PROPOSED REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES FOR MALL OFFICE,

CUSTOMER SURAU & MALL TENANT AT AEON ALPHA ANGLE, WANGSA MAJU KL
RE : REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES
Our Ref. : JTE / MT / 443 / 21 Date : 29 November 2021

SUMMARY OF QUOTATION PRICE

A) MANAGEMENT OFFICE RM 75,605.80

B) CUSTOMER SURAU RM 34,853.40

C) STORE, CCTV AND FCC RM 4,660.55

TOTAL OF QUOTATION PRICE :- RM 115,119.75


TOTAL PROJECT DISCOUNT :- RM

GRAND TOTAL OF QUOTATION PRICE :- RM 115,119.75

Page 1 Of 7
PROPOSED REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES FOR MALL OFFICE,
CUSTOMER SURAU & MALL TENANT AT AEON ALPHA ANGLE, WANGSA MAJU KL
RE : REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES
Our Ref. : JTE / MT / 443 / 21 Date : 29 November 2021

Item Descriptions Qty Unit Unit Rate Total Amount

A) MANAGEMENT OFFICE
*Note: All Qty are Provisional and shall subject to re-measured on Site

CEILING FINISHES
1 Supply and install 9mm thick fibrous plaster board; Cl-02 complete with
ceiling battens, board joints, frame, ceiling hanger, 10mm wide shadow gap
finished with joint compound for smooth and seamless finish, including all
necessary suspension system; all to manufacturer's details and approved
drawing.
a) To Mall Management office 130 m2 93.50 RM 12,155.00
b) To Guest room 17 m2 93.50 RM 1,589.50
c) To Facility Store & Workshop 26 m2 93.50 RM 2,431.00
d) To HR & Document Store 8 m2 93.50 RM 748.00
e) To Store & Mall Safe Room 20 m2 93.50 RM 1,870.00
f) To Staff Pantry & Locker Area 24 m2 93.50 RM 2,244.00
g) To Corridor 63 m2 93.50 RM 5,890.50

FLOOR FINISHES
2 Supply and lay selected carpet floor 4mm thk or equivalent, laid in pattern
to Employer's requirement; all in accordance to manufacturer's
recommendation and instructions
a) To Mall Management office 130 m2 161.50 RM 20,995.00
b) To Guest room 17 m2 161.50 RM 2,745.50
c) To Facility Store & Workshop 26 m2 161.50 RM 4,199.00
d) To HR & Document Store 8 m2 161.50 RM 1,292.00
e) To Store & Mall Safe Room 20 m2 161.50 RM 3,230.00
f) To Staff Pantry & Locker Area 24 m2 161.50 RM 3,876.00
g) To Corridor 63 m2 161.50 RM 10,174.50

3 Prepare and apply cementitious waterproofing coating; including upturn to


wall edge; all in accordance to manufacturer's recommendation and
instructions
a) To Staff pantry area around Kitchen Sink (Approx 2m2) 1 Lot 64.60 RM 64.60

4 Supply and install PVC skirting at 75mm high to Employer's requirement;


all in accordance to manufacturer's recommendation and instructions
a) To Mall Management office 52 m 10.20 RM 530.40
b) To Guest room 17 m 10.20 RM 173.40
c) To Facilitiy Sotre & Workshop 22 m 10.20 RM 224.40
d) To HR & Document Store 12 m 10.20 RM 122.40
e) To Store & Mall Safe Room 26 m 10.20 RM 265.20
f) To Staff Pantry & Locker Area 23 m 10.20 RM 234.60
g) To Corridor 54 m 10.20 RM 550.80

Amount Carried Forward :- RM 75,605.80


Page 2 Of 7
PROPOSED REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES FOR MALL OFFICE,
CUSTOMER SURAU & MALL TENANT AT AEON ALPHA ANGLE, WANGSA MAJU KL
RE : REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES
Our Ref. : JTE / MT / 443 / 21 Date : 29 November 2021

Item Descriptions Qty Unit Unit Rate Total Amount

Amount Brought Forward:- RM 75,605.80


A) MANAGEMENT OFFICE (CONT'D)

PAINTING WORKS
1 Emulsion paint; prepare and apply selected 3 coats emulsion paint
or other approved equivalent emulsion paint; all in accordance to
manufacturer's specification, instruction and approval
WALL PAINT
(Colour & Pattern refer to AEON Latest Mall to Office, Pantry, Guest Room
& Facility Workshop/ Store)
a) To Mall Management office 168 m2 9.35 RM 1,570.80
b) To Guest room 51 m2 9.35 RM 476.85
c) To Facility Store & Workshop 66 m2 9.35 RM 617.10
d) To Staff Pantry & Locker Area 69 m2 9.35 RM 645.15
e) To HR & Document Store 36 m2 9.35 RM 336.60
f) To Safe Room 78 m2 9.35 RM 729.30
g) To Corridor 162 m2 9.35 RM 1,514.70

