Labor Cost ------------ P 9,280.00

Summary:
a. Materials Cost 26,120.00
b. Equipment Cost -
c. Labor Cost 9,280.00
Total Item Cost P 35,400.00
Item Unit Cost /sq.m. 35,400.00

10.2. Exhaust Fan Piping


10.2.1 Ground Floor 1.00 lot
a. Materials
Description Quantity Unit Unit Cost Amount
EXHAUST FAN PIPING
a. PVC Pipe
PVC Pipe 100mm x 3m length 18.00 sets 850.00 15,300.00
100mm Ø x Vent Cap 13.00 sets 500.00 6,500.00
OTHER ITEMS
a. Fabricated hangers, clamps,bolts,etc 1.00 lot 6,800.00 6,800.00

Total Material Cost ------------ P 28,600.00

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 3 3 600.00 P 1,800.00
Foreman 1 3 3 520.00 1,560.00
Skilled Laborer 3 3 9 350.00 3,150.00
Unskilled Laborer 3 3 9 250.00 2,250.00

Total Labor Cost ------------ P 8,760.00

Summary:
a. Materials Cost 28,600.00
b. Equipment Cost -
c. Labor Cost 8,760.00
Total Item Cost P 37,360.00
Item Unit Cost /sq.m. 37,360.00
10.2.2 Second Floor 1.00 lot
a. Materials
Description Quantity Unit Unit Cost Amount
EXHAUST FAN PIPING
a. PVC Pipe
PVC Pipe 100mm x 3m length 20.00 sets 850.00 17,000.00
100mm Ø x Vent Cap 17.00 sets 500.00 8,500.00
OTHER ITEMS
a. Fabricated hangers, clamps,bolts,etc 1.00 lot 8,000.00 8,000.00

Total Material Cost ------------ P 33,500.00

b. Equipment None

c. Labor

Designation No. of No. of Days Man-Days Rate / Day Amount


Personnel
Project Engineer 1 4 4 600.00 P 2,400.00
Foreman 1 4 4 520.00 2,080.00
Skilled Laborer 3 4 12 350.00 4,200.00
Unskilled Laborer 3 4 12 250.00 3,000.00

Total Labor Cost ------------ P 11,680.00

Summary:
a. Materials Cost 33,500.00
b. Equipment Cost -
c. Labor Cost 11,680.00
Total Item Cost P 45,180.00
Item Unit Cost /sq.m. 45,180.00

11.0 Electronics & Communication System


11.1 Security & Surveillance (CCTV)
11.1.1 Ground Floor 1.00 lot
a. Materials
Description Quantity Unit Unit Cost Amount
CCTV COMPONENTS
Pullbox 6x6 1.00 pc 390.00 390.00
Pullbox 12x12 1.00 pc 1,200.00 1,200.00
PVC SquareBox 4.00 pcs 70.00 280.00
PVC Junction Box w/cover 18.00 pcs 37.00 666.00
20mm Elect PVC pipe 36.00 pcs 70.00 2,520.00
32mm Elect PVC pipe 22.00 pcs 145.00 3,190.00
63mm Elect PVC pipe 1.00 pc 525.00 525.00
Consumables 1.00 lot 3,000.00 3,000.00

Total Material Cost ------------ P 11,771.00

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 2 2 600.00 P 1,200.00
Foreman 1 2 2 520.00 1,040.00
Skilled Laborer 2 2 4 350.00 1,400.00
Unskilled Laborer 2 2 4 250.00 1,000.00

Total Labor Cost ------------ P 4,640.00

Summary:
a. Materials Cost 11,771.00
b. Equipment Cost -
c. Labor Cost 4,640.00
Total Item Cost P 16,411.00
Item Unit Cost /sq.m. 16,411.00

11.1.2 Second Floor 1.00 lot


a. Materials
Description Quantity Unit Unit Cost Amount
CCTV COMPONENTS
Pullbox 6x6 1.00 pc 390.00 390.00
PVC SquareBox 4.00 pcs 70.00 280.00
PVC Junction Box w/cover 9.00 pcs 37.00 333.00
20mm Elect PVC pipe 15.00 pcs 70.00 1,050.00
32mm Elect PVC pipe 22.00 pcs 145.00 3,190.00
63mm Elect PVC pipe 1.00 pc 525.00 525.00
Consumables 1.00 lot 3,000.00 3,000.00

