Professional Documents
Culture Documents
Construction Centricsustainabilityofprecast
Construction Centricsustainabilityofprecast
net/publication/355486387
CITATIONS READS
0 171
1 author:
V N Heggade
Indian National Academy of Engineering
72 PUBLICATIONS 28 CITATIONS
SEE PROFILE
All content following this page was uploaded by V N Heggade on 24 October 2021.
VN HEGGADE
V.N. Heggade presently, the Chief Executive Officer (CEO), STUP Consultants & former Executive Director of Gammon is a
senior professional with a rich experience of over three and half decades in Construction sector in the areas of Design Management,
Technical Management, Site Management, Project Management & Contract Management of Highways, Bridges, Energy structures
like Chimneys & Cooling towers, Environmental, Marine and Hydraulic structures.
He is a recipient of around 10 National recognitions in addition to an International prize from various institutions, like IRC, ICI,
NDRF, IBC and IABSE. He has more than 150 publications to his credit and is a member of various IRC (Indian Roads Congress)
and BIS (Bureau Of Indian Standards) committees. He is also a member of TG 10.1 of Federation Internationale Du Beton, which
is a special Task Group working on FIB Model code 2020. Apart from being on Technical Board of ICI (Indian Concrete
Institute) and Academic Board of SPCE (Sardar Patel College Of engineering) is also a Fellow of Indian National Academy of
Engineering (FNAE).
It is distressing to see some cases in India following There was possibly a compression failure due to
the the old European practice in the recent past and crushing of concrete
witnessing few mishaps during the construction of They possibly adopted only one stage of
some bridges and flyovers.In some bridges built in prestressing, inducing complete prestressing force
Fig.1 : Precast segmental superstructure failures during construction [reformatted from ref.1]
Fig.3 : Increase in deck widths (Bot left:Godavari bridge Rajmundry,Bot right:Kosi bridge) (Source :
Gammon India Ltd)
Fig.4 : Dotted arrows indicating growth trend in deck widths of spine and wing construction
Let’s synthesise the aspect of what author calls as load is on the structure. This makes the member
‘stresses stretching to limits’ in case of spine and wing reaching its compressive stress almost it’s permissible
construction. Under the construction stage while liimit of 0.48fck. For any reasons if there are any
carrying out the SLS varification for ‘rare combination’ unintended flexural stresses or axial compression
where thermal gradient also needs to be taken in to causing the buckling, there will not be any margin to
account, the compressive stress is to be limited to absorb this additional stresses in the spine beam. There
0.48fck. Though the IRC:112 code specifies that are sufficient reasons for unintended forces on the
thermal and wind conditions need not be considered prestressed spine beam which will be deliberated later
together for this varification, the author recommends in this paper.
that the same should be considered during the
The buckling phenomenon of presressed concrete
construction stage. During the construction stage in
member (Fig.6) is quite complex.The critical buckling
span by span spine and wing construction, 100 %
load for axially compressed member hinged at the ends
prestressing is induced in one go when nearly 50%
Fig.6: Buckling of presrtessed concrete members (Source: concept drawn from ref [2])
and wing construction or single transverse box center web larger than that of the external webs,
segment. It introduces new transverse deformability leading to cracks in the flanges.
issues when there is a vertical component of
Thus there is a very likely possibility of additional
prestressing especially when cross section
unintended compression being induced in to cross
transversely becomes slender.
section for variety of reasons explained above.
At around 1/3rd or 1/4th the span, the prestressing
cables are deviated vertically (which is depicted from 2.4 ‘Scale effects’ during Construction
the two photos in the Fig.8 by the positions of The following inadequacies during the construction
anchorages in the diaphragm segment and sheathing stage also may result in poor workmanship, ramifying
ducts at midspan segments), inducing vertical into mishaps:
component of prestressing. The distribution of shear
stresses for such vertical component is made Fabrication defects in precasting yard.
conventionally with the assumption that the rigid cross Inappropriate and not following the timely
section is transversely not deformable (Fig.8 left (with in pot life of epoxy polymerisation)
bottom). However, depending upon the stiffness of epoxy jointing of segments.
component parts of the cross section this assumption
may not be correct (Fig. 8 right bottom). The rigid Breaking of shear keys during handling of
un-deformable cross section in transverse direction segments.
assumes that a centered vertical component of the
Inadequate Geometric control during
prestressing is evenly distributed among the webs.
matchcasting.
In fact, a center pre vertical component of the
prestressing may induce a transverse deformation in Non uniform temporary prestressing between
the top and bottom flanges with a displacement of the the segments.
Lower strength of materials. not done within the potlife leading to less than
100% contact area between the match cast
Over or Under prestressing
surfaces.
Unscheduled forces on permanent structure
The shearkeys being broken while
due to faulty operation of Bridge Deck Erection deshuttering or handling the segments leading
Equipment (BDE).
to imperfect fitting of the segments.
