Professional Documents
Culture Documents
2017 BORAN A Novel SMED Approach
2017 BORAN A Novel SMED Approach
2017 BORAN A Novel SMED Approach
DOI 10.1007/s00170-017-0424-9
ORIGINAL ARTICLE
Received: 29 December 2016 / Accepted: 11 April 2017 / Published online: 6 May 2017
# Springer-Verlag London 2017
Abstract One of the shortcomings of the conventional conventional SMED method, the setup time is reduced to
single-minute exchange of die (SMED) method is that the 101 min, whereas with the new approach, the setup time is
improvements are made only upon the machine to reduce reduced further to 21.5 min.
setup times. Although most of the setup activities involve
operators, they are not considered adequately in this method. Keywords Single-minute exchange of die (SMED)
In workplaces with non-ergonomic setup systems, operators methodology . Sue Rodgers muscle fatigue assessment
are exposed to different ergonomic risks, and thus, muscle method . Grey-based Taguchi method . Setup Observation and
fatigue is a problem for them. During the setup activities, Analysis Form . Reducing setup time
muscle fatigue increases the setup times and risks of work
accidents. In this study, the muscle fatigue assessment
(MFA) method, also known as the Sue Rodgers method, was 1 Introduction
integrated into the conventional SMED method in order to
evaluate the ergonomic risks in setup activities. Since the tools Today, customers demand products with high quality, a rea-
of the conventional SMED method are insufficient to shorten sonable price, and short response time. Manufacturing com-
setup times, the grey-based Taguchi method, which consists of panies should implement lean and customer-based production
multiresponses such as setup time and fatigue risk, has been to meet all customer demands. Therefore, companies are
used for a setup activity. This method allows the determination forced to produce smaller lots. However, producing smaller
of the process factor levels to minimize these responses. A batch sizes causes more changeovers. Both setup and change-
form has also been developed for the integrated SMED meth- over have been defined as the process of switching from the
od, which is called the Setup Observation and Analysis Form. production of one product or part number to another in a
The developed integrated SMED method based on the Sue machine by changing parts, dies, molds, or fixtures [1].
Rodgers muscle fatigue assessment method and grey-based Thus, a short setup time is critical for being able to produce
Taguchi method has been applied to a CNNx machine in a small quantities of a large diversity of products. It is the basis
factory producing aluminum profiles. The overall setup time of lean manufacturing. The reduction in setup times of a ma-
has been reduced to 73.5 min from 196 min, which indicates a chine or line is a cost-effective contribution to flexible and
total of 122.5 min and 62.5% improvement. With the lean manufacturing [2]. Productive time of a machine can be
increased by reducing its setup time. It is not possible to es-
cape from setup time, but there are activities which reduce
time such as standardization, implementing parallel opera-
tions, improving die transportation mechanization, and im-
* Semra Boran proving die transportation function standardization [3].
boran@sakarya.edu.tr Most initiatives for setup reduction time have been associ-
ated with Shingo’s single-minute exchange of die (SMED)
1
Department of Industrial Engineering, Sakarya University, methodology. The SMED methodology makes it possible to
Adapazarı, Sakarya, Turkey perform equipment setup (changeover) operations in less than
3942 Int J Adv Manuf Technol (2017) 92:3941–3951
10 min, i.e., the number of minutes expressed by a single digit automotive [5, 12–14], electronic assembly [15], aluminum
[4]. It can be considered as one of the tools of lean manufactur- profile extrusion [16], and electrical power control [17].
