Professional Documents
Culture Documents
Thermal Power Stations
Thermal Power Stations
Unit Profile
Electrotherm Kutch Plant is having a state of the art, well integrated 0.5 million
TPA capacity for manufacturing steel. The plant has five induction furnaces of 22
Ton capacity, one LRF and two 2-Strand CCM and captive power plant of 30 MW,
Two Rotary kilns having a capacity of 0.25 million TPA sponge iron, two Blast
furnace capacity of 0.18 million TPA and a unit producing Ductile iron pipes.
With the integration of Hans Ispat steel facility, plant now has a total capacity of
0.6 million TPA, making us the largest producer of TMT in Gujarat.
529
THERMAL POWER PLANT (30 MW/Hr Capacity)
Energy Consumption
530
Energy Conservation initiatives taken in FY 2015-16
7 Power saving by change in PLC L ogic for BC- 1 & BC-4 Magnet 0.44 2.85 0.00
14 Modification in Service air compressors air suction filter 0.22 1.40 0.05
531
Integrated Management System Policy
532
First Prize Thermal Power Stations
(Coal fired plants >100 MW Capacity)
Unit Profile
The plant sources its fuel from South Eastern Coalfields Ltd. (Subsidiary of Coal
India Limited) under a 20 year Fuel Supply Agreement (FSA). The company also
secured approvals to arrange coal from alternative sources to make up for any
shortage in supply of coal under the FSA. Bhakra-Nangal distributary is the perennial
source of water for the plant under an allocation by the state irrigation. The plant is
operated by an in-house experienced team of operations and maintenance
professionals.
Both the units were successfully commissioned within 48 and 54 months and
commenced commercial operations in 2014. Supercritical Boiler & Turbine has been
manufactured indigenously by the JV of L&T-MHPS at Hazira, Gujarat.
533
Significant Milestones & Initiatives
Plant Availability:
Some of the major highlights on efficiency front of the plant are as follows:
534
Energy Performance Indicators:
HFO being viscous in nature requires heating source, to be kept in live condition in
daily operation. Auxiliary steam was therefore utilized for heating in tank matt coil,
pump suction heater and tracing line along the entire piping. Delay in ignition
stability during unit start-up with HFO increased loss of station availability. Complete
switchover was therefore taken from HFO to LDO with the existing system.
Benefits:
Smoother start-up of unit with LDO improved unit start-up time.
Reduced DM water consumption.
535
Implementation of modified unit start-up logic and start-up curve with consent of
OEM.
Turbine cold start-up rolling pressure revised from 85 60 ksc
Benefits:
Reduced secondary oil consumption for start-up
Benefits:
Reduction in OPEX (reduced DM generation and coal consumption)
Benefits:
APC reduction of 697 kWh
Benefits:
Reduction in APC (4270 KW one CW power consumption)
536
First Prize Thermal Power Stations
(Gas fired plants >100 MW Capacity)
Unit Profile
537
2. Present Installed Capacity of Gujarat Industries Power Co. Ltd.
538
Energy Conservation Measures F.Y. 2015-16
539
Energy Policy
540
Second Prize Thermal Power Stations
(Coal & Gas fired plants < 100MW capacity)
PUDUCHERRY POWER
CORPORATION LIMITED
(Puducherry)
Unit Profile
The first and prestigious gas based power plant was set up at T.R. Pattinam,
Karaikal to cater to the power demand of Karaikal region. The plant on Open Cycle
(22.9 MW Gas Turbine) was synchronized during October 1999. The plant was
dedicated to the nation by the Hon'ble Prime Minister of India on 25.05.1999.
The plant was put into commercial operation w.e.f 3rd January 2000. The entire
power generated from the Karaikal Gas Power Plant is supplied to the Electricity
Department, Karaikal. The plant is performing extremely well till date.
The power generated by both the gas and steam turbines are distributed at 11 KV
level and distributed to local industries and consumers. Some of the power is
exported to 110 kV level to nearby 110 kV sub-station.
