PROJECT:B+G+7 OFFICE BULDING

CONTRACTOR:B.G.M CONSTRUCTION
CLIENT:N/S/L/S/CITY MAT SLAB BAR SCHEDULE
LOCATION:A/A N/S/L/S/C WEREDA 03
CONSULTANT: A/A CON/BUREAU

No. of No. of
Description Shape Dia. Length bar Memb Ø6 Ø8 Ø10
Ground floor slab

ON AXIS A to B b/n 3,4,5,6,7,8 &9


on longer side bln axis Ato B 8 5.70 20 6 684

on shorter side bln axis 3,4,5,6,7,8 &9 8 3.70 13 6 288.6


ON AXIS B to C b/n 1,2,3,4,5,6,7,8& 9
on longer side bln axis 1,2,3,4,5,6,7,8& 9 8 3.70 13 8 384.8

on shorter side bln axis B to C 8 2.83 10 8 226.4


ON AXIS C toD b/n 1,2,3,4,5,6 & 7
on longer side bln axis C to D 8 5.7 20 6 684

on shorter side bln axis 1,2,3,4,5,6 & 7 8 3.7 13 6 288.6

Total length(m)
2556.4
Weight per meter(Kg/m)
0.395
Total Weight(Kg)
1009.778

CONTRACTOR -------------- SUPERVISOR -----------------


Project :_____ G+2 CLASS ROOM CONSTRUCTION PROJECT____________________________________
Client :___Oromia Education Bureau______________________________________________________________
Consultant :___Engineering Coorporation Of Oromia________________________________________________
Month:__November__________________ Year________2020 G.C_________________

No.of No.of
Description Shape Dia. Length bar Mem
SECOND FLOOR SUSPENDED BEAMS
ON AXIS A
Top bar 16 7.305 3 1
>> 16 12.000 2 1
>> 16 6.805 2 1
Negative bar 16 1.955 1 1
>> 16 2.660 1 3
>> 16 2.660 2 2
>> 16 1.955 2 1
Bottom bar 14 8.425 3 2
>> 14 8.500 3 1
STIRRUP 8 1.200 336 1
ON AXIS B &C
Top bar 16 6.805 3 2
>> 16 12 3 2
>> 16 9 3 2
>> 16 6.805 3 2
Negative bar 16 1.955 1 2
>> 16 2.660 1 14
>> 16 1.955 1 2
Bottom bar 14 8.425 3 4
>> 14 8.500 3 4
Stirrup 8 1.2 479 4
ON AXIS D
Top bar 16 7.305 2 1
>> 16 12 2 1
>> 16 6.805 2 1
Negative bar 16 1.955 1 1
>> 16 2.660 2 5
>> 16 1.955 2 1
Bottom bar 14 8.425 3 2
>> 14 8.500 3 1
STIRRUP 8 1.2 330 1
ON AXIS 1&9 b /n C&D
Top bar 16 7.510 3 2
Negative bar 16 2.555 2 2
>> 16 2.955 2 2
Bottom bar 14 6.750 4 2
STIRRUP 8 1.200 158 2
ON AXIS 1&9 b /n B&C at stair landing
beam
Top bar 16 4.340 3 2
Bottom bar 14 4.340 3 2
STIRRUP 8 1.200 24 5
ON AXIS 2&8 b/n B, C & D
Top bar 16 10.740 3 2
Negative bar 20 3.100 2 2
>> 20 2.955 2 2
Bottom bar 16 9.980 4 2
STIRRUP 8 1.200 153 2
ON AXIS 4, 5 &6 b/n A,B,C & D
Top bar 16 8.77 3 3
>> 16 8.77 3 3
Negative bar 20 2.955 2 3
>> 20 3.100 2 6
>> 20 2.955 2 3
Bottom bar 16 9.955 4 3
>> 16 6.825 4 3
Stirrup 8 1.2 287 3
ON AXIS 7 b/n A,B,C & D
Top bar 20 8.77 3 1
>> 20 8.77 3 1
Negative bar 16 2.955 2 1
>> 16 3.100 2 2
>> 16 2.955 2 1
Bottom bar 16 9.955 4 1
>> 16 6.825 4 1
STIRRUP 8 1.2 278 1
ON AXIS 3 b/n A,B,C & D
Top bar 20 8.77 3 1
>> 20 8.77 3 1
Negative bar 16 2.955 2 1
>> 16 3.100 2 2
>> 16 2.955 2 1
Bottom bar 16 9.955 4 1
>> 16 6.825 4 1
STIRRUP 8 1.2 244 1
Total length(m)
Weight per meter(Kg/m)
Total Weight(Kg)
____________________________________________________________
______________________________________
________________________________________________
C_________________

