TOPIC 09
Scheduling Using
Program Evaluation and Review
Technique [PERT]
Prepared by:
Dr. Khaled Khodary & Dr. Wael Alattyih & Dr. Sunny Narayan
CONTENTS
Project Duration
PERT Computations
1
10/4/2018
2
10/4/2018
3
10/4/2018
4
10/4/2018
Mean = te = (a + 4m + b)/ 6
Where:
a = optimistic time, m = most likely time, and b = pessimistic time.
Project Management Course – Prepared By: Dr. Khaled Khodary Page: 9
Activity durations
p usually follow a
beta curve
Frequency of Occurrence
0.05 0.05
5
10/4/2018
6
10/4/2018
Project Duration
When te has been determined for each activity, project duration
(TE) and float can be determined from te by forward and
backward passes as in a CPM network.
Since the probability is 0.5 that each activity will finish at its
expected time te, there is a probability of 0.5 for the entire
project being finished at time TE.
7
10/4/2018
8
10/4/2018
Normal distribution
Mean = te
te - (Vt)1/2 te te + (Vt)1/2
68.26% of area
te - 2(Vt)1/2 te + 2(Vt)1/2
95.45% of area
te - 3(Vt)1/2 te + 3(Vt)1/2
99.973% of area
PERT Computations
1. Calculate expected activity duration (te)
te = (a + 4m + b)/6
where
a = Optimistic duration, m = most likely duration
b = pessimistic duration
2. Calculate standard deviation of an activity (vt)1/2 = ( te)
(vt)1/2 = (te) = (b – a)/ 3.2 (5%-95% Assumption)
If (b-a) is a large figure, greater uncertainty,
If (b-a) is small amount, less uncertainty.
3. Calculate variance of an activity (vt) = (2 te)
(vt) = 2 (te) = [(b –a) /3.2]2
4. Do CPM analysis, using ‘te’ as activity times.
9
10/4/2018
PERT Computations
5. Identify critical activities with activities times “te*”
6. Calculate project time (Te)
Te = te*
7. Calculate project variance (VT) = 2 (Te)
VT = 2 (Te) = 2 (te*)
For multiple critical paths, consider the highest total of
variances.
8. Calculate project standard deviation (VT)1/2 = (Te)
(Te) = (VT)1/2 or (Te) = (VT)
PERT Computations
10
10/4/2018
PERT Computations
(1- )
11
10/4/2018
Example
The basic information for a small research and development
project is listed in the table below. Use PERT technique to answer
the following questions:
Time in Weeks
Activity Depends on
a m b
A 2 3 4
B 4 5 6
C 1 2 3
D A 3 4 5
E B 1 1 2
F B 3 5 7
G C 1 2 3
H C 1 3 5
I D&E 3 6 9
J F&G 2 3 4
Example
1) Find the expected project duration Te , and project standard
deviation T.
2) What is the probability of completing the work in 15 weeks?
3) What is the probability of completing the work at 15 weeks?
4) What is the probability of not meeting a deadline of 15 weeks?
5) What is the due date that will have a 75% chance of meeting
(round of to the closet digit)?
6) What is the probability that Activity I can start by week 8th? OR,
what is the probability of finishing Activity D by 8 weeks?
7) What is the probability of completing the project between 10
weeks and 12 weeks?
8) What is the probability of not completing the project between
10 weeks and 12 weeks?
Project Management Course – Prepared By: Dr. Khaled Khodary Page: 24
12
10/4/2018
Example
Time in Weeks
Activity Depends on
a m b te t vt
A 2 3 4 3 0.625 0.39
B 4 5 6 5 0.625 0.39
C 1 2 3 2 0.625 0.39
D A 3 4 5 4 0.625 0.39
E B 1 1 2 1.17 0.3125 0.0977
F B 3 5 7 5 1.25 1.56
G C 1 2 3 2 0.625 0.39
H C 1 3 5 3 1.25 1.56
I D&E 3 6 9 6 1.875 3.52
J F&G 2 3 4 3 0.625 0.39
Example
0 0 3 3 0 7
A D
0 3 3 3 4 7
0.39 0.39
0 0 5 5 0.83 6.17 7 0 13
B E I
0 5 5 5.83 1.17 7 7 6 13
0.39 0.0977 3.52
0 0 0 5 0 10 10 0 13 13 0 13
START F J FINISH
0 0 0 5 5 10 10 3 13 13 0 13
0 1.56 0.39 0
0 6 2 2 6 4
C G
6 2 8 8 2 10 ES TF EF
0.39 0.39 Activity
LS t LF
2 3 5
vt
H
10 3 13
1.56
13
10/4/2018
Example
Example
14
10/4/2018
Example
68.26%
95.45%
99.973 %
15