Most important distinction between full span precast Less than 100% contact area between the
construction to that of segmental construction is the
compression joints leading to longitudinal
joints between the segments that has to be perfectly cracks after final prestressing.
fitted with each other.These joints have to transfer
the compression through 100% contact area which is There are some issues which make the match casting
ensured by match casting, either by long line method of precast segments sensitive to certain types of
or by shortline method. defects. Due to the short pouring cycle between
segments (usually a day) the whole process of
Guidelines for design and construction of segmental
segment construction can lead to different type of
bridges, IRC:SP:65 [6]covers in detail the design and
construction defects if specific inspection and
construction requirement for precast segmental
measures are not taken adequately. Some of the most
bridges. Despite these elaborate guidelines, there
common defects during the fabrication and erection
seems to be recurrent issues regarding the quality of
of segments are:
match casting of the segments leading to mishaps
during the construction due to following reasons. The continuous reuse of movable parts of the
formwork might affect its water tightness
Improper placement of concrete, resulting in
after several reuse cycles. This can lead to a
voids/empty pockets in bottom slab and also leakage of the grout component of the
honeycombing at the edges of the segments
concrete mix.
near the end stopper.
The segment pouring sequence, particularly
The epoxy formulation for wet joints not
if a self-compacting concrete mix is not used,
properly applied and temporary prestressing
Another scale effect during match-casting due to the influence of construction method, construction
ever-increasing deckwidth is ‘bow effect’ (Fig. 9). sequence and construction accuracy are significantally
In precast segmental construction, adjacent segments important. Therefore, it is imperative that qualified
must match perfectly to ensure the load transfer (shear engineer(s) with the sufficient knowledge and
and normal forces) through the un-reinforced joint experience are constantly involved in the design
between two precast elements, hence the match scrutiny and Bridge engineers are stationed at the
casting is used for segments production. However, construction site to provide appropriate construction
the heat of hydration and the ambient temperatures management.
may result in curved segments.
The design and construction of precast segmental
The curvature of both segments is formed by the bridges require a tight integration between several
thermal gradients in the match cast segments. The interfaces as part of an industrialised process, and
face of the already cast segment is used as a requires specific measures to be taken into account
shuttering to cast the new segment. Because of the in the quality control of the geometry, materials and
heat of hydration in the new segment a thermal erection and also specialised workmanship in different
gradient is formed in the match cast segment leading areas.
to a curved side between the two adjacent segments.
After the seperation when it comes back to original Detailed documents including method statements,
ambient temperature, the match cast segment returns fabrication and erection procedures and testing
to its original shape whereas the new segment has a requirements need to be specified in the contract
permanent curvature. Factors influencing the blow documents to assist the relevant teams involved in
effect are, width to length ratio of the segment, heat the project to reduce the risks during construction.
of hydration and heat diffusion at the segment The current organisational structure for managing the
surfaces. EPC contract consist of a design consultant to the
3. Quality control during design and contractor, proof-checking consultant to approve the
construction design of the contractor’s designer, safety consultant
to approve the project highway safety and finally
In comparison to other conventional prestressed Authority Engineer (AE) representing the Authority
concrete bridges, for precast segmental bridges, the acting as a supervision consultant including final design
The criteria in EPC contract to complete 3. Scheer, Joachim, Failed Bridges Case Studies,
the design with approvals and the 10 % of Causes and Consequences, 2010 Wilhelm Ernst
the work within a very short period of the & Sohn, Verlag fu¨r Architektur und technische
award of the contract including Wissenschaften GmbH & Co. KG, Rotherstraße
geotechnical investigations, surveying,etc. 21, 10245 Berlin, Germany.
need to be reviewed.
4. Singh, Harpreet, Design & Construction of Spine
The design of launching system or BDE & Wing Segmental, and Strutted Box Segmental
should be proof-checked and load-testing Construction, Online Refresher Course on
should also be conducted. “Pre-Stressed Concrete for Bridges &
Buildings” from 20thMarch - 1stMay 2021.
An experienced and qualified structural
engineer should be introduced as a key 5. Podolny, WalterJr, The cause of cracking in Post-
personnel in Authority Engineer (AE) tensioned Concrete box girder bridges and
contract. retrofit procedures, PCI Journal, March-April
1985,pp 82-139.
5 References
6. IRC: SP:65, Guidelines for design and
1. Bhowmick, Alok. Learning from Bridge
construction of segmental bridges, Indian Roads
Failures-Challenges and Opportunities, CE&CR
Congress, New Delhi.
Journal, February 2021,Vol.34, No.02. pp 22-
33. 7. Fib bulletin 82, Precast segmental Bridges,
Guide to good practice.
2. Leonhardt, Fritz, Prestressed Concrete Design
& Construction, Wilhelm Ernst & Sons, 1964.
Berlin, Munich.