Standard Operating Procedure: Department: Engineering Services Item: Electrical & Substation
Standard Operating Procedure: Department: Engineering Services Item: Electrical & Substation
Item Description:
SL No Items Description
01 1500 KVA, 11/0.415 KV Oil Immersed
Transformer
02 900 KVAr Auto/Manual PFI Panel
03 11 KV HT Switchgear (VCB)
04 LT Panel
05 ELT Panel
06 Floor MDB at every floor
07 Floor SDB at every floor
08 Solar Panel (7 Kw)
Sl No Description
03 Check HT Panel
04 Check LT Panel
2. Weekly Checklist:
SL No Description
3. Documentation:
4. Tools:
a. Tester, Screw Driver, Combination Pliers, Adjustable Pliers, PVC Tape, Nose Pliers,
Wire, Ladder, Torch Light, Cable Tie, Drill Machine, Hammer, Cutting Pliers, Hot