7,302,377.10 Sub-Total Percentage Per Week
7,302,377.10 Sub-Total Percentage Per Week
7,302,377.10 Sub-Total Percentage Per Week
I GROUND FLOOR 14
A EXCAVATION 8 ₱ 1,767,577.45 7.57% 0.00946 0.00946 0.00946 0.00946 0.00946 0.00946 0.00946 0.00946
B STEEL WORKS (FAB & INST) ₱ 3,390,476.45 14.52%
1.B FOOTING 8 ₱ 661,141.41 0.018155272 0.01816 0.01816 0.01816 0.01816 0.01816 0.01816 0.01816
2.B RET. WALL FOOTING 2 ₱ 572,765.01 0.072621089 0.07262 0.07262 0.07262 0.07262 0.07262 0.07262
3.B COLUMN 8 ₱ 460,031.40 0.018155272 0.01816 0.01816 0.01816 0.01816 0.01816 0.01816 0.01816
4.B RET. WALL 13 ₱ 979,950.76 0.011172475 0.01117 0.01117 0.01117 0.01117 0.01117 0.01117 0.01117 0.01117 0.01117 0.01117 0.01117 0.01117
5.B GRADE BEAM 2 ₱ 219,542.40 0.07262 0.07262
6.B GROUND FLR. SLAB 1 ₱ 37,800.00 0.14524
7.B BEAM 4 ₱ 224,815.50 0.03631 0.03631 0.03631 0.03631
8.B INTERMEDIATE BEAM 4 ₱ 117,214.99 0.03631 0.03631 0.03631 0.03631
9.B CANTILEVER BEAM 4 ₱ 117,214.99 0.03631 0.03631 0.03631 0.03631
C FORMWORKS 11 ₱ 1,164,123.20 4.99% 0.00453 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002