F4 Drainage (≈110m length) Update : 09/11/2020

Dimension (mm) Material BNB Contractor

Qty (Nos)

Total Qty
Width (/OD)

Height (/ID)

weight per
mtr(kg/m)
Thickness

Unit
No Type

Length
Material Unit Material Total Labor Unit Labor Total
cost (RM/m) cost (RM) cost (RM)

MAIN ENTRANCE
1 Box Culvert 800 100 1,450 1,000 pcs 16 477.00 7632

SIDE DRAINAGE
1 RC Block Drain 813 100 712 600 pcs 184 39.00 7176 L.S.
2 Bricks 110 75 225 pcs 31620 0.28 8854 (machinery & 24,128
3 BRC 10 2,200 6,000 pcs 22 215.00 4730 manpower)
4 Cement bags 574 16.5 9471
5 Putty Lime bags 287 2.40 689
6 Concrete G15 1,913 150 125,964 40 m3 40 141.00 5640

44,191 24,128

Total Cost 68,319