Professional Documents
Culture Documents
Topic 07 Precedence Diagram-392
Topic 07 Precedence Diagram-392
TOPIC 07
Network Model (Analysis)
Precedence Diagram
Prepared by:
Dr. Khaled Khodary & Dr. Wael Alattyih & Dr. Sunny Narayan
CONTENTS
PRECEDENCE DIAGRAMMING.
HAMMOCK ACTIVITY.
MILESTONES.
1
9/8/2018
PRECEDENCE DIAGRAMMING
9/8/2018 10:05 AM
Project Management Course 3 Page: 3
2
9/8/2018
1. Start-to-Start (SSij)
SSij is equal to the minimum number of time units that must be
complete on the preceding activity (i) prior to the start of the
successor (j). “Lag” is always applied to SS relation.
2. Finish-to-Finish (FFij)
FFij is equal to the minimum number of time units that must
remain to be completed on the successor (j) after the
completion of the predecessor (i).
9/8/2018 10:05 AM
Project Management Course 5 Page: 5
9/8/2018 10:05 AM
Project Management Course 6 Page: 6
3
9/8/2018
9/8/2018 10:05 AM
Project Management Course 7 Page: 7
4
9/8/2018
Start-to-Start example
9/8/2018 10:05 AM
Project Management Course 10 Page: 10
5
9/8/2018
Finish-to-Finish example
9/8/2018 10:05 AM
Project Management Course 11 Page: 11
Finish-to-Start example
9/8/2018 10:05 AM
Project Management Course 12 Page: 12
6
9/8/2018
Start-to-Finish example
9/8/2018 10:05 AM
Project Management Course 13 Page: 13
Example
9/8/2018 10:05 AM
Project Management Course 14 Page: 14
7
9/8/2018
Example
9/8/2018 10:05 AM
Project Management Course 15 Page: 15
Example
9/8/2018 10:05 AM
Project Management Course 16 Page: 16
8
9/8/2018
9/8/2018 10:05 AM
Project Management Course 17 Page: 17
9/8/2018 10:05 AM
Project Management Course 18 Page: 18
9
9/8/2018
9/8/2018 10:05 AM
Project Management Course Page: 19
HAMMOCK ACTIVITY
An activity that extends from one activity to
another, but which has no estimated duration of its
own.
It is time-consuming and requires resources, but its
duration is controlled, not by its own nature, but by
the two activities between which it spans.
10
9/8/2018
MILESTONES
11