Professional Documents
Culture Documents
Ch5 Scope
Ch5 Scope
Ch5 Scope
Chapter Five
Project Scope Management
5.4 Create WBS The process of subdividing project deliverables and project P
work into smaller, more manageable components.
5.5 Validate Scope The process of formalizing acceptance of the completed M&C
project deliverables.
5.6 Control Scope The process of monitoring the status of the project and M&C
product scope and managing changes to the scope baseline.
Because each project is unique, the project manager will need to tailor
the way Project Scope Management processes are applied.
Considerations for tailoring include but are not limited to:
Knowledge and requirements management: organization have
formal or informal knowledge.
Validation and control: existing formal or informal validation and
control-related policies and guidelines.
Development approach: use agile approaches in managing projects.
Stability of requirements: Are there areas of the project with
unstable need agile techniques.
Governance: have formal or informal audit and governance policies,
procedures, and guidelines.
6 Dr. Mohamed Harb
Introduction
Data analysis
• Document analysis:
Document analysis is used to elicit requirements by analyzing existing
documentation and identifying information relevant to the requirements.
22
Dr. Mohamed Harb
5.2 Collect Requirements
23
Dr. Mohamed Harb
5.3 Define Scope
The process of developing a detailed description of the project
and product.
The key benefit of this process is that it describes the product,
service, or result boundaries and acceptance criteria.
Expert Judgment
Data analysis
• Alternatives analysis
Decision making
• Multicriteria decision analysis
Interpersonal and team skills
• Facilitation: key players with a variety of expectations and/or fields of expertise
Product Analysis
translating high-level product descriptions into tangible deliverables.
It include
• Identifying and analyzing the deliverables,
• Structuring and organizing the WBS,
• Decomposing the upper WBS levels into lower-level detailed,
• Developing and assigning identification codes to the WBS components and Verifying
that the degree of decomposition of the deliverables is appropriate.
33 Dr. Mohamed Harb
5.4 Create WBS
Scope Baseline
is the approved version of a scope statement, WBS, and its associated WBS
dictionary, which can be changed only through formal change control
procedures. It consists of:
1. Scope Statement: description of the project scope, major deliverables, assumptions, and constraints
2. WBS: hierarchical decomposition of the total scope of work
3. Work package: The lowest level of the WBS is a work package with a unique identifier.
4. Planning package: A control account may include one or more planning packages. A
planning package is a work breakdown structure component below the control account and
above the work package.
5. WBS Dictionary: provides detailed deliverable, activity, and scheduling information about each
component in the WBS.
Decision-Making
• Voting
Project Documents
• Lessons learned register
• Requirements Documentations
• Requirements Traceability Matrix
A. Team
B. Project manager
C. Customer
D. Stakeholder
Answer: D
Answer: C
A. Control Quality
B. Sequence Activities
C. Manage Quality
D. Schedule Management
Answer: A
Explanation Control Quality checks for correctness, and Validate Scope checks for acceptance.
Answer: A
The project scope statement is an output of the Define Scope process. The work
breakdown structure is an output of the Create WBS process. Scope change requests are
outputs of the Validate Scope and Control Scope processes. The requirements traceability
matrix is an output of the Collect Requirements process, and is used to track the
requirements throughout the life of the project.
55 Dr. Mohamed Harb
All of the following are parts of the scope baseline except the:
Answer: A
Answer: C
A. Work Break down Structures will prevent work from slipping through cracks.
B. Work Break down Structures are of greater value on large projects.
C. Work Break down Structures are required only if the project involves contracts.
D. Work Break down Structures are the only way to identify risks.
Answer: A