Professional Documents
Culture Documents
Proj Fin Q Bank
Proj Fin Q Bank
Cost of Projects
Erection 3.20
Estimate the total cost of the project showing details, and also interest amount
for 2 years. (Provide for 5% contingency for imported items, 10% for indigenous
items and 20% for building structure, nil for erection cost)
b. Government equity is to be fully utilized in the first year and rest of the
funding is assumed to be utilized to the extent of 50% during year 2 and
equally for rest of years
c. Total cost of Rs.2165 lacs is expected to phase out as 50% in year 1, 30%
in year 2, 10% in year 3 and balance 10% after year 3
You are required to work out Year wise phasing of the total cost with
various resources, Interest amount year wise for 3 years. (Ignore
Opportunity cost for Internal generation)
2
EX MBA - SEM IV – PROJECT FINANCE Q BANK
Component TP11 – Qty to be used 120 ton at the price of 90.50 per ton
Component QT11 – Qty to be used 85 ton at the price of 110.50 per ton
Component ZT11 – Qty to be used 135 ton at the price of 45 per ton
Project gets completed in time but there was change in the scope in
between, and the prices also gets changed as under
Component TP11 – Qty used 105 ton at the price of 100.50 per ton
Component QT11 – Qty used 115 ton at the price of 100.75 per ton
Component ZT11 – Qty used 150 ton at the price of 52 per ton
Calculate the project cost as budgeted and actual with the variances
analysis as change in scope as well as price change.
3
EX MBA - SEM IV – PROJECT FINANCE Q BANK
Following details are extracted from the project file for the year 2020-21(Rs
in lacs
Budget Actual
Utilities -
Maintenance 50 60
5
EX MBA - SEM IV – PROJECT FINANCE Q BANK
1. From the following data and information provided, find out the missing
values
Project X
IRR 15%
PI 1.064
NPV ?
Cost of Project ?
Pay back ?
Salvage value 0
Cost of capital ?
6
EX MBA - SEM IV – PROJECT FINANCE Q BANK
a. Company wants to Select the project based on RADR , given that risk
free return of 10% with risk premium adjustment of 2% for X and 8% for
Y
X Y
1 4,00,000 5,00,000
2 3,50,000 4,00,000
3 2,50,000 3,00,000
4 2,00,000 3,00,000
b. For the cash flows of the above example, if certainty equivalent co-
efficient is estimated as under, state which project is better off
X Y
1 0.90 0.80
2 0.80 0.60
3 0.60 0.60
4 0.50 0.50
7
EX MBA - SEM IV – PROJECT FINANCE Q BANK
Probability
4. From the following project details calculate the sensitivity of the following
factors independently and answer which variable is more sensitive?
a. Project cost
b. Annual cash flow
c. Cost of capital
Project cost is estimated to be Rs.12,000. The annual cash flow Rs.4500, life
of project 4 years, cost of capital 14% . IRR is 18%.
8
EX MBA - SEM IV – PROJECT FINANCE Q BANK
6. From the following information ascertain which project is more risky on the
basis of Standard Deviation
X Y
CF Prob CF Prob
7. Firm has determined the following expected rates of return in view the
degree of risks involved in the proposals
Low 24 %
Medium 32%
High 48%
X 44%
Y 30%
P 20%
Q 34%
Air coolers
Raincoats
A B C D E F
Return% 8 8 12 4 9 8
Risk 4 5 12 4 5 6
10
EX MBA - SEM IV – PROJECT FINANCE Q BANK
(S.D)
Profit before tax estimated to be 200000, tax rate 35%. Company requires
10% minimum rate of return from new machine. Should the new machine be
purchased?
12.Company is forced to choose between two projects A and B. both the projects
are designed differently but have identical capacity and can do exactly the
same job. Project A cost 1,50,000 and will have a life of 3 years. Project B
would cost 1,00,000 but will have a life of 2 years. It will require 40,000 pa
11
EX MBA - SEM IV – PROJECT FINANCE Q BANK
to run Project A and 60,000 pa to run Project B. ignore tax. Opportunity cost
is 10% . Suggest the best Project.