Ø6 Ø8 Ø12 Ø14 Ø16 Ø20

21.915
24
13.61
1.955
7.98
10.64
3.91
50.55
25.50
403.20

40.83
72
54
40.83
3.91
37.24
3.91
101.10
102.00
2299.20

14.61
24
13.61

1.955
26.6
3.91
50.55
25.50

396.00
45.06
10.22
11.82
54.00
379.20

26.04
26.04
144.00

64.44
12.4
11.82
79.84
367.20

78.93
78.93
17.73
37.2
17.73
119.46
81.9
1033.20

26.31
26.31
5.91
12.4
5.91
39.82
27.3
333.6
26.31
26.31
5.91
12.4
5.91
39.82
27.3
292.8 292.8
5648.40 435.24 1493.535 202.12
0.395 1.21 1.58 2.47
2231.118 526.6404 2359.785 499.2364
Project :_____ G+2 CLASS ROOM CONSTRUCTION PROJECT____________________________________
Client :___Oromia Education Bureau______________________________________________________________
Consultant :___Engineering Coorporation Of Oromia________________________________________________
Month:__November__________________ Year________2020 G.C_________________

Description Shape Dia. Length No.of bar


FIRST FLOOR SUSPENDED BEAMS
ON AXIS A
Top bar 16 7.305 3
>> 16 12.000 2
>> 16 6.805 2
Negative bar 16 1.955 1
>> 16 2.660 1
>> 16 2.660 2
>> 16 1.955 2
Bottom bar 14 8.425 3
>> 14 8.500 3
STIRRUP 8 1.200 336
ON AXIS B &C
Top bar 16 6.805 3
>> 16 12 3
>> 16 9 3
>> 16 6.805 3
Negative bar 16 1.955 1
>> 16 2.660 1
>> 16 1.955 1
Bottom bar 14 8.425 3
>> 14 8.500 3
Stirrup 8 1.2 479
ON AXIS D
Top bar 16 7.305 2
>> 16 12 2
>> 16 6.805 2
Negative bar 16 1.955 1
>> 16 2.660 2
>> 16 1.955 2
Bottom bar 14 8.425 3
>> 14 8.500 3
STIRRUP 8 1.2 330
ON AXIS 1&9 b /n C&D
Top bar 16 7.510 3
Negative bar 16 2.555 2
>> 16 2.955 2
Bottom bar 14 6.750 4
STIRRUP 8 1.2 158
ON AXIS 1&9 b /n B&C at stair landing
beam
Top bar 16 4.340 3
Bottom bar 14 4.340 3
STIRRUP 8 1.2 24
ON AXIS 2&8 b/n B, C & D
Top bar 16 10.740 3
Negative bar 20 3.100 2
>> 20 2.955 2
Bottom bar 16 9.980 4
STIRRUP 8 1.2 153
ON AXIS 4, 5 &6 b/n A,B,C & D
Top bar 16 8.77 3
>> 16 8.77 3
Negative bar 20 2.955 2
>> 20 3.100 2
>> 20 2.955 2
Bottom bar 16 9.955 4
>> 16 6.825 4
Stirrup 8 1.2 287
ON AXIS 7 b/n A,B,C & D
Top bar 20 8.77 3
>> 20 8.77 3
Negative bar 16 2.955 2
>> 16 3.100 2
>> 16 2.955 2
Bottom bar 16 9.955 4
>> 16 6.825 4
STIRRUP 8 1.2 278
ON AXIS 3 b/n A,B,C & D
Top bar 20 8.77 3
>> 20 8.77 3
Negative bar 16 2.955 2
>> 16 3.100 2
>> 16 2.955 2
Bottom bar 16 9.955 4
>> 16 6.825 4
STIRRUP 8 1.2 244
Total length(m)
Weight per meter(Kg/m)
Total Weight(Kg)
_____________________________________________________________________
________________________________________________
_________________________________________________________
____2020 G.C_________________

