CONSULTANCY SERVICES FOR ENHANCEMENT OF DESALINATED WATER IMPORT AND STORAGE

PROJECT TITLE: CONTRACT NUMBER: CA/CPC/0488/CNSL


FACILITIES AT MAA
KNPC TR. No.: KNPC -GS-DWSF-T-0041 Dated 26.01.2022 Date: 27.01.2022
DOCUMENT TITLE: Work Breakdown Structure & Detailed Level 5 Schedule 0488-GS-1000-G E N-G-A4-0005
ACTION
S.No. DOC. REF. ITEM DESCRIPTION KNPC COMMENTS GS RESPONSE
CODE

1 Level 5 FEED Schedule 28 nos. of activities are dangling (open start). A Complied. Please refer the xer file.

2 Level 5 FEED Schedule 28 nos. of relationships have lags and 04 nos. of relationships have lead. N Lag / Leads are required to retain the network within the time frame.

The schedule contains 95 nos. of Finish-to-Finish relationships and 31 nos. Start-to- Start Most of the documents are inter dependent and FF realtions are
3 Level 5 FEED Schedule N
relationships. required to retain the network with in the time frame.

Milestone M01 Baseline Schedule, S - Curve, P.M. Procedure Completion has a Hard
4 Level 5 FEED Schedule A Constraint removed.
Constraint. Use of constraints shall be justified with reasons.

Although Activity Codes are highlighted in Excel Sheet, the same is not reflected in
5 Level 5 FEED Schedule A Complied. Please refer Project Activity code "Payment Milesone"
0488-GS-1000-G EN-G- Primavera Schedule.
A4-000S-Rev-B
Holidays are considered in the project schedule. Kindly refer Project
6 Level 5 FEED Schedule Holidays are not considered in the project calendar. A
calendar "488 CALENDAR".
Level 5 FEED Schedule
Preliminary design calculation for DM tanks is included under ISBL, whereas the data sheet
7 ISBL-Mechanical A Deliverables rearranged to appropriate levels
and preliminary TBE for DM tanks are included under OSBL. Consultant to clarify the same.
(Static/Rotatic)
Level 5 FEED Schedule Mechanical/ Technical Specification for DM package Unit shall be included as confirmed/
8 ISBL-Mechanical included by Consultant in Mechanical Design Basis. The same was commented in the FEED A Deliverables rearranged to appropriate levels
(Static/Rotatic) Engineering deliverables list submitted by Consultant.
Level 5 FEED Schedule Mechanical Datasheet for Desalinated Water Pit Pumps is included under ISBL, whereas
9 ISBL-Mechanical the preliminary TBE and Mechanical Datasheet for Desalinated Water Pit Pumps is A Deliverables rearranged to appropriate levels
(Static/Rotatic) included under OSBL. Consultant to clarify the same.
It is observed that most documents will be submitted on one specific date, Consultant to
We have ensured that not more than 10 deliverables will be issued on
10 Level 5 FEED Schedule check and distribute documents submission within project time schedule. Considering A
same date from each discipline.
sequence of the document.
Instrument Design Basis, PLC specification and Site survey has been submitted and
Level 5 FEED Schedule This is a baseline schedule submitted for approval. Actuals will be
11 submission dates are not complied with Level 5 FEED Schedule. Consultant to check and N
Instrumentation updated and submitted along with the monthly report.
update the dates accordingly.
Prior to submission of any document to Company, Consultant shall ensure that all
comments provided by Company in other related documents are incorporated / taken care
12 General A Agreed
in the document which is to be submitted (as applicable), by which unnecessary revision of
documents shall be avoided.
WBS shall be updated after finalizing project Deliverable list and incorporating Company's
13 General A Agreed
0488-GS-1000-G EN-G- comments in the documents.
A4-000S-Rev-B
As 11th July 2022 is public holiday, P6 calculated 12th July as
Consultant shall refer to Letter no: KNPC-GS-DWSF-L-0004 for Contractual Completion date completion date. However we have modified the calendar 488 to
14 Level 5 FEED Schedule A
(11-Jul-2022) and revise schedule accordingly. match the contractual requirement of 11th July 2022 as completion
date.

Consultant shall ensure milestones are in line with the Schedule Milestone periods as per
15 Level 5 FEED Schedule A Complied
Article -4 of Appendix-B.

Consultant shall ensure all activities are resource loaded and provide a project specific
16 Level 5 FEED Schedule A Complied. Kindly refer the xer file.
resource-ID.
Page 1 of 2