CEILING PAINT
a) To Ceiling surface of Mall Management office 130 m2 10.20 RM 1,326.00
b) To Ceiling surface of Guest room 17 m2 10.20 RM 173.40
c) To Ceiling surface of Facilitiy Store & Workshop 26 m2 10.20 RM 265.20
d) To Ceiling surface of HR & Document Store 8 m2 10.20 RM 81.60
e) To Ceiling surface of Safe Room 20 m2 10.20 RM 204.00
f) To Ceiling surface of Staff Pantry & Locker Area 24 m2 10.20 RM 244.80
g) To Ceiling surface of Corridor 63 m2 10.20 RM 642.60

DOOR PAINT
2 Timber paint; prepare and apply selected 3 coats matt surface timber paint
or other approved equivalent timber paint; all in accordance to
manufacturer's specification, instruction and approval
a) To existing fire doors 5 Nos 13.60 RM 68.00

WHITEBOARD PAINT
3 Supply & apply Dry Erase Whiteboard Paint - Matt White on wallside
comprises of 1st layer coat Candy White Primer, 2nd layer coat Candy
Whiteboard White Base Coat and Whiteboard Cleanser, Whiteboard Dry
Eraser by 3M & Microfibre Cloth for wet cleaning; including touchup and
preparing of existing surface to paint application and protection after
completion of paint applied (Size approx 8m2) 1 Lot 314.50 RM 314.50

Amount Carried Forward :- RM 84,816.40


Page 3 Of 7
PROPOSED REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES FOR MALL OFFICE,
CUSTOMER SURAU & MALL TENANT AT AEON ALPHA ANGLE, WANGSA MAJU KL
RE : REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES
Our Ref. : JTE / MT / 443 / 21 Date : 29 November 2021

Item Descriptions Qty Unit Unit Rate Total Amount

Amount Brought Forward:- RM 84,816.40


A) MANAGEMENT OFFICE (CONT'D)

ANY OTHER ITEMS:


Allow for other cost and preliminaries not incldued elsewhere in the above
for complying the requirements of the Drawings and Specifications and
due completion fo the works

1 ………………………………………………………………..

2 ………………………………………………………………..

3 ………………………………………………………………..

Total Amount carried to Summary :- RM 84,816.40


Page 4 Of 7
PROPOSED REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES FOR MALL OFFICE,
CUSTOMER SURAU & MALL TENANT AT AEON ALPHA ANGLE, WANGSA MAJU KL
RE : REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES
Our Ref. : JTE / MT / 443 / 21 Date : 29 November 2021

Item Descriptions Qty Unit Unit Rate Total Amount

B) CUSTOMER SURAU
*Note: All Qty are Provisional and shall subject to re-measured on Site

WALL FINISHES
1 Supply and lay pebble wash including with screeded back; laid in pattern
and colour to Employer's requirement; all in accordance to manufacturer's
recommendation and instructions
a) To ablution at 2100mm high 29 m2 9.35 RM 271.15

2 Supply and install wall paper with Brick Image Tiles Finishs to Employer's
requirement; all in accordance to manufacturer's recommendation and
instructions
a) To ablution at 2100mm high 63 m2 45.05 RM 2,838.15

CEILING FINISHES
3 Supply and install 9mm thick fibrous plaster board; Cl-02 complete with
ceiling battens, board joints, frame, ceiling hanger, 10mm wide shadow gap
finished with joint compound for smooth and seamless finish, including all
necessary suspension system; all to manufacturer's details and approved
drawing.
(Design and Pattern to Surau refer REFLECTED CEILING LAYOUT)
a) To Surau 130 m2 93.50 RM 12,155.00
b) EXTRA OVER for forming Light Through & Pendant Light 2 Lot 34.00 RM 68.00
c) To Corridor 81 m2 93.50 RM 7,573.50

FLOOR FINISHES
4 Supply and lay selected laminate timber flooring, laid in pattern on trowelled
smooth screeded bed to Employer's requirement; all in accordance to
manufacturer's recommendation and instructions
a) To Surau 103 m2 51.00 RM 5,253.00

5 Supply and lay selected pebble wash, laid in pattern on screeded bed to
Employer's requirement; all in accordance to manufacturer's
recommendation and instructions
a) To Ablutions 27 m2 9.35 RM 252.45

6 Supply and lay selected wood finish surface tiles, laid in pattern on
screeded bed to Employer's requirement; including 100mm high skirting; all
in accordance to manufacturer's recommendation and instructions
a) To Surau Entrance 4 m2 68.00 RM 272.00

Amount Carried Forward :- RM 28,683.25


Page 5 Of 7
PROPOSED REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES FOR MALL OFFICE,
CUSTOMER SURAU & MALL TENANT AT AEON ALPHA ANGLE, WANGSA MAJU KL
RE : REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES
Our Ref. : JTE / MT / 443 / 21 Date : 29 November 2021