No.of Mem Ø6 Ø8 Ø12 Ø14 Ø16 Ø20

1 21.915
1 24
1 13.61
1 1.955
3 7.98
2 10.64
1 3.91
2 50.55
1 25.50
1 403.20

2 40.83
2 72
2 54
2 40.83
2 3.91
14 37.24
2 3.91
4 101.10
4 102.00
2 1149.60

1 14.61
1 24
1 13.61
1 1.955
5 26.6
1 3.91
2 50.55
1 25.50
1 396.00
2 45.06
2 10.22
2 11.82
2 54.00
2 379.20

2 26.04
2 26.04
2 57.60

2 64.44
2 12.4
2 11.82
2 79.84
2 367.20

3 78.93
3 78.93
3 17.73
6 37.2
3 17.73
3 119.46
3 81.9
3 1033.20

1 26.31
1 26.31
1 5.91
2 12.4
1 5.91
1 39.82
1 27.3
1 333.6

1 26.31
1 26.31
1 5.91
2 12.4
1 5.91
1 39.82
1 27.3
1 292.8 292.8
4412.40 435.24 1493.535 202.12
er meter(Kg/m) 0.395 1.21 1.58 2.47
1742.898 526.6404 2359.785 499.2364
PROJECT: B+G+7 OFFICE BULDING CONTRACTOR:B.G.M CONSTRUCTION
CLIENT : N/S/L/S/CITY MAT BEAM BAR SCHEDULE
LOCATION:A/A N/S/L/S/C WEREDA 03
CONSULTANT : A/A CON/BUREAU

Description Shape Dia. Length No.of bar No.of Mem Ø6 Ø8 Ø10 Ø12 Ø14 Ø16
GROUND FLOOR BEAMS
ON AXIS A
Top bar 14 7.275 3 1 21.83
>> 14 12.000 3 1 36.00
>> 14 6.775 3 1 20.33
Bottom bar 14 8.425 2 2 33.70
>> 14 8.500 2 1 17.00
STIRRUP 8 1.300 121 1 157.30
ON AXIS B &C
Top bar 14 6.775 2 2 27.10
>> 14 12.000 2 2 48.00
>> 14 9.000 2 2 36.00
>> 14 6.775 2 2 27.10
Bottom bar 14 8.425 2 4 67.40
>> 14 8.500 2 4 68.00
Stirrup 8 1.300 161 2 418.60

CONTRACTOR ---------------
PROJECT: B+G+7 OFFICE BULDING CONTRACTOR:B.G.M CONSTRUCTION
CLIENT : N/S/L/S/CITY MAT BEAM BAR SCHEDULE
LOCATION:A/A N/S/L/S/C WEREDA 03
CONSULTANT : A/A CON/BUREAU

Description Shape Dia. Length No.of bar No.of Mem Ø6 Ø8 Ø10 Ø12 Ø14 Ø16
ON AXIS D
Top bar 14 6.775 3 1 20.33
>> 14 12.000 3 1 36.00
>> 14 7.275 3 1 21.83
Bottom bar 14 8.425 2 2 33.70
>> 14 8.500 2 1 17.00
STIRRUP 8 1.300 121 1 157.30
ON AXIS 1&2
Top bar 14 10.580 2 2 42.32
Negative bar 14 3.100 2 2 12.40
>> 14 2.925 2 2 11.70
Bottom bar 14 9.880 3 2 59.28
STIRRUP 8 1.300 47 2 122.20
ON AXIS 3,4,5,6&7
Top bar 14 8.740 3 5 131.10
>> 14 8.740 3 5 131.10
Bottom bar 14 10.055 3 5 150.83
>> 14 6.825 3 5 102.38

CONTRACTOR ---------------
PROJECT: B+G+7 OFFICE BULDING CONTRACTOR:B.G.M CONSTRUCTION
CLIENT : N/S/L/S/CITY MAT BEAM BAR SCHEDULE
LOCATION:A/A N/S/L/S/C WEREDA 03
CONSULTANT : A/A CON/BUREAU

Description Shape Dia. Length No.of bar No.of Mem Ø6 Ø8 Ø10 Ø12 Ø14 Ø16
STIRRUP 8 1.300 78 5 507.00
ON AXIS 8&9
Top bar 14 10.580 2 2 42.32
Negative bar 14 2.925 2 2 11.70
>> 14 3.100 2 2 12.40
Bottom bar 14 9.880 3 2 59.28
STIRRUP 8 1.300 47 2 122.20