ing. It reduces waste and improves flexibility in manufactur- Trovinger and Bohn [15] showed that modern information
ing processes, allowing lot size reduction and flow improve- technology can be used in SMED concepts to some complex
ments. It reduces nonproductive time by streamlining and situations. Cakmakci and Karasu [7] achieved a new integrat-
standardizing the operations for exchange tools, using simple ed methodology that contained SMED and methods-time
techniques and easy applications. However, the process does measurement (MTM). This integration provides both further
not give specific actions to implement, which can result in detailed analysis by motion study and standardization of the
overlooking improvements [5]. optimal changeover procedure that is achieved by SMED and
There is little awareness about the quantitative techniques MTM analysis. Cakmakci [12] used the process capability
that can be used to calculate requirements of having shorter analysis technique, Cpk index, to investigate the relation be-
setup times [3]. Advanced methods to reduce setup time are tween the SMED method and equipment design. Almomani
needed [6]. Alternative methods to shorten internal setup et al. [18] studied different issues about SMED. They used
times can be searched in detail. Therefore, the muscle fatigue analytical hierarchy process (AHP), preference selection index
assessment method and grey-based Taguchi method were in- (PSI), and technique for order preference by similarity to ideal
tegrated into the SMED method in this study. solution (TOPSIS), which are multiple-criteria decision-making
In the conventional SMED method, setup activities are (MCDM) techniques to select the best setup technique among
mostly made by improvements upon machines; however, not the available alternatives. Other factors such as cost, energy,
only machines but also operators take part in the setup pro- facility layout, safety, life, quality, and maintenance that affect
cess. An important lack of the SMED methodology is the the decision-making process were considered. Karasu et al. [6]
consideration and motivation of operators [7]. Ergonomics applied the Taguchi method to SMED to achieve the parameters
and safety issues are also taken into consideration during set without adjustment. Stadnicka [19] studied to reduce setup
setups. Ulutas [8] noted issues related to employer safety time and the risk of problems which can appear during the
and ergonomic principles during setups. Operators do their setup. In this study, tools such as Pareto analysis, statistical
jobs quickly and easily without ergonomic risk; thus, simple analysis, and FMEA were used together with the SMED meth-
however crucial changes must be done in the workplace. This odology. Similarly, the Taguchi method based on grey relational
issue is discussed in the literature [9, 10]. analysis has been extensively studied and implemented in dif-
In workplaces with non-ergonomic systems, operators are ferent processes such as turning [20, 21], drilling [22], laser
exposed to different ergonomic risks, and thus, muscle fatigue cladding [23], and emulsification [24].
is a widespread problem among them. In setup activities, muscle In our limited literature research, we could not find an
fatigue increases setup times and also increases work accident integrated SMED method based on the grey-based Taguchi
risks. Furthermore, duration of treatment because of minor injury method and the Sue Rodgers muscle fatigue assessment meth-
makes setup times longer. Muscle fatigue assessment (MFA) is od together. The difference of the study from the studies in the
one of the risk assessment methods. Muscle fatigue assessment, literature is that the ergonomic risk assessment is applied in
also known as the functional job evaluation technique, was de- the setup activities and the multiresponse Taguchi method is
veloped by Rodgers [11] to characterize the discomfort described used. Therefore, the integrated SMED method and the newly
by operators. With this method, muscle fatigue caused by setup developed “Setup Observation and Analysis Form” will be the
activities is evaluated to decrease setup time. first in the literature.
In this study, further improvement in total setup time after The proposed integrated SMED method has been applied
application of the SMED and Sue Rodgers MFA methods is to an aluminum profile manufacturer. The setup activity time
aimed. It is aimed that time of measuring and assessment of the has been reduced to 73.5 min from 196 min, which results in
first product after a changeover activity can be reduced by the 122.5 min of improvement. With the conventional SMED
experimental design method. The grey-based Taguchi method, method, the setup time is reduced to 101 min, whereas with
which is a multiresponse Taguchi method, is used since there are the new method, the setup time is reduced further to 21.5 min.
two responses: setup time and fatigue risk. The reason for using
grey relational analysis is the subjective evaluation of fatigue risk
assessment by experts. This method is used for obtaining the 2 Methods
level of factors (parameters of the process) which minimize time
of the measuring and assessment of the first product. 2.1 SMED methodology
The Setup Observation and Analysis Form has been newly
developed for the integrated SMED method. Shingo defined SMED as “a scientific approach to setup time
In the literature, the SMED method has been extensively reduction that can be applied in any factory to any machine.”