The Power Station consists of 1 No. Gas Turbine Unit of capacity 22.9 MW, 1 No.
HRSG and 1 No. Steam Turbine Unit of capacity 9.6 MW. The total capacity of the
Power Plant is 32.5 MW.
541
List of Energy Conservation Measures:
Sr. Energy Saving Proposal Annual Energy Annual Energy Investment Simple
No. Saving Cost Saving (Lakh Rs.) Payback
(Lakh kWh) (Lakh Rs.) Period
(Months)
The brief description of the above list of energy savings measures are presented
below:
542
Illustration:
When dumping steam passing was identified, screenshot was taken from the DCS
before isolating dumping & spray line isolation valves. Snapshot after isolation was
also taken.
The above screenshot was taken which reveals that STG generation is 9.4 MW
corresponding to GT load 21.4 MW. At this stage dumping passing steam was
identified. The second screenshot of DCS was taken after rectification in terms of
arresting dumping steam. By arresting dumping steam STG generation was
increased to 9.7 MW corresponding to same GT load 21.4 MW.
Techno Economic:
Project-2: Gland steam excess return control valve pressure setting calibrated
properly to maintain Gland steam supply header pressure to arrest air ingress
from LP gland and thereafter gland steam excess return to condenser was arrested
thereby reducing condenser heat load and increase in power generation.
Based on the above observation, actions were taken for some corrective works
543
1. Gland steam supply header pressure developed.
2. Turbine LP gland air ingress stopped
3. Condenser heat load reduced
4. Improved vacuum and ultimately generation increased.
DCS Screenshot
Techno Economic:
An evaluation was done how generation can be improved if Hogger is taken out
from the system.
544
Saving calculation due to Hogger stoppage
Apart from the above mentioned saving, some other quantifiable saving can also
be achieved mentioned below:
Per annum 2772 TON DM water can be saved @ 350 kg/hr [as in Sl. No.5]
Respective chemical cost can be saved.
Water saving as CBD loss can be saved.
545
Second Prize Thermal Power Stations
(Coal fired plants >100 MW Capacity)
Unit Profile
546
Performance Trends:
Some of the major innovative projects that are being carried out in the last 3 years
in BBGS mainly to reduce their carbon footprints and to conserve energy are:
a. Modification of Hydraulic fluid coupling of BFP of Unit-1 & Unit-2 to save power
consumption.
b. Refurbishment of Air heater of Unit-1
c. Use of Variable speed drives in PA fans of Unit-1&2.
d. Use of LT VFDs.
e. Reduction of throttling loss at Unit-3 Feed Control Station by reduction of
differential pressure.
f. Stage binding (De-staging) of Condensate Extraction Pump of Unit-1&2.
g. Optimization of PA flow for reduction of Un-burnt % of coal in ash.
h. Modification of flue gas ducting by CFD study to lower ID Fan power consumption.
i. Replacement of LT motors with energy efficient motors.
j. Revamping of Cooling Tower & use of carbon shaft for CT fans.
547
k. Optimization of Transformer loadings.
l. Use of low speed seal air fans
m. Use of energy efficient lighting (LEDs) for outdoor and indoor lighting, Timer
circuit has been incorporated to control outdoor lighting.
The Project was taken up for execution as it had huge potential for energy savings.
Alongside the trend shows the Specific energy consumption trends of the last 3
financial years. The target for SEC for FY 2015-16 was 8.1%, the quest for lowering
SEC led us to explore serious possibilities to lower their own consumption.
Unit-1&2 are 250 MW sets having sub-critical double down shot fired boilers. The
major energy consuming drive in a thermal power plant is Boiler feed pump which
recirculates by taking suction from De-aerator and pumping the water at very high
pressure to Boiler for superheated steam generation which is the prime mover of
the turbine in a thermal power plant. BFP consumes around 30-35% of the total
Plant energy consumption.Unit-1&2 have 2 boiler feed pumps each with 2*100%
capacity.