CONTRACTOR ---------------
PROJECT: B+G+7 OFFICE BULDING CONTRACTOR: B.G.M CONSTRUCTION
CLIENT: N/S/L/S/CITY SHEARWALL BAR SCHEDULE
LOCATION: A/A N/S/L/S/C WEREDA 03
CONSULTANT: A/A CONSTRUCTION BUREAU
Month:__November__________________ Year________2020 G.C_________________

No.of No.of no of
Description Shape Dia. Length Bar Mem footing Ø6 Ø8 Ø10 Ø12 Ø14

FOOTING

F1 14 3.2 17 2 10 1088

F2 12 2.6 13 2 14 946.4

F3 12 2 30 7 8 3360
No.of No.of no of
COLUMN Shape Dia. Length Bar Mem column

C1 16 11.9 32 1 18

14 3.475 8 1 18 500.4

C2 16 11.42 32 1 4

14 3.475 8 1 4 111.2

C3 16 7.53 16 1 6

14 7.365 16 1 6 707.04

C4 16 11.42 28 1 4

14 3.475 8 1 4 111.2

Stirrup

C1 8 1.52 66 1 18 1805.76

8 1.14 26 1 18 533.52

C2 8 1.52 64 1 4 389.12

8 1.14 9 1 4 41.04

C3 8 1.52 62 1 6 565.44

C4 8 1.52 64 1 4 389.12

Total length(m) 3724 4306.4 2517.84

Weight per meter(Kg/m) 0.395 0.617 0.888 1.21

Total Weight(Kg) 1470.98 3824.08 3046.59

CONTRACTOR: -------------- SUPERVISOR -----------------


PROJECT: B+G+7 OFFICE BULDING CONTRACTOR: B.G.M CONSTRUCTION
CLIENT: N/S/L/S/CITY SHEARWALL BAR SCHEDULE
LOCATION: A/A N/S/L/S/C WEREDA 03
CONSULTANT: A/A CONSTRUCTION BUREAU

Ø16 Ø20 Ø24

6854.40

1461.76

722.88

1279.04

10318.08

1.58 2.47 3.55

16302.57

CONTRACTOR: -------------- SUPERVISOR -----------------


Project: B+G+7 OFFICE BULDING CONTRACTOR: B.G.M CONSTRUCTION
CLIENT: N/S/L/S/CITY TAKEOFF SHEET
LOCATION: A/A N/S/L/S/C WEREDA 03
CONSULTANT: A/A CONSTRUCTION BUREAU

Item Time Dimen Item Time Dimensi


Qty Description Qty Description
No sing sion No sing on
1 Excavation & Earth work 1.14 Cartaway
1.1 Site clearing 1081.86 item no 1.1 site clearing
1 43.9 L=7*5.5+2*1.2+2*1.5=43.9m 0.2
27.4 W=4*5.5+2*1.2+2*1.5=27.4m 216.37 Site clearing
1202.86 m² 3927.15 Bulk excavation