studied and implemented in various industries such as The SMED methodology makes it possible to perform
Int J Adv Manuf Technol (2017) 92:3941–3951 3943
Neck Head turned partly to side, Head turned to side, head fully Same as moderate but
back, or slightly forward back, head forward about 20° with force or weight;
head stretched
forward
Shoulders Arms slightly away from Arms away from body, no Exerting forces or Right
sides; arms extended support; working overhead holding weight with Left
with some support arms away from
body or overhead
Back Leaning to side or bending Bending forward; no load; lifting Lifting or exerting
arching back moderately heavy loads near force while twisting;
body; working overhead high force or load
while bending
Arms/elbows Arms away from body, no Rotating arms while exerting High forces exerted Right
load; light forces lifting moderate force with rotation; lifting Left
near body with arms extended
Wrists/hands/fingers Light forces or weights Grips with wide or narrow span; Pinch grips; strong Right
handled close to body; moderate-risk angles, wrist angles; Left
straight wrists; especially flexion; use of slippery surfaces
comfortable power grips gloves with moderate forces
Legs/knees Standing, walking without Bending forward, leaning on Exerting high force Right
bending or leaning; table; weight on one side; while pulling or Left
weight on both feet pivoting while exerting force lifting; crouching
while exerting force
Ankles/feet/toes Standing, walking without Bending forward, leaning on Exerting high force Right
bending or leaning; table; weight on one side; while pulling or Left
weight on both feet pivoting while exerting force lifting; crouching
while exerting force
Continuous effort <6 s 6–20 s 20–30 s >30 s
duration 1 2 3 4 (enter VH for priority)
Effort frequency <1/min 1–5/min >5–15/min >15/min
1 2 3 4 (enter VH for priority)
equipment setup (changeover) operations in less than 10 min. of materials, mounting and removing tools, settings and cali-
It provides a rapid way of converting a manufacturing process brations, measurements, trial runs, and adjustments [25].
from processing the current product to processing the next Some methods can be applied in order to reduce activity time.
product. It was originally developed to improve die press
and machine tool setup, but its principles are applied to
changeovers in all types of machines and processes. A setup Table 2 Category scores for three-number rating (effort, duration, and
operation is a preparation or adjustment that is performed once frequency) [27]
before each lot is processed [4]. The SMED methodology also Low (L) Moderate (M) High (H) Very high (VH)
reduces the timeline between the customer order and shipment
by eliminating waste. Thus, it is a lean production method for 111 123 223 323
reducing waste in a manufacturing process. 112 132 313 331
In the SMED methodology, setup activities are divided into 113 213 321 332
internal and external activities. External activities can be car- 211 222 322
ried out during the normal operation of a machine when it is 121 231 4xx
still running. For example, getting the equipment ready for the 212 232 x4x
setup operation can be done before the machine is shut down. 311 312 xx4
Internal activities can be performed only when the machine is 122
shut down. For instance, the dies are attached or removed. The 131
internal and external setup activities contain different opera- 221
tions such as preparation, after-process adjustment, checking
3944 Int J Adv Manuf Technol (2017) 92:3941–3951
Some options such as using functional clamps, implementing are <1 per minute (low-1), 1 to 5 per minute (moderate-2), >5
parallel operations, reducing adjustments to minimum, and to 15 per minute (high-3), and >15 per minute (very high-4).
designing effective tools are suggested. Effort durations are <6 s (low-1), 6 to 20 s (moderate-2), 20 to
A video recording of different runs of the machine is firstly 30 s (high-3), and >30 s (very high-4). Effort levels are chosen
analyzed. The activities and their times can be determined as the percentage of maximum strength in the postures used
using video recording and routing diagrams. There are steps and are as follows: low, <40% of maximum; moderate, 40 to
which are used to reduce the setup time using the SMED <70% of maximum; and heavy, ≥70% of maximum.
methodology [4]: The combinations of scores are ranked in the order of in-
creasing fatigue in Table 2. The least fatiguing combinations
& Separation of the internal and external activities. are at the top of the left side of the table, and the highest are at
& Conversion of internal activities into external activities. the bottom of the right side of the table. A score has a three-
& Streamlining the external and internal activities. Focusing number rating (effort, effort duration, and frequency). For ex-
on streamlining all aspects of the setup operation. Specific ample, the value 332 in the table shows that 3: effort spent, 3:
principles are applied to shorten the setup times. the duration, and 2: effort frequency, respectively. As seen in
& Standardization. All the activities must be standardized to Table 2, the value 332 is a high risk value.
reduce setup time in other machines. It is more difficult to When activity is improved, the new task is re-rated to be
sustain new changeover activity unless standardized. sure that fatigue has been dropped to a lower level.
1 To bring the overhead crane in front of the 8 Internal 2/medium It was decided to bring the overhead None 0 External 2/medium 8
CNC machine crane in front of the CNC machine
before the end of the previous
production.
2 Taking the fixture from the CNC machine 7 Internal 3/high None It was decided to help a 4 Internal 2/medium 3
different person to the main
operator.
Int J Adv Manuf Technol (2017) 92:3941–3951
3 Taking left diffuser from the CNC machine 5 Internal 2/medium None It was decided to, instead of 3 Internal 1/low 2
doing this work, manually
link to the left diffuser with
ropes after taking from the
CNC machine with the
overhead crane.