Total Material Cost ------------ P 8,768.00

b. Equipment None

c. Labor

Designation No. of No. of Days Man-Days Rate / Day Amount


Personnel
Project Engineer 1 2 2 600.00 P 1,200.00
Foreman 1 2 2 520.00 1,040.00
Skilled Laborer 2 2 2 350.00 700.00
Unskilled Laborer 2 2 2 250.00 500.00

Total Labor Cost ------------ P 3,440.00

Summary:
a. Materials Cost 8,768.00
b. Equipment Cost -
c. Labor Cost 3,440.00
Total Item Cost P 12,208.00
Item Unit Cost /sq.m. 12,208.00

11.2 Fire Detection & Alarm System (FDAS)


11.2.1 Ground Floor 1.00 lot
a. Materials
Description Quantity Unit Unit Cost Amount
Pullbox 6x6 1.00 pc 390.00 390.00
Junction Box w/cover Metal 30.00 pc 65.00 1,950.00
Utility Box 3.00 pcs 23.00 69.00
Flexible Metal pipe 13.00 m 45.00 585.00
1/2" RSC pipe w/ coupling 60.00 pcs 220.00 13,200.00
1/2" RSC pipe elbow 4.00 pcs 36.00 144.00
TF Wire #18 4.00 pc 1,500.00 6,000.00
Consumables 1.00 lot 2,000.00 2,000.00

Total Material Cost ------------ P 24,338.00

b. Equipment None

c. Labor

Designation No. of No. of Days Man-Days Rate / Day Amount


Personnel
Project Engineer 1 3 3 600.00 P 1,800.00
Foreman 1 3 3 520.00 1,560.00
Skilled Laborer 3 3 9 350.00 3,150.00
Unskilled Laborer 3 3 9 250.00 2,250.00

Total Labor Cost ------------ P 8,760.00

Summary:
a. Materials Cost 24,338.00
b. Equipment Cost -
c. Labor Cost 8,760.00
Total Item Cost P 33,098.00
Item Unit Cost /sq.m. 33,098.00

11.2.2 Second Floor 1.00 lot


a. Materials
Description Quantity Unit Unit Cost Amount
Junction Box w/cover Metal 36.00 pc 65.00 2,340.00
Utility Box 4.00 pc 23.00 92.00
Flexible Metal pipe 16.00 m 45.00 720.00
1/2" RSC pipe w/ coupling 60.00 pcs 220.00 13,200.00
1/2" RSC pipe elbow 4.00 pcs 36.00 144.00
TF Wire #18 3.00 box 1,500.00 4,500.00

Total Material Cost ------------ P 20,996.00

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 3 3 600.00 P 1,800.00
Foreman 1 3 3 520.00 1,560.00
Skilled Laborer 2 3 6 350.00 2,100.00
Unskilled Laborer 3 3 9 250.00 2,250.00

Total Labor Cost ------------ P 7,710.00

Summary:
a. Materials Cost 20,996.00
b. Equipment Cost -
c. Labor Cost 7,710.00
Total Item Cost P 28,706.00
Item Unit Cost /sq.m. 28,706.00

11.3 Paging System / Public Address


11.3.1 Ground Floor 1.00 lot
a. Materials
Description Quantity Unit Unit Cost Amount
20mm Elect PVC pipe 70.00 unit 70.00 4,900.00
20mm Flexible PVC Pipe 26.00 m 7.00 182.00
Wire #16 7c 2.00 roll 1,900.00 3,800.00
Junction Box PVC 26.00 pcs 65.00 1,690.00
PVC SquareBox 1.00 pc 70.00 70.00
Pullbox 6x6 2.00 pcs 390.00 780.00
Consumables 1.00 lot 3,000.00 3,000.00