Deduction 4143.52 Total cartaway


4 5.5 3 Concrete Work
5.5 3.1 Lean Concrete
121.00 m² 1 40.9 L=7*5.5+1.2*2=40.9
24.4 W=4*5.5+1.2*2=24.4
1081.86 m² Net Site clearing 997.96 m²
Deduction
1.2 Bulk Excavation 4 5.5
1 43.9 L=7*5.5+2*1.2+2*1.5=43.9m 5.5
27.4 W=4*5.5+2*1.2+2*1.5=27.4m 121.00 m²
1.5 876.96 m² Net lean concrete
1804.29 m³ 3.3 Basement mat slab concrete
1 40.9 L=7*5.5+2*1.2=40.9m
Deduction 24.4 W=4*5.5+2*1.2=24.4m
4 5.5 0.5 D=0.50m
5.5 498.98 m³
1.5 2 3.1 Lift shaft footing concret
181.50 m³ 2.30
1622.79 m³ Net bulk Excavation 0.5
1.3 Ditto but 150<x<300 7.13 m³
1 43.9 L=7*5.5+2*1.2+2*1.5=43.9m Deduction
27.4 W=4*5.5+2*1.2+2*1.5=27.4m 4 5.5
1.5 5.5
1804.29 m³ 0.5
Deduction 60.50 m³
4 5.5 Deduction half of beam
5.5 216.86
1.5 2
181.50 m³ 108.43 m³
1622.79 m³ Net bulk Excavation 337.18 m³
1.4 Ditto but 300<x<450 3.4 Basement floor Column concrete
1 43.9 L=7*5.5+2*1.2+2*1.5=43.9m 10 2.6 C1
27.4 W=4*5.5+2*1.2+2*1.5=27.4m 0.7
0.63 0.7
757.80 m³ 12.74 m³
Deduction C2
4 5.5 10 2.6
5.5 0.7
0.63 0.7
76.23 m³ 12.74 m³
681.57 m³ Net bulk Excavation C3
Back Fill 2 2.6
Under mat slab 0.7
2 28.2 L=5*5.5+2*0.35=28.2 0.7
5.85 W=5.5+0.35=5.85 2.55 m³
0.4 C4
131.98 m³ 8 2.6
2 39.2 L=7*5.5+2*0.35=39.2 0.7
5.85 W=5.5+0.35=5.85 0.7
0.4 10.19 m³
183.46 m³ C5
2 29.9 L=5*5.5+2*1.2=29.9 4 2.6
1.2 W=1.2 0.7
0.4 0.7
28.70 m³ 5.10 m³
2 11.7 L=2*5.5+2*0.35=11.7 43.32 m³
1.2 W=1.2
0.4
11.23 m³
8 6.7 L=5.5+1.2=6.7
CONTRACTOR ------------ SUPERVISOR -------------------
Project: B+G+7 OFFICE BULDING CONTRACTOR: B.G.M CONSTRUCTION
CLIENT: N/S/L/S/CITY TAKEOFF SHEET
LOCATION: A/A N/S/L/S/C WEREDA 03
CONSULTANT: A/A CONSTRUCTION BUREAU
Item Time Dimen Item Time Dimensi
Qty Description Qty Description
No sing sion No sing on
1.2 W=1.2
25.73 m³
381.10 m³ (Net back fill under slab)

CONTRACTOR ------------ SUPERVISOR -------------------


Project: B+G+7 OFFICE BULDING CONTRACTOR: B.G.M CONSTRUCTION
CLIENT: N/S/L/S/CITY TAKEOFF SHEET
LOCATION: A/A N/S/L/S/C WEREDA 03
CONSULTANT: A/A CONSTRUCTION BUREAU
Item Time Dimen Item Time Dimensi
Qty Description Qty Description
No sing sion No sing on
Concrete 3.9 In shear wall (basment)
3.5 In Basement beam 13 4.8
Mat beam on axis B,C&D 0.25
3 39.2 2.6
0.7 40.56 m³
1 7 4.8
82.32 m³ 0.25
Mat beam on Axis A&E 2
2 28.2 16.80 m³
0.7
1 57.36 m³ net concrete for basment
39.48 m³ FORMWORK
Mat beam on axis1&8 3.1 To basement mat slab
2 11.7 140.2
0.7 0.5
1 70.10 m²
16.38 m³ To Lift shaft footing pad
Mat beam on axis 2,3,4,5,6&7 2 3.1
6 22.7 2 0.5
0.7 6.20 m²
1 2 2.3
95.34 m³ 2 0.5
4.60 m²
233.52 m³ 80.90 m²
Deduction 3.11 To basement column
34 1 34 2.6 L=2.6m
0.7 2.8 w=4*0.7=2.8m
0.7 Each column concret 247.52 m²
16.66 3.12 To shear wall( lift house)
216.86 m³ Net Reinfor concrete
3.8 4 3.1 In shear wall(25cm thick) 4 3.1
0.25 2 5
5 124.00 m²
15.50 m³
4 2.3
0.25 4 2.3
5 2 5
11.50 m³ 92.00 m²
Inclined part around lift
Longer part
2 4.33 L=0.5*2+0.475+2.6+0.25=4.33m 2 0.25 Side of door
2 0.375 A=1/2(0.5*1.5m)=0.375m 2 2.1
6.50 m³ 2.10 m²
Shorter part
2 3.53 L=0.5*2+0.475+1.8+0.25=3.53m
2 0.375 A=1/2(0.5*1.5m)=0.375m 2 1 Top of door
5.30 m³ 0.25
0.50 m²
2 1.5 L=0.5*2+0.475+2.6+0.25=4.33m
0.475 218.60 m²
4.33 Deduction of door
6.17 m³ 2 1
2 1.5 L=0.5*2+0.475+1.8+0.25=3.53m 2.1
0.475 4.20 m²
3.53
5.03 m³ 214.40 m²
Deduction of door
2 1
0.25
2.1
1.05 m³
48.94 m³ net lift concrete