4 Putting the fixture which is received from 8 Internal 2/medium It was decided to, firstly, place the fixture None 0 External 2/medium 8
the CNC machine, on the shelf of the near the CNC machine and then carry
fixture it to the shelf of the fixture during
second piece processing.
5 New fixture placed near the CNC machine 8 Internal 3/high It was decided to bring the new fixture to None 0 External 3/high 8
after taking the shelf of the fixture the CNC machine before the end of
the previous production.
6 Cleaning the CNC machine 4 Internal 2/medium None It was decided to use both 3 Internal 1/low 1
hands instead of one hand of
the operator in using the air
compressor gun when
cleaning the CNC machine.
7 Putting the fixture on the platform 9 Internal 3/high The fixture is placed on the tray slides for This step has been determined 4 Internal 2/medium 5
easier settlement and housing to the to be the most risky to the
point that it locks when opened. arms and hands. For this,
alternative arm support rails
are placed on the CNC
machine which is mounted
on the support sled. Thus,
the elbows and arms of
employees rest comfortably
on these supports.
8 Determination of the position of the fixture 14 Internal 2/medium Without horizontal and vertical reference None 2 Internal 2/medium 12
on the platform and fixing planes of the fixture, adjusting the
position takes longer. This process
was designed to be a reference to the
part of the plane. This plane has
provided faster and easier settlement
of the fixture.
9 Creating a plane of reference for the datum 11 Internal 2/medium The process of creating a plane of None 0 Internal 2/medium 11
point in the X-axis. reference for the datum point in the
3945
SMED approach
have a conflict between factors, it is necessary to rely on the
subjective experiences of engineers to attain a compromise
(min) [28]. As a result, there will be increase in uncertainty during
6
to investigate multiple responses in process operations. Grey
improvement (min)
relational analysis based on grey system theory can be used
1/low
for solving the complicated interrelationships among multiple
Risk
Internal
Time
(Eqs. 1–3).
It was decided to propose the process
. .
workshop when processing the
. . .
S N ¼ −10log ∑ 1 y2i n ð2Þ
.
S N ¼ −10log s2 ð3Þ
Suggestions
196
0 X i ð jÞ−minni¼1 X i ð jÞ
Activity
X i ð jÞ ¼ ð4Þ
maxni¼1 X i ð jÞ−minni¼1 X ið jÞ
6
the second piece that will be processed
Retouching in the computer software for
Neck 2 2 2 222 2
Shoulders 1 2 1 121 1
Table 3 (continued)
Back 3 2 1 321 3
No. Description
Arms/elbows 3 2 2 322 2
Wrists/hands/fingers 2 1 3 213 2
Legs/knees 2 2 1 221 1
Before
Ankles/feet/toes 2 2 1 221 1
19
3948 Int J Adv Manuf Technol (2017) 92:3941–3951
Table 5 Factors and their levels ζ is the distinguishing coefficient and issued to adjust the
Factors Symbols Levels difference of the relational coefficient. It takes a value between
0 and 1.
1 2 The grey relational grade is calculated as Eq. 9, and it
shows the relationship among the series
Operator A O1 O2
Winch speed (m/min) B 8 14 1 m
Screwdriver speed (rev/min) C 90 2200 Γ0i ¼ ∑ γ ð jÞ ð9Þ
n j¼1 oi
Caliper tool D Vernier Digital
where n is the number of responses. Since higher multiple
responses are desirable, the larger-the-better S/N quality
If a defined target value Xd exists, the response can be characteristic is adopted for the grey relational grade. A
normalized as follows (Eq. 5): higher grey relational grade corresponds to a closer exper-
jX i ð jÞ−X d ð jÞj
imental value to the ideal normalized value. Thus, this
ð5Þ
0
X i ð jÞ ¼ 1−
max maxni¼1 X i ð jÞ−X d ð jÞ; X d ð jÞ−minni¼1 X i ð jÞ grade shows that the corresponding factor combination is
closer to the optimal. The highest grey relational grade is
If the response is aimed to minimize, its characteristic is assigned an order of 1.