Total Material Cost ------------ P 14,422.00

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 2 2 600.00 P 1,200.00
Foreman 1 2 2 520.00 1,040.00
Skilled Laborer 2 2 4 350.00 1,400.00
Unskilled Laborer 3 2 6 250.00 1,500.00

Total Labor Cost ------------ P 5,140.00

Summary:
a. Materials Cost 14,422.00
b. Equipment Cost -
c. Labor Cost 5,140.00
Total Item Cost P 19,562.00
Item Unit Cost /sq.m. 19,562.00

11.3.2 Second Floor 1.00 lot


a. Materials
Description Quantity Unit Unit Cost Amount
20mm Elect PVC pipe 60.00 unit 70.00 4,200.00
20mm Flexible PVC Pipe 23.00 m 7.00 161.00
Wire #16 7c 1.00 roll 1,900.00 1,900.00
Junction Box PVC 23.00 pcs 65.00 1,495.00
PVC SquareBox 1.00 pc 70.00 70.00
Pullbox 6x6 1.00 pc 390.00 390.00
Consumables 1.00 lot 3,000.00 3,000.00

Total Material Cost ------------ P 11,216.00

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 2 2 600.00 P 1,200.00
Foreman 1 2 2 520.00 1,040.00
Skilled Laborer 1 2 2 350.00 700.00
Unskilled Laborer 3 2 4 250.00 1,000.00

Total Labor Cost ------------ P 3,940.00

Summary:
a. Materials Cost 11,216.00
b. Equipment Cost -
c. Labor Cost 3,940.00
Total Item Cost P 15,156.00
Item Unit Cost /sq.m. 15,156.00

11.4 Communication System (Tel., CATV, Data, Nurse Call, Intercom)


11.4.1 Ground Floor 1.00 lot
a. Materials
Description Quantity Unit Unit Cost Amount
TEL Outlet 14.00 set 366.00 5,124.00
CAT6 5.00 box 9,800.00 49,000.00
Pullbox 6x6 7.00 roll 390.00 2,730.00
Pullbox 12x12 5.00 pcs 1,000.00 5,000.00
Utility Box 23.00 pcs 23.00 529.00
25mm Elect PVC pipe 90.00 pcs 80.00 7,200.00
63mm Elect PVC pipe 25.00 pcs 525.00 13,125.00
25mm Elect PVC elbow 30.00 pcs 16.00 480.00
Data Cabinet Close type 3Ft 1.00 unit 22,000.00 22,000.00
LEVITON Cat6 Patch Panel 24P 2.00 unit 9,500.00 19,000.00
LEVITON 2RU Horizontal Cable Manager 2.00 unit 3,800.00 7,600.00
Consumables 1.00 lot 6,000.00 6,000.00

Total Material Cost ------------ P 137,788.00

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 14 14 600.00 P 8,400.00
Foreman 1 14 14 520.00 7,280.00
Skilled Laborer 4 14 56 350.00 19,600.00
Unskilled Laborer 4 14 56 250.00 14,000.00

Total Labor Cost ------------ P 49,280.00

Summary:
a. Materials Cost 137,788.00
b. Equipment Cost -
c. Labor Cost 49,280.00
Total Item Cost P 187,068.00
Item Unit Cost /sq.m. 187,068.00

11.4.2 Second Floor 1.00 lot


a. Materials
Description Quantity Unit Unit Cost Amount
TEL Outlet 13.00 set 366.00 4,758.00
CAT6 outlet w/ faceplate 13.00 set 500.00 6,500.00
CATV outlet 3.00 set 440.00 1,320.00
RG6 (roll of 300m) 1.00 roll 8,160.00 8,160.00
CAT6 4.00 box 9,800.00 39,200.00
Pullbox 6x6 7.00 pcs 390.00 2,730.00
Pullbox 12x12 5.00 pcs 1,000.00 5,000.00
Utility Box 29.00 pcs 23.00 667.00
20mm Elect PVC pipe 40.00 unit 70.00 2,800.00
25mm Elect PVC pipe 115.00 pcs 80.00 9,200.00
63mm Elect PVC pipe 25.00 pcs 525.00 13,125.00
25mm Elect PVC elbow 26.00 pcs 16.00 416.00
Consumables 1.00 lot 6,000.00 6,000.00