Item Descriptions Qty Unit Unit Rate Total Amount

Amount Brought Forward:- RM 28,683.25


B) CUSTOMER SURAU (CON'TD)

FLOOR FINISHES (CONT'D)


1 Prepare and apply cementitious waterproofing coating; including upturn to
wall edge; all in accordance to manufacturer's recommendation and
instructions
a) To Ablutions 27 m2 39.10 RM 1,055.70

2 Supply and install PVC skirting at 75mm high to Employer's requirement;


all in accordance to manufacturer's recommendation and instructions
a) To Surau 54 m 10.20 RM 550.80

PAINTING WORKS
3 Emulsion paint; prepare and apply selected 3 coats emulsion paint
or other approved equivalent emulsion paint; all in accordance to
manufacturer's specification, instruction and approval
WALL PAINT
a) To Surau 255 m2 9.35 RM 2,384.25

CEILING PAINT
a) To Ceiling surface of Surau 130 m2 10.20 RM 1,326.00
b) To Existing ceiling surface of Corridor 81 m2 10.20 RM 826.20

DOOR PAINT
4 Timber paint; prepare and apply selected 3 coats matt surface timber paint
or other approved equivalent timber paint; all in accordance to
manufacturer's specification, instruction and approval
a) To existing fire doors 2 Nos 13.60 RM 27.20

ANY OTHER ITEMS:


Allow for other cost and preliminaries not incldued elsewhere in the above
for complying the requirements of the Drawings and Specifications and
due completion fo the works

5 ………………………………………………………………..

6 ………………………………………………………………..

7 ………………………………………………………………..

Total Amount carried to Summary :- RM 34,853.40


Page 6 Of 7
PROPOSED REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES FOR MALL OFFICE,
CUSTOMER SURAU & MALL TENANT AT AEON ALPHA ANGLE, WANGSA MAJU KL
RE : REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES
Our Ref. : JTE / MT / 443 / 21 Date : 29 November 2021

Item Descriptions Qty Unit Unit Rate Total Amount

C) SECURITY OFFICE, CCTV & FCC


*Note: All Qty are Provisional and shall subject to re-measured on Site

CEILING FINISHES
1 Supply and install 9mm thick fibrous plaster board; Cl-02 complete with
ceiling battens, board joints, frame, ceiling hanger, 10mm wide shadow gap
finished with joint compound for smooth and seamless finish, including all
necessary suspension system; all to manufacturer's details and approved
drawing.
a) To Store 8 m2 93.50 RM 748.00
b) To CCTV & FCC 18 m2 93.50 RM 1,683.00

FLOOR FINISHES
CEMENT RENDER
2 Supply labour and tools for trowel existing floor screeding become
smoothen surface and levelling
a) To Store 8 m2 6.80 RM 54.40
a) To CCTV & FCC 18 m2 6.80 RM 122.40

PAINTING WORKS
3 Emulsion paint; prepare and apply selected 3 coats emulsion paint
or other approved equivalent emulsion paint; all in accordance to
manufacturer's specification, instruction and approval
WALL PAINT
a) To Store 36 m2 9.35 RM 336.60
a) To CCTV & FCC 69 m2 9.35 RM 645.15

CEILING PAINT
a) To Ceiling surface of Store 36 m2 10.20 RM 367.20
b) To Ceiling surface of CCTV & FCC 69 m2 10.20 RM 703.80

ANY OTHER ITEMS:


Allow for other cost and preliminaries not incldued elsewhere in the above
for complying the requirements of the Drawings and Specifications and
due completion fo the works

4 ………………………………………………………………..

5 ………………………………………………………………..

6 ………………………………………………………………..

Total Amount carried to Summary :- RM 4,660.55


Page 7 Of 7
PROPOSED REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES FOR MALL OFFICE,
CUSTOMER SURAU & MALL TENANT AT AEON ALPHA ANGLE, WANGSA MAJU KL
RE : REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES
Our Ref. : JTE / MT / 443 / 21 Date : 29 November 2021

SUMMARY OF QUOTATION PRICE

A) MANAGEMENT OFFICE RM 19,304.05

B) CUSTOMER SURAU RM 12,948.95

C) STORE, CCTV AND FCC RM 5,400.90

D) TENANT LOT (GROUND FLOOR) RM 15,855.75

E) TENANT LOT (FIRST FLOOR) RM 11,648.20

TOTAL OF QUOTATION PRICE :- RM 65,157.85


TOTAL PROJECT DISCOUNT :- RM

GRAND TOTAL OF QUOTATION PRICE :- RM 65,157.85

Page 1 Of 11
PROPOSED REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES FOR MALL OFFICE,
CUSTOMER SURAU & MALL TENANT AT AEON ALPHA ANGLE, WANGSA MAJU KL
RE : REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES
Our Ref. : JTE / MT / 443 / 21 Date : 29 November 2021