the-smaller-the-better and it can be normalized as follows The obtained grey relational grades are analyzed by using
(Eq. 6): analysis of variance (ANOVA) to identify the importance fac-
tors. The levels of these factors are determined. Confirmation
0 maxni¼1 X i ð jÞ−X i ð jÞ
X i ð jÞ ¼ ð6Þ experiments are repeated several times. The mean of grey
maxni¼1 X ið jÞ −minni¼1 X i ð jÞ relational grades is calculated based on the results of the
0 experiments.
where X i is the value after grey relational generation (normal-
The predicted mean grey relational grade (μÞ using the
ized value) and max Xi(j) and min Xi(j) are the largest and optimal level of factors can be calculated according to Eq. 10.
smallest values of the Xi ith response, respectively. A larger
h i
normalized result means better performance, and it should be ^ ¼ T þ ∑pi¼1 T i; j
μ −T ð10Þ
equal to 1. max
Table 7 Determining risk grade for eighth experiment setup improvement values are placed below the “After”
Regions Effort Effort Effort Risk Risk section.
level duration frequency grade
Neck 2 2 2 222 2
Shoulders 1 2 1 121 1 4 Implementing integrated SMED method
Back 2 3 2 232 2
Arms/elbows 2 2 1 221 1 It was decided to apply the new integrated SMED method to
Wrists/hands/fingers 2 2 2 222 2 reduce the setup time of a CNCx machine in a XYZ company
Legs/knees 1 2 1 121 1 in Turkey. The company produces aluminum profiles. The
Ankles/feet/toes 1 2 1 121 1 setup activities of all the CNC machines were observed before
SMED was implemented, and the time taken for setup of each
machine was noted. A CNCx machine that takes longer setup
times compared to other machines’ setup times was chosen.
Confirmatory runs based on optimal factor settings are The details of the setup process of products on the CNCx were
carried out, and the average is computed. If the value of recorded on a video camera. It was determined that part no.
the average obtained from the experiment is between the 2222 has the longest total setup time. Its total setup time was
estimated μ^ CI value, then it accepts a set of factors and broken down into 19 setup activities. Activities’ numbers,
their levels. times, and descriptions were recorded on the new integrated
Setup Observation and Analysis Form, respectively (Table 3).
In the current practice, all of the activities of SMED were
3 Proposed integrated SMED method determined as internal activities and written as internal in the
internal/external column on the form in Table 3.
The steps of the proposed new integrated SMED method is Ergonomic risk assessment was made for 19 activities by
depicted in Fig. 1. The model starts with defining setup activ- applying the Sue Rodgers muscle fatigue assessment method.
ities and times. The steps of the SMED methodology are ap- For defining risks for setup activities, the table developed by
plied. Ergonomic risk values are determined with the Sue Sue Rodgers is used. For example, the risk assessment table
Rodgers muscle fatigue assessment method for every setup for activity 15 “control of first produced part by an operator” is
activity. Improvements are made for reduction and/or elimi- shown in Table 4. Seven parts of the human body are assessed
nation of time and ergonomic risks. The grey-based Taguchi for activity-related risks. The risk factors values were deter-
method is used for further time reduction. mined on the basis of Tables 1 and 2. In Table 2, verbal risk
Information about all these steps is filled in the newly de- values were quantified between 1 and 5 for this study. The
veloped Setup Observation and Analysis Form (Table 3). The values 1, 2, 3, and 4 indicate low, medium, high, and very high
form consists of three steps. Firstly, SMED steps and risk values, respectively. The value 5 (super high value) is used for
values of every activity are recorded below the “Before” sec- 4xx, x4x, and xx4. The back of the body has the highest
tion. Secondly, suggestions for time reduction and suggestions ergonomic risk value (value 3) and thus determines the risk
for risk reduction/elimination are recorded below the value of this activity. Risk assessment was repeated for the
“Suggestions” section. Finally, new time and risk values and other 18 activities.
The grey-based Taguchi method was applied to activity 15, relational degree was 0.9901, which was placed between
which was unimprovable by the SMED and Sue Rodgers 0.7285 and 1.1145, and then the optimum set (A2B2C2) justi-
methods. The activity was an internal activity. In this activity, fied the adequacy of the model. With this set, time was
the part is removed from the CNCx machine and is moved to 15.5 min. In the initial state, activity time was 21 min. Thus,
the control by the operator. It was aimed to simultaneously an improvement of 5.5 min was achieved. Values before and
optimize two responses, time and risk. Both signal-to-noise after application of the grey-based Taguchi method is shown
ratios were determined as the-smaller-the better. The chosen in Table 10.