Total Material Cost ------------ P 99,876.00

b. Equipment None

c. Labor
Designation No. of No. of Days Man-Days Rate / Day Amount
Personnel
Project Engineer 1 11 11 600.00 P 6,600.00
Foreman 1 11 11 520.00 5,720.00
Skilled Laborer 4 11 44 350.00 15,400.00
Unskilled Laborer 4 11 44 250.00 11,000.00

Total Labor Cost ------------ P 38,720.00

Summary:
a. Materials Cost 99,876.00
b. Equipment Cost -
c. Labor Cost 38,720.00
Total Item Cost P 138,596.00
Item Unit Cost /sq.m. 138,596.00
APPROVED BUDGET COST
Name of Project:

Project Location:
Owner:
Implementing Agency 92,463.77 105,672.88 15 198,136.65 182,285.72 380,422.37 1,701,333.37 16,920.27
MARK-UPS
ITEM ESTIMATED DIRECT TOTAL MARK-UP TOTAL INDIRECT
DESCRIPTION QUANTITY UNIT IN PERCENT TOTAL COST UNIT COST
No. COST COST
OCM[1] PROFIT % VALUE VAT[3]
-1 -2 (3) -4 -5 -6 -7 -8 -9 -10 -11 -12 -13
(12%[(5)+
(5)X(8) (9)] (9)+(10) (5)+(11) (12)/(3)
I. Stage 1
1.0 Permits Building and Occupancy Permit (Plans & 1.00 lot 3,145,000.00 - 251,600.00 8.000000 251,600.00 407,592.00 659,192.00 3,804,192.00 3,804,192.00
II. Stage 11 ConstructionOther
PhaseItems only)
1.0 General Provisions
2.0 Sitework
3.0 Concrete /Reinforcement Works -
3.1 Foundation -
3.1.1 Column Footing 100.55 cu.m. 1,320,911.00 92,463.77 105,672.88 15.000000 198,136.65 182,285.72 380,422.37 1,701,333.37 16,920.27
3.1.2 Footing Tie Beam (FTB) 14.16 cu.m. 306,660.00 21,466.20 24,532.80 15.000000 45,999.00 42,319.08 88,318.08 394,978.08 27,893.93
3.1.3 Wall Footing 13.59 cu.m. 125,073.00 8,755.11 10,005.84 15.000000 18,760.95 17,260.07 36,021.02 161,094.02 11,853.86
3.2 Columns & Vertical Stiffiner -
3.2.1 Columns & Vertical Stiffiners 89.04 cu.m. 2,002,310.00 140,161.70 160,184.80 15.000000 300,346.50 276,318.78 576,665.28 2,578,975.28 28,964.23
3.3 Beams -
3.3.1. Ground Floor Beam 14.16 cu.m. 312,184.00 21,852.88 24,974.72 15.000000 46,827.60 43,081.39 89,908.99 402,092.99 28,396.40
3.3.2. Second Floor Beam 31.97 cu.m. 1,093,235.00 76,526.45 87,458.80 15.000000 163,985.25 150,866.43 314,851.68 1,408,086.68 44,044.00
3.3.3. Third Floor 32.85 cu.m. 1,095,325.00 76,672.75 87,626.00 15.000000 164,298.75 151,154.85 315,453.60 1,410,778.60 42,946.08
3.3.4. Roof Deck 40.35 cu.m. 841,587.00 58,911.09 67,326.96 15.000000 126,238.05 116,139.01 242,377.06 1,083,964.06 26,864.04

3.4 Floor Slab/Steel Decking -


3.4.1. Ground Floor 50.68 cu.m. 488,238.00 34,176.66 39,059.04 15.000000 73,235.70 67,376.84 140,612.54 628,850.54 12,408.26
3.4.2. Second Floor Slab (Steel Decking) 54.00 cu.m. 922,559.00 64,579.13 73,804.72 15.000000 138,383.85 127,313.14 265,696.99 1,188,255.99 22,004.74
3.4.3. Third Floor Slab (Steel Decking) 50.00 cu.m. 866,927.00 60,684.89 69,354.16 15.000000 130,039.05 119,635.93 249,674.98 1,116,601.98 22,332.04
3.4.4. Roof Deck with Water Proofing 64.21 cu.m. 811,579.04 56,810.53 64,926.32 15.000000 121,736.86 111,997.91 233,734.76 1,045,313.80 16,279.61