Item Descriptions Qty Unit Unit Rate Total Amount

A) MANAGEMENT OFFICE
*Note: All Qty are Provisional and shall subject to re-measured on Site

DEMOLITION
1 Supply labour and tools to demolition existing wall partitions, floor make-up
board in existing briefing room, floor carpet, ceiling board, lighting fittings,
fire pendant sprinkler head, cold water & sanitary wares and etc. including
cart away from site and protection to sites 1 Lot 6,900.00 RM 6,900.00

WALL AND PARTITIONS


2 Supply and Lay 150mm thk Lightweight Block complete with bonding ties,
L bracket, dowel bar etc; including skim coat to both sides 109 m2 38.25 RM 4,169.25

3 Supply and install including hollow section steel stiffener at 3m span of


Lightweight Block Wall (Floor height approximate 3m high) 10 Nos 126.65 RM 1,266.50

WALL FINISHES
4 Supply and apply skim coat to existing uneven wall surface 1 Lot 191.25 RM 191.25

DOOR & IRONMONGERIES


5 Supply and install timber door panel covered bothsides with plywood panel;
including metal door frame, ironmongeries and other necessary fixing
accessories; all in accordance to manufacturer's recommendations and
instruction
a) Single leaf with paint ; 900mm x 2100mm 1 Nos 419.05 RM 419.05

6 Supply and install Fire rated door to BOMBA's requirement; complete with
metal door frame, ironmongeries and other necessary fixing accessories;
all in accordance to manufacturer's recommendations and instruction
a) Single leaf with paint ; 900mm x 2100mm 4 Nos 1,088.00 RM 4,352.00

7 Supply and install metal door to Employer's requirement; complete with


metal door frame, ironmongeries and other necessary fixing accessories;
all in accordance to manufacturer's recommendations and instruction
a) Single leaf with paint ; 900mm x 2100mm to Safe room 2 No 663.00 RM 1,326.00

Amount Carried Forward :- RM 18,624.05


Page 2 Of 11
PROPOSED REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES FOR MALL OFFICE,
CUSTOMER SURAU & MALL TENANT AT AEON ALPHA ANGLE, WANGSA MAJU KL
RE : REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES
Our Ref. : JTE / MT / 443 / 21 Date : 29 November 2021

Item Descriptions Qty Unit Unit Rate Total Amount

Amount Brought Forward:- RM 18,624.05


A) MANAGEMENT OFFICE (CONT'D)

ALUMINIUM WORKS
7 Supply and install Powder coated aluminium frame 1.2mm thk with 10mm
thk tempered glass window panel; including sub-frames, heads, jambs,
mullions, transomes, gaskets, glazing beads, and any other necessary
fixing accessories; all in accordance to manufacturer's recommendations
and instructions
a) Size 900mm x 1200mm high to Safe Room 1 No 340.00 RM 340.00
b) Size 900mm x 1200mm high to Management Office Entrance 1 No 340.00 RM 340.00

ANY OTHER ITEMS:


Allow for other cost and preliminaries not incldued elsewhere in the above
for complying the requirements of the Drawings and Specifications and
due completion fo the works

1 ………………………………………………………………..

2 ………………………………………………………………..

3 ………………………………………………………………..

Total Amount carried to Summary :- RM 19,304.05


Page 3 Of 11
PROPOSED REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES FOR MALL OFFICE,
CUSTOMER SURAU & MALL TENANT AT AEON ALPHA ANGLE, WANGSA MAJU KL
RE : REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES
Our Ref. : JTE / MT / 443 / 21 Date : 29 November 2021

Item Descriptions Qty Unit Unit Rate Total Amount

B) CUSTOMER SURAU
*Note: All Qty are Provisional and shall subject to re-measured on Site

DEMOLITION
1 Supply labour and tools to demolition existing wall partitions, floor make-up
board in existing briefing room, floor carpet, ceiling board, lighting fittings,
fire pendant sprinkler head, cold water & sanitary wares and etc. including
cart away from site and protection to sites 1 Lot 6,500.00 RM 6,500.00

WALL AND PARTITIONS


2 Supply and Lay 150mm thk Lightweight Block complete with bonding ties,
L bracket, dowel bar etc; including skim coat to both sides 67 m2 38.25 RM 2,562.75

3 Supply and install including hollow section steel stiffener at 3m span of


Lightweight Block Wall (Floor height approximate 3m high) 7 Nos 126.65 RM 886.55

WALL FINISHES
4 Supply and apply skim coat to existing uneven wall surface 1 Lot 284.75 RM 284.75

DOOR & IRONMONGERIES


5 Supply and install Fire rated door to BOMBA's requirement; complete with
metal door frame, ironmongeries and other necessary fixing accessories;
all in accordance to manufacturer's recommendations and instruction
a) Single leaf with paint ; 900mm x 2100mm 2 Nos 1,020.00 RM 2,040.00

SANITARY WARES & FITTINGS


6 Supply and install following Sanitary Fittings:-
a) Ablution Taps 11 Nos 43.35 RM 476.85
b) Soap Dispensers 2 Nos 81.60 RM 163.20
c) Floor Fraps 2 Nos 17.43 RM 34.85

ANY OTHER ITEMS:


Allow for other cost and preliminaries not incldued elsewhere in the above
for complying the requirements of the Drawings and Specifications and
due completion fo the works

7 ………………………………………………………………..