factors (operators, winch speed, screwdriver speed, and cali-
per tool) which had been accepted were effective time and
risk, and their levels are summarized in Table 5. Each factor 5 Results and discussion
had two levels. In addition, interactions among factors were
not taken into consideration. Hereby, an orthogonal array was The proposed integrated SMED method was applied to part
chosen (Table 6). All the eight experiments were randomly no. 2222 of a CNCx machine in an aluminum profile manu-
repeated twice. Risk values for every experiment were deter- facturer. The result is that the overall setup time was reduced
mined with the Sue Rodgers method (Table 6). For example, to 73.5 min from 196 min, which indicates a total of 122.5 min
the risk value “2” for the eighth experiment in Table 6 was and 62.5% improvement. If the conventional SMED method
determined by risk assessment in Table 7. Risk assessment was applied, the setup time would be reduced to 101 min.
was performed for each of the experiments. With the new approach, the setup time was reduced further
In grey relational analysis method application, S/N to 21.5 min. Reductions of 16 and 5.5 min were achieved by
ratio values were normalized with Eq. 6 because “the- the Sue Rodgers method and grey-based Taguchi method,
smaller-the-better” was required. Every experiment’s respectively.
grey relational grades were determined using Eqs. 7–9
(Table 8). In this study, ζ was taken as 0.5. As shown in
Table 8, the highest grade (optimum) was obtained from 6 Conclusion
experiment 8.
To determine effective factors, ANOVA was conducted on This study has three important contributions. The first contri-
the grey relational grade. The results of ANOVA using bution is to demonstrate that integrating the ergonomic risk
Minitab 15 can be seen in Table 9. According to the signifi- assessment analysis method into the SMED method results in
cance level of 0.05, the first three factors were effective while further reduction in setup times. The Sue Rodgers muscle
the fourth factor was not effective. Thus, the set was A2B2C2. fatigue assessment method is used for determining the risk
The predicted mean value of the grey relational degree of muscle fatigue that occurs when the operator performs set-
from Eq. 10 was achieved to be 0.9215. CI was calculated up activities. Ergonomic setup activities reduce fatigue and
as ±0.193 from Eq. 11. A confirmation experiment was per- then lead to decrease in setup times. The second contribution
formed four times, and the mean value of the calculated grey of this study is to show that the multiresponse experimental
design method can be integrated into the SMED method. The 11. Rodgers SH (1992) A functional job evaluation technique.
Ergonomics, Occup Med-State Art 7(4):679–711
grey-based Taguchi method is applied to an activity that can-
12. Cakmakci M (2009) Process improvement: performance analysis of
not be reduced by the SMED method. This multiresponse the setup time reduction-SMED in the automobile industry. Int J
method allows the factor levels of the setup activity to be Adv Manuf Technol Vol 41(1):168–179
determined in such a way that they minimize two responses: 13. Deros BM, Mohaamad D, Idris MHM, Rahman MNA, Ghani JA,
ergonomic risk and time. With this method, the levels of fac- Ismail AR (2011) Setup time reduction in an automotive battery
assembly line. Int J Syst App 5(5):618–625
tors are obtained much faster than with the trial and error
14. Joshi RR, Naik GR (2012) Application of SMED methodology—a
method. The third contribution of the study is that a new case study in small scale industry. International Journal of Scientific
Setup Observation and Analysis Form has been developed and Research Publications 2(8):1–4
to evaluate setup activities according to time and ergonomic 15. Trovinger SC, Bohn RE (2005) Setup time reduction for electronics
risk in SMED applications. assembly: combining simple (SMED) and IT-based methods. Prod
Oper Manag 14(2):205–217
This integrated SMED method can be implemented to all 16. Assaf R, Haddad T (2014) Performance improvement using the
SMED applications to decrease ergonomic risk and activity single minute exchange of die (SMED) methodology in an alumi-
time, and it leads to reduce setup time. Not only time reduction num profiles extrusion production system. The 1st international
but also ergonomic risks are improved with this method. Also, conference on industrial, systems and manufacturing engineering
(ISME’14)
unrecorded minor injuries are expected to decrease.
