No: OM-QA&QC/PL/MS-06
Rev.: 01
INSPECTION & CLEANING Page: 1 of 7
METHOD STATEMENT
FOR
00 For the initial issue & approval Oct 07,2021 Israr Owais Ahmed
INDEX
1. PURPOSE
2. PREPARATION
3. REFERENCES
4. RESPONSIBILITIES
6. PRESHUTDOWN ACTIVITIES
7. SHUTDOWN ACTIVITIES
8. SAFETY INSTRUCTIONS
1. PURPOSE
2. SCOPE
3. REFERENCES
Project Area Layout.
Marked up P& ID
General Arrangement & Detail Drawings
Detailed scope of work
4. RESPONSIBILITIES
1. Descon Supervisor shall coordinate with OQ maintenance and operations
for obtaining work permits and acceptance / renewal of the permit.
2. The Descon Supervisor shall ensure blinding as per the approved blind list
and follow OQ blinding procedure before executing the job.
3. Descon Supervisor shall be responsible for safe execution of the activities
as per scope in accordance with OQ safety policy & procedures.
4. Descon supervisor will deliver toolbox talk on the specific work to be carried
out as per OQ Permit to Work (PTW) and Job Safety Analysis (JSA) and
ensure that all necessary safety precautions are taken for the safe
execution.
5. Descon Planning Engineer will ensure that all necessary inputs such as
drawing’s material, consumables, tools and plant are arranged.
6. Descon supervisor shall be responsible for overall execution of job including
quality of the work within the specified schedule and observing OQ safe
work practices.
7. OQ inspection team will confirm the completion & quality of the job.
7. SHUTDOWN ACTIVITES
A. BLINDING ACTIVITIES
1. Obtain permit prior to start the job. All works shall be carried out only after
PTW’s are issued.
2. Blinding as per signed blind list.
3. Remove end covers & drop down using crane
4. Gas test will be carried out by AGT
5. Offer for as found inspection to OQ.
6. Necessary arrangement to be done for hydrojetting of tubes. Make sure
areas are barricaded with tarpaulin.
7. Hydro jet cleaning of tubes as per scope and inspection requirement.
8. Air blowing if required.
9. Tube inspection internally ECT/IRIS test to be done by OQ inspection.
10. Plug the Defective Tubes (if required).
11. Tube repair (Re Tubing-Rolling) by OQ if required.
12. Channel cover & channel head cleaning/power brushing & offer for
inspection.
13. If any repair is found in shell and weld joints, then repair will be carried out
as per OQ instructions with OQ approved WPS.
14. Offer the shell to OQ for Inspection after repair
15. Carry out shell side test and identify any leakage of tubes and then plug if
required.
16. Reinstall back channel head & channel cover
17. Carry out tube test to check gaskets of channel head covers
18. Draining of water & perform housekeeping.
19. Offer for final inspection to OQ.
C. BOX UP / DEBLINGING
8. SAFETY INDUCTION
During execution of the job all safety measure shall be adopted to ensure safe
work.
1. The workers will be made aware of OQ safety requirements related to this
activity through daily toolbox and safety talks in line with OQ Permit to Work
(PTW) and Job Safety Analysis (JSA) for the daily tasks to be performed.
2. Adequate PPE includes:
a. Helmet
b. Safety glasses
c. Coverall with long sleeves
d. Steel toed safety shoes
e. Appropriate gloves
f. Dust mask (if required)
g. Ear plugs as per job requirement.
h. Individual toxic clip (if required)
i. Other PPE may be worn as per job requirement(s)
3. The workers will be made aware of safety requirements related to this
activity through daily toolbox and safety talks. The work crew who is involve
in confined space and blinding/de-blinding should be fit tested.
4. Tool Box Talk (TBT) shall be performed in each shift and JSA along with
Permit to Work (PTW) requirements will be communicated by area lead to
work crew and shall be understood before starting any work.
5. Escape plan must be available at the work location, indicating:
a. The escape route
b. Emergency assembly point