8 ………………………………………………………………..

9 ………………………………………………………………..

Total Amount carried to Summary :- RM 12,948.95


Page 4 Of 11
PROPOSED REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES FOR MALL OFFICE,
CUSTOMER SURAU & MALL TENANT AT AEON ALPHA ANGLE, WANGSA MAJU KL
RE : REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES
Our Ref. : JTE / MT / 443 / 21 Date : 29 November 2021

Item Descriptions Qty Unit Unit Rate Total Amount

C) STORE, CCTV AND FCC


*Note: All Qty are Provisional and shall subject to re-measured on Site

WALL AND PARTITIONS


1 Supply and Lay 150mm thk Lightweight Block complete with bonding ties,
L bracket, dowel bar etc; including skim coat to both sides 58 m2 38.25 RM 2,218.50

2 Supply and install including hollow section steel stiffener at 3m span of


Lightweight Block Wall (Floor height approximate 3m high) 6 Nos 126.65 RM 759.90

WALL FINISHES
3 Supply and apply skim coat to existing uneven wall surface 1 Lot 246.50 RM 246.50

DOOR & IRONMONGERIES


4 Supply and install Fire rated door to BOMBA's requirement; complete with
metal door frame, ironmongeries and other necessary fixing accessories;
all in accordance to manufacturer's recommendations and instruction
a) Single leaf with paint ; 900mm x 2100mm 2 Nos 1,088.00 RM 2,176.00

ANY OTHER ITEMS:


Allow for other cost and preliminaries not incldued elsewhere in the above
for complying the requirements of the Drawings and Specifications and
due completion fo the works

5 ………………………………………………………………..

6 ………………………………………………………………..

7 ………………………………………………………………..

Total Amount carried to Summary :- RM 5,400.90


Page 5 Of 11
PROPOSED REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES FOR MALL OFFICE,
CUSTOMER SURAU & MALL TENANT AT AEON ALPHA ANGLE, WANGSA MAJU KL
RE : REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES
Our Ref. : JTE / MT / 443 / 21 Date : 29 November 2021

Item Descriptions Qty Unit Unit Rate Total Amount

D) TENANT LOT (GROUND FLOOR)


*Note: All Qty are Provisional and shall subject to re-measured on Site

DEMOLITION
1 Supply labour and tools to demolish and cart away existing wall partitions:-
a) To TENANT LOT G02 - Lot - NIL - RM - NIL -
b) To TENANT LOT G03 (Existing wall size 16m x 3m high) 1 Lot 414.00 RM 414.00
c) To TENANT LOT G04A & 04B (Existing wall size 15m x 3m high) 1 Lot 414.00 RM 414.00
d) To TENANT LOT G13A - Lot - NIL - RM - NIL -
e) To TENANT LOT G13B - Lot - NIL - RM - NIL -
f) To TENANT LOT G16, 24A & 24B (Existing wall size 17m x 3m high) 1 Lot 414.00 RM 414.00
g) To TENANT LOT G23 - Lot - NIL - RM - NIL -
h) To TENANT LOT G30 - Lot - NIL - RM - NIL -
i) To TENANT LOT G33 - Lot - NIL - RM - NIL -

2 Supply labour and tools to demolish and cart away existing floor tiles:-
a) To TENANT LOT G02 - Lot - NIL - RM - NIL -
b) To TENANT LOT G03 - Lot - NIL - RM - NIL -
c) To TENANT LOT G04A & 04B - Lot - NIL - RM - NIL -
d) To TENANT LOT G13A - Lot - NIL - RM - NIL -
e) To TENANT LOT G13B (Approximate 175 Sqft) 1 Lot 414.00 RM 414.00
f) To TENANT LOT G16, 24A & 24B (Approximate 4284 Sqft) 1 Lot 414.00 RM 414.00
g) To TENANT LOT G23 (Approximate 660 Sqft) 1 Lot 414.00 RM 414.00
h) To TENANT LOT G30 (Approximate 1185 Sqft) 1 Lot 414.00 RM 414.00
i) To TENANT LOT G33 (Approximate 1970 Sqft) 1 Lot 414.00 RM 414.00