Achieving Global
Benchmark Figure on
Specific Energy
Consumption.
548
Challenges faced before deployment/implementation
The main challenge was risk evaluation and mitigation of the same. The associated
risks was that in case of abnormal lowering of grid frequency, the modified pump
will not be able to cater full load demand and this situation demands running of the
standby pump. Under the present grid discipline this is a remote possibility, however
under any circumstances the new modified Gear set can be reverted back to old
original set with minimum downtime.
The Boiler feed pump of both Unit-1&2 was such initially designed so as to provide
a max pump speed of 5730 RPM at 47.5 Hz frequency of Input power. At full load
condition the output pump speed of 5300 RPM is sufficient to feed the boiler. Now
since the operating frequency in the grid is around 50 Hz, to keep the output speed
at 5300 RPM there was a loss of around 1148 KW in the hydraulic coupling as oil
was being drained from the coupling to reduce the speed to the required value of
5300 RPM.
Plant envisaged to reduce this coupling loss which was occurring in the hydro-
coupling. By optimizing gearing ratio , plant designed the coupling such that the
output speed of the pump is 5350 RPM which is sufficient to feed the boiler at full
load at an input frequency of 50 Hz.
549
The graphs below shows the energy consumed by BFP vis-à-vis PLF along the
months in 2014 and 2015, before and after implementation of the project respectively
550
Savings:
Leakages in Air Heater tubes resulted in intermixing of fresh air and flue gas thereby
increasing the ID Fan Ampere drawl.
Bulk replacement of air heater tubes resulted in reduction of ID Fan Ampere thereby
saving energy.
Air heater leakage % which is measured every alternate month helped us to reach
the conclusion that mass replacement of heat exchange tubes will give us intended
benefits.
Savings:
551
Second Prize Thermal Power Stations
(Gas fired plants >100 MW Capacity)
Unit Profile
This plant consists of 2 x 104 MW Frame 9-E Gas Turbine Units commissioned in
2002 and 1 x 122 MW STG Unit commissioned in May2003. Gas supply has been
tied up with GAIL through HBJ Pipeline. The Combined Cycle Power Plant (CCPP)
station is comprised of a 2x104 MW Gas Turbines of GT Frame-9E and 1 x 122 MW
Steam Turbine. The Waste Heat flue gases emanating from the gas turbines is
being utilized to generate HP & LP steam in respective Waste Heat Recovery Boilers
(WHRBs / HRSGs) and generate power via a 122 MW steam turbine. The hot gases
of 570o C with a mass flow of approx. 14000 MT/hr is passed through 2 Nos. waste
heat recovery boilers to generate steam.
Plant is certified with ISO certifications of ISO9001, ISO 14000, ISO 18000, as
well.
552
Fuel:
The primary fuel for gas turbine is natural gas being supplied by M/s GAIL. The gas
is received at GAIL Terminal installed in the vicinity of the power station. M/s GAIL
is committed to supply 1.75 MCMD of gas on daily basis. The caloric value of
natural gas being received for power generation is in the band of 8200-8500
kilocalories on NCV basis.
Raw Water :
Raw water requirement is met through Sewage treated water being drawn from
Sen Nursing Home and Delhi Gate Sewage Treatment Plant. The de-mineralized
water requirement for steam generation is met up through sewage treated water
by treating this through RODM (reverse osmosis de-mineralized) process. The
production of cooling water requirement for condenser and other equipment is also
met through STW after processing through Lime softening system. The plant effluent
is discharged to river Yamuna after naturalizing and thus the effluent discharge is
better than sewage water. In fact cleaner water is being discharged to River, making
the project more eco-friendly.
Emission Control :
In order to have control on flue gas emission particularly NOx, a special emphasis
being given. To control NOx, State of art, Dry Low NOx. (DLN) Burners have been
installed on gas turbines. At present the value of NOx. is in order on 17-18 ppm on
base load. The allowable limit of NOx. approved by DPCC (Delhi Pollution Control
Committee) is 35 ppm. This is the first plant in India with a facility to control NOx
emissions by use of dry low Nox technology (DLN) and is an eco-friendly power
station.