Page 57
APPROVED BUDGET COST
Name of Project:

Project Location:
Owner:
Implementing Agency 92,463.77 105,672.88 15 198,136.65 182,285.72 380,422.37 1,701,333.37 16,920.27
MARK-UPS
ITEM ESTIMATED DIRECT TOTAL MARK-UP TOTAL INDIRECT
DESCRIPTION QUANTITY UNIT IN PERCENT TOTAL COST UNIT COST
No. COST COST
OCM[1] PROFIT % VALUE VAT[3]
-1 -2 (3) -4 -5 -6 -7 -8 -9 -10 -11 -12 -13
(12%[(5)+
(5)X(8) (9)] (9)+(10) (5)+(11) (12)/(3)
3.5 Ramp and Stairs 20.73 cu.m. 347,471.00 24,322.97 27,797.68 15.000000 52,120.65 47,951.00 100,071.65 447,542.65 21,589.13
3.6 Driveway 12.14 cu.m. 150,898.00 10,562.86 12,071.84 15.000000 22,634.70 20,823.92 43,458.62 194,356.62 16,009.61
3.7 Concrete Counter 3.30 cu.m. 40,963.00 2,867.41 3,277.04 15.000000 6,144.45 5,652.89 11,797.34 52,760.34 15,987.98
4.0 Masonry Works -
5.0. Metal Works -
6.0 Architectural Finishes -
7.0 Plumbing Works -
8.0 Electrical 1.00 lot 2,370,400.00 165,928.00 189,632.00 15.000000 355,560.00 327,115.20 682,675.20 3,053,075.20 3,053,075.20
9.0 Fire Safety & Protection System -

Page 58
APPROVED BUDGET COST
Name of Project:

Project Location:
Owner:
Implementing Agency 92,463.77 105,672.88 15 198,136.65 182,285.72 380,422.37 1,701,333.37 16,920.27
MARK-UPS
ITEM ESTIMATED DIRECT TOTAL MARK-UP TOTAL INDIRECT
DESCRIPTION QUANTITY UNIT IN PERCENT TOTAL COST UNIT COST
No. COST COST
OCM[1] PROFIT % VALUE VAT[3]
-1 -2 (3) -4 -5 -6 -7 -8 -9 -10 -11 -12 -13
(12%[(5)+
(5)X(8) (9)] (9)+(10) (5)+(11) (12)/(3)
10.0 Mechanical Works -
11.0. Electronics & Communication System -
Total 31,208,602.83 1,918,452.69 2,496,688.23 14.147192 4,415,140.92 4,274,849.25 8,689,990.17 39,898,593.00

PREPARED BY: CHECKED BY: RECOMMENDING APPROVAL: APPROVED:

SUBMITTED BY:

Page 59
SUMMARY OF ESTIMATES

Name of Project:

Project Location
Project Cost
No. of Calendar Days to Complete:
Owner:
Implementing Agency
ITEM DESCRIPTION QTY. UNIT MATERIALS EQUIPMENT LABOR AMOUNT
NO.
I Stage 1
Architectural and Engineering Services 1.00 lot 3,145,000.00 - - 3,145,000.00
II Stage 11 Construction Phase
1.0 General Provisions
1.1. Right of Way 1.00 lot 180,000.00 - - 180,000.00
1.2. Permits 1.00 lot 72,167.82 - - 72,167.82
1.3. Temporary Field Office & Facilities
1.3.1. Field Office 25.00 sq.m. 53,608.00 - 25,360.00 78,968.00
1.3.2. Office Eqpmt., Furnitures & Fixtures 1.00 lot 101,000.00 - - 101,000.00
1.4. Utilities (Water and Electrical) 1.00 lot 225,000.00 - - 225,000.00
1.5. Board Up - Perimeter Protection & Barrier 110.00 lm 49,496.00 - 19,020.00 68,516.00
2.0. Sitework
2.1. Site Demolition 1.00 lot - 180,000.00 86,680.00 266,680.00
2.2. Structural Excavation 349.04 cu.m - 270,000.00 16,920.00 286,920.00
2.3. Backfilling 188.50 cu.m - - 15,350.00 15,350.00
2.4. Filling Materials 663.00 cu.m 268,280.00 8,250.00 58,800.00 335,330.00
2.5. Base and Subbase Course 48.75 cu.m 18,525.00 8,250.00 27,440.00 54,215.00
2.6. Lay-out, Forms & Scaffoldings 1.00 lot 1,154,410.00 - 403,920.00 1,558,330.00
3.0. Concrete /Reinforcement Works
3.1. Foundation
3.1.1. Column Footing 100.55 cu.m. 943,431.00 29,000.00 348,480.00 1,320,911.00
3.1.2 Footing Tie Beam (FTB) 14.16 cu.m. 222,360.00 5,100.00 79,200.00 306,660.00
3.1.3. Wall Footing 13.59 cu.m. 88,333.00 5,100.00 31,640.00 125,073.00
3.2. Columns & Vertical Stiffiner
3.2.1. Columns & Vertical Stiffiners 89.04 cu.m. 1,420,670.00 51,000.00 530,640.00 2,002,310.00
3.3. Beams
3.3.1. Ground Floor Beam 14.16 cu.m. 227,484.00 5,500.00 79,200.00 312,184.00
3.3.2. Second Floor Beam 31.97 cu.m. 799,635.00 16,400.00 277,200.00 1,093,235.00
3.3.3. Third Floor 32.85 cu.m. 801,925.00 16,200.00 277,200.00 1,095,325.00
3.3.4. Roof Deck 40.35 cu.m. 599,607.00 12,300.00 229,680.00 841,587.00
3.4. Floor Slab/Steel Decking
3.4.1. Ground Floor 50.68 cu.m. 348,398.00 13,120.00 126,720.00 488,238.00
3.4.2. Steel Decking (2nd Flr) 54.00 cu.m. 716,909.00 13,900.00 191,750.00 922,559.00
3.4.3. Steel Decking (third floor)) 50.00 cu.m. 661,277.00 13,900.00 191,750.00 866,927.00
3.4.4. Roof Deck with Water Proofing 64.21 cu.m. 575,649.04 6,250.00 229,680.00 811,579.04
3.5. Ramp and Stairs 20.73 cu.m. 247,391.00 13,000.00 87,080.00 347,471.00
3.6. Driveway 12.14 cu.m. 106,068.00 6,400.00 38,430.00 150,898.00
3.7. Concrete Counter 3.30 cu.m. 29,733.00 950.00 10,280.00 40,963.00
4.0. Masonry Works
4.1. Ground Floor 853.00 sq.m. 577,072.00 13,250.00 207,200.00 797,522.00
4.2. Second Floor 884.00 sq.m. 578,406.00 14,000.00 207,200.00 799,606.00
5.0. Metal Works
5.1. Metal Works (Stair Railings & Hand Grab Bar) 928.00 sq.m. 292,932.00 8,400.00 107,120.00 408,452.00
6.0 Architectural Finishes
6.1. Cement Plaster Finishes (Wall, Columns 3,727.00 sq.m. 651,240.00 - 334,640.00 985,880.00
& Beams)
6.2. Door and Windows (Ground & Second Floor)
6.2.1. Doors 1.00 lot 692,803.22 - 236,800.00 929,603.22
6.2.2. Windows 1.00 lot 835,328.00 - 254,560.00 1,089,888.00
6.3. Tilework
6.3.1. Ground Floor 669.00 sq.m. 658,823.00 6,000.00 230,880.00 895,703.00
6.3.2. Second Floor 638.00 sq.m. 750,033.00 6,600.00 260,480.00 1,017,113.00
6.3.3. Counter Tile and Splashboards 39.00 lm 83,708.00 1,800.00 32,120.00 117,628.00
(backsplash and side boards)
6.4. Ceiling Work
6.4.1. Ground Floor 547.00 sq.m 282,750.75 - 100,640.00 383,390.75
6.4.2. Second Floor 541.00 sq.m 258,655.00 - 88,800.00 347,455.00
6.5. Carpentry Work
6.5.1. Cabinets and Counters 1.00 lot 192,814.00 - 88,800.00 281,614.00
6.6. Painting
6.6.1. Ground Floor 1,749.00 sq.m 267,512.00 - 159,840.00 427,352.00