3 Supply labour and tools to demolish and cart away existing ceilings
including lighting fittings, grilles etc.
a) To TENANT LOT G02 - Lot - NIL - RM - NIL -
b) To TENANT LOT G03 - Lot - NIL - RM - NIL -
c) To TENANT LOT G04A & 04B - Lot - NIL - RM - NIL -
d) To TENANT LOT G13A - Lot - NIL - RM - NIL -
e) To TENANT LOT G13B (Approximate 175 Sqft) 1 Lot 414.00 RM 414.00
f) To TENANT LOT G16, 24A & 24B (Approximate 4284 Sqft) 1 Lot 414.00 RM 414.00
g) To TENANT LOT G23 (Approximate 660 Sqft) 1 Lot 414.00 RM 414.00
h) To TENANT LOT G30 (Approximate 1185 Sqft) 1 Lot 414.00 RM 414.00
i) To TENANT LOT G33 (Approximate 1970 Sqft) 1 Lot 414.00 RM 414.00

4 Supply labour and tools to demolish and cart away existing Blockwall to
a) To TENANT LOT G13A (Existing wall size 7m x 3m high) 1 Lot 414.00 RM 414.00
b) To TENANT LOT G30 (Existing wall size 5m x 3m high) 1 Lot 414.00 RM 414.00
c) To TENANT LOT G33 (Existing wall size 5m x 3m high) 1 Lot 414.00 RM 414.00

Amount Carried Forward :- RM 6,624.00


Page 6 Of 11
PROPOSED REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES FOR MALL OFFICE,
CUSTOMER SURAU & MALL TENANT AT AEON ALPHA ANGLE, WANGSA MAJU KL
RE : REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES
Our Ref. : JTE / MT / 443 / 21 Date : 29 November 2021

Item Descriptions Qty Unit Unit Rate Total Amount

Amount Brought Forward:- RM 6,624.00


D) TENANT LOT (GROUND FLOOR) (CONT'D)

WALL AND PARTITIONS


1 Supply and Lay 150mm thk Lightweight Block complete with bonding ties,
L bracket, dowel bar etc; including skim coat to both sides:-
a) To TENANT LOT G02 46 m2 38.25 RM 1,759.50
b) To TENANT LOT G03 - m2 - NIL - RM - NIL -
c) To TENANT LOT G04A & 04B - m2 - NIL - RM - NIL -
d) To TENANT LOT G13A 25 m2 38.25 RM 956.25
e) To TENANT LOT G13B - m2 - NIL - RM - NIL -
f) To TENANT LOT G16, 24A & 24B 112 m2 38.25 RM 4,284.00
g) To TENANT LOT G23 - m2 - NIL - RM - NIL -
h) To TENANT LOT G30 - m2 - NIL - RM - NIL -
i) To TENANT LOT G33 - m2 - NIL - RM - NIL -

2 Supply and install including hollow section steel stiffener at 3m span of


Lightweight Block Wall (Floor height approximate 3.2m high):-
a) To TENANT LOT G02 4 Nos 124.00 RM 496.00
b) To TENANT LOT G03 - Nos - NIL - RM - NIL -
c) To TENANT LOT G04A & 04B - Nos - NIL - RM - NIL -
d) To TENANT LOT G13A 3 Nos 124.00 RM 372.00
e) To TENANT LOT G13B - Nos - NIL - RM - NIL -
f) To TENANT LOT G16, 24A & 24B 11 Nos 124.00 RM 1,364.00
g) To TENANT LOT G23 - Nos - NIL - RM - NIL -
h) To TENANT LOT G30 - Nos - NIL - RM - NIL -
i) To TENANT LOT G33 - Nos - NIL - RM - NIL -

ANY OTHER ITEMS:


Allow for other cost and preliminaries not incldued elsewhere in the above
for complying the requirements of the Drawings and Specifications and
due completion fo the works

3 ………………………………………………………………..

4 ………………………………………………………………..

5 ………………………………………………………………..

Total Amount carried to Summary :- RM 15,855.75


Page 7 Of 11
PROPOSED REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES FOR MALL OFFICE,
CUSTOMER SURAU & MALL TENANT AT AEON ALPHA ANGLE, WANGSA MAJU KL
RE : REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES
Our Ref. : JTE / MT / 443 / 21 Date : 29 November 2021

Item Descriptions Qty Unit Unit Rate Total Amount

E) TENANT LOT (FIRST FLOOR)


