MEED Projects | MENA Project Tracking and Intelligence Tool Page 3 of 6

MEI

Pre-Qualified
Bidder
Awarded Alkifah Contracting
Shafi Ullah Khan, Procurement Officer
(+966) 138459502
shafi.khan@alkifah.com

Product & Capacities ? 

Tank (unit) 6
Water (cubic meter) 210,000

Key project milestones ? 

Main Contract Tender Issue (ITB, RFP) 30 Mar 2014


Main Contract Commercial Bid Submission 1 Jun 2014
Main Contract Award 25 Aug 2014
Main Contract Completion, Commissioning 11 Nov 2021

News and Updates 

11/11/2021 Construction works have been completed.


06/07/2021 Construction works are ongoing and the time frame for its completion is unknown at this juncture.
18/04/2021 Construction works are ongoing.
17/12/2020 Finishing works are ongoing.
20/08/2020 Construction works have been progressed up to 99 percent and expected to complete by end of 2020.
20/04/2020 Construction works are ongoing and expected to complete by December 2020.
07/10/2019 Construction works are ongoing and expected to complete by December 2019.
09/07/2019 Construction works have been progressed up to 90 per cent and expected to complete by December 2019.
06/03/2019 85% of construction works are completed.
The construction works on the project have progressed up to 80 per cent and is expected to be complete by
13/06/2018
beginning of 2019.
13/02/2018 The construction works are ongoing on the project and is expected to be complete by end of 2018.
There has been some addition in the scope of the project related to infrastructure works which has resulted in the
10/10/2017 delay in the project completion, as the additional works will require more 10 months to complete. The overall
project is now expected to complete by August 2018.
30/05/2017 The construction work on the project is ongoing and expected to be complete by July 2017.
18/04/2017 Construction works on the project is on going and expected to complete by May.
08/12/2016 The construction works are ongoing on the project and overall project is expected to get complete by May 2017.
31/08/2016 The construction works are ongoing on the project and completion is unknown at this point in time.
26/04/2016 The construction works have progressed up to 40 per cent and is expected to complete by Q2, 2017.
21/12/2015 Construction work is ongoing on the project and is expected to complete by June 2017.
19/08/2015 Construction work on the project has commenced
13/05/2015 The main contractor appointed on this project is Al Kifah Contracting Company.
25/05/2014 The bid submission date has been postponed to June 1, 2014.
03/04/2014 The client has issued the tender for the main contract. The bid submission date is expected to be on May 5, 2014.

Estimated Cash Flow (Quarterly) ?