MASTER SCHEDULE

PERKUATAN STRUKTUR DERMAGA UTARA TERMINAL BATU AMPAR

PEMBERI TUGAS : BADAN PENGUSAHAAN BATAM


KONSULTAN SUPERVISI : PT. REFENA KEMBAR ANUGRAH
KONTRAKTOR PELAKSANA : PT. NITA JAYA PRATAMA

BULAN-1 BULAN-2 BULAN-3 BULAN-4 BULAN-5


BOBOT M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22
NO URAIAN KEGIATAN
(%) 31/12/21 07/01/22 14/01/22 21/01/22 28/01/22 04/02/22 11/02/22 18/02/22 25/02/22 04/03/22 11/03/22 18/03/22 25/03/22 01/04/22 08/04/22 15/04/22 22/04/22 29/04/22 06/05/22 13/05/22 20/05/22 27/05/22
06/01/22 13/01/22 20/01/22 27/01/22 03/02/22 10/02/22 17/02/22 24/02/22 03/03/22 10/03/22 17/03/22 24/03/22 31/03/22 07/04/22 14/04/22 21/04/22 28/04/22 05/05/22 12/05/22 19/05/22 26/05/22 30/05/22
A PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1.303 0.326 0.326 0.326 0.326
2 Pembuatan Kantor Direksi 0.887 0.887
3 Pembuatan Gudang 0.338 0.338
4 Pembuatan Papan Nama 0.007 0.007
5 Pembuatan Laporan dan Dokumentasi 0.032 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
6 Pembuatan Shop Drawing dan As Built Drawing 0.059 0.030 0.030
7 Penjilidan Dokumen Kontrak 0.023 0.023
8 Pengukuran (Setting Tiang Pancang) 0.046 0.046
9 Pembuatan Pagar Sementara 0.290 0.145 0.145
10 Tes PDA 0.391 0.391
11 Pengujian NDT (Ultrasonic Test) 0.769 0.769
12 Sistem Manajemen Keselamatan dan Kesehatan Kerja (SMK3)
12.1. Pembuatan Dokumen RKK, Prosedur dan Instruksi Kerja dan Penyiapan 0.007 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
Formulir
12.2. Sosialisasi dan Promosi K3 dan Pelatihan
a. Pelatihan P3K 0.020 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
b. Spanduk 0.012 0.012
c. Poster 0.008 0.008
d. Papan Informasi K3 0.026 0.026
12.3. Alat Pelindung Kerja dan Pelindung Diri
a. Topi Pelindung (Helmet) 0.016 0.016
b. Pelindung Mata 0.007 0.007
c. Tameng Muka (Welding Face Shield) 0.016 0.016
d. Sarung Tangan 0.013 0.013
e. Sepatu Keselamatan 0.091 0.091
f. Rompi Keselamatan 0.013 0.013
g. Life Jacket 0.026 0.026
12.4. Asuransi dan Perizinan
a. Asuransi 0.065 0.065
12.5. Personel K3 Konstruksi
a. Petugas K3 Konstruksi 0.228 0.046 0.046 0.046 0.046 0.046
12.6. Fasilitas, Sarana, dan Prasarana Kesehatan
a. Peralatan P3K 0.013 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
12.7. Alat Kornunikasi
a. Handy Talky 0.059 0.059
12.8. Tanda dan Rambu Serta Lampu
a. Rubber Cone uk. 70 cm 0.029 0.029
b. Rambu Petunjuk 0.007 0.007
c. Rambu Larangan 0.007 0.007
d. Rambu Kewajiban 0.007 0.007
e. Rambu Informasi 0.007 0.007
f. Rambu Pekerjaan Sementara 0.007 0.007
g. Jalur Evakuasi 0.007 0.007
h. Lampu Putar 0.007 0.007
12.9. Lain Lain Terkait Pengendalian Resiko K3
a. Konsultasi dengan Ahli Terkait Keselamatan Konstruksi 0.039 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002
b. Alat Pemadam Api Ringan (APAR) 0.010 0.010
c. Bendera K3 0.002 0.002
d. Pelaporan dan Penyelidikan Insiden 0.010 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
e. Pembuatan Kartu Identitas Pekerja di Area Pelabuhan 0.078 0.078
12.10. Penanganan Covid.
a. Thermo Gun. 0.005 0.005
b. Masker Kesehatan 0.033 0.007 0.007 0.007 0.007 0.007
c. Sabun Cair 0.003 0.003
d. Portabel Washing Hand 0.007 0.007

