Kd's Company

Project Report
Demo Site

powered by getpowerplay.in Install App from Playstore


TASK STATUS

9 0
In Progress Late

5 0
Completed Not Started

OVERALL SITE ACTIVITY TODAY

14 0 0
Tasks Updated Issues Created Attendance Logs

ALL UPDATES

11 Aug, 2021
Budgeting
Progress Total Workers
Task Name Remarks
Total Today's Work Skilled Unskilled Total

Budgeting
100% 100% -- -- -- -- --
Start: 10 Aug | End: 20 Aug

Plastering and Mist Coat


Progress Total Workers
Task Name Remarks
Total Today's Work Skilled Unskilled Total

4th Floor M Bedroom Plastering Work


55% 55% -- -- -- 4 --
Start: 18 Oct | End: 30 Oct

Painting
Progress Total Workers
Task Name Remarks
Total Today's Work Skilled Unskilled Total

5th floor corridor painting


33% 33% -- -- -- 5 --
Start: 14 Nov | End: 30 Nov

Electrical
Progress Total Workers
Task Name Remarks
Total Today's Work Skilled Unskilled Total

Slab Electrical Work ( Piping & Conducting) 70% 70% -- -- -- 8 --


Start: 12 Oct | End: 18 Oct
Tiling and Flooring
Progress Total Workers
Task Name Remarks
Total Today's Work Skilled Unskilled Total

c block ground-floor flooring pcc


20% 20% -- -- -- 1 --
Start: 30 Nov | End: 11 Dec

Column and Curtain Wall


Progress Total Workers
Task Name Remarks
Total Today's Work Skilled Unskilled Total

Column RCC work above 8th slab


100% 100% -- -- -- 6 --
Start: 03 Sep | End: 23 Sep

Survey and Strategy


Progress Total Workers
Task Name Remarks
Total Today's Work Skilled Unskilled Total

Site Surveying
100% 100% -- -- -- 6 --
Start: 01 Aug | End: 10 Aug

Ceiling
Progress Total Workers
Task Name Remarks
Total Today's Work Skilled Unskilled Total

3rd floor ceiling Hacking work


92% 92% -- -- -- 12 --
Start: 28 Sep | End: 02 Oct

Roof Installation
Progress Total Workers
Task Name Remarks
Total Today's Work Skilled Unskilled Total

Roof Steel Binding And Concrete


85% 85% -- -- -- 5 --
Start: 02 Oct | End: 12 Oct

Design
Progress Total Workers
Task Name Remarks
Total Today's Work Skilled Unskilled Total

Temple design for 1st floor in kitchen


100% 100% -- -- -- -- --
Start: 20 Aug | End: 03 Sep

Cleaning and final control


Progress Total Workers
Task Name Remarks
Total Today's Work Skilled Unskilled Total

Final deep Cleaning


10% 10% -- -- -- 3 --
Start: 18 Dec | End: 22 Dec

Plumbing
Progress Total Workers
Task Name Remarks
Total Today's Work Skilled Unskilled Total

Tower-B of 2nd floor internal plumbing work


100% 100% -- -- -- 3 --
Start: 23 Sep | End: 28 Sep

Landscaping
Task Name Progress Total Workers Remarks
Work
Total Today's Skilled Unskilled Total

Excavation For landscape


15% 15% -- -- -- 3 --
Start: 11 Dec | End: 18 Dec

Windows, frames and door installation


Progress Total Workers
Task Name Remarks
Total Today's Work Skilled Unskilled Total

Window sill and pelmet


45% 45% -- -- -- 1 --
Start: 30 Oct | End: 14 Nov
SITE PHOTOS

4th Floor M Bedroom Plastering Work - 27% 4th Floor M Bedroom Plastering Work - 28%

5th floor corridor painting - 33% Slab Electrical Work ( Piping & Conducting) -
38%
Slab Electrical Work ( Piping & Conducting) - c block ground-floor flooring pcc - 20%
32%

Column RCC work above 8th slab - 37% Column RCC work above 8th slab - 63%
Site Surveying - 36% Site Surveying - 42%

Site Surveying - 22% 3rd floor ceiling Hacking work - 56%


3rd floor ceiling Hacking work - 36% Roof Steel Binding And Concrete - 45%

Roof Steel Binding And Concrete - 40% Temple design for 1st floor in kitchen - 100%
Final deep Cleaning - 10% Tower-B of 2nd floor internal plumbing work -
68%

Tower-B of 2nd floor internal plumbing work - Excavation For landscape - 15%
32%
Window sill and pelmet - 45% Window sill and pelmet - 45%