*Note: All Qty are Provisional and shall subject to re-measured on Site

DEMOLITION
1 Supply labour and tools to demolish and cart away existing wall partitions:-
a) To TENANT LOT F03 - Lot - NIL - RM - NIL -
b) To TENANT LOT F06 - Lot - NIL - RM - NIL -
c) To TENANT LOT F07 (Existing wall size 10m x 3m high) 1 Lot 414.00 RM 414.00
d) To TENANT LOT F08 (Existing wall size 10m x 3m high) 1 Lot 414.00 RM 414.00
e) To TENANT LOT F13 - Lot - NIL - RM - NIL -
f) To TENANT LOT F22B - Lot - NIL - RM - NIL -
g) To TENANT LOT F23A - Lot - NIL - RM - NIL -
h) To TENANT LOT F23B - Lot - NIL - RM - NIL -
i) To TENANT LOT F31 - Lot - NIL - RM - NIL -
j) To TENANT LOT F32 (Existing wall size 4m x 3m high) 1 Lot 414.00 RM 414.00
k) To TENANT LOT F33 (Existing wall size 18m x 3m high) 1 Lot 414.00 RM 414.00
l) To TENANT LOT F34 - Lot - NIL - RM - NIL -
m) To TENANT LOT F35 - Lot - NIL - RM - NIL -
n) To TENANT LOT F41 - Lot - NIL - RM - NIL -
o) To TENANT LOT KF01A - Lot - NIL - RM - NIL -
p) To TENANT LOT KF01B - Lot - NIL - RM - NIL -
q) To TENANT LOT KF02 - Lot - NIL - RM - NIL -
r) To TENANT LOT KF03 - Lot - NIL - RM - NIL -

2 Supply labour and tools to demolish and cart away existing floor tiles:-
a) To TENANT LOT F03 - Lot - NIL - RM - NIL -
b) To TENANT LOT F06 - Lot - NIL - RM - NIL -
c) To TENANT LOT F07 (Approximate 250 Sqft) 1 Lot 414.00 RM 414.00
d) To TENANT LOT F08 (Approximate 720 Sqft 1 Lot 414.00 RM 414.00
e) To TENANT LOT F13 (Approximate 990 sqft) 1 Lot 414.00 RM 414.00
f) To TENANT LOT F22B - Lot - NIL - RM - NIL -
g) To TENANT LOT F23A - Lot - NIL - RM - NIL -
h) To TENANT LOT F23B - Lot - NIL - RM - NIL -
i) To TENANT LOT F31 - Lot - NIL - RM - NIL -
j) To TENANT LOT F32 (Approximate 400 Sqft) 1 Lot 414.00 RM 414.00
k) To TENANT LOT F33 (Approximate 4413 Sqft) 1 Lot 414.00 RM 414.00
l) To TENANT LOT F34 - Lot - NIL - RM - NIL -
m) To TENANT LOT F35 - Lot - NIL - RM - NIL -
n) To TENANT LOT F41 - Lot - NIL - RM - NIL -
o) To TENANT LOT KF01A - Lot - NIL - RM - NIL -
p) To TENANT LOT KF01B - Lot - NIL - RM - NIL -
q) To TENANT LOT KF02 - Lot - NIL - RM - NIL -
r) To TENANT LOT KF03 - Lot - NIL - RM - NIL -

Amount Carried Forward :- RM 3,726.00


Page 8 Of 11
PROPOSED REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES FOR MALL OFFICE,
CUSTOMER SURAU & MALL TENANT AT AEON ALPHA ANGLE, WANGSA MAJU KL
RE : REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES
Our Ref. : JTE / MT / 443 / 21 Date : 29 November 2021

Item Descriptions Qty Unit Unit Rate Total Amount

Amount Brought Forward:- RM 3,726.00


E) TENANT LOT (FIRST FLOOR) (CONT'D)

DEMOLITION (CONT'D)
1 Supply labour and tools to demolish and cart away existing ceilings
including lighting fittings, grilles etc.
a) To TENANT LOT F03 - Lot - NIL - RM - NIL -
b) To TENANT LOT F06 - Lot - NIL - RM - NIL -
c) To TENANT LOT F07 (Approximate 250 Sqft) 1 Lot 414.00 RM 414.00
d) To TENANT LOT F08 (Approximate 720 Sqft 1 Lot 414.00 RM 414.00
e) To TENANT LOT F13 (Approximate 990 sqft) 1 Lot 414.00 RM 414.00
f) To TENANT LOT F22B - Lot - NIL - RM - NIL -
g) To TENANT LOT F23A - Lot - NIL - RM - NIL -
h) To TENANT LOT F23B - Lot - NIL - RM - NIL -
i) To TENANT LOT F31 - Lot - NIL - RM - NIL -
j) To TENANT LOT F32 - Lot - NIL - RM - NIL -
k) To TENANT LOT F33 (Approximate 4413 Sqft) 1 Lot 414.00 RM 414.00
l) To TENANT LOT F34 - Lot - NIL - RM - NIL -
m) To TENANT LOT F35 - Lot - NIL - RM - NIL -
n) To TENANT LOT F41 - Lot - NIL - RM - NIL -
o) To TENANT LOT KF01A - Lot - NIL - RM - NIL -
p) To TENANT LOT KF01B - Lot - NIL - RM - NIL -
q) To TENANT LOT KF02 - Lot - NIL - RM - NIL -
r) To TENANT LOT KF03 - Lot - NIL - RM - NIL -