17. Ribeiro D, Braga F, Sousa R, Carmo Silva S (2011) An application
In case this integrated SMED approach will be applied to of the SMED methodology in an electric power controls company.
all parts produced by machines, there will be overall Romanian Review Precision Mechanics, Optics and Mechatronics
improvement. No.40, pp.115–122
The use of fuzzy logic in risk assessment is recommended for 18. Almomani MA, Aladeemy M, Abdelhadi A, Mumani A (2013) A
proposed approach for setup time reduction through integrating
future work because the evaluation of the experts is subjective. conventional SMED method with multiple criteria decision-
making techniques. Comput Ind Eng 66:461–469
19. Stadnicka D (2015) Setup analysis: combining SMED with other
tools. Management and Production Engineering Review 6(1):36–
50
References
20. Lin CL (2004) Use of the Taguchi method and grey relational anal-
ysis to optimize turning operations with multiple performance char-
1. Benjamin SJ, Murugaiah U, Marathamuthu MS (2013) The use of acteristics. Mater Manuf Process 19(2):209–220
SMED to eliminate small stops in a manufacturing firm. J Manuf 21. Tzeng CJ, Lin YH, Yang YK, Jeng MC (2009) Optimization of
Technol Manag 24(5):792–807. doi:10.1108/17410381311328016 turning operations with multiple performance characteristics using
2. Gung D, Studel F (1990) A work load balancing model for deter- the Taguchi method and grey relational analysis. J Mater Process
mining set-up time and batch size reduction in G.T. flow line work Tech 209(6):2753–2759
cells. Int J Prod Res 28(4):255–292 22. Haq AN, Marimuthu P, Jeyapaul R (2008) Multi response optimi-
3. Singh BJ, Khanduja D (2010) SMED: for quick changeovers in zation of machining parameters of drilling Al/SiC metal matrix
foundry SMEs. Int J Prod Perf Manag 59(1):98–116 composite using grey relational analysis in the Taguchi method.
4. Shingo S (1985) A revolution in manufacturing: The SMED sys- Int J Adv Manuf Technol 37:250–255
tem. Productivity press, USA translated by Dillon, A.P
23. Mondal S, Kukreja LM, Bandyopadhyay A, Pal PK (2013)
5. Desai MS (2012) Productivity enhancement by reducing setup time
Application of Taguchi-based gray relational analysis for evaluat-
– SMED: case study in the automobile factory. Global Journal of
ing the optimal laser cladding parameters for AISI1040 steel plane
Research in Engineering Mechanical and Mechanics Engineering
surface. Int J Adv Manuf Technol 66(1):91–96
12(5):15–20
24. Vellaiyan S, Amirthagadeswaran KS (2016) Taguchi-Grey relation-
6. Karasu MK, Cakmakcı M, Cakiroglu MB, Ayva E, Demirel-
al-based multi-response optimization of the water-in-diesel emulsi-
Ortabas N (2014) Improvement of changeover times via Taguchi
fication process. J Mech Sci Technol 30(3):1399–1404
empowered SMED/case study on injection molding production.
Measurement 7:741–748 25. Ferradás PG, Salonitis K (2013) Improving changeover time: a
7. Cakmakci M, Karasu MK (2007) Set-up time reduction process and tailored SMED approach for welding cells. Proceedia CIRP 7:
integrated predetermined time system MTM-UAS: a study of ap- 598–603
plication in a large size company of automobile industry. Int J Adv 26. Pannesi RT (1995) Lead time competitiveness in make-to-order
Manuf Technol 33:334–344 manufacturing firm. Int J Prod Res 3(6):150–163
8. Ulutas B (2011) An application of SMED methodology. World 27. Rodgers SH (2005) Muscle fatigue assessment: functional
Acad Sci Eng Technol 5:63–66 job analysis technique in handbook of human factors and
9. Mcintosh R, Culley S, Gest G, Mileham T, Owen G (1996) An ergonomics methods. Stanton N, Hedge A, Brookhuis K,
assessment of the role of design in the improvement of changment Salas E, Hendrick H Ed. CRC PRESS, USA chapter 12,
performance. Int J Oper Prod Man 16(9):5–22 pp. 12-1, 12-9
10. Van Goubergen D, Van Landeghem H (2002) Reducing setup times of 28. Phadke MS (1989) Quality engineering using robust design.
manufacturing lines. In Proceeding of international conference on flex- Prentice-Hall, Englewood Cliffs
ible automation and intelligent manufacturing, Dresden, Germany 29. Deng J (1989) Introduction to grey system. J Grey Syst 1(1):1–2
International Journal of Advanced Manufacturing Technology is a copyright of Springer,
2017. All Rights Reserved.