CONTRACTOR ------------ SUPERVISOR -------------------


Project: B+G+7 OFFICE BULDING CONTRACTOR: B.G.M CONSTRUCTION
CLIENT: N/S/L/S/CITY TAKEOFF SHEET
LOCATION: A/A N/S/L/S/C WEREDA 03
CONSULTANT: A/A CONSTRUCTION BUREAU
Item Time Dimen Item Time Dimensi
Qty Description Qty Description
No sing sion No sing on
Formwork for basement shear wall 1.110 Ground floor beam form work
7 4.8 Intermidiate beam
2 2 24 5.25 L=5.5-0.25=5.25m
134.40 m² 0.75 D=0.25+0.25+0.25=0.75m
13 4.8 94.500 m2
2 2.6 Intermidiate beam
324.48 m² 26 5.25 L=5.5-0.25=5.25m
458.88 m² 0.75 D=0.25+0.25+0.25=0.75m
673.28 m² For both Lift&R.w 102.375 m2
3.13 To basement beam Outer side sponda
L=(5.5*7+1.6*2)*2+(3+0.7+5.5*4)*2=134.8
4 4.8 1 134.8 m
24 1 0.4 D=0.4m
460.80 m² 53.920 m2
1 123.8 Internal part of outer side beam
1 20 5.25 L=5.5-0.25=5.25m
123.80 m² 0.5 D=0.25+0.25m=0.5m
584.60 m² 52.500
Formwork on axis A'-A b/n axis 2-7
3.15 To stair case &Landings 6 2.75
Basement to ground floor 0.75 D=0.25+0.25+0.25=0.75m
landing soffit 12.375 m2
5.25
1.815 315.670 m2
9.53 m² 1.170 Ground floor slab formwork
5.25 L=5.5-0.25=5.25m On axis A-E &1-8
0.81 W=1.06-0.25=0.81m 24 5.25 L=5.5-0.25=5.25m
4.25 m² 5.25 W=5.5-0.25=5.25m
Stair case soffit
L=(3²+1.65²)½ = 3.424m (by 661.50 m2
2 3.42 pythagorean theo..) On axis A'-A &2-7
1.875 5 5.25
12.83 m² 2.75
Steps 72.19 m2
10 1.875 For cantilever b/n B-D
2 0.165 4 5.25
6.19 m² 1.6
side sponda for landing 33.60 m2
2 1.815 Cantilever b/n axis 1-2&7-8
0.165 4 5.25
0.60 m² 1.8
2 0.81 W=1.06-0.25=0.81m 37.80 m2
0.165
0.27 m² 805.09 m2
1.5
0.165
0.25 m²
side sponda = 3.424m (by
L=(3²+1.65²)½
2 3.42 pythagorean theo..)
2 0.33
4.51 m²
Landing beam formwork
1 5.25 L=5.5-0.25=5.25m
2 1.05 W=0.4+0.4+0.25=1.05m
11.03
49.45 m²

CONTRACTOR ------------ SUPERVISOR -------------------


PROJECT:- B+G+7 OFFICE BULDING
CLIENT :- N/S/L/S/CITY
CONSULTANT:- A/A CONSTRUCTION BUREAU
CONTRACTOR:- B.G.M CONSTRUCTION
Month:__November__________________ Year________2020 G.C_________________
LOCATION:- A/A N/S/L/S/C WEREDA 03

Executed
Contract previous

Item Contract Conract


No.
Discription Unit
qty
Unit Price
Amount Previous Current To date

Qty Amount Qty Amount Qty Amount

A-SUB STRUCTURE
1 EXCAVATION & EARTH WORK - -

Clear and remove top soil to an average depth


1.1 M2 1,011.60 5.00 5,058.00 1,081.86 5,409.30 1,081.86 5,409.30
of 20cm.

Bulk excavation over the site to reduce level


1.2 M3 1,125.50 350.00 393,925.00 1,622.79 567,976.50 1,622.79 567,976.50
adepth not exceeding 150cm

1.3 Ditto but 150<x<300cm 1,125.50 350.00 393,925.00 1,622.79 567,976.50 1,622.79 567,976.50

1.4 Ditto but 300<x<450cm M3 1,125.50 80.00 90,040.00 681.57 54,525.74 681.57 54,525.74

1.5 Ditto but for soft rock excavation M3 225.10 0.25 56.28 - - -

1.6 Ditto but for hard rock excavation M3 337.70 0.25 84.43 - - -
Excavation for foundation trench excavation
1.7 in ordinary soil to adepth of 100cm from M3 2,705.10 0.25 676.28 - - -
reduced ground level.
Excavation for isolated footing in ordinary
1.8 soil to depth not exceeding 150cm starting 654.50 350.00 229,075.00 - - -
from reduced ground level