Amount Carried Forward :- RM 5,382.00


Page 9 Of 11
PROPOSED REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES FOR MALL OFFICE,
CUSTOMER SURAU & MALL TENANT AT AEON ALPHA ANGLE, WANGSA MAJU KL
RE : REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES
Our Ref. : JTE / MT / 443 / 21 Date : 29 November 2021

Item Descriptions Qty Unit Unit Rate Total Amount

Amount Brought Forward:- RM 5,382.00

E) TENANT LOT (FIRST FLOOR) (CONT'D)

WALL AND PARTITIONS


1 Supply and Lay 150mm thk Lightweight Block complete with bonding ties,
L bracket, dowel bar etc; including skim coat to both sides:-
a) To TENANT LOT F03 - m2 - NIL - RM - NIL -
b) To TENANT LOT F06 - m2 - NIL - RM - NIL -
c) To TENANT LOT F07 32 m2 38.25 RM 1,224.00
d) To TENANT LOT F08 - m2 - NIL - RM - NIL -
e) To TENANT LOT F13 - m2 - NIL - RM - NIL -
f) To TENANT LOT F22B - m2 - NIL - RM - NIL -
g) To TENANT LOT F23A - m2 - NIL - RM - NIL -
h) To TENANT LOT F23B - m2 - NIL - RM - NIL -
i) To TENANT LOT F31 - m2 - NIL - RM - NIL -
j) To TENANT LOT F32 10 m2 38.25 RM 382.50
k) To TENANT LOT F33 - m2 - NIL - RM - NIL -
l) To TENANT LOT F34 - m2 - NIL - RM - NIL -
m) To TENANT LOT F35 19 m2 38.25 RM 726.75
n) To TENANT LOT F41 67 m2 38.25 RM 2,562.75
o) To TENANT LOT KF01A - m2 - NIL - RM - NIL -
p) To TENANT LOT KF01B - m2 - NIL - RM - NIL -
q) To TENANT LOT KF02 - m2 - NIL - RM - NIL -
r) To TENANT LOT KF03 - m2 - NIL - RM - NIL -

Amount Carried Forward :- RM 10,278.00


Page 10 Of 11
PROPOSED REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES FOR MALL OFFICE,
CUSTOMER SURAU & MALL TENANT AT AEON ALPHA ANGLE, WANGSA MAJU KL
RE : REFURBISHMENT WORKS OF LAYOUT, MECHANICAL & ELECTRICAL (M&E) SERVICES
Our Ref. : JTE / MT / 443 / 21 Date : 29 November 2021

Item Descriptions Qty Unit Unit Rate Total Amount

Amount Brought Forward:- RM 10,278.00


E) TENANT LOT (FIRST FLOOR) (CONT'D)

WALL AND PARTITIONS (CONT'D)


1 Supply and install including hollow section steel stiffener at 3m span of
Lightweight Block Wall (Floor height approximate 3.2m high):-
a) To TENANT LOT F03 - Nos - NIL - RM - NIL -
b) To TENANT LOT F06 - Nos - NIL - RM - NIL -
c) To TENANT LOT F07 4 Nos 105.40 RM 421.60
d) To TENANT LOT F08 - Nos - NIL - RM - NIL -
e) To TENANT LOT F13 - Nos - NIL - RM - NIL -
f) To TENANT LOT F22B - Nos - NIL - RM - NIL -
g) To TENANT LOT F23A - Nos - NIL - RM - NIL -
h) To TENANT LOT F23B - Nos - NIL - RM - NIL -
i) To TENANT LOT F31 - Nos - NIL - RM - NIL -
j) To TENANT LOT F32 1 Nos 105.40 RM 105.40
k) To TENANT LOT F33 - Nos - NIL - RM - NIL -
l) To TENANT LOT F34 - Nos - NIL - RM - NIL -
m) To TENANT LOT F35 1 Nos 105.40 RM 105.40
n) To TENANT LOT F41 7 Nos 105.40 RM 737.80
o) To TENANT LOT KF01A - Nos - NIL - RM - NIL -
p) To TENANT LOT KF01B - Nos - NIL - RM - NIL -
q) To TENANT LOT KF02 - Nos - NIL - RM - NIL -
r) To TENANT LOT KF03 - Nos - NIL - RM - NIL -

ANY OTHER ITEMS:


Allow for other cost and preliminaries not incldued elsewhere in the above
for complying the requirements of the Drawings and Specifications and
due completion fo the works

2 ………………………………………………………………..

3 ………………………………………………………………..

4 ………………………………………………………………..

Total Amount carried to Summary :- RM 11,648.20


Page 11 Of 11