HMBD Review Check List
HMBD Review Check List
HMBD Review Check List
2.4.4 Desuperheating Spray Water Quantity and the Source BFP or CEP
2.5.2 Temperature
2.5.3 Flow
2.5.4 Desuperheating Spray Water Quantity and the Source BFP or CEP
2.6.1 Check all the Flow is considered for arriving Boiler outlet Flow like
g Check GSC, SJAE drain temperature and flow are connected to Hotwell
a Check GSC, SJAE drain temperature and flow are connected to Hotwell
2.10.6 Check the Pressure, temperature and Flow at STG extacrtion point.
Check the power generation capacity at LPH out condition and same meets
2.10.7
the contract requirment
Check whether LP heater drain cooler is provided in the circuit if required
2.11.4 Check the STG exhaust pressure during dumping is lesser than trip level
Check that the STG exhsuast pressure is communicated to ACC vendor if
2.11.5
ACC
2.11.6 Dumping steam steam pressure, temperature and flow at condenser inlet