1.9 Ditto but for soft rock excavation 130.90 0.25 32.73 - - -

Ditto but for hard rock excavation 196.40 0.25 49.10 - - -


1.1

CONTRACTOR----------------- SUPERVISOR----------------------
PROJECT:- B+G+7 OFFICE BULDING
CLIENT :- N/S/L/S/CITY
CONSULTANT:- A/A CONSTRUCTION BUREAU
CONTRACTOR:- B.G.M CONSTRUCTION
Month:__November__________________ Year________2020 G.C_________________
LOCATION:- A/A N/S/L/S/C WEREDA 03
Back fill around trench foundation, footing
with selected soil from out site well compacted
1.11 761.10 80.00 60,888.00 - - -
,rolled & compressed in layer not exceeding
20cm.

Back fill under mat slab with sellected soil


from out side well compacted ,rolled and - 250.00 - 381.10 95,274.00 381.10 95,274.00
compressed in layer not exceeding 20cm.

Back fill under hard core with sellected soil


1.12 from out side well compacted ,rolled and M3 600.30 250.00 150,075.00 - - -
compressed in layer not exceeding 20cm.

Back fill around retaining wall with selelected


granular material (sub grade CBR
>55%,PI<12%,MPD>95%). The filling shall
1.13 M3 716.90 250.00 179,225.00 - - -
be performed in layers of 200 mm with
watering and consolidating each layer properly
with 5-10 ton vibrating roller .

Cart away the excess excavated material to an


1.14 appropriate site not exceeding 20 kms from the M3 6,938.50 20.00 138,770.00 4,143.52 82,870.48 4,143.52 82,870.48
site
25cm,thick basaltic stone or equivalent hard
1.15 core well rolled ,consolidated and blinded with M3 750.40 100.00 75,040.00 - - -
crushed stone .

TOTAL CARRIED TO SUMMARY 1,716,919.80 1,374,032.52 - 1,374,032.52


2 MASONRY WORK - - -
50cm thick hard trachytic roghly dressed
2.1 M3
164.90 1,550.00 255,595.00 - - -
retaining stone masonry mix ratio ( 1:3 )
2.2 Diito but above N.G.L M3 49.50 12.00 594.00 - - -

TOTAL CARRIED TO SUMMARY 256,189.00 - - -

3 CONCRETE WORK - - -
5cm lean concrete quality C-5 with minimum
- - - -
cement content of 150kg/m³, of concrete :

3.1 Footings (Mat slab) M2 527.10 15.00 7,906.50 876.96 13,154.40 876.96 13,154.40

CONTRACTOR----------------- SUPERVISOR----------------------
PROJECT:- B+G+7 OFFICE BULDING
CLIENT :- N/S/L/S/CITY
CONSULTANT:- A/A CONSTRUCTION BUREAU
CONTRACTOR:- B.G.M CONSTRUCTION
Month:__November__________________ Year________2020 G.C_________________
LOCATION:- A/A N/S/L/S/C WEREDA 03
3.2 Masonry M2 125.60 15.00 1,884.00 - - -