B PEKERJAAN STRUKTUR
1 Pile Cap
1.1. Beton fc'33.2 Mpa dengan Silica Fume 2.706 1.353 1.353
1.2. Platform Perancah 4.791 1.597 1.597 1.597
2 Beton Struktur fc'33.2 MPa dengan Silica Fume (Isi Silinder/Pile) 3.314 0.552 0.552 0.552 0.552 0.552 0.552
3 Baja Tulangan BJTD 40 6.813 0.852 0.852 0.852 0.852 0.852 0.852 0.852 0.852
4 Penyediaan Tiang Pancang Baja SPSP dia. 600 mm t. 12 mm (Type C-T) 26.596 4.433 4.433 4.433 4.433 4.433 4.433
5 Penyediaan Tiang Pancang Baja SPSP dia. 400 mm t. 9 mm (Type C-T) 21.703 3.617 3.617 3.617 3.617 3.617 3.617
6 Pemancangan Tiang Baja SPSP dia. 600 mm t.12 mm (Termasuk Penyambungan) 2.789 0.465 0.465 0.465 0.465 0.465 0.465
7 Pemancangan Tiang Baja SPSP dia. 400 mm t.9 mm (Termasuk Penyambungan) 3.851 0.642 0.642 0.642 0.642 0.642 0.642
8 Pre Boring 3.611 0.602 0.602 0.602 0.602 0.602 0.602
9 Pekerjaan Grouting Anchor fix
9.1. Grouting dengan Sika Anchor Fix 2 0.491 0.164 0.164 0.164
9.2. Platform Perancah 1.362 0.454 0.454 0.454
10 Perbaikan Beton Akibat Pengeboran (Grouting dengan Sika Anchor Fix 2) 0.384 0.384

C PEKERJAAN LAIN-LAIN
1 Penyedian dan Pemasangan Composite Wrapping 5.969 1.990 1.990 1.990
2 Pekerjaan Bongkar Pasang Cone Fender 0.052 0.026 0.026
3 Pekerjaan Dudukan Alas Alat Berat (Struktur Baja Profil) 9.719 4.859 4.859
4 Pekerjaan Pengecatan (Perekat Composite Wrapping) 0.692 0.231 0.231 0.231
5 Pengadaan dan Pemasangan Cathodic Protection (p, 5 kg) 0.136 0.068 0.068

TOTAL BOBOT PROGRESS 100.00


RENCANA MINGGUAN 0.00 0.354 0.578 6.279 5.703 0.038 0.607 0.607 0.659 2.828 11.984 11.984 12.780 12.832 12.780 10.950 1.409 3.974 0.857 0.857 1.426 0.099 0.413
RENCANA KUMULATIF MINGGUAN 0.00 0.354 0.932 7.210 12.914 12.952 13.559 14.166 14.826 17.653 29.637 41.621 54.401 67.234 80.014 90.964 92.373 96.348 97.205 98.062 99.488 99.587 100.000

Disetujui Oleh, Diperiksa Oleh, Dibuat Oleh,


PPK 5127.CBD.001.062.A KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA
Pengelolaan dan Penyelenggaraan Serta Pengendalian Mutu Infrastruktur
PT. REFENA KEMBAR ANUGRAH PT. NITA JAYA PRATAMA
Kawasan

TEUKU RIDWAN EFFENDY IR. KABAR SIRAIT DONIE AULIA, ST., MT.
NIP. 197208062002121001 Team Leader Project Manager