13.Dry Twigs and fresh limited is always discarding old items and introducing
new lines of products and is at present considering three alternative
promotion plans. Various combinations of prices and development
expenditure are involved under these plans. High medium and low forecast of
revenues under each plan have been formulated and their respective
probabilities occurrence have been estimated as under – Rs lacs
Initial investment 25 20 24
Life in years 8 8 8
Make detail analysis and suggest which plan is more profitable under NPV
method. Also state which plan is suitable if worst event happened.
12
EX MBA - SEM IV – PROJECT FINANCE Q BANK
0 -10,000
1 3,000
Inflation rate is expected at 7%. Firm’s opportunity
cost of 2 3,000 capital in nominal terms is 14%. Should
the project be 3 3,000 accepted? Justify
Capex for R&D would attract 100% tax write off at the end of the first year
itself. Gain arising from disposal of used assets would be tax free. Company
pays 50 % tax and its cost of capital is 12%.
Analyze the capital expenditure and advice the management by using NPV
method
13
EX MBA - SEM IV – PROJECT FINANCE Q BANK
Material 3 per unit, labour Rs.5 per unit and fixed expenses if manufactured
Rs.90,000 pa. Further to buy machine company take a loan which is to be
repaid in four equal installments of Rs.25,000 (ignore interest part on loan).
Machine repairs cost would be Rs.14000, Rs.10500, Rs.7000 and Rs.3,500
respectively for four years.
Consider 35 % tax rate and 14% required rate of return. Evaluate the
proposal under NPV.
17.A firm has investment proposal requiring cash outflow of Rs.35000. life of
the project is 2 years. The expected cash flows are given below –
There is probability of 0.4 to get CF Rs.20000 during year 1, and in that case
the expected CF of 10,000 or 15,000 or 20,000 with probability of
0.2,0.3,0.5 respectively.
What is the NPV if worst outcome is realized? What is the prob of such
NPV?
What is the NPV if Best outcome is realized? What is the prob of such
NPV?
14
EX MBA - SEM IV – PROJECT FINANCE Q BANK
Once the sales are established at certain volume in first year they will
continue at same volume in subsequent years. Selling price is 12 per unit and
variable cost is 8 per unit. Cash fixed cost amounting to Rs.20,000. Life of
project is 6 years at the end of which scrap value estimated at Rs.3000.
Company expects 10% rate for discounting CF. Calculate NPV, and also
state minimum volume of sales pa to justify the project. Ignore depreciation
and taxation.
19.There is 40% chance that a patient admitted to the hospital is suffering from
cancer. Doctor has to decide whether to operate or not. If the patient is
suffering from cancer and operation is performed, chance to recover is 70%
otherwise (if suffering from cancer but operation not done) it is 35%.
On the other hand if patient is not suffering from cancer and operation
performed, chance to recover is 20% otherwise it is 100%. Assuming death
and recovery are the only possible result, advice doctor whether to operate or
not.
20.An investment banker has a client, who has an option to invest in either real
estate, shares, corporate bonds or Govt. bonds. Investment is to be made for
one year. Yields and its chances are given as under –
a. Real estate – 25% chance of 10% decrease in value, 30% chance that
value will remain stable, 45% chance that value increase by 15%
c. Shares - 25% chance of 20% increase in value, 10% chance that value
will remain stable, 20% chance that value increase by 30%,40% chance
that value increase by 10%, and 5% chance of 5% decrease in value
15
EX MBA - SEM IV – PROJECT FINANCE Q BANK
22.Calculate Beta factor of security under consideration from the following data
1 20 22
2 22 20
3 25 18
4 21 16
5 18 20
6 2 8
7 17 4
8 19 5
9 3 6
10 20 11
24.You are analyzing beta for ABC computers and have divided the company
into its four SBU’s . following data reveals the market value of equity and its
beta factor
Software 50 2.00
25.From the following figures related to Beta limited, calculate ß and cost of
equity
3 17% 19% 8%
4 16% 18% 8%
17
EX MBA - SEM IV – PROJECT FINANCE Q BANK
18
EX MBA - SEM IV – PROJECT FINANCE Q BANK
LEASING OPTION –
1. ABC limited needs an asset for which following two options are under
consideration
Company provides depreciation on Straight line method and applicable tax rate is
25%. Suggest with proper working which option is better for the company
2. Firm can purchase an asset for Rs.2500 having life of 5 years, after which
the salvage value expected Rs.500. Depreciation is on SLM. Use of such
asset would increase the revenue by Rs.1500 pa and will raise operating cash
expenses by Rs.700 pa Tax rate is 50%. Cost of capital is 10%
3. XYZ limited needs an asset for which following two options are under
consideration
Company provides depreciation on Straight line method and applicable tax rate is
30%. Suggest with proper working which option is better for the company
19
EX MBA - SEM IV – PROJECT FINANCE Q BANK
Buy Computers –
Computers on lease –
Advice about debt financing or lease financing. Also state how much lease
rent can be made to have indifference between two options?