Operating Parameters
Annual Operating Parameters FY 2014-15 & 2015-16
553
Energy Conservation Initiatives:
Pragati Power Station is certified with ISO 50001:2011 for effective implementation
of Energy management system (EnMS) covering all the O&M departments of the
plant including water treatment.
During the year 2015-16, arppox 16 nos of energy saving projects were implemented
including electrical and thermal.
PPS-1 consists of three nos of CPHRCP pump. The pumps are integral part of
condenser preheat circuit. These pumps are used to recirculate the hot water from
de-aerator to maintain the fixed temperature at the inlet of the Condensate preheater.
There was a control valve (CV#6) which is opened around 5 % only. To overcome
the throttling loss, the CV was replaced with new CV of low capacity in first phase
and further pump with lower head and LT motor is replaced. Also for fine tune
control, VFD is also installed on the pump and huge amount of energy is saved.
Total investment : 48.51 lacs
Total Savings : 161 KW-
Payback : Less than 1.5 year.
554
2) Changing of cooling tower blades with new profile and shaft with
new carbon shaft:
PPCL consists of induced draft cooling tower having 8 no of cells . Old profile of the
fan blade studied and it was found that it can be changed with new profile which
will conserve energy , further the motor shaft are also replaced with light carbon
shaft to enhance the savings. Presently the project has been implemented on 4 CT
fans.
555
3) Dry Ice blasting of HRSG-II:
During inspection of HRSG II it was observed that the tubes needs cleaning for
better heat transfer at the surface of the tubes. Dry ice blasting carried out during
major overhauling of GT #2 and a decrease in back pressure by 25mm Wc observed,
Which further increased the load on GT by 136 kw .
In belief to the social and commercial cause persistent effort is made towards
energy conservation and in tune with National Mission for Enhanced Energy Efficiency
and to reduce the carbon footprint in the atmosphere, PPS-1 implemented various
other projects such as:
556
Energy Policy
557
Certificate of Merit Thermal Power Stations
(Coal Fired Plants > 100 MW Capacity)
Unit Profile
Nava Bharat Ferro Alloys Limited, Paloncha started their first Ferro alloy furnace of
capacity 16.5 MVA in the year 1975. Later, three more furnaces were installed in
the years 1979, 1983 & 2005 respectively. Presently total installed furnace capacity
is 74.5 MVA and annual production capacity ranges from 1, 17,000 MT to 1, 44,000
MT depending on the product mix.
In the year 1997 Nava Bharat Ferro Alloys Limited entered into the field of power
generation by installing a thermal power plant (Unit-1) using coal as fuel, with a
capacity of 30 MW. In the year 2000, unit-1 capacity was enhanced to 50 MW by
adding another Boiler. Further, in the years 2006 & 2007, two new units each of
capacity 32 MW were added. Present total installed capacity of Power Plant is 114
MW. Surplus power available is sold, to different trading companies, after meeting
the captive and auxiliary requirements.
In the year 2006, organizations name was changed to Nava Bharat Ventures Limited
from Nava Bharat Ferro Alloys Limited.
558
Energy Consumption
559
Plant load factor
a. identifying and creating awareness among all our employees and contract
workmen on the latest energy efficient technologies,
b. implementing appropriate energy efficient and clean technologies,
c. continual improvement in energy conservation practices to achieve global bench
marks,
d. constant monitoring and improving the performance of equipment,
e. organizing energy audits to identify areas for improvement,
f. complying with applicable statuary requirement,
g. encouraging competitive sprit among all our employees, contractors and their
workmen to generate innovative energy conservation ideas and rewarding the
best ideas,
h. sharing the best energy conservations practices among the various units of the
company,
i. educating housewives and school children on energy conservation.
560
Energy Conservation Neasures Implemented
561