CONTRACTOR----------------- SUPERVISOR----------------------
PROJECT:- B+G+7 OFFICE BULDING
CLIENT :- N/S/L/S/CITY
CONSULTANT:- A/A CONSTRUCTION BUREAU
CONTRACTOR:- B.G.M CONSTRUCTION
Month:__November__________________ Year________2020 G.C_________________
LOCATION:- A/A N/S/L/S/C WEREDA 03
Reinforced concrete quality C-25,360 kg of
cement/m3 filled in to form work and vibrated
- - - -
around reinforcement (Formwork and
reinforcement measured separately)
3.3 In footings (mat slab) M3 335.10 2,200.00 737,220.00 337.18 741,796.00 337.18 741,796.00
3.4 In foundation columns M3 52.90 4,200.00 222,180.00 43.32 181,927.20 43.32 181,927.20
3.5 In basement beams M3 90.90 4,200.00 381,780.00 216.86 910,812.00 216.86 910,812.00
3.6 In 13cm thick basement floor Rc slab M3 750.40 15.00 11,256.00 - - -
3.7 In stair case and landing M3 5.20 5,200.00 27,040.00 - - -
3.8 In Shear wall (25cm thick) M3 14.50 5,200.00 75,400.00 48.94 254,490.60 48.94 254,490.60
3.9 In shear wall for basement(25cm thick) M3 225.30 220.00 49,566.00 57.36 12,619.20 57.36 12,619.20
Provide cut and fix in position sawn zigiba
- - - -
wood or equivalent formwork.
3.1 In footings (mat slab) M2 398.40 150.00 59,760.00 80.90 12,135.00 80.90 12,135.00
3.11 To foundation columns M2 302.40 150.00 45,360.00 247.52 37,128.00 247.52 37,128.00
3.12 To Shear wall M2
1,367.90 0.25 341.98 673.28 168.32 673.28 168.32
3.13 To basement beams M2
454.30 450.00 204,435.00 584.60 263,070.00 584.60 263,070.00
3.14 To 13cm thick basement floor Rc slab M2
1,500.70 0.15 225.11 - - -
3.15 To stair case and landing M2 30.50 750.00 22,875.00 49.45 37,085.18 49.45 37,085.18
1.11 To ground floor beam M2 70.40 450.00 31,680.00 315.67 142,051.50 315.67 142,051.50
1.17 To ground floor slab M2 675.68 100.00 67,568.00 805.09 80,508.75 805.09 80,508.75
Reinforcment steel bar according to the
structural drawing. price include cutting, bend, - - - -
placing in position
3.16 Dia 8 mm deformed bar KG 3,843.90 46.00 176,819.40 #REF! #REF! #REF! #REF!
3.17    Dia 10 mm deformed bar KG 1,777.00 35.00 62,195.00 - - - -
3.18    Dia 12 mm deformed bar KG 237.80 225.00 53,505.00 #REF! #REF! #REF! #REF!
3.19     Dia 14 mm deformed bar KG 3,323.20 32.00 106,342.40 #REF! #REF! #REF! #REF!
3.2 Dia 16 mm deformed bar KG - 55.03 - #REF! #REF! #REF! #REF!
3.21   Dia 20 mm deformed bar KG 3,846.40 0.15 576.96 #REF! #REF! #REF! #REF!
3.22   Dia 24 mm deformed bar KG 27,826.10 32.00 890,435.20 Err:509 Err:509 Err:509 Err:509
TOTAL CARRIED TO SUMMARY 3,236,351.54 #REF! #REF!

CONTRACTOR----------------- SUPERVISOR----------------------
PROJECT:- B+G+7 OFFICE BULDING
CLIENT :- N/S/L/S/CITY
CONSULTANT:- A/A CONSTRUCTION BUREAU
CONTRACTOR:-B.G.M CONSTRUCTION
LOCATION:-A/A N/S/L/S/C WEREDA 03

SUMMERY FOR SECOND PAYMENT


Contract Amount Executed Amount

Previous Current To date

SUB STRUCTURE
1
EXCAVATION 1,716,919.80 1,374,032.52 1,374,032.52
2
MASONRY WORK 256,189.00 -
3
CONCRETE WORK 3,236,351.54 #REF! #REF!
4 VARATION( SHORING
WORK ORDER) 1,241,702.08 1,183,133.30 1,183,133.30

SUB TOTAL 6,451,162.42 1,183,133.30 #REF! #REF!

CONTRACTOR------------------------ SUPERVISOR-----------------------
PROJECT:- B+G+7 OFFICE BULDING
CLIENT :- N/S/L/S/CITY
CONSULTANT:- A/A CONSTRUCTION BUREAU
CONTRACTOR:-B.G.M CONSTRUCTION
LOCATION:-A/A N/S/L/S/C WEREDA 03
GRAND SUMMARY
Contract Amount Executed Amount

Contract Amount Previous Current To date

A) SUB STRUCTURE 5,073,993.34 #REF! #REF!

B) SUPER STRUCTURE 37,294,625.89 - - -

VARATION( SHORING WORK


ORDER) 1,241,702.08 1,183,133.30 1,183,133.30

TOTAL 43,610,321.31 1,183,133.30 #REF! #REF!

VAT 15% 6,541,548.20 177,470.00 #REF! #REF!

TOTAL SUM WITH VAT 50,151,869.51 1,360,603.30 #REF! #REF!

CONTRACTOR ------------------- SUPERVISOR----------------------