Page 60 of 66
SUMMARY OF ESTIMATES

Name of Project:

Project Location
Project Cost
No. of Calendar Days to Complete:
Owner:
Implementing Agency
ITEM
DESCRIPTION QTY. UNIT MATERIALS EQUIPMENT LABOR AMOUNT
NO.
7.0 Plumbing Works
7.1. Fixtures and Accessories 1.00 lot 538,958.00 - 189,440.00 728,398.00
7.2. Cold Water Line 1.00 lot 34,910.00 - 14,600.00 49,510.00
7.3. Waste Waterline /Sewer Line and Vent System 1.00 lot 106,892.00 - 37,080.00 143,972.00
7.4. Storm Drainage and Catch Basin 1.00 lot 89,424.00 - 37,080.00 126,504.00
7.5. Septic Tank 2.00 unit 98,102.00 - 54,240.00 152,342.00
8.0. Electrical 1.00 lot 1,828,000.00 - 542,400.00 2,370,400.00
9.0. Fire Safety & Protection System
9.1. Ground Floor 1.00 lot 211,586.00 - 94,400.00 305,986.00
9.2. Second Floor 1.00 lot 249,642.00 - 113,280.00 362,922.00
10.0 Mechanical Works
10.1. Airconditioning Units
10.1.1. Ground Floor 1.00 lot 335,120.00 - 70,040.00 405,160.00
10.1.2. Second Floor 1.00 lot 330,020.00 - 70,040.00 400,060.00
10.1.3. Third Floor (Drainage Piping System) 1.00 lot 26,120.00 - 9,280.00 35,400.00
10.2. Exhaust Fan Piping
10.2.1. Ground Floor 1.00 lot 28,600.00 - 8,760.00 37,360.00
10.2.2. Second Floor 1.00 lot 33,500.00 - 11,680.00 45,180.00
11.0. Electronics & Communication System
11.1. Security & Surveillance (CCTV)
11.1.1. Ground Floor 1.00 lot 11,771.00 - 4,640.00 16,411.00
11.1.2. Second Floor 1.00 lot 8,768.00 - 3,440.00 12,208.00
11.2. Fire Detection & Alarm System (FDAS)
11.2.1. Ground Floor 1.00 lot 24,338.00 - 8,760.00 33,098.00
11.2.2. Second Floor 1.00 lot 20,996.00 - 7,710.00 28,706.00
11.3. Paging System / Public Address
11.3.1. Ground Floor 1.00 lot 14,422.00 - 5,140.00 19,562.00
11.3.2. Second Floor 1.00 lot 11,216.00 - 3,940.00 15,156.00
11.4. Communication System (Tel., CATV, Data, Nurse Call, Intercom)
11.4.1. Ground Floor 1.00 lot 137,788.00 - 49,280.00 187,068.00
11.4.2. Second Floor 1.00 lot 99,876.00 - 38,720.00 138,596.00
GRAND TOTAL 23,418,482.83 724,670.00 7,065,450.00 31,208,602.83
Total ------------------ 31,208,602.83

BREAKDOWN OF ESTIMATES

1.0 : DIRECT COST ( DC ) Php 31,208,602.83


1.1 Material Cost 23,418,482.83
1.2 Equipment 724,670.00
1.3 Labor 7,065,450.00
SUB - TOTAL (A) Php31,208,602.83

2.0 : INDIRECT COST ( IC ) 8,689,990.17


2.1 Overhead Cost & Misc. 1,918,452.69
2.2 Contractor's Profit 2,496,688.23 $0.08
SUB - TOTAL (B) Php4,415,140.92

2.3 Taxes (12.0% of Sub-Total A+B) 4,274,849.25

TOTAL PROJECT COST (TPC) P 39,898,593.00

SUBMITTED BY:

Page 61 of 66
DETAILED ESTIMATES

Name of Project: green


yellow
Project Location: blue
red
Owner: purple
Implementing Agency:
Prepared By: ___________________________________
___________________________________

I Stage 1 1.00 lot


II Stage 11 Construction Phase
1.0 General Provisions
2.0 Sitework
3.0 Concrete /Reinforcement Works
4.0 Masonry Works
5.0 Metal Works
6.0 Architectural Finishes
7.0 Plumbing Works
8.0 Electrical
9.0 Fire Safety & Protection System
10.0 Mechanical Works
11.0 Electronics & Communication System

Page 62
Republic of the philippines
DEPARTMENT OF HEALTH
CENTER FOR HEALTH DEVELOPMENT WESTERN VISAYAS
Q. ABETO ST., MANDURRIAO, ILOILO CITY

INDIVIDUAL PROJECT PROGRAM OF WORK


(DESIGN AND BUILD)

PROJECT TITLE: IMPROVEMENT/UPGRADING OF HOSPITAL APPROP. ACT:


BUILDING (PHASE-1), Along Grid Lines 1-6 and A-K APPROP.
LOCATION: Ciriaco S. Tirol Hosp., Boracay Island, Malay, Aklan PROJ. DURATION:
OWNER: Provincial Government of Aklan
IMPLEMENTING AGENCY: DOH-CHDWV
I. EQUIPMENT
A. MINIMUM EQUIPMENT ON HAND & OTHER MACHINERIES & TOOLS
a. Backhoe d. Concrete Cutter
b. Welding Machine e. Hauling Truck
c. Demolition Hammer f. Concrete Vibrator
ll. Scope of Work Percentage Weight

I Stage 1
Architectural and Engineering Services 9.53
II Stage 11 Construction Phase
1.0 General Provisions
2.0. Sitework
3.0. Concrete /Reinforcement Works
4.0. Masonry Works 0.13
5.0. Metal Works 2.58
6.0 Architectural Finishes 1.32
7.0 Plumbing Works
8.0. Electrical 7.65
9.0. Fire Safety & Protection System
10.0 Mechanical Works
11.0. Electronics & Communication System
T O T A L 100.00
III. BREAKDOWN OF ESTIMATED EXPENDITURES
I T E M
I. Direct Cost
A. Total Cost of Materials
B. Total Cost of Labor
C. Equipment Rental
II. Indirect Cost
A. Overhead-Contingencies & Miscellaneous
B. Contractor's Profit
C. Value Added Tax and With/holding
IV. ESTIMATED PROJECT COST

PREPARED BY:

RECOMMENDING APPROVAL:

Page 63 of 66
Republic of the philippines
DEPARTMENT OF HEALTH
CENTER FOR HEALTH DEVELOPMENT WESTERN VISAYAS
Q. ABETO ST., MANDURRIAO, ILOILO CITY

INDIVIDUAL PROJECT PROGRAM OF WORK


(DESIGN AND BUILD)

PROJECT TITLE: IMPROVEMENT/UPGRADING OF HOSPITAL APPROP. ACT:


BUILDING (PHASE-1), Along Grid Lines 1-6 and A-K APPROP.
LOCATION: Ciriaco S. Tirol Hosp., Boracay Island, Malay, Aklan PROJ. DURATION:
OWNER: Provincial Government of Aklan
IMPLEMENTING AGENCY: DOH-CHDWV

APPROVED: 0

Page 64 of 66
GAA 2012
P39,898,593.00
300 CD

Cutter
g. Concrete Mixer
Vibrator
Total Cost

3,804,192.00

52,760.34
1,029,892.53
526,086.18

3,053,075.20

39,898,593.00

23,418,482.83
7,065,450.00
724,670.00

1,918,452.69
2,496,688.23
4,274,849.25
39,898,593.00