5. Mr Anand, a lessor, want to purchase an asset and give it on lease rent. Cost
of asset is 2500. Expected life is 4 years at the end of which it can be sold at
100. Cost of capital is 7% (after tax). Tax rate is 30%. Annual maintenance
cost is expected at Rs.500 (40% to be borne by lessor as per agreement).
Asset to be depreciate by SLM. Calculate minimum acceptable lease rent for
this agreement to be set by lessor.
20
EX MBA - SEM IV – PROJECT FINANCE Q BANK
Prel expenses 15
Company did not perform well and suffered losses during last few years. Board
of directors are of the opinion that company can be nursed back to healthy
business by proper financial restructuring, proposes following scheme -
c. Debenture holders agree to forego accrued interest, they also agree for new
coupon rate of 9%
d. Creditors agree to forego 25% of their claim, for the balance amount they
have agreed to convert their claim into equity shares of 25 each.
21
EX MBA - SEM IV – PROJECT FINANCE Q BANK
e. For making payment of bank loan, company issues 6 lac new equity shares
of 25 each. Existing shareholders agreed to subscribe new shares and make
payment immediately.
g. Provision to be made for bad debts for Rs.5 lacs, preliminary expenses to
write off
22
EX MBA - SEM IV – PROJECT FINANCE Q BANK
NETWORK ANALYSIS
1. Lift Irrigation project is undertaken with the following activities with the
respective duration in days
1 Site selection A 7
2 Digging well B 3
4 Procurement of pump D 7
5 Installation of pump E 3
6 Test run F 2
Determine logical sequence and draw network diagram, find out Total time
with critical activities
B A
C A
D C
E C
F B,D
G F
H E
23
EX MBA - SEM IV – PROJECT FINANCE Q BANK
I G,H
A -
B -
C A
D A
E A
F B,C
G D
H E,F,G
I H
24
EX MBA - SEM IV – PROJECT FINANCE Q BANK
A -
B -
C B
D A
E A
F D
G E
H D
I C,F
J H,G
K I
25
EX MBA - SEM IV – PROJECT FINANCE Q BANK
A -
B -
C A
D A
E B
F B
G C
H D
I E
J F
K G,H
L I,J
26
EX MBA - SEM IV – PROJECT FINANCE Q BANK
A -
B -
C -
D A
E C
F A
G B,D,E
H B,D,E
I C
J G,F
K G,F
L H,I,J
M I
7. From the Following details available for a particular project, Draw network
diagram and find out total duration with critical path
27
EX MBA - SEM IV – PROJECT FINANCE Q BANK
A - 8 10 18
B - 9 10 23
C - 5 7 9
D A 4 8 42
E C 5 6 37
F B,D,E 4 9 32
G A 8 8 14
H A 1 3 11
I G 9 10 35
J C 10 15 26
K J 10 14 30
L H,F,I,K 16 20 60
M J 5 9 19
N M 4 4 4
O G 8 9 28
P O 4 5 12
Q O 2 6 40
R Q 7 7 19
S M 10 13 46
T L,P,N 15 20 31
28
EX MBA - SEM IV – PROJECT FINANCE Q BANK
29